Академический Документы
Профессиональный Документы
Культура Документы
R
REEQ
QUUE
ESST
TFFO
ORRP
PRRO
OPPO
OSSA
ALL
Date : 29-05-2017
1
ITI LIMITED :: KANJIKODE WEST :: PALAKKAD 678623 :: INDIA
Enquiry Ref: P/MKTG/MLLN/I&C/RFP/2016-2017 Dated 29/05/2017
Sub: Request for Proposal for Appointment of Service Providers for Installation,
commissioning and acceptance testing of VMUX & DXC equipment of Managed
Leased Lines Network Equipment ( MLLN ) at various BSNL Circles
ITI Ltd Palakkad is carrying out the supply, Installation, testing and commissioning of
Managed Leased Lines Network Equipment ( MLLN ) for expanding the existing
BSNL network. For installing, testing and commissioning the V MUX and DXC
equipment indicated in the annexure –A , competitive proposals are invited from
electronic industry based service providers based in India.
The tender will be processed in a THREE BID system on Limited tender basis.,
a) Eligibility
b) Technical bid
c) Financial bid
Bid Schedule
Bid Issue Date 29/05/2017
Last date for receipt of request for 02/06/2017
clarifications from bidders
Pre bid meet at ITI Palakkad 05/06/2017- 01:30pm
Publication of reply to clarifications from 08/06/2017
ITI
Due date for submission of tender at ITI
Ltd., Palakkad by email which is password
protected. (Eligibility Bid will be opened 15-06-2017- 2PM
on the same day, ie. 29/05/2017)
Bidders are advised to study this RFP document carefully before submitting their bids.
Submission of a bid in response to this RFP shall be deemed to have been done after careful
2
study and examination of this document with full understanding of its Scope, Specifications,
Terms, conditions & Implications.
Bidders shall submit their bid through email at the following email addresses:
‘pur4_pkd@itiltd.co.in’ on or before the due date and time specified.
Yours Faithfully
For ITI Ltd , Palakkad
P. S. Rajeev,
CHIEF MANAGER (MM & PLG)
TI Ltd., Kanjikode West,
Palakkad, Kerala, INDIA-678 623.
Phone No: +91 4912566180
Fax No. +91 491 2566 009
Email: pur4_pkd@itiltd.co.in
3
1.00 Project Background - MLLN
The MLLN is a Managed Leased Line Network System , which can provide two types of
leased line connectivity
a. Point to point circuit
b. Point to Multi Point Circuit
The bandwidth of a Managed Leased line can be 64Kbps or n*64 Kbps up to a
maximum of 12 Mbps.
ITI has so far supplied about 10600 nodes to BSNL and the present project is for
expanding existing BSNL nationwide network
ITI Ltd has a technical collaboration with M/s CORIANT Finland and the leased line
technology solution adopted by BSNL is based on this technology. The equipment for the
present BSNL expansion project has been already supplied by ITI,LTD ,Palakkad. As per the
terms and conditions of the contract with BSNL , ITI need to supply, install , test
,commission & maintain the equipment during warranty and subsequent AMC period.
3.00 DEFINITIONS
3.01 “Letter of Intent (LoI)” - means a letter issued by the Tendering Agency indicating
his intention to place Purchase Order on the successful bidder.
3.02 “BSNL” – Bharat Sanchar Nigam Ltd.
3.03 “Leased Line” – A dedicated Communication path between two points for
carrying data , voice and video information.
3.04 “ V MUX” – Versatile Multiplexer
3.07 “ PCM Connectivity” - E1 connectivity between node under installation and the
BSNL MLLN network.
3.08 “ NMS” – Network Management System
3.14 “Tendering Agency” - means the agency which has released the Request for
proposal.
3.15 “The Bidder” – means company participating in this bidding process.
3.16 “The Purchase Order” - means the order placed by ITI on the Service Provider
for the required services as per the RFP. This shall be deemed as “Contract”.
3.17 “The Service Provider” - means company, who is the successful bidder and on
whom ITI has placed a Letter of Intent / Purchase Order for rendering the services as
per the RFP .
3.18 “ Hardware Key “ - is a USB device , which is to be plugged into the service
computer . The device will be supplied by ITI, Palakkad. The service computer
application program will not start if the hardware key is not sensed. Service provider
has to submit a bond at the time of receipt of the hardware key.
3.19 “ Installation Kit “ – a kit of 36 tool is used for installation activity , the list of which
is attached as Annexure B. The service provider has to arrange the number of kits
required for installation.
3.20 “ Testing Kit “ – As per Annexure C, consist of service computer loaded with
application software , USB hardware key , Multi meter , Crone IDC tool , manual
wrapping and unwrapping tool , screw driver ( star & normal). Application software
& hardware key will be provided by ITI.
The hardware key shall be returned to ITI immediately after completion of the
work.
4.01 Survey of the installation site , preparation of installation lay out , approval of the
installation layout by BSNL , coordination with BSNL for 48V power and E1
connectivity , survey for DDF , MDF and runway , preparation of the installation
schedule in consultation with BSNL.
4.02 The hardware (basic equipment & installation materials ) equipment is available in the
BSNL SSA central Stores / exchanges , the list of which will be provided by ITI. The
equipment / installation materials are packed in wooden/carton boxes and the
5
installation cables are supplied in wooden drums. The materials are to be segregated /
kitted as per the bill of materials and are to be moved to the installation location by the
Service Provider . Required cable lengths are to be cut from the cable drum. Safe and
proper Transport arrangements are to be made by the service provider. Material receipt
with details of items collected from the store has to be prepared and maintained by the
Service provider and the same has to be produced to ITI along with the claim for
payment.
4.03 Install the equipment with reference to BSNL approved site specific document PMLLN
30050DC Ver. 1. Installation kits are to be arranged by the service provider. For
rigidity purpose , runways are to be provided by the service provider.
4.04 After the installation , networking of the equipment is to be carried out by connecting
PCM’s and NTU. After successful testing, the equipment is to be offered for
Acceptance Testing of BSNL A/T wing. The testing kit is to be arranged by the service
provider.
4.05 The A/T need to be conducted as per the BSNL approved test procedure. After tests ,
AT certificate without pending points are to be submitted to ITI . The service provider
need to take care of the logistic arrangement of the A/T team as it involves field visits
and inspection.
4.06 The service provider has to appoint a technically qualified zonal and logistic manager to
coordinate the project activities at the allotted telecom district / SSA’s.
6
6.02 TAX Clearance
The bidder must have cleared up-to-date VAT, Service TAX & EPF. To comply
this, documents declaring VAT, Service TAX and EPF Payment to be submitted
along with the EOI
6.03.
The Companies are allowed to bid as a consortium. Out sourcing and sub-contracting
will not be allowed without prior permission of the Marketing department of ITI
Limited., Palakkad. To prove the consortium, the notarized agreement on Rs. 500/-
stamp paper should be produced . Prime bidder shall assign the sole responsibility of
executing the project.
6.04 The bidder/Consortium partners shall not be under a declaration of ineligibility for
corrupt or fraudulent practices. For this a court affidavit by the designated official as
per the format of the responding firm/consortium to be produced along with your
Technical bid.
6.05 . Fees
The responding firm/agency should have made a payment of Rs 2.00 Lakhs as
EMD by way of a Demand Draft in favour of ITI Limited., Payable at Palakkad
through any nationalized bank. EMD will be returned to the successful bidders at the
time of submission of PBG as specified under clause 13.00.EMD of those vendors
who refuse to accept the LOI/work order will be forfeited.
The bidder shall enclose the scanned copies of relevant documents/ compliance
statements and self declarations to support the technical eligibility criteria mentioned
at clause 7.01 to 7.06.
7.01 The Bidder should have executed turnkey telecom projects for BSNL/ MTNL/ Private
telecom service providers or e-governance projects for central / state govts or large
networking projects. The bidder who has experience in telecom turnkey projects will
be given preference. Performance certificate for the past three years of executed work
shall be provided from the respective customers.
7.02 The Bidder must deploy qualified staff for the implementation of the project. Bidder
must enclose the manpower profile with name, qualification, experience and tenure of
service with the Bidder. The bidder shall ensure that all statutory requirements like
minimum wages , PF, ESI etc are complied with.
7.03 The Bidder shall enclose a comprehensive action plan for the implementation of the
project with specific time lines. The Plan of action, diagrammatic form of the flow
chart may be prepared submitted. The bidder should indicate the number of teams
that can be deployed state wise for installation and commissioning. The contract will
be awarded after assessing the capability of the bidder to execute the project.
7
Bidders who get more than 70 % marks in technical scrutiny only will be qualified.
For technical scrutiny the parameters to be considered for evaluation is prior
experience , Track record of performance and the detailed project plan with time
schedules. Bids received without a comprehensive project execution plan will be
summarily rejected.
7.04 The Bidder shall submit their company profile with details of site / branches offices
and registered office, contact persons with address, phone numbers, email IDs etc.
Successful bidder has to set up an office facility at the awarded circle and provide the
address and contact details to ITI Limited, Palakkad within 10 days after the issuance
of LOI/PO. Originals of the documents mentioned in the eligibility criteria need to be
submitted at the time of awarding the work order for verification purpose.
7.05 Manpower
The responding firm must have submitted documentary support to prove the
Manpower strength and the eligible qualification, at present they are having to
complete the project. ( Min. Qualification for Installation team : ITI/Diploma
certificate , Commissioning and acceptance Testing : Electronic Engineering
certificate holders are only acceptable.)
7.06 The Bidder shall submit a clause–wise compliance statement confirming the
acceptance of all the Clauses and sub-Clauses of the tender document. A tender
received with out clause wise compliance will be rejected.
7.07 Validity of the bid shall be 90 days from the date of bid submission.
9.02 The tender will be processed in a THREE BID SYSTEM (Eligibility bid, Technical
Bid and Price Bid to be submitted through email with separate title)
9.03 The Eligibility bid and technical bid should contain scanned copies of the documents
called for under the respective clauses. The incomplete bid will be rejected.
9.04 The Price bid shall be prepared exactly as per the Price bid format at Annexure- D.
Any deviation will lead to rejection of whole price bid.
9.05 Bidder should quote for the zones of his choice and items of work indicated in the
annexure D. The bidder has the option to submit the preference of zone for
installation & commissioning. The work will be awarded based on the price bid status
(L1/L2/L3 etc) and the bidder’s ability to deploy the required teams. The Bidders shall
quote for a max. of 3zones and the work will be awarded for a max. of 2 zones.
9.06 Any bid received at M/s. ITI Ltd., Palakkad, after the deadline for submission of bid
will be rejected. ITI assumes no responsibility of Bids delivered to any other address
other than mentioned email address, it will be the bidder’s responsibility to ensure that
the bids are submitted at the correct email address before the bid closing time. Any
Bid submitted not in line with the clause will be summarily rejected.
9.07 The soft copies of technical and price bid must be password protected and sent
through email before the time and date specified under Bid Schedule.
Different passwords must be used for technical bid and price bid. The password for
technical bid and price bid should be forwarded through email as per the timings
shown in the bid schedule.
9.08 ITI will open first the Eligibility Bids The Bidders who fulfill the Eligibility
Criteria will be short listed for considering the Technical bid. Then Technical Bid will
be opened and qualified bidders will be shortlisted for Financial bid. Price bids of
Technically qualified Bidders will be considered . Price bid will be opened on the
same day as indicated in the bid covering letter. Bidders are welcome to be present at
the time of price bid opening.
9.09 A prospective bidder requiring any clarification of the bidding documents may notify
ITI in writing by email to the address provided above on or before the specified date.
9
Requests for clarification over telephone will not be entertained. Reply to
clarifications / amendments / addendum if any will be forwarded to respective bidder,
by email. Prebid meeting is arranged on 22-05-2017 at 1:30pm at ITI Limited,
Palakkad and all the prospective bidders are requested to attend it without fail.
9.10 Bids shall remain valid for 90 days after the due date of bid submission. ITI shall
reject a bid as non-responsive if the bid is submitted with a shorter validity period.
9.11 The bid shall be signed by the authorized signatory. Authorisation letter from the
competent authority in this regard to be submitted along with other eligibility criteria
documents.
a) 50% on completion of installation and the equipment offered for Acceptance Testing to
BSNL. Copy of the offer letter signed by the BSNL officer to be furnished along with your
claim for payment.
b) 40 % on successful completion of A/T along with A/T certificate issued by BSNL
( not below the rank of DE) without any pending points
c) 10% on successful completion of A/T of the last node in the allotted State
11.01 Time Schedule: The total time period of the project is 2 months from the date of
placement of LOI.
10
Time period from the Date of
S.No Parameter LOI
a. At the end of every week ITI will evaluate the progress and immediate remedial action
has to be taken by the Service Provider to ramp up the deployment. In case the
deployment is not as per the plan, then ITI reserve the right to take further decision on
whether to continue or short close the order without any liabilities to ITI . Further, If
any site/Installation requires special attention/ITI Involvement, the matter to be
brought to the notice of ITI officials and try to solve the issues.
b. The time schedule has to be strictly followed and progress of work has to be
communicated daily. Service Provider should adhere to these timelines.
However, ITI reserve the right to change the aforementioned timelines.
c. Liquidated Damages
Time is the essence of this contract. Should the Supplier/Service provider fails to
deliver and install the system as per the delivery schedule or any extension thereof
which is attributed to the failure of service provider, the Purchaser shall be entitled to
recover from the Supplier/Service provider a penalty equivalent to 0.5 % of the value
of the Purchase Order placed on them for the first four weeks or part thereof and
0.7% per week there after for such delay or part thereof or cancel the purchase order
and place the order on somebody else at the risk of the Supplier/Service provider.
11.02 There will be more than one service providers working in each state based on the
volume of work involved in the state. ITI reserve the right to distribute the orders
among other qualified bidders or to the L1 bidder himself.
11.03 Decision of ITI will be final in allocation of Purchase Order quantities , zone and state.
11.04 Availability of sufficient and qualified manpower and the Bidder managing their
service for timely completion are of major importance in this project. Bidder shall
strictly comply with all statutory rules and regulations regarding Bidders staff (Like
Minimum wages, PF, ESI etc.,) as per applicable law. Bidder shall be solely
11
responsible for payment of wages or any other remuneration or compensation or
claims or expenses of whatsoever nature of its employees on regular basis. If any dues
are reported to ITI, then ITI may at its sole discretion withhold from the bills of the
Bidder such amount, which will be released only after such disputes are settled
amicably. It is clearly understood that ITI shall not have any responsibility or liability
whatsoever towards the employees of Bidder.
Bidder shall indemnify ITI in respect of any costs, claims or liabilities whatsoever
arising from death or injuries to employees of Bidder and all damage to property,
death or personal injuries whatsoever, caused by negligent acts or omissions of such
employees during their presence in the project premises in connection with this
Agreement.
11.05 ITI reserves the right to change the operators if the progress/ quality of the work are
not satisfactory. Bidder is responsible for immediate replacement of these personnel.
11.07 The Bidder shall not assign, in whole or in parts, its obligations to perform under the
contract to third party.
11.08 ITI reserve the right to accept or reject any or all bids without assigning any reasons.
Bids may be accepted or rejected in total or in any part thereof. Any bids not
containing sufficient information in view of ITI, to permit a thorough analysis may be
rejected.
11.09 ITI reserve the right to verify the validity of bid information, and to reject any bids
where the contents appear to be incorrect, in accurate or inappropriate.
11.10 ITI shall have the right to cancel the RFP process at any time prior to award of
contract without thereby incurring any liability to the affected bidder or bidders.
11.11 ITI reserve the right to cancel the order without any liability to ITI account if the
progress is not satisfactory in terms of quality, quantity, time and then ITI reserve the
right to award the contract to any Bidder to complete the work in time.
At the same time as ITI notifies the successful bidder that its bid has been accepted,
ITI will send the contract form to the bidder incorporating all agreements between the
12
parties. Immediately on the receipt of contract form the successful bidder shall sign
and date the contract and return it to ITI.
ITI may at any time by written order given to the supplier/Bidder, make changes
within the general scope of contract.
16.00 TERMINATION
ITI may, without prejudice to any other remedy, by written notice of termination sent
to the Bidder, terminate the contract, in whole or part, without any liability to ITI
whatsoever, if:-
13
f. In any of the above event termination will be without compensation to the Bidder, and
that such termination will not prejudice or affect any right of action or remedy, which
has accrued or will accrue hereafter to ITI.
17.01 The bidder (and his employees) shall not, disclose any part or whole of this RFP
document, of the proposal and/or any specification, plan, drawing, pattern, sample or
information furnished by ITI (including the users) in connection therewith to any
person other than a person employed by the bidder in the performance of the proposal
and/or contract. Disclosure to any such employed person shall be made in confidence
and shall extend only as far as may be necessary for purposes of such performance.
The employees or the third party such as security personnel, etc engaged by the bidder
will maintain strict confidentiality.
17.02 The bidder, his / her employees and agents shall not make any use of any document or
information given by user except for purposes of performing the contract award.
17.03 In case of breach ITI shall take such legal action as it may be required.
18.01 For purpose of this clause, Force majeure means an event beyond the control of the
supplier/Bidder and not involving the supplier/Bidder’s fault or negligence and not
foreseeable. Such events may include, but are not limited to, acts of ITI either in its
sovereign or contractual capacity, wars or revolutions, fires, floods, epidemics,
quarantine restrictions and freight embargoes.
18.02 If a Force majeure situation arises, the supplier/Bidder shall promptly notify
ITI in writing of such conditions and the cause thereof. Unless otherwise directed by
ITI in writing, the supplier/Bidder shall continue to perform its obligations under the
Contract as far as is reasonably practical, and shall seek all reasonable alternative
means for performance not prevented by the Force majeure event.
ITI may at any time terminate the Contract by giving written notice to the Bidder, if
the Bidder becomes bankrupt or otherwise insolvent. In this event termination will be
without compensation to the Bidder, provided that such termination will not prejudice
or affect any right of action or remedy, which has accrued or will accrue hereafter to
ITI
14
20.00 RESOLUTION OF DISPUTES AND ARBITRATION
20.01 All disputes arising between the Parties hereto out of or in connection with this
contract shall be amicably settled between the Parties. Where the Parties hereto fail to
settle the disputes amicably, within ninety (90) days of the written notice of its
existence given by either Party to the other, then such dispute shall be settled by
arbitration by a sole Arbitrator in accordance with Indian Arbitration Rules. The
arbitration proceedings shall take place in Palakkad . Preferred medium is English for
Arbitration proceedings
The service provider must obtain Acceptance test certificates for all nodes allotted to
him without any pending points to be cleared from BSNL T&D officials.
15
EQUIPMENT DETAILS FOR INSTALLATION, TESTING &
COMMISSIONING - ANNEXURE-A
Circle Name of the DXC
VMUX
Circle 128 Port 256 Port
1 A &N 10 0 0
2 Andra Pradesh 83 2 0
3 ASSAM 48 4 0
4 Bihar 0 8 1
5 Chhattisgarh 36 5 0
6 GUJARATH 50 2 1
7 Haryana 74 3 4
8 Himachal Pradesh 8 3 0
9 J&K 30 1 0
10 Jharkhand 118 8 0
11 Karnataka 200 10 0
12 Kolkata Telephones 100 13 0
13 M.P 50 5 4
14 Maharashtra 115 16 1
15 NE-1 19 0 0
16 NE-2 7 0 1
17 Odisha 130 5 1
18 Punjab 90 4 0
19 Rajastan 86 7 0
20 UP East 21 8 1
21 UP WEST 126 7 0
22 Uttarakhand 33 3 0
23 West Bengal 20 4 0
TOTAL 1454 118 14
ITI LIMITED, PALAKKAD ANNEXURE-B
2. CHARGER 1
4. MULTIMETER 1
5. SCREW DRIVER 1
6. KRONE TOOL 1
7. BAFFO CABLE 1
ANNEXURE - D
MLLN 2017 PURCHASE ORDER- ALLOCATION DETAILS QUOTATION FORMAT
Z E 1 Gujarath 50 2 1
O 2 Maharashtra 115 16 1
N I
TOTAL 165 18 2
Z 1 Haryana 74 3 4
O 2 Punjab 90 4 0
N
E 3 Himachal Pradesh 8 3 0
4 Rajastan 86 7 0
2 TOTAL 258 17 4
Z
1 West Bengal 20 4 0
O
N 2 Odisha 130 5 1
E
3 A &N 10 0 0
3 160 9 1
1 Kolkata Telephones 100 13 0
ZONE 4
100 13 0
Z
1 UP East 21 8 1
O
N 2 UP WEST 126 7 0
E
E
3 Uttarakhand 33 3 0
5 TOTAL 180 18 1
1 M.P 50 5 4
ZONE 6 2 Chhattisgarh 36 5 0
TOTAL 86 10 4
1 Bihar 0 8 1
ZONE 7 2 Jharkhand 118 8 0
TOTAL 118 16 1
1 NE-1 19 0 0
2 NE-2 7 0 1
ZONE 8
3 ASSAM 48 4 0
TOTAL 74 4 1
1 Karnataka 200 10 0
2 Andra Pradesh 83 2 0
ZONE 9
TOTAL 283 12 0
1 J&K 30 1 0
ZONE 10
TOTAL 30 1 0
Special Note:
1. The Vendors shall quote for all Zones/States for the above activities.
2. Service Tax will be extra as applicable
3. The L1 status will be based on the formula aA+bB+cC+dD.
Managed Leased Line Network
(MLLN - BSNL Phase IV)
1. DXC – Digital Cross Connect equipment is made up of a new high capacity Tellabs 8188 Switch
consist of a double subrack version with 32 unit slots, GMX2 is the cross-connect matrix and
SCU-H is the control unit. It has SDH cross-connect with multi service grooming at 64 kbps level
and optional STM-1, 4 and 16 interfaces. Forced cooling with three separate fans and filter placed
on the bottom part of the shelf to keep the temperature range appropriate. The SCU-H controls the
speed of the fans and alarms to NMS in case of failure in fans. The Tellabs 8000 network manager
R16A or above can manage this high capacity node. Its ports capacity depends on the type and
number of units inserted in the double subrack with the maximum of 512 Mbps cross connection
capacity. The DXCs supplied to BSNL, India with the following configuration.
1 DXC-128 Ports.
2. DXC-256 Ports
Space
The DXC is installed in standard 19” rack with the following dimensions:
Height – 2.21 Metres
Width – 0.60 Metres
Breadth – 0.42 Metres
The figures below illustrate the infrastructure requirements for 128 Ports DXC and 256 Port DXC .
1) DXC-128 Ports
DXC equipment is made up of a new high capacity Tellabs 8188 Switch consist of a double subrack
version with 32 unit slots, GMX2 is the cross-connect matrix and SCU-H is the control unit. It has
SDH cross-connect with multi service grooming at 64 kbps level and optional STM-1, 4 and 16
interfaces. This DXC is equipped for 128 ports capacity by inserting eight numbers of High capacity
E1C cards.
Subrack Earthing Rack Earthing
3
MCB
10
RXS2-CD
26
31 8188 SWITCH
47
DDF 001-105 PORTS
67
74
DDF 106-128 PORTS
87
107
Floor Plan
0.6 Mtr - Passage
Rack 1
0.6 x 0.6 Mtr.
The following figure shows the 128 ports DXC DDF Krone wiring.
DDF-1
DDF-2
DXC Block 1
106 to 128 Ports
2) DXC-256 Ports
DXC equipment is made up of a new high capacity Tellabs 8188 Switch consist of a double subrack
version with 32 unit slots, GMX2 is the cross-connect matrix and SCU-H is the control unit. It has
SDH cross-connect with multi service grooming at 64 kbps level and optional STM-1, 4 and 16
interfaces. This DXC is equipped for 256 ports capacity by inserting sixteen numbers of High capacity
E1C cards.
Subrack Earthing Rack Earthing
3
MCB
10
RXS2-CD
26
31 8188 SWITCH
47
DDF 001-105 PORTS
67
74
DDF 106-210PORTS
87
107
Floor Plan
0.6 Mtr - Passage
Rack 1
0.6 x 0.6 Mtr.
Power
DXC operates on –48 Volt DC Power Supply.
Total Power requirements = Maximum of 20 Amps (Two sources of 20 Amp)
The following figure shows the 256 ports DXC DDF Krone wiring.
DDF-1
DDF-2
DDF-3
Source 1 MC
B
A1
Source 2 MC
B
A1
3) VMUX
Only one types of VMUX is supplied to BSNL and the port capacity is tabulated as below.
The VMUX is installed in standard 19” rack with the following dimensions:
The figures below illustrate the infrastructure requirements for Type 1B VMUX.
VMUX-Subrack Equipage
P
PFU-A OMH2-8 OMH2-8 OMH2-8 E1C XCG
- - - - - - -
F
1 1 1 1
-
4 4 4 2
A
3
4
5
6
5 5 5 7
8 8 8 8
9
10
11
12
13
14
15
16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
VMUX TYPE 1B
II) VMUX
MCB
VMUX-1
VMUX-2
DDF-1
VMUX-1 VMUX- 1 VMUX-2
Block-1 Block-2 Block-1
DDF-2
VMUX-2 VMUX-3 VMUX- 3
Block-2 DDF-2
Block-1 Block-2
VMUX-3
Floor Plan
Rack 1
0.6 x 0.6 Mtr
Each VMUX can be housed in individual rack. Maximum of three VMUXs can be
housed in one rack as shown in the figure above.
Power
1) VMUX operates on –48 Volt DC Power Supply.
Power requirement for each VMUX sub rack = 5 Amp Max
Each sub rack power supply unit receives –48 Volts through individual MCB placed at
the top rear of the rack.
VMUX-1
21
32
VMUX-2
48
60
DDF1
67
80
DDF2
87
98
VMUX-3
114
126
Issue & Date Drawn By Checked By Approved By
1 28/04/2017
These VMUXs consist of a Single sub rack with 16 unit slots. Each VMUX can be installed
in one 19 inch rack. However maximum of 3 VMUXs can be installed in one 19 inch rack.
Only one type of VMUX is supplied to BSNL in this purchase order. The details of
Port capacity is as given in the second page of this document. Unit requirements of Type
1B VMUXs and power connector pin assignment are given below.
RXS-S 1 Subrack
PFU-A 1 1
OMH2-8 3 3,4,5
E1C 1 15
XCG 1 16
Power
E1C
The E1C G.704 framed interface unit is used for G.703 2048 kbit/s interfaces either in G.704
2048 kbit/s or n x 64 kbit/s framed or 2048 kbit/s unframed mode. The E1C unit includes 16
channels to carry data and also provides a network management communication link
between the Tellabs8100 elements. The physical interface type is a 120-ohm symmetrical pair
complying with the [G.703] specification. The frame structure at 2048 kbit/s is in accordance
with the [G.704] ITU-Recommendation. E1C is very similar to the QMH G.704 framed
interface unit but the number of interfaces is Higher, thus saving rack space
The OMH2-8 is G.SHDSL line interface units are based on ITU-T G.SHDSL
Technology. They are designed for connecting the CTE2 G.SHDSL network terminating
Units (NTUs) to Tellabs 8100 managed access system, comprising both the G.SHDSL NTU
and the control and framing functionality. There is no separate interface module for the unit,
Unit contains 8 No’s Nx64 Interfaces
Termination of backbone E1 and line side Nx64K wiring on Krone type DDF
Block 1 Block 2
E1C Ports 01-05 OMH2 Ports 01-10
E1C Ports 06-10 OMH2 Ports 11-20
E1C Ports 11-15 OMH2 Ports 21-24
E1C Ports 16
Important Note:-
1 2 3 4 5
Tx1A Tx1B Rx1A Rx1B Tx2A Tx2B Rx2A Rx2B TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
6 7 8 9 10
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
11 12 13 14 15
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
16 17 18 19 20
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
21 22 23 24 25
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
26 27 28 29 30
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
31 32 33 34 35
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
36 37 38 39 40
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
41 42 43 44 45
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
46 47 48 49 50
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
51 52 53 54 55
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
56 57 58 59 60
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
61 62 63 64 65
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
66 67 68 69 70
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
71 72 73 74 75
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
76 77 78 79 80
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
81 82 83 84 85
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
86 87 88 89 90
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
91 92 93 94 95
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
96 97 98 99 100
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
1 2 3 4 5
Tx1A Tx1B Rx1A Rx1B Tx2A Tx2B Rx2A Rx2B TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
6 7 8 9 10
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
11 12 13 14 15
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
16 17 18 19 20
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
21 22 23 24 25
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
26 27 28 29 30
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
31 32 33 34 35
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
36 37 38 39 40
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
41 42 43 44 45
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
46 47 48 49 50
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
51 52 53 54 55
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
56 57 58 59 60
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
61 62 63 64 65
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
66 67 68 69 70
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
71 72 73 74 75
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
76 77 78 79 80
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
81 82 83 84 85
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
86 87 88 89 90
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
91 92 93 94 95
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
96 97 98 99 100
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
256
TxA TxB RxA RxB
1 2 3 4 5
Tx1A Tx1B Rx2A Rx2B Tx2A Tx2B Rx2A Rx2B TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
6 7 8 9 10
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
11 12 13 14 15
TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB TxA TxB RxA RxB
16
TxA TxB RxA RxB
1 2 3 4 5 6 7 8 9 10
A B A B A B A B A B A B A B A B A B A B
11 12 13 14 15 16 17 18 19 20
A B A B A B A B A B A B A B A B A B A B
21 22 23 24
A B A B A B A B
Blank
Blank
Nationwide MLLN
Version: 1.0
Page 1 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
INTRODUCTION
This document describes the general procedures for Acceptance Tests (AT) of MLLN
network. Hereafter the abbreviation AT and Acceptance Test are used in this document.
This AT Schedule is prepared for the Additional Purchase Order for MLLN equipment to
be installed and commissioned as part of the existing BSNL Nationwide MLLN.
P.O. Requirements
Type of VMUX
N x 64kbps E1
DC VMUX Type IB 24 16
Three different types of NTUs are available in the scope of this purchase order.
Page 2 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 3 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 4 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 5 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 6 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Steps:
• Verify and note down the units inserted in the DXC as per list below
• Ensure that the Power Supply (PFU-H) and Cross Connection (GMX2) cards are
available in a duplex configuration.
• Ensure that the cards equipped in the DXC are as per the capacity of the DXC
( for e.g. for 128 port DXC there should be 8 x E1C cards)
Expected results:
Page 7 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
VERIFY ALL THE UNITS ARE INSTALLED AS PER PURCHASE ORDER AND NOTE THE
NUMBER OF E1 PORTS (TICK THE PORTS WHICH ARE AVAILABLE)
DXC ID
DXC NAME
CAPACITY 128 PORTS
Page 8 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
VERIFY ALL THE DXCs ARE PROVIDED WITH REDUNDANT POWER SUPPLY UNITS
(PFU-H)AND CROSS-CONNECTION MATRIX CARDS (GMX2)
VERIFY ALL THE DXCS ARE PROVIDED WITH ONE DOUBLE SUBRACK AND ONE
MANAGEMENT CARD
Page 9 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Adding a new DXC to the MLLN network.
Steps:
• Add a DXC Node from the ROT. It is assumed that all HW is already installed.
• Finally after having created the new DXC Node add at least one test circuit between any
node and the new DXC Node for the further test in this section.
Expected results:
It is possible to add a DXC Node to the MLLN network and manage it from a ROT
workstation.
Test passed:
YES NO
Page 10 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
4. Network Synchronization
Objective:
To test the network synchronization with a defined fallback list.
The test step “4.A” has to be conducted in sites where external clock is connected
to the new DXC (2048khz Clock outputs from STM equipments (SSU-T) or ADM
can be used as External clock)
The test step “4.B” has to be conducted in sites wherever external clock is not
available for connecting to the new DXC.
Steps: 4.A
Expected results:
Test passed:
YES NO
Page 11 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
SCU-H backs up the parameters of all units in the nodes. When unit is changed, it gets
a copy of parameters from SCU-H and starts operation.
Steps:
Expected results:
Test passed:
YES NO
Page 12 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Test Layout:
E1C E1C
2 Mbit/s T runk
NODE_1 NODE_2
G.70 3 G.70 3
Steps:
– Add two E1C’s with G703 modules into separate nodes.
– Add E1C’s to unit inventory.
- Change the E1C card state to in use.
– Configure two G703 interfaces for 2Mbps.
– Change the states of interfaces to in use.
– Add one 2M trunk between the nodes.
– Bind the trunk to the interfaces.
– Neighbor node settings.
– Change the state of the trunk to in use.
– Set the state of the trunk to planned.
– Unbind the trunk ends.
– Delete the trunk.
Note: Trunks shall be created between DXC to DXC and VMUX to DXC.
Expected results:
It should be possible to add and delete trunks within network without errors.
Test passed:
YES NO
Page 13 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Test Layout:
Primary Trunk
P-P CIR CUIT
Steps:
• Create a point-to-Point Circuit using Router Window from ROT
• Route a Point-to-Point circuit through the trunk.
• Start Circuit Loop Test for the circuit.
• Check that traffic is normal.
• Delete circuits routed through the trunk
Expected results:
It should be possible to add and delete circuits within MLLN Network without
errors.
Test passed:
YES NO
Page 14 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
8. LED Test
Objective:
Test procedures:
Expected results:
The LED’s should function according to the setting in the test window.
Test passed:
YES NO
Page 15 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
9. Memory Test
Objective:
Test procedures:
Expected results:
The memories in the hardware unit should be OK and the window should indicate
this.
Test passed:
YES NO
Page 16 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Test procedures:
Expected results:
All voltages generated by the hardware unit should be within the ranges. It should
be able to measure the operating voltages of the unit.
Test passed:
YES NO
Page 17 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
# Slot/Unit +1.0V (+/- +1.2V (+/- +2.5V (+/- 3.3V (+/- +5.0V (+/- +1.25V +1.8V
Name 15%) 15%) 15%) 15%) 15%) (+/-15%) (+/-15%)
1
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Page 18 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Steps:
Expected results:
The time stamp of an alarm is indicated in fault report window.
Test passed:
YES NO
Page 19 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 20 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 21 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Steps:
• Verify and note down the units inserted in the DXC as per list below
• Ensure that the Power Supply (PFU-H) and Cross Connection (GMX2) cards are
available in a duplex configuration.
• Ensure that the cards equipped in the DXC are as per the capacity of the DXC
( for e.g. for 256 port DXC there should be 16 x E1C cards)
Expected results:
Page 22 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
VERIFY ALL THE UNITS ARE INSTALLED AS PER PURCHASE ORDER AND NOTE THE
NUMBER OF E1 PORTS (TICK THE PORTS WHICH ARE AVAILABLE)
DXC ID
DXC NAME
CAPACITY 256 PORTS
TOTAL NUMBER OF E1 PORTS: 256 PORTS
Page 23 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
VERIFY ALL THE DXCs ARE PROVIDED WITH REDUNDANT POWER SUPPLY UNITS
(PFU-H)AND CROSS-CONNECTION MATRIX CARDS (GMX2)
VERIFY ALL THE DXCS ARE PROVIDED WITH ONE DOUBLE SUBRACK AND ONE
MANAGEMENT CARD
Page 24 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Adding a new DXC to the MLLN network.
Steps:
• Add a DXC Node from the ROT. It is assumed that all HW is already installed.
• Finally after having created the new DXC Node add at least one test circuit between
any node and the new DXC Node for the further test in this section.
Expected results:
It is possible to add a DXC Node to the MLLN network and manage it from a ROT
workstation.
Test passed:
YES NO
Page 25 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
4. Network Synchronization
Objective:
To test the network synchronization with a defined fallback list.
The test step “4.A” has to be conducted in sites where external clock is connected
to the new DXC (2048khz Clock outputs from STM equipments (SSU-T) or ADM
can be used as External clock)
The test step “4.B” has to be conducted in sites wherever external clock is not
available for connecting to the new DXC.
Steps: 4.A
• Connect a high quality external clock to the new DXC.
• Go to NE synchronization Set and Enable External clock by selecting Station
clock Input GMX2-A and GMX2-B
• Add the SCI to fall back List with Priority 1.
• Add one of the trunk-connected interface in the fallback list with Priority 2
• Check the NE synchronization status and it should show LOCKED.
• Check the Node is working on External Clock (GMX2-SCI)
• Remove the external clock to the node.
• Check with the Clock State is still locked and using sync clock.
• Fix the external clock to the node.
• Check the Node is working on External Clock (GMX2-SCI)
Steps: 4.B
• Connect a clock derived from one of the 2Mbps E1 trunk to the DXC.
• Set one entry to SEC fallback list in the NE synchronisation.
• Check the Locking status and it should show LOCKED and ensure that it is
using the sync clock from the E1 Interface (Not using internal clock)
• Remove the clock to the node by removing E1 stream through which clock is
derived.
• Check with the Clock Status is showing Hold Over (Internal Clock).
• Fix the clock through the trunk.
• Check with the Clock Status is Locked and using Sync-Clock.
Expected results:
Test passed:
YES NO
Page 26 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
SCU-H backs up the parameters of all units in the nodes. When unit is changed, it gets
a copy of parameters from SCU-H and starts operation.
Steps:
Expected results:
Test passed:
YES NO
Page 27 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Test Layout:
E1C E1C
2 Mbit/s T runk
NODE_1 NODE_2
G.70 3 G.70 3
Steps:
– Add two E1C’s with G703 modules into separate nodes.
– Add E1C’s to unit inventory.
- Change the E1C card state to in use.
– Configure two G703 interfaces for 2Mbps.
– Change the states of interfaces to in use.
– Add one 2M trunk between the nodes.
– Bind the trunk to the interfaces.
– Neighbor node settings.
– Change the state of the trunk to in use.
– Set the state of the trunk to planned.
– Unbind the trunk ends.
– Delete the trunk.
Note: Trunks shall be created between DXC to DXC and VMUX to DXC.
Expected results:
It should be possible to add and delete trunks within network without errors.
Test passed:
YES NO
Page 28 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Test Layout:
Primary Trunk
P-P CIR CUIT
Steps:
Expected results:
It should be possible to add and delete circuits within MLLN Network without
errors.
Test passed:
YES NO
Page 29 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
8. LED Test
Objective:
Test procedures:
Expected results:
The LED’s should function according to the setting in the test window.
Test passed:
YES NO
Page 30 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
9. Memory Test
Objective:
Test procedures:
Expected results:
The memories in the hardware unit should be OK and the window should indicate
this.
Test passed:
YES NO
Page 31 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Test procedures:
• Check all voltages generated by the unit are within the limit.
Expected results:
All voltages generated by the hardware unit should be within the ranges. It should
be able to measure the operating voltages of the unit.
Test passed:
YES NO
Page 32 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Page 33 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Steps:
Expected results:
The time stamp of an alarm is indicated in fault report window and in fault view
window.
Test passed:
YES NO
Page 34 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 35 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
NMS related tests for these locations to be done from the existing ROT to which this VMUX is
parented.
Reference and
# Test Item Observation/Result
Remarks
1. Layout Floor Plan As per EI-007 By BSNL
Page 36 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 37 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Steps:
• Ensure that the VMUX is equipped as per the classifications given in the requirements.
For e.g. check that the VMUX- Type IB has been equipped with the requisite number of
N x 64kbps ports and E1 ports.
• Ensure that the common cards are equipped in the VMUX as required in the
configuration.
Expected results:
Verify the units as per the requirement.
Test passed:
YES NO
Page 38 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
VERIFY ALL THE UNITS ARE INSTALLED AS PER PURCHASE ORDER AND NOTE THE NUMBER
OF E1 PORTS AND TRIBUTARY PORTS.
VMUX ID :
VMUX NAME :
VMUX TYPE : IB DC
TOTAL NUMBER OF E1 PORTS: 16
TOTAL NUMBER OF N*64KBPS PORTS: 24
Page 39 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Page 40 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Steps:
• Add a VMUX node through the ROT workstation. It is assumed that all HW is already installed.
• Finally after having created the new VMUX Node, add at least one test circuit between any
node and the new VMUX Node for the further test in this section.
Expected results:
It is possible to add a VMUX Node to the MLLN network and manage it from a NMS
workstation.
Test passed:
YES NO
Page 41 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
3. NETWORK SYNCHRONIZATION
Objective:
• Connect a clock derived from one of the 2Mbps E1 stream to the VMUX.
• Set the node in the network to use this clock and use it to distribute clock to other
nodes.
• Set one entry to fallback list in the nodes.
• Check that the nodes do not use internal clock.
• Remove the clock to the node by removing E1 stream through which clock is
derived.
• Check with the Master Clock State (Verify node is using internal clock).
• Fix the clock through the trunk.
• Check with the Master Clock State (Verify node is using sync- clock).
Expected results:
Test passed:
YES NO
Page 42 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
XCG backs up the parameters of all units in the nodes. When unit is changed, it gets a copy of
parameters from XCG and starts operation. The objective of this test is to test this.
Steps:
Expected results:
It should be possible to detect the unit. The interruption consists of the time needed to replace
the unit and the unit to make a reset and copy the parameters.
Test passed:
YES NO
Page 43 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Test Layout:
E1C E1C
2 M bit/s Trunk
NODE_1 NODE_2
G.703 G.703
Steps:
Note:
Trunks shall be created between VMUX to VMUX and VMUX to DXC if available.
Carry Out BER tests as part of “Test 11” using these trunks .After that delete trunks.
Expected results:
It should be possible to add and delete trunks within MLLN Network without
errors.
Test passed:
YES NO
Page 44 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
6. (A) Creating and Deleting a Circuit Test (for cities having two or more VMUXs)
Objective:
Test Layout:
Pri ma ry Trun k
P- P C IRC UIT
Steps:
• Create a point to point circuit through the ROT. The naming of the circuit should be
starting With the alphabets "AT". For e.g. the name of the circuit could be
"ATtestbangalore1" etc.
Route a point-to-point circuit between two VMUXs through DXC if available. Test the
provision for both auto route and Manual route for creation of the circuit.
Expected results:
It should be possible to add and delete circuits within MLLN network without
errors.
Test passed:
YES NO
Page 45 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
6. (B) Creating and Deleting a Circuit Test (for cities having single VMUX)
Objective:
Steps:
• Create a point to point circuit using NTU through the ROT. The naming of the circuit
should be starting with the alphabets "AT". for e.g. the name of the circuit could be
"ATestbangalore1" etc.
Expected results:
It should be possible to add and delete circuits within MLLN network without
errors.
Test passed:
YES NO
Page 46 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
7. LED Test
Objective:
Test procedures:
• Choose a unit to be tested.
• Open the LED Test window for that unit.
• Set the LED blinking.
• Verify the LED function
• Set the LED back to normal state.
Expected results:
The LED should function according to the setting in the test window.
Test passed:
YES NO
Page 47 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
8. Memory Test
Objective:
Test procedures:
• Choose a unit to be tested.
• Open the Memory Tests window for that unit.
• Put tick mark on Check box of RAM, EPROM, and Flash.
• Verify the result.
Expected results:
The memories in the hardware unit should be OK and the window should indicate
this.
Test passed:
YES NO
Page 48 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Test procedures:
Expected results:
All voltages generated by the hardware unit should be within the ranges shown in the
window. It should be able to measure the operating voltages of the unit
Test passed:
YES NO
Page 49 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
Page 50 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
Steps:
Expected results:
The time stamp of an alarm is indicated in fault report window.
Test passed:
YES NO
Page 51 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
Objective:
To ensure end to end error free path of the circuit through the equipment
Test Setup:
VMUX1 VMUX2
G. 703 G.7 03 Digital Loop
Steps:
• Open “Router” module at NMS.
• Select a circuit
• Open Circuit Loop Tests at different points of circuit from the NMS including loop test
between NTU and VMUX.
• Set configuration for 60 minutes test
• Conduct Data test for 60 minutes
• Ensure error free transmission.
Note: BER tests shall be done creating circuits using NTUs as per ordered types for the site.
Expected results:
Test passed:
YES NO
Page 52 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
THROUGH TEST
BER Test:
BER test between 64 Kbps/1984 Kbps circuit of different NTU connected to different VMUX for 60
Minutes.
Page 53 of 54
MANAGED LEASED LINE NETWORK (MLLN) BSNL PO CT/PO/29/2016-17 DATED
21/03/2017
ACCEPTANCE TEST DOCUMENT VER 1.0
AT Site Name:
DXC 128 Port/ DXC 256Port/
Type of Equipment:
VMUX Type 1B/NMS/DCN
Model No. : 8188/8150/NMS/DCN Subrack Serial No. :
Node ID:
Installer
BSNL
AT Conducted by
AT Official Name / Desgn. Correspondence address Phone : ( )
Mr./Mrs.:
Signature
Mr. /Mrs.
Signature
Page 54 of 54