[GR 11]
Course Objectives:
2. Team build up and interaction with all resource departments for resource balancing
economic manner by forecasting
4. Application on ERP system for customer requirement planning and compare integration
b. Classify the production systems. Mention the characteristics of each of those systems
[CO1] [8]
b. A manufacturing company has monthly demand for one of its products as follows:
b. Explain P &Q systems of controlling the inventories with neat diagrams [CO3] [7]
4. a. Discuss the role of BOM with the help of block diagram [CO5] [7]
b. A house painting contractor has 5 houses to paint following are the estimated times
required to paint each house and due date for completion [8] [CO6]
House Estimated time(days) Due date
A 2.5 8
B 4.0 10
C 3.0 7
D 5.0 14
E 2.0 16
Construct job sequence using SPT rule and EDD rule. Also compute average flow time.
WEEK 1 2 3 4 5 6 7
Auto
Sales 8 10 9 11 10 13 -
Paper I
Paper II