SCHEDULE FOR GEOTECHNICAL INVESTIGATION CFPP 2X25MW, Tarakan

Jun-16 Jul-16 Aug-16 Sep-16


NO ACTIVITY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 \ 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Soil Investigation

Site Visit

1 Work Order/NTP

2 Preparation at Jakarta

3 Mobilization of Equipment

Mobilization fo Drilling team

4 Preparation at Site

5 Drilling Onshore

BH 1

BH 2

BH 3

BH 4

BH 5

BH 6

BH 7
Idul Fitri
BH 8

BH 9

BH 10

BH 11

BH 12

BH 13

BH 14

BH 15

BH 16

6 DCPT

7 Test Pit

8 Geoelectrical Survey

7 Laboratory test

8 Report & Recommendation

PT. TIGENCO GRAHA PERSADA - JAKARTA

Drilling Team 1

Drilling Team 2
NEXT PLAN WORK SCHEDULE FOR ADDITIONAL DRILLING
SURALAYA 9 & 10, MERAK
Jul-19 Aug-19
NO ACTIVITY 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10

Soil Investigation

1 Drilling :

Add CHST 02S

Add CHST 02R

Chimney BHC02

Chimey BHC03

2 Field Test

Crosshole

Permeability Test

PMT Test

3 Demobilization