City : Berhampur

Sector : Water Supply


Physical Progress % Financial Progress %
Sr. No Project Code Title Agency Name Remarks Reasons for Delay Proposed Action Plan
Sch. Act. Sch. Act.
Pipe laying work nearing to completion - 1) Delay in obtaining Main line conncetion is
- 7.8 KM completed out of 7.9 KM. permission from NHAI balance which requires
MS pipe work fabrication, welding and painting work for laying pipeline on shut down of existing
in progress. NH-16. From 1st line.
April'17 to 27th Feb'18
2) Delay in
Improvement of WS to Berhampur -Rehabilitation P2 M/s Orissa Coal & procurement of MS
1 BERHAMPUR/WS/02 (AMRUT/OD/BERHAMPUR/WS/02) Services Pvt. Ltd. 100.00 99.37 100.00 99.00 pipe of dia 900mm
(290m Length)

Pipe laying work under progress - 1)Delay in obtaining Executive has taken
- 2.7 KM completed out of 6.4 KM. permission from NH approval from govt. To
Balance pipeline laying permission rejected by NH Divison-Berhampur for lay balance pipeline in
Division. laying pipeline on NH- IRE(Indian rare earth)
Improvement of WS to Berhampur -Rehabilitation P3 M/s Orissa Coal & 59. From 1st April'17 to area.
2 BERHAMPUR/WS/03 (AMRUT/OD/BERHAMPUR/WS/03) Services Pvt. Ltd. 100.00 43.28 100.00 43.00
09th Oct'18

Pipe laying work nearing to completion - 1) Delay in obtaining


- 9.5 KM completed out of 10.1 KM. permission from NHAI
for laying pipeline on
NH-16 (400 mm DI
Pipe)From 1st April'17
to 27th Feb'18
2) Delay in
finalisation of front by
Client for laying 150mm
dia pipe-approx-628m
3) Delay in starting
the work of RCC pile for
supporting of MS pipe
400mm dia about 300m
Improvement of WS to Berhampur -Rehabilitation P4 M/s Basanta Kumar on bahana Nala on NH-
3 BERHAMPUR/WS/04 (AMRUT/OD/BERHAMPUR/WS/04) Panigarhi 100.00 96.66 100.00 98.00
16

RCC Foundation work completed for both DG set at 1) Delay in finalisation


Dakhinapur & Badamadhabpur. Structural work and of civil and electrical
4 Back-up Power for different WTPs drawings by contractor.
BERHAMPUR/WS/08 (AMRUT/OD/BERHAMPUR/WS/08) M/s ABC Construction 100.00 87.79 100.00 85.00 cable laying completed in Dakhinpur structural work Drawings finally
is in progress at Badamadhabpur.
1250 KVA and 500 KVA DG set received at site. approved on
06/02/2019 by EIL HO.

Top dome of GSR completed at Raghunathpur, MKCG 1)Delay in submitting


medical, Forest colony area, Agulabandha and vertical drawings for GSR by the
wall completed at banchanidhinagar area. contractor. 2)
Roof slab completed at Forest Colony, MKCG area and Delay in mobilisation of
Improvement of Storage Facility in BeMC area agulabandha pump house. Balance 3 nos. pump manpower by the
5 BERHAMPUR/WS/12 (AMRUT/OD/BERHAMPUR/WS/12) M/s Jagdish Patra 100.00 58.64 100.00 61.00
house yet to be taken up. contractor

Pipe laying work under progress - 1) Delay in Manpower Now the labours are
- 10.9 KM completed out of 18.9 KM. mobilisation by the shifting the pipe to
contractor after laying laying locations. Laying
Improvement of Water Supply to Scarcity areas of 10.9 Km pipeline. of pipes will be started.
M/s Rout Infrastructure
6 BERHAMPUR/WS/13 Berhampur under PH Division Berhampur -PKG-7 pvt ltd 100.00 46.19 100.00 46.00
(AMRUT/OD/BERHAMPUR/WS/13)
City : Berhampur
Sector : Parks
Physical Progress % Financial Progress %
Sr. No Project Code Title Agency Name Remarks Reasons for Delay Proposed Action Plan
Sch. Act. Sch. Act.

Nilakantha Nagar Park - Work completed, Patitapaban Nagar Park


Krishna Vihar Park - Work Completed,
Industrial Estate Chakka Park - Work Completed, - Under Hold. Work can
Construction of Parks in Berhampur M/s Surendra Kumar
1 BERHAMPUR/PR/14 100.00 77.03 100.00 41.73 be resumed only after
(AMRUT/OD/BERHAMPUR/PR/14) Panigrahi Patitapaban Nagar Park - Under Hold. Work can be completion of ESR
resumed only after completion of ESR inside park inside park area.
area.

Delay in handing over of


site to AMRUT Contractor will start
Development of Park in Berhampur (Lanjipali Tank, Ganesh Lanjipali Tank Park - Work completed. contractor due to earth civil works in ganesh
2 BERHAMPUR/PR/15 Nagar, Patitapaban Nagar) -Package M/s Prabeen Gantayat 100.00 65.14 100.00 43.84 Ganesh Nagar Park - Earthwork in filling started & filling, guard room and Nagar. Play equipments
(AMRUT/OD/BERHAMPUR/PR/15) Compound wall Completed. boundary wall are already fabricated
construction by BeMC by the manufacturer.
contractor.