Академический Документы
Профессиональный Документы
Культура Документы
2 months
4 months early
14 months faster work 4 months faster
Case 2
delay work
Complete
DELAY IN EARLY COMPLETION
SITUATION
• Many owner will take the stand in the second case that, since the contractor
finished the contract early, there was no damage caused by the delay
• Owner’s consider that the contractor’s bid should be based on taking the
full allowable time for contract completion
• The weakness of owner’s view is that the contractor accepted all risk of
performance of the contract and, in the absence of an owner-caused delay,
would be liable for all extra-time related costs if the contract was not
finished on time as well as liquidated damages
• Therefore the contractor should be entitled to save costs by finishing the
work earlier than required by contract, if able to do so
• The owner causing a 4 month delay is liable for the resulting extra costs to
the contractor even though the contractor finishes the contract work early
CAUSES FOR DELAY AND SUSPENSIONS
OF WORK
• Defective specifications
– When specs and drawings contain errors, the delay often
result due to:
• Attempting to comply with the error
• Waiting for the errors to be corrected and revised specs to be issued
• Site availability problems
– Site availability at the time of issue of NTP
– Unless stated in contract, contractor is entitled to full use of
site at the time of NTP
– Owners failure to provide reasonable means of access to
the work or interruption of access previously provided
CAUSES FOR DELAY AND SUSPENSIONS
OF WORK
• Changing and Differing site conditions
– Changes directed by the owner
– Changes because of problems associated with DSC’s
– The requirement to perform added work can cause a delay
• Constructive notice
– If an act of god shuts down the work or the owner issues a
written directive to suspend all work, the owner has
constructive notice of delay
– Constructive notice means, that even though not
specifically notified formally, the owner knows that the
work is being delayed
– But still, the contractor should always give prompt written
notice of delay to the owner