Академический Документы
Профессиональный Документы
Культура Документы
1. 1. Introduction
1.1. 1.1. Definition of Piping
2
1.2. 1.2. Piping Nomenclature & Components 3
1.3. 1.3. Regulatory Acts, Codes & Standards 5
1.4. 1.4. Line Designation Tables 7
Problem Set 1 8
Problem Set 2 17
3. 3. Supplemental Documents
3.1. 3.1. Owner’s Specifications & Documents 25
3.2. 3.2. Contractor’s Standards & Documents 26
Problem Set 3 27
4. 4. Piping Design
4.1. 4.1. Failure Mechanisms 28
4.2. 4.2. Code Considerations for Design 29
4.3. 4.3. Material Selection
40
4.4. 4.4. Fabricated Tees & Area Reinforcement 54
4.5. 4.5. Piping Flexibility Analysis
58
Exam
Pipe is a pressure tight cylinder used to convey a fluid or to transmit a fluid pressure, ordinarily
designated pipe in applicable material specifications. Materials designated tube or tubing in the
specifications are treated as pipe when intended for pressure service.
Piping is an assembly of piping components used to convey, distribute, mix, separate, discharge,
meter, control or snub fluid flows. Piping also includes pipe-supporting elements but does not
include support structures, such as building frames, bents, foundations, or any equipment
excluded from Code definitions.
Piping components are mechanical elements suitable for joining or assembly into pressure-tight fluid-
containing piping systems. Components include pipe, tubing, fittings, flanges, gaskets, bolting, valves and
devices such as expansion joints, flexible joints, pressure hoses, traps, strainers, in-line portions of
instruments and separators.
• • header
• • branch connection
• • valve
• • flange
• • expansion joint
• • expansion loop
• • pipe support
• • reducer
• • elbow
Pipe system essentials:
Pipe support • • Support elements which serve to maintain the structural integrity of the
piping system, these are typically non-linear elements
Spring support • • Support provided by an element composed of a spring assembly, these are
linear support elements
Expansible fluid • • Any vapour or gaseous substance, any liquid under such pressure and
temperature such that when pressure is reduced to atmospheric, will change to a
gas
Codes
Codes are rules for the design of prescribed systems which are given the force of law through provincial,
state and federal legislation. In Canada, provincial governments have the responsibility for public safety
that includes these facilities, among others:
• • Pressure piping
• • Pressure vessels
• • Boilers
• • Pipelines
• • Plumbing systems
• • Gas piping
The following are applicable to the first four facilities listed above.
Cites the “minimum requirements for the design, construction, testing, operation, maintenance
and repair of pipelines”:
In the US:
As in Canada, some facilities are governed by federal regulations. Interstate pipeline facilities are
defined by the:
The Province of Alberta Safety Codes Act "Design, Construction and Installation of Boilers & Pressure
Vessels Regulations" par 7(2) requires that construction of a pressure piping system must include
submission of drawings, specifications and other information and include:
(a) flow or line diagrams showing the general arrangement of all boilers, pressure vessels, pressure piping
systems and fittings (2 copies)
(b) pipeline identification lists showing the maximum pressures and temperatures for each pressure piping
system (2 copies)
(c) a list of pressure relief devices, including the set pressure (2 copies)
(d) material specifications, size, schedule and primary service rating of all pressure piping and fittings (2
copies)
(f) the pressure pipe test procedure outlining the type, method, test media , test pressure, test temperature,
duration and safety precautions (1 copy)
(g) a form, provided by the Administrator, completed by the engineering designer or contractor which
relates to the general engineering requirements for design and field construction of pressure piping systems
(AB 96)
(h) such other information as is necessary for a safety codes officer to survey the design and determine
whether it is suitable for approval and registration
Problem Set 1
1 1 Which Act governs the design of plant pressure piping systems in Alberta?
3 3 For what fluid service category may a hydrotest be waived per B31.3?
The following codes are used for the design, construction and inspection of piping systems in
North America.
Piping typically found in electric power generating stations, in industrial and institutional
plants, geothermal heating systems and central and district heating and cooling plants.
B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids
Piping transporting products which are predominately quid between plants and terminals
and within terminals, pumping, regulating, and metering stations.
Piping transporting products which are predominately gas between sources and terminals
including compressor, regulating and metering stations, gas gathering pipelines.
Piping typically found in industrial, institutional, commercial and public buildings and in
multi-unit residences which does not require the range of sizes, pressures and
temperatures covered in B311.1
Piping transporting aqueous slurries between plants and terminals within terminals,
pumping and regulating stations.
The following codes are used to specify the geometric, material and strength of piping and components:
Piping component standard developed by the American Society of Mechanical Engineers or the
American National Standards Institute (ANSI)
Piping covering fire protection systems using water, carbon dioxide, halon, foam, dry
chemical and wet chemicals.
SP-6 Standard Finishes for Contact Faces Pipe Flanges and Connecting End Flanges of Valves
and Fittings
SP-25 Standard Marking System for Valves, Fittings, Flanges and Union
SP-44 Steel Pipeline Flanges
SP-53 Quality Standards for Steel Castings and Forgings for Valves, Flanges and Fittings and
Other Piping Components - Magnetic Particle
SP-54 Quality Standards for Steel Castings and for Valves, Flanges and Fittings and Other
Piping Components - Radiographic
SP-55 Quality Standards for Steel Castings and for Valves, Flanges and Fittings and Other
Piping Components - Visual
SP-58 Pipe Hangers and Supports - Material, Design and Manufacture
SP-61 Pressure Testing of Steel Valves
SP-69 Pipe Hangers and Supports - Selection and Application
SP-75 High Test Wrought Butt Welding Fittings
SP-82 Valve Pressure Testing Methods
SP-89 Pipe Hangers and Supports - Fabrication and Installation Practices
2.5 API
The API standards are focused on oil production, refinery and product distribution services.
Equipment specified to these standards are typically more robust than general industrial
applications.
Publ. 941 Steel for Hydrogen Service at Elevated Temperature and Pressures in Petroleum
Refineries and Petrochemical Plants
Publ. 2009 Safe Welding and Cutting Practices in Refineries
Publ. 2015 Safe Entry and Cleaning of Petroleum Storage Tanks
2.6 ASTM
There are numerous American Society for Testing and Materials designations cover the
specification of wrought materials, forgings and castings used for plate, fittings, pipe and valves.
The ASTM standards are directed to dimensional standards, materials and strength
considerations.
A 53 Specification for Pipe, Steel, Black and Hot –Dipped, Zinc Coated Welded and
Seamless
A 106 Specification for Seamless Carbon Steel Pipe for High Temperature Service
A 181 Specification for Forgings, Carbon Steel for General Purpose Piping
A 182 Specification for Forged or Rolled Alloy Steel Pipe Flanges, Forged Fittings, and
Valves and Parts for High Temperature Service
A 193 Specification for Alloy Steel and Stainless Steel Bolting Materials for High
Temperature Service
A 194 Specification for Carbon and Alloy Steel Nuts for Bolts for High Pressure and
High Temperature Service
A 234 Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for
Moderate and Elevated Temperatures
A 333 Specification for Seamless and Welded Steel Pipe for Low Temperature Service
A 350 Specification for Forgings, Carbon and Low Alloy Steel Requiring Notch
Toughness Testing for Piping Components
A 352 Specification for Steel Castings, Ferritic and Martensitic for Pressure Containing
Parts Suitable for Low Temperature Service
A 420 Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Low
Temperature Service
A 694 Specification for Forgings, carbon and Alloy Steel for Pipe Flanges, Fittings,
Valves and Parts for High Pressure Transmission Service
A 707 Specification for Flanges, Forged, Carbon and Alloy Steel for Low Temperature
Service
Problem Set 2
1. 1. A project award has been made. At the kick off meeting, the PM advises that piping design will
be to B31.4. The facility is steam piping in a refinery extending from the boiler to the tank farm.
What do you do or say and why?
3. 3. What flange specification would you expect to reference for a gas pipeline facility?
Due to copyright laws, the following figures have not been published here. We leave as an exercise for the
user to retrieve these for reference.
Many of the Owners in the industries we service are technically sophisticated and will often have
supplementary specifications, standards or practices. It is the intent of these documents to clarify
and provide interpretation of the legislated Codes and industry-accepted standards specific to the
Owner’s facilities.
These specifications typically go beyond the requirements of Codes and without exception do not
contravene a Code requirement.
Engineering contractors may be called upon to provide the engineering specifications for a project
if an Owner does not have his own standards or if required by terms of the contract.
Problem Set 3
3 3 Under what conditions can the Owner’s standard override a Code provision?
• • analytical design
• • material selection
• • geometric layout
• • fabrication
• • inspection specification
• • component specification
Piping and piping components may fail if inadequately designed, by a number of different
mechanisms. These failures, in the majority of cases are either load controlled or displacement
controlled failures.
Design of piping systems is governed by Codes. All codes have a common theme, they are intended to set
forth engineering requirements deemed necessary for safe design and construction of piping installations.
The Codes are not intended to apply to the operation, examination, inspection, testing, maintenance or
repair of piping that has been placed in service. The Codes do not prevent the User from applying the
provisions of the Codes for those purposes.
Engineering requirements of the Codes, while considered necessary and adequate for safe design, generally
use a simplified approach. A designer capable of applying a more rigorous analysis shall have the latitude
to do so, but must be able to demonstrate the validity of such analysis.
Design Conditions
Design conditions refer to the operating and design temperature and pressure that the piping
system will operate at over the course of its design life.
Code Design Temperature & Design Pressure
(P ∗ Do )
tmin = 2( SE + PY ) + A , or
P ∗ d + 2 SE + 2 yPA
t= 2( SE + Py − P)
The limit is based on the limit stress being less than the basic allowable stress at temperature. This limit is
based on the static yield strength of the material.
SL ≤ Sh ; stress due to sustained loadings shall be less than the basic allowable stress at temperature.
Sustained loadings are those due to pressure, self weight of contents & piping and other sustained loadings
particular to the situation. The limit is based on the static yield strength of the material.
P ∗ Do
Slp= 4 ∗ tn
SE ≤ SA = f(1.25 Sc + 0.25 Sh). SE stresses arise from the constraint of the thermal strain displacements
associated with the expansion of pipe due to temperature. The limit is based on fatigue considerations.
Where the sum of the longitudinal stresses is less than Sh, the difference may be used as an
additional thermal expansion allowance.
2 2
Sb + 4∗ St
SE =
2 2
ii M i + io M
o
Sb = Z
B31.1 (cont’d)
Cycles, N Factor, f
P∗D SE − P
P∗D D ∗ (1 −
SE + P
t = 2( SE + PY ) or t = 2 SE or t = 2 (Lamé Equation)
The limit is based on the limit stress being less than the basic allowable stress at temperature. This limit is
based on the static yield strength of the material.
SL ≤ Sh ; stress due to sustained loadings shall be less than the basic allowable stress at temperature.
Sustained loadings are those due to pressure, self weight of contents & piping and other sustained loadings
particular to the situation. The limit is based on the static yield strength of the material.
SE ≤ SA = f(1.25 Sc + 0.25 Sh). SE stresses arise from the constraint of the thermal strain displacements
associated with the expansion of pipe due to temperature. The limit is based on fatigue considerations.
Where the sum of the longitudinal stresses is less than Sh, the difference may be used as an
additional thermal expansion allowance.
Design of Piping – B31.4
Pi ∗ D
t = 2S
The limit is based on the limit stress being less than the basic allowable stress at temperature. This limit is
based on the static yield strength of the material.
S = 0.72 ∗ E ∗ SMYS ,
SL ≤ 0.75 • SA
SL, the stress due to sustained loadings shall be less than 0.75 x the allowable stress range, SA at
temperature. Sustained loadings are those due to pressure, self weight of contents & piping and other
sustained loadings particular to the situation.
SL = E ∗ a ∗ ∆Τ − v ⋅ ∗Sh ≤ 0.9SMYS
SE ≤ SA
Design of Piping – B31.8
B31.8 (1975) essentially limits the pressure design consideration to three items:
Design pressure:
2∗ S ∗t
P= D F•E•T
S = SMYS ,
Further,
B31.8 applies itself to the above ground piping in discussing expansion and flexibility to a temperature of
450 °F.
SE ≤ 0.72 • S
Design of Piping – CSA Z662
Pressure Design:
2S ∗ t × 10 × F × L × J × T
3
SE ≤ 0.72 • S • T
Design of Piping
Code Code +
Calculation Method
Simple
Complex
Answer Quality
Conservative
Accurate
Effort
Least
Most
Design Loads
The Codes prescribe minimum rules for stress conditions and alert the designer explicitly to some
of the loadings likely to act on a system. In addition to the previous listing, most of the Codes
specify design rules for:
The Codes caution the designer to consider the effect of other loadings and their impact on the
stress state of the system:
The Codes do not explicitly alert the designer to other loadings which may cause failure in the
piping system, including:
Key Considerations
• • Material specification
• • Chemical Composition
• • Mechanical Properties
• • Brittle fracture toughness
• • Carbon equivalent
• • Inspection
• • Repair Welding Procedure
Fittings – Low Temp ASTM A 420 WPL6 ASTM A 420 WPL6 ASTM A 420 WPL6
Fittings – High Temp ASTM A 234 WPB ASTM A 234 WPB ASTM A 234 WPB
ASTM A 216 WCB ASTM A 216 WCB
Flanges ASTM A 105 ASTM A 105 ASTM A 105
ASTM A 181 ASTM A 181 ASTM A 181
ASME B16.5 ASME B16.5 ASME B16.5
Flanges – Low Temp ASTM A 350 LF2 ASTM A 350 LF2 ASTM A 350 LF2
ASTM A 352 LCB ASTM A 352 LCB
Flanges – High Temp ASTM A 105 ASTM A 105 ASTM A 105
ASTM A 181 ASTM A 181 ASTM A 216 WCB
ASTM A 216 WCB ASTM A 216 WCB
Valves ASTM A 105 ASTM A 105 API 6D
ASME B16.34 API 600 API 600
Valves – Low Temp ASTM A 350 LF2 ASTM A 350 LF2
ASTM A 352 LCB ASTM A 352 LCB
Valves – High Temp ASTM A 216 WCB ASTM A 216 WCB
As can be seen from the Table, material selection can be made from available national standards
such as ASTM and API.
Material Selection – Common Specifications for Carbon Steel Systems (cont’d)
Brittle fracture refers to the often catastrophic failure of materials when subjected to
stresses at a lower temperature which the materially would normally be able to
withstand at higher temperatures.
A “transition temperature” can be defined at the 13.5, 20, 27 J (10, 15, 20 ft-lb)
energy level.
Charpy test results for steel plate obtained from failures of Liberty ships revealed that
plate failure never occurred at temperatures greater than the 20-J (15 ft-lb) transition
temperature.
This transition temperature varies with the material and is not used as a criterion.
Transition Temperatures
Charpy Testing
Energy
This figure provides a correlation between material group, reference thickness and
exemption temperature.
Material group is defined in Table A-1. For example, SA 106 B is given a Min Temp
rating of “B”. Entering Figure 323.2.2A, this material is impact testing exempt up to a
thickness of 0.5” down to a minimum temperature of –20 F. Curve B rises to a
minimum temperature of 75 F for a material thickness of 3”.
This Table also inherently provides for a risk based approach by bringing in service
fluid, test fluid and pipe design operating stress parameters.
Case Study:
On the next page, the Material Requisition Form has certain boxes marked off to
indicated inspection needs. Not all marked boxes are appropriate! Do you know
which?
INSPECTION REQUIREMENTS
Project No. Project Name Requisition No. Page 1 of 1
INSPECTION CHECKLIST: The Ins pector may c hec k (C), review (R), approve (A ) and/or w itness (W) the
f ollow ing items marked (X) below .
Welder's Qualif ications (R) Sandblast, Painting, Coating and Galvanizing (A )
Draw ing and Proc edures (R) Mechanical/Electrical/Pneumatic Run Test (W & A )
X Material Test Reports (C, R, & A ) X Nameplates , Tagging (C); Marking
Hydrotest (C) X Mac hining Tolerances (C)
Perf ormanc e Test (W on one pump per model) Tube Cleaning and Installation Procedure (R)
Complete Train Test (W & A ) Tube Bundle Ins ertion (W & A )
NPSH Tes t ( A ) One per pump model Shop Fit Up Prior to A ssembly (W)
Sound Level Test X Compliance w ith Specif ic ations (C)
X Dimens ional Chec k (C ) X Cleanliness Prior to Shipment (C)
X NDT (R) Elec tric al and Mec hanic al Runout (C)
Charts (C) Wiring Continuity/High Pot Test (C)
Rotor Balancing (R) X Flange Face Finish (C)
Compliance w ith Dimensional Outline Draw ing (C) Final Equipment Inspection (A )
Compliance w ith V endor's P&ID (C) Final Pac kaging Inspection (W & A )
Coupling Ty pe and Size (R) Seal Pres sure Test (C)
Coupling Hub Contac t
Note s: 1) The Contractor's ins pec tor or des ignate shall hav e ac ces s to V endor's premises f or the purpos e of documentatio
auditing or source inspection.
Paragraph 304.3.2 of the Code provides explicit direction on the proper design of branch connections.
In summary, this paragraph states that branch connections must be made using fittings that are inherently
reinforced such those listed in Table 326.1 or fabricated and sufficiently reinforced using design criteria
based on area reinforcement principles. This presumes that a branch connection opening weakens the pipe
wall and requires reinforcement by replacement of the removed area to the extent it is in excess to that
required for pressure containment. The Code is fully detailed in the necessary calculations. These
calculations can be very tedious, time consuming prone to error if done by hand. A computer program is
advised for productivity; a spreadsheet based program is more than adequate.
No calculation is required for branch connections made by welding a threaded or socket weld coupling or
half coupling if the branch does not exceed 2 NPS nor ¼ the nominal size of the run line. The coupling
cannot be rated for less than 2000 CWP.
The above list is actually very conservative and discretion is required in applying these rules
to ensure economical approach to piping analysis.
Paragraph 319.4.1 lists the conditions under which flexibility analysis may be waived.
Stanford University
Facilities Design & Construction Standards
SECTION 02551
UNDERGROUND STEAM AND CONDENSATE SYSTEM
SPECIFICATIONS
PART 1 GENERAL
A. Steam Distribution System: Steam is the primary heat source for a variety of
heating functions throughout the University. Saturated steam is generated at the
Central Energy Facility and distributed via a loop piping system which operates at
125 psig (353F). (Design conditions for piping are 135 psig and 400F. The
distribution system serves all sections of the Campus as well as the Hospital, Medical
School and Hoover Pavilion.
B. Condensate Return System: The condensate return system operates with 180oF
condensate at 20 psig. Design conditions for piping are 100 psig and 212 F.
A. All materials shall be certified new from factory. Pipe, fittings, and valves shall be
made in the USA or Canada to ANSI/ASME standards and suitably stamped. Piping
components made in other countries shall mot be used unless specifically approved by
the Project Manager.
C. The Contractor shall furnish to the Project Manager all applicable welding
procedures and welder certification and procedure qualification records. All
documentation shall be signed and dated by the appropriate Contractor personnel.
1.05 SUBMITTALS
3. Insulation, expansion joints, joint materials, fittings, valves, and gaskets shall be
stored under cover out of direct sunlight.
B. Handling:
1. Pipe, conduit sections, fittings, valves and other accessories shall be handled in
such a manner as to ensure delivery to the trench in sound, undamaged condition.
2. Special care shall be taken to avoid injury to coatings and linings on pipe and
fittings. Damaged coatings and linings shall be repaired by the Contractor to the
satisfaction of the Project Manager.
PART 2 PRODUCTS
A. Pipe:
3. Steam lines:
B. Fittings:
1. Threaded or socket weld (2 inch and smaller): ANSI B16.11 forged carbon steel,
ASTM A105, 2000# class.
2. Butt-Welded (2.5 inch and larger): ANSI B16.9, ASTM A234 WPB, schedule to
match pipe.
3. Flanged (2.5 inch and larger): ANSI B16.5, ASTM A105 forged steel, 150 or 300
pound class, weld-neck flanges shall be used to match equipment.
4. Unions (2 inch and smaller): ANSI B16.11 forged carbon steel, 800 # class.
6. All buried pipe fittings shall be butt welded for all sizes.
2.02 VALVES
A. General: Valves shall be threaded for 2 inch and smaller piping, flanged for 2.5
inch and larger. Socket weld or butt weld valves shall only be used if specifed on the
Contract Drawings. Acceptable valve manufacturers for steam or condensate service
are provided below; no substitutions unless approved by the Project Manager.
B. Gate Valves:
1. Threaded (2 inch and smaller): ANSI B16.34, 800 pound class, forged steel, bolted
bonnet, OS&Y, conventional port gate valve Walworth, Vogt, or Edwards.
2. Flanged (2.5 inch and larger): ANSI B16.34, 150 pound class, A216 WCB cast
steel body, bolted bonnet, OS&Y., stainless steel trim; Walworth or Stockham.
3. Butt weld (2.5 inch and larger): ANSI B16.34, 150 pound class, A216 WCB cast
steel body, bolted bonnet, OS&Y; stainless steel trim, Walworth or Stockham.
4. Warmup lines: All gate valves 4 inch and larger shall have bypass lines with
appropriately sized warmup valves.
C. Globe Valves:
1. Threaded (2 inch and smaller): ANSI B16.34, 800 pound class, forged steel body,
stainless steel seat ring and plug, bolted bonnet, rising steam; Walworth, Vogt, or
Edwards.
2. Flanged (2.5 inch and larger): ANSI B16.34, 150 pound class, A216 WCB cast
steel body, OS&Y; stainless steel trim, Walworth or Stockham.
D. Ball Valves:
1. Threaded (2 inch and smaller): 150 pound class, steam-rated, cast steel/stainless
steel, Nibco or Walworth.
1. Threaded (for steam trap discharge): 800 pound class, forged steel, stainless steel
disc, swing check; Vogt, Edwards, or Walworth.
2. Flanged (2.5 inch and larger): ANSI B16.34, 150 pound class, A216 WCB cast
steel body, bolted flange cover, swing check; Walworth or Stockham.
3. Vertical lift check valves: threaded, 150/200 pound class, bronze body, for steam
powered condensate pump, Stockham or Walworth. (reference Standard Drawing
MS-59).
F. Rotary Valves: 1. 150 pound class, carbon steel, flanged, Adams or Keystone
Vanessa.
B. Bolting: ASTM A193, Grade B7, for bolts and studs, and ASTM A194, Grade 2H
for nuts.
D. Wall Penetration Seals: High temperature elastomeric link type mechanical seals
compressed with corrosion-protected bolts and compression plates; Thunderline Link-
Seal, no substitution. (Reference Standard Drawing MS-52)
E. Expansion Joints:
1. Expansion joints shall be slip tube type or extenally pressurized bellows type as
designed for the specific location. They shall be 150 psig steam rating, flanged, and
shall conform with the Standards of the Expansion Joint Manufacturers Association.
2. Bellows type joints shall have 316 ss bellows, and may be single or double bellows
style as required for the intended service: Hyspan, Pathway or Senior Flexonics.
3. Slip-tube type shall have external and internal high performance guides rated for
500oF and designed for packing under pressure; Yarway or Hyspan.
4. Slip-tube joints shall be single or double type with center take-off taps as required
for the given service. See Standard Drawing MS-54 for typical installation.
F. Steam Traps for main line or building PRV assembly (see Standard Drawing MS-
55): Steel body, 3/4 inch diameter, thermodynamic disc type, Nicholson TD 301,
Yarway #721, or Spirax Sarco TD. Install 3-way forged steel trap test valve
downstream of trap and before check valve.
G. Automatic Air Vents (for high points on condensate systems): 3/4 inch threadolet
with 3/4 inch gate isolation valve is required upstream of air vent. Air vent shall be
3/4 inch 150 # rating, Sarco 13W or approved equal. Discharge of condensate air
vents in vaults shall be routed to the floor.
H. Strainers (for use on steam trap stations): Y-type with cast or forged steel body,
1/16 inch mesh monel strainer elements, threaded for 2 inch and smaller piping; C.M.
Bailey or Spirax Sarco IT.
I. Pipe Hangers and Supports: Pipe hangers and supports shall be designed, and
located per the requirements of B31.1 and the recommendations of the powder
insulation or prefabricated conduit system vendor.
J. Pressure guages: 4.5 inch dial, bourdon tube, 0 to 200 psig on steam mains, 0 to 50
psig on condensate mains, Ashcroft or equal. Include isolation valve and pigtail coil
on steam guages.
K. Steam main high point vents: Install isolation valve and thermostatic vent on steam
main high points, Spirax Sarcp V-204 or equal. Vent discharge to floor.
L. Insulation:
1. In manholes, pipe 2.5 inch and greater shall be insulated with ASTM C533, Type I,
calcium silicate; 2.5 to 6 inch steam (3 inches thick), 8 to 12 inch steam (4 inches
thick), 2.5 to 6 inch condensate (2 inches thick).
2. In manholes, tunnels, and exterior installations: pipe and fitting insulation shall be
covered with 0.016 inch smooth aluminum jackets with integral moisture barrier.
Stainless steel band on 12 inch center shall hold the insulation to the pipe.
3. Valves and equipment shall be insulated with removable shop-fabricated fiberglass
padding rated for 500oF, with thin wire mesh lining, and covered with 18 ounce high-
temperature fiberglass cloth with velcro straps.
2.04 MANHOLES
1. All structures shall be of reinforced concrete. Main line junctions and service
connections shall be in vaults, which require two openings. Minor assemblies such as
drip legs, can be in pits, which require only one opening.
4. Concrete shall be 2500 psi minimum compressive strength after twenty-eight (28)
days, for both prefabricated and field-constructed manholes.
7. Covers and openings shall be vehicular traffic rated (H-20). 38-1/2 inch Neenah
1792 frames with one 40 inch solid lid and one 40 inch grate lid, both marked
STEAM.
A. The powder insulation system shall provide for minimizing heat loss, corrosion
protection, and unrestricted thermal movement between anchors.
D. Pipe Supports: Anchors shall be located outside vaults, typically at five to ten feet
from the vault wall. Expansion loops shall use guides and vertical supports as
required.
B. Conduit End Seals: Conduit end seals shall be fixed type where there is no thermal
pipe expansion through the end seal, and shall be slip type where there is thermal pipe
expansion through the end seal. One-half inch (1/2") threaded pipe ports at top and
bottom of each end seal shall be provided for draining, venting, and pressure testing
of conduit casings.
C. Insulation: ASTM C533, Type I, calcium silicate, mineral fiber, or C552 cellular
glass three inch (3") for steam, and two inch (2") for condensate shall be used on the
steel pipe within the casing.
1. ANSI B31.1, factory fabricated, with weld testing per design. Casing, couplings,
insulation, and piping shall be identical to those used for straight runs and designed to
ensure complete drainage. Fabricated materials shall be shipped to the job site in
maximum feasible size sections to minimize number of field joints.
2. Loop casings shall be sized to contain pipe movement without crushing the
insulation or causing other damage. Eccentric reducers and increasers or welding
collars designed to serve the same purpose shall be used to allow free drainage
through the loop.
3. Pipe supports shall be slotted to permit unrestricted lateral movement of piping, and
shall be otherwise identical to pipe supports specified for straight runs.
PART 3 EXECUTION
B. Trenching: Stanford may limit the amount of trench to be opened at any time.
C. Bedding:
E. Damage Repair: Utilities, walls, piping, and other improvements damaged during
the course of work shall be repaired to their original condition or replaced by the
Contractor.
F. Excess Material: Excess material and debris shall be removed and disposed of, at
an approved disposal site, within one week after final approval of installation.
A. General:
1. Piping and pipe systems shall be fabricated, assembled, welded, installed and tested
in accordance with ANSI B31.1.
2. Piping shall be cut accurately to field measurements and worked into place without
springing or forcing, except where cold-springing is specified. Piping shall not be
buried, concealed, or insulated until it has been inspected, tested, and approved in
accordance with Article 3.07, Field Quality Control (below).
3. Materials and equipment shall be protected from the weather during construction.
4. Pipe runs underground between vaults shall be welded. Flanged and threaded joints
shall not be buried.
5. Gaskets, packing, and thread compounds shall be suitable for the service. Joint
compound or thread tape shall be applied to male threads only.
6. Arrangement of all piping shall be shown on the drawings. During installation, care
shall be taken to avoid interference with other piping, conduit, and equipment. Lines
shall be trapped only where shown on the drawings.
7. Reducing fittings shall be used for changes in pipe sizes. Bushings shall not be
used.
8. In horizontal lines two inches (2") and larger, reducing fittings of the eccentric type
shall be used to maintain the bottoms of the lines in the same plane for steam, and the
tops of the lines in the same plane for condensate.
9. Pipe shall be adequately supported and anchored so that strain from weight and
thermal movement of piping is not imposed on piping, equipment, or structures.
B. Cleaning:
1. Each section of pipe, fittings, and valves shall be thoroughly cleaned free of all
foreign matter before erection. Interior of piping shall be cleaned thoroughly as
described in Article 3.07 (below) before final connections are made.
2. Open ends of mains shall be plugged or capped during shutdown periods. Lines
shall not be left open at any place where foreign matter might accidentally enter pipe.
E. Steam Line Drainage: Steam lines shall be pitched to allow for condensate drainage
to the low point steam pots. For steam pipes in tunnels sloped down down in the
direction of steam flow, a minimum of three inches per one-hundred feet (3" per 100')
of length is required. Where counterflow of condensate must be accommodated in
steam tunnels, lines shall be pitched up in the direction of steam flow six inches per
one-hundred (6" per 100') feet of length. Buried steam lines shall be pitched to
accommodate the worst case of 6" per 100 feet. Steam lines may be peaked with lines
pitched as above. Final pipe elevations must be recorded on the as-built drawings.
F. Welding:
required for construction of the steam distribution and condensate return systems.
c. Contractor shall determine the suitability of welding procedures used to ensure that
welds meet the requirements specified herein.
2. Beveling: Field bevels and shop bevels shall be done by mechanical means or by
flame cutting. Where beveling is done after flame cutting, surfaces shall be ground
and thoroughly cleaned of scale and oxidation just prior to welding. Beveling shall
conform with ANSI standards.
3. Butt welds: All butt welds shall be open root, multi-pass welds, 6010 or 6011 root
with 7018 filler caps (SMAW welding process).
3. Electrodes shall be stored in a dry, warm area and kept free of moisture during
fabrication operations. Electrodes that have lost part of their coatings shall be
discarded.
4. Welds shall be inspected in accordance with ANSI B31.1 requirements. The Owner
will radiograph 5 to 10% of the welds.
5. If any welds are found to be defective, the Contractor is responsible for full 100%
radiograph testing of all the welds. Repair of defective welds by adding weld material
over the defect, or by peening shall not be permitted. Welders responsible for
defective welds shall be re-qualified before performing more welding on the job.
6. All finished weld joints shall be painted with high temperature black paint.
G. Anchor Blocks:
1. Anchor Blocks: Concrete anchor blocks shall be provided for pipe anchorage not
less than five feet (5') from building or manhole walls (except where metal anchor at
the vault wall is shown on the Contract Drawings). Size and position of anchor blocks
shall be as shown on Standard Drawings MS-51 and MS-52. Anchor blocks shall be
cast against undisturbed earth using concrete that conforms to ASTM C-94 and has a
minimum compressive strength of 2,500 psi at twenty-eight (28) days.
1. Insulation shall be continuous through pipe hangers with calcium silicate inserts to
prevent crushing of insulation.
2. Steam and condensate valves and equipment in manholes and buildings shall be
insulated and covered with removable jackets. Insulation shall stop short of
bolts/studs at flanges to allow their removal without damage of permanent insulation.
3. Trap sections between unions in steam trap manifolds shall not be insulated.
4. No exposed insulation will be permitted. Aluminum or PVC end caps that match
the insulation jackets shall be used to cover the ends of insulation runs.
5. Steam and condensate lines in manholes, tunnels, and buildings shall be color
coded as follows, or as otherwise directed by the Project Manager:
High pressure steam - RED (darker shade)
Reduced pressure steam - RED (lighter shade)
Condensate Return (building) - Orange (lighter shade)
Condensate Return (steam system traps) - Orange (darker shade)
A. Valves shall be installed in accordance with ANSI B31.1 and ASME Section VIII.
B. Valves shall be installed as shown on the drawings and as required for proper
functioning of the system.
D. All flange bolts shall be lubricated with a high temperature bolt lubricant approved
by the Project Manager. Flanged bolt torquing shall be in a incremental staggered
patternto assure even compression of the gasket.
A. Traps and Manifolds: Steam drip and mud legs, guard and blowdown valves, and
piping shall be as shown on Standard Drawing MS-55. Dual traps stations shall be
installed at all mud legs unless otherwise indicated on the drawings. Multiple trap
manifolds at one location shall be in the same horizontal plane.
1. Hangers shall be sized to allow for continuous pipe insulation through the hangers.
Hangers shall not be permitted to touch steam pipe.
1. Conduit sections shall be joined after leak testing of carrier pipe. Conduit joining
materials provided or specified by the system manufacturer shall be used.
2. Pipe shall be insulated and casing joined to provide field joint equal to factory
fabricated section on conduit system. Connections to existing conduit systems of a
different manufacturer or type shall be made only in manholes or buildings and never
in buried locations.
B. Conduit End Seals: Conduit end seals in manholes or tunnels shall be provided
with gooseneck vents on the top and drain valves on the bottom. In buildings, conduit
end seals shall be provided with threaded brass plugs. Refer also to Standard Drawing
MS-51.
A. General: The Project Manager or his representative will conduct field inspections
and shall witness all field tests specified in this Section. The Contractor shall perform
field tests and provide labor, equipment, and incidentals required for testing. The
Contractor shall produce evidence, when required by the Project Manager, that any
item of work has been constructed properly in accordance with the Contract Drawings
and Specifications.
B. Field Tests:
1. General: All anchor blocks and restraints shall be complete prior to testing.
Concrete supports shall be fully cured.
2. Piping Initial Air Leak Tests: Before insulation is applied at field joints, piping
shall be pressurized to twenty-five (25) psig air pressure and tested for leaks with soap
solution. Leaks shall be repaired and test repeated.
a. Test pressure gauges for a specific test shall have dials indicating not less than one
and one-half (1-1/2) times nor more than two (2) times the test pressure.
5. Cleaning: After pressure and hydrostatic testing, the pipe system shall be flushed
with a water/chemical solution. The procedure, cleaning solutions, and disposal shall
be approved by the Project Manager.
6. Operational Tests: After completion of the work, the system shall be operated for
not less than six (6) hours at operational temperatures and pressures to demonstrate
satisfactory function. The movement of each expansion joint shall be checked, and
each valve shall be operated in both cold and hot conditions.
END OF SECTION