Scope of Supply/Work for Protection Relay and Control Panels

PROJECT: JAZAN - INTEGRATED GASIFICATION COMBINED CYCLE (IGCC) DS NO:

CUSTOMER: SAUDI ARABIAN OIL COMPANY DESC:

PLANT LOC: SAUDI ARABIA REV:

EQ TAGs:

DIVISION OF RESPONSIBILITY(Included but not be limited to)


ITEM DESCRIPTION BY Supplier
A Scope of supply
Protection Relay and Control Panels as mentioned in the Specification, X
1 Datasheet and Drawings
Nameplate shall be abrasion resistant, stainless steel and attached with X
2
stainless steel hardware
3 Coordination with Owner for cable connection interface X
c
Nameplate, lifting lugs and earth lug for individual Equipment & Package X
5

All supporting steel work, platform, walkway,stair case and hardware,


which from part of the complete installation of the equipment including
steel foundation frame, anchor bolts, holding down bolts, buses,
6 insulators, flexible connectors, etc., required for all mechanical and X
electrical items.

7 Anchor bolt, nuts and washers (To be galvanized) X


Special tools for erection and maintenance (Optional) X
8

Critical spare parts (Optional) X


9

Installation and commissioning spare parts (Optional) X


10

Maintenance and operational spare parts for two years (Optional) X


11
Operation and Maintenance Manual X
12

13 Operation materials if required X


14 Interface points as per MR layout including all wall penetrating GIB X
brackets, support structures and fixtures.

B Scope of work
SERVICES
Drawings and Documents of Supplier-supplied equipment with sufficient
1.1 X
details for installation and maintenance.
1.2 Design, engineering and documentation X
1.3 Manufacturing X
1.4 Factory Shop Tests X
1.5 Factory Performance test X
1.6 Additional Factory Tests X
1.7 On-site Testing X
1.8 Site acceptance test X
1.9 Installation work

Page 1 OF 4
Scope of Supply/Work for Protection Relay and Control Panels
PROJECT: JAZAN - INTEGRATED GASIFICATION COMBINED CYCLE (IGCC) DS NO:

CUSTOMER: SAUDI ARABIAN OIL COMPANY DESC:

PLANT LOC: SAUDI ARABIA REV:

EQ TAGs:

DIVISION OF RESPONSIBILITY(Included but not be limited to)


ITEM DESCRIPTION BY Supplier
1.10 Training of operating and maintenance personnel X
1.11 Painting (primer, finish) work at factory X
1.12 Rust preventing treatment X
1.13 Monthly Progress Report X
1.14 Operating and maintenace manuals X
1.15 Startup and testing assisstance X
1.16 Field erection labor and equipment
1.17 Project Review Meetings X
1.18 Constructability Review X
Supervisory sevice for installation and test operation (perdiem X
1.19
basis)
1.20 Insulation and lagging work X
Seaworthy export packing and inland transportation to the X
1.21 port (FOB)

Page 2 OF 4
k for Protection Relay and Control Panels
SEP-PGB-EL-SOW-0036

Protection Relay and Control Panels

00 DATE: 14-Mar-16

ONSIBILITY(Included but not be limited to)


BY Purchaser COMMENTS

To be quoted separately

To be quoted separately

To be quoted separately

To be quoted separately

SERVICES

Page 3 OF 4
k for Protection Relay and Control Panels
SEP-PGB-EL-SOW-0036

Protection Relay and Control Panels

00 DATE: 14-Mar-16

ONSIBILITY(Included but not be limited to)


BY Purchaser COMMENTS

X
X
X

Page 4 OF 4