Академический Документы
Профессиональный Документы
Культура Документы
A design guide
Karen Fisher
David Ramsbottom
Published by Thomas Telford Publishing, Thomas Telford Ltd, 1 Heron Quay, London E14 4JD.
URL: http://www.thomastelford.com
A catalogue record for this book is available from the British Library
ß Queen’s Printer, Controller of Her Majesty’s Stationery Office and HR Wallingford Ltd
This work is not subject to the terms of the Class Licence for the reproduction of Crown Copyright material.
Following the General Election in June 2001, the responsibilities of the former Department of the
Environment, Transport and the Regions (DETR) in this area were transferred to the new Department for
Transport, Local Government and Regions.
All rights, including translation, reserved. Except as permitted by the Copyright, Designs and Patents Act
1988, no part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or
by any means, electronic, mechanical, photocopying or otherwise, without the prior written permission of the
Publishing Director, Thomas Telford Publishing, Thomas Telford Ltd, 1 Heron Quay, London E14 4JD.
This book is published on the understanding that the authors are solely responsible for the statements made
and opinions expressed in it and that its publication does not necessarily imply that such statements and/or
opinions are or reflect the views or opinions of the publishers. While every effort has been made to ensure
that the statements made and the opinions expressed in this publication provide a safe and accurate guide, no
liability or responsibility can be accepted in this respect by the authors or publisher.
River diversions are artificial channels that are used to divert all or part of the
river flow. River diversions are required for a variety of reasons, including
flood relief channels, permanent diversions to permit developments on, or
adjacent to, rivers, and temporary diversions to permit construction work in
rivers.
The design of river diversions covers a wide range of topics, including site
selection, hydrology, hydraulics, environmental considerations, engineering
design, legislation and planning, construction and maintenance. It is very
important that all these aspects are considered during the feasibility and design
stages of river diversions in order to minimise the risk of unforeseen problems
arising during the planning and implementation stages.
The primary purpose of this book is, therefore, to provide guidance on the
design of river diversions taking into account the wide range of issues that must
be considered. The book provides an introduction to these issues and references
are provided to give a more complete coverage of particular aspects. In
addition, specialist advice may also be required for particular aspects of a
scheme but this will depend on the individual scheme and the capabilities of the
design team.
River diversions vary in size from small channels to major river engineering
schemes. The Windsor, Eton and Maidenhead scheme on the River Thames, for
example, consists of an 11 km long flood relief channel with a capacity of 215
cumecs. The principles set out in this book apply to all types and sizes of river
diversion, although the amount of effort needed will depend on the magnitude of
the problems to be addressed.
David Ramsbottom graduated from Cambridge University in 1975 and has spent
his career in water engineering and management. He worked for consulting
engineers Rendel, Palmer and Tritton on harbour and river engineering between
iii
RIVER DIVERSIONS
1975 and 1979, and then for Sir Mott MacDonald and Partners on irrigation,
drainage and river engineering between 1979 and 1988. Since joining HR
Wallingford in 1988, he has specialised in river engineering and management,
including catchment management, flood control and flow measurement.
iv
Acknowledgements
The Design Guide was developed by HR Wallingford Ltd and was funded by the
Department of the Environment (now the Department of the Environment,
Transport and the Regions) under the Partners in Technology Scheme. A Steering
Group was established to assist with the development of the Design Guide. In
addition to attending meetings to discuss and review the Design Guide, members
of the Steering Group advised on particular aspects, provided information on
examples of river diversions and reviewed draft versions of the overall document.
The Steering Group consisted of:
v
RIVER DIVERSIONS
engineering industries worldwide for over 50 years in more than 60 countries. The
company provides appropriate solutions for engineers and managers working in:
• water resources
• groundwater
• urban drainage
• rivers
• tidal waters
• ports and harbours
• coastal waters
• offshore.
Editor's Note
Following the General Election in June 2001, various Government departments
have been renamed and reorganised. This guide was written prior to the General
Election and the names of the Government departments used were correct at the
time of writing.
vi
Contents
Illustrations xiii
2. Outline design 11
2.1. Introduction, 13
2.2. General procedure, 14
2.2.1. Technical, 14
2.2.2. Environmental, 15
2.2.3. Consultation, 15
2.2.4. Legislation, 15
2.3. Data collection, 16
2.3.1. Catchment management, 16
2.3.2. Geomorphology, 17
2.3.3. Hydrological and hydraulic data, 19
2.3.4. Engineering data, 20
2.3.5. Environmental data, 21
2.4. Outline design, 22
2.4.1. Site selection and layout, 22
2.4.2. Flow rate, 25
2.4.3. Hydraulic design, 25
2.4.4. Environmental aspects, 27
2.4.5. Operation and maintenance, 29
vii
RIVER DIVERSIONS
5. In-channel structures 65
5.1. Control structures, 67
5.1.1. Calculation of flow at a control structure, 68
5.1.2. Fixed weirs, 68
5.1.3. Moveable weirs, 72
5.1.4. Flumes, 73
5.1.5. Gated structures, 73
5.1.6. Orifices, pipes and culverts, 74
5.1.7. Air-regulated siphons, 75
5.1.8. Dams for diversion purposes, 75
5.2. Crossing structures, 76
viii
CONTENTS
5.2.1. Bridges, 76
5.2.2. Culverts, 76
5.3. Maintenance of passage structures, 77
5.3.1. Fish passes, 77
5.3.2. Navigation lock, 78
5.4. Inlet structures, 78
5.4.1. Location and alignment, 79
5.4.2. Transition and entrance, 80
5.4.3. Outlet structures, 81
6. Sediment transport 83
6.1. Introduction, 85
6.2. Initiation of motion, 86
6.3. Sediment transport in non-cohesive, uniform
sediments, 88
6.3.1. Bed load, 89
6.3.2. Suspended load, 89
6.3.3. Wash load, 89
6.3.4. Total load, 89
6.4. Application and use of sediment transport formulae, 89
6.5. Graded sediments, 90
6.6. Cohesive sediments, 90
6.7. Alluvial friction, 91
6.8. Regime theory, 91
6.8.1. Application of regime theory, 92
Part C Construction 93
7. Construction issues 95
7.1. Introduction, 97
7.2. Environmental considerations, 97
7.3. Duration and season, 98
7.3.1. Permanent diversion channels, 98
7.3.2. Temporary diversion channels, 98
7.4. Form of construction, 98
7.4.1. Permanent diversion channels, 98
7.4.2. Temporary diversion channels, 99
7.5. Ground conditions, 99
7.6. Groundwater, 100
7.7. Water quality, 100
7.8. Pumping, 101
7.8.1. Temporary diversion channels, 102
7.9. Risk and integrity of works, 102
7.10. Storage and disposal of material, 102
7.10.1. Permanent diversion channels, 102
7.10.2. Temporary diversion channels, 102
ix
RIVER DIVERSIONS
x
CONTENTS
Appendices 137
Appendix 1. Methods for calculating the tailwater elevation, 139
Appendix 2. Roughness coefficients for natural channels, 145
Appendix 3. Legislation and statutes, 147
Appendix 4. Examples of river diversions, 151
Index 173
xi
Illustrations
Tables
Table 1. Checklist of the principal considerations
for the design of river diversions 16
Table 2. Baseline data 21
Table 3. Standard methodologies for data collection 22
Table 4. Impacts on flora and fauna of diverting a
channel 62
Table 5. Structure types 67
Table 6. Different soil types and associated
problems 114
Table 7. Risks associated with cofferdam
construction 116
Table 8. Risks in pipeline construction 120
Table A2.1. Roughness coefficients for natural channels 146
Table A4.1. Flow split at the Maidenhead, Windsor and
Eton flood relief channel 156
Figures
Figure 1. Different types of diversion channel:
(a) permanent diversion channel replacing
existing channel; (b) permanent diversion
of part of the flow – wet diversion channel;
(c) diversion of part of the flow during
floods – dry diversion channel;
(d) temporary diversion channel 6
Figure 2. How to use the design guide 8
Figure 3. Acceptable and unacceptable options for
river diversion 24
Figure 4. Wraysbury River – existing river
downstream of the diversion 26
Figure 5. Design procedure for river diversions 32
Figure 6. Water flow and structural components
of pool riffle sequences: (a) plan view;
(b) long profile 47
Figure 7. Pool riffle sequence in a straight channel 49
xiii
RIVER DIVERSIONS
xiv
ILLUSTR ATIONS
xv
Part A
Feasibility and planning
Introduction
1
1. Introduction
1.1. BACKGROUND
A river diversion is an artificial channel that is used to divert all or part of the river
flow. River diversions may be required for a range of civil engineering projects,
including flood alleviation schemes, developments on, or adjacent to, a
watercourse, and schemes for new highways or highway widening. Some river
diversions are temporary in order to permit construction work to be carried out
and others are permanent. The objective of this book is to provide guidelines on
the design of river diversions. River diversion design requires a multi-disciplinary
approach. As the awareness of environmental issues has increased, the effects of
engineering works on the ecology, fisheries and pollution within rivers has
become increasingly important. The planning, design and construction of river
diversions needs to take these issues into account alongside engineering
considerations.
(a) Permanent ‘wet’ diversion to replace the existing channel. In this case all the
flow is diverted on a permanent basis. For example, a new road or other
development may require a permanent river diversion. Permanent diversions
were constructed on the River Biss (see Section A4.3 in Appendix 4).
(b) Permanent diversion of part of the flow. A diversion channel that diverts part
of the flow may either be wet or dry. In both cases a method of splitting the
flow (usually a hydraulic structure) will be needed. Diversion of part of the
flow was carried out on the River Colne at Accommodation Lane (see
Section A4.4.2). A flood relief channel is an example of a permanent
5
RIVER DIVERSIONS
(a) (b)
Main flow
Control
Control
structure
structure
may be
required
Control
structure
may be
required
(c) (d)
6
INTRODUC TION
diversion of part of the flow. In this case the existing channel is too small for
the flood capacity required and the diversion channel accommodates the
excess flow. This channel may be wet or dry. In the latter case, flow only
occurs in the diversion channel during a flood. A particular case where a
flood relief channel may be the only solution is where buildings or other
features close to the river prevent the possibility of increasing the flow
capacity by river widening or other improvements to the channel and
adjacent floodplains. Flood relief channels were used on the River Colne at
Staines and Lower Horton (see Section A4.4).
(c) Temporary diversion of all flow. In this case the flow is diverted through a
temporary diversion channel in order to undertake work on the existing
channel or a structure before returning the water to the existing channel. A
temporary diversion may be used where a river structure needs to be
constructed in the dry, or the channel must be closed to permit river
restoration or other channel works to be undertaken. A temporary diversion
channel was utilised at Brockenhurst gauging station (see Section A4.5).
(d) Temporary diversion of part of the flow. Part of the flow, usually the high/
flood flows may be diverted to allow work to be undertaken within or
adjacent to the existing channel.
• planning
• data requirements
• outline design
• detailed design
• environmental considerations
• construction, operation and maintenance
• legislation.
The guide is generally intended for application in the UK but many of the basic
principles including, for example, hydraulic design are applicable in other
countries.
The guide is generally concerned with permanent diversions but the methodology
is also applicable to temporary diversions. Many river diversions, particularly
temporary diversions, are carried out on small rivers and streams where considerable
effort in design cannot normally be justified. However, even in these cases it is
important to ensure that the fundamental issues (e.g. flow capacity and
environmental impact) are addressed adequately. Temporary diversions often take
the form of pipe diversions and CIRIA Report 168 (1997b) should be referred to for
more detailed design guidance on pipe diversions.
7
RIVER DIVERSIONS
Chapter 1
Chapter 2
Chapter 3
In channel structures
Chapter 5
Sediment transport
Chapter 7 Chapter 8
Part C: Construction
Part D: Legislation
8
INTRODUC TION
9
Outline design
2
2. Outline design
2.1. INTRODUCTION
An outline design is needed to assess the feasibility of the river diversion and the
likely costs. For permanent diversions this work normally forms part of the
feasibility study where a range of options would be assessed. The choice of option
is determined by a number of factors, including the availability of land and
topography, cost, planning considerations, design standards, environmental
considerations and public opinion.
Temporary river diversions are often designed by contractors as part of the
temporary works needed to undertake an engineering project.
Before any river diversion scheme is designed, the options and alternatives
should be considered on engineering, economic and environmental grounds. Once
the options have been considered and a decision has been taken to divert the river
on a permanent or temporary basis, attention can be turned to planning, detailed
design and construction. It is important that the environmental, engineering and
economic consequences of any proposals are considered fully at this stage
together with possible impacts on the wider catchment.
Creating a river diversion may have a major impact on the natural habitat of a
channel as well as on navigation, archaeology, recreation, landscape, flood
storage, sediment transport and flow. The impacts of diverting a river can be
numerous and include:
• loss of established aquatic and riparian habitat
• loss of stable (historical) geomorphological regime leading to erosion or
sediment deposition
• loss of flood storage and changes in drainage routes
• loss of agricultural land
• disturbance of archaeological sites
• noise and dust pollution
• changes in ground and surface water quality, including chemical, biological and
physical
• alteration of interchange with groundwater
• changes in sedimentation regimes
• disruption to navigation and recreation
• localised deposition at the point of convergence/divergence with the main
channel
13
RIVER DIVERSIONS
2.2.1. Technical
To assess the technical feasibility of a river diversion, the following must be
addressed:
14
OUTLINE DESIGN
2.2.2. Environmental
An environmental scoping exercise should be commenced at this stage as the first
stage in an Environmental Impact Assessment. The scoping exercise should
identify environmental constraints, concerns and opportunities. These may
include the effect of the works on the flora and fauna, water quality, recreation
and amenities, and should take account of catchment considerations and the
overall sustainability of the project.
Existing baseline environmental information should be collected and assessed
to determine whether the data are of sufficient quality to use in an Environmental
Assessment. If not, define the baseline information to be collected as described in
Section 2.3.5.
The need for a full Environmental Statement for the preferred option may also
be identified during the outline design stage. If significant environmental effects
are likely to result from the project then an Environmental Statement will be
required. Taking informal advice from statutory consultees at this stage will
provide a good indication of the need for an Environmental Statement. It is
especially important to consult with the local planning authority in determining
the need for and the scope of an Environmental Statement. Guidance on preparing
an Environmental Statement is given by the Department of Environment (DoE –
the DoE is now known as the Department of the Environment, Transport and the
Regions) document entitled Preparation of Environmental Statements for
planning projects that require Environmental Assessment: A good practice guide
(DoE, 1995). Even if an Environmental Statement is not required, an informal
assessment should be carried out as good practice to ensure that potential impacts
are identified and managed.
2.2.3. Consultation
Consultations should be carried out with statutory and non-statutory bodies to
involve and inform. These consultations are needed to assess reaction and
opinion, and to identify constraints and issues to be taken into account in the
design process. Relevant organisations include the Environment Agency, the river
authority (if different from the Environment Agency), local people, angling clubs,
the local planning authority and environmental organisations.
2.2.4. Legislation
Legislative and planning requirements must be considered when taking account of
the status of the local watercourse (main river or ordinary watercourse, see
Section 9.4), as well as many other criteria.
Designing a river diversion is not simply a question of choosing a channel or
pipe large enough to convey the required flow. There are many factors to consider
and conflicting requirements may arise. The best solution may involve a compro-
mise but the designer should seek to produce the best solution under the circum-
stances by taking into account technical, economic and environmental aspects.
15
RIVER DIVERSIONS
Table 1. Checklist of the principal considerations for the design of river diversions
16
OUTLINE DESIGN
are defined as discrete geographical units with boundaries derived primarily from
surface-water considerations and comprising one or more hydrometric sub-
catchments.
The issues of catchment management relate mainly to permanent river
diversions. The effect of the diversion on the whole catchment must be considered
at the feasibility stage of the project in order to ensure that any adverse impacts
and mitigation measures are identified before detailed design is carried out.
Issues affecting the whole catchment include:
For each main river, the Environment Agency will have a Local Environment
Agency Plan (LEAP). These provide a useful source of information when
assessing catchment issues. LEAPs provide information on the catchment,
including the interests of county, borough, district and town councils and the local
development plans for the catchment.
LEAPs have been developed with the help of local communities and groups.
They are used to reconcile conflicts between competing uses of water, integrate
water and land uses, and they consider issues within both short-term and long-
term time horizons.
LEAPs consider the various water users’ interests and include the development
of a long-term vision and medium-term strategies and actions through
consultations with local communities and organisations.
A LEAP may include the history of the river and development of the catchment
from old maps, photographs and anecdotal evidence. A LEAP provides useful
information on the past development of the river and the likely changes to the
river in the future.
2.3.2. Geomorphology
A LEAP may include a geomorphological assessment or survey of the river,
which will provide valuable information regarding the shape, size and plan form
of the river in its existing and historical context. However, if the LEAP does not
include this information it is advised that a geomorphological assessment is
carried out. Any proposed diversion can then be considered in the light of the
assessment to determine the deposition/erosion potential of the diversion channel
and what the impact would be on the upstream and downstream reaches of the
river.
The findings of the geomorphological assessment and survey should be taken
into account in the design of the channel. The assessment will also identify
maintenance problems and erosion/deposition issues. The geomorphological
assessment consists of the following:
17
RIVER DIVERSIONS
• fluvial audit
• historical change analysis.
Fluvial audit
A fluvial audit is a geomorphological assessment of channel stability. Its basis lies
in obtaining a semi-quantitative understanding of the sediment budget of a reach
within the context of its catchment. It is critical when assessing the catchment
factors that influence the fluvial geomorphology of a reach.
Traditionally, there has been a lack of consideration given to geomorphological
issues at the planning stage of a project leading to a later treatment of the
symptoms rather than early treatment of the causes. Linkages need to be made
between catchment processes, sediment transport and morphological dynamics at
an early stage of a project.
A fluvial audit makes use of available and easily collected information to assess
the stability of the current channel. It incorporates the collection of two different
types of data:
(a) Documentary evidence at the scale of the catchment and channel network for
extended time periods to identify Potentially Destabilising Phenomena
(PDP).
(b) Field evidence and site specific documents used to assess the current channel
stability, to characterise the operation of the sediment system and to confirm/
reject evidence of channel response to any PDP.
18
OUTLINE DESIGN
changes have occurred. In some cases the channel will have been constrained and
it will be more difficult to determine the natural changes in the system.
Sediment modelling
One-dimensional sediment models or hand calculations can be used to determine
the volumes of sediment entering and leaving a reach and the likely impacts
upstream and downstream. Bed samples need to be collected from representative
sections in the river if these calculations are to be performed. This technique will
enable the flow of sediments into and out of the reach in the existing situation to
be matched in the design of the diversion channel.
• an assessment of the size and nature of the catchment area upstream of the
diversion channel and other information needed to provide a hydrological
estimate of flood flows
• an assessment of the maximum flood level based on known information, gauge-
board levels from the Environment Agency or the local authority, or local
information, including photographs and newspaper cuttings
• if the river has a gauging station there should be information on flood levels and
flows, and care should be taken that the gauging station rating curve used is
suitable for high flows. In particular, if ‘drowning’ of gauging structures occurs,
this must be taken into account in the rating. In addition, flood water may
bypass the gauging site (and, hence, not be measured). Photographs of the
gauging station during flood flows are very helpful.
The designer should also look at the impact of any future developments,
highlighted in the catchment plans or local plans, which may impact upon the
runoff and affect future flood peak flows, especially for urban storm events.
19
RIVER DIVERSIONS
Low flows
For diversion channels, the low flow is likely to be as important as the flood
flows. The low flow regime is the dominant regime and influences the water
quality, self-cleansing ability, ecology, fish migration, recreation, visual amenity
and access for maintenance.
It is recommended that low flow data should be collected. Low flow data can
often be collected from gauging station records, especially where water resource
or environmental information has been important. If these data are not available,
low flow estimates can be made using flow gaugings and/or hydrological
calculation.
Sediments
Properties of bed material can be determined by taking a bulk sample of sediments
and grading the sediment through a variety of sieves. Some indication can be
made of the sediment load upstream and downstream of the diversion channel
from knowledge of the nature of the catchment.
• local survey of the existing channel and floodplain at the site, defining channel
alignment, size, slope, bed material and floodplain extent
• local survey of any proposed route of the diversion channel
• soil conditions – particular concerns include:
❍ running sand close to the line of the proposed channel
❍ weak material close to any proposed structure on the channel
• permeability of ground and depth of groundwater
• contaminated material, which may need to be removed from the site or capped
prior to the site being suitable for use
• topography of adjacent land
• constraints, such as services, land uses, buildings and infrastructure.
20
OUTLINE DESIGN
21
RIVER DIVERSIONS
• identify all the constraints to be considered in the river diversion design, one of
which is to meet all the requirements of a planning application
• identify mitigation/enhancement opportunities
• produce a sketch design showing key dimensions and levels.
Topographical considerations
A primary requirement of a river diversion is a suitable route where the ground
levels are similar to the existing river in order to avoid the need for excessive
earthworks or culverts.
22
OUTLINE DESIGN
Ground conditions
Ground conditions must be taken into account in planning the layout of the river
diversion. Issues to be considered include unsuitable material for excavation (for
example, rock), and the permeability of the ground and depth of groundwater.
Contaminated land
If contaminated land is encountered for a permanent diversion, it may be more
economic to find an alternative solution. If this were not possible the material
excavated may be subject to Waste Management Licence and Landfill Tax and
may be removed from the site. Alternatively, on-site remediation action may be
taken. It is important in this situation to contact the Waste Management Authority.
Any material exposed may need to be capped and the permanent diversion would
require to be lined to ensure no contamination to the surface water from
23
RIVER DIVERSIONS
Unacceptable Acceptable
3
5
Pr
op
Ne
os
w
ed
roa
r
2
oa
1
d
d
(a) (b)
Unacceptable Acceptable
4
2 (b)
1 3
(c) (d)
(a) Unacceptable realignment to avoid road. Impacts: gradient will be steepened, habitat lost and erosion potential
(b) Acceptable alternative to (a) as the hydraulic gradient is maintained and potential habitat is created:
1. Realigned channel as mirror image of the original
2. Spoil fills part of the channel
3. Section develops as isolated pond
4. 'New' land incorporated with wildlife potential
5. Backwater created from old channel
(c) Unacceptable realignment to improve flood capacity locally. Impacts: gradient steepened, habitat lost and erosion
potential increased
(d) Acceptable alternative to (c) as habitat is maintained and erosion potential is not increased:
1. Straight cut eliminates meander
2. Drop weir or rock armoured riffle with pool, dissipates excess energy and stabilises upstream bed level
and velocities
3. Spoil fills part of old channel or is left as a flood/low-flow channel
4. Old channel developed as backwater refuge
Figure 3. Acceptable and unacceptable options for river diversion (adapted from
RSPB et al., 1994 by kind permission of the RSPB).
24
OUTLINE DESIGN
groundwater. The lining would then be hidden by gravel or soil and stabilised by
vegetation. The solution would depend on the morphology of the channel. For
example, this solution may not be appropriate for a geomorphologically active
channel where severe erosion could occur.
• what is the desired standard to which the channel should be designed? (this is
usually specified as a flood of a specified return period)
• the design flood could be exceeded by a more extreme event and the impact of
higher flows must be considered
• the flow for a flood of specified return period could increase in the future as a
result of climate change, development and other land use changes in the
catchment.
If the diversion is temporary, and only the contractor’s work will be affected by
inadequate provision for flow, then the contractor’s risk assessment should
balance the cost of providing a larger diversion against the risk of inundation of
the works. If other parties are likely to be affected by inadequate provision for
flow then the decision on the standard of design flood is likely to be made by the
river authority.
• requirement for a larger flood capacity, when the channel may be larger
• where the channel is designed for low flows and more frequent flooding is
permitted.
25
RIVER DIVERSIONS
completely straight and over-wide. Over the past 20 years the channel has created
its own berms, which have become vegetated and the channel has begun to
meander within those berms. The existing river downstream of the diversion
channel was also affected by the construction and is trying to return to its more
natural condition as shown in Figure 4. The banks are now vegetated with small
trees and the banks are beginning to erode to a more natural shape. As Figure 4
shows, the return to a more natural state is taking a long time as the river is not
very active morphologically. This is an example where a geomorphological
assessment would have provided important design information on the stability and
rate of change of the channel.
The formula for the outline design of the channel is given in Equation 1 in
Section 4.4.1. This will provide a channel shape of the required cross-sectional
area and hydraulic radius (area/wetted perimeter). The shape can then be modified
to include environmental enhancements, such as variability in channel shape.
The outline design should include details of hydraulic structures associated with
the diversion. These might include:
26
OUTLINE DESIGN
Local population
The impact on the population, housing, services and employment should be
investigated. The impact of the proposed river diversion on the local population
should be cross-referenced with other issues being considered, such as noise,
traffic and land use.
27
RIVER DIVERSIONS
Passage of fish
The scheme should not worsen conditions for fish, including allowing for the
passage of fish where required. The timing of the works should make allowance
for fish migration and spawning. Fish rescues and the transfer of fish from the old
channel to the new channel may be required.
Recreation
Access for fishermen and ramblers may be required, especially if there is an
existing public footpath. Moving a public footpath can be subject to rights of way
procedures and it would be necessary to consult the local authority. Other
recreation facilities, for example, use of the river for canoeing and sailing, may
need to be maintained or created as an enhancement resulting from the scheme.
Navigation
The new channel may be required to permit the passage of boats and canoes. In
such cases a channel of adequate width and depth for the boats in question must be
28
OUTLINE DESIGN
provided. The navigation authority should be consulted and, in the case of main
rivers, this will usually be the Environment Agency.
Archaeology
Archaeological sites that may be affected by the scheme should be identified. The
county archaeologist should be contacted in order to obtain this information.
(a) Access to control structures, particularly during flood events where the
floodplain and local roads may be underwater.
(b) Access to screens, bridges and other locations where debris could accumulate
and cause blockages to flood flows.
(c) The requirements for river maintenance should be agreed with the river
authority before the design is carried out. Maintenance might involve
dredging, cutting of vegetation in the channel and, on the banks, the removal
of rubbish and repairs to structures, bank protection, etc. Provision should be
made in the design to permit access for maintenance using appropriate plant,
which could either be land mounted or floating plant.
29
Part B
Detailed design
RIVER DIVERSIONS
Part B covers the detailed design of the diversion channel. Figure 5 illustrates the
components of the detailed design procedure. The hydraulic and engineering
design, which concerns the layout and physical dimensions of the diversion, must
at the outset consider all other relevant aspects, including geomorphology,
environment, landscape and recreation. It may also be necessary to consider other
related issues, for example, river water quality.
Design flow
Chapter 3
Boundary conditions Plan form Channel shape Sizing the channel Channel size
Section 4.1 and Appendix 1 Section 4.2 Section 4.3 Section 4.4 and shape
Additional
In-channel structures Bank protection Sediment transport Environmental factors design
Chapter 5 Section 4.8 Chapter 6 Section 4.10 aspects
32
Design flowrate
3
3. Design flow rate
The design flow rate for the diversion is normally based on the design flood flow:
(a) Replacing the existing channel: permanent, wet diversion channel. If the
diversion channel is to replace the existing channel then the flow capacity
should be at least the same as the existing channel. However, it is good
practice to design for a particular design flood in order to minimise the
possibility of the diversion channel causing flooding in areas that were not
previously at risk of flooding.
In this situation care must be taken to ensure that increasing the flow
capacity of the channel does not cause morphological or environmental
concerns. For example, an enlarged channel may silt up and revert to its
former natural size unless regularly maintained.
(b) Diversion of flood flows: dry diversion channel. The diversion channel may
be a dry channel, only required to take the flood flows during flood
conditions. In this case the design flow will be the difference between the
total design flow and the capacity of the existing channel.
(c) Diversion of part of flow: wet diversion channel. For a wet diversion channel,
which carries part of the total flow, the channel design will need to
accommodate only part of the overall flow at any time. However, the
diversion arrangements must permit some flow in the diversion channel for
the full range of flows. For normal flows, the flow split will be based on
morphological and environmental considerations.
35
RIVER DIVERSIONS
• use the full FEH statistical procedure, calibrated using local data on flood flows
and water levels, or
• where there are no local data, use the FEH statistical and rainfall-runoff
methods and average the results.
In either case, reference must be made to the FEH, including the associated
software produced by the Centre for Ecology and Hydrology. Alternatively,
estimates can be made using methods presented in standard hydrological
textbooks on hydrology and flow estimation.
Hydrological estimates obtained using any hydrological procedure, including
the FEH, are subject to a considerable degree of uncertainty. Where possible the
estimates should be ‘calibrated’ using observed river flow and water level data.
The FEH procedures specifically apply to the UK. In other countries alternative
methods must be used. For example, the US Soil Conservation Service method is
widely used (US SCS, 1972).
36
DESIGN FLOW R ATE
this case, an adjustment may be needed to take account of the difference between
the catchment areas at the gauging station and the site.
The accuracy of recorded flows at many gauging stations during floods is
variable because of uncertainties, such as flows bypassing the gauging site or lack
of check calibration flow gaugings at high flows. If the estimated median annual
flood obtained from local data is significantly less than the FEH prediction, the
cause should be investigated and, if in doubt, the FEH figure should be used.
• where a risk assessment indicates that a lower flood return period could be
accepted as the diversion will only be in place for a very short period compared
with the design life of a permanent diversion, and no other sites or properties
are at risk
• where additional capacity, for example, flow through the work site, could be
quickly provided with no great additional expense and danger.
37
RIVER DIVERSIONS
38
Detailed channeldesign
4
4. Detailed channel design
The normal depth method may be used where the river downstream is
reasonably uniform in shape and slope for a distance of 07 D/s m, where D is the
channel depth and s is the water surface slope. This distance is referred to as the
‘backwater length’.
The backwater method should be used except where good observations of flood
flows and corresponding water levels are available.
Where available, observations of flood events may be used to construct a rating
curve (plot of water level against flow) and estimate the water level for the design
flood flow. Observed water level data should be used with caution because of
possible inaccuracies or failure to record the level at the flood peak.
41
RIVER DIVERSIONS
4.1.4. Observations
At some sites, where recent floods have occurred, information may be available
that relates the flow rate to the depth of water in the channel. If this technique is to
be used then the designers must be aware of two issues:
A rating curve (plot of water level against flow) should be constructed using the
observed data and should be used to estimate the water level for the design flood
flow.
42
DE TAILED CHANNEL DESIGN
The general shape of the channel should be determined before the detailed
sizing of each cross section of the channel is carried out.
43
RIVER DIVERSIONS
The slope, s, is initially taken as the bed slope of the existing channel and the
initial estimate of roughness can be determined as described in Section 4.6 below.
A fuller description of the application of the Manning equation is given in
Appendix 1 (Section A1.1).
A river channel normally consists of the following:
• a main channel, with a maximum flow similar in magnitude to the mean annual
flood
• an area on either bank for flood flows which, combined with the main channel,
is able to carry the design flood flow
• in some cases there is a low flow channel within the main channel.
• different gradient
• different size or shape.
44
DE TAILED CHANNEL DESIGN
Decisions can then be made about any design changes or mitigation measures
that may be required to negate or reduce the impacts of the changes.
If the diversion channel is to take part of the total flow and is to be wet under
normal conditions, the split of flow under a range of conditions needs to be
determined and the size of channel designed to carry this range of flow.
The design flow for the main channel is usually close to bankfull flow. Once
the bankfull area of the channel is decided, consideration can be given to the
extremes of the flow range and to the channel shape in order to accommodate the
design and other flows. The low flow channel should be designed to provide
sufficient depth and velocities for water quality and environmental reasons.
Section 4.9 describes the requirements for water quality in more detail. Section
3.4 outlines methods for determining low flow conditions within channels to meet
ecological requirements.
The final hydraulic design of the channel should be undertaken using the
backwater method outlined in Appendix 1. The backwater method can be used for
the final design, as the channel is unlikely to be uniform and there may be little
observed flood data available. This method takes account of the water level for the
design flow at the downstream end of the diversion and the fact that the water
surface is not parallel to the bed. The final design should also include the impact
of structures, including control structures, bridges and culverts (see Chapter 5).
Computational hydraulic models are normally used to undertake backwater
calculations. Models of the existing river and diversion channels can be used to
determine the detailed design and size of the channel. Where flood storage is
significant, the models can be run in unsteady flow. In this case a flow hydrograph
is used as input data at the upstream end of the diversion and a rating curve
(relationship between water level and flow) is used at the downstream end.
The initial design of the channel can be entered into the model and tested for
the design flows. Modelling of the river diversion design has the following
advantages over manual methods of design:
• complex channel shapes can be used without the need to calculate section
properties by hand
• the design can be tested easily for a range of flow conditions
• dimensions can be changed easily to optimise the design
• the design can be tested under unsteady flow conditions, which takes account of
storage on the floodplain
• the shape and roughness of the channel can be changed easily to take account of
environmental features, such as vegetation.
45
RIVER DIVERSIONS
46
DE TAILED CHANNEL DESIGN
Maximum
velocity
Edge of
riffle or
shoal
Pool
Riffle
Pool
Riffle
(a)
Pool Pool
Riffle
Fine sediment
(gravel)
and some gravel
(b)
Figure 6. Water flow and structural components of pool riffle sequences: (a) plan
view; and (b) long profile (adapted from Horne and Goldman, 1994)
determining the overall capacity and size of the river channel. A major design
criteria for diversion is the ability of the channel to convey flood flows.
Determination of the flood conveyance of a channel is dependent upon values of
the roughness coefficient at bankfull flow. The values of roughness coefficients
under low flow conditions are generally higher than for flood flows. Therefore,
different values must be used for the design of the low flow channel. Roughness
coefficients are liable to vary seasonally depending on the type of vegetation
present in the channel and the maintenance carried out. If the amount of
vegetation in the channel varies significantly seasonally then different roughness
coefficients must be used for each season.
The roughness coefficient for a river channel may be determined using any
of the approaches detailed in Fisher (2000) with modification to take account
of bend losses if meanders or bends occur in the study reach. These methods
are all qualitative or semi-qualitative and involve the use of comparison of the
intended design channel with pictures or selecting the roughness values from a
list depending on the channel characteristics. As an initial estimate, the latter
of these two approaches is recommended and the list is reproduced in
Appendix 2.
If other environmental features, such as vegetation, are incorporated into the
channel design, this may alter the initial roughness estimate. Care must be taken
when evaluating channel roughness for vegetated channels as the n value is likely
47
RIVER DIVERSIONS
to vary seasonally. Fisher (2000) provides detailed methods for determining the
roughness of a channel with a range of environmental features.
Large-scale roughness elements, such as boulders, are sometimes used for the
creation of rock pools in steep streams in order to improve the spawning and
nursery areas for fish. The size of boulders is often similar to, or greater than, the
depth of flow in the channel under normal flow conditions. Standard equations for
small-scale roughness do not apply to large-scale roughness where, locally, the
flow is non-uniform with zones of separation, acceleration and deceleration
around the roughness elements. Fisher (2000) provides details of the methods of
analysis for these large-scale roughness elements.
48
DE TAILED CHANNEL DESIGN
Pool
5 to 7 channel widths
sequences within the existing river, the spacing of these features and the type and
size of gravels on the riffles should be transferred to the diversion channel, as far
as is reasonable. In diversion channels they may be constructed or encouraged by
the use of current deflectors or groynes. The location of the pools and riffles
should match the existing channel.
A feature of riffles is that water flows through, as well as over, the gravel,
allowing fish eggs and small benthic invertebrates to obtain oxygen and protection
from predators.
49
RIVER DIVERSIONS
Flow
(a) (b)
(c) (d)
(e) (f)
50
DE TAILED CHANNEL DESIGN
51
RIVER DIVERSIONS
over the substrate, provide food for larvae. The hard, stable substrate becomes
colonised by mosses, lichen and algae, which provide food and shelter for stream
invertebrates. These, in turn, provide food for fish and river birds.
Stone weirs have been used to enhance the fisheries and landscape value or the
water power potential of small rivers over many centuries. It may be preferable to
repair historic structures than to construct new structures.
4.7.4. Vegetation
There is lateral variation in the dominant plant type across natural channels due to
variations in depth, velocity and substrate. The type of vegetation present will
have an effect on the hydraulic performance of the channel. The designer should
be aware of the following;
(a) In mid-channel, broad and floating leafed plants will dominate if velocity is
low, and may significantly retard flow. This means more silt is trapped,
which smothers invertebrates.
(b) The edge of the channel is the most diverse area for plants if the bed is stable
and will be populated by stiffer species, such as reeds. In these edge zones,
silt is trapped, creating low berms, which are good habitats for invertebrates.
Their formation may be encouraged by the use of groynes.
(c) A proportion of both banks and flood berms should be vegetated in order to
provide shade, bank protection, and habitat for mammals and birds. This may
be achieved by constructing multi-stage channels, which permit hydraulic
connectivity between the channel and floodplain to be retained, and increase
floodplain storage.
(d) The intermediate vegetation established through natural succession is most
beneficial for flora and fauna. Therefore, it is important to specify a
maintenance programme. Selective pruning is a simple way to control
vegetation. It is possible to estimate the hydraulic impact of vegetation,
which depends on the amount of cover and type (Fisher, 2000).
(e) Wetlands may be established on the edge of the channel, and are rich sources
of nutrients and shelter for invertebrates and fish.
(f) The presence of trees helps provide shelter for fish and invertebrates.
(g) Topsoil should not normally be imported to the site. Local topsoil should be
reused as far as possible.
The riparian corridor bordering the channel should also be considered when
designing a new watercourse or when diverting an existing one. Mammals, such
as otters, voles, shrews and bats, all inhabit the riparian zone and require a variety
of bankside cover, including wetlands, in order to thrive. Riparian vegetation at
the edge of the channel is very important in increasing fish stocks and providing
cover, bank stability, and a source of food and shading. The ecological succession
that occurs after the creation of a diversion channel, from bare bank to fully
forested, is most beneficial for fisheries. Figure 11 shows a typical lateral
variation in vegetation across a channel.
52
DE TAILED CHANNEL DESIGN
Bankful WL
LWL
Bank top Bank side Channel edge Mid-channel Channel edge Bank top
Figure 11. Lateral variation in vegetation across the channel (Fisher, 2000)
53
RIVER DIVERSIONS
Before After
Bank excavated
and channel dredged
(a)
Partial dredging
(b)
Margin widened
No bankside
to create edge
margin
habitat
(c)
Figure 12. Enhancing (option a), retaining (option b) and creating (option c) edge
habitats (adapted from Brandon, RSPB et al., 1994 by kind permission of the RSPB)
54
DE TAILED CHANNEL DESIGN
Floodplain
Pool and
riffle
Eroding
cliff
High
ground
Incised
'by-pass'
Wooded
channel
'island' at
mid-channel
height
Willow
revetment
Consolidated
overspill
Alder
High ground
Bifurcated
channels
Figure 13. Edge habitats that can be created during river diversion (RSPB et al.,
1994 by kind permission of the RSPB)
55
RIVER DIVERSIONS
Figure 14. Grass-planted gabions with fibre rolls at the foot of the wall
used to deflect fast flows from banks (see Section 4.7.2). Figures 14–17 show
some types of bank protection that utilise both structures and vegetation. The
Environment Agency R&D publication Waterway bank protection: a guide to
erosion assessment and management (1999b) is a useful tool and a design guide
for channel revetments is also available (Escarameia, 1998).
56
DE TAILED CHANNEL DESIGN
Young plants
Eroded bank
Stakes
Fibre roll
Figure 16. Use of fibre rolls for bank protection (RRC, 1993)
0·1 – 0·3 m
Reed clumps
planted in
gabion basket
Willow stakes
Stone
Figure 17. Bank protection combining vegetation with stones in a gabion basket –
depending on the bed material, the channel is vulnerable to undercutting at the toe of
the gabion basket (adapted from Hemphill and Bramley, RSPB et al., 1994 by kind
permission of the RSPB)
57
RIVER DIVERSIONS
• if the diversion will have inflows from a sewage treatment works, the dissolved
oxygen content may be affected
• where the diversion route contains contaminated soils there is potential for the
watercourse to be polluted
• when the diversion channel has a ‘sweetening flow’ (a low flow intended to
maintain a minimum flow in the channel at all times), the impact of any
alterations to water quality is amplified.
Sulphur
Atmospheric pollution is increasing the amount of sulphur in rivers and streams.
At times of low flow, when sediments are oxidised, hydrogen sulphide may be
released, which can kill fish and which has an unpleasant odour. Leaving dead
vegetation to rot in the channel also has this effect and it is therefore
recommended that this is removed after cutting.
Chlorine
Chlorine is vital for photosynthesis to occur but in its free form (chloramines) it is
highly toxic. Usually sunlight converts chlorine into harmless chloride ions but in
58
DE TAILED CHANNEL DESIGN
areas where sewage pollution is high there may be enough chloramines present to
damage fish. It is important to maintain a minimum flow during diversion work in
order to ensure enough dilution occurs.
Chelating agents
Chelating agents change toxic metals into a more stable form. The main source of
these agents is humic acid and citrate, which are both produced during leaf death. The
presence of overhanging vegetation is desirable in order to maintain a supply of leaves.
Sediments
Transported sediments can cause turbidity that impairs the respiration of fish,
buries plants and covers spawning gravel. Turbidity increases with velocity and
affects the amount of light reaching the river bed. Sediments act as a site for ion
exchange between the aqueous and solid phases of inorganics. Consequently,
when concentrations of inorganics are high, sediments absorb them, and when
they are low they release them. This dynamic equilibrium or ‘buffering’ may be
upset if sedimentation rates change or loading increases. During construction, care
should be taken to reduce dust disturbance, particularly when moving and
transporting material. Dust also contributes to nitrogen and phosphorous loading.
Straw bales can be used to intercept runoff from the site into the watercourse.
The major water quality parameters that can be affected by river diversion works
are oxygen and the amount of nutrients (nitrates and phosphates).
4.9.2. Oxygen
The dissolved oxygen (DO) content of water determines the type of aquatic
invertebrates that can survive in the channel. Oxygen levels can be affected by
changes in velocity and depth, and uptake by vegetation and organic matter, such
as sewage. At less than 10% saturation of oxygen, fish will not be able to survive
and a low DO content also reduces the potential for fish eggs to survive to maturity.
The DO content may be affected in the following ways:
• diverting flow may cause a decrease in velocity, which, in turn, reduces that
rate of re-oxygenation
• diverting flow may also reduce the dilution of organic pollutants that demand
oxygen
• organic pollution from sewage or slurry runoff uses oxygen as it decomposes
and this produces a DO sag curve downstream of the point of introduction of
the effluent – a minimum critical value of DO will be reached some distance
away from the source and designers should ensure that features are added that
keep this critical value above the level required by invertebrates and fish
• high levels of nutrients result in high levels of photosynthesis, which can cause
over-saturation at certain times of day
• creating a channel with meanders slows flow, reduces slope and turbulence and,
hence, re-oxygenation.
59
RIVER DIVERSIONS
To ensure DO content remains high, weirs, riffles and vegetation can all be
used to re-oxygenate water. However, there is little that can be done by the
designer of a diversion to reduce the effect of sewage inflows and agricultural
diffuse pollution.
4.9.3. Nitrates
Nitrates move easily through soils and are a major source of nutrients in streams
and rivers. The main source of nitrates is runoff from agricultural land and sewage.
Anoxic sediments provide a sink through the process of nitrogen fixing, creating a
nitrate equilibrium in the river. Dredging or draining during construction work may
upset this equilibrium, allowing the release of nitrogen back into the water.
The amount of nutrients in the channel has an impact on the biomass present, in
particular, conditions for algae growth. Agricultural use of nitrate-based fertilisers
means that in low flows the concentration of nitrates in water may be high,
allowing algae blooms to form. Algae can be toxic, use a lot of DO and are
unsightly. In large quantities, nutrients, such as nitrates, phosphates and organic
matter, can cause over-production, known as eutrophication. This ‘nutrient
enrichment’ is a very serious environmental problem in the UK and even small
amounts of eutrophication can cause a loss of species diversity.
4.9.4. Phosphates
The lack of phosphates often limits the growth of organisms. Sediments act as a
buffer system for phosphorous. Increases in sedimentation may upset the
equilibrium, making phosphorous scarce. As phosphorous is essential for all
living organisms, excess sedimentation should be avoided. Wetlands are useful in
keeping phosphorous levels up, as phosphates are released 1000 times faster in
anoxic sediments than in those that are oxygenated.
60
DE TAILED CHANNEL DESIGN
the river. Plant, animal, fish stock and invertebrate surveys should ideally be
carried out in addition to the RCS.
In considering the design of a diversion channel, it should be remembered that
the natural habitat in a watercourse at one location is not always the same as that
in another watercourse at another location. For example, in the UK, species
diversity decreases as you travel north and there is an absence of pools and riffles
in the steep streams of Scotland.
4.10.1. Fisheries
Fish are sensitive to velocity, depth, substrate, temperature and water quality.
From a fisheries point of view, stream habitat is seen as the space where fish
develop, including refuge and cover areas, spawning and egg hatching zones and
food supply areas. In designing a diversion channel there are five environs that
should be considered:
• spawning habitat, comprising well graded sediments that allow water to pass
through and oxygenate eggs
• food-producing areas that have a high macroinvertebrate diversity and mass –
riffles are the main food supply areas of this kind
• refuge areas that protect fish from strong currents and predation – vegetation,
boulders and pools provide sanctuary for fish, hence the importance of
backwaters and vegetation
• a requirement of fisheries is a varying flow regime, the magnitude of which
vary with age, species composition and season – of particular importance are
the minimum flow and flushing flows, the absence of which can lead to anoxic
and silted conditions
• water quality, including temperature, pollutants and DO content – poor water
quality produces an unbalanced population and low DO has a negative impact
on fry, trout and salmon.
In order to maintain or improve conditions for fish in diversion channels, the
following should be considered:
Possible design features include pools and riffles, current deflectors, low weirs,
river margins and the placement of boulders in the channel.
61
RIVER DIVERSIONS
Destruction of vegetation Loss of existing habitat for birds and terrestrial mammals
Groundwater level rises as uptake by vegetation decreases
Increase sediment downstream of the diversion site
Invasion of non-native species
Decrease in photosynthesis and oxygen levels
Dredging Loss of large numbers of invertebrates
Loss of instream vegetation
Loss of pools and riffles Loss of refuge for invertebrates
Decrease in diversity
Loss of oxygenation
Decrease in velocity Increased siltation
Invertebrates smothered
More vegetation, increased risk of flooding
Decrease in depth Loss of edge habitat
Damage to floating and submerged vegetation
More instream vegetation, blocking flow
Earthworks adjacent Risk to established vegetation
Risk of disease spreading
Risk of weed spreading, e.g. Japanese knotweed
62
DE TAILED CHANNEL DESIGN
Light
Large allochthonous
Bacteria particulate organics
Allochthonous
dissolved organics
and inorganics
Micro-meso macrophyte
Fungi, primary autochthonous
protozoans producers
Detritus
Dissolved organics
and tiny particulate Scrapers
organics grazers
Shredders
Predators Filterers
collectors Predators
4.10.4. Wetlands
The creation of wetlands by river diversions should be encouraged where
possible, as they support a profusion of wildlife. In addition, they provide flood
storage, groundwater recharge and the ability to convert inorganic nutrients into
less harmful organic substances. Wetlands are the transitional zones between
terrestrial and aquatic habitats, and, therefore, can play an important role in
preventing pollutants leaching into rivers and streams. Wetlands are very effective
in removing nitrates by the process of de-nitrification. Wetlands can be provided
on the berms of two-stage channels. These are the areas adjacent to the normal
river channel that provide additional capacity for flood flows.
63
RIVER DIVERSIONS
64
In-channel structures
5
5. In-channel structures
Structures may be required on diversion channels in order to control the flow and/
or water level, and to provide crossing points. In addition, where part of the flow
is diverted, a control structure may also be required on the existing river channel
downstream of the offtake to the diversion channel.
Structure types that may be required in the design of a river diversion are listed
in Table 5.
* For example, where the diversion channel is shorter than the existing channel, a control structure is
normally required so that the slope in the diversion channel is the same as the existing channel.
67
RIVER DIVERSIONS
68
IN- CHANNEL STRUC TURES
H
Y1
1:5
1:2 W
Q = 0·633 b g H 3/2 Q = C bw 2g Y1
(a) (free outflow)
(b)
Q = 0·46 b g H 3/2
Discharge depends on length, slope, inlet
(c) geometry and tailwater conditions
First approximation-control
treated as an orifice with Q = K H
L
(K obtained from known maximum values
of Q and H )
H
(d)
B b
Q = 0·544 b g H 3/2
(e)
Weirs may be either sharp crested or broad crested. Broad-crested weirs are by
far the most common type, as sharp-crested weirs are normally only suitable for
use on small channels.
There are several different types of weir, each of which have different
characteristics. One advantage of the use of weirs is that the crest can have a
variety of levels, allowing low flows to spill over through a notch and flood flows
to pass over a wider crest, minimising the rise in water levels upstream. Another
advantage of weirs is that floating debris can pass downstream without causing an
obstruction.
69
RIVER DIVERSIONS
Weirs may be constructed using concrete with or without a stone facing. Stone
weirs have environmental benefits, as discussed in Section 4.7.3. Stone weirs
might also be more acceptable from an aesthetic point of view but there is greater
uncertainty in the hydraulic performance.
The weirs outlined in this Section are normally designed to be perpendicular to
the flow. However, weirs that cross the river at an angle or are V-shaped in plan
may be more visually attractive, although there is greater uncertainty in the
hydraulic analysis.
A side weir is a structure commonly used to divert flows, for example, at mill
sites. The hydraulic analysis of side weirs is more difficult than standard weirs
because the water level above the crest can vary significantly along the crest and
the approach flow is not perpendicular to the crest. Side weirs are, however, a
common type of inlet structure for ‘dry’ flood diversion channels, where water
passes over the side weir when the water level (and, therefore, flow) in the main
river reaches a certain critical point. In such cases, the weir can sometimes consist
of a length of embankment where the crest level is set lower than the adjoining
bank and the landward face is reinforced to protect against erosion.
Broad-crested weirs
A broad-crested weir is generally considered to be one in which the thickness of
the diaphragm wall exceeds 60% of the thickness of the nappe (overfalling stream
of water). They have the distinct advantage of being more robust than plate weirs,
being usually constructed of concrete. They have little trouble in passing floating
debris, as they often extend across the entire width of the channel. They are also
the only option for weirs of large size and capacity.
The disadvantage of broad-crested weirs is that their hydraulic characteristic is
significantly influenced by the viscous boundary layer formed on the top of the
weir. This flow is very sensitive to changes in the roughness of this surface as well
as to small local changes in the geometry of its upstream edge. A common type of
broad-crested weir used for flow measurement is the Crump weir.
The theoretical equation for the broad-crested weir is:
70
IN- CHANNEL STRUC TURES
71
RIVER DIVERSIONS
The exact value of the coefficient will vary depending on such factors as
friction losses, bed level and approach conditions. It is often more convenient to
allow for the effect of approach velocity as a velocity correction coefficient (Cv).
In this case, the generic equation for the broad-crested weir is:
p
Q Cd Cv g Lh3=2
4
Values of Cd for a wide variety of shapes of cross section are given in Ackers
et al. (1978).
The above formulae apply to modular flow conditions, where the water passing
over the crest is not affected by the water level on the downstream side of the
weir. If, however, the downstream water level becomes too high then it will begin
to affect the hydraulic characteristic of the weir, which is then said to be drowned.
The modular limit is normally assumed to have been reached when the height
of the downstream free surface above the weir crest reaches a specified proportion
of the height of the upstream free surface above the weir crest (75% for the Crump
weir). However, it is still possible to calculate the upstream water level if both the
discharge and downstream water level are known, and the hydraulic
characteristics for the partially drowned condition are available. These are
typically presented as a family of characteristic curves with non-dimensional
tailwater elevation as the parametric variable.
The Crump weir is designed to provide a reliable water level to flow
relationship in both modular and drowned flow conditions. It has two formulae,
one for modular operation and the other to provide a modified discharge Qs when
the weir is operating in the drowned condition. They are:
p
Q Cd Cv L g h3=2
5a
where Cd 0.633
h is the upstream head over the crest
hp is the downstream head over the crest.
72
IN- CHANNEL STRUC TURES
The standard form of weir equation given in Section 5.1.2 (Equation 2) applies
to moveable weirs.
5.1.4. Flumes
There are a variety of circumstances in which it is not acceptable to raise the bed
of the channel, for example, when the available upstream head is restricted. In
such cases, a flume might offer a suitable alternative. The flume also works by
restricting the passage of the flow but, in this case, the restriction is created by
reducing the channel width. The flow is forced to accelerate to get through the
narrow section or throat of the flume and is then returned to the channel via a
diverging transition. A streamlined hump may be incorporated in the throat of the
flume to further reduce the size of the flow passage.
Since the flow velocity through the flume is higher than in the parent channel, it
is less likely to suffer from an accumulation of sediment upstream than a weir.
Flumes are generally used on relatively small channels but flumes have been
installed on the River Tame in Birmingham in order to control the level flow
relationship at the offtake for flood storage areas. Like weirs, certain types of
standard flume can be used for flow measurement. These include the Venturi
flume and the Parshall flume.
The Venturi flume has the same general theoretical equation as a broad-crested
weir:
3=2
p U02
Q 0544b2 g h
6
2g
73
RIVER DIVERSIONS
0·6
Free discharge
0·5
0·4
0·3
C
0·2
Experimental
Energy equation between
0·1 sections 1–2,
momentum equation
y3/w = 2 between sections 2–3
3 4 5 6 7 8
0
0 2 4 6 8 10 12 14 16
y1/w
Figure 22. Value of C for vertical sluice gates (adapted from Henry, 1950)
74
IN- CHANNEL STRUC TURES
p
Q Cd ao 2gh
8
Orifices and short pipes are susceptible to blockage by debris. This can be
mitigated by the use of screens or small sumps upstream, although care is needed
in the design of screens to ensure that they do not block.
The determination of flow through a culvert is complicated as it is controlled by
many variables. For a more detailed analysis, refer to the Culvert Design Guide
(CIRIA, 1997b).
Priming level
Normal range h
of waterlevel
Breakflow level
75
RIVER DIVERSIONS
diversion. A temporary dam was used at the downstream end of works on the
River Colne at Wraysbury Mill (see Section A4.8 in Appendix 4).
5.2.1. Bridges
Bridges across small river diversions may consist of single span structures that
have no effect on the hydraulics of the diversion channel. Piers and possibly
approach embankments may be required and these will affect the flow. The
impact can be calculated using the method given by the US Bureau of Public
Roads (USBPR, 1978). The basic method is reproduced in the Highways Agency
Advice Note The effect of highway construction on flood plains (Highways
Agency, 1995).
5.2.2. Culverts
A culvert is a covered channel or pipeline, which is used to continue the diversion
channel under the crossing (or other obstruction). The structure may consist of one
or more barrels, constructed using pipes, concrete box sections or corrugated
metal arches. A culvert consists of an inlet structure, the barrel and an outlet
structure. Particular factors to consider in the design of culverts include:
• whether the culvert flows with a free surface or is surcharged at high flows –
the larger the culvert, the smaller the head-loss and risk of blockage
• the possibility of blockage of the culvert by debris – trash screens can be
provided to reduce this risk but they require careful design to avoid causing a
blockage in the channel.
76
IN- CHANNEL STRUC TURES
These and other design aspects, together with hydraulic design formulae, are
contained in the CIRIA Report 168 (1997b).
Flo
w
Figure 24. Schematic of a Larinier fish pass with plain baffles (Armstrong, 1994)
77
RIVER DIVERSIONS
for the passage of fish. At Brokenhurst (see Section A4.5) weir boards were
placed in the diversion channel to create pools upstream and turbulence
downstream, encouraging fish to migrate upstream. A good all round international
reference is Clay (1995).
• the transition and entrance to the structure from the river channel
• the structure
• the downstream stilling basin and sediment control works
• additional features, such as screens and fish passes.
The structure must be designed to pass the design flows with certain specified
upstream water levels. One possible design criterion is that the upstream level for
Flow
Guide wall
Lock wall
Upstream
approach
Downstream Lock gate channel
approach Lock chamber
channel
Lock wall
78
IN- CHANNEL STRUC TURES
the design flood must not be increased by the river diversion works. In addition to
the upstream design levels, the downstream levels are required. These will be
obtained from the design of the diversion channel using the methods outlined in
Section 4.4.
The structure type should be selected based on the discussion in this chapter.
The structure could consist of a single type of structure or a combination of
structure elements (for example, a fixed weir for normal flows together with a
gated structure for high flows).
Having obtained upstream and downstream water levels for the design flows,
the hydraulic design can then be carried out. This will provide the basic
dimensions and levels of the structure that would then be used in the engineering
design.
Surface current
Bottom current
Figure 26. Typical current path in a flow bend, showing variation in surface and
bottom current variation (adapted from Razvan, 1989)
79
RIVER DIVERSIONS
Figure 27. Attraction of near bed flows to a 90º intake, arrows indicating direction
of flow (adapted from Avery, 1989)
If the flow is diverted through a large angle, the flow patterns will be disturbed
and bed load will be attracted towards the intake, as indicated on Figure 27.
80
IN- CHANNEL STRUC TURES
Main flow
Bottom flow
separation line
Diverted flow
81
Sedimenttransport
6
6. Sediment transport
6.1. INTRODUCTION
The size and plan form of rivers is not random but depends upon the nature of the
flow, sediment and topography. Though our understanding of the physics is far
from perfect, there is a belief that, under particular conditions, there is a stable
river form. If a river reach does not conform to these stable conditions then it is
likely that morphological change will take place, which may lead to expensive
maintenance or remedial work.
The design of diversion works should consider the following issues:
(a) Sediment transport rate. A river diversion, by its nature, will only alter part
of the length of a river. As only a reach of river is affected, then the sediment
transport rate upstream and downstream will remain unaffected. If the design
does not ensure that the sediment transport rate in the diverted reach matches
that upstream and downstream, then either erosion or deposition is likely to
occur. Methods to calculate sediment transport are discussed in Sections 6.2–
6.6.
(b) Alluvial resistance. The design should take account of the hydraulic
roughness that is likely to develop in the diverted reach, see Section 6.7.
(c) Channel size and shape. For a given discharge, sediment load and sediment
size, there is a stable channel size and shape, often referred to as a regime
channel. If another size or shape is adopted, then it is likely that erosion or
deposition will take place in order to make the channel correspond more
closely to regime conditions. A discussion of the application of regime
theory to rivers is given in Section 6.8.
(d) Plan form. The design should take account of the natural plan form of the
river. Attempts to straighten a river are often difficult and, in the long term
fruitless, unless a large amount of effort is expended on river training or
maintenance.
(e) Bank stability. Diversion works that lead to increases in bank height may
lead to bank failure. This may introduce extra sediment into the fluvial
system and may result in further problems, either upstream or downstream.
It should be recognised that most natural rivers will change their plan form over
time, though the speed of such change may vary significantly from river to river.
85
RIVER DIVERSIONS
Thus, it is natural in rivers for some erosion and deposition to take place. A river
that does not change over time should be regarded as being unnatural in some
way. Thus, the diverted reach should change and develop, ideally, in the same
way as a natural reach of the river.
Usually, the relationship between the grain Reynolds number and the mobility
number is plotted as the familiar Shields’ curve. The Shields’ curve is not suitable
for use in design calculations as both the X and Y contain two independent
variables. To determine the depth of flow at which a particular particle size will
commence movement, the Shields’ curve can be re-plotted as shown in Figure 29
with the two dimensionless ratios:
s
gd 3 So3 gD3
s ÿ 1
XY and X 2 =Y
11
s ÿ 1v v2
86
10 000
1000
grains
Bed undulations gradually
become shorter and deeper
XY =
10 Flat irregularities
in bed
SEDIMENT TR ANSPORT
1 Short shoals
Ripples
0·1
102 103 104 105 106 107 108 109 1010 1011
X2 gD 3 (s –1)
=
Y ν2
87
Example
For a channel with the following properties:
So = 110-3
s = 265
D = 0009 m
v = 1151106 (kinematic viscosity of water at 15º)
From Figure 29 the value of XY is then read off the plot. In this case XY = 40.
The depth of flow at which motion will occur can then be calculated:
s
981 d 3
1 10ÿ3 3
XY 40 ) d 083 m.
265 ÿ 1 1151 10ÿ6
• bed load
• suspended load
88
SEDIMENT TR ANSPORT
• wash load
• total load.
89
RIVER DIVERSIONS
designed to carry certain water and sediment rates. Thus, the movement of water
and sediment are inter-related and cannot be separated.
Sediment transport equations can be of use to the engineer in a variety of
problems. In the design of rivers or diversion channels, the capacity of the channel
to carry both water and sediment must be calculated. If the amount of sediment
entering the channel is greater than the capacity of the channel to transport that
sediment, the sediment will be deposited. If the reverse is true, the channel may
erode.
• field measurements
• laboratory testing of sediment
• modelling of hydrodynamics and sediment transport.
90
SEDIMENT TR ANSPORT
91
RIVER DIVERSIONS
92
Part C
Construction
RIVER DIVERSIONS
• construction issues
• health and safety on site.
94
Constructionissues
7
7. Construction issues
7.1. INTRODUCTION
This chapter deals with some of the issues that may arise during the construction
of a river diversion. Even though the issues are primarily related to construction,
the designer must be aware of them and take due consideration of them during the
design process. Most of these issues refer to both temporary and permanent
diversions, although the examples usually refer to one or the other.
• carry out work during low flow periods to minimise silt disturbance
• put temporary silt traps downstream
• phase work to allow recolonisation and provide refuge for fauna
• dredge in an upstream direction to allow flora and fauna to float downstream
and recolonise
• avoid sensitive sites, for example Sites of Special Scientific Interest (SSSIs)
• transplant vegetation as work progresses
• use natural succession to revegetate the area wherever possible
• use natural gravels exposed by the work
• avoid removing mature trees
• once constructed, allow the new channel to stand with water in it – this will
give time for planted vegetation to become established before water flows
through the diversion and this will, in turn, provide protection for new
earthworks.
97
RIVER DIVERSIONS
98
CONSTRUC TION ISSUES
structure may be left high to form a temporary cofferdam and then trimmed off to
the required level when the cofferdam is no longer required.
During wet periods where the groundwater levels are high, or in areas with
more permeable soil conditions, dewatering using pumps may be required. Sheet
piling is normally used to form the cofferdams. Silent piling techniques, for
example vibrated sheeting, may be required especially in urban areas.
Temporary works may be designed by the scheme designer to support the
permanent diversion. The buildability of these works must be considered under
the CDM Regulations. For example, if earth embankments are used between the
diversion channel and the existing channel to prevent overtopping from one
channel to another there may be space limitations.
99
RIVER DIVERSIONS
7.6. GROUNDWATER
The effect of a river diversion on groundwater flow depends very much on local
conditions such as soil type, vegetation cover and the position of the ground-
water table. Possible impacts of a river diversion on groundwater include the
following:
• in permeable areas, leachate from spoil may reach the groundwater – placing
spoil on impermeable membranes can reduce this potential problem
• if sheet piles are placed to stop the flow, water may seep around the piles and
re-enter the excavation
• artificial channels intercept groundwater and can lower or stabilise levels
• trenches backfilled with a more permeable material will act as conduits and can
be used to channel groundwater towards wetland areas
• when channels are dredged, surface water and groundwater are mixed – this
may cause the precipitation of calcium carbonate, which must be broken up
before water is introduced into the channel
• the lowering of the water table may be beneficial in some areas as it may reduce
waterlogging – however, this may have adverse environmental impacts.
Where there is a danger that the groundwater will affect the stability of
excavations, boreholes should be used to monitor and observe changes in
groundwater levels.
A particular issue is the interaction between contaminated groundwater and the
river diversion. Boreholes and permeability tests are required to determine
existing conditions. In most conditions continuity between groundwater and the
surface water of the diversion channel is acceptable. However, where the
groundwater and/or ground conditions through which a river diversion is proposed
are contaminated, an exclusion system should be used to break the continuity
between the river and the contaminated material. This may be achieved using a
skin lining, for example, bentonite. Liner technology is well established and an
example of the use of liners on the River Ash is given in Section A4.1. A
monitoring system may be required and structural engineering solutions are
available although they can be costly. Care must be taken to avoid uplift where the
groundwater level exceeds the water level in the channel.
10 0
CONSTRUC TION ISSUES
Figure 30. Offline settling lagoons for contaminated groundwater on the River Ash
Offline settling tanks should be used to settle out sediments stirred up during
the construction process. These can be relatively crude arrangements. For
example, water and suspended sediments can be pumped into a skip that has an
offtake pipe in the top part to take off clean water back into the river, leaving the
sediment to settle in the skip. The skip will need to be cleaned of sediments from
time to time. Other settling tank arrangements that can be used include a series of
parallel pipes designed to settle the sediment and return clean water to the river.
An alternative arrangement is to dig a settling basin at the downstream end of the
diversion channel in order to catch suspended sediments. Offline storage may also
be used to store contaminated water on site. Figure 30 shows the offline lagoons
used on the River Ash to store contaminated groundwater from the excavation and
to pump this to the foul water sewer over 800 m away.
7.8. PUMPING
Pumping is often required in river diversions to dewater areas that need to be dry
during works. This often involves continual pumping from a cofferdam in order to
ensure dry conditions for construction. Pumping, therefore, can be a costly part of
the construction process. In areas where electricity supplies are not available,
generators can be used but the costs are reduced if an existing electricity source is
available. There should be a backup power supply system for pumps run from
electricity in case of failure in the power supply.
There can be problems with spillage and contamination from a diesel pump and
pumps should always be mounted on a tray to catch diesel spilt during filling and
leaks or drips during running. The trays should be drained regularly to ensure no
spillage into the river or surrounding ground where groundwater could become
contaminated.
101
RIVER DIVERSIONS
Noise from pumps may be a problem, especially as pumps are often running
continuously. Security of the pumps should also be considered, as it has been
known for the general public to turn pumps off in the night due to the noise.
Methods are available for assessing construction risks in river and estuary
engineering (DETR, 1999).
102
CONSTRUC TION ISSUES
103
RIVER DIVERSIONS
7.12. ACCESS
Footpaths for the general public and access for anglers may need to be provided
and maintained during the works as it is often difficult to close footpaths. Access
may be restricted to one side of the river. Sometimes the access needs to be from
the same side of the river as the diversion channel and, therefore, a bridge or other
form of temporary access is required across the diversion to the river.
The temporary works can sometimes be used to form part of the access for
pedestrians. Figure 31 shows the diversion works on the River Dever at Bransbury
Gauging Station, where the temporary earth embankment was used as access
across the river.
7.13. SECURITY
In low-risk areas a fence around the site is usually sufficient with a locked
compound to protect materials and plant. Pumps need to be protected to avoid
them being turned off. In high-risk, urban areas, a security guard may be required
in addition to fencing.
10 4
Health and safety on site
8
8. Health and safety on site
8.1. INTRODUCTION
In river diversion projects, health and safety is the responsibility of everyone on
site and must be an integral part of project planning. All works require a health
and safety plan to be drawn up that takes into account factors such as the legal
requirements, planning (risk, cost and noise assessments), company policy and
safe methods of work, including monitoring and reviewing, in order to meet site
specific rules and professional codes of conduct. All parties involved in the
diversion project have a statutory duty to protect not only their employees but also
the public from hazards associated with the works.
The basis of the regulation of health and safety in the UK is the Health and
Safety Act 1974 which provides a comprehensive legislative framework within
which to promote, stimulate and encourage high health and safety standards. Of
the subsequent legislation, the Construction (Design and Management)
Regulations 1994 are particularly relevant to river diversion projects. The CDM
Regulations apply to all design and construction work of over 30 days duration,
involving more than five people. However, they provide a useful framework for
works of any duration. CIRIA Report 145 (CIRIA, 1997a) provides a good basic
guide to the CDM Regulations. Health and safety in construction (HSE, 1995)
provides a general guide to regulations on construction sites.
The CDM Regulations place the duties of health and safety on clients,
designers, planning supervisors and contractors to focus on health and safety at all
stages of construction and demolition, from conception, design and planning to
commissioning and maintenance. To satisfy legal requirements, a designer must
carry out risk assessments and liaise closely with the planning supervisor
appointed by the client to ensure that all risks are minimised. A health and safety
plan is then drawn up which must be referred to and developed throughout the
project. A health and safety file, which is kept on site, must also be updated
regularly. The CDM Regulations include the relationship between the project
team parties, as shown in Figure 32.
Professional bodies, such as the Institution of Civil Engineers (ICE), have their
own codes of conduct that bind all members. Item 1 of the Rules for Professional
Conduct of the ICE state that members have full regard for the public interest in
matters of health and safety. Similar rules exist in the codes of other professional
bodies. There is numerous health and safety legislation that applies to river
107
RIVER DIVERSIONS
Client
Principle contractor
Designer Planning supervisor
Main contractor
108
HE ALTH AND SAFE T Y ON SITE
In the case of high-risk activities, permits to work are required as part of safe
work systems. The employer issues the permit to employees after the risks
involved in working on a particular site have been explained. Permits are only
issued after safe working procedures have been incorporated into the health and
safety plan. A case study design guide to risk assessment can be found in CIRIA
Report 145 (CIRIA, 1997a).
The key to successful health and safety planning is risk assessment and control.
Health and safety must be monitored and implemented in a systematic and
controlled way throughout the design, construction, operation and maintenance of
the works. A heavy responsibility is placed on the designer to ensure health and
safety is maintained throughout the works.
109
RIVER DIVERSIONS
health and safety provisions must be stringently applied in all cases. As well as the
risks associated with construction, additional hazards arise in river diversion work
owing to (CIRIA, 1997c):
• water (still or flowing)
• fluctuating flow rates and levels
• hydraulic structures, such as intakes, outfalls and weirs
• tides and currents
• rapid changes in weather, particularly in arid, urban or upland areas, which can
be prone to flash flooding
• waterborne diseases, such as Weils’ disease
• fixed structures, boats and rafts
• steep banks, which may be slippery or loose
• other water users.
For these reasons it is strongly recommended that personnel do not work alone
near water.
110
HE ALTH AND SAFE T Y ON SITE
Overseas:
• cholera
• typhoid
• polio.
• install safe working access, considering the impact of waves and debris on
working platforms, the undermining of supports by scour and corrosion of
equipment
• erect barriers, guard rails, toe boards and warning signs where there is a risk of
people falling into water
• provide life jackets conforming to BS EN 395 and safety lines for workers
• keep all ladders and platforms clean to avoid slipping
• ensure there are sufficient people present that are trained in rescue techniques
• pre-plan emergency procedures and assess the need for a fully equipped and
manned rescue boat
• install flood warning systems in areas known to be subject to flash flooding.
The Water Services Association produces advisory safety sheets, which are a
useful aid to risk assessment and planning for work in rivers.
111
RIVER DIVERSIONS
8.5.1. Introduction
Three main types of excavation occur in river diversion work: trenches,
cofferdams and caissons. These all present specific problems for the designer.
No unsupported excavation can be considered safe no matter how shallow and it is
vital that the designer minimises the risks associated with excavation in order to
avoid serious accidents. The dangers of working below ground level are increased
by working in, near or on water, as ground and surface water can have a major
impact on the way ground behaves. Excavations must be made safe by designing a
safe slope angle or by installing side supports where necessary. Support may be in
the form of sheet piles, drag boxes or proprietary systems, which have the
advantage of being installed without requiring people to enter the excavation. A
quick and easy means of escape out of an excavation should always be provided in
case of sudden wall collapse.
During excavation work the working face and support system must be
examined daily.
112
HE ALTH AND SAFE T Y ON SITE
Problem Solution
Header pipe
Sheet piling
GWL
GWL
Well point
Figure 33. Groundwater problem and potential solution (adapted from CIRIA SP
136, 1996)
113
RIVER DIVERSIONS
8.5.7. Services
The list of services that may be found under and over the site include gas, water
and oil pipes, telephone cables and fibre optics, electricity, sewers and street
lighting. Note:
(a) It is important to note that all service locations are approximate. Damaging
any one of these services can be very costly to repair and may carry a
significant danger to life.
(b) Before work commences a plan of the services on site should be drawn
up.
(c) Additional information about the location of services can be obtained by
calling SUSIEPHONE (Standard Utilities Services Information for
Excavators, tel: 0800 800333) and by calling the Ordnance Survey (helpline
tel: 0845 6050505).
114
HE ALTH AND SAFE T Y ON SITE
8.5.8. Trenches
Trenches less than 12 m deep may not require support if the ground is firm but
should not be considered safe unsupported. All trenches over 12 m deep must have
their sides supported sufficiently or they must be battered back to a safe angle that is
dependent on the soil properties of the site. Sharma and Lewis (1994) suggest that:
An unsupported cut in a dry cohesionless soil is not feasible. For such soils a stable slope can
be excavated at an angle where a factor of safety (F) is used and F is equal to tan/tan,
where is equal to the angle of internal friction of the sand. On the other hand, in cohesive
soils, having an undrained strength of c, an unsupported vertical trench can be excavated to a
height of H 4c=
, where
is the unit weight of the soil.
The above statement highlights the need for an accurate site investigation, as a
safe trench design must take into account soil type, which may vary rapidly along
the route of a river diversion, where old river channels are likely to be encountered.
Side support in trenches can be provided in a number of ways:
• struts and walling
• ground anchors
• fill.
Trenches should be inspected daily before use and a written record made of this
check once a week. For further information on the excavation of trenches consult
CIRIA Report 97 Trenching practice (1994a), BS 6031 Code of practice for
earthworks (British Standards Institution, 1981b) and the Construction
Regulations 1996.
8.5.9. Cofferdams
Cofferdams are used in river diversions to keep soil and water out of the original
channel or the diversion channel. It is often a temporary structure and can be a
land or water cofferdam, the former being excavated in a dry location and the
latter being surrounded by water. The most common type of cofferdam used in
river diversion work is the single walled dam, as opposed to the double wall as
shown in Figure 34.
WL
Lateral support Granular fill
WL
Ties
Excavation
Excavation
(a) (b)
Figure 34. Single and double wall cofferdams: (a) single wall; (b) double wall
115
RIVER DIVERSIONS
Construction Noise from Excess noise Health risk Environ- Provide ear
of cofferdam plant to workers mental protection
health Work within
inspection certain hours
Select suitable
plant
Use of sound
barriers
Vibration Excess ground Structural Cost, delay/ Structural survey
from plant vibration instability public Selection of plant
of adjacent relations Selection of
property (PR) method
and work
High river Flooding of Collapse or Damage to Use protective
flow/flood works damage of works boom to stop
works/loss Delay to floating debris
of life works Flood warning
system
High wind Handling of Collapse of Blockage Meteorological
conditions piles in piles of river checks
difficult waves Warning system
Slippery Unstable Slips, trips Health, cost Warning signs,
surfaces footing and falls trip boards,
correct footwear
Working at Falls Injury/loss Health, Safety helmets,
height over of life cost, delays lifejackets, safety
water ropes
116
HE ALTH AND SAFE T Y ON SITE
Single walled cofferdams are constructed using sheet piling, cast in place bored
piles or diaphragm walls, and can be laterally supported by struts, ground anchors or
fill. It is the designer’s responsibility to ensure the trench has an adequate factor of
safety against collapse. The infiltration of groundwater into excavations reduces the
factor of safety. Cofferdams are mentioned specifically in the Construction (Health,
Safety and Welfare) Regulations 1996 and require the supervision of a competent
person throughout construction, installation, and dismantling. Cofferdams should be
inspected daily before use and a written record made of the inspection. Some of the
risks associated with the construction of cofferdams are shown in Table 7.
For further information refer to BS 8004: 1986 Code of Practice for
Foundations and CIRIA SP 95 The design and construction of sheet-piled
cofferdams (1993b).
8.5.10. Caissons
A caisson may be used in river diversion work as an alternative to coffer-
dams when working close to a structure or in weak ground where piling would
disturb the ground too much. The type used would be a box caisson as shown
in Figure 35.
The caisson may be constructed on land at its final location or floated into
position. Transportation of a caisson may require special permission. Caissons are
placed by using their self-weight to sink into the ground. In river diversions they
may be floated into position, in which case they must be held in position while
being lowered. Situations in which caissons may not be suitable include sites with:
Water level
Prepared surface
117
RIVER DIVERSIONS
Rotation
Settlement
Horizontal
displacement
Prop
Services
Heave
Foundation may be subject to
lateral and vertical movement
Horizontal
displacement
118
HE ALTH AND SAFE T Y ON SITE
Even if good construction practices are followed there will still be some
settlement outside the excavation unless inward movement of the wall is
controlled. To minimise movement a good understanding of site conditions must
be combined with detailed design and monitoring. By ensuring settlement is
minimised during river diversion work, the risk of structural failure can be
reduced.
8.6.1. Pipelines
Pipelines may be used in river diversion work to carry flow around the site.
Pipelines may be placed in a trench or alongside works if the diversion is
temporary. The main influences on the hazards caused by pipes are their size,
material, location and depth. Care should be taken in choosing a pipe that has a
large enough capacity to carry flood flows, otherwise water will bypass the pipe
119
RIVER DIVERSIONS
Stacked pipes, particularly close to excavations Crush and impact injuries, death,
and lifting and lowering operations falling materials
Working at depth, trench collapse Crush and impact injuries
Dangerous atmospheres Fire and explosions, suffocation
Operation of equipment in a confined space Damage to hearing
Noise and dust (particularly from asbestos Risk to workers’ health
cement pipes)
Water and sewage Flooding, drowning and diseases
Groundwater Trench instability
and flow into the site, defeating the object of diverting flow around it. The main
risks in pipeline construction and repair are provided in Table 8.
A risk assessment and method of working must consider how hazards alter as
the pipe-laying process progresses. Points to consider include:
• delivery of pipes
• stacking
• lifting
• working with asbestos cement pipes
• maximum carrying capacity of the pipe and design flow
• action in case of flood flows.
120
Part D
Legislation
RIVER DIVERSIONS
(a) The requirements for consents, permits and authorisations, e.g. planning
permissions. Breach of these requirements is usually a criminal offence.
(b) Civil or criminal liability in respect of the carrying out of work with regard to
such things as nuisance caused by noises, the disposal of waste (section 34,
Environmental Protection Act 1990) and the common laws.
12 2
Legalresponsibilities and
planning
9
9. Legal responsibilities and planning
MAFF must approve flood defence schemes carried out by flood defence
operating authorities if the scheme is either grant aided or would cost over
£05 million. The Water Resources Act 1991 contains several provisions of
relevance to river engineers including:
(a) MAFF designates ‘main’ rivers and holds a definitive map (as does the
Environment Agency, section 193 of the Water Resources Act 1991).
(b) MAFF can give grants for engineering schemes to operating authorities
including the Environment Agency.
(c) MAFF must authorise compulsory purchases of land made by operating
authorities.
125
RIVER DIVERSIONS
The Environment Agency has a general supervisory duty for all flood
defence matters regardless of the status of the river. The Environment Agency
then has specific operational and regulatory powers for main rivers and default
powers on ordinary watercourses. The Environment Agency’s approval is
necessary for temporary and permanent diversions on main rivers and also
126
LEGAL RESPONSIBILITIES AND PL ANNING
(a) The supervisory duty of the Environment Agency is stringently applied to all
river works.
(b) Section 165 of the Water Resources Act 1991 gives the Environment Agency
permissive powers in respect to maintenance, improvement and construction
on main rivers.
(c) The Environment Agency is a statutory consultee in the planning process for
planning applications and development plans, including those applications
that involve works in, adjacent to or within the floodplain.
(d) Highways authorities must obtain consent from the Environment Agency or
drainage bodies before any work is carried out on a river or drainage channel
(Highways Act 1980). Note that work related to bridges could be exempt and
works carried out under an order may not require Environment Agency
consent. However, the Environment Agency should be consulted in all cases.
(e) Section 109 of the Water Resources Act 1991 states that no one may erect a
structure in/over/on a main river except with the consent of and in
accordance with plans approved by the Environment Agency.
(f) Proposals to construct or alter a culvert require consent from the
Environment Agency (or Internal Drainage Board if in their area) or local
authority. (Note that there may be an exemption for highway authorities
regarding ordinary watercourses and that works done under an Order will
normally also be exempt.)
(g) The Environment Agency has the powers to improve any existing
watercourse, including deepening, widening, placing structures, etc. In the
case of river diversions the Environment Agency may actually be the
promoter of works, e.g. for flood defence purposes.
(h) No alterations may be made to a structure in, over or under a main river
without Environment Agency consent (unless it is in an emergency).
127
RIVER DIVERSIONS
9.7.1. Culverts
Permission from the Environment Agency must be granted before a main river
may be culverted and an Environmental Statement may be required. Before
culverting any watercourse, including ditches, if that culverting is likely to affect
flow (which is usually the case), the consent of the Environment Agency (or IDB
128
LEGAL RESPONSIBILITIES AND PL ANNING
in an IDB district) is required. Note that the key word is ‘affect’, not restrict, and,
as such, the Environment Agency consent is required for practically all culverting.
As river diversion works may involve temporary culverts, the above requirements
must be taken into account at the planning stage.
129
RIVER DIVERSIONS
9.8.2. Procedure
In order to obtain planning permission, an application is made to the local
planning authority where the land is situated. The authority has a discretion to
refuse planning permission or to grant it (including granting it subject to
conditions) under the Town and Country Planning Act 1990. The legal
requirements for applicants are found in the legislation. An applicant is required
to serve notice on owners of land and on any tenants. Publication of the planning
application is required by the authority, which allows any interested party a period
of six weeks to comment before a decision is taken on the application.
130
References
10
10. References
Ackers, P., White, W. R., Perkins, J. A. and Harrison, A. J. M. (1978). Weirs and flumes for flow
measurement, J. Wiley and Sons, Chichester.
Armstrong, G. (1994). NRA experience with freshwater fish passes. Fish Passes in Barrage and
Weir Design, one day seminar at HR Wallingford, 16 June.
Avery, P. (ed.) (1989). Sediment control at intakes. A design guide. BHRA fluid engineering
centre.
Bettess and White (1983). Meandering and braiding of alluvial channels. Proceedings of the
Institution of Civil Institutions, Part 2.
British Standards Institution (BSI) (1981a). Code of practice for site investigations. BS 5930:1981.
BSI.
British Standards Institution (BSI) (1981b). Code of practice for earthworks. BS 6031:1981. BSI.
British Standards Institution (BSI) (1986). Code of practice for foundations. BS 8004:1986. BSI.
Chang, H. H. (1988). Fluvial Processes in River Engineering. J. Wiley and Sons, Chichester.
Chapman, D. (1992). Water quality assessments, a guide to the use of biota, sediments and water
in environmental monitoring. Chapman and Hall Ltd, UK.
Construction Industry Research and Information Association (CIRIA) (1983). Site investigation
manual. A. J. Weltman and J. M. Head. CIRIA Special Publication 25. Published in
conjunction with Property Services Agency, DoE, London
Construction Industry Research and Information Association (CIRIA) (1988). Control of
groundwater for temporary works. S. H. Somerville. CIRIA Report 113, London.
Construction Industry Research and Information Association (CIRIA) (1992). Medical code of
practice for working with compressed air. CIRIA Report 44, London.
Construction Industry Research and Information Association (CIRIA) (1993a). Site safety
handbook. S. C. Bielby. CIRIA Special Publication 90, London.
Construction Industry Research and Information Association (CIRIA) (1993b). The design and
construction of sheet-piled cofferdams. B. P. Williams and D. Waite. CIRIA Special
Publication 95. Published by CIRIA in conjunction with Thomas Telford Limited, London.
Construction Industry Research and Information Association (CIRIA) (1994a). Trenching
practice. D. J. Irvine and R. J. H. Smith. CIRIA Report 97, London.
Construction Industry Research and Information Association (CIRIA) (1994b). Environmental
handbook for building and civil engineering projects. CIRIA Special Publication 97, London.
Construction Industry Research and Information Association (CIRIA) (1995). Remedial treatment
for contaminated land, Volume 5: Excavation and disposal. CIRIA Special Publication 105,
London.
133
RIVER DIVERSIONS
Construction Industry Research and Information Association (CIRIA) (1996). Site guide to
foundation construction. CIRIA Special Publication 136, London.
Construction Industry Research and Information Association (CIRIA) (1997a). CDM Regulations
case study guidance for designers: An interim report. J Crooks et al. CIRIA Report 145,
London.
Construction Industry Research and Information Association (CIRIA) (1997b). Culvert design
guide. D. Ramsbottom. R. Day and C. Rickard. CIRIA Report 168, London.
Construction Industry Research and Information Association (CIRIA) (1997c). Site safety for the
water industry. Sir William Halcrow and Partners Ltd, CIRIA Special Publication 137, London.
Chartered Institution of Water and Environmental Management (CIWEM) (1989). Water practice
manual 8: River engineering part II, structures and coastal defence works, T. W. Brandon
(Ed.). CIWEM.
Clay, C. H. (1995). Design of fishways and other fish facilities, 2nd edition. CRC Press, Florida,
USA.
Department of the Environment (DoE) (1989). Environmental Assessment: a guide to the
procedures. DoE, Her Majesty’s Stationery Office, London.
Department of the Environment (DoE) (1992). Development plans and regional planning
guidance, PPG12. DoE, Her Majesty’s Stationery Office, London.
Department of the Environment (DoE) (1993). Environmental Appraisal of Development Plans.
DoE, Her Majesty’s Stationery Office, London.
Department of the Environment (DoE) (1994). Planning policy guidance: planning and the
historic environment, PPG15. DoE, Department of National Heritage, Her Majesty’s Stationery
Office, London.
Department of the Environment (DoE) (1995). Preparation of Environmental Statements for
planning projects that require Environmental Assessment: A good practice guide. DoE, Her
Majesty’s Stationery Office, London.
Department of the Environment, Transport and the Regions (DETR) (1999). Construction risks in
river and estuary engineering. DETR, Her Majesty’s Stationery Office, London.
Einstein, H. A. (1944). Bed load transportation in mountain creek. US Department of Agriculture
Soil Conservation Service.
Environment Agency (1996a). Environmental Assessment scoping handbook for projects. Her
Majesty’s Stationery Office, London.
Environment Agency (1996b). Blue-green algae, Leaflet HO-5/96-20K-A-ASRG. Her Majesty’s
Stationery Office, London.
Environment Agency (1999a). R&D Technical Report W21: Fluvial Design Guide-Scoping Study
Proposals. Environment Agency.
Environment Agency (1999b). Waterway bank protection: a guide to erosion assessment and
management. Environment Agency.
Escarameia, M. (1998). River and channel revetments – a design manual, Thomas Telford Ltd,
London.
Fisher, K. R. (2000). Handbook for assessment of hydraulic performance of environmental
channels (draft). HR Wallingford.
Head, C. R. (1975). Siphons in river engineering. BHRA Symposium, Paper C2.
134
REFERENCES
135
Appendices
Appendix 1.
Methods for calculating the tailwater
elevation
For channels where the design flow is contained within the banks, A and P are
calculated as shown in Figure A1.1(a). For channels where the design flow
exceeds the channel capacity as shown in Figure A1.1 (b), Q is calculated using
the following formula:
( ! ! !)
2=3 2=3 2=3
AC R C AL R L AR R R
Q s1=2
13
nC nL nR
where nC, nL and nR are Manning’s n values for the channel, left floodplain and
right floodplain respectively.
139
RIVER DIVERSIONS
A AL AR
AC
P PL PR
PC
(a) (b)
The procedure for calculating the tailwater for a given design flow can be
iterative, as follows:
Water surface
profile
Control point
E
D
C
B A
Proposed location
of diversion outlet
14 0
APPENDIX 1
Several cross sections should be surveyed between the downstream limit of the
river diversion and the control point or downstream limit of the backwater length.
The most convenient way of applying the backwater method is to use computer
software.
To use this method without the need for a computer the cross sections should be
simplified to a common geometric shape, e.g. trapezoidal channel, rectangular
channel, etc. over the length which the backwater calculation will take place.
The object of the backwater method is to calculate the water surface elevation
at the upstream limit of a length of channel. The backwater method involves
calculating a water surface profile starting at the downstream end and working
upstream. Thus, the starting points will be at the downstream control point or limit
of backwater length.
The most efficient method for calculating the required upstream elevation is to
make use of Figure A1.3. The first row in the table corresponds to the section
where the start depth is ys and all the data for columns 1 to 9 are known. The total
head in column 14 for the first row is equal to the value in column 7. The chainage
at the start depth is 0, which can be entered into column 1.
To complete column 9, the friction slope, Sf, use will need to be made of a
Manning’s roughness value. If, however, the bed and culvert walls/channel banks
are not of the same roughness then a compound roughness will need to be
determined. Determine the compound roughness using the method in
Section A1.3.
The value of n0 (compound roughness) can then be used in place of n in the
calculation of Sf. Each of the rows after row 1 will correspond to a reach between
two of the stations where the water depth is to be determined.
The next step is to calculate the depth of flow at the first station along the
channel, a distance x upstream from the starting point. Initially a trial value of
the depth y is guessed and entered into column 3 and columns 2 and 4 to 9 are
calculated as in the first row. Column 10 is then the mean between the friction
slope at the start depth (in row 1) and that for the trial depth in column 9, row 2.
The head loss due to friction, hf, (column 12) is then the product of Sf and x.
If a bend has occurred in the culvert/channel reach the head loss due to the
bend, hb, should be entered into column 13. The final column is then the sum of
total head, H, for the previous reach (row 1 in this case) and hf and hb in row 2.
If columns 14 and 7 are equal then the initial depth guessed was correct. If they
are not equal then a second value for the depth at the first station has to be
selected. To help reduce the number of guesses required before column 14 and 7
agree, a correction factor, y, can be calculated:
e
y
15
3S f x
1 ÿ Fo
2
2R
where e is the difference between column 7 and column 14 for the first trial
depth
x is the distance from the last station
141
142
RIVER DIVERSIONS
hb
v 12
hf
2g
v 22
z = zstart – S (∆x)
2g
y1 Q
V=
A
y2 v2
Slope S H1 = z + y +
2g
Q 2n 2P 4/3
Sf =
∆x A10/3
z1 Sf (prev) + Sf
Sf =
z2 2
x hf = ∆xSf
Datum
H = H prev + hf + hb
x z y A v v2 H1 P Sf Sf ∆x hf hb H
2g
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14)
If y is negative then the value should be added to the depth of flow guessed in
column 3, whereas if y is positive the value should be taken from y. With a new
depth, y, calculated using the correction factor columns 2 and 4 to 14 can be
recalculated and the process outlined above repeated until columns 7 and 14 agree
within an acceptable tolerance.
When a depth of flow at the first station has been determined this then becomes
the start point for the next reach in order to calculate the depth of flow at the
second station, etc.
1
ni
143
Appendix 2.
Roughness coefficients for natural
channels
145
RIVER DIVERSIONS
Manning’s n value
Type of channel and description Minimum Normal Maximum
146
Appendix 3.
Legislation and statutes
The lists below cover the legislation and statutes that may be relevant to the
planning, design and implementation of river diversions. While the most
commonly referred to items of legislation are covered in the text, the list
provides a source or reference for the range of legislation that might have to be
considered. Legislation is periodically improved and updated, and users of this
guide should be aware of the most recent relevant legislation.
A3.1. GENERAL
• Highways Act 1980
• Wildlife and Countryside Act 1981
• Local Government Act 1985 and 1992
• Agriculture Act 1986
• Water Act 1989
• Environmental Protection Act 1990
• Water Resources Act 1991
• Land Drainage Act 1991
• Local Government (Wales) Act 1994
• Environment Act 1995
147
RIVER DIVERSIONS
A3.4. ENVIRONMENTAL
• Environment Agency (1996) Blue-green algae P13/9/96 AN-15k-APRI
• EC Directive 1994, Conservation Regulations
• EC Directive 1994, Habitat Regulations
• Wildlife and Countryside Act 1981
• Food and Environmental Protection Act 1985
• Environmental Protection Act 1990
• Environment Act 1995
• Habitat (Water Fringe) Regulations 1994 (SI 1994/1291)
• Habitat (Former set-aside-land) Regulations 1994 (SI 1994/1292)
• Habitat (Salt-Marsh) Regulations 1994 (SI 1994/1293)
• Conservation (Natural habitats etc.) Regulations 1994 (SI 1994/2716)
• Habitat (Water fringe) (Wales) Regulations 1994 (SI 1994/3064)
• The Environmental Impact Assessment (Land Drainage Improvement Works)
Regulations 1999 (SI 1999/1783)
14 8
APPENDIX 3
149
Appendix 4.
Examples of river diversions
A4.1.1. Description
Permanent diversion channel and associated structures to increase the capacity of
the River Ash (a ‘main’ river) to carry increased discharge from Ashford Common
water treatment works. The scheme was promoted by the Environment Agency
and funded by Thames Water Utilities.
A4.1.2. Design
A 300 m section of the existing river channel upstream was dredged to increase
hydraulic capacity. A 325 m diversion channel with capacity of 1 m3/s was
constructed on a landfill site to convey extra flow from the upgraded works.
The new trapezoidal channel was lined in order to prevent contaminated
groundwater entering the channel and river water leaking out. The lining of the
channel consisted of puddled clay overlayed by an HDPE (High Density
Polyethylene) liner and a geotextile overlayed with a cellular geotextile that could
be filled with topsoil. The lining is shown in Figure A4.1. Once the lining was in
place a layer of gravel was placed on top to provide substrate.
151
RIVER DIVERSIONS
Figure A4.2. Intake with trash screen, low-flow weir and boom
The inlet structure to the diversion channel was a reinforced concrete culvert
with a trash screen, low-flow weir and boom as shown in Figure A4.2.
152
APPENDIX 4
A4.1.4. Groundwater
As the diversion was constructed on a landfill site the groundwater on the site was
contaminated and had to be pumped to a foul sewer 800 m away. Groundwater
from the workings was pumped into lagoons (Figure A4.5) in order to settle and
be mixed with river water. The resulting mixed water was then tested and
measured amounts released back into the river. In addition, the lagoons allowed
the storage of groundwater for gradual release to the sewer.
153
RIVER DIVERSIONS
A4.17. Access
During construction a temporary road from a nearby lane was utilised to access
the works. Pedestrian access to the finished channel was provided by a timber
footbridge. Vehicular access was provided over a 3 m box culvert.
A4.1.8. Contractual
None of the land was owned by the Environment Agency or by Thames Water.
Permission for entry to carry out works was obtained by agreement with the
individual freeholder and leaseholders.
154
APPENDIX 4
A4.2.1. Description
A flood relief channel was designed to carry a maximum of 215 m3/s of flood
water from the River Thames in order to provide flood protection to a 1 in 65
year standard for Windsor, Eton and Maidenhead. The Environment Agency
promoted the scheme and it was partly funded by a MAFF grant. The scheme
involved the construction of a channel that carries a sweetening flow all year
round and begins to receive flood water once the flow in the River Thames
exceeds 200 m3/s. Flow into the diversion channel is controlled manually by
radial gates while the other gates on the channel are operated automatically on
the upstream water level. The scheme is one of the largest of its kind to have
been undertaken in the UK.
A4.2.2.Route
The diversion route was influenced by archaeological sites, local land use,
topography and farming practices.
A4.2.3. Design
The relief channel comprises an 11 km section of channel running from
Maidenhead to beyond Windsor. The majority of the channel is trapezoidal,
unlined with a bed width of 30–35 m, side slopes of 1:15 and a depth of 5 m.
Channel width varies however, from 25 m under structures to 102 m in areas
of environmental enhancement. The channel design capacity is 215 m3/s. The
split of flows between the total flow and flow in the new channel is shown in
Table A4.1.
The hydraulic design of the flood relief channel was undertaken using
computational river models based on the ONDA and HEC2 software. Modelling
was undertaken for a range of floods up to a 1 in 200 year flood scenario. The
hydraulic modelling incorporated all the structures and environmental features on
the relief channel.
155
RIVER DIVERSIONS
Table A4.1. Flow split for the Maidenhead, Windsor and Eton flood relief channel
Above 40 10
40–15 One third of the flow or 10, whichever is lesser
15–10 5
Below 10 Half the total flow
Morphological modelling was carried out to ensure the regime of the river
would not be adversely affected by the diversion. Modelling showed that
maintained dredging of the new channel would not be needed for many years and
no monitoring was suggested, as the entire channel was dug 500 mm deeper than
design to provide sufficient capacity for at least 20 years of siltation.
Structures along the length of the flood relief channel include manually
operated radial gates at the upstream end. There are broad crested weirs along the
length of the diversion, the first being a three-gated weir with radial and flap
gates. There are also five road bridges, six footbridges, five hydraulic controls and
two inverted syphons, which carry local watercourses under the channel.
A4.2.4. Construction
A computerised system controlling the depth of dig and excavation profile was
developed for the scheme. Excavation took place mainly underwater using
hydraulic backhoes connected to this system. All the structures were built in
cofferdams or within diaphragm walls and silent sheet piling was used.
Dewatering was required at the cofferdams.
156
APPENDIX 4
material was stripped and placed in a sealed cell. The cell was lined with clay and
capped with clean material.
A4.2.9. Groundwater
Groundwater modelling was undertaken especially around the Dorney and Slough
sewage works. Weir sites were chosen to maintain existing groundwater levels
with a head drop of approximately 1 m across each weir.
A4.2.10. Access
Consultation was required with the local highways authority to obtain permission
for the movement of lorries. It was important to minimise disruption to the local
people. The size of plant was determined by the magnitude of the loads that the
bridges and access roads could tolerate. Full diversion of the M4 was required
when building the motorway bridge over the diversion channel. Public footpaths
were diverted or maintained where possible. New footpaths and cycle paths along
the diversion channel linked with existing routes. Access was also provided for
wheelchair users of the paths.
A4.2.11. Contractual
Most of the land for the relief channel was obtained through compulsory purchase
orders (CPO) authorised by MAFF. Eton College said that they would only lease
land and this caused a delay until April 1996. Four types of land may not be
purchased under CPO: Crown land, common land, allotments and National Trust
land. In this scheme, both common land and allotments were swapped for
equivalent land. There were many councils involved in the planning of the scheme
and good consultation was essential.
157
RIVER DIVERSIONS
A4.2.16. Maintenance
Ongoing maintenance is initially being carried out by the landscape contractors.
This will then revert to the Environment Agency for five years and eventually
back to the riparian owners.
A4.3.1. Description
A permanent wet diversion channel was constructed so that a supermarket could
be built on land owned by the district council. In addition, a temporary pumped
diversion was used on a stretch downstream of the permanent diversion to allow
river works. The scheme was promoted and funded by the developer.
158
APPENDIX 4
A4.3.2. Design
The river length of the diversion is shorter that the original length. Pool and riffle
sequences were used in the diversion channel to provide regions of low velocity.
Flood defences were required downstream to ensure the works gave a 1 in 100
year flood protection. Environmental features were designed, including an offline
amenity pond, meanders, rock pools, low stone weirs and islands (Figures A4.7
and A4.8). Deflectors were used to force flow through the low-flow channel at
higher velocities.
Steady state hydraulic modelling was undertaken for the hydraulic design of the
channel. The hydrology was modelled taking into account possible future
developments.
159
RIVER DIVERSIONS
A4.3.3. Construction
The temporary diversion was pumped (Figure A4.9) using automatic level
controls to cut in more pumps as required. Flow information was limited but the
work was undertaken in summer when flows were low. A clay sheet piled bund
was used to stop flow at the upstream end and a cofferdam at the downstream end.
The bund crest height was designed so that there would be little backwater effect
upstream. At breakthrough for the permanent diversion, water was allowed to
pond back from the downstream end (Figure A4.10).
Figure A4.9. Piled cofferdam and pumps for the downstream temporary diversion
160
APPENDIX 4
A4.3.4. Material
Excavated material was used for infilling and also by the developer on their
parking area.
A4.3.5. Contractual
A private developer undertook the work but the Environment Agency was keen to
see the work carried out. The involvement of the Environment Agency was vital
in obtaining cooperation from landowners.
161
RIVER DIVERSIONS
Figure A4.12. Siphon on the Staines bypass channel under the A30 road
162
APPENDIX 4
All parts of the Lower Colne Improvement Scheme were promoted and funded
by the Environment Agency with MAFF grant aid.
163
RIVER DIVERSIONS
structure on the Colne Brook downstream of the mill. The two control structures at
the upstream end of the diversion channel have fixed widths and crests, although one
of the weirs at the head of the diversion channel can have stop logs installed. This
structure also has a fish pass. The structure in the Colne Brook is a Crump weir,
which determines the flow split. The new mill structure has a fish pass.
The diversion channel is a permanent feature cut through low-grade agricultural
land of little ecological value. The flood bypass channel was created with a
meandering profile, marginal shelves and a variable depth to provide a variety of
aquatic and wetland habitat types. The marginal shelves were planted with aquatic
and emergent vegetation including branched bur-reed, sweet flag and flowering
rush.
A4.5.1. Description
The gauging station lies on a remote small river in the New Forest with limited
access. The existing weir was to be replaced as it is inaccurate for gauging flow.
Migratory fish are present in the river.
A4.5.2. Design
A diversion channel 900 mm wide with straight trapezoidal sides (Figure A4.14)
was used in conjunction with a pipe over which an access track was laid. The
16 4
APPENDIX 4
channel had weir boards at regular intervals to create pools upstream and
turbulence downstream to allow fish to pass. The Environment Agency specified
the normal water level and maximum level of working so that any damming
would not elevate upstream water levels above set levels. The temporary diversion
channel ran into a backwater/creek at the side which needed desilting at the end of
the work. The new weir was constructed with a fish pass through the centre.
A4.5.3. Construction
The construction of the new weir used the permanent works as temporary works.
Sheet piles were driven in upstream of the structure to prevent flow under and
around it. The sheet piles were left high to form a temporary cofferdam and then
trimmed at the end of the project. The trimming was done underwater, which was
expensive.
An air percussion hammer was used to drive piles through the clay on site with
a vibro hammer being used in gravels. As the area is remote, piling was allowed
between 9 a.m. and 5 p.m. on weekdays. Problems arose during construction with
rubbish and debris upstream of the existing structure, so a trench was dug across
the face of the piles to allow the rubbish to be collected and removed.
A4.5.4. Season
The diversion was scheduled to take place over a summer period of ten weeks.
Work was delayed into the autumn resulting in flooding of the site once.
165
RIVER DIVERSIONS
A4.5.5. Material
Diversion material from the channel was stored and then used as backfill above
the pipe. Some fill material was brought onto the site to backfill behind the
headwalls.
A4.5.6. Access
A temporary road had to be built as the site was remote. The access road was
made of geotextile covered with stone and local gravel. Once work was completed
the road was taken up. A landscaper then used local stone to construct a
permanent road.
A4.5.7. Sediments
The diversion took place in the summer so sediment loads were low. Scour was
not considered a problem as flows were very low.
A4.5.8. Maintenance
The piped section of the diversion was left in place with a penstock at the
upstream end and a grille at the downstream end. The penstock can be opened if
maintenance is needed on the weir, diverting flow for a short period of time.
A4.5.10. Environmental
Two old oak trees on the left bank were worked around. The contract specified
that the fish pass must be in place before the existing weir was demolished.
During construction the fish pass in the diversion channel was used by many large
fish.
A4.5.11. Risk
As the work was delayed by six weeks into the autumn, a claim was put in when
the works were flooded.
166
APPENDIX 4
A4.6.1. Description
The existing road bridge at the site was removed and a new one built
incorporating an electromagnetic gauging station. A temporary diversion channel
was cut into the right bank and an earth bund built around the bridge.
A4.6.2. Design
The temporary diversion channel was a similar width to the existing river – 4 m
wide. The crest level of the bund was taken as 450 mm above normal water level
based on flow and level information given to the contractor.
A4.6.3. Construction
A temporary cofferdam was proposed around the bridge but this was expensive
and would involve piling close to housing. An earth bund was built around the
structure with continuously pumped well points and a perforated land drain
300 mm below the surface.
A4.6.4. Access
Temporary crane mats were laid over the diversion channel to provide access for
plant and pedestrians/horses. A footbridge was not required as pedestrians used
the earth bund as access across the river.
A4.6.5. Groundwater
There were some problems dewatering the excavation owing to the high
groundwater levels and seepage.
A4.6.6. Material
The excavated material from the diversion channel was used to build the bund and
was topped off with material from off-site.
A4.6.8. Environmental
The pumps utilised were silenced and there were no problems with noise or spills
of oil or diesel.
167
RIVER DIVERSIONS
A4.6.9. Sediments
At breakthrough sediments were flushed. Breakthrough was timed to take place in
the late afternoon/early evening to ensure the least disturbance to fishermen
downstream. By morning the sediment plume had dispersed.
A4.7.1. Description
Reconstruction of the lock took place using the permanent main channel as a
temporary diversion. The work took place over two winters to cause least
disturbance to navigation and involved enlarging and repairing the lock structure.
A4.7.2. Design
A temporary cofferdam was constructed round the lock over two winter work
periods. In the first contract period, 14 m piles were driven through 13 m of gravel
and chalk on either side of the lock. During the second contract period of four
months, pile were installed across the head and tail of the lock to allow demolition
of the old lock chamber and construction of the new one. The work carried out can
be seen in Figure A4.15.
168
APPENDIX 4
A4.7.3. Construction
The length of piles was determined from borehole information. During the first
period of work, piles needed to be installed with the minimum of noise and vibration
owing to the poor condition of the tail structure and proximity of the lock house. In
difficult ground conditions a water jetting hose was used to assist penetration. The
system was so successful that noise levels were lower than those generated by the
weir close by. In construction of the new lock structure, 14 m long piles were used to
ensure no props below ground level were required. The cofferdam is shown in
Figure A4.16.
A4.7.4. Seasonality
Work was confined to the winter months when river traffic is at a minimum and
inconvenience to river users is reduced.
169
RIVER DIVERSIONS
A4.7.5. Contractual
The use of the permanent river channel as a diversion saved the contractors time
and money.
A4.8.1. Description
Channel improvements for flood protection including localised dredging and
lining of the channel with reinforced concrete.
A4.8.2. Design
A temporary cofferdam was constructed at the upstream end of the channel
(Figure A4.17) with a flexible pipe diverting water alongside the works (Figure
A4.18). The flexible tube had a carrying capacity of 24 m3/s and the level of the
pipe inlet was specified by the Environment Agency. At the downstream end, a
Portadam was used to temporarily dam the channel (Figure A4.19). The channel
was lined with reinforced concrete and the banks were stabilised using a
geotextile.
170
APPENDIX 4
Figure A4.18. Flexible pipe diverting flow while concrete reinforcing was placed
A4.8.3. Environmental
A site of archaeological significance was located next to the works and care was
taken not to disturb the site during the diversion.
A4.8.4. Access
A temporary access road was constructed for anglers and a tenant farmer.
A4.8.5. Construction
Owing to the work being carried out from September to December there was some
flooding during the construction. The Environment Agency specified maximum
upstream cofferdam levels but did not give a specific method of working.
171
Index
173
RIVER DIVERSIONS
174
INDEX
175
RIVER DIVERSIONS
176