Вы находитесь на странице: 1из 4

E-02c1: Kirkland-NE 85th Street BRT Inline Station (Intensive

Capital)
Project Number E-02c1 PROJECT AREA AND REPRESENTATIVE ALIGNMENT
Subarea East King
Primary Mode BRT
Facility Type Station
Length N/A
Version ST Board Workshop
Date Last Modified 11-15-2015

SHORT PROJECT DESCRIPTION


This project would construct a BRT inline station on I-405 at NE
85th Street with pedestrian bridges and elevators to bus stops on
NE 85th Street.
Note: The elements included in this representative project will be
refined during future phases of project development and are subject
to change.

KEY ATTRIBUTES
REGIONAL LIGHT No
RAIL SPINE
Does this project help complete
the light rail spine?

CAPITAL COST $243 — $260


Cost in Millions of 2014 $

RIDERSHIP <1,000
2040 daily boardings

PROJECT ELEMENTS · BRT inline station at NE 85th Street in Kirkland with pedestrian access to bus stops along both directions
of NE 85th Street
· Peak headways at this station: 10 minutes
· 1 percent for art per Sound Transit policy
· Non-motorized access facilities (bicycle/pedestrian) and transit-oriented development (TOD)/planning due
diligence (see separate document titled “Common Project Elements”)
NOT INCLUDED · Enhanced aesthetic surface treatments on the retaining walls
· Operations (I-405 BRT service to this inline station is included in project E-02b-SegA)
· Parking not included
· Sustainability measures and bus/rail integration facilities not included in BRT projects on WSDOT right-of-
way
· See separate document titled “Common Project Elements”
ISSUES & RISKS · Relies on WSDOT to maintain adequate speed and reliability of I-405 express toll lane system
· Risk associated with construction of inline station
· At the NE 85th St inline station the posted speeds of the interchange “loop” ramps will need to be reduced
from 25 mph to 20 mph because the curve radii need to be reduced to connect into the widened I-405 and
avoid major interchange ramp reconstruction and right of way impacts; the reconstruction of the I-405
bridges over NE 85th Street will create construction staging challenges to maintain the movement of high
volumes of traffic through this interchange
· Remediation may be required for poor soil conditions and hazardous materials
Sound Transit 3 Template Release date: December 4, 2015
Page 1 of 4
E-02c1: Kirkland-NE 85th Street BRT Inline Station (Intensive
Capital)

Sound Transit has developed a conceptual scope of work for this candidate project for the purpose of generating a representative range
of costs, both capital and operating; and benefits, including ridership forecasts, TOD potential, multi-modal access and others. This
information is being developed to assist the Sound Transit Board as it develops an ST3 system plan, including phasing of investments
and financial plan, for voter consideration. Final decisions on project elements (e.g., alignment, profile, number of stations, station
locations, and number of parking stalls) will be determined after completion of system planning, project level environmental review and
preliminary engineering during which additional opportunities for public participation will be provided. Therefore, this scope definition
should not be construed as a commitment that all representative features will be included in the final developed project.

Long Description:
This project will construct a BRT inline station on I-405 at NE 85th Street with pedestrian bridges and elevators to bus stops on NE 85th Street.

Assumptions:
· BRT will operate in I-405 express toll lanes through Kirkland
· BRT service span: up to 19 hours of service Monday – Saturday, 17 hours on Sunday
· For non-motorized station access allowances, the NE 85 th Street BRT station is categorized as a suburban station
Environmental:
Sound Transit will complete project-level state and federal environmental reviews as necessary; provide mitigation for significant impacts; obtain and
meet the conditions of all required permits and approvals; and strive to exceed compliance and continually improve its environmental performance.

Utilities:
Utility relocation as needed to complete the project, including fiber optics, sewer, water, overhead electric/communications, etc.

Right-of-Way and Property Acquisition:


· Right-of-way acquisition and easements as needed to complete the project
· For the NE 85th Street inline station, property acquisition will be needed along both on-ramps to I-405 for the widening of the mainline
required by the inline station in the I-405 median

Potential Permits/Approvals Needed:


· FHWA approval for modifications to interchanges and ramps
· WSDOT and FHWA approvals for use of and/or crossings of I-405 rights-of-way
· Agreements with WSDOT and King County Metro for use of inline stations
· Building permits: Electrical, Mechanical, Plumbing
· Utility connection permits
· Construction-related permits (clearing and grading, stormwater management, street use, haul routes, use of city right-of-way)
· Master use
· Land use approvals (Conditional use, design review, site plans, Comprehensive Plan or development code consistency, Special Use
Permits)
· All required local, state, and federal environmental permits
· NEPA/SEPA and related regulations

Project Dependencies:
· WSDOT I-405 Master Plan widening projects
· Affected by E-02b I-405 BRT Project (all other segments)

Potential Project Partners:


· WSDOT · King County
· City of Kirkland · FTA
· FHWA · Transit partner serving this project: King County Metro

Sound Transit 3 Template Release date: December 4, 2015


Page 2 of 4
E-02c1: Kirkland-NE 85th Street BRT Inline Station (Intensive
Capital)
Cost:
Sound Transit has developed a conceptual scope of work for this candidate project for the purpose of generating a representative range of costs,
both capital and operating; and benefits, including ridership forecasts, TOD potential, multi-modal access and others. This information is being
developed to assist the Sound Transit Board as it develops an ST3 system plan, including phasing of investments and financial plan, for voter
consideration. Final decisions on project elements (e.g., alignment, profile, number of stations, station locations, and number of parking stalls) will
be determined after completion of system planning, project level environmental review and preliminary engineering during which additional
opportunities for public participation will be provided. Therefore, this scope definition should not be construed as a commitment that all
representative features will be included in the final developed project.
In Millions of 2014$

ITEM COST COST WITH RESERVE


Agency Administration $12.83 $13.73
Preliminary Engineering & Environmental
$8.35 $8.94
Review
Final Design & Specifications $16.67 $17.84
Property Acquisition & Permits $0.52 $0.56
Construction $170.03 $181.93
Construction Management $15.00 $16.05
Third Parties $3.33 $3.57
Vehicles $0.00 $0.00
Contingency $16.67 $17.84
Total $243.41 $260.45

Design Basis: Conceptual

The costs expressed above include allowances for TOD planning and due diligence, Sustainability, Bus/rail integration facilities, and Non-Motorized
Access. These allowances, as well as the costs for Parking Access included above, are reflected in the following table. Property acquisition costs are
not included in the table below, but are included within the total project cost above.

ITEM COST COST WITH RESERVE


TOD planning and due diligence $0.02 $0.02
Sustainability N/A N/A
Parking access N/A N/A
Non-motorized (bicycle/pedestrian) access $0.88 $0.94
Bus/rail integration facilities N/A N/A

Sound Transit 3 Template Release date: December 4, 2015


Page 3 of 4
E-02c1: Kirkland-NE 85th Street BRT Inline Station (Intensive
Capital)
Evaluation Measures:

MEASURE MEASUREMENT/RATING NOTES


Regional Light Rail Spine No
Does project help complete regional light rail spine?

Ridership < 1,000


2040 daily station boardings

Capital Cost $243 — $260


Cost in Millions of 2014 $

Annual O&M Cost N/A I-405 BRT service to this inline


Cost in Millions of 2014 $ station is included in project E-
02b-SegA
Travel Time N/A
In-vehicle travel time along the project (segment)

Reliability Medium-High Relies on WSDOT to manage the


Quantitative/qualitative assessment of alignment/route in exclusive express toll lanes to provide
right-of-way speed and reliability

System Integration Medium-Low Medium-low number of existing


Qualitative assessment of issues and effects related to connections to daily transit connections in vicinity
existing local bus service and potential future integration opportunities of NE 85th at I-405 in Kirkland

Ease of Non-motorized Access Medium-Low Low intersection density providing


Qualitative assessment of issues and effects related to non-motorized non-motorized access with long
modes distances and large parcels as
barriers
Percent of Non-motorized Access 25-35%
Percent of daily boardings

Connections to PSRC-designated Regional Centers 0 centers


Number of PSRC-designated regional growth and
manufacturing/industrial centers served

Land Use and Development/TOD Potential


Quantitative/qualitative assessment of adopted Plans & Policies and Medium-Low Limited support in local and
zoning compatible with transit-supportive development within 0.5 mile regional plans; approx. 30% of
of potential stations land is compatibly zoned
Qualitative assessment of real estate market support for development
Medium-High Strong market support
within 1 mile of potential corridor

Density of activity units (population and employment for 2014 and Pop/acre = 2014: 8; 2040: 9
2040) within 0.5 mile of potential stations Emp/acre = 2014: 5; 2040: 12
Pop + Emp/acre = 2014: 13; 2040: 21

Socioeconomic Benefits
Existing minority / low-income populations within 0.5 mile of potential 22% Minority; 4% Low-Income
stations
2014 and 2040 population within 0.5 mile of potential stations Pop: 2014: 3,800; 2040: 4,600

2014 and 2040 employment within 0.5 mile of potential stations Emp: 2014: 2,700; 2040: 6,000
For additional information on evaluation measures, see http://soundtransit3.org/document-library

Sound Transit 3 Template Release date: December 4, 2015


Page 4 of 4

Вам также может понравиться