Академический Документы
Профессиональный Документы
Культура Документы
Construction has been part of our life since the beginning of human existence. Nowadays,
Construction section plays an important roles in the development of any nations. Thus, the
industry represents one of the most dynamic and complicated industry developments across the
globe. All modern civilization development will involve construction in varies form such as
building or roadway.
Construction industry is unique and complex. The complexity of the construction industry is
largely due to many parties involved including the owner or developer, the consultants, the
contractors, the subcontractors and many others. Each parties have their own role and
responsibility in order to complete a particular project. A client is the owner of the land who
engage a main contractor to oversee the construction site. A subcontractor, on the other hand, is
the contractor who deals with the main contractor to construct a specific aspect of the main
Generally, the main contractor will sublet part of their work to subcontractor due to their lack of
knowledge in some specialized work such as plumbing works and electrical works. Main
subcontractors can carry out specific works more effectively than main contractor (Markowitz,
2007).
The practice of subletting work to another contractor is not the sole privilege of the main
contractor. Due to the complexity of the modern construction industry, the subcontractor also
sublet their work to another lower-tier subcontractor. The phenomenon is known as the
multilayer subcontracting. For example, a main contractor can sublet his work to a concreting
then further sublet part or entire of their work to another third party and so on as presented in
Subcontracting is practiced more broadly in building construction project than in engineering and
industrial project. Malaysia, as a developing country, are having construction projects in every
urban area. The practice of subcontracting are widely practiced across every construction
Although subcontracting practices is generally beneficial to the main contractor and the
completion of the project, many problem also arises from the subcontracting practices.
Nonetheless, the issues regarding subcontracting are rarely recognized and dealt with. As a
consequence, some projects are not finished on time or on assigned budget due to subcontracting
issues. In the worst case, the project will fail or unable to finish. Thus, it is very important to
The main purpose of this research is to explore and minimize the issues regarding subcontracting
Subcontracting has been a tradition for a long time in construction industry. It is impractical to
complete a project without subletting part of the work to subcontractors because different skills
subcontracting practices also introduce certain issues that affects both construction quality and
Subcontracting is both beneficial and risky to the success of a project because the performance of
the subcontractor will drastically impact the performance of the project. Lew at al. (2012)
claimed that the ability of main contractor to appoint a suitable subcontractor is essential to the
success of a construction project. The statement also been reinforced by Mbachu (2008),
conforming that subcontractors is the major factor to the ability of main contractor to complete
In Malaysia, subcontracting practices is associated with many issues. One of the biggest issue
arising from subcontracting is payment problem. Main contractor often withheld a high
percentage of subcontractor’s work done as a retention money. Other than that, the final payment
due to subcontractor is often delayed by main contractor. As a result, subcontractor will face
Safety issues is also a major problem arising from subcontracting whereby subcontractor practice
a poor safety and health measure at the construction site. The construction sector has always
been regarded as one of the most hazardous sector compared to other sectors (Rozanah, 2015).
Safety precaution is mandatory in all construction activities from excavation work to structural
works. Nonetheless, subcontractors tend to ignore the safety precaution in order to gain extra
profit. As a consequence, construction site accident occurs in almost every project. Table 1.1
shows the statistic done by the Department of Occupational Safety and Health (DOSH) on fatal
accident in year 2018. The construction sector has recorded 232 accidents, which is among the
Table 1.1: Malaysia Occupational Accidents Statistics by Sector Year 2018 (DOSH, 2018)
Non-
Permanent
SECTOR Death Permanent Total
Disability
Disability
Hotel and Restaurant 2 1 120 123
Utilities (Electricity, Gas, Water and Sanitary
5 168 173
Service)
Finance, Insurance, Real Estate and Business
5 22 190 217
Services
Construction 8 118 106 232
Transport, Storage and Communication 1 12 124 137
Manufacturing 197 62 2969 3228
Wholesale and Retail Trade 3 1 69 73
Public Services and Statutory Authorities 1 9 48 58
Mining and Quarrying 3 4 34 41
Agriculture, Forestry and Fishery 14 26 709 749
TOTAL 234 260 4537 5031
Communication issues arises with subcontracting especially when there is two or more layer of
subcontractor is involved. As the layer of subcontracting increases, the harder it is to pass down
order or information. In the fast paced nature of construction industry, communication issues will
severely impact the work progress and cause delay in a construction project.
The involvement of subcontractors in the construction industry presents challenges that will
affect the project’s performance in many ways. Therefore, to tackle the problem as mentioned
i) What are the issues associated with subcontracting practices in construction industry
of Malaysia.
ii) What are type of subcontractor and why do main contractor sublet work in
iii) What are the necessary action that needed to be taken in order to minimize the issues
Malaysia.
ii) To identify the type of subcontractor and why main contractor sublet work in
iii) To propose the necessary actions that needed to be taken in order to minimize the
To complete the research, main contractor and subcontractor will be selected. Both of the parties
are directly responsible for the construction process and directly involved in the subcontracting
issues. Main contractor is the client who contractually engage with the subcontractor to perform
part of his contracted work the project owner or developer. Hence, the main contractor shall deal
This research will be focusing on minimizing the issues arising from subcontracting practices in
construction industry of Malaysia. Thus, the research data will be collected primarily in the
The finding of this research will benefit two primary parties. The first party, consisting of the
builders including the main contractor and subcontractor. With minimum subcontracting issues,
they can proceed their work with minimum hindrance. As a result, they can finish their contract
work in time, with minimum cost and produce good quality. The second party who will be
benefited from this research is the owner of the project/building. By minimizing the
subcontracting issues, the completed building can be handover back to the owner on time with
higher quality assurance. The study will help them to uncover critical areas of subcontracting
issues and help them to implement an appropriate management process so that the subcontracting
2.1 Introduction
In order to conduct a research, it is important to review past studies that were been done by
others. The previous chapter has overviewed and explained the practice of subcontracting. Other
than that, the problems which would arise from subcontracting have also been identified. This
chapter will further discuss the topic on the problem associated with subcontracting, type of
subcontractors, reason for applying subcontracting and the possible way to minimize
The first issue that arises from subcontracting practices is payment issue. Adnan, Faisal &
Bassam (2012) identified that delay in contract payment is one of the major causes of problems
between main contractor and subcontractor. A local culture of Malaysia’s local culture is that
subcontractor shall only be paid when the main contractor has received payment from the client.
The phenomenon is known as the “back-to-back payment”. In local industry practice, the back-
to-back payment clause is often included in the provision of their subcontract by the main
contractor. Mohamed Nor Azhari at el. (2014) stated that the back-to-back payment issue is more
relevant to nominated sub-contractor in case of main contractor does not received payment from
the client. As the main contractor delay in honoring payment to his direct subcontractor, all
layers of subcontractor will receive late payment as well (Samuel, 2011 & Munaaim, Dauurl and
Abdul-Rahman, 2007). The late or non-payment by the main contractor will have a serious effect
on subcontractor’s cash flow. A subcontractor may suffer from bankruptcy or become insolvent
from the cash flow problem. As a result, the completion of the project will be delayed.
Another issue arising from subcontracting practices is safety issue. Patrick et al. (2014) identified
that the practice of subcontracting had an adverse effect on the safety of site workers. As the
layer of subcontract increases, the subcontractor will gain lesser and lesser profit from the
contract. Thus, majority of subcontractor ignore site safety measure in order to save cost
(Charan, Sidney and Andrew, 2017). Patrick et al. (2014) observed that subcontractor often
intended to complete their work in the shortest possible time in order to receive a greater amount
of progress payment. To achieve the goal, subcontractor tends to work in excess hour and
eventually, closing their eyes on the safety measures. As a consequences, the risk of site accident
will increase. Pia and Nadezha (2015) claimed that site accident happens more frequently in
specialist subcontracted work such as piling works because they are considered more dangerous
and hazardous.
Adnan, Faisal & Bassam (2012) claimed that communication issues will arise from
project client. When a decision is made by a consultant or project client, the decision will be
passed down to the main contractor in the form of work order or site instruction. Subsequently,
the main contractor will then issue another work order or site instruction to the subcontractor
who actually does the work. When the layer of subcontracting increases, the process will be
repeated multiple times, resulting in a lengthy communication chain. The same lengthy process
will be applied when the subcontractor intend to obtain an approval or respond to any site issues.
Other than that, a communication error might occur when the information is being transferred to
another party. For example, a main contractor might misunderstand the instruction from
will be happened. Wang et al. (2018) observed that poor and lengthy communication chain is one
Domestic subcontractor is the type of subcontractor who is selected and appointed by the main
contractor himself. The domestic subcontractor enters into contract with the main contractor to
perform part of the main contractor’s work. The main contractor is free to appoint any
subcontractor according to his own selecting criteria. The main contractor remains fully
Nominated subcontractor is the type of subcontractor who is selected and recommended by the
project owner (client), but enters into contract with the main contractor. The client will have the
freedom of choosing which subcontractor to perform a specific work. After that, the client will
nominate the subcontractor to the main contractor and instruct the main contractor to employ the
nominated subcontractor. Thus, the main contractor will held no responsibility to the work
One of the main reason to practice subcontract is to be access to their specialist skill.
Construction industry is large and unique because all firms offer different service of works. It is
very rare for one contractor to have his own in-house work force who can perform every tasks
work. For example, a piling contractor is an expert of piling foundation who is familiar with all
the work method, safety measures and authority requirement. A specialist contractor can perform
the work more efficient than a general contractor, leading to a lower cost, higher quality and
Another reason to practice subcontract is due to the shortage in resources of the main contractor.
The two major resources that was needed by a contractor to perform a work is labor and plant.
However, it is almost impossible for a main contractor to own, operate and maintain all kinds of
equipment and plant (Choudhry et al., 2012). Besides, Choudhry et al. (2012) also mentioned
that a main contractor is usually incapable of hiring skilled workers in every specialist field to
complete a building project. For instance, a piling work will require the use of heavy piling and
crane machine. If a main contractor were to own a piling machine, the plant will used during
foundation work and will be idling for the rest of the project duration. Thus, it is impractical to
own the machine for a long term period due to its high maintenance fee. As a result, it is
Samer and Assem (2013) stated nomination of subcontractor is having various benefit to the
project client. Firstly, the main reason for a project client to nominate a subcontractor is to allow
the project client to proceed with main contractor tender process when part of the works is not
fully developed. Other than that, the project client can have total control over the cost, time and
quality due to earlier involvement of nominated subcontractor to assist the consultant in the
design stage. Samer and Assem (2013) also found that the nomination subcontractor’s
involvement will shorten the time of main contractor to submit his tender because the main
With the increases of subcontracting layer, various issues will be faced including the
communication issue which is the direct factor of project delay. Choudhry et al. (2012) suggested
that by reducing the number of subcontracting layer, the communication issue arising from
communication chain between parties will be shorten. As a consequences, less time will be
consumed when issuing instruction and less error will be made when conveying information.
Besides, limited layer of subcontracting can also allow a higher profit margin for the bottom
layer subcontractor who perform the work. Thus, the subcontractor can allow more cost in safety
contractor’s capability, resources, capacity, past record of completed projects and various other
criteria. Hesaham, Remon and Enas (2018) stated that the conventional appointment of
In Malaysia, standard form of contract such as PAM subcontract 2018 is commonly used
between main contractor and nominated subcontractors. Contrarily, domestic subcontractors are
normally bind by a simple contract drafted by the main contractor which have only included
some basic provision such as retention money and completion date. Samuel (2011) & Choudhry
et al. (2012) recommended that a standard form of contract between contractor and subcontractor
shall be adopted in order to minimize payment issue arising from subcontracting practices. All
form of standard contract such as PAM subcontract 2018 and PDW 203A provides provision on
payment and non-payment such as procedure and timeframe to honour payment and the
subcontractor will then result in the breach of contract so that subcontractor has his right to
suspend his work or determine his own employment. Furthermore, all standard form of contract
available in Malaysia does not contain the back-to-back payment clause which has been used by
Hinze, J., and Tracy, A. (1994). “The contractor-subcontractor relationship: The subcontractor’s
Gainesville, FL.
Clough, R., and Sears, G. (1994). Construction contracting, Wiley, New York.
Choudhry, R., Hinze, J., Arshad, M. and Gabriel, H. (2012). Subcontracting Practices in the
138(12), pp.1353-1359.
performance in the construction industry,” Construction Management and Economics, vol. 26,
Kigo, P.W., 2007, “A study into the effects of selection and management of the nominated
accident-statistics/by-sector/2099-occupational-accidents-statistics-by-sector-2018 (Accessed: 18
July 2019)