Вы находитесь на странице: 1из 5

Comparison of Cost and Time Performance

of Design-Build and Design-Bid-Build


Delivery Systems in Florida
R. Edward Minchin Jr., M.ASCE 1; Xiaoxiao Li 2; Raja R. Issa, F.ASCE 3;
and Gary G. Vargas 4
Downloaded from ascelibrary.org by ROBERTSON ENGINEERING & on 09/07/13. Copyright ASCE. For personal use only; all rights reserved.

Abstract: The choice of construction delivery system is one of the most important decisions that a public highway agency will make
with regard to a highway, bridge, or transit construction project. Although several research projects have been conducted on the subject
of comparing costs and project duration, there has been no study that statistically analyzes these factors specifically for transportation
projects, much less one that eliminates the largest variable of all: different public agencies. The objective of the research reported in
this paper was to determine which of two delivery methods, design-bid-build (DBB) and design-build (DB), delivers highway and bridge
construction projects at the lowest cost and in the shortest time period, and to back up the findings with a rigorous statistical analysis of the
data. Data were taken from the databases of the Florida Department of Transportation (FDOT) and arithmetically and statistically compared
through Levene’s test, the independent samples t-test, the Welch unequal variances t-test, and the Mann-Whitney U test. In fact, this paper’s
unique contribution is its rigorous statistical analysis of data gathered directly from FDOT, comparing the performance of the two delivery
systems in Florida over a finite period of time. In this comparison, DBB projects performed significantly better in terms of cost according
to all statistical and arithmetic tests. DBB projects did not compare as favorably in terms of duration. Some tests showed a statistically
insignificant advantage to the use of DB over DBB, whereas other tests showed no difference between the two. Other public agencies can
replicate the research and determine whether the same findings hold true in their situation. DOI: 10.1061/(ASCE)CO.1943-7862.0000746.
© 2013 American Society of Civil Engineers.
CE Database subject headings: Design/build; Bids; Project management; Costs; Florida; Comparative studies.
Author keywords: Delivery system; Design-bid-build; Design-build; Project; Cost; Duration; Comparison; Contracting.

Introduction systems was in compliance with the states’ own contract procure-
ment statutes.
All construction was once performed by using a form of the design- The allure for fast-track construction processes like DB was a
build (DB) delivery system. In the 1920s and 1930s, knowledge result of growing impatience on the part of the public with the
of construction materials and methods grew at a rapid pace as a lengthy process for highway and bridge construction that usually
result of significant research, mostly sponsored by the American accompanies the DBB delivery system. Florida began their DB pro-
Association of State Highway Officials, now known as AASHTO. gram with a state-funded $50 million pilot program in the early
With this new knowledge came specialization, and with speciali- 1990s, hoping to convince the Federal Highway Administration
zation came the design-bid-build (DBB) project delivery system, (FHWA) to grant federal funds for the construction of highways
which dominated horizontal construction in the US for decades. and bridges using the DB delivery system. The pilot program
In 1998, it became easier to procure federal funding for projects was successful, and in 1996 FDOT received federal funds to use
by utilizing alternative delivery systems if the use of those delivery the DB system for the first time. Since 1996, DB has become a
commonly used tool for the construction of Florida’s highways
1
Rinker Associate Professor of Construction, Rinker School of Building and bridges.
Construction, Univ. of Florida, 304 Rinker Hall, Gainesville, FL 32611 The objective of the study was to compare the performance of
(corresponding author). E-mail: minch@ufl.edu the two most used delivery systems employed for highway and
2
Graduate Assistant, Cornell Univ., 1601 Hasbrouck Apts., Ithaca, bridge construction by FDOT. This was accomplished by a rigorous
NY 14850. E-mail: xl423@cornell.edu
3
Holland Professor of Construction, Rinker School of Building
statistical analysis of data gathered directly from the FDOT website.
Construction, Univ. of Florida, 304 Rinker Hall, Gainesville, FL 32611. Preliminary estimate values, contract award price, actual cost, origi-
E-mail: raymond-issa@ufl.edu nal contract duration, and final duration of completed FDOT high-
4
Senior Project Manager, Balfour Beatty Construction, 1020 Cultural way and bridge projects, chosen at random, comprised the data
Park Blvd., Cape Coral, FL 33990. E-mail: gvargas@balfourbeattyus that were gathered and analyzed; a comparison of these represents
.com the questions of the study. Levene’s test, the independent samples
Note. This manuscript was submitted on July 24, 2012; approved on t-test, the Welch unequal variances t-test, and the Mann-Whitney
May 29, 2013; published online on June 1, 2013. Discussion period open
until December 23, 2013; separate discussions must be submitted for in-
U tests were all performed on the data. The specific data were
dividual papers. This paper is part of the Journal of Construction Engi- chosen because these are the most important parameters, outside
neering and Management, © ASCE, ISSN 0733-9364/04013007(5)/ of quality, for measuring the effectiveness of the two project deliv-
$25.00. ery systems.

© ASCE 04013007-1 J. Constr. Eng. Manage.

J. Constr. Eng. Manage.


Literature Review components of construction, which requires the agency to form
a more comprehensive method to ensure the quality of the work.
Several early studies found that DB outperformed DBB in cost A survey from the report demonstrated the different ways in which
and schedule performance (Songer and Molenaar 1997; Molenaar state transportation agencies have successfully controlled quality
and Songer 1998; Konchar and Sanvido 1998). by focusing on all aspects of the construction phases; however,
Gransberg and Senadheera (1999) conducted a national survey this does not seem to be the case for all agencies. In the same
of 15 DOTs; the results showed DB to be the alternative method year, Gransberg and Windel (2008) pinpointed the issue of com-
commissioned by all surveyed DOTs. Through further analysis, the municating the quality requirements of public agencies on DB
authors were able to identify three different systems that were used projects. The study found that some owners tend to rely on the
to advertise and award DB. The low-bid, adjusted score, and best qualification evaluation process rather than being proactive on
value systems were compared to identify their strengths and weak- the issue. There are still many improvements that are not yet used
nesses. The key was found to be matching the proper method with by most agencies that can enhance the performance of DB; many
Downloaded from ascelibrary.org by ROBERTSON ENGINEERING & on 09/07/13. Copyright ASCE. For personal use only; all rights reserved.

the appropriate project type. This paper educated the team about agencies still use traditional DBB exclusively or have not utilized
different aspects of DB.
DB to its full advantage. These papers, written much later than
Molenaar et al. (1999) studied the emergence of DB into the
some of the others, provided education on the newer discoveries
public segment of the industry as it replaced traditional DBB.
in the DB process.
Their work analyzed each party’s responsibility with regard to
Hale et al. (2009) compared the performance of DBB and DB
the delivery system and explains the procurement process and the
to determine whether one project delivery method is superior with
structure of this particular method. This paper, too, educated the
regard to time and cost. Similar military buildings were used as
authors about the DB process.
two samples of projects delivered with each of the two delivery
Chan et al. (2002) sought specific project conditions that
methods. DB projects were proven to be superior in performance
could help to increase success rates of projects when using DB.
The author pointed out that measures of success are defined by in almost every measure.
Touran et al. (2009) published a paper on an evaluation process
three factors—time, cost, and quality—but believed that a more
comprehensive metric should be established. This paper solidified that is able to help agencies to identify the suitable delivery sys-
the understanding that time and cost make up two-thirds of the tem for use in specific projects. The paper identifies 24 key con-
measures for comparing delivery systems. cerns that will determine the ideal delivery system. The 24 key
Ibbs et al. (2003) provided a comprehensive analysis of 67 concerns were studied by the authors and helped to frame the
global projects from the database of the Construction Industry study, although the aim of this research was not to develop a guide
Institute. The results showed that DB projects may not provide or model for choosing the best delivery system for a given set of
all of the benefits to project performance that advocates claim. circumstances. No reports of research performed or data compared
The study found that time saving was a definitive advantage of DB or compiled by any public transportation agency was found in the
project delivery, but the positive effects of cost and productivity literature search.
changes were not convincing. This paper influenced how this basic
research question was stated and how data were gathered and
analyzed. Its conclusions, which were different from most similar Method of Research
studies, aided this study by freeing researchers from the absolutes
that can corrupt a research effort. The aim of the research was to gain a better understanding about
Shr and Chen (2004) studied the growing popularity of the relative performances of the DBB and DB delivery systems.
incentive/disincentive bidding for highway construction. This To better understand the performance of the DBB system, the
method was found to shorten the contract time by making it diffi- Florida Department of Transportation (FDOT) was asked to pro-
cult for the contractor to not accelerate the project. The authors vide two statistics that are closely tied to the potential success of
developed a quantitative model to establish reasonable incentive any project: cost and duration. These measures were shown be-
or disincentive rates based on construction cost and time. However, cause the literature shows that these, along with quality (materials
like the low bid method, incentive/disincentive contracting may and workmanship), are the most important measures to most public
cause the quality of the final product to decline if the incentives are transportation agencies (Ibbs et al. 2003; Chan et al. 2002).
aimed only at time reduction. This paper provided education on Within the cost category, three components were compared:
ways that agencies influence contract duration. original cost estimate, awarded bid amount, and final cost of the
El Wardani et al. (2006) studied a total of 76 DB projects and project. The duration category focused on the original contract
identified correlations between the procurement processes and the duration and the final duration. Thirty projects, using each of the
overall performance of the projects. The studied procurement meth- two delivery systems (60 projects total), were chosen at random
ods were sole source, qualification based, best value, and low bid from the FDOT database. Each project was $7 million or greater
selection. This study underpins the concept that the study of deliv- in contract amount and constructed between 2002 and 2010.
ery systems is important and relevant in improving the quality of Almost all of these projects included both bridge and asphalt high-
transportation construction. way paving work. This allows for a comparison between the two
Scott (2006) pointed out the problem associated with low bid in delivery systems based on the two major types of work done by
DB: instead of receiving the benefits of cost control, most of the FDOT (bridges and asphalt paving) for the whole cost range of
time it will result in a decrease in the quality of the final product. DB projects awarded by FDOT.
This paper illustrated how nuances and tweaks of an established
system like DB can result in different outcomes than might have
otherwise been experienced. Preliminary Data Analysis
Gransberg et al. (2008) addressed the issue of quality assur-
ance concerning DB as it relates to transportation projects. One of First, a simple preliminary analysis was conducted on each set of
the disadvantages of DB is the lack of control over the detailed data. The preliminary analysis was cursory and arithmetic in nature.

© ASCE 04013007-2 J. Constr. Eng. Manage.

J. Constr. Eng. Manage.


Design-Bid-Build Projects the final cost listed. Therefore, those projects were not included in
the statistical analysis. Outliers in the remaining group were the
Among the 30 projects investigated, the largest difference listed
same two projects. Once the outliers were removed, the SD became
on any project between the original cost estimate and the awarded
amount was 130.21%. The SD for the amount of error between 103.06% and the average error fell to 45.30%.
original cost estimates and the awarded amounts is 32.68% and In the comparison between the contract duration and final du-
the average error is 12.55%. The same analysis was conducted ration, nine of the 30 samples did not have the final duration listed,
to compare the original cost estimates and the final costs. The data and thus, were not included in the statistical analysis. The project
show an average error of 20.42% and a SD of 40.14%. The largest with the greatest difference had a 92.50% discrepancy. The average
difference for this set of data was 154.64%, which came from the error was 20.20%, and the SD was 25.40%. Unlike the DBB proj-
same project that provided the largest difference between the origi- ects, which all exceeded the contract duration, there were three
nal cost estimate and the awarded amount. The SR 826/Palmetto projects that were completed early with DB, including one with a
difference of −17.20% (all calculations were based on the original
Downloaded from ascelibrary.org by ROBERTSON ENGINEERING & on 09/07/13. Copyright ASCE. For personal use only; all rights reserved.

Expressway South project, which showed the largest difference


in both categories, seems to be the only extreme outlier for this estimated cost and contracted duration).
set of data. The statistics are greatly reduced when this data point In terms of cost, the results of the preliminary analysis indicated
is removed. that DBB is the more reliable method. The discrepancies among the
The amount of error between actual durations and contract original estimate, awarded bid, and final cost are significantly lower
durations was also studied. The largest difference was 86.00%. than those of DB. The comparison of duration between the systems
On average, the projects exceeded the contract duration by yielded minimal differences.
23.00% with a SD of 18.40%. Unlike the cost analysis, which
sometimes had a negative error value, indicating completion within
budget, all the projects exceeded their contract durations by at Statistical Analysis
least 2.74%.
An independent samples t-test was conducted to compare the per-
cent error between the original estimate and the awarded contract
Design-Build Projects amount for DB and DBB highway construction projects. The mean
FDOT provided data on 30 projects that occurred between the value and SD of the percent error between original estimate and
years of 2002 and 2010 and had either original estimates or original awarded contract amount were calculated as shown in Table 1 for
contract amounts exceeding $7 million, including original cost DB (mean ¼ 108.47, SD ¼ 284.03) and DBB (mean ¼ 12.55,
estimate, awarded bid amount, final cost, original contract duration, SD ¼ 33.24) highway construction projects. As shown in Table 2,
and final duration. the variances of the DB and DBB projects were not the same; the
In all of the provided DB projects, the largest variation between significance level of the Levene’s test was p ¼ 0.004 (<0.05) with
the original cost estimate and awarded amount was 1,380.00% tð31.905Þ ¼ 1.897, p ¼ 0.067 (>0.05) (two-tailed). The magni-
more than the estimated cost. This was followed by an 807.70% tude of the differences in the means [mean difference ¼ 50.575,
difference on another project. As a result of these two outliers 95% confidence interval (CI): −7.103 to 198.957] was moderate
in the data, the SD for the error between the original cost estimates (eta squared ¼ 0.057).
and the awarded amounts was 284.00% and the average error was Similarly, an independent samples t-test was conducted to
108.50%. Once the two outliers were removed, the SD became compare the percent error between the original estimate and final
95.70% and the average error was reduced to 42.80%. When com- contract amount for DB and DBB highway construction projects.
paring the original cost estimates to the final cost, the SD for The mean value and SD of the percent error between original es-
the amount of error was 324.30% and the average was 135.40%. timation and final cost were calculated for DB (mean ¼ 135.371,
However, in this group of comparisons, nine projects did not have SD ¼ 324.304) and DBB (mean ¼ 20.423, SD ¼ 40.138) high-
way construction projects. The variances of the DB and DBB proj-
ects were unequal; the significance level of the Levene’s test was
Table 1. Mann-Whitney U Test Statistics
p ¼ 0.004 (<0.05) with tð22.517Þ ¼ 1.690, p ¼ 0.105 (>0.05)
Error between Error between Error between (two-tailed). There were no significant differences between the
original estimate original estimate contracted percent error of the original estimate and the final cost of the DB
and awarded and final duration and DBB projects. The magnitude of the differences in the means
contract contract and final (mean difference ¼ 114.948, 95% CI: −25.925 to 255.821) was
Parameter amount (%) amount (%) duration (%)
moderate (eta squared ¼ 0.053).
Mann-Whitney U 401.000 275.000 278.000 As stated, the authors removed 9–11 projects from the DB sam-
Wilcoxon W 866.000 740.000 554.000 ples as outliers or due to lack of project duration data. On the other
z −1.115 −1.256 −1.202 hand, the DBB sample had just one outlier. This made the sam-
Asymptotic 0.265 0.209 0.229
ple sizes unequal. In addition, it was found that the variances
signature (2-tailed)
of DBB and DB samples were not equal for two of the metrics.

Table 2. Levene’s Test for Equality of Variances: Independent Samples Test for Original Estimation and Awarded Contract
95% CI of the
difference
Signature Mean Standard error
Status of variances F Signature t df (2-tailed) difference difference Lower Upper
Equal variances 9.171 0.004 1.837 60.000 0.071 95.927 52.215 −8.517 200.372
No equal variances 1.897 31.905 0.067 95.927 50.575 −7.103 198.957
Note: F = F-statistic; t = t-statistic; df = degrees of freedom.

© ASCE 04013007-3 J. Constr. Eng. Manage.

J. Constr. Eng. Manage.


This is problematic because the t-test is not robust toward dif- set into account (Mann-Whitney) shows no significant difference
ferences in variance and unequal sample sizes at the same time. between the two delivery systems in time or cost.
One potential solution is to randomly select an equal sample size.
Another possible solution is to use another statistical test such as
Welch’s test, which is not sensitive to equality of the variance and Conclusions
sample size.
Another independent samples t-test was conducted to compare In this comparison, DBB projects performed significantly better
the percent error between the original and awarded contract amount in terms of cost and not quite as well in terms of duration. The
for DB and DBB highway construction projects. SPSS, version 21, preliminary arithmetic analysis indicated that the DBB method
was used because it performs a Student’s t-test and a Welch un- outperformed the DB method for contractors’ performance in meet-
equal variances t-test simultaneously and provides output for both ing contract cost and for the accuracy of preliminary cost estimates;
(Ruxton 2006). the duration comparison among the systems showed minimal dif-
Downloaded from ascelibrary.org by ROBERTSON ENGINEERING & on 09/07/13. Copyright ASCE. For personal use only; all rights reserved.

The mean value and SD of the percent error between original ferences and a slight edge for DB.
and awarded amount were calculated for DB (mean ¼ 108.47 To further understand the data obtained at this level, Leven’s
SD ¼ 284.03) and DBB (mean ¼ 12.55 SD ¼ 33.24) highway Test and an independent samples t-test were conducted to com-
construction projects. The variances in the percent error between pare the percent error between the original estimation and awarded
the original and awarded contract amount for DB and DBB projects contract amount for DB and DBB highway construction proj-
were not the same: the significance level of the Levene’s test was ects. The magnitude of the differences in the means (mean
p ¼ 0.004 < 0.05. difference ¼ 50.575, 95% CI: −7.103 to 198.957) was moderate
There was no significant difference between the percent errors (eta squared ¼ 0.057) in the percent error between original cost
for DB and DBB projects [tð31.905Þ ¼ 1.897, p ¼ 0.067 > 0.05 estimation and awarded contract price. Similarly, with the amount
(two-tailed)]. The magnitude of the differences in the means of error that occurred between the original estimate and final
(mean difference ¼ 50.575, 95% CI: −7.103 to 198.957) was mod- contract amount, the magnitude of the differences in the means
erate (eta squared ¼ 0.057) (Pallant 2011). (mean difference ¼ 114.948, 95% CI: −25.925 to 255.821) was
A nonparametric Mann-Whitney U test does not require data moderate. The magnitude of the differences in the means for the
normality. Nonparametric Mann-Whitney U tests (Pallant 2011) original estimate and final contract amount (mean difference ¼
were conducted to test for differences among the percent error −0.299, 95% CI: −15.05 to 9.08) was very small (eta squared ¼
between the following parameters for DB and DBB highway 0.048). Therefore, the statistical analysis mostly confirmed the
construction projects: original estimate and awarded contract conclusions of the preliminary finding (arithmetic analysis) that
amount; original estimate and final contract amount; and contracted the DBB method was more consistent and reliable in matters of
and final duration. The results of the Mann-Whitney U tests are cost than the DB method. There was a slightly, although signifi-
shown in Table 1. The results revealed no statistically significant cantly, better showing by DB in the mean of the percent error in
difference in the percent error between the original estimate and the group statistics for contracted duration versus final duration.
the awarded contract amount for DB (median ¼ 3.03, n ¼ 32) Because of concerns that the t-test is not robust toward dif-
and DBB (median ¼ 6.01, n ¼ 30): U-statistic (the area ‘under’ ferences in variance and unequal sample sizes at the same time,
the receiver operating characteristic 〈http://en.wikipedia.org/wiki/ Welsh’s test was executed. Welsh’s test examines the same statis-
Receiver_operating_characteristic〉 curve) U ¼ 401, z-statistic tical issues, but is not affected by data sets with unequal sample
(normal distribution with a mean of ‘zero’) z ¼ −1.115, p-value sizes and differences in variance at the same time. Mann-Whitney
p ¼ 0.265 > 0.05, coefficient of correlation r ¼ 0.14. The dif- also examines the same statistical issues and is not affected by a
ference in the n-values (32–30) was because two of the DBB lack of normality in the data sets. Therefore, because the normality
values were more than three SD from the mean and eliminated of the data was in question, the Mann-Whitney test was executed.
as outliers. Similarly, the results indicated no significant difference The results of all five tests (including the arithmetic analysis) were
between the original estimate and final contract amount for DB not contradictory regarding the differences in the performance of
(median ¼ 16.69, n ¼ 23) and DBB (median ¼ 11.95, n ¼ 30): the two delivery systems in the areas of cost and time. The tests
U ¼ 275, z ¼ −1.256, p ¼ 0.209 > 0.05, r ¼ 0.17. Finally, the showed little to no difference between the two systems in the area
results also indicated no significant difference between the con- of time (duration) performance. This does not mean that the DBB
tracted and the final project duration for DB (median ¼ 12.56, system gets the project from conception to operation as quickly
n ¼ 23) and DBB (median ¼ 18.25, n ¼ 30): U ¼ 278, as DB. The data do not necessarily indicate that to be the case.
z ¼ −1.202, p ¼ 0.229 > 0.05, r ¼ 0.17. The difference in the The data do indicate that, given the project duration assigned to
n-values (30–23) in this case was because, in addition to the each project at the time that construction begins, the performance
two outliers in the previous (original versus awarded) test, of DB is the same or slightly better than DBB (depending on the
nine DBB project files in the FDOT database did not include a test results consulted) at completing the project within the assigned
final (actual) cost. project duration. Regarding project cost performance, the DBB
Regarding time (duration) performance, the statistical tests method was shown to be (depending on the test results consulted)
showed little to no difference between the two systems. This does the same or superior to the DB method, both in preliminary esti-
not mean that the DBB system gets the project from conception to mate versus award price and award price versus final (actual) price.
operation as quickly as DB. Given the project duration assigned The test that theoretically takes all of the quirks of the data set into
before each project, the performance of DB is the same, or slightly account (Mann-Whitney) shows no significant difference between
better than DBB (depending on the test results consulted), at com- the two delivery systems in time or cost.
pleting the project on time. Regarding cost, the DBB method was This paper’s unique contribution is its rigorous statistical analy-
shown to be (again, depending on the test results consulted) the sis of data gathered directly from FDOT over a finite period of time,
same or better than the DB method, both in preliminary estimate comparing the performance of the DB and DBB delivery systems
versus award price and preliminary estimate versus final (actual) in Florida. Several research projects have been conducted on the
price. The test that theoretically takes all of the quirks of the data subject of cost and project duration comparisons; there has not,

© ASCE 04013007-4 J. Constr. Eng. Manage.

J. Constr. Eng. Manage.


until now, been a study that statistically analyzes these factors spe- El Wardani, M., Messner, J., and Horman, M. (2006). “Comparing procure-
cifically for transportation projects. This study also eliminates the ment methods for design-build projects.” J. Constr. Eng. Manage.,
largest statistical variable of all: different public agencies. 132(3), 230–238.
Several previous studies have concluded that DB outperformed Gransberg, D. D., Datin, J., and Molenaar, K. (2008). NCHRP synthesis
DBB in cost and schedule performance (Songer and Molenaar 376: Quality assurance in design-build projects, Transportation Re-
search Board of the National Academics, Washington, DC.
1997; Molenaar and Songer 1998; Konchar and Sanvido 1998;
Gransberg, D. D., and Senadheera, S. P. (1999). “Design-build contract
Hale et al. 2009). This study only corroborates the schedule part
award methods for transportation projects.” J. Transp. Eng., 125(6),
of these findings, which may be explained by the fact that three 565–567.
of these studies were conducted 15 years ago. Perhaps since the Gransberg, D. D., and Windel, E. (2008). “Communicating design quality
introduction of DB, those performing DBB projects have learned requirements for public sector design/build projects.” J. Manage. Eng.,
how to do things better by observing or participating in DB proj- 24(2), 105–110.
ects. Another possible explanation is that all four of these studies Hale, D., Shrestha, P., Gibson, G., and Migliaccio, G. (2009). “Empirical
Downloaded from ascelibrary.org by ROBERTSON ENGINEERING & on 09/07/13. Copyright ASCE. For personal use only; all rights reserved.

used data from projects other than transportation construction. comparison of design/build and design/bid/build project delivery
It was later than 1998 when DB was widely used for transportation methods.” J. Constr. Eng. Manage., 135(7), 579–587.
construction in the US. FDOT was and is a leader in the DB move- Ibbs, C., Kwak, Y., Ng, T., and Odabasi, A. (2003). “Project delivery
ment and FDOT had its first DB project funded by the FHWA in systems and project change: Quantitative analysis.” J. Constr. Eng.
1996, when these studies would have been in the data gathering Manage., 129(4), 382–387.
stage. The study by Hale et al. (2009) used military buildings. Konchar, M., and Sanvido, V. (1998). “Comparison of US project delivery
Finally, not all of the literature points to superior performance systems.” J. Constr. Eng. Manage., 124(6), 435–444.
by DB. Ibbs et al. (2003), in a later study, agreed with the findings Molenaar, K. R., Songer, A., and Barash, M. (1999). “Public-sector
design/build evolution and performance.” J. Manage. Eng., 15(2),
of this study; that is, with the superior performance by DB in sched-
54–62.
ule performance, but not in cost performance.
Molenaar, K. R., and Songer, A. D. (1998). “Model for public sector
design-build project selection.” J. Constr. Eng. Manage., 124(6),
Limitations and Recommendations 467–479.
Pallant, J. F. (2011). SPSS survival manual, 4th Ed., McGraw-Hill,
A future study utilizing more data is recommended. Although sets
New York.
of 30 are statistically relevant, more projects would assure a higher
Ruxton, G. D. (2006). “The unequal variance t-test is an underused alter-
degree of normality. Also, it was very difficult to collect all the data native to Student’s t-test and the Mann–Whitney U test.” Behav. Ecol.,
needed on projects. Nine of the 30 DB project data sets did not 17(4), 688–690.
include project duration. This can be overcome, perhaps, by selling Scott, S., III (2006). “Best-value procurement methods for highway con-
the research project to the agency with the point that the author struction projects.” NCHRP Rep. 561, Transportation Research Board
can continue to revisit the agency for more data to replace faulty of the National Academies, Washington, DC.
data such as these. It is recommended that, if possible, the study be Shr, J. F., and Chen, W. T. (2004). “Setting maximum incentive for
conducted using data from a single agency, as with this study. This incentive/disincentive contracts for highway projects.” J. Constr. Eng.
keeps the large variable of different agencies out of the study. It is Manage., 130(1), 84–93.
recommended that agencies other than FDOT replicate the study Songer, A. D., and Molenaar, K. R. (1997). “Project characteristics for suc-
and determine how the two delivery systems perform, relative to cessful public-sector design-build.” J. Constr. Eng. Manage., 123(1),
one another, in their states. 34–40.
SPSS version 21 [Computer software]. IBM Corporation, Armonk,
NY.
References Touran, A., Molenaar, K. R., Gransberg, D. D., and Ghavamifar, K. (2009).
“Decision support system for selection of project delivery method
Chan, A. P., Scott, D., and Lam, E. (2002). “Framework of success criteria in transit.” Transportation Research Record 2111, Transportation
for design/build projects.” J. Manage. Eng., 18(3), 120–128. Research Board, Washington, DC, 148–157.

© ASCE 04013007-5 J. Constr. Eng. Manage.

J. Constr. Eng. Manage.

Вам также может понравиться