Вы находитесь на странице: 1из 2

SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Visual Inspection of Pneumatic Test for Reinforcing Pads,
SAIC-A-2016 25-May-05 MECH-
Sleeves, or Weld-Plus-Ends Couplings
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Reinforcing Pads or Sleeves


(NOTE: A separate test is not required if the reinforcing pads or sleeves
A
are installed before pressure testing of the piping. Test is required for
pads or sleeves installed in hot tap installation.)

Re-inforcing pads that will require pneumatic test are provided with at
A1 Best Practice
least a 1/4" tapped vent hole.
A pneumatic test of 173 kPa (ga) (25 psi) shall be applied to the SAEP-311,
A2
reinforcing pad or ring after installation. Para. 3.8.8
The test pressure is then be reduced to 21 - 35 kPa (ga) (3 - 5 psi) for a SAEP-311,
A3
tightness test using a soap solution. Para. 3.8.8

B Weld-Plus-Plus Ends Coupling (SAEP-310)

SAEP-312,
B1 Both ends of the weld-Plus-Ends coupling are welded to the pipe. Para. 3.4.13
(Step 2)
SAEP-312,
B2 All of the thrust screw ends are welded over. Para. 3.4.13
(Step 2)

Apply a pneumatic test at 5 to 10 psig at each end of the coupling


through the top clamping screw holes, apply soap solution over all the SAEP-312,
B3 welds and check for leaks. Para. 3.4.13
(NOTE: Test Relief valve is not requirede for this test per G.I.-2.102, (Step 5)
Para. 5.5 )

C Inspection for leaks

All joints including welded shall be left exposed for visual leak detection SAES-L-150,
C1
during the strength test. Para. 7.3

Visual examination is done with sufficient safe access such that the
SAES-A-004,
C2 component to be inspected is in close proximity to the eye(24").
Para. 6.3.2
(ASME Sec V, Article 10, Para. I-1075 & Article 9, Para. T-952)
The joint/area to be inspected is properly illuminated by natural or
SAES-A-004,
C3 supplemental white light.
Para. 6.3.2
(ASME Sec V, Article 10, Para. I-1075 & Article 9, Para. T-952)
The bubble forming solution is compatible with the temperature of the
test conditions.
(NOTE: As a standard technique, the temperature of the SAES-A-004,
C4
surface of the part to be examined shall not be below Para. 6.3.2
40°F (4°C) nor above 125°F (52°C) throughout the
examination.) (ASME Sec V, Article 10, Para. I-1032 b & I-1072)

Page 1 of 2
SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Visual Inspection of Pneumatic Test for Reinforcing Pads,
SAIC-A-2016 25-May-05 WELD-
Sleeves, or Weld-Plus-Ends Couplings
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

The bubble forming solution is applied to the surface to be tested by


flowing, spraying, or brushing the solution over the examination area.
SAES-A-004,
C5 (NOTE: The number of bubbles produced in the solution by application
Para. 6.3.2
should be minimized to reduce the problem of masking bubbles caused
by leakage. ) (ASME Sec V, Article 10, Para. I-1073)

After application of bubble forming solution, there is no presence of


SAES-A-004,
C6 continuous bubble growth on the surface of the material in the region
Para. 6.3.2
under examination. (ASME Sec V, Article 10, Para. I-1076)

SAES-L-150,
C7 Pressure gages showed no loss in pressure.
Para. 5.2

REMARKS:

REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, (30 June, 2003)
2. SAEP-312, PLIDCO Weld+Ends Couplings, (31 January, 2005)
3. SAEP-311, Installation of Hot Tapped Connections, (29 January, 2003)
4. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (30 September, 2003)
5. ASME Sec V, Nondestructive Examination, (July 1, 2001)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 2 of 2

Вам также может понравиться