Date Time Audit Area Location Process/Activities Reference Document Auditors Auditees
1000-1030 OPENING MEETING (Meeting Room, TCF Office, Lot 86) ALL ALL
Subcontractor: - Documentation Mngmnt ( RFI Management, QC Reports ,Surveillance Report, NCR, Filling System) - Organization Chart
TCF Office / Site
1400-1600 Petromigas - QCF Mangement prior to Turnover completion - Project Specific Procedure
Verification Hazrin/
(Structural)
- Infrastructure Mangement at site operation area (Tools & Equipment with valid Calibration) - Inspection Report / QCF Auditor #2 Sugumaran
- Project specification as per ITP requirement and report traceability - Calibration Record & Certificate
- RAPID-P0014-0029-PMG-PRC-0001-0016
Storage/
Preservation/ - Record (Material Inspection & receiving/traceability & issuance). - Warehouse Management And Material Handling
TCF Office / Site Syahida/
1400 - 1600 Material
Verification
- Store maping, material segregation and inventory status - RAPID‐P0014‐0026‐PMG‐PRC‐0001‐0026 Auditor #3 Razali
Management &
- Scrap and Surplus Management & Control - Material Management Procedure Revision A
Traceability
- Material Protection & Preservation - Project Specific Procedure
- Welder List / Welder Performance - Daily Welding Report/ NEWS - Approved WPS Procedures
- Welding Document Records / WQT - QCF report and Test Package requirement - Approved ITP Welding / WQT / Piping / NDE
- QC/ NDE Report / Document Mngmnt - RFI Management - Records of DWR and NDE selection
28/3/2018
- Equipment Calibration - NEWS Database
Wednesday Welding & NDE
Management - SR & NCR Management - SCR & NCR Records
Zhou Jiulong
including - Test Package arrangement - Site Welding Consumable Control Procedure
TCF Office / Site (QCE-HQC)
1400 - 1600 interface with
Verification - Traceability of QCF - Welder List / Welder Pass
Auditor #4 Jonty (NEWS
NEWS
Interface)
28/3/2018 QA/QC Activities - Welder / Welding activities / Consumables Control / Quiver / Electrode House Mngmnt - Related WPS
Wednesday (Site Verification)
- Tracebility - WIB implementation, Material, Weld, & NDT - Inspection & Testing Equipment Calibration
- Material Protection & Preservation - Project Specific Procedure
- Infrastructure Mangement at site operation area (Calibration status & log)
TBA Auditors discussion, clarification, objective evidance compilation & Report Writing