Вы находитесь на странице: 1из 4

Hazard Identification & Risk Assessment & Control Management specific to Piling Operation

Hazard Potential effects Risk management or mitigation

Sequencing of piling work. Conflict with other parts of Plan for safe, practical and economic working, not just for time. Avoid return
the project construction visits for piling rigs if possible.
creating unsafe working
conditions.

Piles located in positions with Personal injury from falling Design the foundation so that the plan position of piles or alignment of the wall
restricted working space, e.g. debris, crushing. Unsafe allows adequate working space with and operational. Only in extreme
corners of site and adjacent to removal of guards or situations, and after, a controlled procedure may be implemented.
public areas outside the site. auger cleaners. Risk to
third parties.

Piling near to the top of slopes. Slope failure, rig/tripod Consider the requirements for adequate safe working space, exclusion zones
overturning. and storage areas. The physical limits of the designed platform should be
clearly defined on site. Evaluate the balance between optimum earthworks
Working in excavations. Access ramps and wall scheme and optimum pile foundation scheme.
props can impede working
space.

Inadequately Rig/tripod overturning, Ensure working platform is designed, constructed and maintained in
designed/constructed/maintained unsafe working conditions accordance with published guidance or other appropriate best practice. Specify
working platforms. for operatives. site investigation works to take account of the need for measuring near surface
soil properties required for design. Construct platform according to
specification, inspect regularly and maintain to original specification. Operate
proper procedures for excavations (e.g. for removal of obstructions) and
reinstatement.

Underground services. Personal injury or death, Enquiries with utility companies to establish presence of services. Arrange pile
loss of amenity, delay to positions to “bridge” over services. Instigate permit to dig/work systems.
project.

Unexploded explosive ordnance Personal injury or death, Undertake preliminary risk assessment and if possibility of UXO is identified
(UXO). damage to construction notify client of his CDM responsibilities should it appear they have not been
plant and/or surrounding discharged. Follow on with detailed assessment and risk mitigation. Implement
property, delay to project. UXO risk management strategy and emergency response plan.

Overhead services. Injury to workforce, Instigate appropriate method statements and lifting plans. Agree working
electrocution, fire, loss of clearances with utility companies. Utilise smaller/low headroom plant if

Page 1 of 4
Hazard Identification & Risk Assessment & Control Management specific to Piling Operation

Hazard Potential effects Risk management or mitigation

amenity, delay to project. required, possibly with a change of construction technique if technically
acceptable.

Working adjacent to major Plant or materials falling Instigate appropriate method statements and lifting plans. Agree working
highways or railways onto road or rail clearances with relevant authority. Utilise smaller plant possibly with a change
of construction technique if technically acceptable.

Static load tests using kentledge Dangers of working at Wherever technically feasible use reaction piles or other means of providing the
as the reaction for loading. height. reaction.

CFA auger changes. Personal injury. Limit number of pile sizes on one project where possible by varying pile lengths.

Hand tying of reinforcement Repetitive strain injuries. Use automated cage making equipment or tying tools.
cages.

Racking of/damage to Injury to operatives from Consider design of reinforcement cages to ensure adequate robustness for
reinforcement cages while lifting. falling steel bars. temporary lifting stresses. Consider provision of lifting rings etc.

Open pile bores or wall panel Operatives falling into Avoid leaving pile bores open, implement suitable protection measures such as
excavations, with or without open bore or excavation, barriers and life-jackets.
support fluid. injury and possible
drowning.

Diaphragm wall panel instability Instability of heavy plant at Ensure adequate slurry head above high groundwater level. Avoid excessive
prior to concreting. surface with potential for surcharge and/or ground borne vibration near panel.
overturning.

Displaced pile/panel support fluid Contamination of open Adequate containment by bunding and control by pumping and
during concreting. water courses. tanking/settlement tanks as necessary.

Contaminated spoil. Infection of piling Use displacement piling methods unless these are technically unsuited to the
operatives, contamination site soil conditions or performance requirements of the foundation.
of the site and the
surrounding area.

Ground water contamination. Damage to water Carry out foundation risk assessment. Consider increasing pile size or number
resources. of piles to allow piles to stop above water table

Page 2 of 4
Hazard Identification & Risk Assessment & Control Management specific to Piling Operation

Hazard Potential effects Risk management or mitigation

“Immediate” environmental Unacceptable levels of Determine acceptable levels of both effects that can be tolerated by the nearest
impact. noise and/or vibration, receptors (both human and non-human). Compare these with predicted levels
hearing damage to from piling techniques suited to the ground conditions and load bearing
operatives. requirements, remembering to take account of anticipated programme periods
and all ancillary operations. Enforce hearing protection zones. Use quiet
hammers or alternative non-percussive installation methods (e.g. contiguous
flight auger).

Excessive vehicle movements Traffic incidents, personal Piling techniques that reduce or eliminate spoil will reduce this risk.
on/off site. injury, air pollution, noise.

Flighting of soils during pile Damage to/instability of Consider the susceptibility of soils to flighting due to piling method or plant
installation. adjacent buildings. employed. Implement suitable monitoring/construction controls or alternative
piling methods or plant.

Incorrect retaining wall Excavation below design Ensure excavation sequence (including levels) is communicated to project
excavation sequence. depth leading to potential team.
wall failure.

Ground movements behind Damage/instability of Consider the effect of ground movements arising out of pile installation and wall
retaining walls. adjacent structures. excavation on adjacent structures. Consider if any monitoring is required.
Communicate any construction controls (including responsibilities) to project
team.

Pile trimming to cut-off level and Vibration white finger Correct use of mechanical pile croppers or other means of pile trimming that do
exposing of reinforcement. injuries. not involve the excessive use of hand-held tools.

Scabbling pile surface. Personal injury from flying Use pile concrete retardant to enable “lighter methods” of achieving scabbled
debris, vibration white finish to pile surface.
finger injuries.

Exposed ends of reinforcement Personal injury. Use protection caps on the bars after pile trimming and before placing
after pile trimming. foundation concrete.

Inadequate access to piles for Personal injury trips and Ensure safe access to pile head – avoid steep sides of excavations for pile
integrity testing. slips. caps –provide safe means of access and egress.

Page 3 of 4
Hazard Identification & Risk Assessment & Control Management specific to Piling Operation

Hazard Potential effects Risk management or mitigation

Congested reinforcement in pile Personal injury to integrity Ensure there is uncluttered access to pile heads at time of test. Plan for
caps around head of pile during testing operatives integrity testing to taken place between pile trimming and placing of pile cap
integrity tests. steel.

Inadequate or non-existent Inaccurate assumptions Educate the Client regarding the value of a good GI and specify a scope of
ground investigation report. about soil parameters & intrusive investigation works that is appropriate to the nature of the project and
profile leading to the anticipated ground conditions, starting with a good desk study.
inadequate pile
performance.

Confirmation of bedrock levels. Bedrock or boulders? Establish from desk study the expected depth to bedrock and treat shallow
refusal of cable percussion boring with suspicion. Continue for an appropriate
depth below “rockhead” with rotary drilling to prove the rock.

Over reliance on pile end Excessive pile settlement Consideration of partial factor of safety greater than unity on shaft resistance
bearing in variable/layered rocks. possible pile failure. only or reduced end bearing component.

Concrete durability. Inadequate concrete Ensure that ground and groundwater samples are collected and tested to
specification. establish the chemical properties.

Page 4 of 4

Вам также может понравиться