Tunnel Chronology, Cisumdawu Toll Road Phase II

DATE Meeting Subject and Requirements Status Pictures


27/10/2016 PCM Cisumdawu toll road phase II, Jakarta
1. To complete the geological studies of the critical points and the shear tension analysis. COMPLETE
2. To hold the excavation and tunnel stability simulation using the FE(Finite Element) model. The said
simulation will be held in accordance to the agreed construction scheme (pattern design) and with COMPLETE
consideration of the effect of ground water flow. The length of stand up time will be able to be stand up time is
determined by the FE simulation. around 2 hours
without any support.
3. To immediately hold an additional investigation as to complete existing data, the additional data will
COMPLETE
also be used as input to the FE model,and the mock up is advised to be done in the projected site. additional 3 BH soil
investigation.
4. For the contractor to deliver the Method Statement to the KKJTJ (Bridge and Tunnel Safety Comittee) COMPLETE
22/11/2016 tunnel
method statement
meeting
22/11/2016 tunnel method statement meeting,Bandung
1. Details of pipe roof(L=12m), including the 3M overlap, for each cycle COMPLETE
shop drawing
2. China standard or code of convergence and tunnel roof displacement COMPLETE
provided
3. The details of Tunnel Portal cross section COMPLETE
shop drawing
4. The stability calculation of slope including shear force and safety factor COMPLETE
slope analysis report
5. Reply to PU about the reason for Adit test changing to Mock-up COMPLETE
replied in letter
6. The protective measures for slope boulder and surface water COMPLETE
replied in letter
7. List of machinery and equipment COMPLETE
submitted
8. Details of grouting and composition COMPLETE
single-stage grouting
9. Determine grouting composition according to the grouting test on field COMPLETE
recommendation
(w/c,%):60%,80%

Page 1,Total 3 pages


Tunnel Chronology, Cisumdawu Toll Road Phase II
DATE Meeting Subject and Requirements Status Pictures

22/12/2016 Grouting trail, shotcrete trail COMPLETE

COMPLETE
29/12/2016 Grouting trail,dig-out checking
trail result: pass

10/01/2017 Grouting Review Meeting


1. It should be made the proposal according to the contract related to the grout with water to cement COMPLETE
ratios from 1:1 to 0.6:1 recommendation(w/c
):
0.6:1, 0.8:1
2. It shll be increase the angle of fan blades on the agitator arm at the mixer In progress
3. Cement slurry to do 5×5cm cube specimen, and test the compressive strength In progress
4. The grouting machinery shall have backup machinery COMPLETE
5. Pipe-roof of steel pipe grouting hole axial spacing of 25cm is appropriate COMPLETE

Page 2,Total 3 pages


Tunnel Chronology, Cisumdawu Toll Road Phase II
DATE Meeting Subject and Requirements Status Pictures
6. Tunneling encountered in the sand or gravel layercan be used 4m grouting pipe, the contractor can COMPLETE
propose the original design pipe-roof φ114mm×12m, overlap 3m change into a small catheter Refer to NATM
φ60mm×6m, overlap 2m of the program. method statement
7. How to deal with the gravel and sand layer during tunnel work. COMPLETE
Refer to NATM
method statement
8. A dry mix process shotcrete trial spraying in field should do 7, 14, 28 days of test the compressive
strength. In progress

9. Prepare the wet mix process shotcrete machine for standby use. Dry shotcrete is
better applicable for
this site condition of
groundwater
according to
experience
10. The contractor have conducted 3 additional BH investigations, and the Contractor was requested to
COMPLETE
add the SPT value to the Geological Investigation Report.

Meeting held at Bridge Engineering Directorate in Jakarta, approve tunnel justification of shorten
13/01/2017 cut & cover from 220m to 80m on condition that the construction duration and Contract Price will not
be changed.

Page 3,Total 3 pages