COMPLETE
29/12/2016 Grouting trail,dig-out checking
trail result: pass
9. Prepare the wet mix process shotcrete machine for standby use. Dry shotcrete is
better applicable for
this site condition of
groundwater
according to
experience
10. The contractor have conducted 3 additional BH investigations, and the Contractor was requested to
COMPLETE
add the SPT value to the Geological Investigation Report.
Meeting held at Bridge Engineering Directorate in Jakarta, approve tunnel justification of shorten
13/01/2017 cut & cover from 220m to 80m on condition that the construction duration and Contract Price will not
be changed.