DCI DREDGE VI
IR Number : 01195
IMO Number : 7365772
Ship Type : HOPPER SUCTION DREDGER
Gross Tonnage : 3713
Date of Build : 30/04/1975
Survey Status
: Generated on 04/06/2019
Survey Status Report
IR CLASS
SHIP SURVEY STATUS
Name DCI DREDGE VI : IR Number 01195
Status Class Suspended : IMO Number 7365772
Table of Contents
Ship Particulars
Condition of Class
Statutory Condition
Memoranda
Additional Information
IRCLASS Contacts
Ship Particulars
Identification
e HOPPER SUCTION :DREDGER Flag INDIAN :
: Port of Registry Mumbai :
Date of
: Registry 19/06/1975 :
Classification
ss Notation Hull SUL, HOPPER DREDGER, "INDIAN COASTAL VESSEL" :
:
Ship
ClassStatus
History
: From Date : To Date : Reason : Remarks :
104 m :
:
15.49 m :
:
Bore : Stroke
300 mm
Engine Builder Maschinenfabrik Augsburg Augsburg
31/05/1974
:
:
Invoicing Address
DREDGING CORPORATION
: OF INDIA LTD.
:530 035
64866(20lines)
95-234/398
581/2565920
dtech@Dcil.Co.In
MLC
OF INDIA LTD. :
:
Company ID : 0904110
IRS
Class Certificate HC 30/05/2019 29/10/2019 INT
Statutory Certificate
IRS HC
International Energy Efficiency Certificate 29/11/2016 FT
IRS HC
Indian Coastal Vessel Safety Certificate 30/05/2019 03/06/2019 ST
Intermediate Survey
Intermediate Survey (
Annual Survey
Docking Survey
Previously done on 27
Intermediate Dockin
Postponement upto
Continuous Survey Mach
Statutory Audits /
Statutory Certificates Status Last Audit Range Dates Status
Date
MLC 29/06/2019 -
Inspection Certifica
MLC Inspection Certifica
Condition of Class
Code Due Date Previous Reference Prev Ref Dt Mod Current Reference Curr Ref Dt Asgn
Statutory Condition
*** No Statutory Condition Recommended ***
Memoranda
Code Previous Reference Prev Ref Dt Mod Current Reference Curr Ref Dt Asgn
Additional Information
Code Previous Reference Prev Ref Dt Mod Current Reference Curr Ref Dt Asgn
MA0810. RGK
Automatic Identification System Installed (05-2006).
As declared by the managers vide e-mail to IRS H.O.all existing safety,navigational,communication and fire fighting
equipment to be retained and maintained in line with the requirements of Merchant Shipping Act even after certification to
Indian Coastal Vessel as per Coastal Vessels rules notification 2014.
PSC/FSI Deficiencies
Code Previous Reference Prev Ref Dt Mod Current Reference Curr Date
Due Ref Dt Asgn
Z0801. During the first Intermediate/ Renewal survey of MARPOL Annex VI 02/05/2016 MDR15P163/MDR/
(whichever occurs first) on or after 1 January 2013, SEEMP be verified on
board and the vessel be issued with International Energy Efficiency
Certificate.
Z0802. As required by SOLAS Ch.II-2 Reg.15.2.2.6, an onboard means of recharging 03/12/2014 KND14P199/KND/
breathing apparatus cylinders used during drills is to be provided or a suitable
number of spare cylinders to be carried on board to replace those used during
drills by 1 July 2014 which will be verified by surveyor at first survey after 1
July 2014.
Z0803. As required by SOLAS Ch.II-2 Reg.10.10.1, self-contained compressed air 10/11/2016 CHN16P190/CHN/
breathing apparatus of fire-fighter's outfits to comply with paragraph 2.1.2.2 of
chapter 3 of the Fire Safety Systems Code (i.e. Compressed air breathing
apparatus to be fitted with an audible alarm and a visual or other device which
will alert the user before the volume of the air in the cylinder has been
reduced to no less than 200 l) by 1 July 2019.
Z0804. A minimum of two two-way portable radiotelephone apparatus for each fire
party for fire fighter’s communication to be carried on board (as required by
SOLAS Ch.II-2 Reg.10.10.4) not later than the first survey after 1 July 2018.
Those two-way portable radiotelephone apparatus to be of an explosion proof
type or intrinsically safe.
Z0805. Ship-specific plans and procedures for recovery of persons from the water to 03/12/2014 KND14P199/KND/
be placed on board (as required by SOLAS Ch.III Reg.17-1) by the first
periodical or renewal safety equipment survey of the ship to be carried out
after 1 July 2014 whichever comes first.
Z0806. Appropriate portable atmosphere testing instrument/s (as a minimum capable 10/11/2016 CHN16P190
of measuring concentrations of oxygen, flammable gases or vapours,
hydrogen sulphide and carbon monoxide) will be required (SOLAS Ch.XI-1
Reg.7) to be carried on board from 01/07/2016. Instruments carried under
other requirements may satisfy this regulation. Suitable means shall be
provided for the calibration of all such instrument/s.
0300
0452
0460
0477
0506
0522
0547
0658
0703
Code *** Items Due Next 12 Months *** Assigned Date Due Date
0711 Bed Plates,Frames,Tie Rods,Holding Down Bolts & Chocks 02/05/2016 29/12/2019
Lub.Oil System
1120 Main Engine Lub.Oil Pump 02/05/2016 29/12/2019
Cooling System
1207 Outer Main Sea Water/Fresh Water Cooling Pump 02/05/2016 29/12/2019
Electrical System
1375 Switch Boards & Fittings 02/05/2016 29/12/2019
Sea Connections
1486 Stbd Side Suctions 02/05/2016 29/12/2019
0025 5 05/2016 02/2021 No.1 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0033 5 05/2016 02/2021 No.2 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0041 5 05/2016 02/2021 No.3 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0058 5 05/2016 02/2021 No.4 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0066 5 05/2016 02/2021 No.5 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0074 5 05/2016 02/2021 No.6 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0082 5 05/2016 02/2021 No.7 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0090 5 05/2016 02/2021 No.8 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0103 5 05/2016 05/2021 No.1 Main Journal & Bearing
0111 5 05/2016 05/2021 No.2 Main Journal & Bearing
0128 5 05/2016 05/2021 No.3 Main Journal & Bearing
0136 5 05/2016 05/2021 No.4 Main Journal & Bearing
0144 5 05/2016 05/2021 No.5 Main Journal & Bearing
0152 5 05/2016 05/2021 No.6 Main Journal & Bearing
0160 5 05/2016 05/2021 No.7 Main Journal & Bearing
0177 5 05/2016 05/2021 No.8 Main Journal & Bearing
0185 5 05/2016 05/2021 No.9 Main Journal & Bearing
0193 5 05/2016 05/2021 No.1 O.F Inj.Pump,H.P O.F Pipes & Shielding
0206 5 05/2016 05/2021 No.2 O.F Inj.Pump,H.P O.F Pipes & Shielding
0214 5 05/2016 05/2021 No.3 O.F Inj.Pump,H.P O.F Pipes & Shielding
0222 5 05/2016 05/2021 No.4 O.F Inj.Pump,H.P O.F Pipes & Shielding
0230 5 05/2016 05/2021 No.5 O.F Inj.Pump,H.P O.F Pipes & Shielding
0247 5 05/2016 05/2021 No.6 O.F Inj.Pump,H.P O.F Pipes & Shielding
0255 5 05/2016 05/2021 No.7 O.F Inj.Pump,H.P O.F Pipes & Shielding
0263 5 05/2016 05/2021 No.8 O.F Inj.Pump,H.P O.F Pipes & Shielding
0271 5 05/2016 05/2021 Engine Trial
0288 5 05/2016 Insulation Exhaust Manifold & Piping
0296 5 05/2016 Crankcase Doors & Relief Devices
0300 5 05/2016 12/2019 Crankshaft Alignment
0317 Postponed 5 01/2014 10/2018
26/02/2019 Vibration Damper/s
0325 5 05/2016 05/2021 Camshaft/s & Camshaft/s Drive
0333 5 05/2016 05/2021 Bed Plates,Frames,Tie Rods,Holding Down Bolts & Chocks
0341 5 05/2016 05/2021 Super Charger
0358 5 05/2016 05/2021 Main Engine Air Cooler
0366 5 05/2016 05/2021 Main Engine Attached Lub.Oil Circulating Pump
0374 5 05/2016 05/2021 Main Engine Attached O.F Booster Pump
0382 5 05/2016 05/2021 Coupling
0390 5 Stbd Inline Trunk Piston Type Engine 76
Next Due
Postpone
Code Status Cycle Date Date
Date Description
0403 5 12/2017 No.1 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0411 5 12/2017 No.2 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0428 5 12/2017 No.3 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0436 5 12/2017 No.4 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0444 5 12/2017 No.5 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0452 5 05/2016 12/2019 No.6 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0460 5 05/2016 12/2019 No.7 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0477 5 05/2016 12/2019 No.8 Cyl,Cvr,Pstn,Con Rod,C.Pin Brg & Webs,Vlvs & Gears
0485 5 05/2016 05/2021 No.1 Main Journal & Bearing
0493 5 05/2016 05/2021 No.2 Main Journal & Bearing
0506 5 05/2016 12/2019 No.3 Main Journal & Bearing
0514 5 05/2016 05/2021 No.4 Main Journal & Bearing
0522 5 05/2016 12/2019 No.5 Main Journal & Bearing
0530 5 05/2016 05/2021 No.6 Main Journal & Bearing
0547 5 05/2016 12/2019 No.7 Main Journal & Bearing
0555 5 05/2016 05/2021 No.8 Main Journal & Bearing
0563 5 05/2016 05/2021 No.9 Main Journal & Bearing
0571 5 05/2016 05/2021 No.1 O.F Inj.Pump,H.P O.F Pipes & Shielding
0588 5 05/2016 05/2021 No.2 O.F Inj.Pump,H.P O.F Pipes & Shielding
0596 5 05/2016 05/2021 No.3 O.F Inj.Pump,H.P O.F Pipes & Shielding
0600 5 05/2016 05/2021 No.4 O.F Inj.Pump,H.P O.F Pipes & Shielding
0617 5 05/2016 05/2021 No.5 O.F Inj.Pump,H.P O.F Pipes & Shielding
0625 5 05/2016 05/2021 No.6 O.F Inj.Pump,H.P O.F Pipes & Shielding
0633 5 05/2016 05/2021 No.7 O.F Inj.Pump,H.P O.F Pipes & Shielding
0641 5 05/2016 05/2021 No.8 O.F Inj.Pump,H.P O.F Pipes & Shielding
0658 5 05/2016 12/2019 Engine Trial
0666 5 05/2016 Insulation Exhaust Manifold & Piping
0674 5 05/2016 Crankcase Doors & Relief Devices
0682 5 05/2016 Crankshaft Alignment
0690 Postponed 5 01/2014 10/2018
26/02/2019 Vibration Damper/s
0703 5 05/2016 12/2019 Camshaft/s & Camshaft/s Drive
0711 5 05/2016 12/2019 Bed Plates,Frames,Tie Rods,Holding Down Bolts & Chocks
0728 5 05/2016 05/2021 Super Charger
0736 5 05/2016 05/2021 Main Engine Air Cooler
0744 5 05/2016 12/2019 Main Engine Attached Lub.Oil Circulating Pump
0752 5 05/2016 12/2019 Main Engine Attached O.F Booster Pump
0760 5 05/2016 05/2021 Coupling
0777 5 Port Main Reduction Gearing 82
Next Due
Postpone
Code Status Cycle Date Date
Date Description
0822 5 12/2014 Foundation Bolts & Chocks
0830 5 Stbd Main Reduction Gearing 88
Next Due
Postpone
Code Status Cycle Date Date
Date Description
1207 5 05/2016 12/2019 Outer Main Sea Water/Fresh Water Cooling Pump
1215 5 05/2016 06/2019 Sea Water Pipes/Valves/Filters
1223 5 12/2017 Main Engine Fresh Water Cooling Pump
1231 5 12/2017 Main Engine Fresh Water Cooler
1248 5 05/2016 07/2019 Fresh Water Pipes/Valves/Filters
1256 5 Bilge & Ballast System 132
Postpone
Code Status Cycle Date Date Description
5013 5 05/2016 Thickness Determinatio
5021 5 05/2016 Bridge Superstructure
5038 5 05/2016 Upr Deck Plating
5046 5 05/2016 Forecastle Deck Plating
5054 5 05/2016 Forecastle Tween Deck
5062 5 05/2016 Hopper Space
Hopper Keelson Space
Postpone
Code Status Date Cycle Date Description
5070 5 05/2016
5087 5 05/2016 Port Hopper Side Buoyancy Space
5095 5 05/2016 Stbd Hopper Side Buoyancy Space
5108 5 05/2016 Aft Tween Deck Store Space
5116 5 05/2016 Pump Room Double Bottom Dry Space
5124 5 05/2016 Forepeak Space/s
5132 5 05/2016 Engine Room
5140 5 05/2016 Fwd Pump Room
5157 5 05/2016 Fwd Chain Locker
5165 5 05/2016 Aft Chain Locker
5173 5 Forepeak Tank
5181 5 05/2016 Examination
5198 5 05/2016 Test
5202 5 Aftpeak Tank
5210 5 05/2016 Examination
5227 5 05/2016 Test
5235 5 Pump Room No.2 Port Fwd Inner Drain Double Bottom Tank
5243 5 05/2016 Examination
5251 5 05/2016 Test
5268 5 Pump Room No.3 Port Fwd Drain Double Bottom Tank
5276 5 05/2016 Examination
5284 5 05/2016 Test
5292 5 Pump Room No.3 Stbd Fwd Drain Double Bottom Tank
5305 5 05/2016 Examination
5313 5 05/2016 Test
5321 5 Pump Room No.4 Stbd Sludge Double Bottom Tank
5338 5 05/2016 Examination
5346 5 05/2016 Test
5354 5 Pump Room No.5 Port Aft Drain Double Bottom Tank
5362 5 05/2016 Examination
5370 5 05/2016 Test
5387 5 Pump Room No.5 Stbd Aft Drain Double Bottom Tank
5395 5 05/2016 Examination
5408 5 05/2016 Test
5416 5 No.6 Port Upr L.O Tank
5424 5 05/2016 Examination
5432 5 05/2016 Test
5440 5 No.6 Stbd Upr O.F Tank
5457 5 05/2016 Examination
Postpone
Code Status Date Cycle Date Description
5465 5 05/2016 Test
5473 5 No.7 Port Midship Fwd F.W Tank
5481 5 05/2016 Examination
5498 5 05/2016 Test
5502 5 No.7 Stbd Fwd Midship F.W Tank
5510 5 05/2016 Examination
5527 5 05/2016 Test
5535 5 No.8 Port Aft Midship O.F Tank
5543 5 05/2016 Examination
5551 5 05/2016 Test
5568 5 No.8 Stbd Aft Midship O.F Tank
5576 5 05/2016 Examination
5584 5 05/2016 Test
5592 5 E.R Flat No.9 Port Fwd Inner L.O Tank
5605 5 05/2016 Examination
5613 5 05/2016 Test
5621 5 E.R Flat No.10 Port Fwd Outer O.F Tank
5638 5 05/2016 Examination
5646 5 05/2016 Test
5654 5 E.R Flat No.11 Stbd Fwd Lwr L.O Tank
5662 5 05/2016 Examination
5670 5 05/2016 Test
5687 5 E.R Flat No.12 Stbd Fwd Upr O.F Tank
5695 5 05/2016 Examination
5708 5 05/2016 Test
5716 5 E.R No.13 Centre Sludge Double Bottom Tank
5724 5 05/2016 Examination
5732 5 05/2016 Test
5740 5 E.R No.14 Port Drain Double Bottom Tank
5757 5 05/2016 Examination
5765 5 05/2016 Test
5773 5 E.R No.14 Stbd Drain Double Bottom Tank
5781 5 05/2016 Examination
5798 5 05/2016 Test
5802 5 E.R No.15 Stbd Aft Drain Double Bottom Tank
5810 5 05/2016 Examination
5827 5 05/2016 Test
5835 5 No.16 Centre Aft F.W Tank
5843 5 05/2016 Examination
Postpone
Code Status Date Cycle Date Description
5851 5 05/2016 Test
5868 5 05/2016 E.R Double Bottom
5876 5 05/2016 Under Engines
5884 5 05/2016 Steering Gear Com
5892 5 05/2016 Windlass
5905 5 05/2016 Anchors/s
5913 5 05/2016 Cables
5921 5 05/2016 Steering Gear
5938 5 05/2016 Aux.Steering Gear
5946 5 05/2016 Hand Pump/s
5954 5 05/2016 Sounding Pipes
5962 5 05/2016 Air Pipe/s
5970 5 05/2016 Mast/s
5987 5 05/2016 Fire Equipment
5995 5 Means Of Escape
6006 5 05/2016 Machinery Space
6014 5 05/2016 Crew & Passenger
6022 5 05/2016 Spaces In Which C
6030 5 05/2016 Communication-Bri
6047 5 05/2016 Communication-Bri
6055 5 05/2016 Helm Indicator
6063 5 05/2016 Hatchways & Closin
6071 5 05/2016 Ventilators,Airpipes
6088 5 05/2016 Casings & Their Clo
6096 5 05/2016 Deckhouses,Comp
6100 5 05/2016 Superstructures & C
6117 5 05/2016 Windows,Side Scut
6125 5 05/2016 Scuppers,Sanitary
6133 5 05/2016 Guard Rails & Bulw
6141 5 05/2016 Freeing Ports
6158 5 05/2016 Gangways,Walkwa
Postpone
Code Status Date Cycle Date Description
4053 5 02/2016
4061 5 02/2016 Sternbush
Survey Station Report Number Survey Held First Visit Date Last Visit Date
CHN18P182
KOCHI AS,COC(M),CSM 07/01/2019
04/12/2018
CHN18P146
KOCHI CHNGFE3,CMPAFSGENEX,CSM,GENEXICC,ICVPPIN,ICVSCIN 31/10/2018
08/10/2018
CHN18P136
KOCHI COC(H),ICVPPIN,ICVSCIN 29/09/2018
11/09/2018
BOM17P663
MUMBAI AS,COC(H),CSM,IAPPIS,ILLAS,IOPIS,IS,SAFIS,SRTPS 23/12/2017
01/11/2017
BOM17P512
MUMBAI DAMH,GEFSI 10/08/2017
10/08/2017
MGO16P116
GOA CMPAFSGENEX,GENEXICC,IAPPGENEX,IEECGP,ILLRSEX,IOP 29/11/2016
29/11/2016
GENEX,MARPOL Annex IV
GENEX,SAFGENEX,SEQGENEX,SRTGENEX
CHN16P190
KOCHI AS,GEFSI,IAPPAS,ILLAS,IOPAS,SAFAS,SEQAS,SRTPS 10/11/2016
22/10/2016
MDR15P163
CHENNAI AS,CMPAFSPS,COC(H),CSM,DS,IAPPRS,IEECIN,ILLRS,IOPRS, 02/05/2016
27/10/2015
MARPOL Annex IV
RS,REH,REINCLASS,SAFRS,SEQRS,SRTRS,SSH,TS(OG)p,TS(
OG)s
CHN15PX005
KOCHI GESIVOY,IAPPGENEX,ILLRSEX,IOPGENEX,MARPOL Annex IV 14/09/2015
08/09/2015
GENEX,SAFGENEX,SEQGENEX,SRTGENEX
MDR15PX005
CHENNAI GESIVOY,IAPPGENEX,ILLRSEX,IOPGENEX,MARPOL Annex IV 04/07/2015
02/07/2015
GENEX,SAFGENEX,SEQGENEX,SRTGENEX
KND15PX005
KANDLA GESIVOY,IAPPGENEX,ILLRSEX,IOPGENEX,MARPOL Annex IV 29/05/2015
26/05/2015
GENEX,SAFGENEX,SEQGENEX,SRTGENEX
KND14P199
KANDLA AS,COC(H),CSM,DS,IAPPGENEX,ILLRSEX,IOPGENEX,MARPOL 03/12/2014
17/09/2014
Annex IV GENEX,SAFGENEX,SEQGENEX,SRTGENEX,SSH
***List of Reports pending at Survey Station (for Reporting / SIC Review)***
Survey Station Report Number Survey Held First Visit Date Last Visit Date
CHN19P099
KOCHI GELAIDUP 03/06/2019
03/06/2019
CHN19P056
KOCHI COC(H),DS,GENEX,GENEXSTICC,ICVPPGENEX,ICVSCGENEX, 30/05/2019
05/04/2019
REINCLASS
IRS will be issuing hard copy as well as e-certificates for a period of 5 years from the commencement of this service.
e-Certificate verification from IRClass website can also be done by scanning the QR Code, printed on the bottom right
side of the certificate using any QR CODE scanning application available in app store.
e-Certificate can be downloaded from IRClass website by using the Unique Tracking ID provided to each certificate or
by scanning the QR code printed on the face of the certificate. e-certificates can also be directly downloaded from
IRClass website by using login credentials provided to the company.
When surveys are completed by flag administration or other RO surveyors, attending surveyor/auditor shall print the
e-certificate from IRClass website & endorse towards surveys being completed. Copy of survey report along with
endorsed certificate shall be forwarded electronically to ecertificates@irclass.org
Contact us
ecertificates@irclass.org
Request for issuance of e-certificates / related queries are to be sent to
Phone : +91 22 30519538 / 656 / 781
2. Where a vessel is damaged to an extent resulting in towage outside port limits, it shall be the Owners' responsibility to
notify IRS at the first practicable opportunity.
3. Any alteration proposed to be carried out to approved scantlings and arrangements of the hull machinery or equipment
are to meet with approval of IRS. Such approved alterations are to be carried out under the inspection of, and to the
satisfaction of surveyors.
4. When a ship is detained by Port State Control, IRS is to be immediately notified by the owner / operator for arranging
attendance by a Surveyor.
5. When a vessel meets any accident such as fire, collision etc., it shall be the Owners' responsibility to notify IRS at the
first practicable opportunity.
7. If the vessel's class has been laid up, in order to maintain the laid up status, it shall be the Owners' responsibility to
offer the vessel for general examination within the window of periodical survey.
8. When a vessel is under survey, it shall be Owners' responsibility to notify IRS if vessel is sailing out of port limits.
9. The class of a vessel will be liable to be suspended if the Owner fails to notify IRS of any damage to the ship's
machinery or equipment, which may adversely affect classification of the vessel or subsequently fails to arrange
the survey as may be advised by IRS.
10. The class of a vessel will be automatically suspended from the expiry date of Certificate of Class or by the e
of any extension granted, if the special survey has not been completed by the due date and an extension ha
agreed to, or the vessel is not under attendance by the surveyor with a view to complete the surveys prior to
service.
11. The class of a vessel will also be automatically suspended if the annual, intermediate survey become o
12. The class of a vessel will be subject to a suspension procedure if an item of continuous survey is ov
annual survey, unless the item is dealt with or postponed by agreement.
13. The class of the vessel will also be subject to a suspension procedure if recommendations and/
are not dealt with by the due date or postponed by agreement, by the due date.
14. The class of a vessel will be liable to be suspended if alterations are carried out on items wh
classification of the ship without informing IRS, except in the case of emergency repairs.
15. The class of a ship is liable to be withheld or, if already granted, may be withdrawn in ca
or expenses chargeable for the service rendered.
16. Where any ship proceeds to sea with less freeboard than that approved by IRS or w
higher on the ship's sides than the position assigned or approved by IRS, the ship's
17. When it is found that a ship is being operated in a manner contrary to that agree
being operated in conditions or in areas more onerous than those agreed, the cla
IRCLASS Contacts
DISCLAIMER :-
Information provided in ship survey status by IRClass is solely provided for the convenience of Owners or
Managers as a guide to their ship's survey status and in no way substitute for advice from IRClass.
Neither Indian Register of Shipping, nor any of its employees, assures any responsibility for the accuracy or legal
liability for any loss or damage that may be sustained as a result of using their services.