Вы находитесь на странице: 1из 17

DEDICATED FREIGHT CORRIDOR CORPORATION OF INDIA LIMITED

Civil, Structures and Track Works


Contract Package 303

Method Statement for


Anti-Termite Treatment of Buildings

Document No. DOC/CP-303/MS/ST/00

PROJECT MANAGER/PROJECT
QUALITY
REV DATE PREPARED BY SHE TEAM DIRECTOR
TEAM

R0 25-July-2019 Mohamed Ashiq M P. Jhariya Naba Haldar

REVIEWED/ CHECKED
REVIEWED/ REVIEWED/
BY RECOMMENDED BY
CHECKED APPROVED BY TL
CHECKED BY DTL
(FORMATION/
(HSE) BY (QA/QC)
STRUCTURE)

Sensitivity: LNT Construction Internal Use


Revision History

Revision Revision Revision Details Approved by


No. Date Revision

0 25-July-2019 Initial Submission

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

Index

SL NO Description Page no.


1 Scope of work 1

2 Access/egress 1

3 Lighting 1

4 Manpower list 1
5 Responsibilities 2

6 Plant & equipment 2

(a) Plant & equipment schedule 2

(b) PPE 2

7 Material 3

8 Health, safety and environmental protection 3

(a) Manpower 3

(b) Equipment 3

(c) Environmental Protection 3

(d) Welfare arrangements 4

9 Sequence / method of work 4

(a) General 4

(b) Sequence of work 5

(c) Quality procedure 6

10 Technical information 6

11 Emergency contact details 8

12 Risk Assessment 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

1.PURPOSE OF METHOD STATEMENT

The purpose of this method statement is to describe the sequence of activities which will be
followed to execute preconstruction ant termite treatment work in the DFCCIL project. This
method statement will ensure that safety measures are implemented throughout the progress of
works.

2. SCOPE OF WORK

This method statement covers the general requirement for preconstruction ant termite treatment
for the building to protect against attack by subterranean termites by suitable chemical
treatment measure.

2. ACCESS/EGRESS

a) Proper access and egress will be ensured before and till completion of work.
b) Temporary signage will be provided at access and egress. Approaches and exits
shall be clearly defined by barricades and warning/caution signs.

3. LIGHTING

a) Proper illumination will be ensured at site during work. Luminance Flux level
shall be maintained between 200-250.
b) P&M and Safety personnel will be ensuring the required intensity of light at work area.

4.MANPOWER LIST

SL. No. Designation Number of People

1 DGM 1

2 Planning Manager 1

3 EHS Manager 1

4 Construction Manager 3

5 Planning Engineer 2

6 Site Senior Engineer 1

7 Site Engineer 3

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 1 of 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

5.RESPONSIBILITIES

SL. No. Name Designation


1 A. K. Singh CPM/D
2 S. K. Saxena PM
3 Anshul Srivastava Planning Manager
4 A.K Mishra DGM Buildings
5 Arvind Jha Building Construction Manager
6 Anil Kumar Sharma Safety In charge
7 Maiylraj Kumar S Assistant Construction Manager Buildings
8 Mithilesh Kumar Singh Assistant Construction Manager Buildings
9 Tanmoy Basu Assistant Construction Manager Buildings
10 Neelkesh Mahato Site Senior Engineer
11 Naveen Panchal Site Engineer
12 Md. Ifkar Alam Site Engineer
13 Suraj Kumar Prajapati Planning Engineer
14 Md. Ashiq M Planning Engineer
15 Vikas Jangra Site Engineer
16 Karan Dutta Site Engineer
17 Dharma Teja Site Engineer

6. PLANT & EQUIPMENT

A. Plant & Equipment Schedule

The equipment engaged for works shall be checked and approved by P&M Department.

Machinery /Tools/Equipment engaged to carryout Ant termite treatment are as follow:

a) Pressure Pumps
b) Sprayer arrangement (hand)
c) Measuring Jar
d) Containers and drum
e) Mild Steel Rod 12 mm dia (for rodding hole)

B. Personal Protective Equipment


a) All workmen should wear proper Personal Protective Equipment (PPEs) like safety
helmets, gumboots/safety shoes, reflective jackets etc. All workmen shall wear face
mask while carrying out spraying operation.
b) Routine inspection shall be done by Site engineer/Supervisor to ensure working
conditions before commencing of works.
c) Target area where spraying operation is done shall be cordoned suitably.

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 2 of 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

7. MATERIALS

Chloropyriphos (Conforming to IS 8944) / Lindane 20% EC (Conforming to IS 632) or


equivalent material of approved make.

8.HEALTH, SAFETY AND ENVIRONMENTAL PROTECTION

A. Manpower

a) Safety and health induction shall be conducted by the SHE Manager/ Engineer prior to
commencement of works to all personnel involved as per the approved SHE Plan
(DFCCIL/DOC/CP-303/SHE-002 rev 04).
b) All personnel will wear the required Personal Protective Equipment (safety shoes,
helmet, safety sun glasses and high visibility safety jacket) as per the SHE plan.
c) During peak hours in summer season, suitable measures shall be taken to avoid any
heat stroke, suffering due to peak temperature of the day to the workers.
d) All work at site will be carried out in accordance with this method statement (Risk
assessment attached).
e) The Construction Manager/Site Engineer responsible for the job will be present at site
during working hours and will implement SHE control measures against risks identified
on site and a safety engineer will monitor all activities. A site briefing will take place
before works commencement. Any incident, injury, and near miss will be reported
immediately to the L&T Project management and SYSTRA/DFCCIL

B. Equipment

a) All equipment shall be inspected by the L&T SHE/ Plant Department prior to work.
b) The operators will also practice a daily visual inspection to their equipment prior to
start work.
c) Those inspections will be implemented as per L&T equipment procedure.

C. Environmental Protection

a) All personnel should apply Health and Sanitation requirements to themselves and
maintain a good housekeeping on site as per the L&T SHE plan (DFCCIL/DOC/CP-
303/SHE-002 rev 04).
b) Oil spillage from motorized equipment shall be avoided by placing adequate
catch/retention basin in the work site.
c) Dust shall be controlled by spraying water on regular basis. Goggles and dust masks
will be used where dust is generated.
d) Controls will be utilized in accordance with the Project EMP.

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 3 of 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

D. Welfare arrangements

a) Drinking water will be provided in the site offices and the workers rest area.
b) Shaded areas will be provided for staff and workers to take rest and food.
c) Ablution Containers will be provided for staff and workers near the rest areas.
d) First-Aid kits will be available with the site engineer/ first-aider.
e) At least two personnel on the site will hold at least the one-day first-aid competency.
f) The site team shall also hold a First-Aid kit within the vehicle.

9. SEQUENCE / METHOD OF WORK

The sequential activity and corresponding methods are detailed below-

A. General

1. Storage of Material:

a) Chemical Containers shall be kept under sealed conditions in lockable store/ shaded
area (as identified).
b) Empty containers should be disposed from the site immediately and a separate log to
be maintained for empty containers

2. Chemical Preparation:

As per technical datasheet of the approved product.

3. Application Method

a) Chemical emulsion shall be applied uniformly at prescribed rate in all the stages of
treatment.
b) Application of chemical emulsion shall be done using hand operated pressure pump.
c) Ensure uniform spraying of chemical to facilitate proper coverage and penetration.
d) Chemical emulsion shall be applied by trained worker in accordance to manufacture's
recommendation.

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 4 of 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

B. Treatment sequence:

a) Soil Treatment:

Treating the soil beneath the building and around the foundations with a soil insecticide is
a preventive measure. The purpose of treatment is to create the barrier between the ground
from where termites come and wood work or other cellulosic materials in the buildings.
The chemical emulsions Lindane 20 EC/Chlorpyrifos shall be applied uniformly at the
prescribed rate in all the stage of treatment.

b) Treatment for RCC Foundations:

In the case of RCC foundations, the concrete is dense being a 1:2:4 (cement: fine
aggregates: coarse aggregates, by volume) mix or richer, the termites are unable to
penetrate it, it is therefore, unnecessary to start the treatment from the bottom of
excavations. The treatment shall start at a depth of 500 mm below the ground level except
when such ground level is raised or lowered by filling or cutting after the foundations have
been cast. In such cases, the depth of 500 mm shall be determined from the new soil level
resulting from the filling or cutting mentioned above, and soil in immediate contact with
the vertical surfaces of RCC foundations shall be treated at the rate of 7.5 I/m2.

c) Treatment of Top Surface of Plinth Filling:

The top surface of the consolidated earth within plinth walls shall be treated with chemical
emulsion at the rate of 5 l/m2 of the surface before the sand bed or sub-grade is laid. If the
filled earth has been well rammed and the surface does not allow the emulsion to seep
through, holes up to 50 to 75 mm deep at 150 mm centres both ways maybe made with 12
mm diameter mild steel rod on the surface to facilitate saturation of the soil with the
chemical emulsion.

d) Treatment at Junction of the Wall and the Floor:

Special care shall be taken to establish continuity of the vertical chemical barrier on inner
wall surface from ground level (where it had stopped with the treatment described in 7.2.2)
up to the level of the filled earth surface. To achieve this, a small channel 30 mm x 30 mm
shall be made at all the junctions of wall and columns with the floor (before laying the
sub-grade) the rod holes made in the channel up to the ground level 150 mm apart and the
iron rod moved backward and forward to break up the earth and chemical emulsion poured
along the wall at the rate of 7.5 l/m2 of vertical wall or column surface so as to soak the
soil right to the bottom. The soil should be tamped back into place after the operation.

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 5 of 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

e) Treatment of Soil along External Perimeter of Building:

After the building is complete, the earth along the external perimeter of the building should
be rodded at intervals of 150 mm and to a depth of 300 mm. The rods should be removed
backward and forward parallel to the wall to break up the earth and chemical emulsion
poured along the wall at the rate of 7.51 l/sqm of vertical surfaces. After the treatment, the
earth should be tamped back into place. The earth outside the building should be graded
and treatment should be carried out on completion of building. In the event of filling more
than 300 mm, the external perimeter treatment shall extend to the full depth of filing upto
ground level so as to ensure continuity of the chemical barrier.

f) Treatment of Soil Surrounding Pipes, Wastes and Conduits:

When pipes, wastes and conduits enter the soil inside the area of foundations, soil
surrounding the point of entry shall be loosened around each such pipe, waste or conduit
for a distance of 150 mm and to a depth of 75 mm before treatment is commenced. When
they enter the soil external to the foundations, they shall be similarly treated at a distance
of over 300 mm unless they stand clear of the walls of the building by about 75mm.

C. Quality procedure

a) Ensure emulsion shall be mixed as per manufacturer recommendation


b) Ensure necessary testing/checking shall be done as per ITP
c) Ensure material is delivered in sealed containers for use at site.

10. TECHNICAL INFORMATION

This method statement is prepared with reference to the following documents:


a) BOQ Specification
b) Project QA/QC Plan
c) Project EHS plan
d) IS 6313(Part 2) : 2013 and IS 632

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 6 of 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 7 of 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

11. EMERGENCY CONTACT DETAILS:

S.No. Name Designation Contact No.


1 A. K. Singh CPM/D 9650149933
2 S. K. Saxena PM 8239567875
3 Anshul Srivastava Planning Manager 8800115012
4 Anil Kumar Sharma Safety In charge 7518022568
5 Nexa Hospital 8929400448

12. RISK ASSESSMENT

Annexure-I

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 8 of 8

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 5 of 6

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 25-07-2019 Page 6 of 6

Sensitivity: LNT Construction Internal Use


METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS
METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS
METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 19-07-2019 Page 5 of 6
METHOD STATEMENT FOR ANTI TERMITE TREATMENT OF
DFCC CP 303
BUILDINGS

Document No. Rev. Date Page


DOC/CP-303/MS/ST/00 0 19-07-2019 Page 6 of 6

Вам также может понравиться