Load Calculations:
Self weight of slab = 0.15 * 25 = 3.75 kN/m²
Finishing load-50thk. = 0.05 * 24 = 1.20 kN/m²
Live load = 0.75 kN/m²
Reinforcement:
Required in Shorter Span Reinf Required Reinf Provided
Support 10Ø @ 545mm c/c - 10 dia @ 200 mm c/c
Mid span 10Ø @ 545mm c/c - 10 dia @ 200 mm c/c
Required in Longer Span
Support 10Ø @ 545mm c/c - 10 dia @ 200 mm c/c
Mid span 10Ø @ 545mm c/c - 10 dia @ 200 mm c/c
Actual Shear Stress < Design Shear Stress 0.145 < 0.532 SAFE
Actual span/depth ratio < Modified span/depth ratio 30.17 < 33.75
Rev
Project Construction of Sewage Treatmeny Plant of Capacity 375KLD
0
Doc., Designed Checked Approved
19-H20-STP-STR-01
Number VJ GJ DM
Title Structural Design Calculation of Underground STP tank
Design of Slab Panel @ 175.50m Level
Slab name : S1
Data:
Concrete M25 fck = 25 N/mm²
Steel Fe 500 fy = 500 N/mm²
Load Calculations:
Self weight of slab = 0.15 * 25 = 3.75 kN/m²
Finishing load-50thk. = 0.05 * 24 = 1.20 kN/m²
Live load = 0.75 kN/m²
Reinforcement:
Required in Shorter Span Reinf Required Reinf Provided
Support 10Ø @ 545mm c/c - 10 dia @ 200 mm c/c
Mid span 10Ø @ 545mm c/c - 10 dia @ 200 mm c/c
Required in Longer Span
Support 10Ø @ 545mm c/c - 10 dia @ 200 mm c/c
Mid span 10Ø @ 545mm c/c - 10 dia @ 200 mm c/c
Actual Shear Stress < Design Shear Stress 0.097 < 0.532 SAFE
Actual span/depth ratio < Modified span/depth ratio 30.17 < 33.75