AI Issuance Status since 29 Jan 2019

AI No. Discipline Location Description of change Issue Date Cost Estimate (HK$)
1. Additional alarm bells will be provided to
cover the C&ED 291 M Restroom and C&ED
292 F Restroom as per the FSD comment during
their inspection on 3 Jan 2019. 2. Additional
remote indicator will be provided to cover the
FS-068 FS DOG Filtration Plant Room as per the FSD comment 29/1/2019 18,000.00
Additional exit sign, directional
sign and essential lighting to suit latest GBP.
EE-165 EE FSD Revise Tx room lighting layout for FS Inspection. 29/1/2019 69,000.00
Additional hose reels with associated pipeworks,
alarm bells, manual call points, visual fire alarms,
remote indicators, directional signs, heat
detectors and smoke detectors will be provided as
FS-069 FS CEBI per the FSD comment during their inspection on 31/1/2019 139,000.00
Additional alarm bells, manual call points, visual
fire alarms and smoke detectors will be provided
as per the FSD comment during their inspection
FS-070 FS FXRVIS on 17-22 Jan 2019. 31/1/2019 86,000.00
Additional exit sign, directional
sign and essential lighting to suit latest GBP.
Revise Tx room lighting layout and 4/F lighting
EE-166 EE HKP layout for FS Inspection. 31/1/2019 45,000.00
Change 3 nos. of isolator from
40A (DP) to 63A (TPN). Change the
corresponding MCCB units from 40A (SPN) to
EE-169 EE PTB 63A (TPN). Change the corresponding power 31/1/2019 219,000.00
Change the rating of isolators for
under deck bridge deck bridge lighting from 40A
(TPN) to 63A (TPN). Change the rating of
isolators for gantry lighting from 40A (SPN) to
63A (TPN). Change the corresponding power
EE-170 EE CRBO cable from 2-core to 4-core. 12/2/2019 81,000.00
Omit IT trunking in IMMD 13
Strong Room. Extend cable tray to floor panel
with brush outlet for cabling work at all conputer
rooms. Revise adaptable boxes location and
additional concealed conduit for Facial Access
EE-171 EE PTB Control System at IMMD 20 Computer Server 12/2/2019 23,000.00
Revise Kiosk 75x75mm trunking to suit the final
EE-173 EE CPK setting out of VEC for ImmD operation need. 12/2/2019 18,800.00
Modification of F&E cable
EE-175 EE PTB containment to suit user daily's operation 14/2/2019 98,000.00
Modification of F&E cable
containment to suit user daily's operation.
EE-176 EE CEBI Modification of electrical layouts to suit user 14/2/2019 20,000.00
Modification of F&E cable
containment to suit user daily's operation.
EE-177 EE CEBO Modification of electrical layouts to suit user 14/2/2019 14,000.00
Change 1 no. of Directional Exit
EE-178 EE DOG Sign to 2 nos. of Directional Exit Sign. 14/2/2019 4,000.00
Additional emergency lighting
and revise exit sign at FXI to suit FS Inspection
EE-179 EE FXI comment. 14/2/2019 25,000.00
Revise card reader, breakglass, door
SY-053 SY CEBI release button provision to suit user requirements. 14/2/2019 5,000.00
Relocate repeated panel and thermostat to suit
AC-047 AC CEBO user's daily operation. 21/2/2019 120,000.00
Additional FRP enclosure to be provided in
Genset Room as per the FSD comment during
AC-048 AC PTB their inspection on 22 Jan 2019. 21/2/2019 288,000.00
Additional 6nos. of 20W horn speaker to suit FS
AE-008 AE CEBI Inspection comment at CBI. 21/2/2019 33,000.00
Additional Telephone points,
adaptable boxes and socket outlets for FSD
operation need. Revise Trunking routing to suit
EE-168 EE FSD for FSD operation need. 21/2/2019 266,000.00
Extend cable tray to floor panel
with brush outlet for cabling work at all conputer
EE-172 EE CEBI rooms. 21/2/2019 2,000.00
Revise Kiosk 75x75mm trunking to suit the final
EE-174 EE GVK setting out of VEC for ImmD operation need. 21/2/2019 28,200.00
Revise emergency lighting and
EE-180 EE CEBI exit sign at CBI to suit FS Inspection comment. 21/2/2019 55,000.00
Revise of drainage pipeworks
routing to match the latest coordination and
SD-056 SD GVKI SCCU approval drawing 21/2/2019 277,000.00
Additional drainage pipeworks
to suit latest GBP. Revise of drainage pipeworks
routing to match the latest coordination and
SD-057 SD CEBO SCCU approval drawing 21/2/2019 198,000.00
Revise of drainage pipeworks
routing to match the latest coordination and
SD-058 SD GVKO SCCU approval drawing 21/2/2019 298,000.00
Relocate adaptable box and socket to suit C&ED
operation need as per the joint site inspection on
14 Dec 2019. Additional adaptable box for the
EE-183 EE GVKI vertical posts to suit ImmD and C&ED operation 27/2/2019 221,500.00
Relocate adaptable box and
socket to suit C&ED operation need as per the
joint site inspection on 14 Dec 2019. Additional
adaptable box for the vertical posts to suit ImmD
EE-184 EE GVKO and C&ED operation need. 27/2/2019 221,500.00
Relocate socket at DOG NER to
EE-185 EE DOG suit C&ED operation need. 27/2/2019 44,000.00
Additional hose reels with associated pipeworks,
sprinkler heads with associated pipeworks, alarm
bells, breakglasses, heat detectors, flashing lights
and directional signs will be provided as per the
FS-075 FS CEBO FSD comment during their inspection on 19-22 1/3/2019 80,000.00
Additional 5nos. of 20W horn speaker
AE-009 AE CEBO to suit FS Inspection comment at CBO. 6/3/2019 28,000.00
Revise emergency lighting at
EE-182 EE CEBO CBO to suit FS Inspection comment. 6/3/2019 24,000.00

Additional VAC Panel for Pedestrian Bridge as


per GBP approval.
AC-049 AC PB 11/3/2019 50,000.00

Additional Drip Tray (c w Water Leakage


Sensor) & LCP suit user's daily operation.
AC-050 AC PTB 11/3/2019 50,000.00

Additional Drip Tray (c w Water Leakage


Sensor) & LCP suit user's daily operation.
AC-051 AC CEBI 11/3/2019 50,000.00

Additional Drip Tray (c w Water Leakage


Sensor) & LCP suit user's daily operation.
AC-052 AC CEBO 11/3/2019 50,000.00

Replace air grilles to security grille and


Additional duct-type thermostat and relocation of
the A/C controllers in Detention Quarters' area to
suit for user's operation.
AC-053 AC PTB 11/3/2019 188,000.00

Additional motorized fire and smoke dampers,


smoke detectors and associated control
accessories to suit the latest Fire Safety
Management Plan submission due to the
additional FRP ceiling. (SM-AR-968 & AI-A-
159)
AC-054 AC CEBI 11/3/2019 98,000.00

Additional motorized fire and smoke dampers,


smoke detectors and associated control
accessories to suit the latest Fire Safety
Management Plan submission due to the
additional FRP ceiling. (SM-AR-968 & AI-A-
159)
AC-055 AC CEBO 11/3/2019 98,000.00

Additional motorized fire and smoke dampers,


smoke detectors and associated control
accessories to suit the latest Fire Safety
Management Plan submission due to the
additional FRP ceiling. (SM-AR-968 & AI-A-
159)
AC-056 AC HKP 11/3/2019 109,000.00
Revise trunking routing,
adaptable box and conduit at CPK to suit ImmD's
operation need. Additional adaptable box and
EE-190 EE DPK conduit at CPK to suit C&ED's operation need. 11/3/2019 131,000.00
Revise trunking routing at GVK
to suit ImmD's operation need. Blank off 13A
F.S.U. at GVK to suit ImmD's operation need.
Additional adaptable box and conduit at GVK to
EE-191 EE GVK suit C&ED's operation need. 11/3/2019 122,000.00
Update Trunking Arrangement
EE-192 EE CBI for CBI G/F C&ED 159 Rocas Room. 11/3/2019 12,000.00
Revise F.C.U for AFA panel and
EE-193 EE FSD battery charger to switched and neon light type. 11/3/2019 5,000.00

Relocation of Two Weather-proof


Power Socket at Stair ST-02 of FSD to suit for
EE-194 EE FSD AI-WS-052 for site coordination. 11/3/2019 8,000.00
Revise lighting layout to suit with
EE-195 EE CEBI additional false ceiling. 11/3/2019 12,000.00
Revise cable containment
arrangement for 2350mm Headroom at CBI to
EE-197 EE CEBI suit C&ED operation need. 11/3/2019 197,000.00
Addition power provision and
cable containment for Government Funded Wi-Fi
EE-106 EE PTB at PTB. 11/3/2019 297,000.00
Revise power provision to suit
EE-181 EE CEBI IMMD IT daily operation. 11/3/2019 58,000.00
Addition of F.C.U for FS panel as
per approved GBP. Addition of Emergency
EE-196 EE PB lighting at G/F staircase of Pedestrian bridge. 12/3/2019 23,000.00
Revise cable containment routing
for IMMD 96 duty office console table to suit
EE-198 EE CEBI ImmD's operation need. 12/3/2019 6,000.00
Replace the luminaires to Impact
Protection type (IK10) to suit user's operation
need. Remove occupancy sensor and daylight
sensor to suit user's operation need. Relocate
water heater remote panel and lighting switch
outside the rooms to suit user's operation need.
Relocate water heater and power point to ceiling
level at shower room to suit user's operation need.
Remove power provision for Hand Dryer in the
EE-199 EE PTB shower room / toilet and socket in examination 12/3/2019 167,000.00
Additional 2 nos. of Panic Alarm
SY-012 SY PTB Button for IMMD 16 Vistor Rooms at PTB. 12/3/2019 5,000.00
Interconnect F&E trunking at PTB
EE-204 EE PTB to suit IMMD's operation need. 15/3/2019 14,000.00
Revise emergency lighting at CBO
EE-203 EE CEBO to suit FS inspection comment and aesthetic 15/3/2019 39,000.00
Additional emergency lighting and revise exit
EE-201 EE FXO sign at FXO to suit FS Inspection comment. 15/3/2019 32,000.00
Addition of MCB units and cable
EE-200 EE PTB for CEDD 5.3 convenience store. 15/3/2019 18,000.00
RFI-BS-4027 Revise raised floor sockets
EE-205 EE (PTB) arrangement in C&ED 79. 15/3/2019 277,000.00
Revise lighting and power layout
EE-206 EE FSD to suit FSD Vent/ DG comment at FSD. 15/3/2019 49,000.00
Replace and additional the institutional sprinkler
heads with the associated pipeworks in Detention
FS-072 FS PTB Quarter's area to suit the user's operation. 15/3/2019 8,000.00
Additional control module for the additional
FS-073 FS PB VAC panel as per GBP approval. 15/3/2019 10,000.00
Additional sprinkler heads with associated
pipeworks and smoke detectors will be provided
FS-074 FS HKP to suit the FSMP. 15/3/2019 41,000.00
Additional visual fire alarm will be provided as
per the FSD comment during their inspection on
FS-076 FS FXRVIS 11-12 Mar 2019. 15/3/2019 13,000.00
Additional detectors, sprinkler heads with
associated pipeworks will be provided as per the
FS-077 FS CEBI FSD comment during their inspection on 14-17 15/3/2019 21,000.00
Replacement of Protection C.T. from
2250A to 2000A in the Main LV SWBDs at CBI
SY-013 SY GVK to suit CLP comment. 15/3/2019 92,000.00
Replacement of Protection C.T. in the
SY-014 SY CPK Main LV SWBDs at CBO to suit CLP comment. 15/3/2019 62,000.00
Revise plumbing pipeworks
arrangement for 2350mm Headroom at CBI to
WS-041 WS CEBI suit C&ED operation need. 15/3/2019 246,000.00
Revise raised floor sockets
circuitry and cable containment in IMMD 20
EE-210 EE PTB Computer Server Room at PTB. 19/3/2019 206,000.00
Additional insulation for SEF LMCP panels to
AC-059 AC PTB suit FSD requirements. 20/3/2019 220,000.00
Revise the lighting and cable
EE-207 EE CEBI containment due to additional of false ceiling. 20/3/2019 25,000.00
Revise the lighting and cable
EE-208 EE CEBO containment due to additional of false ceiling. 20/3/2019 24,000.00
Additional weatherproof socket
EE-209 EE GVK for C&ED E-lock at each Kiosk. 20/3/2019 41,000.00
Revise lighting layout in CEDD
Convenience Store and ATM. Revise power
EE-211 EE PTB provision for ATM, Convenience Store and 20/3/2019 63,000.00
Cut off data conduit below raised
EE-212 EE CEBI floor and reserved 100mm under raised floor. 20/3/2019 7,000.00
Extension of 200 mm CT cable
EE-213 EE CEBO tray under raised floor in C&ED 186 NER at 20/3/2019 3,000.00
Revise the power provision for
SM/BS/391 shielding door from 2 nos. of 20 SPN to 2 nos. of
EE-216 EE (FXI&O) 32A TPN for FXI and FXO. 21/3/2019 12,000.00
Revise lighting layout in C&ED
EE-217 EE DOG NER at DOG. 21/3/2019 11,000.00
Addition of power point for water
leakage detection control panel. Additional of
EE-186 EE PTB power points for PABX racks. 21/3/2019 7,000.00
Addition of power point for water
leakage detection control panel. Additional of
EE-187 EE CEBI power points for PABX racks. 21/3/2019 2,000.00
Addition of power point for water
leakage detection control panel. Additional of
EE-188 EE CEBO power points for PABX racks. 21/3/2019 5,000.00
Revise emergency lighting and
exit sign at CBI to suit FS Inspection comment
EE-214 EE CEBI and aesthic concern. 21/3/2019 49,000.00
Remove 4 nos of lighting fittings
L34 to suit user's operation need. Change 9 nos.
socket outlet to 6 nos. of floor box to suit user's
EE-215 EE FSD operation need. 21/3/2019 31,000.00
Revise power provision to suit
EE-218 EE CEBO IMMD IT daily operation. 21/3/2019 42,000.00
Revise PTB IMMD resilience
room sockets circuitry and cable containment
EE-228 EE PTB arrangement. 25/3/2019 151,000.00
Revise power provision to suit
EE-189 EE PTB IMMD IT daily operation. 27/3/2019 293,000.00
Addition of 1 no. of 100x100 ARS Trunking at
EE-220 EE CEBI CBI. 27/3/2019 6,000.00
SM/BS/209 Additional 4 nos. of Power Point
EE-221 EE (PTB) for Triangular Totem Board at PTB 2/F. 27/3/2019 37,000.00
Additional conduit and adaptable
box to interconnect at FSD to suit user's operation
EE-222 EE FSD need. 27/3/2019 7,000.00
Modification of Power Requirements for Revised
EE-223 EE FSD Folding Gates at Building 3 (FSD). 27/3/2019 32,000.00
SM/BS/277 Addition of conduits and adaptable
EE-224 EE (FSD) box for card access of door G03 at FSD. 27/3/2019 3,000.00
Relocate lightings and sensors to
EE-225 EE CEBI suit FRP enclosure for FS re-inspection. 27/3/2019 105,000.00
Addition of normal MCB Board,
RCD Board and MCB Units for C&ED 245 and
EE-226 EE PCEBI&O 262 NER under raised floor sockets. 27/3/2019 60,000.00
Addition of normal MCB Board,
RCD Board and MCB Units for C&ED 77 NER 1
EE-227 EE PTB under raised floor sockets. 27/3/2019 83,000.00
Relocation of Electrical Provision
in detention area corridor. Addition of F.C.U for
EE-229 EE HKP MFSD in detention area corridor. 27/3/2019 51,000.00
Revise lighting layout of PTB 2/F
C&ED 35 Video Interview room due additional
of False ceiling. Relocation of F.S.U to suit for
RFI-BS-3825 the newlocation of indoor units in PTB 2/F
EE-230 EE (PTB) C&ED 24 Special Equipment Store. 27/3/2019 33,000.00
Revise power supply for for
EE-231 EE CEBI IMMD 100 raised floor sockets. 27/3/2019 170,000.00
Revise sprinkler pipework routing to suit IMMD's
FS-079 FS GVK operation need. 27/3/2019 9,000.00
Additional sprinkler heads with associated
FS-080 FS PTB pipeworks will be provided as the change of 27/3/2019 65,000.00
Relocation of the VRV indoor units to suit for tha
AC-060 AC PTB additional false ceiling. 28/3/2019 12,000.00
Additional hose reels with associated pipeworks,
alarm bells, breakglasses, flashing lights, fire
extinguishers, sand buckets, directional signs and
FS-071 FS PTB exit signs will be provided as per the FSD 28/3/2019 1,055,000.00
Revise power and cable containment
EE-232 EE HKP layout at POB to suit user's operation need. 29/3/2019 89,000.00
Addition of 2 nos. of 32mm dia
conduits connected from FEHD 6 to 2 nos. of
adaptor boxes at low level for FEHD sever rack
in FEHD server room. Addition of 2 nos. of
25mm dia conduits with 75x75 adaptor boxes
EE-233 EE PTB connected from FEHD server room to TEL 29/3/2019 6,000.00
Addition of adaptor box and
EE-234 EE GVK associated conduits for DICS CCTV at GVK. 29/3/2019 2,500.00
Addition of adaptor box and
EE-235 EE CPK associated conduits for DICS CCTV at CPK. 29/3/2019 2,500.00
Provision of earthing system to suit
EE-239 EE CEBI with latest design. 29/3/2019
Relocate the panel of fixed sprayer unit in FSD
FS-078 FS FSD 10b DG store Cat 5 to suit the DG requirement. 29/3/2019 17,000.00
Revise HKPF IT Trunking at PTB to
EE-240 EE PTB suit user requirements. 1/4/2019 23,000.00
Provision of earthing system to suit
EE-241 EE CEBO with latest design. 1/4/2019
Provision of earthing system to suit
EE-242 EE FXRVIS with latest design. 1/4/2019
Provision of earthing system to suit
EE-243 EE HKP with latest design. 1/4/2019
Provision of earthing system to suit
EE-244 EE FSD with latest design. 1/4/2019
EE-246 EE GVK Addition of F.S.U for FS panel at GVK. 2/5/2019 36,000.00
EE-247 EE MS1 Addition of F.S.U for FS panel at MS1 2/5/2019 2,000.00
EE-248 EE MS2 Addition of F.S.U for FS panel at MS2 2/5/2019 48,000.00
Relocation of Junction box and Trunking as per
AC-061 AC FSD FSD's Comments during FS inspection on 15 Feb, 3/5/2019 5,000.00
The heat detector with the associated cable /
FS-081 FS FSD wiring shall be replaced to be intrinsically safe 14/5/2019 32,000.00
The heat detector with the associated cable /
FS-082 FS PTB wiring shall be replaced to be intrinsically safe 14/5/2019 46,000.00
Relocate lighting switch and adaptable
box at POB to suit FS Inspection comment.
EE-245 EE HKP Change the type of exit sign to T1-E1 at 6/F 14/5/2019 9,000.00
Change the lighting fitting in LPG
store and vaporizer room to explosionproof type.
Additional of weatherproof switch outside LPG
store and vaporizer room in PTB away from
hazard zone. Provision of MICC Cables for
EE-249 EE PTB electrical wiring inside LPG room and vaporizer 14/5/2019 70,000.00
Revise provision and arrangement of
EE-202 EE PTB exit sign and directional sign in PTB. 17/5/2019 298,000.00
Addiiton of 2 nos. of L2E and
exchange location of 1 no. of L5E and L5 as per
comments from FS inspection. Addiional F.S.U
EE-250 EE CEBI for MSFD in C&ED detention cell area in CBI. 17/5/2019 42,000.00
Revise provision and arrangement of
EE-251 EE PTB emergency lighting in PTB. 17/5/2019 273,000.00
Additional control module for interfacing the fire
signal from subway, additional directional signs
to suit the approved GBP and hose reels widl be
FS-083 FS PTB added and relocated to suit the latest approved 17/5/2019 299000.00
Additional alarm bells will be provided as per the
FS-084 FS CEBI FSD comment during their inspection on 8-10 17/5/2019 46,000.00
Additional valve with associated
pipeworks will be provided to suit the WSD
WS-042 WS MLP requirement. 17/5/2019 150,000.00
Revise of drainage pipeworks
SD-059 SD MS2 routing to match the SCCU approval drawing 17/5/2019 192,000.00
Revise of drainage pipeworks
SD-060 SD SEW routing to match the SCCU approval drawing 17/5/2019 168,000.00
Addition of exit sign to suit FSD
EE-252 EE PUT approval GBP for PUT. 23/5/2019 32,000.00
Relocation of sprinkler heads with associated
pipework will be required in order to prevent the
FS-085 FS FSD clash at the top of furnitures. 24/5/2019 143,000.00
Revised the sprinkler heads for 2350mm
FS-086 FS CEBI headroom at CEBI to suit C&ED operation need. 24/5/2019 73,000.00
Revised the sprinkler heads for 2350mm
FS-087 FS CEBO headroom at CEBO to suit C&ED operation 29/5/2019 65,000.00
Additional fire extinguishers will be provided as
FS-088 FS PUT per the FSD comment during their inspection on 29/5/2019 3,000.00
Addition 32mm PVC conduit connected to
EE-254 EE MS2 drawpit. 29/5/2019 5,000.00
Relocation of Electrical Provision in
EE-255 EE PTB detention area corridor. 29/5/2019 279,000.00
Additional power points for ACMV
EE-256 EE PTB trade for FS inspections. 29/5/2019 274,000.00
Additional power points for FS trade
EE-257 EE PTB for FS inspections. 29/5/2019 136,000.00
Addition of emergency lighting in
EE-259 EE PUT electrical cabinet. 29/5/2019 12,000.00
Revise exit sign provision in 1/F and
2/F. Revise emergency lighting for IMMD 21
EE-260 EE PTB UPS Room. Additional lighting in Ventilation 29/5/2019 97,000.00

AE-010 AE CEBI Re-wiring Speaker at CBI Corridor. 30/5/2019 77,000.00


Relocate ImmD traditional counter
EE-258 EE PTB lighting switch. 30/5/2019 85,000.00
Additional of exit sign according to
EE-261 EE MS2 GBP. 30/5/2019 12,000.00
Addition of tee-off trunking from
existing PABX trunking connected to nearest
EE-262 EE CEBI point of existing telephone trunknig. 30/5/2019 7,000.00
Addition of tee-off trunking from
existing PABX trunking connected to nearest
EE-263 EE CEBO point of existing telephone trunknig. 30/5/2019 7,000.00

EE-264 EE PTB Additional cables for MoE lighting. 6/6/2019 123,000.00


Additional racks for PA system in
AE-011 AE PB Brdige C. 6/6/2019 297,000.00
Additional conduits for the connection from
direct fire telephone link connection point to FS
FS-089 FS MLP panel will be provided. 6/6/2019 290,000.00
Additional heat detectors and remote indicators
FS-090 FS CEBO will be provided as per FSD inspection on 3 June 6/6/2019 53,000.00
Additional fused connection units for
EE-265 EE CEBI lift panel. 10/6/2019 12,000.00
Additional fused connection units for
EE-266 EE CEBO lift panel. 10/6/2019 6,000.00
Addition of fused connection unit for
EE-253 EE PTB CCTV and PA rack in PTB. 17/6/2019 193,000.00
The status of motorized fire and smoke dampers
shall be changed from normally open to normally
AC-062 AC PTB closed as per FSD's comments. 17/6/2019 65,000.00
Relocate the fire hydrant with associated
FS-092 FS CEBO pipeworks to suit the approved GBP 21/6/2019 69,000.00
Additional visual fire alarm will be provided to
FS-093 FS Weigh Station suit the approved GBP 21/6/2019 12,000.00
Additional alarm bells will be provided and
Viusal fire alarm will be deleted as per FSD
FS-094 FS GVK (I&O) inspection on 26-27 June 2019 28/6/2019 108,000.00
Additional hose reel with associated pipeworks,
alarm bell and breakglass will be provided as per
FSD inspection on
FS-095 FS MS2 24-25 June 2019. 28/6/2019 113,000.00
Addition of lighting as per FSD
inspector inspection comment on 24 June, 2019
EE-267 EE MS2 for Building "Irrigation Pump Room". 2/7/2019 13,000.00
Addition of lighting as per FSD inspector
inspection comment on 24 June, 2019 for
EE-268 EE MS1 Building "EUVSS". 2/7/2019 40,000.00

Addition of lighting as per FSD inspector


inspection comment on 26 June, 2019 for
EE-269 EE GVK Building "GVKIO". 5/7/2019

FS-096 FS MS2 Additional Breakglass unit and fire extinguisher 5/7/2019 7000
Additional alarm bells and sprinkler heads with
associated pipeworks will be provided as per FSD
FS-097 FS C&PCK comments on 4 July 2019 5/7/2019 136,000.00
Additional E-lighting for Coach canoply and
EE-270 EE PTB additional F.C.U for FS panel outside DG Store 9/7/2019 143,000.00
Additional F.C.U for FS panel outside DG Store
and additional F.C.U for ELV Equipment from
EE-271 EE FSD RFI-BS-4037 9/7/2019 31,500.00
Additional alarm bells, breakglass and sprinkler
heads with associated pipeworks will be provided
as per FSD comments on 4
FS-098 FS PCEB July 2019 9/7/2019 120,000.00
As per FSD inspector's request, 93°C high
temperature sprinklers instead of 68°C normal
temperature sprinklers will be
provided under skylights/glazed roof of Coach
Covered Walkway
and Glazed Canopy to suit Clause 14.4 of BS EN
FS-091 FS PTB 12845:2003. 17/7/2019 297,000.00
Additional monitor modules for the interface of
the control of fire
shutters at 1/F Supermarket & 2/F Convenience
Store between
AC & FS will be provided as per FSD comments
FS-100 FS PTB on 12 July 2019 17/7/2019 5,000.00
Addotional directional sign, exit sign, visual fire
alarm and breakglass unit will be provided as per
FS-101 FS PB FSD comments on 15 July 2019 17/7/2019
Addotional alarm bell and breakglass unit will be
FS-102 FS MS2 provided as per FSD comments on 15 July 2019 17/7/2019 27,000.00

EE-274 EE PB Additional E-lighting for PB 19/7/2019 33,000.00

AE-012 AE PB Additional speakers for PB 19/7/2019 90,000.00

EE-275 EE PTB Additional concealed conduit for IMMD 75 20/7/2019 12,000.00


Additional alarm bells, breakglass units,visual
fire alarms, heat detectors and sprinkler heads
will be provided as per FSD comments on 12 July
2019
FS-103 FS PTB Relocation of fire hydrants as per FSD comments 23/7/2019 235000
1. Revise layout to suit the latest architectural
layout (AI-A-019).
FS-012 FS MS2 2. Review the use of settlement joint. 191,000.00

EE-272 EE PTB Additional E-lighting for SES panel, last exit 24/7/2019
Additional E-lighting for small rooms and
EE-273 EE PTB protected lobby 24/7/2019
Additional of repeated FS signal to RF Exit Door
SY-054 SY PTB for emergency release 26/7/2019 9,800.00

EE-276 EE PCEBIO Additional - E - Lighting 26/7/2019 111,000.00