Вы находитесь на странице: 1из 15

SECOND DIVISION Respondent did not immediately undertake the

[G.R. No. 159411. March 18, 2005] necessary repairs as the water level was still
TEODORO I. CHAVEZ, petitioner, vs. HON. high. Three (3) weeks later, respondent was
COURT OF APPEALS and JACINTO S. informed by a barangay councilor that major
TRILLANA, respondents. repairs were being undertaken in the fishpond
DECISION with the use of a crane. Respondent found out
PUNO, J.: that the repairs were at the instance of
Assailed in this petition for review is the petitioner who had grown impatient with his
Decision dated April 2, 2003[1] of the Court of delay in commencing the work.
Appeals in CA-G.R. CV No. 59023[2] which In September 1996, respondent filed a
modified the Decision dated December 15, complaint before the Office of
1997 of the Regional Trial Court (RTC) of the Barangay Captain of Taliptip, Bulacan,
Valenzuela City, Branch 172, in Civil Case No. Bulacan. He complained about the
5139-V-97, as well as its Resolution dated unauthorized repairs undertaken by petitioner,
August 8, 2003[3] which denied petitioners the ouster of his personnel from the leased
motion for reconsideration. premises and its unlawful taking by petitioner
The antecedent facts are as follows: despite their valid and subsisting lease
In October 1994, petitioner Teodoro contract. After conciliation proceedings, an
Chavez and respondent Jacinto Trillana agreement was reached, viz.:
entered into a contract of lease[4] whereby the KASUNDUAN
former leased to the latter his fishpond at Sitio Napagkasunduan ngayong araw na to ika-17
Pariahan, Taliptip, Bulacan, Bulacan, for a term ng Setyembre ng nagpabuwis Teodoro Chavez
of six (6) years commencing from October 23, at bumubuwis na si G. Jay Trillana na ibabalik
1994 to October 23, 2000. The rental for the ni G. Chavez ang halagang P150,000.00 kay
whole term was two million two hundred forty G. Trillana bilang sukli sa natitirang panahon
thousand (P2,240,000.00) pesos, of which one ng buwisan.
million (P1,000,000.00) pesos was to be paid Ngunit kung maibibigay ni G. Chavez ang
upon signing of the contract. The balance was halagang P100,000.00 bago sumapit o
payable as follows: pagsapit ng ika-23 ng Setyembre, taong
b. That, after six (6) months and/or, on or kasalukuyan, to ay nangangahulugan ng
before one (1) year from the date of signing buong kabayaran at hindi P150,000.00.
this contract, the amount of THREE Kung sakali at hindi maibigay ang P100,000.00
HUNDRED FORTY-FOUR THOUSAND ang magiging kabayaran ay
(P344,000.00) pesos shall be paid on April 23, mananatiling P150,000.00 na may paraan ng
1995 and/or, on or before October 23, 1995 pagbabayad ng sumusunod:
shall be paid by the LESSEE to the LESSOR. Ang P50,000.00 ay ibibigay bago sumapit o
c. That, the LESSEE, shall pay the amount of pagsapit ng ika-31 ng Oktubre 1996 at ang
FOUR HUNDRED FORTY-EIGHT balanseng P100,000.00 ay ibibigay sa loob ng
THOUSAND (P448,000.00) pesos x x x to the isang taon subalit magbibigay ng promissory
LESSOR on April 23, 1997 and/or, on or before note si G. Chavez at kung mabubuwisang ang
October 23, 1997, and on April 23, 1998 kanyang palaisdaan ay ibibigay lahat ni G.
and/or, on or before October 23, 1998 the Chavez ang buong P150,000.00 sa lalong
amount of FOUR HUNDRED FORTY-EIGHT madaling panahon.
THOUSAND (P448,000.00) pesos x x x. Kung magkakaroon ng sapat at total na
Paragraph 5 of the contract further provided kabayaran si G. Chavez kay G. Trillana ang
that respondent shall undertake all construction huli ay lalagda sa kasulatan bilang waiver o
and preservation of improvements in the walang anumang paghahabol sa nabanggit na
fishpond that may be destroyed during the buwisan.
period of the lease, at his expense, without Alleging non-compliance by petitioner with
reimbursement from petitioner. their lease contract and the
In August 1996, a powerful typhoon hit the foregoing Kasunduan, respondent filed a
country which damaged the subject fishpond. complaint on February 7, 1997 against
petitioner before the RTC of Valenzuela City, matter thereof, his alleged violation of the lease
docketed as Civil Case No. 5139-V-97. contract with respondent, was already
Respondent prayed that the following amounts amicably settled before the Office of
be awarded him, viz.: (a) P300,000.00 as the Barangay Captain of Taliptip, Bulacan,
reimbursement for rentals of the leased Bulacan. Petitioner argued that respondent
premises corresponding to the unexpired should have followed the procedure for
portion of the lease contract; (b) P500,000.00 enforcement of the amicable settlement as
as unrealized profits; (c) P200,000.00 as moral provided for in the Revised Katarungang
damages; (d) P200,000.00 as exemplary Pambarangay Law. Assuming arguendo that
damages; and, (e) P100,000.00 as attorneys the RTC had jurisdiction, it cannot award more
fees plus P1,000.00 for each court appearance than the amount stipulated in the Kasunduan
of respondents counsel. which is P150,000.00. In any event, no factual
Petitioner filed his answer but failed to or legal basis existed for the reimbursement of
submit the required pretrial brief and to attend alleged advance rentals for the unexpired
the pretrial conference. On October 21, 1997, portion of the lease contract as well as for
respondent was allowed to present his moral and exemplary damages, and attorneys
evidence ex-parte before the Acting Branch fees.
Clerk of Court.[5] On the basis thereof, a Indeed, the Revised Katarungang
decision was rendered on December 15, Pambarangay Law[8] provides that an
1997[6] in favor of respondent, the dispositive amicable settlement reached after barangay
portion of which reads: conciliation proceedings has the force and
WHEREFORE, judgment is hereby rendered effect of a final judgment of a court if not
as follows: repudiated or a petition to nullify the same is
(1) Ordering the defendant to reimburse to the filed before the proper city or municipal court
plaintiff the sum of P300,000.00 representing within ten (10) days from its date.[9] It further
rental payment of the leased premises for the provides that the settlement may be enforced
unused period of lease; by execution by the lupong tagapamayapa
(2) Ordering the defendant to pay plaintiff the within six (6) months from its date, or by action
sum of P500,000.00 representing unrealized in the appropriate city or municipal court, if
profit as a result of the unlawful deprivation by beyond the six-month period.[10] This special
the defendant of the possession of the subject provision follows the general precept
premises; enunciated in Article 2037 of the Civil
(3) Ordering the defendant to pay plaintiff the Code, viz.:
sum of P200,000.00 as moral damages; A compromise has upon the parties the effect
(4) Ordering the defendant to pay plaintiff the and authority of res judicata; but there shall be
sum of P200,000.00 as exemplary damages; no execution except in compliance with a
and judicial compromise.
(5) Ordering the defendant to pay plaintiff the Thus, we have held that a compromise
sum of P100,000.00 as and for attorneys fees, agreement which is not contrary to law, public
plus costs of suit. order, public policy, morals or good customs is
Petitioner appealed to the Court of Appeals a valid contract which is the law between the
which modified the decision of the trial court by parties themselves.[11] It has upon them the
deleting the award of P500,000.00 for effect and authority of res judicata even if not
unrealized profits for lack of basis, and by judicially approved,[12] and cannot be lightly set
reducing the award for attorneys fees aside or disturbed except for vices of consent
to P50,000.00.[7] Petitioners motion for and forgery.[13]
reconsideration was denied. Hence, this However, in Heirs of Zari, et al. v.
petition for review. Santos,[14] we clarified that the broad precept
Petitioner contends that the Court of enunciated in Art. 2037 is qualified by Art. 2041
Appeals erred in ruling that the RTC of of the same Code, which provides:
Valenzuela City had jurisdiction over the action If one of the parties fails or refuses to abide by
filed by respondent considering that the subject the compromise, the other party may either
enforce the compromise or regard it as party entitled thereto; and (b) an action in
rescinded and insist upon his original demand. regular form, which remedy is
We explained, viz: judicial.[21] However, the mode of enforcement
[B]efore the onset of the new Civil Code, there does not rule out the right of rescission under
was no right to rescind compromise Art. 2041 of the Civil Code. The availability of
agreements. Where a party violated the terms the right of rescission is apparent from the
of a compromise agreement, the only recourse wording of Sec. 417[22] itself which provides
open to the other party was to enforce the that the amicable settlement may be enforced
terms thereof. by execution by the lupon within six (6) months
When the new Civil Code came into being, its from its date or by action in the appropriate city
Article 2041 x x x created for the first time the or municipal court, if beyond that period. The
right of rescission. That provision gives to the use of the word may clearly makes the
aggrieved party the right to either enforce the procedure provided in the Revised
compromise or regard it as rescinded and Katarungang Pambarangay Law
insist upon his original demand. Article 2041 directory[23] or merely optional in nature.
should obviously be deemed to qualify the Thus, although the Kasunduan executed
broad precept enunciated in Article 2037 that by petitioner and respondent before the Office
[a] compromise has upon the parties the effect of the Barangay Captain had the force and
and authority of res judicata. (underscoring effect of a final judgment of a court, petitioners
ours) non-compliance paved the way for the
In exercising the second option under Art. application of Art. 2041 under which
2041, the aggrieved party may, if he chooses, respondent may either enforce the
bring the suit contemplated or involved in his compromise, following the procedure laid out in
original demand, as if there had never been the Revised Katarungang Pambarangay
any compromise agreement, without bringing Law, or regard it as rescinded and insist upon
an action for rescission.[15] This is because he his original demand. Respondent chose the
may regard the compromise as already latter option when he instituted Civil Case No.
rescinded[16] by the breach thereof of the other 5139-V-97 for recovery of unrealized profits
party. and reimbursement of advance rentals, moral
Thus, in Morales v. National Labor and exemplary damages, and attorneys fees.
Relations Commission[17] we upheld the Respondent was not limited to
National Labor Relations Commission when it claiming P150,000.00 because although he
heeded the original demand of four (4) workers agreed to the amount in the Kasunduan, it is
for reinstatement upon their employers failure axiomatic that a compromise settlement is not
to comply with its obligation to pay their an admission of liability but merely a
monetary benefits within the period prescribed recognition that there is a dispute and an
under the amicable settlement. We reiterated impending litigation[24] which the parties hope
the rule that the aggrieved party may either (1) to prevent by making reciprocal concessions,
enforce the compromise by a writ of execution, adjusting their respective positions in the hope
or (2) regard it as rescinded and so insist upon of gaining balanced by the danger of
his original demand upon the other partys losing.[25] Under the Kasunduan, respondent
failure or refusal to abide by the compromise. was only required to execute a waiver of all
We also recognized the options in Mabale v. possible claims arising from the lease contract
Apalisok,[18] Canonizado v. if petitioner fully complies with his obligations
Benitez,[19] and Ramnani v. Court of thereunder.[26] It is undisputed that herein
Appeals,[20] to name a few cases. petitioner did not.
In the case at bar, the Revised Having affirmed the RTCs jurisdiction over
Katarungang Pambarangay Law provides for the action filed by respondent, we now resolve
a two-tiered mode of enforcement of an petitioners remaining contention. Petitioner
amicable settlement, to wit: (a) by execution by contends that no factual or legal basis exists
the Punong Barangay which is quasi-judicial for the reimbursement of alleged advance
and summary in nature on mere motion of the rentals, moral and exemplary damages, and
attorneys fees awarded by the court a quo and We likewise sustain the award for exemplary
the Court of Appeals. damages considering petitioners propensity not
The rule is that actual damages cannot be to honor his contractual obligations, first under
presumed, but must be proved with a the lease contract and second, under the
reasonable degree of certainty.[27] In the case amicable settlement executed before the Office
at bar, we agree with petitioner that no of the Barangay Captain. Since respondent
competent proof was presented to prove that was compelled to litigate and incur expenses to
respondent had paid P300,000.00 as advance protect his interest on account of petitioners
rentals for the unexpired period of the lease refusal to comply with his contractual
contract. On the contrary, the lease contract obligations,[30] the award of attorneys fees has
itself provided that the remaining rentals to be sustained.
of P448,000.00 shall be paid on April 23, 1997 IN VIEW WHEREOF, the petition is
and/or, on or before October 23, 1997, and on PARTIALLY GRANTED. The assailed Decision
April 23, 1998 and/or, on or before October 23, dated April 2, 2003 of the Court of Appeals in
1998 the amount P448,000.00. Respondent CA-G.R. CV No. 59023 is modified by deleting
filed his complaint on February 7, 1997. No the award of P300,000.00 as reimbursement of
receipt or other competent proof, aside from advance rentals. The assailed Decision is
respondents self-serving assertion, was AFFIRMED in all other respects.
presented to prove that respondent paid the SO ORDERED.
rentals which were not yet due. No proof was Austria-Martinez, Callejo, Sr.,
even presented by respondent to show that he Tinga, and Chico-Nazario, JJ., concur.
had already paid P1,000,000.00 upon signing
of the lease contract, as stipulated therein.
Petitioner, in paragraphs 2 and 7 of his
answer,[28] specifically denied that respondent William Golangco Construction Corporation
did so. Courts must base actual damages v. Ray Burton
suffered upon competent proof and on the best Development Corporation, G.R. No. 163582,
obtainable evidence of the actual amount August 9, 2010
thereof.[29] Facts:
As to moral damages, Art. 2220 of Ray Burton Development Corporation
the Civil Code provides that same may be (RBDC) and William Golangco Construction
awarded in breaches of contract where the Corporation (WGCC) entered into a Contract
defendant acted fraudulently or in bad faith. In for the construction of the Elizabeth Place
the case at bar, respondent alleged that (Office/Residential Condominium).
petitioner made unauthorized repairs in the WGCC filed a complaint with a request
leased premises and ousted his personnel for arbitration with the Construction Industry
therefrom despite their valid and subsisting Arbitration Commission (CIAC). In its
lease agreement. Petitioner alleged, by way of complaint, private respondent prayed that
defense, that he undertook the repairs because CIAC render judgment ordering petitioner to
respondent abandoned the leased premises pay private respondent the amount of, to wit:
and left it in a state of disrepair. However, 1. P24,703,132.44 for the unpaid
petitioner presented no evidence to prove his balance on the contract price;
allegation, as he did not attend the pretrial 2. P10,602,670.25 for the unpaid
conference and was consequently declared in balance on the labor cost
default. What remains undisputed therefore is adjustment;
that petitioner had a valid and subsisting lease 3. P9,264,503.70 for the unpaid
contract with respondent which he refused to balance of additive works;
honor by giving back possession of the leased 4. P2,865,615.10 for extended
premises to respondent. We therefore sustain overhead expenses;
the conclusion of both the trial court and the
Court of Appeals that an award of moral
damages is justified under the circumstances.
5. P1,395,364.01 for materials Board of Arbitrators shall be submitted to the
cost adjustment and trade Construction Arbitration Authority created by
contractors' utilities expenses; the government, which is no other than the
6. P4,835,933.95 for interest CIAC. Moreover, other matters not dealt with
charges on unpaid overdue by provisions of the contract or by special
billings on labor cost adjustment agreements shall be governed by provisions of
and change orders. the Construction Industry Arbitration Law, or
or for a total of Fifty Three Million Six Hundred Executive Order No. 1008.
Sixty-Seven Thousand Two Hundred Nineteen Petitioner's claims that it is entitled to
and 45/xx (P53,667,219.45) and interest payment for several items under their contract,
charges based on the prevailing bank rates on which claims are, in turn, refuted by
the foregoing amount from March 1, 2002 and respondent, involves a "dispute arising from
until such time as the same shall be fully paid. differences in interpretation of the contract.
RBDC filed a Motion to Dismiss the Under Section 1, Article III of the CIAC
aforesaid complaint on the ground of lack of Rules, an arbitration clause in a construction
jurisdiction. It is petitioner's contention that the contract shall be deemed as an agreement to
CIAC acquires jurisdiction over disputes arising submit an existing or future controversy to
from or connected with construction contracts CIAC jurisdiction, "notwithstanding the
only when the parties to the contract agree to reference to a different arbitration institution or
submit the same to voluntary arbitration. In the arbitral body in such contract x x x."
contract between petitioner and private Elementary is the rule that when laws or rules
respondent, petitioner claimed that only are clear, it is incumbent on the court to apply
disputes by reason of differences in them. When the law (or rule) is unambiguous
interpretation of the contract documents shall and unequivocal, application, not interpretation
be deemed subject to arbitration. thereof, is imperative.
Issue: whether or not CIAC has jurisdiction It bears to emphasize that the mere
over the case. existence of an arbitration clause in the
Held: CIAC had jurisdiction over the dispute construction contract is considered by law as
between herein parties an agreement by the parties to submit existing
The CIAC has original and exclusive or future controversies between them to CIAC
jurisdiction over disputes arising from, or jurisdiction, without any qualification or
connected with, contracts entered into by condition precedent. To affirm a condition
parties involved in construction in the precedent in the construction contract, which
Philippines and all that is needed for the CIAC would effectively suspend the jurisdiction of the
to acquire jurisdiction is for the parties to agree CIAC until compliance therewith, would be in
to submit the same to voluntary arbitration. conflict with the recognized intention of the law
Respondent's contention, that the only disputes and rules to automatically vest CIAC with
it agreed to submit to voluntary arbitration are jurisdiction over a dispute should the
those arising from interpretation of contract construction contract contain an arbitration
documents and it argued that the claims clause.
alleged in petitioner's complaint are not Moreover, the CIAC was created in
disputes arising from interpretation of contract recognition of the contribution of the
documents, hence, the CIAC cannot assume construction industry to national development
jurisdiction over the case, is tenuous. goals. Realizing that delays in the resolution of
The contract between herein parties construction industry disputes would also hold
contained an arbitration clause which mean up the development of the country, Executive
that parties agreed to submit disputes arising Order No. 1008 expressly mandates the CIAC
by reason of differences in interpretation of the to expeditiously settle construction industry
contract to a Board of Arbitrators the disputes and, for this purpose, vests in the
composition of which is mutually agreed upon CIAC original and exclusive jurisdiction over
by the parties, and, as a last resort, any other disputes arising from, or connected with,
dispute which had not been resolved by the
contracts entered into by the parties involved in Agreement.
construction in the Philippines.
Thus, there is no question that in this As the impasse remained unresolved, BCA
case, the CIAC properly took cognizance of filed a Request for Arbitration dated April 7,
petitioner's complaint as it had jurisdiction over 2006 with the Philippine Dispute Resolution
the same. Center, Inc. (PDRCI), pursuant to Section
19.02 of the Amended BOT Agreement which
Philippine Supreme Court Decision: provides:
Department of Foreign Affairs and Bangko Section 19.02. Failure to Settle Amicably — If
Sentral ng Pilipinas vs. Falcon and BCA the Dispute cannot be settled
International Corporation; G.R. No. 176657; amicably within ninety (90) days by mutual
September 1, 2010. discussion as contemplated under
Section 19.01 herein, the Dispute shall be
The Philippine Department of Foreign Affairs settled with finality by an arbitrage
(“DFA”) implemented its Machine tribunal operating under International Law,
Readable Passport and Visa Project (the hereinafter referred to as the
“MRPV Project”) under the Build-Operate- "Tribunal", under the UNCITRAL Arbitration
andTransfer (“BOT”) scheme. Pursuant to the Rules contained in Resolution
BOT Law, having found that BCA 31/98 adopted by the United Nations General
International Corporation (“BCA”) submitted the Assembly on December 15, 1976,
sole complying bid, direct negotiations and entitled "Arbitration Rules on the United
were commenced between DFA and BCA for Nations Commission on the
the MRPV Project. In compliance with the International Trade Law". The DFA and the
Notice of Award and the BOT Law, BCA BCA undertake to abide by and
incorporated a project company, the Philippine implement the arbitration award. The place of
Passport Corporation (“PPC”) to undertake and arbitration shall be Pasay City,
implement the MRPV Project. Philippines, or such other place as may
Consequently, on February 8, 2001 a Build- mutually be agreed upon by both parties.
Operate-Transfer Agreement (“BOT The arbitration proceeding shall be conducted
Agreement”) was entered into by the DFA and in the English language.
the PPC. Later, an Amended BOT
Agreement was entered into by the DFA and Thereafter, the DFA and the Bangko Sentral ng
BCA with the conformity of PPC. Then, an Pilipinas (“BSP”) entered into a
Assignment Agreement was executed by BCA Memorandum of Agreement for the latter to
and PPC, whereby BCA assigned and provide the former passports compliant
ceded its rights, title, interest and benefits with international standards. The BSP then
arising from the Amended BOT Agreement to solicited bids for the supply, delivery,
PPC. installation and commissioning of a system for
the production of Electronic Passport
On December 9, 2005, the DFA sent a Notice Booklets or e-Passports.
of Termination to BCA and PPC due to Thus, BCA filed a Petition for Interim Relief
their alleged failure to submit proof of financial under Section 28 of the Alternative Dispute
capability to complete the entire MRPV Resolution Act of 2004 (the “ADR Act of
Project in accordance with the financial 2004”), with the Regional Trial Court of Pasig
warranty under Section 5.02 (A) of the City. In that petition, BCA prayed for, among
Amended others, that the trial court grant interim
BOT Agreement. On December 14, 2005, BCA relief to BCA prior to the constitution of the
sent a letter to the DFA demanding that arbitral tribunal in the form an order
it immediately reconsider and revoke its temporarily restraining the DFA and BSP and
previous notice of termination, otherwise, BCA their agents (i) from awarding a new
would be compelled to declare the DFA in contract to implement the MRPV Project, or
default pursuant to the Amended BOT any similar electronic passport or visa
project; or (ii) if such contract has been held that the issuance of the injunction by the
awarded, from implementing such MRPV trial court was not warranted and
Project amounted to grave abuse of discretion.
or similar projects until further orders from the
court. The Supreme Court emphasized that its
decision touches only on the issues of (a) the
On January 23, 2007, the trial court ordered jurisdiction of the trial court to issue a writ of
the issuance of a temporary restraining order preliminary injunction as an interim relief
restraining the DFA and the BSP and their under the factual milieu of this case; and (b)
agents from awarding a new contract to the entitlement of BCA to injunctive relief.
implement the MVPV Project or any similar The merits of the DFA and BCA's dispute
electronic passport or visa project, or if such regarding the termination of the Amended
contract has been awarded, from implementing BOT Agreement must be threshed out in the
such or similar projects. proper arbitration proceedings. The civil
After hearing, the trial court issued an Order case pending before the trial court is purely for
granting BCA's application for preliminary the grant of interim relief since the main
injunction. Hence, the DFA and the BSP filed a case is to be the subject of arbitration
Petition before the Supreme Court proceedings.
assailing the order of the trial court and the
issuance of the writ of preliminary injunction. The Supreme Court noted that during the
The Supreme Court noted that under Section pendency of this case, the arbitration case was
28 of the ADR Act of 2004, the grant of an dismissed by the PDRCI for lack of jurisdiction,
interim measure of protection by the proper in view of the lack of agreement
court before the constitution of an arbitral between the parties to arbitrate before the
tribunal is allowed. PDRCI. The Supreme Court held that in view
of intervening circumstances, BCA can no
The Supreme Court also stated that the ADR longer be granted injunctive relief and the civil
Act of 2004 is a general law applicable to all case before the trial court should be
matters and controversies to be resolved accordingly dismissed. However, this is without
through alternative dispute resolution methods. prejudice to the parties resolving the main
This law allows a Regional Trial Court to grant controversy in arbitration proceedings, in
interim or provisional relief, including accordance with the provisions of the
preliminary injunction, to parties in an Amended BOT Agreement, which should
arbitration case prior to the constitution of the proceed
arbitral tribunal. This general statute, however, with dispatch.
must give way to a special law governing
national government projects, namely, Republic of the Philippines
Republic Act No. 8975 which prohibits courts, Supreme Court
except the Supreme Court, from issuing a Manila
temporary restraining order and/or a writ of
preliminary injunction in cases involving
national government projects.

However, the Supreme Court found that DFA


and BSP failed to prove that the MRPV
Project is a “national government project” as
defined in Republic Act No. 8975 and thus,
the trial court had jurisdiction to issue the
injunction. As to whether the issuance of the
injunction was proper, the Supreme Court,
after considering the arguments of the parties,
SPECIAL THIRD DIVISION construction of the nursery shade
net area; plus interest at 6% per
annum to be computed from the
ELPIDIO S. UY, doing business G.R. Nos.
date 147925-26
of the filing of the complaint
under the name and style until finality of this Decision and
of EDISONDEVELOPMENT & CONSTRUCTION, Present:
12% per annum thereafter until
Petitioner, full payment. Respondent PEA is
CORONA, C.J.
further *
ordered to pay petitioner
VELASCO,
Uy 10% **
JR.,of the total award as
NACHURA,
attorneys fees.
- versus - Chairperson,
BRION,SO***and
ORDERED.[1]
PERALTA, JJ.
Uy seeks partial reconsideration of our
Decision.
Promulgated:
He argues that:
PUBLIC ESTATES AUTHORITY ,
Respondent. July 7,I 2010

x------------------------------------------------------------- x x x THE HONORABLE COURT


--------------------x ERRED IN THE COMPUTATION
OF THE DAMAGES DUE THE
RESOLUTION PETITIONER FOR THE
STANDBY EQUIPMENT COST.
NACHURA, J.:
II
Before us are (i) the Motion for Partial
Reconsideration filed by petitioner Elpidio S. x x x PETITIONER SHOULD BE
Uy (Uy), doing business under the name and REIMBURSED FOR COSTS
style of Edison Development & Construction INCURRED FOR ADDITIONAL
(EDC), and (ii) the Motion for Reconsideration HAULING DISTANCE OF
filed by respondent Public Estates Authority TOPSOIL ALSO BECAUSE THE
(PEA) of our June 8, 2009 Decision, the fallo of EVIDENCE ON RECORD
which reads: CONFIRMS THE EXISTENCE
OF RESPONDENT PEAS
WRITTEN CONSENT, AND THE
WHEREFORE, the petition FACT THAT IT IS
is PARTIALLY GRANTED. The INDESPENSABLE TO
assailed Joint Decision and Joint COMPLETING THE
Resolution of the Court of PROJECT. WITHOUT SUCH
Appeals in CA-G.R. SP Nos. ASSURANCE OF
59308 and 59849 REIMBURSEMENT,
are AFFIRMED with MODIFICAT PETITIONER WOULD NOT
IONS. Respondent Public HAVE TAKEN SUCH PRUDENT
Estates Authority is ordered to ACTION.
pay Elpidio S. Uy, doing business
under the name and style Edison III
Development and
Construction, P55,680,492.38 for x x x PETITIONER SHOULD BE
equipment rentals on ALLOWED TO RECOVER THE
standby; P2,275,721.00 for the COSTS HE INCURRED FOR
cost of idle manpower; THE MOBILIZATION OF WATER
and P6,050,165.05 for the TRUCKS ALSO BECAUSE
RESPONDENT BREACHED ITS
OBLIGATIONS UNDER THE We will deal first with Uys motion.
CONTRACT.
Uy objects to the factor rate used in the
IV computation of the award for standby
equipment costs. He points out that the actual
WITH REGARD TO THE COURT number of equipment deployed and which
OF APPEALS ILLEGAL remained on standby, occasioned by the delay
INJUNCTION PREVENTING in delivery of work areas, has not been
PETITIONER FROM considered in the computation. The
RECOVERING HIS CLAIMS Association of Carriers and Equipment Lessors
AGAINST RESPONDENT PEA (ACEL) rate or the factor rate used was only
IN CIAC CASE NO. 03-2001, the total average rate, without regard to the
THIS SHOULD HAVE BEEN actual number of equipment deployed. He,
LIFTED SINCE IT INVOLVES therefore, insists that an increase in the award
CLAIMS SEPARATE AND is in order.
DISTINCT FROM THE
CASE A QUO. [2]
We find Uys argument on this point
meritorious; and this Court is swayed to modify
the formula used in the computation of the
PEA, on the other hand, assails the Decision award.
on the following grounds:

I. The Certification,[4] dated December 6,


1996, shows that EDC mobilized the following
THE FACTUAL FINDINGS AND equipment for the Heritage Park Project, viz.:
CONCLUSIONS OF THE
CONSTRUCTION INDUSTRY Description Number
ARBITRATION COMMISSION
(CIAC) INSOFAR AS THE Road Grader 2
ARBITRAL AWARD TO Pay Loader 2
PETITIONER IS CONCERNED, Dump Trucks 10
WHICH THE COURT OF Tractor with 2
APPEALS AND THE FIRST attachments
DIVISION OF THIS Backhoe 2
HONORABLE COURT Delivery Trucks 3
AFFIRMED, HAS LONG Rolo-tiller 0
BECOME FINAL AND Concrete Mixer 4
EXECUTORY. Bar Cutter 2
Welding Machine 2
II. Roller 1
Bulldozer 1
THE CIAC ARBITRAL AWARD Concrete Cutter 2
HAD ALREADY BEEN Plate Compactor 2
IMPLEMENTED UNDER WRIT Compressor/Jack 3
OF EXECUTION DATED 19 Hammer
SEPTEMBER 2000, WRIT OF Genset 5KVA 1
EXECUTION DATED 31 Electric drill/ Holesaw 4
AUGUST 2001 AND
SUPPLEMENTAL WRIT OF These equipment remained in the
EXECUTION DATED 10 APRIL project site on the days that EDC was waiting
2002.[3] for the turnover of additional work
areas.[5] Thus, we agree with Uy that the actual alleged right under the Landscaping and
number of equipment mobilized should be Construction Agreement. Therefore, the
included in computing the award for standby landscaping agreement is indispensable in the
equipment cost. The award must, therefore, be prosecution of his claims in both CIAC Cases
modified using the following formula: No. 02-2000 and No. 03-2001. We reiterate
that a party, either by varying the form or action
Actual period of delay (18.2 or by bringing forward in a second case
months) x average rate per ACEL additional parties or arguments, cannot escape
x number of equipment the effects of res judicata when the facts
remain the same, at least where such new
parties or matter could have been impleaded or
However, we cannot simply accept in full Uys pleaded in the prior action.
claim that he is entitled to P71,009,557.95 as
standby equipment cost. The records show In fine, except for the claim for standby
that not all of the equipment were operational; equipment costs, this Court finds no cogent
several were under repair.[6] Accordingly, we reason to depart from our June 8, 2009
find it necessary to remand the records of the Decision.
case to the Construction Industry Arbitration
Commission (CIAC), which decided the case in We now go to PEAs motion.
the first instance, for the proper computation of
the award of standby equipment cost based on PEA insists that our Decision in this
the foregoing formula. case transgresses the principle of res judicata.
It asserts that the propriety of Uys monetary
On the claim for costs for additional hauling claims against PEA had already been
distance of topsoil and for mobilization of water considered and passed upon by this Court in
truck, we maintain our ruling that a written G.R. Nos. 147933-34.
approval of PEAs general manager was
indispensable before the claim for additional The argument is specious.
cost can be granted. In this case, the additional
costs were incurred without the written In G.R. Nos. 147933-34, this Court was
approval of PEA. The denial of Uys claims very explicit in its declaration that its Decision
was, therefore, appropriate. was independent of, and without prejudice to,
the appeal filed by Uy, viz.:
We cannot sustain this claim that is
premised mainly on the principle of unjust However, in order not to
enrichment. We stress that the principle of prejudice the deliberations of the
unjust enrichment cannot be validly invoked by Courts Second Division in G.R.
a party who, through his own act or omission, Nos. 147925-26, it should be
took the risk of being denied payment for stated that the findings made in
additional costs by not giving the other party this case, especially as regards
prior notice of such costs and/or by not the correctness of the findings of
securing their written consent thereto, as the CIAC, are limited to the
required by law and their contract.[7] arbitral awards granted to
respondent Elpidio S. Uy and to
Similarly, we find no cogent reason to lift the denial of the counterclaims of
the injunction issued in CIAC Case No. 03- petitioner Public Estates
2001. We are not persuaded by Uys argument Authority. Our decision in this
that the claims under CIAC Case No. 03-2001 case does not affect the other
are different from his claims in CIAC Case No. claims of respondent Uy which
02-2000. As we explained in our Decision, were not granted by the CIAC in
there is only one cause of action running its questioned decision, the
through Uys undertakings the violation of his merits of which were not
submitted to us for determination corporation organized under Philippine laws.
in the instant petition.[8] Private respondent RRN Incorporated
(hereinafter respondent) is likewise a domestic
corporation organized under Philippine laws.
Indubitably, this Courts Decision in G.R. Respondent filed a claim for arbitration against
Nos. 147933-34 will not bar the grant of petitioner before CIAC for recovery of unpaid
additional award to Uy. account which consists of unpaid portions of
the sub-contract, variations and unused
WHEREFORE, Uys Motion for Partial materials in the total sum of P5,275,184.17 and
Reconsideration is PARTLY GRANTED. PEAs legal interest in the amount of P442,014.73.
Motion for Reconsideration, on the other hand, Petitioner filed a counterclaim for overpayment
is DENIED with FINALITY. The assailed in the amount ofP2,512,997.96.
Decision dated June 8, 2009 The parties admitted several facts before the
is AFFIRMED with MODIFICATION as to the CIAC. It was shown that petitioner and
award of standby equipment cost. The case is respondent executed an Agreement and
hereby REMANDED to the Construction Conditions of Sub-contract (hereafter
Industry Arbitration Commission solely for the Agreement signed on June 11, 1996 and June
purpose of computing the exact amount of 14, 1996, respectively. Respondent signified its
standby equipment cost pursuant to the willingness to accept and perform for petitioner
formula herein specified. The CIAC in any of its projects, a part or the whole of the
is DIRECTED to compute the award and effect works more particularly described in Conditions
payment thereof within thirty (30) days from of Sub-Contract and other Sub-contract
receipt of the records of this case. documents.
On June 11, 2002, the parties executed a
No further pleadings will be entertained. "Supply of Manpower, Tools/Equipment,
Consumables for the Electrical Works-Power
SO ORDERED. and Equipment Supply, Bus Duct Installation"
for the Phillip Morris Greenfield Project
ANTONIO EDUARDO B. NACHURA (hereafter Project) covered by Purchase Order
Associate Justice Nos. 4501200300-000274 and 4501200300-
000275 amounting toP15,724,000.00
and P9,276,000.00 respectively, or a total
G.R. No. 172525 October 20, 2010 amount of P25,000,000.00. The parties also
SHINRYO (PHILIPPINES) COMPANY, agreed that respondent will perform variation
INC., Petitioner, orders in the Project. In connection with the
vs. Project, petitioner supplied manpower
RRN INCORPORATED,* Respondent. chargeable against respondent.
DECISION Respondent was not able to finish the entire
PERALTA, J.: works with petitioner due to financial
This resolves the Petition for Review difficulties. Petitioner paid respondent a total
on Certiorari under Rule 45 of the Rules of amount of P26,547,624.76. On June 25, 2005
Court, praying that the Decision1 of the Court of [should read 2003], respondent, through its
Appeals (CA) dated February 22, 2006, former counsel sent a letter to petitioner
affirming the Decision of the Construction demanding for the payment of its unpaid
Industry Arbitration Commission (CIAC), and balance amounting to P5,275,184.17.
the CA Resolution2 dated April 26, 2006, Petitioner claimed material back charges in the
denying herein petitioner's motion for amount of P4,063,633.43. On September 26,
reconsideration, be reversed and set aside. 2003, respondent only
The facts, as accurately narrated in the CA acknowledged P2,371,895.33 as material back
Decision, are as follows. charges. Thereafter, on October 16, 2003,
Petitioner Shinryo (Philippines) Company, Inc. respondent sent another letter to petitioner for
(hereinafter petitioner) is a domestic them to meet and settle their dispute.
On January 8, 2004, respondent sent another reckoned from June 25, 2003 up to the filing of
letter to petitioner regarding the cost of the case on October 11, 2004 and 12%
equipment rental and the use of scaffolding. of P3,728,960.54 from the finality of the
Thereafter, on August 12, 2004, petitioner sent judgment until fully paid and arbitration cost
a letter to respondent denying any unpaid of P104,333.82 representing claimant's share
account and the failure in their negotiations for of the arbitration cost which respondent should
amicable settlement. reimburse.
On September 3, 2004, respondent, through its SO ORDERED.]
new counsel, advised petitioner of their Petitioner accepts the ruling of the CIAC only in
intention to submit the matter to arbitration. Issue No. 1 and Sub-Issue No. 1.1 and in Issue
Thereafter, their dispute was submitted to No. 2 in so far as the amount of P440,000.00
arbitration. During the preliminary conference, awarded as back charges for the use of
the parties agreed in their Terms of Reference scaffoldings. x x x3
to resolve eight issues, to wit: On February 22, 2006, the CA promulgated the
1. What should be the basis in assailed Decision affirming the decision of the
evaluating the variation cost? CIAC. The CA upheld the CIAC ruling that
1.1 How much is the variation petitioner failed to adduce sufficient proof that
cost? the parties had an agreement regarding
2. Is the Respondent (petitioner in the charges for respondent's use of the manlift. As
instant case) justified in charging to the other charges for materials, the CA held
claimant (herein respondent) the that the evidence on record amply supports the
equipment rental fee and for the use of CIAC findings. Petitioner moved for
the scaffoldings? If so, how much reconsideration of said ruling, but the same
should be charged to Claimant? was denied per Resolution dated April 26,
3. What should be the basis in 2006.
evaluating the total cost of materials Hence, this petition where it is alleged that:
supplied by Respondent to the Project I. THE HONORABLE COURT OF APPEALS
which is chargeable to Claimant? COMMITTED GRAVE REVERSIBLE ERROR
3.1 How much is the total cost of WHEN IT DENIED PETITIONER'S CLAIM
materials supply chargeable to FOR MANLIFT EQUIPMENT RENTAL IN THE
Claimant? AMOUNT OFP511,000.00 DESPITE
4. How much is the value of the EVIDENCE ON RECORD THAT
remaining works left undone by the RESPONDENT RRN ACTUALLY USED AND
Claimant in the project? BENEFITED FROM THE MANLIFT
5. Is the Claimant's claim for inventory of EQUIPMENT.
excess materials valid? If so, how much II. IN RENDERING THE QUESTIONED
is the value thereof? DECISION AND QUESTIONED
6. Is the Respondent entitled to its claim RESOLUTION, THE HONORABLE COURT
for an overpayment in the amount OF APPEALS HAS DECIDED A QUESTION
of P2,512,997.96? OF SUBSTANCE NOT IN ACCORD WITH
7. Is Claimant entitled to its claim for LAW AND/OR WITH THE APPLICABLE
interest? If so, how much? DECISIONS OF THE HONORABLE
8. Who between the parties shall bear SUPREME COURT.
the cost of Arbitration? III. THE COURT OF APPEALS COMMITTED
The CIAC rendered the assailed decision after A GRAVE REVERSIBLE ERROR IN
the presentation of the parties' evidence. [The AFFIRMING THE CIAC AWARD FOR THE
dispositive portion of said decision reads as VALUE OF INVENTORIED MATERIALS
follows: CONSIDERING THAT:
WHEREFORE, judgment is hereby rendered in A. RESPONDENT RRN
favor of the claimant and respondent is ordered ADMITTED THE VALIDITY OF
to pay claimant its unpaid account in the sum THE DEDUCTIONS ON
of P3,728,960.54 plus legal interest of 6% ACCOUNT OF MATERIAL
SUPPLY, WHICH INCLUDED INTERESTS AND ARBITRATION COSTS IN
THE INVENTORIED FAVOR OF RESPONDENT RRN.4
MATERIALS. The petition is bereft of merit.
B. RESPONDENT RRN HAS NO Despite petitioner's attempts to make it appear
BASIS TO CLAIM BECAUSE that it is advancing questions of law, it is quite
ENGR. BONIFACIO ADMITTED clear that what petitioner seeks is for this Court
THAT RESPONDENT RRN to recalibrate the evidence it has presented
FAILED TO ESTABLISH before the CIAC. It insists that its evidence
WHETHER THE MATERIALS sufficiently proves that it is entitled to payment
CAME FROM RESPONDENT for respondent's use of its manlift equipment,
RRN OR FROM PETITIONER and even absent proof of the supposed
AND THAT IT WAS agreement on the charges petitioner may
PETITIONER THAT ACTUALLY impose on respondent for the use of said
INSTALLED THE SAID equipment, respondent should be made to pay
MATERIALS AS PART OF based on the principle of unjust enrichment.
REMAINING WORKS THAT Petitioner also questions the amounts awarded
PETITIONER TOOK OVER by the CIAC for inventoried materials, and
FROM RESPONDENT RRN. costs incurred by petitioner for completing the
C. THE CLAIM FOR THE VALUE work left unfinished by respondent.
OF INVENTORIED MATERIALS As reiterated by the Court in IBEX
IS A DOUBLE CLAIM OR International, Inc. v. Government Service
DOUBLE ENTRY BECAUSE IN Insurance System,5 to wit:
THE COMPUTATION OF THE It is settled that findings of fact of quasi-
FINAL ACCOUNT, judicial bodies, which have acquired
RESPONDENT RRN WAS expertise because their jurisdiction is
CREDITED THE FULL confined to specific matters, are generally
CONTRACT PRICE AND THE accorded not only respect, but also finality,
COST OF VARIATIONS, WHICH especially when affirmed by the Court of
INCLUDED THE INVENTORIED Appeals. In particular, factual findings of
MATERIALS. construction arbitrators are final and
IV. IN RENDERING THE QUESTIONED conclusive and not reviewable by this Court
DECISION AND QUESTIONED on appeal.
RESOLUTION, THE COURT OF APPEALS This rule, however, admits of certain
COMMITTED A GRAVE REVERSIBLE exceptions. In Uniwide Sales Realty and
ERROR IN THAT IT COMPLETELY Resources Corporation v. Titan-Ikeda
DISREGARDED THE PROVISION OF THE Construction and Development Corporation,
SUBCONTRACT, WHICH ALLOWED we said:
PAYMENT OF ACTUAL COST INCURRED BY In David v. Construction Industry and
PETITIONER IN COMPLETING THE Arbitration Commission, we ruled that, as
REMAINING WORKS THAT PRIVATE exceptions, factual findings of construction
RESPONDENT ADMITTEDLY FAILED TO arbitrators may be reviewed by this Court when
COMPLETE. the petitioner proves affirmatively that: (1) the
V. THE COURT OF APPEALS COMMITTED A award was procured by corruption, fraud or
GRAVE REVERSIBLE ERROR WHEN IT other undue means; (2) there was evident
COMPLETELY DISREGARDED THE partiality or corruption of the arbitrators or any
EVIDENCE ON ACTUAL COST INCURRED of them; (3) the arbitrators were guilty of
BY PETITIONER IN COMPLETING THE misconduct in refusing to hear evidence
REMAINING WORKS. pertinent and material to the controversy; (4)
VI. THE COURT OF APPEALS COMMITTED one or more of the arbitrators were disqualified
GRAVE REVERSIBLE ERROR WHEN IT to act as such under Section nine of Republic
AFFIRMED THE CIAC AWARD FOR Act No. 876 and willfully refrained from
disclosing such disqualifications or of any other
misbehavior by which the rights of any party Article 22 of the New Civil Code reads:
have been materially prejudiced; or (5) the Every person who, through an act of
arbitrators exceeded their powers, or so performance by another, or any other means,
imperfectly executed them, that a mutual, final acquires or comes into possession of
and definite award upon the subject matter something at the expense of the latter without
submitted to them was not made.1avvp++i1 just or legal ground, shall return the same to
Other recognized exceptions are as follows: (1) him.
when there is a very clear showing of grave In order that accion in rem verso may prosper,
abuse of discretion resulting in lack or loss of the essential elements must be present: (1)
jurisdiction as when a party was deprived of a that the defendant has been enriched, (2) that
fair opportunity to present its position before the plaintiff has suffered a loss, (3) that the
the Arbitral Tribunal or when an award is enrichment of the defendant is without just or
obtained through fraud or the corruption of legal ground, and (4) that the plaintiff has no
arbitrators, (2) when the findings of the Court of other action based on contract, quasi-contract,
Appeals are contrary to those of the CIAC, and crime or quasi-delict.
(3) when a party is deprived of administrative An accion in rem verso is considered merely
due process.6 an auxiliary action, available only when there is
A perusal of the records would reveal that none no other remedy on contract, quasi-contract,
of the aforementioned circumstances, which crime, and quasi-delict. If there is an obtainable
would justify exemption of this case from the action under any other institution of positive
general rule, are present here. Such being the law, that action must be resorted to, and the
case, the Court, not being a trier of facts, is not principle of accion in rem verso will not lie.9
duty-bound to examine, appraise and analyze As found by both the CIAC and affirmed by the
anew the evidence presented before the CA, petitioner failed to prove that respondent's
arbitration body.7 free use of the manlift was without legal ground
Petitioner's reliance on the principle of unjust based on the provisions of their contract. Thus,
enrichment is likewise misplaced. The ruling of the third requisite, i.e., that the enrichment of
the Court in University of the Philippines v. respondent is without just or legal ground, is
Philab Industries, Inc.8 is highly instructive, missing. In addition, petitioner's claim is based
thus: on contract, hence, the fourth requisite − that
Unjust enrichment claims do not lie simply the plaintiff has no other action based on
because one party benefits from the efforts or contract, quasi-contract, crime or quasi-delict −
obligations of others, but instead it must be is also absent. Clearly, the principle of unjust
shown that a party was unjustly enriched in the enrichment is not applicable in this case.
sense that the term unjustly could mean The other issues raised by petitioner all boil
illegally or unlawfully. down to whether the CIAC or the CA erred in
Moreover, to substantiate a claim for unjust rejecting its claims for costs of some materials.
enrichment, the claimant must unequivocally Again, these issues are purely factual and
prove that another party knowingly received cannot be properly addressed in this petition
something of value to which he was not entitled for review on certiorari. InHanjin Heavy
and that the state of affairs are such that it Industries and Construction Co., Ltd. v.
would be unjust for the person to keep the Dynamic Planners and Construction Corp.,10 it
benefit. Unjust enrichment is a term used to was emphasized that mathematical
depict result or effect of failure to make computations, the propriety of arbitral awards,
remuneration of or for property or benefits claims for "other costs" and "abandonment" are
received under circumstances that give rise to factual questions. Since the discussions of the
legal or equitable obligation to account for CIAC and the CA in their respective Decisions
them; to be entitled to remuneration, one must show that its factual findings are supported by
confer benefit by mistake, fraud, coercion, or substantial evidence, there is no reason why
request. Unjust enrichment is not itself a theory this Court should not accord finality to said
of reconvey. Rather, it is a prerequisite for the findings. Verily, to accede to petitioner's
enforcement of the doctrine of restitution. request for a recalibration of its evidence,
which had been thoroughly studied by both the
CIAC and the CA would result in negating the
objective of Executive Order No. 1008, which
created an arbitration body to ensure the
prompt and efficient settlement of disputes in
the construction industry. Thus, the Court held
in Uniwide Sales Realty and Resources
Corporation v. Titan-Ikeda Construction and
Development Corporation,11 that:
x x x The Court will not review the factual
findings of an arbitral tribunal upon the artful
allegation that such body had
"misapprehended facts" and will not pass upon
issues which are, at bottom, issues of fact, no
matter how cleverly disguised they might be as
"legal questions." The parties here had
recourse to arbitration and chose the
arbitrators themselves; they must have had
confidence in such arbitrators. The Court will
not, therefore, permit the parties to relitigate
before it the issues of facts previously
presented and argued before the Arbitral
Tribunal, save only where a clear showing is
made that, in reaching its factual conclusions,
the Arbitral Tribunal committed an error so
egregious and hurtful to one party as to
constitute a grave abuse of discretion resulting
in lack or loss of jurisdiction.12
As discussed above, there is nothing in the
records that point to any grave abuse of
discretion committed by the CIAC.
The awards for interests and arbitration costs
are, likewise, correct as they are in keeping
with prevailing jurisprudence.13
IN VIEW OF THE FOREGOING, the Petition
is DENIED. The Decision of the Court of
Appeals dated February 22, 2006 and its
Resolution dated April 26, 2006
are AFFIRMED.
SO ORDERED.
DIOSDADO M. PERALTA
Associate Justice

Вам также может понравиться