1 MV14 - Decommissioning (Draft Version as preliminary info only) 507,83 days 01/01/18 2 STOP OF PRODUCTION 0 days 30/06/18 30/06 3 SAIL AWAY 0 days 24/03/19 24/03 4 PB Contract Definition and Agreement for Demob 0 days 30/03/18 30/03 5 SPC Pending Clarifications regarding FPSO Destination 0 days 30/03/18 30/03 6 PHASE 1 - Engineering Detail Scope Definition 238,83 days 01/01/18 7 Chain Jack System Refurbshiment 176 days 16/02/18 20 Sea Water Lift Hose 0 days 25/08/18 25/08 22 Mooring Disconnection 1,17 days 01/07/18 26 Oceanic Towing 56,83 days 02/07/18 31 Riser Pull Out 76 days 03/03/18 38 HPUs Maintenance 0 days 02/07/18 02/07 40 NORM Mapping 182 days 01/01/18 43 Topside Cleaning Up 0 days 14/05/18 14/05 46 Cargo Tank Cleaning 0 days 06/04/18 06/04 48 Offloading Hose Removal 0 days 02/07/18 02/07 50 Advisor Service 91 days 02/04/18 53 FPSO Equipment Transfer to MdB 74 days 20/02/18 57 Power Generation 0 days 31/05/18 31/05 59 PHASE 2 - Procurement 390 days 01/01/18 60 Service Procurement 390 days 01/01/18 61 Chain Jack System Refurbshiment 204 days 08/03/18 95 Sea Water Lift Hose 18 days 25/08/18 100 Mooring Disconnection 94 days 01/07/18 113 Oceanic Towing 116 days 19/09/18 130 Riser Pull Out 94 days 03/03/18 151 HPUs Maintenance 18 days 14/10/18 156 NORM Mapping 390 days 01/01/18 165 Topside Cleaning Up 18 days 14/05/18 174 Cargo Tank Cleaning 18 days 06/04/18 179 Offloading Hose Removal 18 days 31/10/18 184 Advisor Service 236,83 days 02/04/18 197 FPSO Equipment Transfer to MdB 18 days 05/05/18 202 Power Generation 18 days 31/05/18 207 Rescue Team (3rd Party) 15 days 01/06/18 210 Material Procurement 262,83 days 18/04/18 211 Chain Jack Refurbshiment Material 13 days 18/04/18 215 Sea Water Lift Hose Removal Material 5 days 29/08/18 218 Mooring Disconnection Material 5 days 03/10/18 221 Station Keeping Acessories Material 5 days 03/10/18 224 Towing Acessories Construction Material 5 days 07/10/18 227 Riser Pull Out Equipment Material and Spares 5 days 26/04/18 230 Topside Cleanning Up 5 days 26/05/18 233 Cargo Tank Cleaning 5 days 11/06/18 236 Sea Fastening Material 5 days 01/01/19 239 FPSO Access Ladder 5 days 06/12/18 242 Messenger Chain Procurement 5 days 24/09/18 244 PHASE 3 - Deliverables 279,83 days 01/05/18 245 Document Contractors Delivery (Plans and Procedures) 253,83 days 01/05/18 254 Material Delivery 279,83 days 01/05/18 267 PHASE 4 - Pre Execution 367,83 days 21/03/18 268 HPU Repair 30 days 01/11/18 270 Messenger Chain Installation 15 days 25/10/18 272 Riser Pull-Out Preparative 106 days 21/03/18 281 Chain Jack System 215,17 days 11/04/18 295 Preparative for Oceanic Towing 43 days 09/02/19 300 Preparative for Station Keeping 44 days 23/12/18 303 PHASE 5 - Execution 394,83 days 24/04/18 304 Others 67 days 03/10/18 307 Riser Pull-Out 95 days 30/06/18 310 Top Side Cleaning 192 days 30/06/18 405 Offloading Hose Removal 6,67 days 08/01/19 408 Hull Tanks Integrity x Decommissioning 329,83 days 24/04/18 457 Mooring Lines Disconnection 47 days 05/02/19 461 Licences and Permits 90 days 24/12/18 467 Oceanic Towing to ASIA 60 days 25/03/19