Академический Документы
Профессиональный Документы
Культура Документы
* Same; Same; Court agrees with the appellate court in its ruling that the
non-delivery of the oil well cement is a matter properly cognizable by the
OIL AND NATURAL GAS COMMISSION, petitioner, vs. COURT OF APPEALS regular courts as stipulated by the parties in Clause 15 of their contract.—
and PACIFIC CEMENT COMPANY, INC., respondents. This Court agrees with the appellate court in its ruling that the non-
delivery of the oil well cement is a matter properly cognizable by the
regular courts as stipulated by the parties in Clause 15 of their contract:
“All questions, disputes and differences, arising under out of or in
Statutory Construction; Doctrine of Noscitur a Sociis; According to the
connection with this supply order, shall be subject to the exclusive
maxim noscitur a sociis, where a particular word or phrase is ambiguous
jurisdiction of the court, within the local limits of whose jurisdiction and
in itself or is equally susceptible of various meanings, its correct
the place from which this supply order is situated.”
construction may be made clear and specific by considering the company
of the words in which it is found or with which it is associated, or stated
differently, its obscurity or doubt may be reviewed by reference to
associated words.—The doctrine of noscitur a sociis, although a rule in the Remedial Law; Constitutional Law; Judgment; The constitutional mandate
construction of statutes, is equally applicable in the ascertainment of the that no decision shall be rendered by any court without expressing therein
meaning and scope of vague contractual stipulations, such as the clearly and distinctly the facts and the law on which it is based does not
aforementioned phrase. According to the maxim noscitur a sociis, where preclude the validity of “memorandum decisions” which adopt by
a particular word or phrase is ambiguous in itself or is equally susceptible reference the findings of fact and conclusions of law contained in the
of various meanings, its correct construction may be made clear and decisions of inferior tribunals.—The constitutional mandate that no
specific by considering the company of the words in which it is found or decision shall be rendered by any court without expressing therein clearly
with which it is associated, or stated differently, its obscurity or doubt may and distinctly the facts and the law on which it is based does not preclude
be reviewed by reference to associated words. the validity of “memorandum decisions” which adopt by reference the
findings of fact and conclusions of law contained in the decisions of
inferior tribunals. In Francisco v. Permskul, this Court held that the
following memorandum decision of the Regional Trial Court of Makati did
Same; Same; As in statutes, the provisions of a contract should not be read
not transgress the requirements of Section 14, Article VIII of the
in isolation from the rest of the instrument but, on the contrary,
Constitution: “MEMORANDUM DECISION—After a careful perusal,
interpreted in the light of the other related provisions.—Thus, this Court
evaluation and study of the records of this case, this Court hereby adopts
has held that as in statutes, the provisions of a contract should not be read
by reference the findings of fact and conclusions of law contained in the
in isolation from the rest of the instrument but, on the contrary,
decision of the Metropolitan Trial Court of Makati, Metro Manila, Branch
interpreted in the light of the other related provisions. The whole and
63 and finds that there is no cogent reason to disturb the same.
every part of a contract must be considered in fixing the meaning of any
“WHEREFORE, judgment appealed from is hereby affirmed in toto.”
of its parts and in order to produce a harmonious whole. Equally
(Italics supplied.)
applicable is the canon of construction that in interpreting a statute (or a
contract as in this case), care should be taken that every part thereof be
given effect, on the theory that it was enacted as an integrated measure
and not as a hodge-podge of conflicting provisions. The rule is that a Same; Same; Same; Even in this jurisdiction, incorporation by reference is
construction that would render a provision inoperative should be allowed if only to avoid the cumbersome reproduction of the decision of
avoided; instead, apparently inconsistent provisions should be reconciled the lower courts, or portions thereof, in the decision of the higher court.—
whenever possible as parts of a coordinated and harmonious whole. Hence, even in this jurisdiction, incorporation by reference is allowed if
only to avoid the cumbersome reproduction of the decision of the lower
courts, or portions thereof, in the decision of the higher court. This is
particularly true when the decision sought to be incorporated is a lengthy
Same; Same; The non-delivery of the oil well cement is definitely not in the
and thorough discussion of the facts and conclusions arrived at, as in this
nature of a dispute arising from the failure to execute the supply
case, where Award Paper No. 3/B-1 consists of eighteen (18) single spaced
order/contract design, drawing, instructions, specifications or quality of
pages.
the materials.—But in accordance with the doctrine of noscitur a sociis,
this reference to the supply order/contract must be construed in the light
of the preceding words with which it is associated, meaning to say, as
being limited only to the design, drawing, instructions, specifications or Same; Same; The Court has held that matters of remedy and procedure
quality of the materials of the supply order/contract. The non-delivery of are governed by the lex fori or the internal law of the forum.—The
the oil well cement is definitely not in the nature of a dispute arising from recognition to be accorded a foreign judgment is not necessarily affected
the failure to execute the supply order/contract design, drawing, by the fact that the procedure in the courts of the country in which such
instructions, specifications or quality of the materials. That Clause 16 judgment was rendered differs from that of the courts of the country in
should pertain only to matters involving the technical aspects of the which the judgment is relied on. This Court has held that matters of
contract is but a logical inference considering that the underlying purpose remedy and procedure are governed by the lex fori or the internal law of
of a referral to arbitration is for such technical matters to be deliberated the forum. Thus, if under the procedural rules of the Civil Court of Dehra
upon by a person possessed with the required skill and expertise which Dun, India, a valid judgment may be rendered by adopting the arbitrator’s
may be otherwise absent in the regular courts. findings, then the same must be accorded respect. In the same vein, if the
procedure in the foreign court mandates that an Order of the Court
becomes final and executory upon failure to pay the necessary docket
fees, then the courts in this jurisdiction cannot invalidate the order of the Commission at the time of dispute. It will be no objection to any
foreign court simply because our rules provide otherwise. such appointment that the arbitrator so appointed is a
Commission employer (sic) that he had to deal with the matter to
which the supply or contract relates and that in the course of his
duties as Commission's employee he had expressed views on all
Same; Due Process; The essence of due process is to be found in the or any of the matter in dispute or difference.
reasonable opportunity to be heard and submit any evidence one may
have in support of one’s defense or, stated otherwise, what is repugnant The arbitrator to whom the matter is originally referred being
transferred or vacating his office or being unable to act for any
to due process is the denial of opportunity to be heard.—Time and again
reason the Member of the Commission shall appoint another
this Court has held that the essence of due process is to be found in the person to act as arbitrator in accordance with the terms of the
reasonable opportunity to be heard and submit any evidence one may contract/supply order. Such person shall be entitled to proceed
have in support of one’s defense or stated otherwise, what is repugnant with reference from the stage at which it was left by his
to due process is the denial of opportunity to be heard. Thus, there is no predecessor. Subject as aforesaid the provisions of the
violation of due process even if no hearing was conducted, where the Arbitration Act, 1940, or any Statutory modification or re-
party was given a chance to explain his side of the controversy and he enactment there of and the rules made there under and for the
time being in force shall apply to the arbitration proceedings
waived his right to do so.
under this clause.
The arbitrator may with the consent of parties enlarge the time,
from time to time, to make and publish the award.
On July 23, 1988, the chosen arbitrator, one Shri N.N. Malhotra, resolved
This proceeding involves the enforcement of a foreign judgment rendered
the dispute in petitioner's favor setting forth the arbitral award as follows:
by the Civil Judge of Dehra Dun, India in favor of the petitioner, OIL AND
NATURAL GAS COMMISSION and against the private respondent, PACIFIC
CEMENT COMPANY, INCORPORATED. NOW THEREFORE after considering all facts of the case, the
evidence, oral and documentarys adduced by the claimant and
carefully examining the various written statements, submissions,
The petitioner is a foreign corporation owned and controlled by the
letters, telexes, etc. sent by the respondent, and the oral
Government of India while the private respondent is a private corporation
arguments addressed by the counsel for the claimants, I, N.N.
duly organized and existing under the laws of the Philippines. The present
Malhotra, Sole Arbitrator, appointed under clause 16 of the
conflict between the petitioner and the private respondent has its roots
supply order dated 26.2.1983, according to which the parties, i.e.
in a contract entered into by and between both parties on February 26,
M/S Oil and Natural Gas Commission and the Pacific Cement Co.,
1983 whereby the private respondent undertook to supply the petitioner
Inc. can refer the dispute to the sole arbitration under the
FOUR THOUSAND THREE HUNDRED (4,300) metric tons of oil well cement.
provision of the Arbitration Act. 1940, do hereby award and direct
In consideration therefor, the petitioner bound itself to pay the private
as follows: —
respondent the amount of FOUR HUNDRED SEVENTY-SEVEN THOUSAND
THREE HUNDRED U.S. DOLLARS ($477,300.00) by opening an irrevocable,
divisible, and confirmed letter of credit in favor of the latter. The oil well The Respondent will pay the following to the claimant: —
cement was loaded on board the ship MV SURUTANA NAVA at the port of
Surigao City, Philippines for delivery at Bombay and Calcutta, India. 1. Amount received by the Respondent
However, due to a dispute between the shipowner and the private
respondent, the cargo was held up in Bangkok and did not reach its point
against the letter of credit No. 11/19
destination. Notwithstanding the fact that the private respondent had
already received payment and despite several demands made by the
petitioner, the private respondent failed to deliver the oil well cement. dated 28.2.1983 US $ 477,300.00
Thereafter, negotiations ensued between the parties and they agreed
that the private respondent will replace the entire 4,300 metric tons of oil 2. Re-imbursement of expenditure incurred
well cement with Class "G" cement cost free at the petitioner's designated
port. However, upon inspection, the Class "G" cement did not conform to
by the claimant on the inspection team's
the petitioner's specifications. The petitioner then informed the private
respondent that it was referring its claim to an arbitrator pursuant to
Clause 16 of their contract which stipulates: visit to Philippines in August 1985 US $ 3,881.00
Except where otherwise provided in the supply order/contract all 3. L.C. Establishment charges incurred
questions and disputes, relating to the meaning of the
specification designs, drawings and instructions herein before by the claimant US $ 1,252.82
mentioned and as to quality of workmanship of the items ordered
or as to any other question, claim, right or thing whatsoever, in
any way arising out of or relating to the supply order/contract 4. Loss of interest suffered by claimant
design, drawing, specification, instruction or these conditions or
otherwise concerning the materials or the execution or failure to from 21.6.83 to 23.7.88 US $ 417,169.95
execute the same during stipulated/extended period or after the
completion/abandonment thereof shall be referred to the sole Total amount of award US $ 899,603.77
arbitration of the persons appointed by Member of the
In addition to the above, the respondent would also be required filing fees, and thereafter issued an Order on February 7, 1990,
liable to pay to the claimant the interest at the rate of 6% to wit:
on the above amount, with effect from 24.7.1988 up to
the actual date of payment by the Respondent in full ORDER
settlement of the claim as awarded or the date of the
decree, whichever is earlier.
Since objections filed by defendant have been rejected through
Misc. Suit No. 5 on 7.2.90, therefore, award should be made
I determine the cost at Rs. 70,000/- equivalent to US Rule of the Court.
$5,000 towards the expenses on Arbitration, legal
expenses, stamps duly incurred by the claimant. The cost
will be shared by the parties in equal proportion. ORDER
Pronounced at Dehra Dun to-day, the 23rd of July 1988. 2 Award dated 23.7.88, Paper No. 3/B-1 is made Rule of the
Court. On the basis of conditions of award decree is passed.
Award Paper No. 3/B-1 shall be a part of the decree. The
To enable the petitioner to execute the above award in its plaintiff shall also be entitled to get from defendant (US$
favor, it filed a Petition before the Court of the Civil Judge in 899,603.77 (US$ Eight Lakhs ninety nine thousand six hundred
Dehra Dun. India (hereinafter referred to as the foreign court and three point seventy seven only) along with 9% interest per
for brevity), praying that the decision of the arbitrator be made annum till the last date of realisation. 4
"the Rule of Court" in India. The foreign court issued notices to
the private respondent for filing objections to the petition. The
private respondent complied and sent its objections dated Despite notice sent to the private respondent of the foregoing order and
January 16, 1989. Subsequently, the said court directed the several demands by the petitioner for compliance therewith, the private
private respondent to pay the filing fees in order that the respondent refused to pay the amount adjudged by the foreign court as
latter's objections could be given consideration. Instead of owing to the petitioner. Accordingly, the petitioner filed a complaint with
paying the required filing fees, the private respondent sent the Branch 30 of the Regional Trial Court (RTC) of Surigao City for the
following communication addressed to the Civil judge of Dehra enforcement of the aforementioned judgment of the foreign court. The
Dun: private respondent moved to dismiss the complaint on the following
grounds: (1) plaintiffs lack of legal capacity to sue; (2) lack of cause of
action; and (3) plaintiffs claim or demand has been waived, abandoned,
The Civil Judge or otherwise extinguished. The petitioner filed its opposition to the said
motion to dismiss, and the private respondent, its rejoinder thereto. On
Dehra Dun (U.P.) India January 3, 1992, the RTC issued an order upholding the petitioner's legal
capacity to sue, albeit dismissing the complaint for lack of a valid cause of
Re: Misc. Case No. 5 of 1989 action. The RTC held that the rule prohibiting foreign corporations
transacting business in the Philippines without a license from maintaining
a suit in Philippine courts admits of an exception, that is, when the foreign
M/S Pacific Cement Co., corporation is suing on an isolated transaction as in this case. 5 Anent the
issue of the sufficiency of the petitioner's cause of action, however, the
Inc. vs. ONGC Case RTC found the referral of the dispute between the parties to the arbitrator
under Clause 16 of their contract erroneous. According to the RTC,
Sir:
[a] perusal of the shove-quoted clause (Clause 16) readily
1. We received your letter dated 28 April shows that the matter covered by its terms is limited to "ALL
1989 only last 18 May 1989. QUESTIONS AND DISPUTES, RELATING TO THE MEANING OF
THE SPECIFICATION, DESIGNS, DRAWINGS AND INSTRUCTIONS
HEREIN BEFORE MENTIONED and as to the QUALITY OF
2. Please inform us how much is the court WORKMANSHIP OF THE ITEMS ORDERED or as to any other
fee to be paid. Your letter did not mention questions, claim, right or thing whatsoever, but qualified to "IN
the amount to be paid. ANY WAY ARISING OR RELATING TO THE SUPPLY
ORDER/CONTRACT, DESIGN, DRAWING, SPECIFICATION, etc.,"
3. Kindly give us 15 days from receipt of repeating the enumeration in the opening sentence of the
your letter advising us how much to pay to clause.
comply with the same.
The court is inclined to go along with the observation of the
Thank you for your kind consideration. defendant that the breach, consisting of the non-delivery of the
purchased materials, should have been properly litigated
before a court of law, pursuant to Clause No. 15 of the
Pacific Cement Co., Inc.
Contract/Supply Order, herein quoted, to wit:
By:
"JURISDICTION
B. THE JUDGMENT OF THE CIVIL COURT OF The doctrine of noscitur a sociis, although a rule in the construction of
DEHRADUN, INDIA WAS AN AFFIRMATION OF THE statutes, is equally applicable in the ascertainment of the meaning and
FACTUAL AND LEGAL FINDINGS OF THE ARBITRATOR scope of vague contractual stipulations, such as the aforementioned
AND THEREFORE ENFORCEABLE IN THIS phrase. According to the maxim noscitur a sociis, where a particular word
JURISDICTION; or phrase is ambiguous in itself or is equally susceptible of various
meanings, its correct construction may be made clear and specific by
C. EVIDENCE MUST BE RECEIVED TO REPEL THE considering the company of the words in which it is found or with which
EFFECT OF A PRESUMPTIVE RIGHT UNDER A it is associated, or stated differently, its obscurity or doubt may be
FOREIGN JUDGMENT. 10 reviewed by reference to associated words. 13 A close examination of
Clause 16 reveals that it covers three matters which may be submitted to
arbitration namely,
The threshold issue is whether or not the arbitrator had jurisdiction over
the dispute between the petitioner and the private respondent under
Clause 16 of the contract. To reiterate, Clause 16 provides as follows: (1) all questions and disputes, relating to the meaning of the specification
designs, drawings and instructions herein before mentioned and as to
quality of workmanship of the items ordered; or
Except where otherwise provided in the supply
order/contract all questions and disputes, relating to
the meaning of the specification designs, drawings (2) any other question, claim, right or thing whatsoever, in any way arising
and instructions herein before mentioned and as to out of or relating to the supply order/contract design, drawing,
quality of workmanship of the items ordered or as to specification, instruction or these conditions; or
any other question, claim, right or thing whatsoever,
in any way arising out of or relating to the supply (3) otherwise concerning the materials or the execution or failure to
order/contract design, drawing, specification, execute the same during stipulated/extended period or after the
instruction or these conditions or otherwise completion/abandonment thereof.
concerning the materials or the execution or failure
to execute the same during stipulated/extended The first and second categories unmistakably refer to questions and
period or after the completion/abandonment disputes relating to the design, drawing, instructions, specifications or
quality of the materials of the supply/order contract. In the third category, . .", thus indicating that the jurisdiction of the arbitrator is not all
the clause, "execution or failure to execute the same", may be read as encompassing, and admits of exceptions as may be provided elsewhere in
"execution or failure to execute the supply order/contract". But in the supply order/contract. We believe that the correct interpretation to
accordance with the doctrine of noscitur a sociis, this reference to the give effect to both stipulations in the contract is for Clause 16 to be
supply order/contract must be construed in the light of the preceding confined to all claims or disputes arising from or relating to the design,
words with which it is associated, meaning to say, as being limited only to drawing, instructions, specifications or quality of the materials of the
the design, drawing, instructions, specifications or quality of the materials supply order/contract, and for Clause 15 to cover all other claims or
of the supply order/contract. The non-delivery of the oil well cement is disputes.
definitely not in the nature of a dispute arising from the failure to execute
the supply order/contract design, drawing, instructions, specifications or The petitioner then asseverates that granting, for the sake of argument,
quality of the materials. That Clause 16 should pertain only to matters that the non-delivery of the oil well cement is not a proper subject for
involving the technical aspects of the contract is but a logical inference arbitration, the failure of the replacement cement to conform to the
considering that the underlying purpose of a referral to arbitration is for specifications of the contract is a matter clearly falling within the ambit of
such technical matters to be deliberated upon by a person possessed with Clause 16. In this contention, we find merit. When the 4,300 metric tons
the required skill and expertise which may be otherwise absent in the of oil well cement were not delivered to the petitioner, an agreement was
regular courts. forged between the latter and the private respondent that Class "G"
cement would be delivered to the petitioner as replacement. Upon
This Court agrees with the appellate court in its ruling that the non- inspection, however, the replacement cement was rejected as it did not
delivery of the oil well cement is a matter properly cognizable by the conform to the specifications of the contract. Only after this latter
regular courts as stipulated by the parties in Clause 15 of their contract: circumstance was the matter brought before the arbitrator. Undoubtedly,
what was referred to arbitration was no longer the mere non-delivery of
All questions, disputes and differences, arising under the cargo at the first instance but also the failure of the replacement cargo
out of or in connection with this supply order, shall to conform to the specifications of the contract, a matter clearly within
be subject to the exclusive jurisdiction of the court, the coverage of Clause 16.
within the local limits of whose jurisdiction and the
place from which this supply order is situated. 14 The private respondent posits that it was under no legal obligation to
make replacement and that it undertook the latter only "in the spirit of
The following fundamental principles in the interpretation of liberality and to foster good business relationship". 20 Hence, the
contracts and other instruments served as our guide in arriving undertaking to deliver the replacement cement and its subsequent failure
at the foregoing conclusion: to conform to specifications are not anymore subject of the supply
order/contract or any of the provisions thereof. We disagree.
The constitutional mandate that no decision shall be rendered by any Time and again this Court has held that the essence of due process is to
court without expressing therein dearly and distinctly the facts and the be found in the reasonable opportunity to be heard and submit any
law on which it is based does not preclude the validity of "memorandum evidence one may have in support of one's defense 33 or stated otherwise,
decisions" which adopt by reference the findings of fact and conclusions what is repugnant to due process is the denial of opportunity to be
of law contained in the decisions of inferior tribunals. In Francisco v. heard. 34 Thus, there is no violation of due process even if no hearing was
Permskul, 26 this Court held that the following memorandum decision of conducted, where the party was given a chance to explain his side of the
the Regional Trial Court of Makati did not transgress the requirements of controversy and he waived his right to do so. 35
Section 14, Article VIII of the Constitution:
In the instant case, the private respondent does not deny the fact that it
MEMORANDUM DECISION was notified by the foreign court to file its objections to the petition, and
subsequently, to pay legal fees in order for its objections to be given
After a careful perusal, evaluation and study of the consideration. Instead of paying the legal fees, however, the private
records of this case, this Court hereby adopts by respondent sent a communication to the foreign court inquiring about the
reference the findings of fact and conclusions of law correct amount of fees to be paid. On the pretext that it was yet awaiting
contained in the decision of the Metropolitan Trial the foreign court's reply, almost a year passed without the private
Court of Makati, Metro Manila, Branch 63 and finds respondent paying the legal fees. Thus, on February 2, 1990, the foreign
that there is no cogent reason to disturb the same. court rejected the objections of the private respondent and proceeded to
adjudicate upon the petitioner's claims. We cannot subscribe to the
private respondent's claim that the foreign court violated its right to due
WHEREFORE, judgment appealed from is hereby process when it failed to reply to its queries nor when the latter rejected
affirmed in toto. 27 (Emphasis supplied.) its objections for a clearly meritorious ground. The private respondent
was afforded sufficient opportunity to be heard. It was not incumbent
This Court had occasion to make a similar pronouncement in upon the foreign court to reply to the private respondent's written
the earlier case of Romero v. Court of Appeals, 28 where the communication. On the contrary, a genuine concern for its cause should
assailed decision of the Court of Appeals adopted the findings have prompted the private respondent to ascertain with all due diligence
and disposition of the Court of Agrarian Relations in this wise: the correct amount of legal fees to be paid. The private respondent did
not act with prudence and diligence thus its plea that they were not
We have, therefore, carefully reviewed the evidence accorded the right to procedural due process cannot elicit either approval
and made a re-assessment of the same, and We are or sympathy from this Court. 36
persuaded, nay compelled, to affirm the correctness
of the trial court's factual findings and the soundness The private respondent bewails the presumed bias on the part of the
of its conclusion. For judicial convenience and arbitrator who was a former employee of the petitioner. This point
expediency, therefore, We hereby adopt by way of deserves scant consideration in view of the following stipulation in the
reference, the findings of facts and conclusions of the contract:
court a quo spread in its decision, as integral part of
this Our decision. 29 (Emphasis supplied) . . . . It will be no objection any such appointment that
the arbitrator so appointed is a Commission
Hence, even in this jurisdiction, incorporation by reference is employer (sic) that he had to deal with the matter to
allowed if only to avoid the cumbersome reproduction of the which the supply or contract relates and that in the
decision of the lower courts, or portions thereof, in the decision course of his duties as Commission's employee he
of the higher court. 30 This is particularly true when the decision had expressed views on all or any of the matter in
sought to be incorporated is a lengthy and thorough discussion dispute or difference. 37 (Emphasis supplied.)
of the facts and conclusions arrived at, as in this case, where
Award Paper No. 3/B-1 consists of eighteen (18) single spaced Finally, we reiterate hereunder our pronouncement in the case
pages. of Northwest Orient Airlines, Inc. v. Court of Appeals 38 that:
Furthermore, the recognition to be accorded a foreign judgment is not A foreign judgment is presumed to be valid and
necessarily affected by the fact that the procedure in the courts of the binding in the country from which it comes, until the
country in which such judgment was rendered differs from that of the contrary is shown. It is also proper to presume the
courts of the country in which the judgment is relied on. 31 This Court has regularity of the proceedings and the giving of due
held that matters of remedy and procedure are governed by the lex fori or notice therein.
the internal law of the forum. 32 Thus, if under the procedural rules of the
Under Section 50, Rule 39 of the Rules of Court, a
judgment in an action in personam of a tribunal of a
foreign country having jurisdiction to pronounce the
same is presumptive evidence of a right as between
the parties and their successors-in-interest by a
subsequent title. The judgment may, however, be
assailed by evidence of want of jurisdiction, want of
notice to the party, collusion, fraud, or clear mistake
of law or fact. Also, under Section 3 of Rule 131, a
court, whether of the Philippines or elsewhere,
enjoys the presumption that it was acting in the
lawful exercise of jurisdiction and has regularly
performed its official duty. 39
The foreign judgment being valid, there is nothing else left to be done
than to order its enforcement, despite the fact that the petitioner merely
prays for the remand of the case to the RTC for further proceedings. As
this Court has ruled on the validity and enforceability of the said foreign
judgment in this jurisdiction, further proceedings in the RTC for the
reception of evidence to prove otherwise are no longer necessary.
SO ORDERED.