Doc. No.

:
SIDHI QUALITY SYSTEM PROCEDURE Rev. No. : 00
ALCAST INITIAL SUPPLY CONTROL Date :
Page : 1 of 2.

1.0 PURPOSE :

To define special control needs to be exercised during the initial phase of mass production with the purpose of
collecting sufficient data in order to judge whether the mass production can be continued using the existing process .

2.0 SCOPE :

This procedure is applicable to all new parts & change parts (both customer ECN’s and in-house changes .

3.0 RESPONSIBILITIES :

The overall responsibility of maintaining the effectiveness and implementation of this procedure lies with
Head Manufacturing.

4.0 PERIOD :

The I/C is applicable for 3 months after SOP at customer end for new parts & 1 month after SOP at customer end for
changed parts.

5.0 DESCRIPTION :

Special condition to be observed by I/C control:

S.NO. CRITERIA METHODS RESPONSIBILITY


1 New part manufactured APQP ACTIVITIES Dev. head
2 Major modification in any parts Review control plan QA Manager
3 A new machinery is installed Lay out inspection QA Manager
4 When a major change in process Change control plan QA Manager
5 When a part is remanufacturing Lay out inspection QA Manager
after long lay off(>=12 months)

Activities during initial supply control.


A. From start of the Production trail three months time period is consider as a initial supply.
B. these two special activities are done –
a. Precaution
b. Prevention

In Phase a i.e. Precaution


1. Inspection / Testing frequency increase in Incoming inspection, Inprocess Inspection, Final inspection.
2. Inspection and testing parameters are also increase in all stages.
In Phase b i.e. Prevention
1. Process capabilities study will do of critical dimensions .
2. Skilled operator is use for operation
3. Supplier audit is done
4. Role and responsibility of supervisors/managers is defined.

Approved By
Prepared By
Doc. No. : QSP-EG-03.
QUALITY SYSTEM PROCEDURE Rev. No. : 00
AEW INITIAL SUPPLY CONTROL Date : 06.06.09
Page : 2 of 2.

C. Criteria for termination of Initial supply


1. Cpk more than 1.67 is achieved
2. All the problem which occurred during the development are resolved and cross check to assure that they
remains resolved
3. Any new problem arising during the initial supply control are also resolved.

Termination authority during initial supply is QA head.

D. Visual Display
1. All Process under initial supply to be identified by putting display on each process with part name, part
number, start date, end date etc.
2. For single piece flow processes , start and end stations identified

Initial supply control tags have


1. Part name/no.
2. supplier name
3. change type i.e. New Product /Design/ process
4. process flow diagram In back of the tag.

E. The records of defects and rejection data during initial supply control period maintained separately by QA dept.
and Development dept. for future reference and compression.

 Retention period

. The records of defects and rejection data during initial supply control period maintained separately by QA dept.
and Development dept. for future reference and compression A parts retention period is 11 years and for general
parts 1 years.

THE PROCEDURE IS APPLICABLE TO ALL THE SUPPLIERS SUPPLY NEW OR CHANGE PARTS

6.0 RECORDS

5.1 Initial Phase Control Register.


5.2 In Process check sheet.

Approved By