ID Task Mode Task Name Duration February

Start
11 July 21 January 1
6/3 8/19 11/4 1/20 4/6
1 1 Agile Bukit Bintang (Malaysia) 900 days Wed 1/1/20
2 1.1 Mobilization 30 days Wed 1/1/20
3 1.2 Basement 1- Transfer floor 350 days Fri 1/31/20
4 1.2.1 Concrete Structure Work 150 days Fri 1/31/20
5 1.2.2 Block Work 125 days Sat 3/21/20
6 1.2.3 Wall Plastering 125 days Mon 4/20/20
7 1.2.4 Wall Finishes 150 days Sun 5/10/20
8 1.2.5 Floor Finishes 150 days Sat 5/30/20
9 1.2.6 Doors & Windows 100 days Fri 6/19/20
10 1.2.7 Ceiling work 100 days Thu 7/9/20
11 1.2.8 Waterproofing 150 days Sun 6/14/20
12 1.2.9 Elecrical Work 175 days Mon 6/29/20
13 1.2.10 Mechanical & Plumbing Work 175 days Mon 6/29/20
14 1.2.11 Fire Protection & detection 100 days Thu 8/13/20
15 1.2.12 CCTV,Telephone, InterCom 75 days Wed 10/7/20
16 1.2.13 Lightning Protection System 75 days Wed 10/7/20
17 1.2.14 External Painting 100 days Wed 10/7/20
18 1.3 Tower A 475 days Thu 7/9/20
19 1.3.1 Concrete Structure Work 350 days Thu 7/9/20
20 1.3.2 Block Work 325 days Sun 8/23/20
21 1.3.3 Wall Plastering 325 days Tue 9/22/20
22 1.3.4 Wall Finishes 300 days Thu 10/22/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1
ID Task Mode Task Name Duration February
Start
11 July 21 January 1
6/3 8/19 11/4 1/20 4/6
23 1.3.5 Floor Finishes 300 days Thu 10/22/20
24 1.3.6 Doors & Windows 275 days Sun 12/6/20
25 1.3.7 Ceiling work 275 days Mon 12/21/20
26 1.3.8 Waterproofing 225 days Sat 11/21/20
27 1.3.9 Elecrical Work 325 days Fri 11/6/20
28 1.3.10 Mechanical & Plumbing Work 325 days Fri 11/6/20
29 1.3.11 Fire Protection & detection 150 days Tue 1/5/21
30 1.3.12 Gas installation 125 days Tue 1/5/21
31 1.3.13 MV Distribution System 150 days Fri 4/30/21
32 1.3.14 CCTV,Telephone, InterCom 125 days Tue 5/25/21
33 1.3.15 Lightning Protection System 100 days Wed 2/24/21
34 1.3.16 External Painting 75 days Fri 8/13/21
35 1.4 Tower B1 575 days Thu 7/9/20
36 1.4.1 Concrete Structure Work 425 days Thu 7/9/20
37 1.4.2 Block Work 400 days Sun 8/23/20
38 1.4.3 Wall Plastering 400 days Tue 9/22/20
39 1.4.4 Wall Finishes 375 days Thu 10/22/20
40 1.4.5 Floor Finishes 375 days Thu 10/22/20
41 1.4.6 Doors & Windows 350 days Sun 12/6/20
42 1.4.7 Ceiling work 350 days Mon 12/21/20
43 1.4.8 Waterproofing 300 days Sat 11/21/20
44 1.4.9 Elecrical Work 400 days Fri 11/6/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 2
ID Task Mode Task Name Duration February
Start
11 July 21 January 1
6/3 8/19 11/4 1/20 4/6
45 1.4.10 Mechanical & Plumbing Work 400 days Fri 11/6/20
46 1.4.11 Fire Protection & detection 225 days Tue 1/5/21
47 1.4.12 Gas installation 200 days Tue 1/5/21
48 1.4.13 MV Distribution System 225 days Fri 4/30/21
49 1.4.14 CCTV,Telephone, InterCom 200 days Tue 5/25/21
50 1.4.15 Lightning Protection System 175 days Mon 5/10/21
51 1.4.16 External Painting 95 days Mon 11/1/21
52 1.5 Tower B2 575 days Thu 7/9/20
53 1.5.1 Concrete Structure Work 425 days Thu 7/9/20
54 1.5.2 Block Work 400 days Sun 8/23/20
55 1.5.3 Wall Plastering 400 days Tue 9/22/20
56 1.5.4 Wall Finishes 375 days Thu 10/22/20
57 1.5.5 Floor Finishes 375 days Thu 10/22/20
58 1.5.6 Doors & Windows 350 days Sun 12/6/20
59 1.5.7 Ceiling work 350 days Sun 12/6/20
60 1.5.8 Waterproofing 300 days Sat 11/21/20
61 1.5.9 Elecrical Work 400 days Fri 11/6/20
62 1.5.10 Mechanical & Plumbing Work 400 days Fri 11/6/20
63 1.5.11 Fire Protection & detection 225 days Tue 1/5/21
64 1.5.12 Gas installation 200 days Tue 1/5/21
65 1.5.13 MV Distribution System 225 days Fri 4/30/21
66 1.5.14 CCTV,Telephone, InterCom 200 days Tue 5/25/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 3
ID Task Mode Task Name Duration February
Start
11 July 21 January 1
6/3 8/19 11/4 1/20 4/6
67 1.5.15 Lightning Protection System 175 days Mon 5/10/21
68 1.5.16 External Painting 100 days Wed 10/27/21
69 1.6 Tower C1 550 days Thu 7/9/20
70 1.6.1 Concrete Structure Work 400 days Thu 7/9/20
71 1.6.2 Block Work 375 days Sun 8/23/20
72 1.6.3 Wall Plastering 375 days Tue 9/22/20
73 1.6.4 Wall Finishes 350 days Thu 10/22/20
74 1.6.5 Floor Finishes 350 days Thu 10/22/20
75 1.6.6 Doors & Windows 325 days Sun 12/6/20
76 1.6.7 Ceiling work 325 days Sun 12/6/20
77 1.6.8 Waterproofing 275 days Sat 11/21/20
78 1.6.9 Elecrical Work 375 days Fri 11/6/20
79 1.6.10 Mechanical & Plumbing Work 375 days Fri 11/6/20
80 1.6.11 Fire Protection & detection 200 days Tue 1/5/21
81 1.6.12 Gas installation 175 days Tue 1/5/21
82 1.6.13 MV Distribution System 200 days Fri 4/30/21
83 1.6.14 CCTV,Telephone, InterCom 175 days Tue 5/25/21
84 1.6.15 Lightning Protection System 150 days Thu 4/15/21
85 1.6.16 External Painting 100 days Sat 10/2/21
86 1.7 Tower C2 550 days Thu 7/9/20
87 1.7.1 Concrete Structure Work 400 days Thu 7/9/20
88 1.7.2 Block Work 375 days Sun 8/23/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 4
ID Task Mode Task Name Duration February
Start
11 July 21 January 1
6/3 8/19 11/4 1/20 4/6
89 1.7.3 Wall Plastering 375 days Tue 9/22/20
90 1.7.4 Wall Finishes 350 days Thu 10/22/20
91 1.7.5 Floor Finishes 350 days Thu 10/22/20
92 1.7.6 Doors & Windows 325 days Mon 12/21/20
93 1.7.7 Ceiling work 325 days Mon 12/21/20
94 1.7.8 Waterproofing 275 days Sat 11/21/20
95 1.7.9 Elecrical Work 375 days Fri 11/6/20
96 1.7.10 Mechanical & Plumbing Work 375 days Fri 11/6/20
97 1.7.11 Fire Protection & detection 200 days Tue 1/5/21
98 1.7.12 Gas installation 175 days Tue 1/5/21
99 1.7.13 MV Distribution System 200 days Fri 4/30/21
100 1.7.14 CCTV,Telephone, InterCom 175 days Tue 5/25/21
101 1.7.15 Lightning Protection System 150 days Thu 4/15/21
102 1.7.16 External Painting 100 days Sat 10/2/21
103 1.8 Pool Construction 200 days Thu 8/13/20
104 1.9 Elevetors installation 225 days Tue 9/7/21
105 1.10 External drainage 150 days Wed 10/27/21
106 1.11 Miscellaneous works 180 days Mon 11/1/21
107 1.12 Testing & Commissioning 160 days Sat 12/11/21
108 1.13 Handing over 160 days Mon 1/10/22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 5
June 11 November 21 May 1 October 11 March 21 September
4/6 6/22 9/7 11/23 2/8 4/26 7/12 9/27 12/13 2/28 5/16 8/1

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 6
June 11 November 21 May 1 October 11 March 21 September
4/6 6/22 9/7 11/23 2/8 4/26 7/12 9/27 12/13 2/28 5/16 8/1

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 7
June 11 November 21 May 1 October 11 March 21 September
4/6 6/22 9/7 11/23 2/8 4/26 7/12 9/27 12/13 2/28 5/16 8/1

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 8
June 11 November 21 May 1 October 11 March 21 September
4/6 6/22 9/7 11/23 2/8 4/26 7/12 9/27 12/13 2/28 5/16 8/1

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 9
June 11 November 21 May 1 October 11 March 21 September
4/6 6/22 9/7 11/23 2/8 4/26 7/12 9/27 12/13 2/28 5/16 8/1

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project-Malaysia - Cop
Summary Manual Summary Rollup Critical
Date: Thu 8/1/19
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 10