MRP Data maintanance:

T Code: MM02

 Enter material
 Select MRP and Work scheduling views
 Select MRP type PD or V1
 Maintain reorder point for consumption base planning materials
 Select MRP controller based on material type
 Select lot sizing process EX or FX
 Maintain lot sizes
 Maintain In- house production time and GR processing time
 Maintain strategy group 10 or 20 for FG materials only
 Maintain availability check 02
 Select Dependent requirements as 2
 Select production supervisor for FG and SFG based on production line
 Select scheduling profile Z111 for FG and Z112 for FG