Weekly Status Report

One Tara Blvd, suite 200 | Nashua NH 03062 | Tel: 603-321-4217 | Fax: 603-328-9316

Prepared by: Akino John Kennedy


Group: Application Delivery and Network Services
Date: February 8th,2019
Client Name: Dell

Monday Tuesday Wednesday Thursday Friday Saturday Sunday


(02/04) (02/05) (02/06) (02/07) (02/08) (02/09) (02/10)
8 8 8 8 8

Issues and Accomplishments


Red (Alarms to management, help needed from management team)
Items below represent critical issues that are keeping Project(s) from delivering on schedule.
These items need management help in resolving. Stated below issues must be resolved by scheduled
date
Project Issue / Possible Solution Issue Resolution Date
Application Issue: N/A N/A
Load Possible Solution: N/A
balancing Issue: N/A N/A
Possible Solution: N/A
Yellow (Issues)
Items below represent issues that management should be aware of Project(s) livering on schedule.
These items may not need management help in resolving. Stated below issues must be resolved by
scheduled date.
Project Issue / Possible Solution Issue Resolution Date
Application Issue: N/A N/A
Load Possible Solution: N/A
balancing Issue: N/A N/A
Possible Solution: N/A
Green (Key accomplishments, progress, acknowledgments)
Items below represent accomplishments or progress made on deliverables for the week.
Project Accomplishments Task Accomplishment
Date
Application 1. Removed profiles on load balancers and added new February 8th, 2019
Load profiles.
balancing 2. Implemented iRule to redirect traffic to specific
URL.
3. Deleted unused vlans on existing switches.
4. Trouble shoot network issues.
5. Consultation on new load balancing requests.
Weekly Status Report

One Tara Blvd, suite 200 | Nashua NH 03062 | Tel: 603-321-4217 | Fax: 603-328-9316

Next Week Priorities


Items below represent I will be working on next week. These items may include new and/or outstanding
tasks.
Blue (Outstanding deliverables)
Items below represent previous week’s deliverables extended into current week. Original schedule date
and the reason for extending originally scheduled date must be included. Outstanding tasks may include
issues outlined in the previous section.

Project Task Original Reason for Extending Schedule


Schedule Date Date
Application N/A N/A N/A
Load
balancing

Black (New deliverables)


Items below represent new deliverables scheduled for the next week. Deliverables should be completed
by scheduled date.

Project Task Scheduled Date


Application 1. Configure new switches for new location in round rock. N/A
Load 2. Write instructions and get it approved to replace faulty
balancing hard drive on load balancer.
3. Write instructions to upgrade the version of load
balancer from 10.2.4 to 11.5.0.
4. Consultation on new load balancing requests.

Employee Signature:
Date: February 8th , 2019

Manager Signature: _______________________________________

Date: ___________________________________________________
Weekly Status Report