Академический Документы
Профессиональный Документы
Культура Документы
FOUNDATION
ENGINEERING
MARINE AND FOUNDATION
ENGINEERING 3
THINK FURTHER
COWI's history in civil engineering dates back to 1930 when the
company was founded. Since then, COWI has pushed the boundaries
of marine design through our involvement in more than 3,300 marine
projects worldwide. These projects range from large and technically
challenging LNG terminals, container ports and waterfront developments
to equally challenging cooling water systems, offshore wind farms, flood
protection, locks and dams.
AIN SUKHNA MARINE OIL TERMINAL - GORGON BARROW ISLAND LNG PLANT - AQABA LNG - SHTOKMAN LNG TERMINA - BATUMI TERMINAL - NEW PIER AND QUAY
STOCKHOLM VÄRTAHAMNEN - HANSTHOLM QATAR - JEBEL ALI T3-Q10 CONTAINER TERMINAL - NEW YORK CITY CRUISE TERMINAL DREDGING - CALETA LA MISION PORT - NORVIKUDDEN
CONTAINER AND RO-RO TERMINAL - DEVELOPMENT PLAN FOR KRONBORG CASTLE AND ELSINORE HARBOUR - LUSAIL DEVELOPMENT - MUSEUM OF ISLAMIC
ART - AL ZORAH DEVELOPMENT - BEIRUT CENTRAL DISTRICT, MARINE WORKS - CASTING BASIN COSTA AZUL - QATAR - HONG KONG THREE RUNWAY SYSTEM - LONDON ARRAY -
WIKINGER OFFSHORE WIND FARM - YANBU 2 POWER PLANT AND WATER PROJECT - RABIGH POWER PLANT NO 2 - NEW ORLEANS FLOOD PROTECTION BARRIER
DATA
Project period 2013-2017
Client Per Aarsleff A/S
SERVICES
Photo: Stockholm Hamn
OSLO
COPENHAGEN
LONDON
QATAR
MANILA
CHENNAI
In COWI, we take pride in our achievements. Since the 1970's, we
have been at the forefront of marine engineering, setting the standard KUALA LUMPUR
for tomorrow’s best practices. Together with our clients, we have been
SINGAPORE
involved in more than 3,300 marine projects all over the
world – from Argentina to the far corners of Russia.
We can take your marine project further than you imagine. COWI's key
marine and coastal engineering offices are shown here. With offices,
around the globe, we are never far away. And regardless of the scope
of your marine construction or problem, we deliver worldwide.
DATA
Project period 2007-2014
Client Ministry of the Interior,
Elsinore Municipality
SERVICES
›› Overall planning
›› Preparation of tender documents
›› Project management consultant for the
implementation of the entire project
›› Environmental and geotechnical investigations
›› Cost estimations
›› Supervision of works.
Photo: Winther airphoto
MARINE AND FOUNDATION
ENGINEERING 17
SERVICES
DATA
›› Master planning
Project period 2009-2013
›› Bathymetric and topographic surveys
Client Aarsleff / Bilfinger Berger
›› Geotechnical investigations
Joint Venture
›› Environmental impact assessment
›› Conceptual and detailed design SERVICES
›› Preparation of tender documents ›› Hydraulic load calculations
›› Assistance in the tendering and contracting ›› Structural design
phase ›› Geotechnical design
›› Construction supervision. ›› Driveability analyses
›› Cathodic protection analysis and design
›› Scour assessment
DATA
Project period 2010-2017
Client Iberdrola Renovables
SERVICES
›› Structural design of topside and jackets
›› Hydraulic design
›› Geotechnical design
›› Electrical and mechanical design
›› Low voltage design.
OWF App
MARINE AND FOUNDATION
ENGINEERING 21
OUR SERVICES
With our services, we cover the entire life cycle of
a marine project from early ideas to the operational
phase and rehabilitation – or decommissioning when
the time comes.
DIFFERENT PHASES
DIFFERENT SERVICES
SITE SUPERVISION
We handle all disciplines relating to
preconstruction and construction, project
completion and subsequent defects liability
INDEPENDENT DESIGN CHECK AND
period and we deliver full project quality
VALUE ENGINEERING
Agility and expertise are the key to efficient marine and coastal engineering. We provide assistance to clients of complex
documentation.
We bring both to the table to make sure we provide you with the exact marine projects assessing if the project is RE-EVALUATION AND REHABILITATION
service and expertise your project needs – regardless of where you are in reliable, safe, durable, constructable We cover all phases and every step of the
the process. and optimal. inspections to ensure that technical evaluations
are coherent – from visual inspections to
special studies of load capacity and safety of
structures.
CONSTRUCTION ENGINEERING
We design rehabilitation works for existing
The right selection and combination of
structures for increased capacity and for
construction methods is of crucial importance
replacement of key structural elements.
to any marine project. We handle erection
schemes, logistics, temporary structures as
well as the erection engineering itself.
DESIGN
We handle everything from development of OPERATION AND MANAGEMENT
PROJECT IMPLEMENTATION
design basis to construction aspects as well Our asset management is based on worldwide
We provide policy planning, advice and
as life-cycle design. We have state-of-the- practical experience with planning, budgeting
management consulting for project decision
art analysis tools which enable us to deliver and handling of short and long-term operation,
and project implementation.
competitive designs to tight schedules. With maintenance and rehabilitation works, as well
our vast experience we can secure delivery of as implementation of management concepts.
your project to quality, on time and budget.
SITE STUDIES
Understanding the environment in which the
project is to be constructed requires knowledge
obtained from various sources. The quality FEASIBILITY STUDIES CONSTRUCTION MANAGEMENT
of the project depends on the accuracy and We have all the competencies to carry out We handle the contract, monitor the progress DECOMMISSIONING
details of information obtained through these feasibility studies. And we take into account of the project in all details as well as cost To facilitate the choice between removal
investigations. They include met-ocean data technical, environmental, social and economic control and take care of risk management. We options, we carry out quantitative, comparative
gathering and assessment, seismic and aspects to establish the basis for the right also handle stakeholders and authorities and risk assessments of the various options and
tsunami studies, collision/spill risk assessment decisions. perform technical follow-up. we take damaged structures, personnel and
and mitigation, and navigation simulations. environmental risks into account.
MARINE AND FOUNDATION
ENGINEERING 25
DATA
Project period 2011-2016
Client Saudi Archirodon Ltd.
SERVICES
›› Met-ocean study and numerical modelling of waves
and hydrodynamics
›› Recirculation modelling for confirmation of the
location of seawater intake and outfall
›› Numerical flow modelling for optimisation of
seawater intake channel
›› Layout and design of seawater outfall transition
structure and GRP pipelines covered by rock
protection
›› Design of seawater intake channel and breakwaters
›› Design of dredging, reclamation and foundation of
structures
Photo: COWI
COWI provided numerical modelling and design COWI also completed the shell design for
services for the marine subcontract. the navigable pass precast segments, paving
blocks and the lifting frame for the navigable
DATA pass segments and supported the design of
Project period 2010-2013 the tainter gates.
Client Huta Marine Works Ltd.
DATA
SERVICES Project period 2005-2020
›› Hydraulic engineering and numerical modelling Client U.S. Army Corps of Engineers,
›› Management of physical modelling of pumping Louisville District
station, carried out in hydraulic lab, breakwater
revetment, and outfall structure SERVICES
›› Geotechnical engineering ›› Casting yards/launch system
›› Piping engineering for intake glass reinforced ›› Dredging
pipes ›› Heavy lift systems
›› Electrical engineering for the cathodic protection ›› Detailed design of all precast and insitu cast
of marine works. concrete elements
›› Foundation design
›› Mooring and berthing analysis
Photo: COWI
Photo: COWI
›› Seismic analysis
›› Cost estimation.
MARINE AND FOUNDATION
ENGINEERING 29
DATA
Project period 2008-2012
Client The U. S. Army Corps of Engineers
SERVICES
›› Numerical modelling
›› Concept and detailed design of the main sector
gate monolith, batter pile floodwall, reinforced
concrete by-pass barge gate, MRGO berm
structure, GIWW approach walls, and scour
OUR TEAMS
Since we designed our first marine project, we have actively
participated in the research and development of new
techniques, the use of new materials and new technologies
in the field of marine structures.
DIFFERENT ASSIGNMENTS
DIFFERENT COMPETENCIES
Our large pool of engineers and experts enables the project manager
to set up a team with the right competencies to match your project.
THE CONSTRUCTION THE GEOTECHNICAL THE PROJECT THE STRUCTURAL THE SEISMIC THE HYDRAULIC AND
> STRUCTURAL DESIGN > DREDGING DESIGN > COST ESTIMATION > REHABILITATION ENGINEERING > WAVE
SPECIALIST EXPERT MANAGER ENGINEER EXPERT COASTAL EXPERT
MODELLING > HYDRAULIC MODELLING > SOIL STRUCTURE INTERACTION > HYDRODYNAMIC FLOW MODELLING Our construction Our geotechnical Our project manager Our senior structural Based on information Our hydraulic expert
specialist works to expert specifies is responsible for engineers are from the site, our is responsible for
> CURRENT MODELLING > METOCEAN STUDIES > SERVICE LIFE DESIGN > LABORATORY TESTING > SEISMIC secure the balance the geotechnical managing the contract responsible for all seismic expert determining how
between design and site investigations, with the client and for basic engineering establishes spectra the hydrodynamic
ANALYSES > FATIGUE ASSESSMENTS > FINITE ELEMENT ANALYSES > LIFE CYCLE COSTS > SUSTAINABLE
construction. analyses the results delivering the project aspects of the and time series to be processes influence
ENGINEERING > MECHANICAL AND ELECTRICAL INSTALLATION DESIGN > OPERATIONAL RISK MANAGEMENT and establishes a on agreed time and project – drawings used in the design the design and
geotechnical design budget. and verification, to process. functionality of any
> CONSTRUCTION RISK MANAGEMENT > NAVIGATION SIMULATION > MASTER PLANNING > STRUCTURAL DYNAMICS basis for the project. secure practical structure.
buildable structures.
> SHIP COLLISION RISK > UTILITIES > BUILDING DESIGN > MODEL TEST VERIFICATIONS > SHIP IMPACT PROTECTION
OUR EXPERTISE
Every marine project is unique. To meet this challenge, we have world-class
engineers and experts working together to integrate seamlessly all aspects
of marine engineering – from the marine construction itself to traffic planning,
geo mapping and environmental impact assessment.
For every project, from a small coastal protection project to a major LNG
terminal, we establish a specific team to ensure that we deliver the best
solution for you.
Photo: COWI
MARINE AND FOUNDATION
ENGINEERING 39
DIFFERENT CHALLENGES
DIFFERENT EXPERTISE
We combine our expertise and competencies to deliver
the optimal solution to your challenge.
DESIGN PROCUREMENT
›› Marine foundation design ›› Procurement strategies
›› Offshore wind turbine foundations ›› Tender documents LIFE CYCLE CONSIDERATIONS
›› Marine terminals ›› Scheduling ›› Operation and emergency planning
›› Ports ›› Contracting ›› Inspection and maintenance systems
›› Coastal engineering ›› Life cycle cost optimization CONSTRUCTION
›› Waterfront developments ›› Sustainability ›› Construction management
›› Man-made islands ›› Site supervision
CONCEPT DEVELOPMENT ›› Breakwaters
›› Marine structures ›› Electrical and mechanical design
SITE INVESTIGATIONS
›› Renderings and animations of installations
›› Design basis development
›› Geological, wind and hydraulic IMPACT ASSESSMENT
investigations ›› Environmental impact
›› Operational risk and safety ›› Hydraulic modelling
concepts ›› Social impact
›› Metocean conditions ›› Planning impact
›› Cost impact
MARINE AND FOUNDATION
ENGINEERING 41
THE PEARL-QATAR
The Pearl-Qatar project involved detailed
design of the reclamation works for the 400
hectare new island requiring approximately
13.5 million m³ of fill and the associated sea
defence structures for the 40 km of new
shoreline.
DATA
Project period 2003-2008
Client United Development
Company (UDC)
SERVICES
›› Bathymetric survey
›› Design of marinas
›› Design of culverts
›› Design basis
›› Conceptual design
›› Detailed design
›› Preparation of tender and contract documents.
MARINE AND FOUNDATION
ENGINEERING 43
DATA SERVICES
Project period 2010-2013 ›› Detailed evaluation of the top of competent stratum
Client Abu Dhari National Oil Company ›› Required embedment depth of deep cement
(ADNOC) columns
›› 3D ground model
SERVICES ›› Quantities for DCM clusters
›› Design checking and review ›› Technical assessment of possible non-compliant
›› Project management and construction supervision DCM works.
›› Administration
›› Control
›› Review
›› Follow-up
›› Commissioning
›› Quantities for DCM clusters
›› Technical assessment of possible
non-compliant works.
MARINE AND FOUNDATION
ENGINEERING 45
WHAT IS NEEDED?
Protection against high tides and rain or an economic analysis of consequences
or intervention. We are ready to take on whatever is needed on requests from
the municipalities or the citizens.
MARINE AND FOUNDATION
ENGINEERING 47
BAHRAIN LNG IMPORT PORT OF REDWOOD CITY, KNPC NORTH AND SOUTH PIER RUWAIS GASPORT, AL ZOUR LNG IMPORT, PORT OF ANCHORAGE, PLANNING FOR CRUISE SHIP CHHARA PORT, CARGO TERMINAL, PORT OF SONAREF REFINERY MARINE
TERMINAL CALIFORNIA, USA SURVEY, KUWAIT UAE KUWAIT ALASKA, USA FACILITY, GREENLAND INDIA OWENDO, GABON, WEST AFRICA TERMINAL, ANGOLA
DATA DATA DATA DATA DATA
DATA DATA DATA DATA DATA
›› Project Period: 2015-2019 ›› Project Period: 2011-2013 ›› Project Period: 2012-2014 ›› Project period: 2015 ›› Project Period: 2016-2018
›› Project period: 2017 ›› Project period: 2013 ›› Project period: 2017-2018 ›› Project period: 2016 ›› Project period: 2013-2014
›› Client: Whessoe Engineering Limited ›› Client: Port of Redwood City ›› Client: Kuwait National Petroleum ›› Client: Excelerate Energy Limited ›› Client: Hyundai Engineering and
›› Client: Port of Anchorage ›› Client: Qaasuitsup Kommunia ›› Client: Simar Port Pvt Ltd ›› Client: AFCONS Overseas Project ›› Client: Odebrecht Angola Projectos e
›› (main PMC consultant), Nogaholding Company and Integral Services Co. Partnership Construction Company
Deepwater access for bulk, neo-bulk, and Gabon SARL Serviços Lda
›› Onshore receiving facility and pipeline W.L.L. (ISCO) The Port of Anchorage is undertaking a Updating and clarifying current and future The greenfield port at Chhara 50 km
liquid cargos. Existing Wharves 1 and 2, Abu Dhabi Gas Industries Ltd. (GASCO) New liquefied natural gas regasification
(4.1 km, buried) modernization program to upgrade the cruise ship operations at the Ilulissat Ice- to the west of Diu Airport will build a Gabon Special Economic Zone (GSEZ) Sonangol is planning to build a refinery
built in the 1930’s and 1940’s, are used Terminal for gas import and export of intends to develop a gas port at the plant to supply natural gas to Kuwait
›› Subsea pipeline (4.3 km, 10-15 m water port’s facilities and provide new structures fiord in Qaasuitsup Kommunia in northern breakwater with a total length of 4.2 km Ports S.A. builds a new general cargo in Lobito including a marine terminal to
for offloading aggregate, primarily from crude oil and refined products, for vessels existing sulphur terminal in Ruwais, Abu national gas grid.
depth) that can survive extreme seismic events Greenland. comprising of 3.3 km section to protect terminal comprising a 420 m long berth receive Angolan crude oils, which will be
Panamax vessels. COWI was retained to of up to 300,000 DWT. Dhabi to provide a natural gas supply
›› Breakwater (600 m long, 15 m water SERVICES and Cook Inlet’s harsh marine environment, the liquefied natural gas berths, container including quay, storage and service crane processed into refined liquid products
lead a modernization project for Wharves through a floating storage and regasifica- SERVICES
depth) SERVICES COWI will provide detailed design of the which includes extreme tidal fluctuations and multipurpose berths and coal jetties. for general cargo and container vessels, along with solid byproducts. The new
1 and 2. tion unit (FSRU). Excelerate provides the ›› Review of current cruise ship traffic to
›› Regasification platform with jacket ›› Sub- and superstructure inspections following units: and winter ice impacts. The new resilient COWI has been awarded the services dredged to -14.0m CD, for import of marine terminal will consist of two berths,
138.000 m³ FSRU and upgrades the jetty Ilulissat town in terms of opportunities
substructure and regas. module SERVICES including underwater inspection of piles ›› Jetty I and II: OP, BD, MDs and IB, structures will have a 75-year design life. related to the detailed design of the general cargo such as grain, re-bars and one capable of loading liquid products
topside HP loading arms and associated and challenges
›› Berthing jetty for FSU (175,000 m³) ›› Coordination of site investigations ›› Non-destructive testing and gauging Trestle: main trestle, arm 1 and arm 2, breakwater. hydrocarbons, and export of palm oil and and solid products and for loading liquid
nearshore ancillary facilities, including a SERVICES ›› Meetings and interviews with
and LNG carriers up to QMax size. including a geotechnical exploration, with ultrasound equipment Approach channel and flare platform containers. AFCONS Gabon SRL is the products and for loading liquid products
24" pipeline linking to the local gas grid. ›› Structural design stakeholder groups to identify local SERVICES
hydrographic survey, topographic ›› Structural calculations of typical ›› Intake tower, pipelines and pump contractor for design and construction of and unloading heavy crude oil as well as
Bahrain LNG W.L.L. is establishing an ›› Geotechnical engineering concerns and preferences ›› Data collection and review of existing
survey, and hazardous material surveys sections in North and South Piers SERVICES station the works. AFCONS has appointed RH- a materials offloading facility.
LNG import and regasification facility with ›› Coastal engineering. ›› Field trips by foot and by boat along the data
›› Marine structural design ›› Finite element modelling and structural ›› Berth layout and mooring study ›› Outfall diffuser, pipelines and chamber DHV as its Lead Design Consultant COWI
peak send-out capacity of 800 MMSCFD, wilderness coast north of the Icefiord to ›› Establishment of design conditions SERVICES
›› Production of bridging documents for assessments ›› Desktop navigation simulation ›› Land reclamation and rock revetment. is the independent engineer.
approximately 4 km off the coast near the identify suitable locations with potential ›› Concept design and detailed design for ›› Independent design verification (IDV)
Mina Salman port. the design-build team ›› Survey and re-assessment study for the ›› Basic and detailed marine and structural SERVICES
for development of new marine facilities selected concept of marine facilities (blockworks,
›› Permitting North Pier engineering
›› Summary report with proposed next ›› Design basis for hydraulic design ›› Independent design verification of revetments, reclamation)
SERVICES ›› Review and approval of the design-build ›› Re-assessment calculations and ›› Civil engineering for the onshore
steps. ›› Geotechnical design marine and onshore facilities, including ›› Technical assistance on dynamic
›› PMC sub-consultant for the marine works teams' 75%, 95% and final designs rehabilitation strategy study. building and pipe racks.
›› Specification and supervision for 2D and civil infrastructure and MEP works compaction trial tests
›› Technical advisor to the National Oil ›› Quality assurance during construction.
3D physical modelling tests. ›› Alternative design of revetment and
and Gas Holding Company for certain ›› Independent modelling of structures.
heavy duty pavement.
interface-related activities.
MARINE AND FOUNDATION
ENGINEERING 49
BREAKWATER FOR VIZHINJAM HANSTHOLM PORT EXPANSION, SALWA RESORT HOTEL, MARINE MONACO URBANISATION EN SHENZHONG LINK, RENTEL OFFSHORE WIND FARM, MERKUR OFFSHORE WIND THORNTON BANK OFFSHORE FORMOSA 1 OFFSHORE HORNS REV C, KRIEGERS
PORT, INDIA DENMARK WORKS, QATAR MER PHASE PRO/EXE CHINA BELGIUM FARM, GERMANY WIND FARM - PHASE 1, WIND FARM FOUNDATIONS, FLAK A AND B, TRANSFORMER
BELGIUM TAIWAN PLATFORMS, DENMARK
DATA DATA DATA DATA DATA DATA DATA
›› Project period: 2017-2018 ›› Project period: 2017-2018 ›› Project period: 2014-2015 ›› Project period: 2015-2013 ›› Project period: 2016-2017 ›› Project period: 2014-2017 ›› Project period: 2015-2017 DATA DATA DATA
›› Client: HOWE Engineering projects ›› Client: Per Aarsleff A/S ›› Client: Tashgeel & Besix JV ›› Client: SAM L'Anse du Portier ›› Client: Shenzhong Link Management ›› Client: Rentel NV ›› Client: DEME GeoSea NV ›› Project period: 2006-2008 ›› Project period: 2014-2015 ›› Project period: 2013-2015
(India) pvt Limited Center ›› Total: 550 MW ›› WTG: Alstom Haliade 150, 6 MW ›› Client: Dredging International n.v. ›› Client: Formosa Wind Power Co. ›› Client: Energinet.dk
Hanstholm is a major fishery harbour Private Engineering Office develops a The Principality has contracted for a
›› Water depth: 22-32 m ›› Foundation no.: 66 Belgium ›› Total: 144 MW
COWI carried out the detailed design of on the Danish North Sea coast. It has major high end resort. It includes a marina 60,000-sqm extension of the city of The 24 km link will connect the cities of Concept and basic design of two trans-
›› Foundations no: 42 ›› Water depth: 27-33 m ›› WTG: REpower 5.0 MW ›› Water depth: 15-30 m
the 3.1 km long rubble mound break- launched a design-build tender for an in the middle and man-made beaches at Monaco into the sea. SOCOTEC and Shenzhen and Zhongshan across the former platforms for the 600 MW Kriegers
›› Foundation type: Monopile ›› Foundation type: Monopile ›› Water depth: 30 m ›› Foundations no.: 36
water. expansion with new outer breakwater- both sides. The harbour has an almost COWI carry out the independent verifica- Pearl River Delta. The link comprises Flak offshore wind farms. Futhermore,
sand quay wall. The eastern breakwater is ellipsoidal shape in order to protect the tion of the detailed design. The project two approach bridges, two bridges, the Rentel NV is developing an offshore wind MERKUR Offshore Wind builds Merkur ›› Foundation no.: 6 ›› Foundation type: Monopile/Jacket
SERVICES
COWI develops cthe oncept and detailed
1 km long, the main western breakwater basin from waves from W and NW. The comprises 17 perimeter caissons, a world’s widest immersed tunnel and two farm in Belgian territorial waters with in the German part of the North Sea. The ›› Foundation type: Gravity based
An offshore wind farm in East Asia on the design of Horns Rev C 400 MW trans-
›› Numerical modelling for establishing is 400 m long, both exposed to severe beaches are constructed as a basin leisure boat marina and land reclamation artificial islands. The islands are designed sand dunes of 5 m in height. Rentel has approval process for the development Detailed design of foundations. In western coast of Taiwan, consisting of former platform.
design waves waves from the North Sea, with significant dredged along the coast. The beaches for the construction of underground park- to minimize the blocking effect in the appointed Dredging International NV as complies with the requirements of the 2003-04 we carried out a concept study, 36 turbines in total, is planned to be
›› Detailed design with Accropode® II as wave heights in the order of 7-8 m. are stabilised with beach islands with a ing spaces as well as roads, utilities and environmentally sensitive river delta and EPCI contractor, and COWI (in joint ven- German Federal Maritime and Hydro- SERVICES
including the innovative conical shell installed in 2018.
primary units. very special layout. high-rise housing. the loads from typhoon waves and associ- ture with Technum-Tractebel) is Dredging graphic Agency (BSH). The construction ›› Design of foundations
COWI carried out the tender design of structure, eventually adopted by the
›› Detailed geotechnical design ated water levels. Both islands will be International’s design consultant for the is contracted to GeoSea for which COWI, SERVICES ›› Basic and detailed design of 2x400 MW
breakwaters and revetments based on SERVICES SERVICES
project owner. In 2006-2008 we carried
›› Technical specs for physical model tests reclaimed from sand dredged in the river detailed design of the monopole founda- with IPU as sub-consultant, carries out ›› Front end engineering design and and 200 MW platforms including
the port expansion layout provided by the out the detailed design.
and visit to lab ›› Marina layout confirmation ›› Independent verification of the detailed and protected by revetments with armour tions and transition pieces for 42 Siemens the detailed design of the foundations, detailed design of foundation for eight mechanical and electrical design.
port, and after the award of the design-
›› Detailed structural design of wave wall ›› Review of existing data and design design of the caissons and their of rocks and concrete blocks. The services Gamesa SWT-7.0-154 turbines. viz. design of primary and secondary steel SERVICES positions
build contract to Aarsleff, the detailed
›› Technical specifications for breakwater ›› Basis of design foundations as well as the marina and include independent design checks of the and transition pieces, bolted connection ›› Structural design of foundations ›› Front end engineering design of the
design. SERVICES
›› Interface with concrete armour licensor ›› Geotechnical interpretative report associated structures two islands. between monopole and transition piece, ›› Geotechnical design entire wind farm.
›› Workshop on construction methodology SERVICES ›› Detailed design of marina outer ›› Independent modelling of the wave ›› Design of foundations geotechnical design, hydrodynamic load ›› Numerical and physical hydraulic
›› Bill of quantities and issue of good-for- breakwater and beaches agitation inside the marina and SERVICES ›› Geotechnical design modelling of installation stages,
›› Tender design of breakwaters and calculation, scour protection, corrosion
construction drawings. revetments ›› Review of quay wall settlement analysis numerical calculation models of the ›› Dredging ›› Scour and corrosion protection protection, low voltage design, and ship including dynamic loads and scour
›› Detailed design. ›› Technical specifications. caisson structures in order to verify the ›› Reclamation and ground improvement ›› Designer's risk assessment collision friendliness analysis. ›› Appurtenances design, including boat
designer’s numerical modelling ›› Initial perimeter of large steel cylinders ›› Risk management. landing and J-tubes
›› Assistance to marine environmental ›› Protecting perimeter structures SERVICES ›› Project follow-up in construction stage.
monitoring of construction activities. ›› Rescue harbours. ›› Detailed design and FEM analysis
›› Concrete and grout structures.
OWF App
MARINE AND FOUNDATION
ENGINEERING 51
SEAWATER INTAKE RE-GASIFI- QURAYYAH INDEPENDENT GASCO 4TH NGL TRAIN, RAS AL KHAIR, FOLSOM DAM SPILLWAY CHARLEROI LOCKS AND RAS LAFFAN NEW SHIP REPAIR BRADDOCK DAM LOCK 2,
CATION TERMINAL 2, MALAYSIA POWER PLANT, SAUDI ARABIA UNITED ARAB EMIRATES SAUDI ARABIA CA, USA DAM - LOCK #4, PA, USA YARD, QATAR MONONGAHELA RIVER, PA, USA
PEARL JUMEIRAH, BUSAN-GEOJE FIXED LINK, AL ZORAH DEVELOPMENT, HONG KONG THREE-RUNWAY LIVING BREAKWATERS, NEW DOHA PORT, GREAT BELT TUNNEL, CLIMATE LEMVIG FLOOD BARRIER, STORM DAMAGE ASSESSMENT,
UAE SOUTH KOREA UAE MAIN RECLAMATION, CHINA NY, USA QATAR CHANGE EVALUATION, DENMARK DENMARK DENMARK
DATA DATA DATA DATA SERVICES DATA DATA DATA DATA DATA
›› Project period: 2009-2014 ›› Project period: 2003-2011 ›› Project period: 2008-2012 ›› Project period: 2017 ›› Verification of land based DCM design ›› Project period: 2017 ›› Project period: 2009-2019 ›› Project period: 2017 ›› Project period: 2010 ›› Project period: 2013-2014
›› Client: Meraas Development LLC ›› Client: Daewoo Engineering & ›› Client: SOLIDERE ›› Client: Jan De Nul / Chun Wo JV ›› Settlement estimate for both natural and ›› Client: SCAPE/Landscape Architecture ›› Client: The Government of Qatar ›› Client: Sund & Bælt ›› Client: Municipality of Lemvig ›› Client: Danish municipalities
Construction Co. Ltd. improved ground conditions PLLC
An offshore development area, constructed Technical support and construction Hong Kong Airport is currently operating The port will be built in phases with the 18 km long fixed road and rail link across Floods have through many years been The storm Bodil in December 2013
›› Stone columns: Verification and
from Dubai sourced reclaimed sand and The Busan-Geoje Fixed Link connects the supervision for dredging and reclamation, at near full capacity. In order to secure the Staten Island and Raritan Bay were hard first phase having a capacity of two million the Great Belt comprising a low bridge, a threat to Lemvig, a low-lying town in coincided with very high water levels in
development of alternative optimised
locally sourced rock. The sand is retained island of Geoje with the large city Busan rock work, ground improvement, settle- airport for future expansion it has been hit by Super Storm Sandy in 2012 and TEU (twenty-foot equivalent unit) per year a suspension bridge and a tunnel, COWI Northern Jutland near the North Sea. In Danish waters and caused much material
ment monitoring etc. A 12 sq km parcel design for land based stone columns
along the perimeter of the development in the southern part of South Korea, decided to build a third runway and asso- much of the shore of Staten Island is and by 2030, when fully operational, the was contracted by the owner Sund & 2010, the Municipality initiated a project damage. It gave impetus to many climate
of land was developed along the coast ›› PVD & surcharging: Verification and
with rockwork slopes that are designed to improving access from the city to the ciated airside facilities. The current airport being eroded as a result of creation of port will be able to handle six million TEU Bælt to perform a climate assessment to counter the threat of climate change adaptation acitvies.
of Ajman by Al Zorah Development. One development of alternative design
provide shoreline stability and a seaward industrial and recreational areas on Geoje is placed on an artificial island off Lantau shipping channels, heavy fishing of the of container capacity per year. A total of of the tunnel ramps. The study included and created new qualities and develop-
of the features of the development is a for combined PVD and surcharging SERVICES
defence of the upland areas. Island. The link comprises three major Island. The airport expansion covers shellfish resources and exposure to wave five import/export terminals will be built an assessment of the effects of climate ment opportunities for the city. The
mangrove area. The mixed-use develop- design, providing reduced surcharge action and coastal erosion. This project ›› Inspection
elements; one of the world's deepest and 6.5 million m², and will require reclama- on the 20 sq km area which will serve as change based on newer statistical data solution was an eastethically pleasing
SERVICES ment will stretch along 3 km of coastline requirements is one of ten projects selected by the ›› Surveys
longest immersed tunnels and two long- tion of an additional 75 million m³ of fill. the port of entry for cargo, containers, as well as the potential impact of climate high-water barrier in the harbour.
›› Assessment of subsurface conditions and include commercial, residential, ›› Vibro-compaction of reclamation fill: Department of Housing and Urban Develop- ›› Design and permitting of coastal
span cable-stayed bridges. The project site is characterised by very livestock, vehicles, bulk grain and other change in relation to the original design
›› Concept, preliminary and detailed recreational, educational and healthcare Review of compaction requirements. ment (HUD) across the Sandy-affected SERVICES structures following damage by the
difficult ground conditions with up to 15 m goods. Additionally, the port will include a criteria.
design of marine, geotechnical and SERVICES facilities as well as a golf course, marinas Preparation of alternative solution using region to be pursued in the final stage ›› Project management consultant for the storm Bodil.
of soft clay and dumped mud pits where cruise terminal, a base for offshore industry
hydraulic services ›› Preliminary design, detailed design and and hotels. resonance vibratory plate compaction of the Rebuild By Design competition to SERVICES high water barrier and renewal of urban
contaminated material from other projects supply vessels and coastguard vessels.
›› Specification of surcharging and technical support during construction ›› Geotechnical interpretation: Preparation create innovative solutions for resiliency. ›› Risk analysis space, including relocation of utlities
SERVICES has been placed and capped. The excavation, including an 11 km long
settlement monitoring of rock structures ›› Sand compaction piles (SCP) for sub-sea of geological and geotechnical model COWI was selected to provide coastal ›› Analysis of the robustness of the and new street furniture.
›› Design of dredging and reclamation In order to accommodate the ground navigation channel dredged into the sea,
›› Hydrodynamic numerical modelling. embankment for reclamation area engineering and marine biology expertise. surface water systems
›› Marina design and design of marine conditions, while complying with strict required 95 million cubic metres of materi-
›› Deep cement mixing (DCM) for tunnel ›› Sloping and vertical seawalls: The proposed strategy, living, growing ›› Update of the operational risk analysis
structures environmental regulations, extensive als to be removed in the first phase.
trench verification of tender design breakwaters, will combine offshore break- ›› cost estimate.
›› Beach stability ground improvement is utilised. The
›› Advanced numerical modelling for ›› Preliminary Environmental Monitoring waters with creation/restoration of finfish SERVICES
›› Numerical modelling of waves, currents
employer's ground improvement methods Plan (EMP) and shellfish habitats to enhance ecologi-
verification and water levels ›› Environmental impact assessment
include: Deep Cement Mixing (DCM), ›› 4D BIM model based on Contractor's cal benefits of the structure.
›› Physical hydraulic model testingTrial ›› Environmental impact assessment studies (EIA)
Stone Columns, Prefabricated. programme
testing for SCP and DCM. ›› Power station impact study SERVICES ›› Advice and monitoring during
›› Cost estimate ›› Review of Contractor's Method construction.
Statements for reclamation and ground ›› Feasibility study
›› Construction supervision.
improvement. ›› Evaluation
›› Cost estimate.
MARINE AND FOUNDATION
ENGINEERING 55