Вы находитесь на странице: 1из 214

MADHYA PRADESH POWER TRANSMISSION

COMPANY LIMITED

MADHYA PRADESH
POWER TRANSMISSION
MANUAL ON
COMPANY LIMTED
PRE-COMMISSIONING
AND PERIODICAL
TESTING OF EHV
EQUIPMENT

MANUAL ON
PRECOMMISSIONING
NOV’17
AND PERIODICAL
TESTING OF EHV
EQUIPEMNTS

Nov-17

1
A committee consisting of the
following officers was constituted
Vide letter No.
04-04/3158 dated 25/9/2017

 Er. P.K. GARGAVA (CO-ORDINATOR)


Superintending Engineer (T&C), SAGAR-9425804959

 Er. PRADEEP RAGHAV


Executive Engineer 400 KV Testing Division, Bhopal
-9425804998

 Er. PRANAY JOSHI


Assistant Engineer 400 KV Testing Division, Nagda
-9425804951

 Er. ASHISH SHARMA


Assistant Engineer 400 KV Testing Division, Bhopal
-9425806932

2
CONTENTS

CHAPTER SUBJECT AUTHOR PAGE NO,


1. POWER TRANSFORMER Er. P.K. Gargava 4-77
Er. Pranay Joshi
2. D.C. SYSTEM OF SUB- Er. P.K. gargava 78-81
STATION Er. Nutan Sharma
3. D.C. LEAKAGE PROBLEM OF Er. Nutan Sharma 82-98
SS
4. DISTANCE RELAY Er. Pradeep 99-128
PROTECTION Raghav
Er. Ashish Sharma
5. DIFFERENTIAL RELAY Er. Ashish Sharma 129-152
Er. Chndrabhan
Kushvah
6. LBB PROTECTION Er. P.K. Gargava 153
7. BUS-BAR PROTECTION Er. P.K. Gargava 154-157
8. POWER LINE CARRIER AIDED Er. Rajesh 158-162
TRIPPING Shandilya
Er. Pradeep
Raghav
9. OVER CURRENT AND EARTH Er. Ashish Sharma 163-177
FAULT RELAY
10. EHV CIRCUIT BREAKER Er. P.K. Gargava 178-186

11. POTENTIAL Er. P.K. Gargava 187-193


TRANSFORMER/CVT Er. Pranay Joshi
12. CURRENT TRANSFORMER Er. P.K. Gargava 194-203
Er. Pranay Joshi
13. SURGE ARRESTOR Er. P.K. Gargava 204-207
14. ANNEXURE 208-214

3
CHPATER-1
POWER TRANSFOREMR
TESTING
Er. P.K. Gargava Er. Pranay Joshi

INTRODUCTION
The Power Transformers are very important and costliest equipments in any Power
Grid network including the Grid Network of M.P. Power Transmission Co Ltd(MPPTCL).
They are basically installed in Grid Sub stations. The Grid network of MPPTCL consists of
400 KV and 220 KV and 132 KV Substations having transmission lines and the Power
Transformers. The Power Transformers in Grid S/S are used for transforming voltages from
one level to another without changing the supply frequency (Definition of the Transformer).
In MPPTCL the Voltages are transformed from 400 KV to 220 KV, 220 KV to 132 KV, 220
KV TO 33 KV and from 132 KV to 33 KV.

Classification of Transformer
In MPPTCL Power Transformer are classified by voltage class as:
400 KV Class
 400/220/33 KV 315 MVA Auto Transformer having three windings HV(440kv),
IV(220kv) & LV(33kv)

220 KV Class
 220/132/33 KV 125 & 160 MVA Auto Transformer having three windings HV (220kv),
IV (132kv) & LV (33kv).

 200/33/33 KV 100 MVA Three winding Transformer HV (220kv), LV1 (33kv) & LV2
(33kv).

 200/33 KV 100 MVA Two winding Transformer HV(220kv), & LV (33kv)

132 KV Class
 132/33 KV 20, 40, 50 & 63 MVA Two winding Transformer having HV (132kv) & LV
(33kv).

These auto transformers have their main winding star connected with the neutral solidly
earthed. They also have a 33/11 KV delta connected tertiary winding with MVA Capacity
1/3rd of that Transformer rating to connect phase compensating devices like shunt
capacitors, static var compensators etc. When not needed, the tertiary is kept idle.
TESTING OF TRANSFORMER
The following Tests are specified in IS:2026 (Part I), specification for power
transformers, Part-I, General:

4
TYPE TESTS:
 Measurement of winding resistance.
 Measurement of Voltage ratio and check of Voltage Vector relationship.
 Measurement of impedance voltage/short circuit impedance (principal tapping) and
load loss.
 Measurement of no load loss and current.
 Measurement of insulation resistance.
 Dielectric tests
 Temperature rise test
 Tests on ON-LOAD tap-changers, where appropriate

ROUTINE TESTS
 Measurement of Winding resistance.
 Measurement of Voltage ratio and check of voltage vector relationship.
 Measurement of impedance voltage/short circuit impedance (Principal tapping and
load loss)
 Measurement of no-load loss and current.
 Measurement of insulation resistance.
 Dielectric tests
 Tests on ON-LOAD tap-changers, where appropriate.

SPECIAL TESTS:
 Dielectric tests
 Measurement of Zero-sequence impedance of three phase transformers.
 Short circuit test.
 Measurement of acoustic noise level.
 Measurement of harmonics of the no-load current.
 Measurement of the power taken by the fans and oil pumps.

TESTS CARRIED OUT AT FACTORY:

Type/Routine/Special tests if any as specified by the MPPTCL in the P.O.


specification will be done at the factory by the transformer manufacturer in the presence of
the nominated Engineer of the MPPTCL. The test results will be authenticated by the
Manufacturer’s Engineer and the MPPTCL Engineer who witnessed the test and sent to the
MPPTCL for acceptance.
TESTS CARRIED OUT AT SITE:
A transformer may be tested at site under the following circumstances.
 A new or second hand/ repaired transformer to be commissioned :- Pre-
commissioning tests to be done.
 Tests to be conducted to determine the healthiness or other-wise of the
transformer that has been taken out of service on the actuation of
Buchholz/Differential relay or on observing some abnormal occurrence that has
placed a question on the healthiness of the transformer :- Routine test to be
done

5
Pre-commissioning testing of Transformer:
After arrival of Transformer at site , thorough inspection shall be done immediately on arrival
for any damages to X-mers in transport.
a. Transformer received filled with oil, oil level in main tank is to be verified by
comparing the oil level shown by manufacturer before dispatch in their
document. A sample of oil shall be taken from bottom of the tank and send
the oil sample for oil parameter testing, test result found, should be
comparable as per IS 1866 and factory test result.
b. If X-mer received is filled with nitrogen, the nitrogen gas pressure reading
should be taken and ensure that gas pressure is positive. Dew point of N2
gas has also to be recorded with ambient temp and check wether the test
results are comparable or not .
c. CORE INSULATION TEST : After above Take IR value of Core to Tank ,
Core to Frame and Frame to Tank (if external provision provided) with
insulation tester at 2.5 KV or at Voltage level over which test is performed at
factory
d. Core-Tank-Frame are shorted to each other as shown in Figure (1) below, for
IR Value measurement remove the shorting and take the reading and note
down the result in Table(1) as shown below. The tank shall be grounded
during the test and compare the result with factory test results. In no case,
these IR value found, should be zero between Core-Tank-Frame.

Figure (1): Core-Tank-Frame Arrangement for Testing

Terminal Test voltage IR value measurement


for 1 min
Core-Tank
Core-Frame
Frame-Tanke

6
Table (1): Core-Tank-Frame IR value measurement format

If any abnormality noticed from above point a to c the X-mer should not be un-
loaded from the trailer and proper intimations should be given to the manufacturers and
higher authorities for necessary action.
After unloading of transformer on plinth and complete erection of main Tank, bushing,
conservator , radiators and other accessories and complete oil filling of transformer, Pre-
commissioning test are to be perform over transformer. The Procedure of various Pre-
Commissioning test are elaborated below:

1. Ratio Test
Ratio measurements must be made on all taps to confirm the proper alignment and
operation of the tap changers. The test should preferably be performed by automatic
Transformer turns ratio (TTR) meter.
A. Using automatic Transformer turns ratio (TTR) meter.
Here Testing is describing using DV Power Three Phase transformer turn ratio tester
TRT3X as shown in Figure (2). In addition to determining the voltage transformation ratio
which is the primary objective of this test, the polarity between the windings and phase
relationship between phases can also be easily established by the ratio meter in a single
operation. Before using the ratio meter, the instruction manual for operating the ratio meter
must be carefully studied and all precautions noted therein must be followed

Figure(2) : Front Panel of DV Power Three Phase transformer turn ratio tester TRT3X

a. Colors and marking of test cable of DV Power Three Phase transformer turn ratio
tester TRT3X shown in Table-(2)

7
b.
IEC Test ANSI Australian Transformer Australian Malaysian
Test Lead
Lead Test Lead Test Lead Terminal Test Lead Test Lead
Color IEC
Marking Marking Marking Voltage Colors Colors

1N H0 N Neutral Blue Black Black

1U H1 A High Red Red Red

1V H2 B High Black White Yellow

1W H3 C High Yellow Blue Blue

2N X0 n Neutral Blue Black Black

2U X1 a Low Red Red Red

2V X2 b Low Black White Yellow

2W X3 c Low Yellow Blue Blue

Table-(2) : Test lead marking and color

c. Figure (3) Shows the connection of TRT3X turn ratio tester to 3-Ph Auto-
transformer, HV Test cable lead H1(Red), H2(Yellow),H3(Blue) and H0(Black)
Connected to Transformer HV-1U,1V,1W and N respectively and LV Test cable lead
X1(Red), X2(Yellow),X3(Blue) and X0(Black) Connected to Transformer LV-
2U,2V,2W and N.

Figure(3): Example of connecting TRT3x to a three-phase autotransformer

8
d. If the three-phase transformer autotransformer has a tertiary winding, it should be
tested the same way as the secondary. The transformer is energized using the high
voltage windings. Test leads 2U, 2V, 2W and 2N (X1, X2, X3 and X0) are in this case
connected to the tertiary winding of the transformer.
e. Figure (4) Shows the connection of TRT3X turn ratio tester to 3-Ph conventional
two winding transformer. HV Test cable lead H1(Red), H2(Black),H3(Yellow) and
H0(Blue) Connected to Transformer HV-1U,1V,1W and 1N respectively and LV Test
cable lead X1(Red), X2(Black),X3(Yellow) and X0(Blue) Connected to Transformer
LV-2U,2V,2W and 2N

Figure(4): Example of connecting TRT3x to a three-phase conventional Two winding


transformer

f. Figure (5) Shows the connection of TRT3X turn ratio tester to 1-Ph Auto-
transformer,. HV Test cable lead H1(Red) and H0(Blue) Connected to Transformer
HV-1U and 1N respectively and LV Test cable lead X1(Red) and X0(Blue)
Connected to Transformer LV-2U and 2N.

9
Figure(5): Example of connecting TRT3x to a single-phase autotransformer

g. Figure (6) Shows the connection of TRT3X turn ratio tester to 1-Ph conventional
two winding transformer,. HV Test cable lead H1(Red) and H0(Blue) Connected to
Transformer HV-1U and 1N respectively and LV Test cable lead X1(Red) and
X0(Blue) Connected to Transformer LV-2U and 2N.

Figure(6) Example of connecting TRT3x to a single-phase conventional Two winding


transformer

h. Single Phase Test Mode of TRT3X :

10
 If the test object is a three-phase transformer or three-phase
autotransformer, the single-phase test is performed by applying a single-
phase test voltage to each of the three H terminals in turns. The voltages
across each of the corresponding X terminals are then measured. The ratio
of these voltages is calculated and presented on the display. It is repeated
for all three phases automatically, based on the selected/detected
transformer vector group
 If the test object is a single-phase transformer or single-phase
autotransformer, the TRT3x will apply one single-phase test voltage
between selected H terminals, and will measure voltage across selected X
terminals
i. Three Phase Test mode of TRT3X :
 The TRT3x will apply true three-phase test voltage between the terminals
1U-1V-1W (H1-H2-H3, A-B-C), and will measure a three-phase voltage
between the terminals 2U-2V-2W (X1-X2-X3, a-b-c). Three turns ratios are
calculated, as per the Table 3
Applied voltage Measured voltage
Phase
between terminals between terminals

1U-1V 2U-2V
A H1-H2 X1-X2
A-B a-b

1V-1W 2V-2W
B H2-H3 X2-X3
B-C b-c

1W-1U 2W-2U
C H3-H1 X3-X1
C-A c-a

Table-3 : Three Phase Turn Ratio


j. Viewing Result : When the test is completed, the TRT3x automatically displays the
test results as shown in Figure(7) To scroll between all the results, ▲ and ▼ should
be used.

11
Figure(7) : Results after test

k. Results of the transformation turns or voltage ratio are absolute, and may be
compared with the specified values measured during factory testing. The turns ratio
tolerance should be within 0.5 % of the nameplate specifications

B. When automatic Transformer turns ratio (TTR) meter not available.


When a ratio meter is not available, the ratio may be determined by using testing
board as shown in Figure(8) .connect all three phases of HV,IV,LV and Neutral Bushing
top through insulated wire at respected terminal marked on testing board and testing is done
in steps as elaborated below:
a. 3-Phase Supply given to the HV winding of the transformer terminal 1U-1V-1W and
measuring the voltage applied to the H.V. side i.e. 1U-1V,1V-1W & 1W-1U and
measure the voltage induced in the LV Windings by taking measurement at the LV
terminals i.e 2U-2V,2V-2W & 2W-2U and then calculate the ratio and note down the
result as shown in Table(4) .

MEASURED RATIO & % DEVIATION


TAP STD. 1V-
NO RATIO 1U-1V/2U- % % %
1W/2V- 1W-1U/2W-2U
2V DEV DEV DEV
2W

Table-(4) : Format for Three Phase Turn Ratio

12
b. % Deviation is calculated from formula = (Cal. Ratio – Std. Ratio)/Std. ratio * 100
Where Cal. Ratio is Calculated ratio and Std. Ratio is Standard Ratio of Transformer.

c. % Deviation should be less then <+- 0.5 %

d. This is not an accurate method, as the instruments used to measure the voltage may
not have the required accuracy.

e. The ratio is to be determined at all the taps. The test can be started from one
extreme tap and measurement taken for each tap up to the other extreme by
operating the OLTC without switching off supply voltage while operating the OLTC.
Increase or decrease in the LV side voltage for each tap should more or less
correspond to the percentage mentioned for that tap in the name-plate.

1 Magnetic Balance Test.


This test is a low voltage test conducted at factory and site by applying single phase
voltage between phase and neutral of a winding and measuring voltage induced in other two
phases of the same winding and all the three phases of other windings at Normal tap. This
test is done to find out whether the magnetic paths of the transformer core are balanced.
l. For 3-Ph Auto-transformer having tertiary winding, Figure(8) shown the Testing
Board for magnetic balance test of Transformer.

13
Figure(8) Arrangement for measurement of magnetic Balance

Connect all three phases of HV,IV,LV and Neutral Bushing top through insulated
wire at respected terminal marked on above testing board as 1U,1V,1W ,2U,2V,2W &
3U,3V,3W N respectively and testing is done in three steps as elaborated below :
 Apply 1-Ph Voltage 230 V across one phase of Highest Voltage (HV) winding
terminal and neutral i.e 1U-N, then measure Induced voltage in other two HV
terminals across neutral i.e 1V-N & 1W-N and Intermediate Voltage (IV)
Winding Terminal and neutral 2U-N,2V-N & 2W-N and Lowest Voltage (LV)
winding terminal 3U-3W,3U-3V & 3V-3W as shown in Figure(9)

14
Figure(9) Measurement of magnetic Balance when 1-ph supply given on HV side and
measure on HV,IV & LV side

Repeat the test for Remaining Two phase of HV winding i.e for 1V-N & 1W-N
and note down the result as shown in Table-5.
230V Measure Induce Voltage in Volts at Terminal
Supply
1U- 1V- 3U- 3V-
at 1W-N 2U-N 2V-N 2W-N 3U-3V
N N 3W 3W
terminal
1U-N 230
1V-N 230
1W-N 230
Table-5 :1-ph 230V supply given to HV terminal and voltage measure at HV,IV &
LV Terminal
 Apply 1-Ph Voltage 230 V across one phase of Intermediate Voltage (IV)
Winding Terminal and neutral i.e 2U-N, then measure Induced voltage in
other two IV terminals across neutral i.e 2V-N & 2W-N and Lowest Voltage
(LV) winding terminal 3U-3W,3U-3V & 3V-3W as shown in Figure(10).

15
Figure(10) : Measurement of magnetic Balance when 1-ph supply given to IV
terminal and voltage measure a ,IV & LV

Repeat the test for Remaining Two phase of IV winding i.e 2V-N & 2W-N and
note down the result as shown in Table-6.

230V Supply Measure Induce Voltage in Volts at Terminal


at terminal 2U-N 2V-N 2W-N 3U-3W 3U-3V 3V-3W
2U-N 230
2V-N 230
2W-N 230
Table-6 :1-ph 230V supply given to IV terminal and voltage measure a ,IV & LV
Terminal
Note :- When voltage is applied on IV side don’t measure the voltage on
HV side as due to step up phenomena high voltage is induce on HV
side which will damage the Voltage meter.

 Apply 1-Ph Voltage 230 V across one phase of Lowest Voltage (LV) winding
terminal i.e 3U-3W, then measure Induced voltage in other two LV terminals
i.e. 3U-3V & 3V-3W as shown in Figure(11)

16
Figure(11) : Measurement of magnetic Balance when 1-ph 230V supply given to
LV terminal and voltage measure LV Terminal

Repeat the test for Remaining Two phase of LV winding i.e 3U-3V & 3V-3W
and note down the result as shown in Table-7.

Measure Induce Voltage in Volts at Terminal


230V Supply at terminal
3U-3W 3U-3V 3V-3W
3U-3W 230
3U-3V 230
3V-3W 230
Table-7 :1-ph 230V supply given to LV terminal and voltage measure LV
Terminal

Note :- When voltage is applied on IV side don’t measure the voltage on


HV & LV side as due to step up phenomena high voltage is induce on
HV side which will damage the Voltage meter.

 Compare the measured result with factory test results and the identical results
confirm no damage due to transportation.

m. For 3-Ph Conventional transformer having Two Winding or Three Winding,


Figure(8) shown the Testing Board for testing magnetic balance test of Transformer
connect all three phases of HV,LV and Neutral Bushing top through insulated wire at
respected terminal marked on testing board as 1U,1V,1W ,2U,2V,2W & 1N,2N
respectively and testing is done in three steps as elaborated below:
 Apply 1-Ph Voltage 230 V across one phase of Highest Voltage (HV) winding
terminal and neutral i.e 1U-N, then measure Induced voltage in other two HV

17
terminals across neutral i.e 1V-N & 1W-N and Low Voltage (LV) Winding
Terminal and neutral 2U-N,2V-N & 2W-N as shown in Figure(12).

Figure(12) : Measurement of Magnetic Balance when 1-ph 230V supply given to


HV terminal and voltage measure at HV & LV

Repeat the test for Remaining Two phase of HV winding i.e. 1V-N & 1W-N
and note down the result as shown in Table-8.

230V Supply Measure Induce Voltage at Terminal


at terminal 1U-N 1V-N 1W-N 2U-N 2V-N 2W-N
1U-N 230
1V-N 230
1W-N 230
Table-8 :1-ph 230V supply given to HV terminal and voltage measure at HV & LV
Terminal
 Apply 1-Ph Voltage 230 V across one phase of Low Voltage (LV) Winding
Terminal and neutral i.e 2U-N, then measure Induced voltage in other two LV
terminals across neutral i.e 2V-N & 2W-N as shown in Figure(13)

18
Figure(13) : Measurement of Magnetic Balance when 1-ph 230V supply
given to LV terminal and voltage measure at LV

Repeat the test for Remaining Two phase of LV winding i.e for 2V-N & 2W-N
and note down the result as shown in Table-9.

Measure Induce Voltage at Terminal


230V Supply at terminal
2U-N 2V-N 2W-N
2U-N 230
2V-N 230
2W-N 230
Table-9 :1-ph 230V supply given to LV terminal and voltage measure on LV
Terminal

Note :- When voltage is applied on LV side don’t measure the voltage on


HV side as due to step up phenomena high voltage is induce on HV
side which will damage the Voltage meter.

 Compare the measured result with factory test results and the identical results
confirm no damage due to transportation.

n. Also the applied voltage may be expressed as 100% voltage and the induced voltage
may be expressed as percentage of the applied voltage. This will help in comparison
of the two results when the applied voltages are different. The voltage induced in
the centre phase shall be 50 to 90% of the applied voltage. However, when the
centre phase is excited then the voltage induced in the outer phases shall be
30 to 70% of the applied voltage

19
2 Magnetizing current Test :
This test is performed to locate defects in the magnetic core structure, shifting of
windings, failure in turn to turn insulation or problem in tap changers. These conditions
change the affective reluctance of the magnetic circuit, thus affecting the current required to
establish flux in the core. Abnormal value of magnetizing current can indicate inter turn short
in the windings or problem in the core like core shifting etc., So magnetizing current is a very
important parameter to be taken before commissioning a new Transformer
Note :- This test should be done before DC measurements of winding resistance
to reduce the effect of residual magnetism. Magnetizing current readings may be
effected by residual magnetism in the core. Therefore, transformer under test may be
demagnetized before commencement of magnetizing current test.

A. Using Omicron CPC-80 Capacitance and Tan Delta measurement kit.

For 3-Ph Auto-transformer having tertiary winding: Here Testing is describing


using Omicron CPC-80 Capacitance and Tan Delta measurement kit shown in
Figure(14) for measurement of magnetizing current.
Before using the Omicron CPC-80, the instruction manual for operating the Kit must
be carefully studied and all precautions noted therein must be followed

20
Figure(14) : Omicron CPC-80 Capacitance and Tan Delta measurement kit used for
magnetizing current measurement

Setup of Omicron CPC-80 kit for measurement of magnetizing current:


i. Power Supply for Kit should be phase controlled with ground
ii. Ground terminal of kit and supply board should be same.
iii. Properly connect both kits via serial interphase connector and Ext. Booster
cable as per the slots shown in Figure(14) .
iv. Connect the HV and LV leads as per slot an color code as shown in
Figure(14).
v. Power on the Kit and create a template of power transformer as describe in
instruction manual.
vi. Select the Supply voltage between 0 to 10 KV at which magnetizing current
will be measure depending upon the current measuring limit of Kit.

vii. Keep Step of variac as 5 and disable or kept OFF other ICON as shown in
Figure(16)

21
Figure(15) : Omicron CPC-80 Front panel

Figure(16) : Omicron CPC-80 Magenetizing current measurement tempalate

viii. Now Push Start Button two times for starting the Test.

22
ix. When Testing Done Result Shown on Screen as shown in Figure(16)
 For HV Side- Connect HV Lead of Testing Kit on R phase of Highest Voltage
(HV) winding terminal i.e 1U and LV Lead of Testing Kit on neutral i.e N as
shown in Figure(17), then Start the Kit as explain above and measure
magnetizing current of HV R-phase i.e for 1U-N.

Figure(17) : Measurement of HV Magnetizing current

Repeat the test for Remaining Two phase of HV winding i.e. 1V-N & 1W-N
and note down the result as shown in Table-10.

Supply Measured Magnetizing Current


Tap No.
Voltage 1U-N 1V-N 1W-N
230 V
5 KV
10 KV
Table-(10) :Measurement of Magnetizing Current of HV Terminal.

 For IV Side- Connect HV Lead of Testing Kit on R phase of Intermediate


Voltage (IV) winding terminal i.e 2U and LV Lead of Testing Kit on neutral i.e
N as shown in Figure(18), then Start the Kit as explain above and measure
magnetizing current of IV R-phase i.e for 2U-N.

23
Figure(18) : Measurement of IV Magnetizing current

Repeat the test for Remaining Two phase of IV winding i.e. 2V-N & 2W-N and
note down the result as shown in Table-11.

Supply Measured Magnetizing Current


Tap No.
Voltage 2U-N 2V-N 2W-N
230 V
5 KV
10 KV
Table-11 : Measurement of Magnetizing Current of IV Terminal

Note :- For IV Side measure the Magnetizing current at all taps in order
check correctness of tap Changer.

 For LV Side- Connect HV Lead of Testing Kit on R phase of Low Voltage


(LV) winding terminal i.e 3U and LV Lead of Testing Kit on B phase of Low
Voltage (LV) winding terminal i.e. 3W as shown in Figure(19), then Start the
Kit as explain above and measure magnetizing current of LV R-phase i.e for
3U.

24
Figure(19) : Measurement of LV Magnetizing current

Repeat the test for Remaining Two phase of LV winding i.e. 3U-3V & 3V-3W
and note down the result as shown in Table-12.

Supply Measured Magnetizing Current


Tap No.
Voltage 3U-3W 3U-3V 3V-3W
230 V
5 KV
10 KV
Table-12 :Measurement of Magnetizing Current of LV Terminal.

 Compare the measured result with factory test results and the identical results
confirm no damage due to transportation.

o. For 3-Ph Conventional transformer having Two Winding or Three Winding,

 For HV Side- Connect HV Lead of Testing Kit on R phase of Highest Voltage


(HV) winding terminal i.e 1U and LV Lead of Testing Kit on neutral i.e 1N as

25
shown in Figure(20), then Start the Kit as explain above and measure
magnetizing current of HV R-phase i.e for 1U-N.

Figure(20) : Measurement of HV Magnetizing current

Repeat the test for Remaining Two phase of HV winding i.e. 1V-N & 1W-N
and note down the result as shown in Table-13
Supply Measured Magnetizing Current
Tap No.
Voltage 1U-N 1V-N 1W-N
230 V
5 KV
10 KV
Table-13 :Measurement of Magnetizing Current of HV Terminal.

 For LV Side- Connect HV Lead of Testing Kit on R phase of Low Voltage


(LV) winding terminal i.e 2U and LV Lead of Testing Kit on neutral i.e 2N as
shown in Figure(21), then Start the Kit as explain above and measure
magnetizing current of LV R-phase i.e for 2U-N.

26
Figure(21) : Measurement of LV Magnetizing current

Repeat the test for Remaining Two phase of LV winding i.e. 2V-N & 2W-N
and note down the result as shown in Table-14.
Supply Measured Magnetizing Current
Tap No.
Voltage 2U-N 2V-N 2W-N
230 V
5 KV
10 KV
Table-14 : Measurement of Magnetizing Current of LV Terminal

Note :- For LV Side measure the Magnetizing current at all taps in order
check correctness of tap Changer.

 Compare the measured result with factory test results and the identical results
confirm no damage due to transportation

p. The test values on the outside legs should be within 15 % of each other, and values
for the centre leg should not be more than either outside for a three- phase
transformers. Results compared to factory tests made under the same conditions
should not vary more than 25%. If the measured exciting current value is 50
times higher than the value measured during Factory test, then there is
likelihood of a fault in the winding which needs further analysis.

B. When Omicron CPC-80 kit is not available.

27
a. For 3-Ph Auto-transformer having tertiary winding, Figure(8) shown the testing
board for testing magnetizing current of Transformer connect all three phases of
HV,IV,LV and Neutral Bushing top through insulated wire at respected terminal
marked on testing board and testing is done in three steps as elaborated below :
 For HV Side- Apply 1-Ph Voltage 230 V across one phase of Highest Voltage
(HV) winding terminal and neutral i.e 1U-N, and measure the current with
Ammeter or Current Clamp meter in 1U phase with proper current range
selection as shown in Figure(21).

Figure(21) : Measurement of HV Magnetizing current


Repeat the test for Remaining Two phase of HV winding i.e for 1V-N & 1W-N
and note down the result as shown in Table-15.

Tap 230 V Supply Voltage Measured Magnetizing Current in


No. At Terminal (mA)
1U-N 1U
1V-N 1V
1W-N 1W
Table-15 : Measurement of Magnetizing Current of HV Terminal

 For IV Side-Apply 1-Ph Voltage 230 V across one phase of Intermediate


Voltage (IV) Winding Terminal and neutral i.e 2U-N, and measure the current
with Ammeter or Current Clamp meter in 2U phase with proper current range
selection as shown in Figure(22).

28
Figure(22) : Measurement of IV Magnetizing current
Repeat the test for Remaining Two phase of IV winding i.e for 2V-N & 2W-N
and note down the result as shown in Table-16.

Tap 230 V Supply Voltage Measured Magnetizing Current in


No. At Terminal (mA)
2U-N 2U
2V-N 2V
2W-N 2W
Table-16 : Measurement of Magnetizing Current of IV Terminal

Note :- For IV Side measure the Magnetizing current at all taps in order
check correctness of tap Changer.

 For LV Side-Apply 1-Ph Voltage 230 V across one phase of Lowest Voltage
(LV) winding terminal i.e 3U-3W and measure the current with Ammeter or
Current Clamp meter in 3U phase with proper current range selection as
shown in Figure(23).

29
Figure(23) : Measurement of LV Magnetizing current

Repeat the test for Remaining Two phase of LV winding and note down the
result as shown in Table-17.

Tap 230 V Supply Voltage Measured Magnetizing Current in


No. At Terminal (mA)
3U-3W 3U
3U-3V 3V
3V-3W 3W
Table-17 : Measurement of Magnetizing Current of L V Terminal

 Compare the measured result with factory test results and the identical results
confirm no damage due to transportation

b. For 3-Ph Conventional transformer having Two Winding or Three Winding,


Figure(8) shown the testing Board for testing magnetizing current of Transformer
connect all three phases of HV , LV and Neutral Bushing top through insulated wire
at respected terminal marked on testing board and testing is done in three steps as
elaborated below:
 For HV Side- Apply 1-Ph Voltage 230 V across one phase of Highest Voltage
(HV) winding terminal and neutral i.e 1U-N, and measure the current with
Ammeter or Current Clamp meter in 1U phase with proper current range
selection as shown in Figure(24)

30
Figure(24) : Measurement of HV Magnetizing current

Repeat the test for Remaining Two phase of HV winding i.e for 1V-N & 1W-N
and note down the result as shown in Table-18.

Tap 230 V Supply Voltage Measured Magnetizing Current in


No. At Terminal (mA)
1U-N 1U
1V-N 1V
1W-N 1W
Table-18 : Measurement of Magnetizing Current of HV Terminal

 For LV Side-Apply 1-Ph Voltage 230 V across one phase of Intermediate


Voltage (IV) Winding Terminal and neutral i.e 2U-N, and measure the current
with Ammeter or Current Clamp meter in 2U phase with proper current range
selection as shown in Figure(25).

31
Figure(25) : Measurement of LV Magnetizing current

Repeat the test for Remaining Two phase of LV winding i.e for 2V-N & 2W-N
and note down the result as shown in Table-19
Tap 230 V Supply Voltage Measured Magnetizing Current in
No. At Terminal (mA)
2U-N 2U
2V-N 2V
2W-N 2W
Table-19 : Measurement of Magnetizing Current of LV Terminal

Note :- For LV Side measure the Magnetizing current at all taps in order
check correctness of tap Changer..

 Compare the measured result with factory test results and the identical results
confirm no damage due to transportation

c. The test values on the outside legs should be within 15 % of each other, and values
for the centre leg should not be more than either outside for a three- phase
transformers. Results compared to factory tests made under the same conditions
should not vary more than 25%. If the measured exciting current value is 50
times higher than the value measured during Factory test, then there is
likelihood of a fault in the winding which needs further analysis

32
3 Vector group test
Vector group test is done to determine the phase relation ship of transformer. It very
important in order to paralleling or banking two or more transformers. Phase-relation tests
are made to determine angular displacement and relative phase sequence. Phase-relation
or vector group verification test is performed on a three phase transformer or on a bank of
three single-phase transformers.
.Vector group of transformer is also tested by automatic Transformer turns ratio (TTR)
meter as shown in Figure(2) and the procedure for testing vector group is same as turn ratio
testing as describe in Para 1.A.
a. When a ratio meter is not available, the vector group may be determined by using
testing Board as shown in Figure(8). connect all three phases of HV,IV,LV and
Neutral Bushing top through insulated wire at respected terminal marked on testing
board and testing is done in steps as elaborated below:
b. For 3-Ph Auto-transformer with tertiary winding having Vector group YNa0d11
testing is done in steps elaborated below:
1. Connected 1U and 3U terminal together in the arrangement as shown in
Figure(26) and 3-Ph supply given to HV terminal i.e on 1U-1V-1W.

Figure(26) : Connection Diagram for Vector group test of Auto X-mert


2. Now measure the voltages between the terminal as given in factory test
result for verification of Vetor Group YNa0d11
3. As per factory test result , Measure the Voltage between terminal as:
I. 1V-2V
II. 1V-2W
III. 1V-3V
IV. 1V-3W
V. 1W-2U
VI. 1W-2V
VII. 1W-3V
VIII. 1W-3W
IX. 1U-N
X. 1U-2U
XI. 2U-N

4. Now for vector group YNa0d11 , following are the condition to verify the
vector group,

33
If , I = II = V = VI,
IX = ( X + XI )
III = IV = VIII < VII

Then Vctor group is YNa0d11

c. For 3-Ph Two Winding transformer having Vector group YNyn0 testing is done
in steps elaborated below:
1. Connected 1U and 2U terminal together in the arrangement as shown in
Figure(27) : Measurement and 3-Ph supply given to HV terminal i.e on
1U-1V-1W.

Figure(27) : Connection Diagram for Vector group test of Two Winding X-


mert

2. Now measure the voltages between the terminal as given in factory test
result for verification of Vetor Group YNyn0
3. As per factory test result , Measure the Voltage between terminal as:
I. 1U-2W
II. 1U-2V
III. 1W-2W
IV. 1V-2V
V. 1U-2N
VI. 1N-2n
VII. 1U-1N
4. Now for vector group YNyn0 , following are the condition to verify the
vector group,
If , I = II ,
III = IV
V + VI = VII
Then Vector group is YNyn0

4 Short Circuit test.


This test is used to detect winding movement that usually occurs due to heavy fault
current or mechanical damage during transportation or installation since dispatch from the
factory.
a. Ensure the isolation of Transformer from High Voltage & Low voltage side with
physical inspection of open condition of the concerned isolators. In case tertiary is
also connected, ensure the isolation of the same prior to commencement of testing.

34
b. The measurement is performed in Three Phase. This test is performed for the
combination of two winding.
c. Before commencing the test, the short circuit current is to be calculated for the
available Supply mains voltage from the percentage impedance of the transformer.
For Example

I. For 315 MVA X-mer 400/220/33 KV Having %Z (HV-IV) = 11.28 % , %Z (HV-


LV) = 41.97 % & %Z (IV-LV) = 26.64 % at Normal tap and HV rated current –
455 A, IV rated Current – 827 and LV rated Current – 1837 A ( 105 MVA
base)

Now %Z (HV-IV) i.e 11.28 % of 400 KV = 45120 V will Deliver rated current of
455 A on Short Ckt of IV Side
Therefore 3-Ph Supply 440 V will deliver = (440 * 455) / 45120 = 4.43 A, Short
circuit current of HV side.
For IV Side Short circuit current = 4.43 * (400/220) = 8.06 A
Now %Z (HV-LV) i.e. 41.97 % of 400 KV = 167880 V will Deliver rated current
of 455 A on Short Ckt of LV Side
Therefore 3-Ph Supply 440 V will deliver = (440 * 455) / 167880 = 1.19 A, Short
circuit current of HV side.
For LV Side Short circuit current = (1.19 * (400/33)) / 1.732 = 8.32 A

II. For 40 MVA X-mer 132/33 KV Having %Z (HV-LV) = 9.68 % , at Normal tap
and HV rated current – 175 A and LV rated Current – 700 A

Now %Z (HV-LV) 9.68 % of 132 KV = 12777.6 V will Deliver rated current of


175 A on Short Ckt of LV Side
Therefore 3-Ph Supply 440 V will deliver = (440 * 175) / 12777.6 = 6.02 A,
Short circuit current of HV side.
For LV Side Short circuit current = 6.02 * (132/33) = 24.08 A

d. Based on the calculated short circuit currents for the available mains voltage, the
instruments to read the HV and LV currents and the range to be selected can be
decided for the short circuit test.
e. The transformer testing Board used for Magnetic balance test is can also be used
for Short circuit current test as shown in Figure(8).

35
f. For 3-Ph Auto-transformer having tertiary winding, Connect all three phases of
HV,IV,LV and Neutral Bushing top through insulated wire at respected terminal
marked on above testing board as 1U,1V,1W ,2U,2V,2W & 3U,3V,3W N
respectively and testing is done in steps as elaborated below.
I. 3-phase Supply is given to HV Side with IV side Shorted and kept LV Side
open as shown in Figure(28) and then measure the HV and IV Current using
Current Clamp Meter or Tong Tester with Neutral Grounded and without
Neutral grounded and Note down the result in Table-20 as shown below

Figure(28) : Measurement of Short Circuit current of HV with IV Shorted

Applied 3 Ph Voltage on HV Side with IV Shorted and LV Open


Neutral Measured Current( Amp) Applied Voltage (V)
Condition 1U 1V 1W 2U 2V 2W 1U-1V 1V-1W 1W-1U
1N
Ungrounde
d
Grounded

Table(20) :Format for Measurement of Short Circuit current of HV with IV Shorted

II. 3-phase Supply is given to HV Side with LV side Shorted and kept IV Side
open as shown in Figure(29). and then measure the HV and LV Current using

36
Current Clamp Meter or Tong Tester with Neutral Grounded and without
Neutral grounded and Note down the result in Table-21 as shown below

Figure(29) : Measurement of Short Circuit current of HV with LV Shorted

Applied 3 Ph Voltage on HV Side with LV Shorted and I V Open


Neutral Measured Current( Amp) Applied Voltage (V)
Condition 1U 1V 1W 3U 3V 3W 1U-1V 1V-1W 1W-1U
1N
Ungrounde
d
Grounded

Table(21) :Format for Measurement of Short Circuit current of HV with LV Shorted

g. For 3-Ph Conventional Two Winding transformer , Connect all three phases of
HV,LV and Neutral Bushing top through insulated wire at respected terminal
marked on above testing board as 1U,1V,1W,1N and 2U,2V,2W, 2N respectively
and testing is done in steps as elaborated below.

I. 3-phase Supply is given to HV Side with LV side Shorted as shown in


Figure(30) and then measure the HV and LV Current using Current Clamp
Meter or Tong Tester with Neutral Grounded and without Neutral grounded
and Note down the result in Table-22 as shown in next page

37
Figure(30) : Measurement of Short Circuit current of HV with LV Shorted

Applied 3 Ph Voltage on HV Side with LV Shorted


Neutral Measured Current( Amp) Applied Voltage (V)
Condition 1U 1V 1W 2U 2V 2W 1U-1V 1V-1W 1W-1U
1N
Ungrounde
d
Grounded

Table(22) :Format for Measurement of Short Circuit current of HV with LV Shorted

h. Compare the result with factory test result or with Theoretical calculated current
The acceptable criteria should be the measured short circuit current will be within 3
percent .Variation in short circuit of more than 3% should be considered significant
and further investigated.

5 Capacitance and Tan Delta of Transformer Windings.


Capacitance & Tan δ measurement of Transformer windings shall be taken between the
windings collectively (i.e. with all the windings being connected together) and the earthed
tank (earth) and between each winding and the tank at 5KV/10KV with fully automatic test kit
so as to have reliable test result.. Before taking measurements the neutral should be
disconnected from earth. Here Testing is describing using Omicron CPC-80 Capacitance
and Tan Delta measurement kit as shown in Figure(14).

38
Before using the Omicron CPC-80, the instruction manual for operating the Kit must
be carefully studied and all precautions noted therein must be followed
Setup of Omicron CPC-80 kit for measurement of Capacitance & Tan δ of
Transformer windings:
i. Power Supply for Kit should be phase controlled with ground

ii. Ground terminal of kit and supply board should be same.


iii. Properly connect both kits via serial interphase connector and Ext. Booster
cable as per the slots shown in Figure(14) . .
iv. Connect the HV and LV leads as per slot an color code as shown in
Figure(14) ..
v. Power on the Kit and create a template of power transformer as describe in
instruction manual .
vi. Select the Supply voltage 5 KV & 10 KV at which Capacitance & Tan δ
measures
vii. Keep Step of variac as 20 and select Capacitance and Tan δ ( Cp, DF(Tan
δ))
viii. Select the Desired test mode as UST, GST or GSTg
ix. Now Push Start Button two times for starting the Test.
x. When Testing Done Result Shown on Screen as shown in Figure(31)

39
Figure(31): Screen showing result in different mode
a. Figure(32) Shows the combination of capacitance between the windings and
between winding and tank (earth).CH is the capacitance between the HV/IV winding
and grounded tank and core, CL is the capacitance between the LV winding and
grounded tank and core and CHL is the capacitance between the HV/IV winding and
LV winding.

40
Figure(32) : Capacitance between the Windings

b. Ensure that test specimen is isolated from other equipments. Removal of Jumpers
from Bushings is Pre-Requisite for C & Tan δ Measurement of Windings.
c. For 3-Ph Auto-transformer, Short all HV (High Voltage bushing), IV (Intermediate
Voltage Bushing) and Neutral (isolated from earth) Bushings together. Also short all
LV (Low Voltage) Bushings together as shown in Figure(33) .

Figure(33) : Top View of 3-ph Auto transformer with Shorting

Capacitance and Tan δ measurement of windings should be done in following


combinations as shown in Table-23

Tes
Winding Test Capacitanc
t Test Lead Connection Remark
Combination Mode e symbol
no.
1. HV-IV/LV UST CHL HV lead of test Kit to shorted
2. HV-IV/LV+ G GST CH + CHL HV/IV bushing of transformer
LV lead of test kit to shorted LV to be
HV-IV/ LV with
3. GSTg CH LV bushing of transformer as guarded
Guard
shown in Figure(34)
4. LV/HV-IV UST CHL LV lead of test Kit to shorted
5. LV+ G /HV-IV GST CL + CHL HV/IV bushing of transformer
HV lead of test kit to shorted HV to be
LV /HV-IV with
6. GSTg CL LV bushing of transformer as guarded
Guard
shown in Figure(35)
Table-23 : Winding Combination for Capacitance & Tan δ measurement for Auto
Transformer

41
Figure(33) : Arrangement for Capacitance & Tan δ measurement for Auto Transformer

Figure(34) : Arrangement for Capacitance & Tan δ measurement for Auto Transformer
d. For 3-Ph Conventional Two winding or Three Winding Transformer Short all
HV(High Voltage bushing) and HV Neutral (isolated from earth) Bushings together
and Short all LV(Low Voltage) Bushings and LV Neutral (isolated from earth)
Bushings together as shown in Figure(36).

42
Figure(36) : Top View of 3-ph Two Winding transformer with Shorting

Capacitance and Tan δ measurement of windings should be done in following


combinations as shown in Table-24

Tes
Winding Test Capacitanc
t Test Lead Connection Remark
Combination Mode e symbol
no.
1. HV/LV UST CHL HV lead of test Kit to HV/IV
2. HV/LV+ G GST CH + CHL bushing of transformer
LV lead of test kit to LV LV to be
HV/ LV with
3. GSTg CH bushing of transformer as guarded
Guard
shown in Figure(37)
4. LV/HV UST CHL LV lead of test Kit to HV/IV
5. LV+ G /HV GST CL + CHL bushing of transformer
HV lead of test kit to LV HV to be
LV /HV with
6. GSTg CL bushing of transformer as guarded
Guard
shown in Figure(38)
Table-24 : Winding Combination for Capacitance & Tan δ measurement for
Conventional Two winding Transformer

43
Figure(37) : Arrangement for Capacitance & Tan δ measurement for 3-ph Two Winding
Transformer

Figure(38): Arrangement for Capacitance & Tan δ measurement for 3-ph Two Winding
Transformer
e. Measurement inter-check can be done by calculating
C1= C2-C3 & C4= C5- C6
Where C stands for capacitance attached suffix (1…6) denotes the sr. no. of test in
above Table-23 & 24

44
f. Compare the measured result with factory test results, the accepted deviation from
the values measured at factory tests should be less than 10%.
g. Tan delta (δ) of Winding at 20˚C should be less than 0.007.

6 Capacitance and Tan Delta of Bushings


Capacitance & Tan δ measurement of bushings shall be done at 5KV/10KV with fully
automatic test kit so as to have reliable test result. The test kit should be suitable to work in
charged switchyard environment i.e induction suppression unit should be provided along
with double shielded leads. Here Testing is describing using Omicron Capacitance and Tan
Delta measurement kit as shown in Figure(14).
b. For 3-Ph Auto-transformer, Short all HV (High Voltage bushing), IV (Intermediate
Voltage Bushing) and Neutral (isolated from earth) Bushings together. Also short all
LV (Low Voltage) Bushings together as shown in Figure (33).
c. For 3-Ph Conventional Two winding or Three Winding Transformer Short all
HV(High Voltage bushing) and HV Neutral (isolated from earth) Bushings together
and short all LV(Low Voltage) Bushings and LV Neutral (isolated from earth)
Bushings together as shown in Figure (36)
d. The bushing porcelain and test tap are to be properly cleaned before the
commencement of tests.
e. Environmental factors like variation in temp, relative humidity, surrounding charged
object etc have great influence on measurement of dissipation factor. Care should
be taken to control the above factors during the measurement

45
Figure (39) Internal Bushing Capacitance arrangement

f. (Tan delta (δ) point ) of the Bushing which is to be tested. Figure(39) shows the
internal arrangement of Bushing. C1 is the capacitance between HV terminal of
bushing and test tap(Tan delta (∂) point ) and C2 is the capacitance between test
tap(Tan delta (∂) point) and earth
g. Measurement of C1 Capacitance and Tan δ in UST Mode :
 Connect the crocodile clip of the HV cable to the top terminal of the any one
shorted HV/IV and LV bushings for the measurement of HV/IV, N and LV
Bushing respectively. Unscrew the test tap(Tan delta (δ) point ) cover, in
order to Un-earth Tan delta (δ) point insert a pin in the hole of the central
test tap stud by pressing the surrounding contact plug or remove the
earthing strip from the flange by unscrewing the screw (holding earth strip to
the flange body) as per the arrangement available in bushing at site .
Connect the LV cable to the test tap (Tan delta (δ) point ) (strip/central
stud) of the bushing.
 Apply 5KV/10KV in UST Mode from C & TAN δ measurement Omicron Kit
through cable. Repeat the test for all Bushings by changing only LV lead
connection of the kit to test tap(Tan delta (δ) point ) of the Bushing which is
to be tested
 Compare the measured result with factory test results, the accepted
deviation from the values measured at factory tests should be less than
10%.

46
 Tan delta (δ) of bushings at 20˚C should be less than 0.007
h. Measurement of C2 Capacitance and Tan δ in GSTg Mode :
 HV lead to be connected to the test tap(Tan delta (δ) point ) of the bushing
under test (if required additional crocodile type clip may be used) and LV of
the kit to be connected to the ground. HV of the bushing is to be connected
to the Guard terminal of the test kit.
 Apply 500V in GSTg mode from C & TAN δ measurement Omicron Kit
through a screened cable. Repeat the test for all Bushings by changing only
HV lead connection of the kit to test tap
 Compare the measured result with factory test results. The capacitance
between bushing test tap(Tan delta (δ) point ) and ground is largely
influenced by the stray capacitances in the ground parts in the transformer
and hence large deviation in the measured value shall be accepted when
compared with the factory test value.

i. Do not test a bushing (new or spare) while it is in its wood shipping crate, or while it
is lying on wood. Wood is not as good an insulator as porcelain and will cause the
readings to be inaccurate. Keep the test results as a baseline record to compare with
future tests.
j. It is to be ensured that C& Tan δ measurement of bushings and testing of turrets
carried out before installation. This will prevent installation of bushings having C&
Tan δ values beyond permissible limits.
k. It is to be ensured that Test Tap points are earthed immediately after carrying
out the measurements for that particular Bushing and earthing of test tap to be
ensured by carrying out continuity test

7 Insulation Resistance IR value measurement.


Objective of this test is to determine whether the Transformer is in a condition to
receive high voltages in to it and the condition of the insulations involved.
a. Factors affecting the IR value are temperature, dryness of insulations, cleanliness,
humidity, condition of oil etc .For similar designs IR values need not be same at
same temperature. It may be noted that no national / international standards
specify minimum IR values for trans-formers. The value of IR may be very low
under heavy fog or humid condition
b. During insulation resistance measurement, IR value progressively increases with the
time of application of test voltage and it reaches almost a steady value after a length

47
of time. Insulation resistance varies inversely with temperature and is generally
corrected to a standard temperature (usually 60 °C) using Multiplication Factor table
available in Transformer life sketch book.
c. Insulation resistance of transformer for different winding combination is taken at Oil
Temp. (OT) at time of testing for 15 second, 60 seconds( 1 min) and 600 seconds(10
min) at 5 KV Voltage.
d. The ratio of 60 second insulation resistance to 15 second insulation resistance value
is called dielectric absorption coefficient or Index (DAI). For oil filled transformers
with class A insulation, in reasonably dried condition the absorption coefficient will be
more than 1.3.
DAI = ( R60 / R15 )
Where R60 is the Insulation Resistance at 60 sec. & R15 is the Insulation Resistance at
15 sec
e. Polarization Index Test is ratiometric test, insensitive to temperature variation and
may be used to predict insulation system performance. The polarization index is the
ratio of the 10 min to the 1 min mega ohm readings.
PI = ( R600 / R60 )
Where R600 is the Insulation Resistance at 600 sec. & R60 is the Insulation Resistance
at 60 sec
f. Before Starting the I.R value measurement following points must be ensure :
I. The transformer neutral is to be disconnected from ground. It should be ensured
that there are no jumpers connected on to the transformer bushings.
II. The bushing porcelain and test tap are to be properly cleaned before the
commencement of tests
III. The Insulation Tester may be preferably kept on a flat wooden board or stool.
Insulation Tester leads should be strong and have a very good insulation.
IV. The HV lead between the transformer bushing connection and Insulation Tester
terminal must be kept suspended in the air by holding with a sufficiently long and
good and flexible insulation tape (glass tape or dry cotton tape for instance) so
that no part of the HV lead comes into contact with the earth or transformer body.
V. If the transformer has been under hot oil circulation, the insulation resistance has
to be measured after the transformer has sufficiently cooled.
VI. Along with the IR values, the winding/oil temperatures at the time of test, Date
and time, details of the Insulation tester used and the weather condition are to be
noted
VII. Figure(40) below show the Front panel of Megger Make AVO BM25 Insulation
Tester

48
g. Testing Procedure For 3-Ph Auto-transformer, Short all HV (High Voltage
bushing), IV (Intermediate Voltage Bushing) and Neutral (isolated from earth)
Bushings together. Also short all LV (Low Voltage) Bushings together as shown in
Figure(33) .
I. Now connect HV lead of Insulation Tester to the any one shorted bushing of
HV/IV winding and the ground lead of Insulation Tester connected to one of the
earth terminals of transformer tank. as shown in Figure(41).

49
Figure(41) : Showing the arrangement for measurement of IR value between
HV-E

II. Now record Insulation resistance of HV to E for 15 second, 60 seconds( 1 min)


and 600 seconds(10 min) at 5 KV Voltage & calculate DAI & PI and note down
the result in Table(25)
III. Now connect HV lead of Insulation Tester to the any one shorted bushing of LV
winding and the earth lead of Insulation Tester connected to one of the earth
terminals of transformer tank. as shown in Figure(42)..

Figure(42) : Showing the arrangement for measurement of IR value between LV-E

50
IV. Now record Insulation resistance of LV to E for 15 second, 60 seconds( 1 min)
and 600 seconds(10 min) at 5 KV Voltage & calculate DAI & PI and note down
the result in Table(25)
V. Now connect HV lead of Insulation Tester to the any one shorted bushing of
HV/IV winding and the earth lead of Insulation Tester connected to any one
shorted bushing of LV winding of transformer tank. as shown in Figure(43).

Figure(43) : Showing the arrangement for measurement of IR value between HV-LV

VI. Now record Insulation resistance of HV to LV for 15 second, 60 seconds( 1 min)


and 600 seconds(10 min) at 5 KV Voltage & calculate DAI & PI and note down
the result in Table(25)

IR Value Measurement DAI PI


Test IR Value of 60 Sec
Terminal 15 60 R60 /
Voltage 600 Sec R600 / R60 Converted at 60 oC
Sec Sec R15
HV-E
LV-E
HV-LV
Table(25) : Format for taking the reading of I.R Value measurement.

h. Testing Procedure For Conventional Two winding transformer, Short all HV


(High Voltage bushing) and HV Neutral (isolated from earth) Bushings together.
Short all LV (Low Voltage) Bushings and LV Neutral (isolated from earth) Bushings
together as shown in Figure(36). .

51
I. Now connect HV lead of Insulation Tester to the any one shorted bushing of HV
winding and the earth lead of Insulation Tester connected to one of the earth
terminals of transformer tank. as shown in Figure(44).

Figure(44) : Showing the arrangement for measurement of IR value between HV-E

II. Now record Insulation resistance of HV to E for 15 second, 60 seconds( 1 min)


and 600 seconds(10 min) at 5 KV Voltage & calculate DAI & PI and note down
the result in Table(25)
III. Now connect HV lead of Insulation Tester to the any one shorted bushing of LV
winding and the earth lead of Insulation Tester connected to one of the earth
terminals of transformer tank. as shown in Figure(45)..

52
Figure(45) : Showing the arrangement for measurement of IR value between HV-E

IV. Now record Insulation resistance of LV to E for 15 second, 60 seconds( 1 min)


and 600 seconds(10 min) at 5 KV Voltage & calculate DAI & PI and note down
the result in Table(25)
V. Now connect HV lead of Insulation Tester to the any one shorted bushing of HV
winding and the earth lead of Insulation Tester connected to any one shorted
bushing of LV winding of transformer tank. as shown in Figure(46).

53
Figure(46) : Showing the arrangement for measurement of IR value between HV-E

VI. Now record Insulation resistance of HV to LV for 15 second, 60 seconds( 1 min)


and 600 seconds(10 min) at 5 KV Voltage & calculate DAI & PI and note down
the result in Table(25)

i. The following are guidelines for evaluating transformer insulation using polarization
index values:

Polarization Index Insulation Condition


Less than 1 Dangerous
1.0-1.1 Poor
1.1-1.25 Questionable
1.25-2.0 Fair
2.0 – 4.0 Good
Above 4.0 Excellent

A PI of more than 1.25 and DAI of more than 1.3 are generally considered
satisfactory for a transformer when the results of other low voltage tests are
found in order. PI less than 1 calls for immediate corrective action.

54
j. Testing Procedure For IR Value measurement of Bushing ..
I. The bushing porcelain and test tap are to be properly cleaned before the
commencement of tests
II. For 3-Ph Auto-transformer, Short all HV (High Voltage bushing), IV
(Intermediate Voltage Bushing) and Neutral (isolated from earth) Bushings
together. Also short all LV (Low Voltage) Bushings together as shown in
Figure(33). .
III. Connect HV Lead of Insulation tester to the top terminal of the any one shorted
HV/IV or N bushings and the earth lead of insulation tester to the test tap(Tan
delta (δ) point ) of the bushing as shown in Figure(47). and measure the IR value
at voltage as measure in factory test.

Figure(47) : Showing the arrangement for measurement of IR value of Bushing

IV. Repeat the test for all HV/IV/N Bushings by changing only the earth lead of
insulation tester to test tap(Tan delta (δ) point ) of the Bushing which is to be
tested.
V. Repeat above step III & IV for the measurement of IR value for LV Bushings

VI. For 3-Ph Conventional Two winding or Three Winding Transformer Short all
HV(High Voltage bushing) and HV Neutral (isolated from earth) Bushings
together and short all LV(Low Voltage) Bushings and LV Neutral (isolated from
earth) Bushings together as shown in Figure(36).

55
VII. Connect HV Lead of Insulation tester to the top terminal of the any one shorted
HV or N bushings and the earth lead of insulation tester to the test tap(Tan delta
(δ) point of the bushing as shown in Figure(47). and measure the IR value at
voltage as measure in factory test.
VIII. Repeat the test for all HV Bushings by changing only the earth lead of insulation
tester to test tap(Tan delta (δ) point ) of the Bushing which is to be tested
IX. Repeat above step VII & VIII for the measurement of IR value for LV Bushings

k. For bushings, an IR value of above 10,000 MΩ is considered satisfactory.

l. Compare the above measured result of transformer and bushing with factory test
results and if any deviation found will reporting immediately.

8 Frequency Response Analysis Test.


Frequency Response Analysis (FRA) is conducted to assess the mechanical integrity of
the transformer which may get disturbed due to transportation shocks or Short Circuit forces
experienced in service. FRA signatures will be taken after assembly and oil filling and
compared with factory testing to ensure the healthiness of core /coil assembly during
transportation. These signatures will be benchmark for future reference. The FRA signatures
should be analysed in conjunction with Impact Recorder readings. Report of Impact recorder
readings is to be obtained from manufacturer

9 Winding Resistance Measurement.


Winding resistance measurement is an DC Test and perform to check for any
abnormalities due to loose connections, broken strands and high contact resistance in tap
changers.
a. The winding resistance should preferable be carried out last after completion of all
other LV tests , as after this test core gets saturated and tests like magnetizing
current, magnetic balance etc. carried out after winding test may be affected and
indicate a misleading results, if the core is not de-magnetized before carrying out
these tests.
b. Here Testing is describing using SCOPE TRM 25 Winding resistance measurement
kit as shown in Figure(48). Before using the SCOPE TRM 25, the instruction manual

56
for operating the Kit must be carefully studied and all precautions noted therein must
be followed

Figure(48) : Front pane of Scope Make TRM25 Winding resistance measurement kit

NORMAL
0.0 V 0.00 A
HV 1U - S1 S2
REVERSED 1.814 V 7.0 mA
NORMAL 0.0 V 0.00 A
R – PHASE
LV 2 U – S1 S2
REVERSED 3.89 V 15.1 mA
NORMAL 0.0 V 0.0 A
NCT S1 S2
REVERSED 2.36 V 9.0 mA
NORMAL
0.0 V 0.00 A
HV 1 V – S1 S2
REVERSED 1.84 V 7.2 mA
Y – PHASE NORMAL 0.0 V 0.00 A
LV 2 V – S1 S2
REVERSED 3.96 V 15.6 mA
NORMAL
0.0 V 0.0 A

57
NCT S1 S2
REVERSED 2.389 V 9.4 mA
NORMAL
0.0 V 0.00 A
HV 1 W – S1 S2
REVERSED 1.80 V 6.8 mA
NORMAL
0.0 V 0.00 A
B – PHASE
LV 2 W – S1 S2
REVERSED 3.89 V 15.2 mA
NORMAL 0.0 V 0.0 A
NCT S1 S2
REVERSED 2.356 V 9.2 mA

c. LOW IMPEDANCE REF TEST: Nowadays we are using numerical differential relays
and almost all relays are having REF element (restricted earth fault). The numerical
relays are also giving advantage of using Low Impedance REF. In Low Impendence
Winding resistance is measured by applying Voltage and current from the kit,
SCOPE TRM 25 have three voltage Channel V1, V2 & V3 and current channel C +/-.
d. Connection for the current lead clamp should be made to the outer side of the
bushing and Voltage lead clamp should be connected to the inner side w.r.t current
lead clamp as shown in Figure(49). and be ensure that Voltage and current lead
clamp should not touch other physically.

Figure(49) : Connection of voltage and current clamp

58
e. The transformer winding is highly inductive. To reduce the high inductive effect it is
advisable to use a sufficiently high current to saturate the core. This will reduce the
time required to get a stabilized reading.
f. Before starting the measurement following point must be ensure.
I. Isolate the transformer to be tested .
II. Connect master earthing cable to the instrument.
III. Clean the area of transformer bushing where test lead clamp connection are to
be made.
IV. Ensure that earthing connection, if any is removed from Neutral terminal of
transformer.
V. Now make connection for CURRENT (C+, C-) and VOLTAGE ( V1+, V1- & V2+,
V2- & V3+, V3-) lead as describing below, to the transformer bushings.
VI. The winding/oil temperatures at the time of test, Date and time, details of the
Testing kit used and the weather condition are to be noted
g. Testing Procedure For 3-Ph Auto-transformer, Here winding resistance of HV
winding, IV winding and LV winding is measure.
I. Connect Current lead clamp C+ to 1U terminal of HV Bushing and Current lead
clamp C- to 2W terminal of IV Bushing
II. Connect Channel-1 Voltage lead clamp V CH1+ & VCH1- across 1U-N, Channel-2
Voltage lead clamp VCH2+ & VCH2- across 2U-N and Channel-3 Voltage lead
clamp VCH3+ & VCH3- across 2W-N as shown in Figure(50)..

59
Figure(50) : Connection for TRM25 Winding resistance measurement kit for Auto x-
mer

III. Ensure that the current lead clamp should be made to the outer side of the
bushing and Voltage lead clamp should be connected to the inner side w.r.t
current lead clamp.
IV. The tap changer should be changed from contact to contact so that contact
resistance can also be checked Now Bring the tap Position to Tap No-1 and Start
the testing and record the resistance of 1U-N, 2U-N & 2W-N at tap no-1 .
Measurement of winding resistance to be carried out from tap position 1 to 17
and note down the result in Table-26 & Table-27 as shown below.
V. Now repeat the process as explain above in points I to IV for the measurement of
resistance of 1W -N, 2V-N & 1V-N by connecting leads as shown in Figure(51).
and note down the result in Table-26 & Table-27 as shown below.

Figure(51) : Connection for TRM25 Winding resistance measurement kit for Auto
x-mer
VI. For measurement of winding resistance of LV delta connected windings, such as
tertiary winding of auto- transformers, measurement shall be done between pairs
of line terminals by 3U-3V using single voltage channel V CH1+ & VCH1- and current
channel C+ & C- as shown in Figure(52) and repeat the same process for
measurement of resistance for 3V-3W & 3U-3W and note down the result in
Table-28 as shown below.

60
Figure(52) : Connection for TRM25 Winding resistance measurement kit for
Tertiary of Auto X-mer

Winding Resistance at Oil Temp =


Average R at Average R at
Tap No 1U-N 1V-N 1W-N
Oil Temp. 75 deg.

Table(26) : Format for Winding resistance measurement of HV Winding

Winding Resistance at Oil Temp =


Average R at Average R at
Tap No 2U-N 2V-N 2W-N
Oil Temp. 75 deg.

Table(27) : Format for Winding resistance measurement of IV Winding

Winding Resistance at Oil Temp =


Average R at Average R at
Tap No 3U-3W 3U-3V 3V-3W
Oil Temp. 75 deg.

Table(28) : Format for Winding resistance measurement of LV Winding

61
VII. Now Calculate the resistance at 75°C as per the following formula
R75 = Rt (235+75)/(235+t ), Where Rt = Measure Resistance and t is winding
temperature

h. Testing Procedure For conventional Two winding transformer, Here winding


resistance of HV winding and LV winding is measure.
I. Connect Current lead clamp C+ to 1U terminal of HV Bushing and Current lead
clamp C- to 2W terminal of IV Bushing
II. Connect Channel-1 Voltage lead clamp V CH1+ & VCH1- across 1U-1N, Channel-2
Voltage lead clamp VCH2+ & VCH2- across 1W-1N and Channel-3 Voltage lead
clamp VCH3+ & VCH3- across 2U-2N as shown in Figure(53)

Figure(53) : Connection for TRM25 Winding resistance measurement kit for Two
Winding X-mer

III. Ensure that the current lead clamp should be made to the outer side of the
bushing and Voltage lead clamp should be connected to the inner side w.r.t
current lead clamp.
IV. The tap changer should be changed from contact to contact so that contact
resistance can also be checked Now Bring the tap Position to Tap No-1 and Start
the testing and record the resistance of 1U-1N, 1W-1N & 2U-2N at tap no-1 .

62
Measurement of winding resistance to be carried out from tap position 1 to 17
and note down the result in Table-29 & Table-30 as shown below.
V. Now repeat the process as explain above in points I to IV for the measurement of
resistance of 1V-1N, 2V-2N & 2W-2N by connecting leads as shown in Figure-54
and note down the result in Table-29 & Table-30 as shown below.

Figure(54) : Connection for TRM25 Winding resistance measurement kit for Two
Winding X-mer

Winding Resistance at Oil Temp =


Average R at Average R at
Tap No 1U-N 1V-N 1W-N
Oil Temp. 75 deg.

Table(29) : Format for Winding resistance measurement of HV Winding

Winding Resistance at Oil Temp =


Average R at Average R at
Tap No 2U-2N 2V-2N 2W-2N
Oil Temp. 75 deg.

63
Table(30) : Format for Winding resistance measurement of LV Winding

VI. Now Calculate the resistance at 75°C as per the following formula
R75 = Rt (235+75)/(235+t ), Where Rt = Measure Resistance and t is winding
temperature

i. The resistance value obtained should be compared with the factory test valueResults
are compared to other phases in Star-connected transformers or between pairs of
terminals on a Delta–connected winding to determine if a resistance is too high or
low. Because field measurements make it unlikely that precise temperature
measurements of the winding can be made, the expected deviation for this test in the
field is 5.0 % of the factory test value.

10 Through Fault Stability test.


Through fault stability test is an important end to end testing for transformer. The test
is conducted for verifying CT connections in differential relay its stability in through fault
condition.
A power transformer is connected to the High voltage bus and Low voltage bus of the
sub-station through Circuit breakers, Current transformers, Lightning arrestor and Isolator
as illustrated in figure(1) below . A Three winding Auto Transformer connected 400/200/33
KV 315 MVA transformer is taken here. Current rating for this transformer is 455/827/1837
A.

64
Figure(1): Bay Diagram of 315 MVA X-mer showing equipment covers in Through
Fault stability test

To carry out test all three phase one side of transformer is shorted and 3 phase LV
voltage is applied on other side. Generally voltage is applied on HV side and LV side all
three phase are shorted. If current observed in relay is very low then supply can be fed from
LV side and shorting can be done in HV side. When shorting is done taking CT in circuit, it is
called OUT OF ZONE FAULT. When shorting is done in such a way that no current is
flowing through CT then it is called IN ZONE FAULT TEST. When this test is conducted
current in differential relay, backup relay and meter can also be checked and verified. When
voltage is applied say on HV side and LV is shorted then current will be drawn according to
percentage impedance of the transformer. Percentage impedance of transformer is the
percentage of HV voltage when applied to HV side of transformer and LV 3 phase is shorted.
Here Through fault stability test of 400/200/33 KV 315 MVA transformer is explain
% impedance (Z) = 11.28

65
Now %Z i.e 11.28 % of 400 KV = 45120 V will Deliver rated current of 455 A on Short Ckt
of 220 KV Side
Therefore 3-Ph Supply 440 V will deliver = (440 * 455) / 45120 = 4.43 A, Short circuit
current of 400 KV side.
For 220 KV Side Short circuit current = 4.43 * (400/220) = 8.06 A
CTR- HV 400KV Side 500/1, and LV 220KV Side 1200/1
A. OUT OF ZONE FAULT TEST : Three phase Voltage applied on HV 400 KV Side
and Shorting is provided on LV 220 KV Side keeping 220 KV Side CT IN.
a. Current shown in GE T60 Differential relay on HV and LV side is shown in
figure (2) below. This is stable condition all Three phase current are shown
with zero negative sequence current:

66
Figure(2): Current in HV & LV side when 3-Phase supply given to HV Side with LV
Side Shorted keeping LV CT IN
b. Now in order to check phase wise CT connection kept out HV R-phase
supply and keeping all 3-Ph LV side shorted and then current in HV and LV
side is shown in figure(3) below , Here Negative sequence current shown
because 1 phase out:

67
Figure(3): Current in HV & LV side when HV R-ph supply out with LV Side Shorted
keeping LV CT IN

c. Now kept out HV Y-phase supply and keeping all 3-Ph LV side shorted and
then current in HV and LV side is shown in figure(4) below, Here Negative
sequence current also shown because 1 phase out:

Figure(4): Current in HV & LV side when HV Y-ph supply out with LV Side Shorted
keeping LV CT IN

d. Now kept out HV B-phase supply and keeping all 3-Ph LV side shorted and
then current in HV and LV side is shown in figure(5) below, Here Negative
sequence current also shown because 1 phase out:

68
Figure(5): Current in HV & LV side when HV B-ph supply out with LV Side Shorted
keeping LV CT IN

B. IN ZONE FAULT TEST : Three phase Voltage applied on HV 400 KV Side and
Shorting is provided on LV 220 KV Side keeping 220 KV Side CT OUT. Current in
GE T60 relay on HV & LV Side is shown below in Figure (6) , Here Current on LV
Side is zero.

69
Figure(6): Current in HV & LV side when 3ph supply given on HV side with LV Side
Shorted keeping LV CT OUT.

70
11 REF Stability test.
This test is performed to check the correctness of CT polarity, CT secondary core
connections, connections at relay terminals and operation of relay under fault conditions.

A. HIGH IMPEDANCE REF TEST: For High Impedance REF relay Transformer
Bushing CT’s of Same Ratio are used and connected to the relay as shown below in
figure (7). Here CT connection of Auto Transformer with High Impedance REF relay
is shown

Figure(7): Connection diagram of HV,IV,LV & N Bushing CT for High Impedance REF
Relay.
a. High Impedance REF relays are voltage operated relay in order to check the
stability of REF voltage across CT terminal of REF relay are check by
changing polarity of connected CT.
b. 3-Phase AC Voltage applied on HV Side keeping LV Side all three Phase
Open. Now Earth LV side R-phase and measure the voltage across CT
terminal of REF relay and also measure the current in CT lead.

71
c. Under Normal Bushing CT polarity voltage across CT terminal of REF relay
and current in CT lead is zero which is stable condition, now reverse CT
polarity of NCT and measure the voltage across CT terminal of REF relay and
also measure the current in CT lead, considerable voltage and current
appears at CT terminal of REF relay which is unstable condition. Now
normalize the CT polarity of NCT.
d. Repeat the Process as describe in above point b & c for LV Y-phase and B-
phase and check the REF stability
e. Below table shows the result of REF stability test of 315 MVA Auto
Transformer

MEASURED VOLTAGE
MEASURED
PHASE CT POLARITY ACROSS REF TERMINALS
CURRENT
AT PANEL END
B. REF, CTs of different ratios can be used and bushing CTs are also not required.
GE and AREVA are giving Low impedance element and ABB relay can be configured
:
a. Advantage of LOW IMPEDANCE REF
 Low Impedance REF uses main differential CT thus if it is provided on HV
side then its zone covers main CT to HV side transformer winding.
Likewise on LV side it covers main LV CT to LV winding of transformer. In
auto transformer it covers complete differential zone. Hence, besides
differential protection second unit protection can be availed for
transformer bays and transformer windings. Whereas High impedance
REF is restricted to transformer only. Most of the time tripping occurs due
to fault in bays.
 The low impedance REF is free from Harmonic restraint feature; hence
we can get rid of delay caused by harmonic restraint feature. We can
safely charge transformer without thinking of delay in tripping due to
harmonic block
b. Setting of LOW Impedance REF in GE & AREVA Differential relay
In GE T60 Differential relay

72
In Areva Differential relay

73
c. Through Fault Stability test of LOW Impedance REF
 Apply three phase voltages from HV side but if secondary currents are
very low and are not measurable by numerical relay then voltages can be
fed from LV side.
 Three phase voltages are applied from LV side of transformer and on HV
side instead of shorting three phase only one phase is grounded as
shown in figure(8) . This is similar to single phase to ground fault. In this

74
way zero sequence current will flow in neutral circuit and if relay is
configured correctly no REF differential current will be observed.

Figure(8)

d. Current in GE T60 Relay with REF Correct polarity

75
e. Current in GE T60 Relay with REF In-Correct polarity

76
_______________________________________________________________________

77
CHAPTER-2
DC SYSTEM OF EHV SUB-STATION

Er. P.K. Gargava Er. Nutan Sharma

Rated voltage of the D.C. Control supply for Sub-station installations can be selected
from fairly standardised values of 220 V for 400 KV S/s, 110V for 132 KV S/s and 48 for
Communication system. The voltage of a lead-acid cell being 2 Volts per cell, the number of
cells in the battery would be half of the rated dc Voltage adopted. The energy storage
capacity of a battery is expressed in Ampere-hours which is the product of current in
amperes and the number of hours for which the same can be usefully delivered by the
battery. The ampere-hour capacity of a battery of lead acid cells varies with the rate of
discharge. The capacity is more at slower rates of discharge and less at higher rates of
discharge. Hence there is need for adopting a standard reference rate of discharge. The
Indian Standard Specifications listed in para 3.1 have adopted l0-hour rate as the standard
rate of discharge for specifying the Ah capacity of stationary batteries.
For Tubular Cells- IS: 1651-1991

Effect of temperature on Battery life-

Variations in the Choice of "Float" Voltage

78
The "Float" voltage being higher than the nominal voltage per cell, the DC bus voltage is
also higher than the rated voltage. For example a float voltage of 2.2 volts per cell would
raise the dc bus voltage to 121 volts in a 110 volt system with a 55 cell battery. Although the
bus voltage is about 10% higher than the rated voltage. it is acceptable for most
applications. However, if on account of special considerations variation of this order is not
permissible for a particular application one of the following charging procedures may be
adopted:
Selecting a Lower Float Voltage
This minimum float voltage should normally be 2.2 volts per cell. If a lower floating voltage is
adopted. It will call for application of equalising charges more frequently. Table below gives
in idea of the intervals at which equalising charges have to be applied corresponding to the
different floating voltages.

Boost Charging
Boost charging of battery is required to restore the specific gravity of the electrolyte in the
cells to then fully charged value. Boost charging is done by charging the battery at a high
rate till the specific gravity of electrolyte in the cells is restored to the fully charged value of
1.200 ± 0.005 at 27"C. This rate should be as high as is consistent with the pace of chemical
reaction taking place in the battery. If charging current higher than that consistent with the
chemical reaction is sent into the battery, the whole of it will not be utilised for charging the
cells and it will result in break-down of water in the electrolyte and liberation of hydrogen and
oxygen gases. This liberation of gases is called gassing. Violent gassing can result in
shedding of active material from the plates and damage to the cells. Too high a charging
current can also produce excessive heating which also can damage the cells. The
temperature of Electrolyte should not normally be allowed to exceed 38°C but in no case
more than 50°C during charging. If temperature tends to increase, the charging current may
be reduced and period of charge may be increased proportionately.
Boost Charging Scheme
As stated earlier under floating condition, the battery charger has an output voltage almost
equal to the rated voltage of the load. For boost charging, the output voltage of the charger
has to be increased to about 2.40 - 2.65 volts per cell in order to drive the required boost

79
charging current into the battery. Unless special measures are taken, the load also can be
subjected to higher voltage during this operation and the equipment constituting the load can
get damaged. The various methods for boost charging of battery without application of
higher than the rated voltage of the load are described below briefly.
Separate Boost and Float Charger Scheme with Blocking Diodes:
This scheme IS shown in figure below under float charge condition the boost charger switch
"S" is in the "off' position. The coil of contractor "A" is not energised. In this position, contacts
1, 2 and 3 of the contactor are open, but Its normally closed contact 4 is closed, and the
circuit of dc contactor "B" the contacts of which are In closed position, is complete. Thus the
battery, the float charger and the load are in parallel connection. The load current is being
supplied by the float charger which is also sending a small float charge current into the
battery so that the battery is maintained in a fully charged condition. If an emergency arises
and the ac supply fails, the output of float charger goes off but the battery is available to the
load. After the emergency is over and the ac supply is restored it is desired to boost charge
the battery. The boost charger switch "S" has to be closed. This energises the boost charger
through contacts 1. 2 and 3 of contactor "A" and a suitable voltage is applied across the
battery and it starts receiving the boost charge current. Contactor "A" being in energised
position, its normally closed contact 4 opens and de-energises contactor “B", thereby
opening its contacts. Thus the battery and the boost charger are isolated from the load and
the float charger. In this position, the high voltage of the boost charger is not applied to the
load which continues to be fed by the float charger. If during the boost charging operation,
the ac supply fails the contactor "A" drops, thereby energising contactor “B" the contacts of
contactor “B” there upon parallel the battery and the load. During the infinitely small time
involved in the cascade switching of contactor "A" and “B ", the load is connected through
the blocking diode across a reduced number of cells which depending on the degree of
recharging can supply up to the nominal system voltage to the load. If one of the chargers
becomes defective, the remaining healthy charger can still provide the charging facility even -
though it is somewhat restricted and a complete break-down is obviated. This scheme,
however, does not provide a direct connection between battery and the dc load, as during
the failure of AC supply, the flow of current has to take place through diode and contacts of
the contactor.

80
Thus if float mode of battery fails charger is to be kept in boost mode and manually we have
to keep voltage up to 121 Volts. The contactor B should also be kept on continuously by a by
a switch “full battery in circuit”. If for some time if battery is to be charged on boost then this
switch can be opened. Now the load will be fed through diode.

Reference manual:- Manual on specifications of Sub-station battery, charging equipment


and DC switch gear

_____________________________________________________________________

81
CHAPTER-3
DC LEAKAGE

Er. P.K. Gargava Er. Nutan Sharma


The DC system in EHVV substations provides auxiliary supply to control and relay
panels, breakers tripping coils and other automated equipments. The reliable operation of
relays and breakers is very important for transmission system. The DC source usually
consists of a bank of lead acid batteries connected in series to obtain the required voltage.
The floating DC voltage is fed through control cables. The DC leakage may occur due to
following reasons:-
 Damage of cable insulation
 Cutting of cable at C&R panel or Breaker mechanism ends
 Unconnected cores of cable lying on ground
 Insulation failure of trip coil, semaphore, relays, MOG etc
 Moisture ingress
‘DC Leakage’ causes unbalance voltage between positive to Earth and negative to earth.
Further degradation or multiple earthing of DC system may create short circuit leading to
failure of DC supply. Failure of DC supply to C&R panel or breaker means breakers and
relays will not operate if fault occurs. IEC- 60364-4-41 chapter 413-1-5-4 recommends that
first fault must be eliminated from the system within minimum possible time.
DETECTION OF DC LEAKAGE
1. Indication and alarm of charger
Charger are equipped with leakage current ampere meter and a mid-point earth
switch if switch is operated then amp meter will show leakage current value and
alarm will be there.
2. Two lamp method
Two incandescent lamps are connected in series between positive and negative
terminals and mid point is earthed. If there is no leakage both lamps will glow equally.
This circuit can be installed on any panel through fuse for monitoring.
Fig

3. DC voltmeter
Instead of lamps voltmeter can be provided which can read voltage with (+) and (-)
sign with selector switch.
Fig

82
DC MIXING
400 KV Sub-stations and most of the 220 KV Sub-stations are having dual DC supply
source. Trip coil-1 of breaker is connected to DC source-1 and trip coil-2 is connected to DC
source-2. The C&R panels are also having two DPR and differential relays and their
auxiliary DC supply sources are independent. As two separate sources are available it is
very important to take care of mixing of DC source during commissioning of CB and C&R
panels. The possibilities increase when modifications are done in a haphazard manner.
The mixing of DC even on a single point will mix complete DC sources and then It becomes
very difficult to detect and eliminate DC mixing.
In a mix DC system if DC leakage is occurred it will affect both sources. Multiple DC
leakage may cause situation worse. Ghost voltage or fictitious very high voltage may appear
between positive to Earth and negative to earth. If leakage is having low resistive path then
there is strong possibility of mal-operation of relay/breaker and burning of relay/breaker coils.
Keeps watch on DC mixing regularly and if it is observed then it is to be attended
immediately. To detect problem first check latest work of commissioning or modification. If
problem is chronic then each individual panels are to be checked one by one for mixing
whenever shutdown is availed.

DETECTION AND RECTIFICATION OF DC LEAKAGE

To detect and rectify problem of leakage current it is necessary to quantify the leakage
current and then identify the source of leakage

Following three methods can be adopted:-


1. DC Earth Fault Locator
2. Leakage current clamp meter.
3. Conventional Lamp Method.

1. DC Earth Fault Locator


TDCEFL of CSD instrument which have been supplied earlier to Testing Divisions are user
friendly DC Earth (Ground) Fault Locator. This portable instrument consisting of Signal
Generator & Signal Receiver uses latest digital signal processing technology. It detects earth
faults in live DC system quickly in online condition and relieves the substation maintenance
engineers from nightmare of earth leakages & its detection. It is an excellent solution for
preventive maintenance & troubleshooting of ground faults.

83
Features
 No need to cut down the DC system, T-DCEFL can locate the earth fault, increases
the power network reliability.
 It can test the AC Cross, to prevent the damage to devices because of that.
 Auto test the DC system voltage, and can adjust the output voltage according to
different DC system, like 230V, 110V, 48V and 24V.
 High intelligence, auto tell the grounding status, it can alarm when the system is
grounded.
 It can indicate the current direction, to test the loop grounding fault.
 It can display the grounding current waveform, the operator can tell the grounding
condition and avoid the effect for the distributed capacitance.
 Using digital signal processing technique, calculate and display the current lively, the
sensibility is highly increased, max. 100K bad insulation fault can be detected.
 The Transmitter can measure the grounding resistance and distributed capacitance,
calculate automatically the best frequency for the output signal.
 The Transmitter can have two power supply methods, DC and AC; it can be powered
by the DC system directly.
 Low voltage indication function.

PRINCIPLE OF OPERATION
T-DCEFL is composed by Transmitter, Receiver and Clamp.

Signal Generator or transmitter (Fixed) is connected across faulty bus bar (+ Ve or –Ve) and
ground, transmitted low frequency square wave signal. These transmitted signal flows from
generator to ground through fault and from ground it return back to Signal Transmitter, thus
path of signal is completed. During this operation, Signal Transmitter unit internally assesses
fault condition & automatically injects required voltage & current.

84
a. TRANSMITTER

Fig. 7.1 SIGNAL TRANSMITTER

85
b. RECEIVER

Fig. 7.2 SIGNAL RECEIVER

86
c. Clamp

Fig. 7.3 SIGNAL RECEIVER CLAMP


Fault tracing and pinpointing is carried out by signal receiver with current sensor clamp. After
connecting clamp at faulty cable receiver will show indication of signal strength and fault
current direction.

Fig. 7.4 USE OF SIGNAL RECEIVER CLAMP

87
Procedure
If there is fixed earth fault line selection device installed to the DC system, it should power off
it when we use the T-DCEFL for the fault detection, and also it is necessary to take off the
alarming relay to increase the detection accuracy.
Connection to use the Transmitter
To power off the Transmitter first, connect the +, - and Earth to the +, - and Earth of the DC
system separately. The red clip connects the positive polarity (+220v, +110v, +48v, +24v),
and the black clip connects to the negative polarity (0v), while the green clip connects the
earth (system earth).
Power supply
If the DC system is 220V or 110V system, we can use it to power the T-DCEFL Transmitter.
If the system is 48V or 24V, use the 220V AC to power it. When use DC system to power it,
the DC indication will light; when we use 220Vac to power it, the AC indication lights.
After connect well the Transmitter, power on it, and it will display the software information,
and then it will do the testing, the display is as Fig. 7.5 shows.

Fig. 7.5 System parameter display


The output frequency in Fig. 7.5 is the best suitable output frequency calculated by the
Transmitter according to the detection result. If the positive bus is earthed, the + indication
will light; if the negative bus is earthed, the – indication will light. If it is necessary to test the
system parameter again, please press PARAMETER TEST button, the Transmitter will test
and display the system parameter again. Press FREQUENCY, it
can set the output frequency manually.

88
Connection to use the Receiver
Set the frequency
Plug the signal cable of the clamp to the Receiver, power on the clamp. Then hold the
ON/OFF button of the Receiver over 1 second, the Receiver is powered on. The reminding
information will display as Fig. 7.6

Fig. 7.6 Operation reminding display


According to the above information, clip the clamp to the grounding cable of the Transmitter,
to enter the frequency setting display by pressing FREQUENCY button, the display is as
Fig.7.7 shows.

Fig.7.7 Frequency Setting Display


Here, the frequency displayed is 2Hz, and it blinks, press the FREQUENCY can change the
frequency, please be noted that the frequency set should be the same as the frequency of
the Transmitter. After setting the frequency, press SET REF. button, the display will be as
Fig.7.8 shows.

89
Fig. 7.8 Set Ref. reminding display

Attention: once the frequency is set, it cannot be changed, it needs to restart the Receiver if
the operator wants to set it again.
It will display SET REF. ?, we can press the SET REF. to confirm after the waveform is
stabilized. This process may need 5~20 seconds according to different frequency. After
setting the reference, the Receiver will record phase angel and display the current direction.
The display will be as Fig. 7.9

Fig. 7.9 Set Ref. finished Display

Here, the arrow on the upper right is the current direction. If it is before the fault location, it is
upward arrow, if there is earthed loop; it is downward arrow after the fault location. The
current value will also be displayed. If the DC system is earthed, it will display and alarm.
Attention: please don’t power off the Receiver before finding the fault position, because it
needs to reset the frequency and reference.

90
After finishing the set reference process, the Receiver will enter the testing process. Clip the
Clamp to the branch that needs to detect first, then press the ZERO button on the
Clamp, after that, press the REVERT button on the Receiver, the Receiver will test again.
The longer it tests, the better accuracy will have. Please remember to press ZERO and
REVERT every time the operator wants to clip the Clamp to a new branch.
Pinpointing:
To locate the earth fault is to measure the resistive current that flows the fault position using
Clamp, where there is earthed fault, there will have resistive current; while if it has no
earthed fault, there will have no resistive current. The branch with high grounded
capacitance and no earthed fault, there will have no resistive current, only capacitive current.
Pinpoint the fault position and pinpointing Procedures
A. First need to locate the branches, use the Clamp to clip the whole batch, two
branches or one branch, test them. If the grounded resistance is high, the Receiver
will not alarm, the operator can only tell whether there is branch earthed by the
waveform. If the grounded resistance is near to or lower than the national standard,
the Receiver will display the earthed condition and alarm.
B. If there is earthed branch, please go on the locating with the Tree method, from
branch to branch, then to smaller branch, till find the earthed line.
C. If we know that one circuit is earthed, and we need to pinpoint it, we need to locate
from the main to the end branches. If there is earthed waveform or alarm, which
indicates that the fault is still in the smaller branches, go on with the locating, till to
the end. If we still can not find the fault, then fault location is at the location between
where there is waveform and no waveform, then go on with the pinpointing.
D. If we can not find the fault location even to the end, it shows that the fault is with the
devices. If there are no faults on the branches, please locate the bus, the insulation
monitoring device and alarming relay.
Please locate the battery if there is no fault for the above all parts.
If loop earthed fault occurred to the DC system, the place where the current direction
changes is the fault position. (Please be noted that the current direction on the Clamp
should keep unchanged.)

91
Fig. 7.10 Single point earthed fault pinpointing process

Fig. 7.11 Multi points earthed fault pinpointing process

92
Fig.7.12 Loop earthed pinpointing process

Typical Waveforms
When the DC to earth distribution capacitance is high, the capacitive current will be high, this
will influence the measuring accuracy of branch resistive current, the grounding resistance
measurable will decrease. When the grounding resistance is high enough, the auto alarming
function will invalid, then we can only tell it is capacitive earth or resistive
earth through the waveform.
The character of waveforms is as follows:
A、Earthed branch
The waveform looks like rectangular, the rise and drop edge changes with the system to
ground capacitance, the higher the capacitance is, the change will be more flat. The less the
grounding resistance is, the bigger amplitude of the waveform will be, it is as Fig. 7.13
shows.

Fig.7.13 Waveform for branch earthed

93
B、High Capacitance with earthed branch
The rise and drop edge of the waveform changed sharply, the rise edge has spikes. The
higher the capacitance is, the sharper the spike is. While the less of the resistance, the
amplitude will be big, as Fig.7.14 shows.

Fig.7.14 Waveform for high Capacitance with earthed branch


C、High Capacitance without earthed branch
The rise edge is sharp, drop edge is flat. The higher of the capacitance, the amplitude is
bigger, it is as Fig.7.15 shows.

Fig.7.15 Waveform for High Capacitance without earthed branch


D、No earthed branch
The waveform is flat, almost like a straight line, it is as Fig. 7.16 shows.

Fig.7.16 Waveform for no earthed branch

94
Precautions
1) Connect the Transmitter with the bus or faulty branches, please pay attention to the
polarity, the red is to the Positive bus, the black is to the Negative bus, the green is to
the ground.
2) If there is fixed earth fault line selection device installed to the DC system, it should
power off it when we use the T-DCEFL for the fault detection, and also it is necessary
to take off the alarming relay to increase the detection accuracy.
3) Because the Clamp is with high sensibility, please keep it still, do not move or shake
it. Or, the magnetic field of the earth may influence the testing result.
4) The Receiver will auto power off if there is no operation within 60 minutes, it can
power off if the battery is too low.
5) Battery:- The Receiver is using built-in rechargeable lithium battery, please charge it
when the it is low. It takes 8 hours to charge it. If it is urgently needed, charge it for 10-
15 minutes, it can be operated for 30-50 minutes.
The Clamp uses high capacity alkaline battery, if the battery indication is
lighting, it shows that the battery needs to be replaced.
6) The Clamp cannot power off automatically, please power off it after using. If it cannot
be used for a long time, please take out the battery.

2. LEAKAGE CURRENT CLAMP METER


These are very much like the clamp meters used for measuring load currents, but deliver
significantly better performance when measuring currents below 5 mA.
PRINCIPLE OF OPERATION
When the jaws of a clamp meter placed around a conductor, it reads the value of current
depends on the strength of the alternating electromagnetic field surrounding the conductors.
When testing the grouped live conductors of a circuit, the magnetic fields produced by the
load currents cancel each other out. Any imbalance current comes from leakage from the
conductors to ground or elsewhere. To measure this current, a leakage clamp meter should
be able to read less than 0.1 mA.

Fig.7.17 Leakage current clamp meter

95
Tracing the source of leakage current

This method of measurements identifies the overall leakage and the source. The first
measurement can be made on the main conductor to the panel. Measurements 2, 3, 4 and 5
are made subsequently to identify circuits carrying the larger amounts of leakage current.

Fig.7.18 Use of Leakage current clamp meter

Leakage current can be an indicator of the effectiveness of insulation on conductors. It is


possible to locate the source of leakage current by using a low current leakage current
clamp to take methodical measurements as described above. To accurately measure low
current levels, it is essential that the mating faces of the jaws are protected from damage,
are kept clean and are closed completely together without an air gap when testing. Avoid
twisting the jaws of the clamp meter as this can cause erroneous measurements.

3. CONVENTIONAL LAMP METHOD

If DC earth leakage kit is not available then we can detect the leakage with the help of
tungsten lamp and low range DC ammeter or tong tester.

METHOD :-
If + ve is earthed in system than connect lamp between –ve and ground as shown in fig
7.19, If - ve fault is in system than put lamp between +ve and ground as shown in fig 7.20.

96
+VE

Bulb

-VE

Fig. 7.19 +Ve Bus earth

+VE

60/100 W
Bulb

-VE

Fig. 7.20 –Ve Bus earth


Procedure
I. First identify the faulty bus by measuring voltage.
II. Choose (switchable load) lamp rating according to the measureable current read by
tong tester.
III. According to the faulty bus make connection as shown in above fig 7.19 & 7.20.
Means put switchable load opposite to faulty bus at main distribution.
IV. Note the current read by tong tester at main distribution in load switch on condition
for reference Iref.
V. After measure the current switch off the load.
VI. Connect tong tester in feeder 1 as shown in fig 7.21 to measure the branch current
(I1). Now switch on the load connected at main distribution and measure the current
(I2). of the same feeder.

97
+VE

-VE

Tong tester TC
Tong tester Tong tester Tong tester Tong tester
ANN
Bulb
CLOSING

INDICATION
N
FEEDER 1 FEEDER 2 FEEDER 3 FEEDER 4 FEEDER 5

PATH FOR FAULTY CURRENT

Fig. 7.21 –Ve earth in indication ckt. of feeder 5


VII. Repeat the process explained in point VI if there is no difference in reading of I 1 I2.
VIII. If there is difference in reading of I 1 I2 then concentrate on the further DC distribution
of that feeder (like TC1/TC2, Ann & Indication etc).
IX. Now repeat the process explained in point VI for TC1/TC2, Ann & Indication etc of
identified faulty feeder.
X. Remove the identified earth point (check wire insulation, moisture, ann and TB
insulation) to get healthy DC status.
XI. In case of single point earth difference of I 1 I2 is equal to Iref. and for multi point earth
difference of I1 I2 is less than to Iref.

__________________________________________________________
.

98
CHAPTER-4
TESTING OF NUMERICAL DISTANCE PROTECTION RELAY WITH 3-
Ø SECONDARY INJECTION KIT
Er. Pradeep Raghav Er. Ashish Sharma

Equipments used:
Testing kit – PONOVO, Model PW460, Software – Powertest v2.22
Relay – GE, D-60, version 6.0X
A. COMMUNICATION OF TESTING KIT WITH LAPTOP –
Type of Communication - Ethernet
IP address (Kit Default) - 192.168.1.133
Laptop - IP = 192.168.1.199, Subnet mask = 255.255.255.0

To confirm the connection, open the Powertest software – setup – Aux DC


and set it to 48V, 110V, 220V DC as per choice and click ok. The LED on AUX DC
terminals will glow up. We can measure the DC voltage output of the kit by multimeter as
well.
Switch off the AUX DC following the same procedure as above.

99
Caution - If the DC output of the kit is being used for energizing a relay or anything
then first ensure that the DC terminals of kit are open (not connected) to that equipment as
the difference in voltage rating may affect the equipment.
We can also do the communication check by various other methods like
voltage injection, current injection etc., but since the Aux DC output is seldom used
hence it is preferred for communication check.

B. COMMUNICATION OF RELAY WITH LAPTOP –


Communication of relay to laptop may be done in various ways. Practically,
communication via serial port and Ethernet port is used. Following is a detailed table for
some of the mostly used relays in MPPTCL –

S. RELAY SOFTWARE & Communication Through


MODEL
NO. MAKE VERSION
Serial Ethernet

√ Possible in
ENERVISTA V.5.3 relay version
1. GE D 60 (straight
& ABOVE 6.0x and
cable) above


AGILE V.1.0 &
AREVA P441/442 (straight X
2. ABOVE
cable)

3. ABB REL- 670 PCM 600 X √

DIGSI V4.8 & √


4. SIEMENS 75A621 √
ABOVE (cross cable)

ACCELERATOR √
5. SEL 311C-2 √
QUICKSET (cross cable)


6. TOSHIBA GRZ-100 RSM-100 (straight X
cable)

100
C. CONNECTIONS BETWEEN KIT & RELAY –
For testing a distance protection relay, the relay must be provided secondary
injection of current and voltages. The testing kit has terminals for output of current and
voltage. These analog outputs may be connected to a relay via test terminal block (TTB)
or disconnecting type TBs in the panel. Connecting the kit to disconnecting type TBs is
preferred as these are the initial points for CT & PT in the panel. Injecting through these
points, full CT & PT circuit of the panel (up to the relay) is checked.

101
Disconnecting Type Terminal Blocks (TBs) – above

Test Terminal Block (TTB/RTB) – above

Test Terminal Block (TTB/RTB) – above

102
Test Plug – compatible with English Electric/ALSTOM make TTB - above

In addition to CT and PT, testing kit contains some output contacts (potential
free or energized) and digital inputs (potential free or energized).

Binary Inputs – These are the hardwired terminals which receive various information
e.g. CB status, Carrier Healthy status , Carrier received , air pressure / spring charged
status, Master trip relay contact etc .These inputs are then used in various logics which
assists protection scheme. So these inputs are tested by extending the station DC to
them sequentially and change in status is examined through software of the relay. Some
of the relays have provision for energizing these contacts through their auxiliary 48 V
DC, but in practice they are not used so correct DC voltage for inputs needs to be
configured.

Binary Output – These are the output contacts of the tripping relays. Some of the
outputs are heavy duty contacts which can be used to trip the CB directly while some are
less rated and are used to energize various trip/auxiliary relays. The binary/digital output
gets energized through various digital signals in the numerical relay or through some
sets of logics. Most of the numerical relays have provision for testing of these contacts
through their software which is called force closing of the binary output. All the binary
outputs have to be checked for proper operation i.e. whether N/O contacts are closing
and N/C contacts are opening using the multimeter.

103
AUX DC output & Binary Inputs Binary Outputs
These outputs and inputs may be used in various tests which will be
explained later in this write-up. A preview of the outputs and inputs available in the kit is
as follows –

104
Caution - Following checks must be done prior to connecting the kit in the panel
wiring –
1. It should be ensured that the disconnecting link is properly opened to isolate yard
connections to panel. Extra care is to be taken for shorting the CT in case of a line
having line side CT and is being fed from transfer breaker.
2. If testing through a TTB, proper isolation of yard and panel must be checked. In CT
terminals, there should be no continuity between yard side terminals and panel side
terminal. In PT terminals, there should be no phase to neutral or phase - phase
voltages present on panel side of TTB. The voltages must be zero at panel side and
normal system voltages at yard side.
3. Digital inputs to be provided in the kit must be checked that whether they are potential
free or energized. Special care must be taken as an energized input may damage the
input card of the kit if not properly programmed. However, it is always better to use
potential free inputs.
4. Inputs and outputs must be checked and to be duly programmed in the kit.

D. CHECKING HEALTHINES OF CONNECTIONS – After connecting CT, PT, outputs and


inputs from kit to relay, the healthiness of the same must be checked as the wrong
connections may damage the kit or the relay.
For this purpose, (4V, 3 I) module in Basic mode of the kit may be used.

105
Caution - After this we will start current and voltage injection hence, it is necessary to
remove any additional protection which may mal-operate. These protections may
be LBB, overload relay or bus-bar protection etc. Please ensure to remove LBB
links, overload relay links etc., so that operation of any protection in panel under
test does not cause mal-operation to any other feeder.
During this check, we will inject phase-wise voltages and currents from the kit
by following process –
1. Check that the magnitude voltages (Va, Vb & Vc) and currents (Ia, Ib & Ic) are zero
(0) and the phase angles are at balanced positive sequence i.e. 0, -120° & +120°.
2. Start the injection with null voltage and current by pressing run button or F2.

106
3. Check the voltage and current values in the relay. The relay must show zero voltages
and zero currents. These values may be checked on relay screen or at the human
machine interface (HMI) screen in relay software in laptop.
4. Change the magnitude of R-phase voltage as Va = 63.51 <0°
5. Check R-phase voltage in relay. There must be voltage in only R-Ø and rest all
phases must be zero. However, if in the relay only phase-phase voltages are available
on the screen; this will be reflected on the R-Y and B-R phase voltages. Checking
phase – neutral voltages will make it clear.
6. Change the magnitude of Y-Ø voltage as Vb = 63.51 <-120° and check in the relay.
Checking the phase difference along with phase is preferred.
7. Change the magnitude of B-Ø voltages Vc = 63.51 <120° and check in the relay along
with phase difference.
8. Change magnitude of R-Ø current as Ia= 0.2 <0° or any other value as desired. Check
the same in the relay.
9. Change the magnitude of Y-Ø current as Ib= 0.2 <-120°. Check the same along with
phase difference in the relay.
10. Change the magnitude of B-Ø current as Ic = 0.2 <120°. Check the same along with
phase difference in the relay.
11. Stop the injection by pressing stop button or ESC.

During this check, if there is any deflection in any of the six quantities, it may
be checked and eradicated at this point of time only, otherwise it will lead to erroneous
testing and confusing results.

107
E. ZONES REACH TESTING – This is also known as Zone Verification Test or Reach
Accuracy Test. All Numerical DPRs are equipped with 3 Forward Zones and 1 Reverse
zone. Extra Zones may also be there. During this test, currents and voltages are fed
through the testing kit so as to simulate the faults in various zones. Operations of the
relay at maximum reach or at the boundary of the zones are checked and it is verified
that the reach of the relay is as per the settings provided. The operations of the various
binary outputs are tested. This test is carried out at the line angle. This test will be done
to check the different forward and reverse zones of impedance protection.
Since, our CT, PT injection is ready, the impedance protection will be tested
using Z-PHI module under protection mode of the kit. Different types of relays may use
different type of characteristics but testing them with Z-PHI module will not make any
deviation in results because we will do the testing along line angle only. For more
accurate testing, we can take the RIO file (with .rio extension) or predefined templates of
PONOVO kit for each separate relay.

Continuing with the Z-phi module, there is a “Setting” bar at the bottom of test
area as shown in figure –

108
Here, we should fill up the ohmic values in Z <Ø form.
LN Zone1 = LL Zone1=Impedance of zone-1
LN Zone2 = LL Zone2=Impedance of zone-2
LN Zone3 = LL Zone3=Impedance of zone-3
LN Zone4 = LL Zone4=Impedance of zone-4
LN T1 = LL T1= time delay of zone-1 = 0 msec.
LN T2 = LL T2= time delay of zone-2
LN T3 = LL T3= time delay of zone-3
LN T4 = LL T4= time delay of zone-4.
Since, zone 5 is not used in any of the protection; it must be set to any value
with a very high operating delay.
The last value “PHI” is of line angle. The fixed values are as follows –
132 KV → 68.03°
220 KV → 78.69°
400KV → 84.90°

Besides setting bar there is a “parameter” bar, as shown in the figure below.

109
Preferred setting are as follows –
Pre-fault time → 1.0 sec
Post-fault time → 0.100 sec
Trigger Mode → Time
PT at → Line/Bus (whichever is the case)
CT Polarity → Line
CB Sim. → No
Test Mode → Iconst.
K0 number →1
KE given as → K (0), phi (K0) or Z0/Z1
Vz define →0
Iload → 0.20 Amps
Iload ph → 30°

Typical values of earth fault compensation are as follows –

132 kV 220 kV 400 kV


Sr. No. Type of value
(Panther ACSR) (Zebra ACSR) (Moose

110
ACSR)

K0, Phi K0
1 Resembles to 0.754 <10.07° 0.753 <-0.72° 0.863 <-13.40°
{(Z0-Z1)/3Z1}

2 Z0/Z1 3.25 <7° 3.26 <-0.5° 3.59 <-9.75°

Besides parameter bar, there is “Binary” bar in which we can set the digital
inputs and outputs for the relay. The preferred settings are as follows –

Now, the setup is ready for impedance testing.


Following steps must be followed to set the test point – (This will be done only once)
1. In the testing panel, open the quick add menu.
2. In Z1, Z2, Z3, Z4, uncheck all the boxes for 0.95 or 1.05 and tick on only one box
related to zone-1 at 0.95. Edit the value from 0.95 to 0.98.
3. Make current to be injected as 2 Amps.
4. Tick on assessment.
5. Enter line angle related to voltage level of the line (as mentioned in settings
menu).
6. Fault mode → transient
7. Fault type → A-Z
8. Click ok.
9. Remove all the other test points if present except this point on the test panel.

111
# ZONE – 1 Testing – Since, only one test point is available, make sure that
checkbox against test point name is ticked (√).
For zone-1 testing, follow the procedure below –
1. Check that IZI =0.98 ᵡ Zeset1. This shows that the fault to be fed will be at the
test point which is 98% of zone-1, PHI= line angle as mentioned in setting menu.
2. Set the fault type → AE, BE, CE, AB, BC or CA.
3. Set the fault time to 0.100 sec (or may be any other value but less than Z-2
delay).
4. Set current = 2 Amps.
5. Set directions as forward (as this is a forward reach zone).
6. Fault mode = Transient
7. Start the test by pressing RUN or F2.
8. Check all the fault indications and fault values on the relay.
9. The fault distance must be equal to 98% of zone-1 reach. (e.g. In most of the
cases zone-1 is 80% of line length so, the fault distance of this test point must be
0.98 ᵡ 0.80 ᵡ line length).
10. Repeat this testing at 98% of zone -1 for rest of phases i.e. B-E, C-E, A-B, B-C,
C-A.
11. Now, we will check the boundary point of Zone-1 by injecting 105% of Zone-1
impedance which is basically a zone-2 fault. But the injection time must be less
than zone-2 delay. So, this will confirm that for a zone- 2 fault, the relay is not
tripping before zone-2 relay.
For this, set IZI = 1.05 ᵡ Zeset1, with rest all setting same.
For this fault the relay must not be for all six faults i.e. AE, BE, CE, AB, BC, CA.

112
12. The results may be tabulated as follows –

ZONE-1 A-E B-E C-E A-B B-C C-A


Fault distance
at 98%
No tripping checked
at 105%

Caution – In some relays, while testing 105% fault, SOTF protection may operate. So, it is
advised to disable SOTF if it is operating and enable it positively at the end of testing.

# ZONE – 2 Testing – The same test point of zone-1 will be modified for zone-2
testing. The procedure is as follows –
1. Edit the value of │Z│=0.98 × Zeset2.
2. Change the fault time to (0.100+Z-2 delay) or may be any other but less than Z3
delay.
3. Rest all the setting will be same.
4. Start the testing for all six faults and tabulate the results as mentioned previously.

113
# ZONE – 3 Testing – The procedure is as follows –
1. Edit the value of │Z│=0.98 × Zeset3.
2. Change the fault time to (0.100+Z-3 delay).
3. Reset all setting will be same.
4. Start the testing for all six faults and tabulate as mentioned previously.

# ZONE – 4 Testing – The procedure is as follows –


1. Edit the value of │Z│= 0.98 × Zeset4.
2. Change the fault time to (0.100+Z-4 delay).
3. As Zone-4 is a reverse zone, set the direction to reverse.
4. Reset all the setting will be same.
5. Start the testing for all six faults and tabulate as mentioned previously.

Note – SEL relay prefers to use Zone-3 as reverse reach and Zone-4 as longest
forward reach. If this is the case, then for testing of Zone-3, direction must be set to
reverse and fault time must be set to (0.100+Zone-3delay) and Zone-4 to be tested
likewise.

114
In the end of the zone reach testing, this template may be saved so that
during next testing all the setting of parameters can be avoided. For this, click on
“Task” (on the top menu bar) and select “save as template file (F)” rename the file
with extension “.tpl” and save in the required folder.
F. CARRIER AIDED TRIPPING TEST – Distance protection is a three stepped protection
in which Z1 reach is normally set to be 80 % of the main line. Remaining 20% of the line
is covered in Z2 which is a time delayed protection. In order to reduce the time of the
operation carrier aided protection is used.

When the fault is within the line A-B but out of the reach of zone-1 of end A, it will be in
zone-1 reach of remote end B, hence, remote end relay will send a permissive carrier
command to end A.
Under Permissive Under Reach (PUR) scheme the relay at end B sends the
signal (as the fault is in zone 1) to end A and on receipt of the signal from End B and Z2
pick up at end A the relay operates in Z1 time. DPR of end A is waiting for Zone-2 delay
to elapse and then trip it in zone-2, but as soon as carrier command is received, end A
also trips the breaker instantaneously, hence clearing the fault.
This protection is based on the principle that “if the fault is within the line then
why zone-2 delay?”
For testing of this protection the steps are as follows –
1. Energize the carrier receive input of the relay using output contact of the kit or
external shorting lead. For using output contact of the kit , in the Binary setting,
make setting as follows –

Out 1 = close
Output mode = time
Output time = 0.050 (50 msec)
Output hold time= 0.050 (50 msec)
DC +ve must be connected to Terminal-1 of output -1. Terminal-2 must be
connected to carrier receive input of the relay.

115
2. Inject a zone-2 fault with delay less than zone-2 delay. The condition of 105% of
zone-1 for 0.100 msec can be used.
3. For this fault, the relay must trip and the indications (LED, facia annunciator)
must be checked likewise.
4. Feedback timer may be used to check whether the relay is tripping before zone-2
delay. Settings for feedback timer are as follows –
In Binary setting bar, set Binary input 1 as Trip ABC and connect a potential free
contact of DPR or 86 Master Trip relay Input-1 of the kit.
Binary In.1 = Trip ABC, Trip Sel. = 1234
5. This test must for all phases - AE, BE, CE, AB, BC & CA.

G. SWITCH ON TO FAULT (SOTF) TEST – This protection is provided to trip the line as
soon as the line is charged to a persisting fault. Numerical relays have different logics for
SOTF condition. But the essential condition is closing of the line and rise of the current
and/or Z2 pick up. For testing of SOTF this condition is simulated by feeding a Z2 fault or
over current condition and creating the condition of line charging utilizing the binary
inputs for this purpose.

If a line is charged from end A and there is a fault persisting in the line, either it will fall in
Zone-1 reach or it will fall in the remaining section which is in Zone-2 reach from end A.
Hence, this test is checked for both Zone-1 and Zone-2.
The process is as follows –
1. Energize the “CB close” input signal of the relay using kit output contact or TNC
switch or external shorting. Settings for binary output are mentioned previously.
Set output time= 0.00 sec, Set output hold time= 0.100 sec
2. Inject a Zone-1 fault with fault time of 0.100 sec (or less than zone-2).
3. Check for indications of SOTF operated along with trip time via feedback using
binary inputs.
4. Inject a Zone-2 fault with delay less than Zone-2 delay.
5. Check for indications of SOTF operated along with trip time via feedback using
binary inputs.

116
H. AUTO-RECLOSE OPERATION AND LOCKOUT TESTING – Experience reveals that
the majorities of the faults is single phase to ground faults and are of transient nature.
So, complete isolation of the line for such types of the faults will cause interruption of the
power. Hence, it is an established practice to give one attempt for closing after dead time
and tripping for successive / permanent fault. This is known as single phase single shot
auto-reclosing feature and is adopted for 400 and 220 kV lines. This test should be
carried out when all other tests have been carried out including tripping of the CB and
pole wise operation of the breaker. Auto-reclose operation is programmed to counter
transient faults present in the line. This protection activates whenever a zone-1 phase-to-
ground fault occurs in the system.
To test this protection, two terms have to be understood first. They are –
1. Dead time – As the relay senses a zone-1 phase-to-ground fault, it operates
instantaneously and trips the faulty phase only. After some time a close
command is given by the relay which closes the breaker. This time duration
between generation of trip command for faulty phase and generation of close
command is Dead time.
Generally, Dead time= 1sec (1000 msec).
2. Reclaim time – When close command is given by the relay, the tripped pole
closes and the relay senses “All poles ON” condition through auxiliary contacts.
Now, if any type of fault (even a phase-to-ground fault of zone-1) comes again
within a specified period of time, the relay gives a 3-∅ trip command and makes
all 3-poles of the CB to OFF condition.
This specific time is known as Reclaim time.
Generally, reclaim time = 25sec.

• Conditions for Auto reclosing –


1. Breaker must be suitable for single pole operation.
2. Breaker must have sufficient energy /power for tripping, closing and subsequent
tripping if necessary. This is termed as CB healthy condition.
3. Status of the Carrier must be healthy. Some of the carrier panels have output of
Carrier Fail condition. So, depending on the requirement of the numerical relay,
this may be inverted to satisfy the relay requirement.
4. Pole discrepancy (PDR) time of the relay must be larger than the Dead Time of
relay. As Dead time is 1 sec, PDR delay must be set as 1.1sec or more.
5. Breaker must have remained closed before tripping.

117
6. Only one pole of the CB must get opened.
7. There is an auto-reclose switch in the panel which has two positions IN or OUT.
This switch must be IN for successful auto-reclosure.
8. There is a carrier IN/OUT switch. This must be in IN condition. Sometimes carrier
healthy/fail and carrier IN conditions are clubbed together.
9. Absence of any other auto-reclose block condition e.g. Operation of B/U relay,
B/B operation, Phase to phase operation, SOTF operation etc.

• Conditions for auto reclose blocking –


1. Successive fault in reclaim time. Reclaim time is set as 25 sec and if any fault
develops within reclaim time it will lead to three phase tripping even if the fault is
of single phase.
2. Phase to phase fault, three phase fault, Bus-Bar fault, SOTF condition, Z2 or Z3
faults.
3. Back up relay operation, over voltage, LBB operation.
4. Any faults occurring within reclaim time after manual closing of the line.

Testing procedure for Auto-reclose is as follows –


1. Close the CB. Check the status of all 3 poles of the CB in the relay. They all must
be ON.
2. Check the local/remote switch condition in the CB. Auto-reclosure operates only
in Remote condition.
3. Check for carrier IN/out switch in the panel. Carrier protection must be IN.
4. Inject a Zone-1 phase-to-ground fault preferably R-∅.
5. R-∅ pole of the CB will trip and will close automatically after set dead time.
6. Wait for reclaim time to elapse, i.e. more than 25 sec.
7. Now inject Y-∅ fault and check for CB operation of Y-∅ pole only.
8. Again after reclaim time, check for B-∅ fault.
9. As soon as auto-reclosure is checked for B-∅, inject any of the phase-phase or
phase –ground fault before reclaim time.
10. All 3-poles of the CB will trip confirming a lockout condition.

118
Testing procedure for Auto-reclose for new spare relays during commissioning or
programming –

The schematic diagram is as follows –

Following additional equipments are required for this test –


1. 1 no. Master Trip Relay having operating as well as resetting coil. Spare CT
switching relay may be used if available.
2. If above set-up is not available, 2 nos. Master trip relays (Hand reset type) are
required.

The test will be conducted by following procedure –


1. Connect the operating coil A to the R-∅ pole trip output.
2. Connect the NC contact as feedback of R-∅ pole.
3. Connect the resetting coil to Auto-reclose close command output.
4. Connect the NO contact as feedback of R-∅ pole.
5. Make contact status of Y-∅ and B-∅ permanently energized.
6. Inject a Phase-to-ground fault of Zone-1.

119
7. The trip output will get activated and hence coil A operates.
8. This opens the contact and the relay senses that the R-∅ pole got opened.
9. After Dead time, the Auto-reclose close output closes and operates coil B.
10. The NO contact becomes close and the R-∅ pole status is again active which
confirms the Auto-reclose condition.
11. If the coil B is not operating after Dead time, either the relay is not giving 1-∅ trip
command (providing a 3-∅ definite trip) or it is not giving a close command. This
must be checked by oscillography and correction in settings must be done.
12. Similar tripping must be checked for Y-∅ and B-∅.
13. After testing for all 3 phases a lockout command must also be checked to trip all 3
poles of the CB.

I. Power Swing Blocking (PSB) Test – Power Swing Blocking is a function which blocks
the operation of the relay in between a definable impedance range. This function senses
the rate of change of impedance during a fault and when the impedance crosses the
outer boundary, it resets. Generally, PSB blocks the operation of DPR in Zone-2 & Zone-
3 and trips in Zone-1. A descriptive figure is as follows –

120
As the figure shows, power swing may be set in a Two-step mode or Three-
step mode.

For testing of this feature, State sequence (4V, 3I) module under Basic mode is used.

121
The procedure for testing is as follows –
1. Add the number of states using “ADD” button in the test panel.
2. For a Two-step PSB, keep 3 no. states as follows –
a. Outside outer circle,
b. Between outer and inner,
c. Inside inner circle.
3. For a Three-step PSB, keep 4 no. states as follows –
d. Outside outer circle,
e. Between outer and middle,
f. Between middle and inner
g. Inside inner circle.
4. Now, referring to the settings provided in the relay, the impedance and time
delays will be set in each state.
5. Click on the first state in the test panel and then open “Fault Cal” menu.
6. Set the fault type as required: AE, BE, CE, AB, BC, CA.
7. Feed the impedances in Z-phi form or R-X form. This impedance must be more
than the outer circle impedance.
8. Set test mode as “I constant”.
9. Set test current as 2 Amps or any appropriate value.
10. Set I-load = 0.2 Amps, with some power angle (say 30°). This will be the load
current in rest of the phases.
11. Set earth fault compensation if the fault fed is a phase-to-earth fault as mentioned
previously. Click OK

12. Now, the respective values of secondary voltages and currents will be shown
automatically.

122
13. Check frequency to be 50 Hz.
14. Trigger mode is “Time”.
15. Set duration as 5 sec to 10 sec.
16. Set ext. time to 0.00 sec. Settings for first state are complete.

17. For second state, click on the name of second state and open Fault Cal menu.
18. Set the impedance value between outer circle and inner circle. Rest all values will
be same. Click OK.
19. Set duration of the fault equal to or more than the delay provided in the relay
setting.
20. Similarly, set the states for other PSB zones.
21. After setting all states, click on the first state and start the Test. This will inject the
impedances in predefined states for given duration.
22. Operation may be checked by taking feedback timer and configured LEDs.
J. Load Encroachment test – This feature indicates the condition of increasing load with
decrease in voltage.

123
It must be checked that the reach of load encroachment impedance is kept more
than longest forward reach (Zone-3). Generally, 80% of voltage and 120% of current
values at an angle of 30° are taken for impedance calculation. For testing of this feature,
State sequence (4V, 3I) module under Basic mode is used.

124
The procedure for testing is as follows –
1. By default, two states are present – Prefault and Fault. In prefault state, feed
balanced voltages and balanced currents for a delay of 5 sec to 10 sec.
2. In the fault state, open the Fault Cal menu and provide impedance less than
provided in the relay setting.
3. If in the relay, the setting is not in the impedance form, the secondary voltages
and current values may be set and injected for a particular duration.
4. If in the relay, the settings are not in the impedance form, normal three phase
voltage and current are fed to the relay. The current of the relay is increased to
1.2 times and voltage is reduced to 0.80 p.u. at an angle of 30 Deg Lag. The
relay should not operate at this loading condition. The relay must operate on
increase in current and decrease in voltage.
5. Feedback timer must be taken to check the actual time of operation and must be
compared with the time provided in the relay settings.
K. Broken conductor test – If in a live line, one phase conductor gets broken and it is well
beyond any fault creating condition, there will be no indication of the fault. Only, the
current of that particular phase will become zero due to open circuit. But, this condition
will generate negative sequence currents in the line.

125
The relay setting for broken conductor feature is nothing but a negative
sequence over-current element with a timer feature. For testing of this feature, Quick test
(4V, 3I) module under Basic mode is used.
The procedure for testing is as follows –
1. Set the voltages to normal balanced voltages as follows –
Va = 63.51 <0°, Vb = 63.51 <-120°, Vc = 63.51 <120°
2. Set the currents of all three phases to zero and the angles must be positive
sequence as 0°, -120° & 120°.
3. In the “Quantity” menu, select any two phase currents say Ia, Ib.
4. Set step = 0.1 Amp.
5. Now, run the test and keep increasing the set value of currents using up and
down arrows (on keyboard) / buttons (on test panel).
6. The value at which the broken conductor operates is the approximate value of
when one phase gets open circuited.

The above procedure may be adopted when we are injecting positive


sequence currents and the delay in operation of broken conductor element is
zero. If we want to check the protection with negative sequence currents and to
check the delay also, the procedure is as follows –
1. Set the voltages to normal balanced voltages as above.
2. Change the sequence of currents to “negative sequence” by right clicking in
“angle” values of current and make all 3 magnitudes to zero.

126
3. Set the known value of pickup as the step value.
4. Select Quantity as Ia, Ib, Ic and Run the test.
5. Lock the present test values by clicking on the lock icon in the test panel.
6. Increase the current values to the set pickup value using up arrows of keyboard
or up button in the test panel. The values may be seen in the magnitude.
7. Unlock the test panel to inject the changed values.
8. The timer will start increasing and will stop as soon as the feedback is received.
6. The indication may be checked and the delay shown by the feedback timer must
be checked to be in accordance to the delay provided in the setting.

L. VT Fuse Fail Test – Numerical relays have different logics for ascertaining the condition
of fuse fail. Under this condition the relays are programmed to block the operation of
impedance protection, otherwise there may be false operation in case of any fuse fail or
loose connection. Three phase current and voltages are fed to the relay and one of the
voltage say of R phase is reduced to simulate the condition of the fuse fail to check that
the VTFF element of the relay operates to block the operation of the relay. Some of the
relays use CB auxiliary contact in logic for VTFF.
For testing of this feature, Quick test (4V, 3I) module under Basic mode is
used.
The procedure for testing is as follows –
1. Set the voltages to normal balanced voltages as follows –
Va = 63.51 <0°, Vb = 63.51 <-120°, Vc = 63.51 <120°.
2. Set the currents of all three phases to 0.2 Amps as follows –
Ia = 0.2 <0°, Ib = 0.2 <-120°, Ic = 0.2 <120°.
3. In the “Quantity” menu, select voltage of any phase say Va.
4. Set step = 30 volts or a greater value may be taken.
5. Run the test.
6. Lock the present test values by clicking on the lock icon in the test panel.
7. Decrease the voltage value using down arrows of keyboard or down button in the
test panel. The values may be seen in the magnitude.
8. Unlock the test panel to inject the changed values.
9. The timer will start increasing and will stop as soon as the feedback is received.

M. Overvoltage Operation Test – Over-voltage protection is basically used for 400 kV


lines as these lines are having very high voltage level and are mostly of very long
lengths. Hence, if the line is charged at one end only or is very lightly loaded, the

127
voltages at other end increase remarkably due to Ferranti effect. However, this
protection may also be available as stand-alone external relays; most of the Numerical
relays also do have the feature for this protection. This protection may be provided in
phase-to-earth, phase-to-phase or 3-phase mode, along with or without a delay.
For testing of this feature, Quick test (4V, 3I) module under Basic mode is
used.
The procedure for testing is as follows –
10. Set the voltages to normal balanced voltages as follows –
Va = 63.51 <0°, Vb = 63.51 <-120°, Vc = 63.51 <120°.
11. Set the currents of all three phases to 0.2 Amps (or any other load current) as
follows
Ia = 0.2 <0°, Ib = 0.2 <-120°, Ic = 0.2 <120°.
12. In the “Quantity” menu, select voltage of any phase say Va (in case of phase-to-
earth mode), or any two phases say Va, Vb (in case of phase-to-phase mode), or
all the 3 phases Va, Vb, Vc (for 3-∅ mode).
13. Set step = “x” volts. This “x” may be calculated as follows –
e.g, the setting is for 110% of Phase-phase voltage with a delay of 4 sec. Then,
Quantity = (Va,Vb) or (Vb, Vc) or (Vc, Va)
Step = (110% X 63.51) – (63.51) = 6.4 Volts.
14. Run the test.
15. Lock the present test values by clicking on the lock icon in the test panel.
16. Increase the voltage value using up arrows of keyboard or up button in the test
panel. The values may be seen in the magnitude.
17. Unlock the test panel to inject the changed values.
18. The timer will start increasing and will stop as soon as the feedback is received.

Annexure – 1: Per km impedances of different type of conductors.


Copper +ve seq. Zero seq.
Sr. Conducto
equivalen impedance Impedance
No. r
t R-X form Z-phi form R-X form Z-phi form
0.1603 + 0.3603 +
1 Panther 0.200 0.4286
1.3951 <75°
j0.3975 <68.03° j1.3478
0.0795 + 0.2702 +
2 Zebra 0.400 0.4053 1.3209
j0.3975 <78.70° j1.2930 <78.20°
0.0280 + 0.2914 +
3 Moose 0.650 0.3180 1.1410
j0.3168 <84.90° j1.1028 <75.20°

________________________________________________________________
128
CHAPTER-5

TESTING OF NUMERICAL DIFFERENTIAL PROTECTION


RELAY WITH 3-Ø SECONDARY INJECTION KIT

Er. Pradeep Raghav Er. Chandrabhan Kushavh Er. Ashish Sharma

Equipments used:
Testing kit – PONOVO, Model PW460, Software – Powertest v2.22
Relay – GE, T-60, version 6.0X

Following Heads are same as explained in DPR testing procedure:-


A. COMMUNICATION OF TESTING KIT WITH LAPTOP
B. COMMUNICATION OF RELAY WITH LAPTOP
C. CONNECTIONS BETWEEN KIT & RELAY
D. CHECKING HEALTHINES OF CONNECTIONS – During DPR testing, we injected 1
set of voltages and 1 set of currents. In Differential testing, 1 more set of current for second
winding may also be injected. However, we will do this during stability testing

Following Tests are performed for a differential relay:-


E.DIFFERENTIAL STABILITY TEST – This test is performed to check the stable
conditions during normal current flow in the transformer.
To conduct the test, Quicktest (4V, 6I) module under Basic mode may be used.

129
The process is as follows –
1. Set all three phases of current output -1 to the value calculated as explained later.
2. Set all three phases of current output -2 to the value calculated as explained later.
Maintain proper phase difference as per the case between the two currents as
explained later.
3. Run the test.
4. The relay must show the primary or secondary currents on the screen or software
HMI. The values must be confirmed to be in order.
5. This is a no-trip condition and the same must be confirmed.

The calculations for current to be injected are as follows –


Example-1 – 40 MVA, 132/33 kV Xmer, HV CTR = 400/1, LV CTR = 800/1. Current
output-1 (Ia, Ib, Ic) will be used in HV side and Current output-2 (Ia’, Ib’, Ic’) will be used
in LV side.
Ia = (HV side Full load Current) ÷ (HV side CT Ratio)
Ia = 175 ÷ 400 = 0.4375 <0°,
Similarly, Ib = 0.4375 <-120° & Ic = 0.4375 <120°.
Ia’ = (LV side Full load Current) ÷ LV side CT Ratio
Ia’ = 700 ÷ 800 = 0.875 <180°,
Similarly, Ib’ = 0.875 <60° & Ic’ = 0.875 <300°.

130
Any other set of currents may also be used but care must be taken for the
Transformation Ratio and CT Ratio on both sides. LV side currents are shifted by 180° to
maintain Transformer action.

Example-2 – 315 MVA, 400/220/33 kV Xmer, HV CTR = 1000/1, IV CTR = 1200/1, LV


CTR = 1000/1.

Case-1 – Stability between HV & IV:-


Current output-1 (Ia, Ib, Ic) will be used in HV side and Current output-2 (Ia’, Ib’, Ic’) will
be used in IV side.
Ia = (HV side Full load Current) ÷ HV side CT Ratio
Ia = 455 ÷ 1000 = 0.455 <0°,
Similarly, Ib = 0.455 <-120° & Ic = 0.455 <120°.
Ia’ = (IV side Full load Current) ÷ IV side CT Ratio
Ia’ = 827 ÷ 1200 = 0.689 <180°,
Similarly, Ib’ = 0.689 <60° & Ic’ = 0.689 <300°.

Case-2 – Stability between HV & LV:-


Current output-1 (Ia, Ib, Ic) will be used in HV side and Current output-2 (Ia’, Ib’, Ic’) will
be used in LV side.
Ia = (HV side Full load Current) ÷ HV side CT Ratio
Ia = 455 ÷ 1000 = 0.455 <0°,
Similarly, Ib = 0.455 <-120° & Ic = 0.455 <120°.
Ia’ = (LV side Full load Current) ÷ LV side CT Ratio
Ia’ = 5511 ÷ 1000 = 5.511 <210°,
Similarly, Ib’ = 5.511 <90° & Ic’ = 5.511 <330°.
Any other set of currents may also be used (considering the limitations of continuous
current flow in kit or relay, otherwise scaling on both sides may be done) but care must
be taken for the Transformation Ratio and CT Ratio on both sides. IV side currents are
shifted by 180° to maintain Transformer action. LV side currents are shifted by 210° to
maintain Transformer action for an 11 Delta winding.

E. DIFFERENTIAL PICK-UP TEST – This test is performed to check the un-biased


region of the differential slope. This setting defines the minimum differential current
required for operation. It is chosen, based on the amount of differential current that
might be seen under normal operating conditions. Two factors may create differential

131
current during the normal transformer operation: errors due to CT inaccuracies and
current variation due to on-load tap changer operation. Generally, pick-up = 0.15 to
0.25.

Caution – In some relays, while testing differential protection, REF protection may operate if
used as a low impedance REF. So, it is advised to disable REF if it is operating and
enable it positively at the end of testing. Similarly, disable other elements which
may operate and take utmost care to enable them at the end of testing.
To conduct the test, Quicktest (4V, 6I) module under Basic mode may be used.
HV Pick-up
1. Set all three phases of current output-1 and output-2 to zero.
2. In the Quantity tab set the parameter as Ia, so that only HV side current increases.
3. Step = 0.01 Amps.
4. Run the test.
5. Increase the value of R-∅ current by up arrow in keyboard or up button on test
panel.
6. Note the current at which the relay trips.
7. Similarly test for Y-∅ and B-∅.
8. The results may be tabulated as follows –

132
Differential Currents Restrained currents
Current
HV Pick-up
Injected
Id-R∅ Id-Y∅ Id-B∅ Ir-R∅ Ir-Y∅ Ir-B∅
Current
injection on
HV R-∅
Current
injection on
HV Y-∅
Current
injection on
HV B-∅

LV Pick-up
1. Set all three phases of current output-1 and output-2 to zero.
2. In the Quantity tab set the parameter as Ia’, so that only LV side current increases.
3. Step = 0.01 Amps.
4. Run the test.
5. Increase the value of R-∅ current by up arrow in keyboard or up button on test
panel.
6. Note the current at which the relay trips.
7. Similarly, test for Y-∅ and B-∅.
8. The results may be tabulated as follows –

Differential Currents Restrained currents


Current
LV Pick-up
Injected
Id-R∅ Id-Y∅ Id-B∅ Ir-R∅ Ir-Y∅ Ir-B∅
Current
injection on
LV R-∅
Current
injection on
LV Y-∅
Current
injection on
LV B-∅

Check – To check that the value of injected current at which the relay is tripping,
calculations are as follows:-
Iinjected = 1.5 X (Full load current ÷ CT Ratio) X pick-up setting. (for 1-∅ current injection).
Iinjected = (Full load current ÷ CT Ratio) X pick-up setting. (for 3-∅ current injection).

133
F. DIFFERENTIAL SLOPE TEST – When an external fault causes a heavy current to
flow through the protected zone, differences in the magnetic characteristics of the
current transformers on both sides undergo the conditions of saturation and may cause
a significant current flow through the differential measuring element coil. If it is greater
than the respective pickup threshold, the device can trip even though no fault occurred
in the protected zone. Current restraint (stabilisation) prevents such erroneous
operation. In differential protection systems for protected objects with two terminals, a
restraining quantity is normally derived from the current difference |I1 – I2| or from the
arithmetical sum |I1| + |I2|. Both methods are equal in the relevant ranges of the
stabilisation characteristics. For protected objects with more than two ends, such as
multi-winding transformers, busbars etc, only the arithmetical sum method is possible.
For 2 measuring points, tripping or differential current is –
Idiff = |I1 + I2|, and the stabilisation or restraining current Istab = |I1| + |I2|.
The current sum definition is extended for more than 2 measurement locations, example
of a three-winding power transformer with 4 measuring locations,
Idiff = |I1 + I2 + I3 + I4|
Istab = |I1| + |I2| + |I3| + |I4|
Idiff is derived from the fundamental frequency current and produces the tripping effect
quantity, Istab counteracts this effect.
To conduct the test, Quicktest (4V, 6I) module under Basic mode may be used.

The process is as follows –


1. Set all three phases of current output -1 to zero.

134
2. Set all three phases of current output -2 to zero.
3. In the Quantity tab set the parameter as Ia’. This will increase the current for LV
winding only.
4. Step = 0.01 Amps.
5. Set the value of Ia to a random value. (preferably 0.5 to 1.0)
6. Set the value of Ia’ according to transformation ratio and CT ratio alongwith proper
phase angles to have a stabilized condition
7. Run the test.
8. Increase or decrease the value of LV R-∅ current (Ia’) by up arrow in keyboard or
up button on test panel.
9. Note the current at which the relay trips.
10. Similarly test for Y-∅ and B-∅.
11. The results may be tabulated as shown previously.

Check – To check that the relay has tripped in the slope-1 region, the ratio of differential
current to restraining current during tripping must be calculated. This must be equal
to the slope value.
Slope = (Differential current ÷ Restraining current).
Generally, Slope-1 = 20% and Slope-2 = 50%.

N. UNRESTRAINED DIFFERENTIAL PICK-UP TEST – High current faults in the


protected zone may be cleared instantaneously without regard to the restraint currents.
Fast tripping uses both the fundamental component of the differential current as well as
instantaneous values. Instantaneous value processing ensures fast tripping even if the
current fundamental component was strongly attenuated by current transformer
saturation.
So, this protection operates comparatively faster than normal differential
element, whenever there is current more than the set value in the differential coil. This
protection is irrespective of harmonics in the current. .
To conduct the test, Quicktest (4V, 6I) module under Basic mode may be used.
1. Set all three phases of current output-1 and output-2 to zero.
2. In the Quantity tab set the parameter as Ia, so that only HV side current increases.
3. Set Step as the setting of unrestrained differential element.
4. Run the test.
5. Lock the test values by clicking on the lock icon.

135
6. Increase the value of R-∅ current by up arrow in keyboard or up button on test
panel.
7. Unlock the test values.
8. Similarly test for Y-∅ and B-∅ and for LV side as well.

G. 2nd HARMONIC BLOCK TESTING – Even-harmonic elements (second and fourth


harmonic) provide security against inrush currents during transformer energization.
However, 2nd harmonics are more dominant and 4 th harmonics are negligible. In
transformers and shunt reactors in particular, high short-time magnetising currents may
be present during power-up (inrush currents). These currents enter the protected zone
but do not exit it again. They thus produce differential quantities, as they seem like
single-end fed fault currents. Also during parallel connection of transformers, or an over-
excitation of a power transformer, differential quantities may occur due to magnetising
currents caused by increased voltage and/or decreased frequency. The inrush current
can amount to a multiple of the rated current and is characterised by a considerable 2 nd
harmonic content (double rated frequency), which is practically absent during a short-
circuit. If the second harmonic content in the differential current exceeds a selectable
threshold, tripping is blocked by the differential current threshold. Generally, 2nd
Harmonic setting = 20%.

To conduct the test, Quicktest (4V, 6I) module under Basic mode may be
used. The process is as follows –
1. Set all three phases of current output -1 to zero.
2. Set all three phases of current output -2 to zero.
3. In the Quantity tab set the parameter as Ia’, Ib’, Ic’. This will increase all the three
current for LV winding simultaneously.
4. Step = 0.1 Amps.
5. Click on the frequency tab. A new window will open as follows –

6. In this window, uncheck the “Equal for all” option.

136
7. Change frequencies of Ia’, Ib’, Ic’ to 100 Hz i.e. 2 nd harmonic.

8. On the relay terminals, take out current output-2 from LV winding and connect it in
parallel to current output-1 (phase-wise) so that both current sources feed only HV
winding.
9. Set all the six currents to 1 Amps value as follows –
Ia = 1.0 <0°, 50 Hz Ia’ = 1.0 <0°, 100 Hz
Ib = 1.0 <-120°, 50 Hz Ib’ = 1.0 <-120°, 100 Hz
Ic = 1.0 <120°, 50 Hz Ic’ = 1.0 <120°, 100 Hz
10. Decrease the set quantities using down arrow/button.
11. The relay must not trip until the 100 Hz current magnitude comes down to 0.2
Amps. This shows 2nd harmonic blocking upto 20%.

H. 5th HARMONIC BLOCK TESTING – Steady-state overexcitation is characterised by


odd harmonics. The 3rd or 5th harmonic is suitable to detect overexcitation. As the 3rd
harmonic is often eliminated in transformers (e.g. in a delta winding), the fifth harmonic
is more commonly used. Converter transformers also produce odd harmonics which are
practically absent in the case of an internal short-circuit. The differential currents are
analysed for harmonic content. For frequency analysis digital filters are used which
perform a Fourier analysis of the differential currents. As soon as the harmonics' content
exceeds the set thresholds, a restraint of the respective phase evaluation is started. The
filter algorithms are optimised for transient behaviour such that additional measures for

137
stabilisation during dynamic conditions are not necessary. This setting is provided to
block the differential protection during overexcitation. When the 5th harmonic level
exceeds the specified setting (5th harmonic ratio) the differential element is blocked.
The overexcitation inhibit may work on a per-phase basis or combined 3 phase basis.
Generally, 5th harmonic setting = 40%.

To conduct the test, Quicktest (4V, 6I) module under Basic mode may be used. The
process is as follows –
1. Set all three phases of current output -1 to zero.
2. Set all three phases of current output -2 to zero.
3. In the Quantity tab set the parameter as Ia’, Ib’, Ic’. This will increase all the three
current for LV winding simultaneously.
4. Step = 0.1 Amps.
5. Click on the frequency tab. A new window will open as follows –

6. In this window, uncheck the “Equal for all” option.


7. Change frequencies of Ia’, Ib’, Ic’ to 250 Hz i.e. 5 th harmonic.

138
8. On the relay terminals, take out current output-2 from LV winding and connect it in
parallel to current output-1 (phase-wise) so that both current sources feed only HV
winding.
9. Set all the six currents to 1 Amps value as follows –
Ia = 1.0 <0°, 50 Hz Ia’ = 1.0 <0°, 250 Hz
Ib = 1.0 <-120°, 50 Hz Ib’ = 1.0 <-120°, 250 Hz
Ic = 1.0 <120°, 50 Hz Ic’ = 1.0 <120°, 250 Hz
10. Decrease the set quantities using down arrow/button.
11. The relay must not trip until the 250 Hz current magnitude comes down to 0.4
Amps. This shows 5th harmonic blocking upto 40%.

I. VOLTZ PER HERTZ TESTING – The overexcitation or overfluxing protection is used


to detect increased overflux or overinduction conditions in generators and transformers,
especially in power station unit transformers, which cause impermissible temperature
rise in the iron. An increase in induction above the rated value leads very quickly to
saturation of the iron core and to large eddy current losses which cause impermissible
temperature rise in the iron. Overexcitation occurs when a transformer magnetic core
becomes saturated. When this happens, stray flux is induced in nonlaminated
components, causing overheating. The overexcitation protection picks up when the
permissible limit of induction is exceeded in the core of the protected object (e.g. power
station unit transformer). The overexcitation protection measures the ration
voltage/frequency U/f, which is proportional to the induction B in the iron core (with
invariable dimensions).

139
The maximum of the three phase-to-phase voltages is decisive for the
calculation. The overexcitation protection includes two definite time stages. As soon as a
threshold (warning stage U/f >) has been exceeded, the pickup indication is output and a
timer starts. A warning message is transmitted subsequently to the expiration of this
timer. This is used as V/f Alarm. As soon as a second threshold (warning stage U/f >>)
has been exceeded, another pickup indication is output and a timer T U/f >> starts. A trip
command is issued subsequent to the expiration of this timer. This is used as V/f Trip.

Generally, V/f Alarm = 112%, delay = 15 sec &


V/f Trip = 115%, delay = 12 sec.
We can test this by varying either voltages or frequency or both. However, testing by
varying voltages and keeping frequency constant is always an easy deal. So, this
method is explained below.
For testing of this feature, Quick test (4V, 3I) module under Basic mode is used. The
procedure for testing is as follows –
For V/f Alarm –
19. Set the voltages to normal balanced voltages as follows –
Va = 63.51 <0°, Vb = 63.51 <-120°, Vc = 63.51 <120°.
20. Set the currents of all three phases to 0.2 Amps (or any other load current) as –
Ia = 0.2 <0°, Ib = 0.2 <-120°, Ic = 0.2 <120°.
21. In the “Quantity” menu, select voltage of any phase say Va (in case of phase-to-
earth mode), or any two phases say Va, Vb (in case of phase-to-phase mode), or
all the 3 phases Va, Vb, Vc (for 3-∅ mode).
22. Set step = “x” volts. This “x” may be calculated as follows –
e.g, the setting is 112% with a delay of 15 sec. Then,
Quantity =Va or Vb or Vc or (Va,Vb) or (Vb, Vc) or (Vc, Va) or (Va, Vb, Vc)
Step = (112% X 63.51) – (63.51) = 7.63 Volts.

140
23. Run the test.
24. Lock the present test values by clicking on the lock icon in the test panel.
25. Increase the voltage value using up arrows of keyboard or up button in the test
panel. The values may be seen in the magnitude.
26. Unlock the test panel to inject the changed values.
27. The timer will start increasing and will stop as soon as the feedback is received.

For V/f Trip –


1. Set the voltages to normal balanced voltages as follows –
Va = 63.51 <0°, Vb = 63.51 <-120°, Vc = 63.51 <120°.
2. Set the currents of all three phases to 0.2 Amps (or any other load current) as –
Ia = 0.2 <0°, Ib = 0.2 <-120°, Ic = 0.2 <120°.
3. In the “Quantity” menu, select voltage of any phase say Va (in case of phase-to-
earth mode), or any two phases say Va, Vb (in case of phase-to-phase mode), or
all the 3 phases Va, Vb, Vc (for 3-∅ mode).
4. Set step = “x” volts. This “x” may be calculated as follows –
e.g, the setting is 115% with a delay of 12 sec. Then,
Quantity =Va or Vb or Vc or (Va,Vb) or (Vb, Vc) or (Vc, Va) or (Va, Vb, Vc)
Step = (115% X 63.51) – (63.51) = 9.53 Volts.
5. Run the test.
6. Lock the present test values by clicking on the lock icon in the test panel.
7. Increase the voltage value using up arrows of keyboard or up button in the test
panel. The values may be seen in the magnitude.

141
8. Unlock the test panel to inject the changed values.
9. The timer will start increasing and will stop as soon as the feedback is received.

J. RESTRICTED EARTH FAULT TESTING – The Restricted Earth Fault (REF)


element is used to provide sensitive protection against ground faults in wye-connected
transformer winding. The element is “restricted” in the sense that protection is restricted
to ground faults within a zone defined by neutral and line CT placement. REF protection
is a technique for sensitive detection of ground faults in a grounded wye-connected
transformer winding. Because it employs a neutral CT at one end of the winding and the
normal set of three CTs at the line end of the winding, REF protection can detect only
ground faults within that particular wye-connected winding. For REF to function, the line
end CTs must also be connected in wye, because the technique uses comparison of
zero-sequence currents. Delta-connected CTs cancel out all zero-sequence
components of the currents, hence, eliminating one of the quantities which the REF
element needs for comparison. REF feature may be used as High Impedance or Low
Impedance.
The restricted earth fault protection detects earth faults in power transformers,
shunt reactors, neutral earthing transformers/reactors, or rotating machines, the starpoint
of which is led to earth. It is also suitable when a starpoint former is installed within a
protected zone of a non-earthed power transformer. A precondition is that a current
transformer is installed in the starpoint connection, i.e. between the starpoint and the
earthing electrode. The starpoint CT and the phase CTs define the limits of the protected
zone exactly.
Generally, the internal element in numerical relays is Low Impedance type.
Low impedance restricted earth fault –
Low impedance REF is based on comparing the vector sum of the phase
currents of the transformer winding to the neutral point current.
The differential and bias currents are calculated from the current variables
after scaling the phase currents. In a biased differential relay, the through current is
measured and used to increase the setting of the differential element. For heavy through
faults, one CT in the scheme can be expected to become more saturated than the other
and so differential current can be produced. However, biasing increases the relay setting
so the resulting differential current is insufficient to cause operation of the relay.

142
143
REF on an earthed transformer winding - above

REF on an earthed shunt reactor with CTs in the reactor leads - above

144
REF on an earthed auto-transformer – above
Testing of Low impedance REF – The testing of low impedance REF is just an overcurrent
test on the NCT terminals of the relay. The testing of this feature is very simple as
compared to the concept. For testing of this feature, Quick test (4V, 3I) module under
Basic mode is used. The procedure for testing is as follows –
7. Connect the current output of the kit to the REF NCT terminals in the relay.
8. Set the currents of all three phases to zero.
9. In the “Quantity” menu, select the phase currents of which the terminals are
connected in Step-1.
10. Set step = 0.01 Amp.
11. Now, run the test and keep increasing the set value of currents using up and
down arrows (on keyboard) / buttons (on test panel).
12. The value at which the REF operates must be checked with the setting provided,
keeping the CT ratio in mind.

High impedance restricted earth fault – An external resistor is required to provide


stability in the presence of saturated line current transformers. The high impedance
REF protection works on the high impedance circulating current principle. When
subjected to heavy through faults the line current transformer may enter saturation
unevenly, resulting in unbalance. To ensure stability under these conditions a series
connected external resistor is required, so that most of the unbalanced current will
flow through the saturated CT. As a result, the current flowing through the relay will
be less than the setting, therefore maintaining stability during external faults.
Sample calculations for a High Impedance REF are as follows –

145
146
Testing of High impedance REF – The testing of high impedance REF is also done by
injecting current terminals of the relay. Only care to be taken is to bypass/short the
stabilizing series resistance. For testing of this feature, Quick test (4V, 3I) module under
Basic mode is used. The procedure for testing is as follows –
1. Connect the current output of the kit to the terminals in the relay.
2. Set the currents of all three phases to zero.
3. In the “Quantity” menu, select the phase currents of which the terminals are
connected in Step-1.
4. Set step = 0.01 Amp.
5. Now, run the test and keep increasing the set value of currents using up and
down arrows (on keyboard) / buttons (on test panel).
6. The value at which the REF operates must be checked with the setting provided,
keeping the CT ratio in mind.

Annexure-I – Sample calculations for SEL 387E relay

147
148
149
150
Annexure-II – Sample characteristics for SIEMENS relay –

151
Annexure-III – Sample characteristics for P64X relays –

152
CHAPER-6
LBB PROTECTION
Er. P.K. Gargava

LBB (Local breaker block scheme) scheme is an important scheme of protection


system. If during a fault circuit breaker doesn’t operate then fault is cleared by all incoming
sources by LBB scheme. Without LBB scheme the fault will cleared from remote end in
second or third zone time and thus fault clearing time will increase.
Nowadays most of the numerical relays are having inbuilt LBB feature or breaker failure
feature. If bus bar protection scheme is provided at substation then BB scheme can
incorporate LBB scheme of individual feeders. There are two methods by which LBB
scheme can be implemented:-
A. LBB scheme of feeder/XMER C&R panel relays DPR/Differential is used but tripping
command is issued through BB scheme.
B. In this method LBB feature of Individual feeder/ transformer panel is not used. Only
LBB initiation signal is sent to BB scheme for each tripping by individual
feeder/transformer C&R panel’s master relay then BB protection panel’s logic relay
is used for LBB operation and for issuing trip command. This facility is available in
GE make BB relays.
Settings for LBB scheme:-
A. Setting of current-100% or full load current
B. Setting of Timer for LBB- 200ms
C. Input of breaker status-(optional)
D. Input of Master relay/ tripping relay-
To test LBB scheme if is already commissioned at SS then links of tripping to feeders
should be removed to avoid unwanted tripping. Follow steps as under:-
Method A- scheme is tested on individual panel.

Timer current Breaker status LBB operation


210ms 110% ON Yes
190ms 110% ON NO
210ms 90% ON NO
210ms 110% OFF No

Method B
-Similar test is performed on BB scheme logic relay

Note:- Use re-trip feature of scheme if it is available in scheme time setting for re-trip can me
100ms.

153
CHAPTER-7
BUS-BAR PROTECTION
Er. P.K. Gargava

In our system nowadays we are using numerical Bus-bar protection scheme. The
scheme is comprising of 3 nos. single phase low impedance BB differential relays. The bus-
bar scheme is also having separate LBB element or it can be used for giving signals to
tripping relays when LBB initiation command is received.
The BB relays are tested phase wise. The numerical test kits which we are using are
having 6 current outputs. The following tests are to be carried out on BB scheme:-
1. Differential pickup, bias test and Directional feature of relay for each phase
2. Stability test of all feeders phase wise
3. BB operation for Bus-1, Bus-2, Transfer bus and check zone.
4. CT selection incomplete
5. CT switching
6. CT ALARM for bus-1
7. BUS-1 & Bus-2 Interconnected
8. Voltage block feature
9. LBB operation

1. Differential pick up and bias test is tested by procedure given in testing of Diff
relay. Current can be injected in input terminal of any one feeder.

2. To check Directional feature in Bus- I inject current as under:-

NON-OPERATION MODE

FDR Name of feeder Current BB operation Tripping


connected on injected
Bus
Bus-1 FDR-1 1.0 Amp Angle Bus-bar is N
0 deg stable
BUS-1 FDR-2 0.5 Amp Angle N

154
100 deg
BUS-1 FDR-3 0.5 Amp Angle N
100 deg

OPERATION MODE

FDR Name of feeder Current BB operation Tripping


connected on injected
Bus
Bus-1 FDR-1 1.0 Amp Angle Bus-bar Y
0 deg operated
BUS-1 FDR-2 0.5 Amp Angle Y
80 deg
BUS-1 FDR-3 0.5 Amp Angle Y
80 deg

3. STABILITY TEST OF BUS-BAR SCHEME:-

Before testing keep voltage input below set limit say 90% or disable voltage block
feature of scheme:-

Inject current as under as under:-

FDR Name of feeder Current BB operation Tripping


connected on injected
Bus
Bus-1 FDR-1 3.0 Amp Angle Bus-bar is N
0 deg stable
BUS-1 FDR-2 1.0 Amp Angle N
180 deg
BUS TIE FDR-3 2.0 Amp Angle N
180 deg
BUS-2 FDR-4 1.0 Amp Angle N
180 deg
BUS-2 FDR-5 1.0 Amp Angle N
180deg

Bus tie current will show import in Bus-1 and export in Bus-2. The direction is
dependent on CT connections. If showing reverse and both bus are in unstable
condition then injected current angle is to be changed from 0 Degree to 180 degree.
This stability test is to be performed for all feeders.

4. Operation of BB relay
BUS-1 or ZONE-1
Inject current as under as under:-
FDR Name of feeder Current BB operation Tripping
connected on injected
Bus
Bus-1 FDR-1 1.0 Amp Angle Bus-1 or Zone- Y
0 deg 1 will operate

155
BUS-1 FDR-2 1.0 Amp Angle Y
0 deg
BUS TIE FDR-3 2.0 Amp Angle Y
180 deg
BUS-2 FDR-4 1.0 Amp Angle N
0 deg
BUS-2 FDR-5 1.0 Amp Angle N
0 deg

BUS-2 or ZONE-2
Inject current as under as under:-
FDR Name of feeder Current BB operation Tripping
connected on injected
Bus
Bus-1 FDR-1 3.0 Amp Angle Bus-2 or Zone- N
0 deg 2 will operate
BUS-1 FDR-2 1.0 Amp Angle N
0 deg
BUS TIE FDR-3 2.0 Amp Angle Y
0 deg
BUS-2 FDR-4 1.0 Amp Angle Y
0 deg
BUS-2 FDR-5 1.0 Amp Angle Y
0 deg

Direction of Bus tie current will be reversed.

TESTING OF OTHER FEATURES

A. CT Selection Incomplete:
In stable BB change the Bus of any feeder from Bus-I to Bus II or Bus-II to Bus-I by
selection of bus isolator switch. The CT selection incomplete alarm will appear. Bus-1 & Bus-
2 will pick up but Check Zone will not Pickup.

B. CT Alarm for BUS-1 or BUS-2:


If any CT in Bus-1 is shorted or bypassed or High current is injected during Primary
or secondary injection. Then Bus-1 will Pick up but do not operate (due to directional
feature), Check zone will also pick up.
Similar operation can be checked for Bus-II
C. BUS-1 AND BUS-2 INTERCONNED
If Both Bus side isolator of any feeder is closed then Bus-I & Bus-II interconnected
window will appear and in case of any bus fault both bus will operate. To check this feature
close replica of isolators of Bus-I and Bus-II and inject currents for BB operation, feeders of
both buses will trip.
D. VOLTAGE BLOCK FEATURE:

156
This feature is very important but setting should not be very low. Keep voltage healthy
and test BB for fault. It will not operate or will not issue trip command. Then reduce
voltage below setting value say 90% and test for BB fault condition, now relay will
issue trip command.
E. LBB operation:-
1. If BB is used only for issuing trip command then give initiation on any feeder
of say Bus-I and check that all feeders of Bus-1 and Bus tie master trip relays
will operate.
2. If LBB scheme of BB of is used then with initiation of LBB signal we have
ensure that set current is there in that particular feeder. If current is below set
limit LBB will not operate.

_________________________________________________________________________

157
CHAPTER-8
POWER LINE CARRIER AIDED TRIPPING

Er. Rajesh Shandilya Er. Pradeep Raghav

Various Carrier protection Schemes are being used for Tripping the circuit
simultaneously from both the ends; for Line Protection, Over voltage Protection,
Hand Tripping, Busbar Protection, LBB Protection.
Distance protection of line is a stepped protection and instantaneous element
(Zone1) covers (usually) 80% of the line.
Thus 40% of line 20% from each end is covered under Zone2 protection and any
fault in this region shall be cleared in Zone2 time from either end.
Carrier protection is a way by which the information of Zone1 f ault for either end is
conveyed to other end for simultaneous tripping from both ends. Simultaneous
tripping allows the sufficient time for arc extension which is prime criteria for
successful Auto-reclosure operation from both ends.
In the absence of carrier tripping, sequential tripping shall take place for faults
beyond Zone1 time causing
1. Fault to be fed from one end up to Z2 time.

2. Re-closure shall be attempted before arc extension resulting in three phases tripping.

3. A temporary fault may become permanent fault.

Two types of Carrier protection Schemes are commonly used


1. Permissive Tripping Scheme
(For Line Protection)

2. Direct Tripping Scheme


(For Over Voltage Protection, Hand Tripping, Busbar Protection, LBB Protection)

Permissive Tripping Schemes


Permissive transfer tripping is the most frequently used scheme for the protection of
transmission lines. The transfer tripping link between the protection equipment at the
ends of the line ensures that all faults can be cleared in the time of the first zone
along 100% of the line. In a permissive scheme, the transfer tripping signal from the
Protection Coupler is connected in series with a local criterion (protection starting,

158
directional decision or phase selection) and tripping can only take place at the
receiving end, if a transfer tripping signal is being received and the local protection
relay detects a fault in the direction of the protected line. The reception of a spurious
tripping signal caused by interference on the communications channel cannot
therefore give rise on its own to unwanted tripping. On the other hand, a delayed
transfer tripping signal may mean that a fault on the line is tripped in the time of zone
2 instead of un-delayed in zone 1.
High dependability and short transmission time theref ore take priority over security in
a permissive scheme.
The following configuration and settings of the most important parameters are
recommended for all permissive transfer tripping schemes, i.e. under-reaching and
over-reaching distance protection and directional comparison:
Command transmission: a, b (un-coded)
Transmission time: Approx- 12 ms
Security: Step1
Command prolongation: 20 ms
Guard channel (pilot): 100 Baud

Direct Transfer Tripping

Typical applications for direct transfer tripping are breaker back-up protection,
compensator protection and power transformer protection; line protection with direct
transfer tripping would be an exception. The requirements with respect to
transmission time are generally not too demanding.

In the case of direct transfer tripping, the tripping command from the tele-protection
equipment goes directly to the circuit-breaker tripping coil. Thus a spurious tripping
signal resulting either from interference or human error will cause unwanted, usually
three-phase tripping of the line and will block the operation of any auto-reclosure
relay.

159
A genuine transfer tripping signal, on the other hand, must on no account be lost
whether there is interference on the communications channel or not, because then a
line fault would not be isolated with correspondingly serious consequences.

Extremely high security and high dependability are therefore more important than
transmission time for direct transfer tripping.

In order to fulfill these requirements, the Protection Coupler uses coded tripping
signals for direct transfer commands. Coded signals provide the necessary
additional security against incorrect interpretation of speech, audio signals coupled
into the system and incorrect manipulations on the equipment.

The following configuration and settings are recommended for breaker back-up
protections, compensator protection and power transformer protection (but not for
steady-state signals):

Command transmission: c, d (coded)


Transmission time: Approx. 26 ms
Security: Step 2
Command prolongation: 100 ms min.
Guard channel (pilot): 100 Baud

With the above settings, a signal-to-noise ratio of about 6 dB is necessary for


successful transmission of tripping commands. The rate of spurious commands for
noise bursts of 200 ms duration and the worst possible signal-to-noise ratio is
theoretically always less than about 10-20 . Since this extremely high level of
security is achieved without blocking the unit, the Protection Coupler is capable of
tripping without intentional delay at any time as soon as a signal-to-noise ratio of
about 6 dB is regained.

160
Permissive under reach scheme

161
Direct trip scheme
Direct trip command is initiated by following incidents
1. Hand tripping
2. LBB operation
3. Bus-bar operation
4. Over voltage relay
The scheme is generally used in 400KV feeders and 220 KV interstate feeders. Two
carrier channels are used to transfer direct trip signals.

____________________________________________________________________

162
CHAPTER-9

TESTING OF OVERCURRENT & EARTH-FAULT RELAY

WITH 3-Ø SECONDARY INJECTION KIT

Er. Ashish Sharma

Equipments used:
Testing kit – PONOVO, Model PW460, Software – Powertest v2.22
Relays used –
1. Make – AVANA, Model – NPA422 ( Non-directional Relay - 51/51N)
2. Make – JVS, Model – JNP 098 (Directional Relay - 67/67N)

O. INTRODUCTION – The objective of overcurrent protection is to prevent excessive


current flow in an electric power circuit from damaging the circuit or surroundings. The
term “excessive current flow” refers to the flow of a current whose value greatly exceeds
the nominal full-load current of the circuit, like the current resulting from a short-circuit.
Overcurrent protection works by first detecting excessive current flow in the protected
circuit and then opening the path through which the excessive current flows as quickly
as possible.
An overcurrent relay can have an inverse time-current characteristic similar to
that of a fuse or a thermal circuit breaker. In an overcurrent relay, the inverse time-
current characteristic is adjustable in current and time (via current and time settings
respectively). An overcurrent relay with an inverse time current characteristic is
commonly referred to as an inverse definite minimum time (IDMT) overcurrent relay.
The current transformers that feed the inputs of any overcurrent relay no
longer operate linearly when they are subjected to high current levels (e.g., currents
exceeding 10 times the current setting of the relay), thereby leading to a significant error
in the measured value of current. Such an error in the measured value of current leads
directly to a significant error in the operating time of any IDMT overcurrent relay. To
avoid errors in the relay operating time at high current levels, most digital or numerical
IDMT overcurrent relays stop following their inverse characteristic and pass to a definite
time characteristic when the current reaches more than about 8 times (this setting is
adjustable) the current setting of the relay.

163
Equations for calculation of TMS for IEC Curves -above

Equations for calculation of TMS for IEEE Curves –above


The IDMT overcurrent relay stops following the inverse characteristic and
passes to a definite time characteristic when the current reaches 20 times the current
setting of the relay. The time setting of the definite time characteristic (i.e., the definite

164
minimum time) is equal to the time value calculated using the equation of the inverse
characteristic and a current value of 20 times the current setting of the relay.
Following is a table providing the time of operation for different types of
curves. Some of the IDMT Curves correspond to IEC standards and the other are of
IEEE standards.

Above chart shows the time of operation for a current multiplier from 2 times
to 20 times (of set PSM value) with a TMS of 1.0. To get the time of operation at any
other TMS (say “x”), the time must be multiplied by “x” for the corresponding current
multiplier and curve.
Example – If PSM = 100% or 1.0 with TLS = 0.05 in a curve of 1.3 sec NI.
The time of operation for current 5 times the PSM will be –
1.86X0.05 = 0.093 sec or 93 millisec.
It must be noted here that the name of the curve resembles to the time of
operation at Current multiplier = 10 and TLS = 1.0.
Despite being classified as Electromechanical, Static or Numerical (on the
basis of their manufacturing components), the IDMT relays can be classified as Non-
Directional and Directional (on the basis of their principle of operation).
Following are the tests performed on these relays –
1. Pick-up test.
2. Inverse characteristics test.

165
3. High set element test.
4. Directional operation test (on directional relays).

Caution – Following care must be taken while testing the relays:


1. Any type of over-load protection must be disconnected while testing the relays.
Otherwise it may mal-operate and trip other feeders without any cause.
2. If LBB feature of back-up relay is being used, then it must be either disabled or LBB
isolation link must be disconnected to avoid any mal-operation.
3. If the feeder is on Transfer Bus Coupler and CTs are line side, proper shorting of CT
at yard side terminals must be ensured. If the relay is a draw-out type the shorting
strip must be healthy. However, additional shorting is always suggested.

P. PICK-UP TEST – Basically Pick-up test is performed for electromechanical relays.


Theoretically, “The first electrical test made on the relay should be a pickup test. Pickup
is defined as that value of current or voltage which will just close the relay contacts from
the 0.5 time-dial position. Allowing for such things as measuring instrument differences
and interpretations of readings, this value should be within ± 5 percent of previous data.
Reset the relay to the original time-dial setting and check at two points such as 3 and 5
times pickup. Always use the same points for comparison with previous tests.”
For numerical relays there is no time-dial etc, so a current must be gradually
increased in definite steps. The LED for R-∅, Y-∅ or B-∅ and the LED for Overcurrent or
Earth-fault must glow up.
For example, if the set PSM for an overcurrent relay is 1.0 then the relay must
pick-up at a current value of 1.1 to 1.2 Amps secondary.
For this test, Quicktest (4V, 3I) module under Basic mode may be used.
Following picture shows a Numerical Non-Directional Back-up relay having
phase-wise LEDs and separate LEDs for O/c & E/f indication.

166
Q. INVERSE CHARACTERISTICS TEST – This will be the test for IDMT curve
protection of the relay. This test will be performed separately for Overcurrent and Earth-
fault elements.

167
For testing of this feature, Quicktest (4V, 3I) module under Basic mode is
used.

Testing Overcurrent element – The procedure for testing is as follows –


For a relay having O/c PSM = 0.75, TLS = 0.30, curve 3.0 sec NI.
13. Set all the 3 phase voltages in the kit to zero – (as they are not required)
Va = 0 <0°, Vb = 0 <-120°, Vc = 0 <120°.
14. Set all the 3 phase currents in the kit to zero –
Ia = 0 <0°, Ib = 0 <-120°, Ic = 0 <120°.
15. Define the binary input for feedback timer under Binary tab. Connect a contact of
back-up relay (preferably potential free) on that timer. Contact of Master trip relay (86)
or Aux. Master trip relay (86X) may also be taken but the feedback timer will show the
time of operation of (back-up relay + master trip relay)
16. For checking the time of operation at 2 times of PSM, make settings as follows –
Quantity = Ia, Ib (for a R-Y phase fault, this can be changed later).
Step = 1.5 Amps (as 2 times of 0.75 PSM is 1.5 Amps).
17. Make angle of Ia =0° and angle of Ib = 180°. It may be other value of angles but the
phase difference must be of 180° to simulate it as a phase-to-phase fault.
18. Run the test with zero current values.
19. Lock the present values by Lock Button.
20. Increase the magnitude of Ia, Ib by up arrow/button.
21. Unlock the test panel.

168
22. The timer will start and will stop as soon the feedback is received on defined and
connected binary input.
23. Check the correctness of this timing. As in this case, the time of operation at 2 times
PSM and TLS = 1 for 3.0 sec NI is 10.03 sec.
So, for TLS = 0.30, it will be 10.03X0.30 = 3.009 sec.
The feedback timer must show a value very close to this value.
24. The results may be tabulated as follows –
O/c fault fed for Time recorded Time recorded Time recorded

(phase) for 2XPSM for 3XPSM for 4XPSM

R-Y

Y-B

B-R

Testing Earth-fault element – The procedure for testing is as follows –


For a relay having E/f PSM = 0.30, TLS = 0.30, curve 3.0 sec NI.
1. Step No. 1, 2 and 3 will be same as for overcurrent testing.
2. For checking the time of operation at 2 times of PSM, make settings as follows –
Quantity = Ia (for R-∅ to earth fault, this can be changed later).
Step = 0.60 Amps (as 2 times of 0.30 PSM is 0.60 Amps).
3. Make angle of Ia =0° or any other as for a single phase to earth fault, the angle of
injected current will not make any issue unless the relay is Directional.
4. Rest all steps will be same as those used for overcurrent testing.
5. The results may be tabulated as follows –
E/f fault fed for Time recorded Time recorded Time recorded

(phase) for 2XPSM for 3XPSM for 4XPSM

R-N

Y-N

B-N

169
Electromechanical relays must be tested for TLS = 1.0 as well to check
proper operation of disc, spring and other moving or non-moving parts of the relay.
However, Numerical relays may be tested at service settings only.
A standard format for testing of electromechanical relays is as follows –

R. HIGH-SET ELEMENT TEST – High-set feature in backup relays is provided to clear


the faults having excessively high current. These types of faults have to be necessarily

170
cleared in less than a definite time. Otherwise, that high current may affect the
transformer feeding the fault. Damage to line equipments is another possibility.
This high-set feature is of a definite minimum time (DMT) type. A very
important aspect is to check the pick-up as well as drop-out of this element. This
element must drop-out as soon as the actuating quantity (current) comes below the
High-set setting. This is necessary for the relays installed at the current source
(transformer incomings) for the fault on a feeder. If the fault has been cleared timely by
feeder relay, then the high-set element of the source relay must drop-out as soon as
possible to avoid any mal-operation.
Following are the images showing the settings for overcurrent highest as
400% for a delay of 100 millisec.

For testing of this feature, State Sequence (4V, 3I) module under Basic mode
must be used.

171
For example, the settings high-set are as follows –
PSM = 400% or 4.0
Delay = 0.10 sec or 100 millisec

The procedure for testing is as follows –


23. Add the number of states using “ADD” button in the test panel.
24. Keep 3 no. of states as follows –
Pre-fault, Fault and trip, & Drop-out.
25. Define the binary input for feedback timer. Connect a contact of back-up relay
(preferably potential free) on that timer.
26. In the pre-fault state, set all the 3 phase currents to balanced load currents as follows

Ia = 0.5 <0°, Ib = 0.5 <-120°, Ic = 0.5 <120°.
27. Set the time of this stage to a definite time, say 5 sec by setting Trigger condition =
Time, Duration = 5 sec.
28. In the fault and trip state, set all the currents to make a fault, say phase-to-phase
fault as follows –
Ia = 4.2 <0°, Ib = 4.2 <180°, Ic = 0 <0°.
Remember that this current value must not be much higher than High-set
pick-up value. This will help in checking the accuracy of high-set pick-up.
29. Set the time of this stage to stop by feedback input Trigger condition = Bin. Inputs.
30. In the drop-out state, set all the currents to a value less than high-set pick-up value
as follows –
Ia = 3.5 <0°, Ib = 3.5 <-120°, Ic = 3.5 <120°.

172
Remember that this current value must not be much lower than High-set pick-
up value. This will help in checking the accuracy of high-set drop-out.
31. Set the time of this stage to stop by feedback input Trigger condition = Bin. Inputs.
32. Set ext. time to 0.00 sec for all 3 states.
33. After setting all states, click on the first state and start the Test. This will inject the
states in the order and the time of operation and drop-out will be shown on the screen.
34. For settings done in the relay as shown above, the fault and trip state must stop at
around 110 millisec and drop-out must come after approx 20 millisec.

Caution – While testing High-set element the TLS of IDMT element must be
increased to a sufficient value so that the IDMT element doesn’t operate while
testing the High-set feature.

S. DIRECTIONAL OPERATION TEST (only for directional relays) – Directional


overcurrent and earth-fault protection is mostly used in 220 kV & 400 kV feeders. If fault
current can flow in both directions through a relay location, it is necessary to add
directional control to the overcurrent relays in order to obtain correct discrimination.
Typical systems which require such protection are parallel feeders and ring main
systems. Generally, the relays use one of the two options available for deciding the
direction of fault –
1. Zero sequence polarizing - The relay performs a directional decision by
comparing the phase angle of the residual current with respect to the inverted
residual voltage:
(–Vres = – (Va + Vb + Vc)) derived by the relay.
2. Negative sequence polarizing - The relay performs a directional decision by
comparing the phase angle of the derived negative sequence current with respect
to the derived negative sequence voltage.

Generally, the angle for directional operation must be set between 30° to 60°.

173
For testing of this feature, Quicktest (4V, 3I) module under Basic mode may
be used. The procedure of testing is as follows –
For a relay having E/f PSM = 0.30, TLS = 0.30, curve 3.0 sec NI.
1. For testing of directional earth-fault feature, set the voltage of faulty phase to a low
value, say 40 Volts to provide polarizing. Rest two phases must be normal –
Va = 40 <0°, Vb = 63.51 <-120°, Vc = 63.51 <120°.
2. Set all the 3 phase currents in the kit to zero –
Ia = 0 <0°, Ib = 0 <-120°, Ic = 0 <120°.
3. Define the binary input for feedback timer under Binary tab. Connect a contact of back-
up relay (preferably potential free) on that timer. Contact of Master trip relay (86) or
Aux. Master trip relay (86X) may also be taken but the feedback timer will show the
time of operation of (back-up relay + master trip relay)
4. For checking the time of operation at 2 times of PSM, make settings as follows –
Quantity = Ia (for a R-phase fault).

174
Step = 0.60 Amps (as 2 times of 0.30 PSM is 0.60 Amps).
5. Run the test with zero current values.
6. Lock the present values by Lock Button.
7. Increase the magnitude of Ia by up arrow/button.
8. Unlock the test panel.
9. The timer will start and will stop as soon the feedback is received on defined and
connected binary input.
10. Check this earth-fault operation for different angles of current. The relay will operate
for 180° in forward direction. This 180° span will depend on the directional angle fed to
the relay. For example, if the directional angle is set to 30°, then the relay will operate
from (30+90) = 120° to (30-90) = -60° or 300°.
11. Similarly check the operations for Y-∅ & B-∅ and overcurrent element as well.

175
176
________________________________________________________

177
CHAPTER-10
EHV CIRCUIT BREAKERS
Er. P.K. Gargava

Circuit Breaker is a switching device capable of making, carrying and breaking\currents


under normal circuit conditions and also making, carrying for a specified time breaking
currents under short circuit conditions. Circuit breakers of the types indicated below are
being presently used in our system.
36 kV - Vacuum and Sulphur hexa fluoride (SF6)
145 kV and 245 kV - Sulphur hexa fluoride (SF6)
420 kV - Sulphur hexa fluoride (SF6)
Ratings of circuit breakers:-

Pre-commissioning and routine test of Circuit breaker in field

1. Capacitance and Tan delta of CB Voltage Grading Capacitor'

178
Circuit Breaker grading capacitors have oil filled paper capacitor elements. The
healthiness of the capacitor elements could be checked by measurement of Capacitance
and Tan delta.
Test Procedure:-
Connect LV cable to the middle of the double interrupter. Connect HV cable to the other end
of the Grading capacitor to be tested. The opposite ends of the grading capacitor have to be
grounded using earth switch. Before applying HV, interference is to be nullified using
Interference suppression unit (ISU). Measurements have to be taken in UST Mode only.
Disconnect the HV cable and connect the same to the other grading capacitor and ground
the previous grading capacitor. Now the second grading capacitor is ready for testing.
Standard procedure (as specified by kit supplier) for measuring capacitance and tan delta in
charged switchyard/induced voltage conditions should be followed. Carry out the
measurements in main and reverse mode/polarity and then compute the average value.
Evaluation of Test Results
Increase in the value of tan a will indicate Chemical deterioration due to age and
temperature, including certain cases of acute deterioration due to localized overheating,
Contamination by water, carbon deposits, bad oil, dirt and other chemicals or ionization. The
acceptable value is 0.007 but any increase in tana and any change in capacitance value is
to be analysed.
2. Dew Point Measurement of SF6 Gas
Dew Point is the temperature at which moisture content in SF6 gas/air starts condensing.
Dew Point when measured keeping regulating valve in service at the outlet of dew point kit
to allow required flow rate of gas/air, is called low point at rated pressure of CB.
Dew Point at Atmospheric pressure
Dew point when measured by regulating the gas flow. at the inl et of dew point kit and
keeping outlet regulating valve (if provided) in fully open condition so that flow rate of gas is
maintained as required, is called low point at atmospheric pressure.
Test Equipment
Dew point measuring kit and associated accessories.
Testing Procedure
All the joints/connectors should be dust and moisture free. If required, same should be
cleaned by clean cloth. Dry the joints and pipe by dry air. Make the connections to the kit
from CB pole ensuring that regulating valve is fully closed at the time of connections of the
Dew point kit. By regulating the flow rate of SF6 gas (0.2 liter/min to 0.5 liter/min - ref. IEC
480), the value of dew point is observed till it becomes stable. If the regulating valve is
provided at outlet of the dew point kit then dew point for rated pressures is to be monitored.

179
Evaluation of Test Results

Measurement of Dew point of SF6 gas is an adequate parameter for condition monitoring
SF6 gas in a CB. Dew point measurement of SF6 gas in a CB indicates the change in the
value of dielectric properties of SF6 gas. The dielectric properties of SF6 gas do get
changed with time due to mixing of impurities like moisture; decomposition products of SF6
gas. Typical arrangement for dew point measurement is given in figure below:

180
Measurement of Circuit Breaker Operating Timings including Pre-insertion Timings
To measure Operating Timings of Circuit Breakers to evaluate the operational performance.
Test Equipment
Circuit Breaker Operational Analyzer and associated accessories.
Testing Procedure
It is to be ensured that R, Y, B phase marking cables are connected with the proper place in
the CB analyzer and colour codes are to be maintained for all the three poles of CB. Give
closing command to closing coil of CB and note down the PIR and main contact closing time.
Take the print out from the analyzer. Give tripping command to trip coil-I of CB and note
down the main contact tripping time. Give tripping cOlIDl1and to trip coil-II of CB and note
down the main contact closing time. Note down the timings for 'CO', ‘OC’ and OCO' by
giving respective commands.
Evaluation of Test Results
(a) Closing timings
Closing time of EHV CBs should not exceed 200 ms and discrepancy should not be there
main contacts and PIR contacts. Discrepancy in operating times of PIR and main contacts
should not exceed the permissible limits.
In any case, main contacts should not close prior to closing of PIR contacts and PIR
contacts should not open prior to closing of main contacts. In case, contact bouncing is
observed in operating timings for PIR and main contacts, same is to be rectified.
(b) Tripping timings
Trip time for EHV CBs should not exceed beyond 35 ms. Discrepancy in operating timings
for Pole to Pole and Break to Break should not be allowed beyond permissible limits which is
3.33 ms and 2.5 ms respectively.
In case, operating times of different poles breaks are not within permissible limits,
Dynamic Contact Resistance measurement to be carried out to see the healthiness of main
contacts.
(c) 'CO' timings
CO timings should be within pel111issible limits as specified by different manufacturers.

Measurement of Dynamic Contact Resistance of EHV Circuit Breakers


To monitor condition of CB main and arcing contacts without opening the
Test Equipment
DCRM kit with CB operational analyzer

181
Testing Procedure:-
CB should be in open position, Isolator of both sides of CB should be in open position
and earth switch of one side of CB should be in open position. To ensure proper
connections, Current Connections clamps at CB flanges , proceed as follows:

The tightness of connections at CB flanges is most important to ensure error free


measurement). CB during CO operation generates lot of vibrations and failure of
connections during this period can dramatically change the dynamic signature of CB
resistance. Typical arrangement of DCRM is given below:

Incoming and outgoing flanges of CB to be cleaned 'vvith polish paper to remove paint,
oxidation, etc., at points where current clamps are mounted. Select this point of connection,
as close as possible to the end of porcelain insulator to ensure that minimum resistance is
offered by flanges, bolts, termiinal connector, etc.

Measurement of Contact Resistance of Circuit Breaker


To measure contact resistance of circuit breaker main contacts.
Test Equipment
Micro ohm meter of 100A and above with associated accessories.
Testing Procedure CB should be in close position and Isolators on both side of CB should be
in open position. The ohm meter operates on the four wire measurement principle. To
measure the contact resistance connect the respective leads and adjust the variac so that
100 amperes current flow through the CB contacts. Value of contact resistance is directly
displayed on the digital LED display screen.

182
Evaluation of Test Results
Contact resistance of the CB contacts indicates wear out and misalignment of the main
contacts. If the value of contact resistance exceeds the permissible limit, i.e., 150 micro
ohms this could result in overheating of the contacts. Therefore, the problem of high contact
resistance should be attended immediately by making proper alignment of contacts or by
replacing arcing/main contacts.

Checking of Pole Discrepancy Relay and Timer for Circuit Breakers


Definition
Pole discrepancy is defined as the difference in closing and opening timings of different
poles ofCB.
Test Equipment
Standard timer, testing leads, etc.
Testing Procedure
Isolators on both sides of CB to be in open position and Earth switch in closed position.
(a) When CB in open position
Closing contact is extended to close one pole, say R-Pole, of CB. After closing R Pole of CB,
this Pole should automatically open after 2.5 seconds (as per pole discrepancy timer
settings). Repeat the test for remaining two poles of CB.
(b) When CB in closed position
Tripping contact is extended to trip one pole, say R-Pole, of CB. Remaining Y and
B- Poles of CB should automatically open after 2.5 seconds. Repeat the same test for
remaining two poles of CB.
(c) Timer checking
Connect standard timer in parallel with CB timer. Extend 220 volt DC to both 'the timers and
note down the timings at which output contacts of timer (which are going to pole discrepancy
trip relay) gets closed. If there is a difference between timing readings of two timers, adjust
the CB timer's settings accordingly.
Evaluation of Test Results
Permissible value of pole discrepancy between two poles of CB is 3.33 m/sec. However,
timer is set to trip the remaining poles taking into consideration the auto reclose scheme
adopted by the utilities.

Operational Lockout Checking for Circuit Breakers:-


Operational lockouts are provided in circuit breakers to prevent the operation of the breaker
during deficiency in the circuit breaker or its operating mechanism. The lockouts provided in
CBs is to be tested to check for any drift/ non-function as they are safety devices to prevent
improper operation leading to failure.

183
Low Pressure Alarm
Close isolation valve between CB Pole and density monitor. Start releasing SF6 gas from
density monitor till the low pressure gas alarm contacts are actuated which is detected by
Multimeter. Note down the pressure and temperature at which the contacts get actuated.
Operational Lockout Alarm
Continue releasing SF6 gas from isolated zone till the operational lockout alan11 contacts
are actuated which are detected by multimeter. Note down the pressure and temperature at
which the contacts get actuated. Gas is to be taken in to gas evacuating unit and after
checking gas to be filled to the rated pressure in the CB.

Pneumatic Operating System Lockout


(a) Compressor START/STOP Switch
Close the isolating valve of CB. Release air into atmosphere from the compressor.
Note down the value of pressure at which compressor starts building up air pressure
and pressure at which compressor stops.
(b) CB auto reclose lockout
Close Isolation valve between pneumatic system and pressure switches. Release air
from the isolated zone to atmosphere. Note down pressure at which A/R L/O contacts of
pressure switch get actuated which are detected by multimeter. The leads of the multimeter
should be connected to the contactor where the AR LlO of CB is made.
(c) CB closing lockout
Release air from the isolated zone to ah11osphere. Note down pressure at which CB
Closing L/O contacts of pressure switch get actuated which are detected by multimeter.
(d) CB operational lockout
Release air from the isolated zone to atmosphere. Note down pressure at which CB
Operational L/O contacts of pressure switch get actuated which are detected by multimeter.
(e) Mechanical Closing Interlock (MCI) (FOR ABB CBs ONLY)
CB should be in closed position. Release air from pneumatic system of CB to atmosphere
and observe whether CB poles start opening, if so, note down the pressure at which tie rod
starts coming down, the movement to stop after a few millimetre. The MCI is provided to
prevent opening of the CB. Non operation of MCB is to be investigated.

184
Reference document is CBIP manual-294

185
_________________________________________________________________________

References from CBIP manual- 294 (EHV Sub-station Equipment maintenance)

186
CHAPTER-11
POTENTIAL TRANSFORMERS AND CAPACITIVE VOLTAGE
TRANSFORMER (CVT) TESTING

Er. P.K. Gargava Er. Pranay Joshi

INTRODUCTION
Voltage transformers (Potential transformers) are used for measurement and
protection. Accordingly, they are either measuring type or protective type voltage
transformers. They may be either single phase or three phase. Voltage transformers are
necessary for voltage directional, distance protections. The primary of voltage transformers
is connected directly to power circuit between phase and ground depending upon rated
voltage and application. The volt-ampers rating of voltage transformers is lesser as of is
power transformer.

Classification of Voltage Transformer


 Electromagnetic potential transformers in which primary and secondary wound on
magnetic core like in usual transformers
 Capacitors potential transformers (CVT) in which primary voltage is applied to a
series capacitor group. The voltage across the one of the capacitors is taken to
auxiliary voltage transformers. The secondary of auxiliary voltage transformers is
taken for measurement of protection
Capacitors potential transformers (CVT) are preferred particularly at voltages above
132 kV due to lower cost and it also serves the purpose of a coupling capacitor for
the carrier equipment.

Figure (1) & (2) below shows the schematic view as well as the construction of a single stack
CVT. Each CVT consists of a coupling capacitor (CC) which acts as a voltage divider and an
Electro Magnetic Unit (EMU) which transforms the medium voltage to standard low voltage.
Depending on the system voltage the CC can be a single or a multi stack unit. The CC and
the EMU are individually hermetically sealed to ensure accurate performance and high
reliability.
Coupling Capacitor(CC)
The Coupling Capacitor (CC) acts as a voltage divider and converts the system voltage to a
medium voltage.
Electromagnetic Unit
The Electromagnetic Unit (EMU) consists of a medium voltage transformer, compensating
reactor, damping element and surge protection device.

187
The CC unit is mounted on the EMU tank and the insulated earth terminal of the CC (marked
as ‘NHF’ in Fig.1 is also accessible for connecting to power line carrier communication
equipment. A surge arrester across this terminal and earth serves as the surge protection
device. The NHF terminal must always be connected to earth if the CVT is not
connected to carrier equipment.

Figure (1) schematic view of CVT

188
Figure (1) Terminals of CVT

189
TESTING OF PT/CVT

12 Visual Inspection
Prior to any electrical testing, complete a visual inspection on the PT/CVT , its structure,
earthing, etc. to confirm it is fit for testing.
If the PT/CVT is a new installation, confirm that all construction items outlined in the
Construction Tool and manufacturer installation instructions have been completed.

Some basic inspections include:


 Ensure external surfaces are clean, dry and damage free.
 Look for external oil leaks, leaks into secondary connection boxes or EMU cases.
Note that an oil leak in some CVTs can cause oil to transfer between the capacitive
stack and the EMU without an external leak being visible.
 Confirm oil/gas levels are acceptable.
 Confirm primary and secondary connections are correct, tight and correctly (new) /
adequately (existing) labelled.
 Confirm primary and secondary earthing is in place and correct. For CVT’s, ensure
the primary earth is either directly connected to earth or connected via power line
carrier communication equipment.
 Confirm if there are any external short from primary to earth (fuse wire is commonly
used on CVT’s during transport and installation to prevent charging capacitor stack)

Caution: N or HF Terminal Earthing is Critical


Before beginning any testing, particularly primary voltage injection, it is important to ensure
that the Neutral terminal on the primary winding has been earthed. For CVTs, the HF
terminal may be earthed directly or via the carrier line matching unit (where fitted). If the HF
terminal is disconnected for testing (eg insulation resistance measurement) then it must be
reconnected immediately afterwards.
If the Neutral N / HF terminal is left disconnected when the VT/CVT is energised, high
voltage will be apparent on this terminal which poses a serious safety risk to staff

13 Insulation resistance Measurement:


Insulation resistance IR tests are one of the easiest and quickest ways to confirm phase to
ground and winding to winding insulation integrity. It helps determine the health of the
insulation between components that are not supposed to be electrically connected. Before
starting this test remove the earthing from Neutral N terminal in PT and from HF
terminal in CVT and after completion of test re earth the N & HF terminal.

190
Insulation resistance IR Measurement done between:
 HV terminal to earth
 HV terminal to secondary terminal
 Secondary terminal to earth
 Each secondary to all other secondary

14 Tan Delta and Capacitance Measurement


CVT condition monitoring based on capacitance and tan delta measurement. A large
number of equipment insulation failures can be identified in advance by carrying out Tan
delta and capacitance measurement. Changes in the value of capacitance indicate abnormal
conditions such as presence of moisture, layer short circuits or open circuits in the capacitor
elements of CVT stacks.
Measurement is to be carried out by 10 KV or 12 KV Automatic Tan Delta measurement test
kit. As there will be induction at switchyard, kits with induction suppression facility to be used
.
Test Procedure
Jumper is to be disconnected from HV terminal, PLCC connections earth connection is to be
removed from HF point bushing and earth connection to be removed from neutral point of
EMU tank. Before carrying out the measurement, the insulator petticoats of CVTs should be
cleaned from moisture, sand, dust particles or salt deposition etc. otherwise measured
values shall be affected greatly by these factors. All safety precautions pertaining to the high
voltage kit used to be observed. HF point should be disconnected from ground PLCC.
Neutral LV of Intermediate transformer should be disconnected from ground. High voltage
from tan delta kit should be applied to primary (HV) terminal . Measurements have to be
taken in GST - Mode. Standard procedure (as specified by kit supplier) for measuring
capacitance and tan delta in charged switchyard induced voltage conditions should be
followed.
NOTE : After testing with high voltage (10 kV), test terminals must be grounded before
being touched by any personnel
Following norms are proposed for evaluation of the test results:

191
Note: If only Tan Delta values exceeds +0.003 (increase from the pre-commissioning
values) and capacitance values are within acceptable norms, the Test results are to be
reviewed for further action by experts.

15 Ratio Test.
This test is Done to check the whether ratio from Primary to secondary winding is correct
or not. Incorrect ratios can be the result of a number of things such as poor manufacturing,
inappropriate materials or inter-turn winding faults.
Test Procedure
i. Ratio test is also done at the time of Tan Delta Measurement, when HV 10 KV/12
KV Supply is given to HV terminal through Tan Delta Measurement kit at the same
time we can measure the voltage at secondary terminal of PT/CVT i.e at 1a-n,2a-n
& 3a-n using multi meter and check the secondary ratio corresponding to HV
Supply.
j. Ratio test of PT/CVT is also done using Automatic transformer turn ratio tester as
described in Transformer testing section.
k. If Tan Delta Measurement kit and Automatic transformer turn ratio kit is not
available, then ratio test is done by injecting 1-ph AC supply to secondary terminal
of PT/CVT say at 1a-n and measure the voltage at other secondary terminal say at
2a-n & 3a-n using multi meter and repeat the process by giving 1-ph AC supply to
secondary terminal say at 2a-n & 3a-n and measure the voltage at other secondary
terminal respectively. Same voltage at other secondary terminal measured indicate
the correct PT/CVT ratio.

Note: When voltage is applied on secondary terminal don’t measure the


voltage on HV Terminal as due to step up phenomena high voltage is induce
on HV side which will damage the Voltage meter and poses a serious safety
risk to staff

192
16 Online Partial Discharge Testing
Partial discharge (PD) testing is used to find a number of defects within the devise such as
voids in insulation, loose connections, loose nuts and bolts, poor earthing and many other
defects. Online partial discharge testing is a non-intrusive, in service test method that can be
used for early detection of faults. This test is done When PT/CVT is in service and done by
outsource agency.
________________________________________________________________________

193
CHAPETR-12
CURRENT TRANSFORMERS TESTING
Er. P.K. Gargava Er. Pranay Joshi

INTRODUCTION
Current transformers are used for measurement and protection. Current transformer
works on conventional electromagnetic transformer principle and are used to transform high
voltage line current to low standard value. A current transformer is intended to operate
normally with the rated current of the network flowing through the primary winding which is
inserted in series in the network.
The primary winding consists of Aluminum sections accommodated in the tank at the top.
The primary connection can be done using Primary terminal (P1 & P2) available outside on
the side of tank. The secondary winding is of insulated copper wire uniformly wound over
the ring type CRGO toroidal cores. The secondary leads are taken though Condenser
Graded bushing and are terminated in the secondary Box at the base of CT. Secondary
terminal of CT are connected to measuring instruments and relays.
Now Days Current Transformer used are of two Types.

1. Dead Tank Current Transformer : Figure(1) & (2) below show the sectional view
and basic diagram of Dead Tank CT

194
Figure (1) : Sectinal View of Dead Tank CT

Figure (2) :Basic Diagram of Dead Tank CT

195
2. Live Tank Current Transformer: Figure (3) & (4) below show the sectional view
and basic diagram of Live Tank CT

Figure (3) : Sectinal View of Live Tank CT

196
Figure (4) :Basic Diagram of Live Tank CT

Classification of Current Transformer:

In MPPTCL Voltage wise CTs are classified as under ;

400 KV Class: CT ratio used for 400 KV Class CT is 2000-1000-500/1 A


 Dead Tank CT: - Below Figure (5) & (6) are the Name Plate Detail of 400 KV BHEL
and ABB Make Dead Tank CT
 Live Tank CT: - Below Figure (7) & (8) are the Name Plate Detail and secondary
terminal detail of 400 KV CGL Make Live Tank CT
220 KV Class: CT ratio used for 220 KV Class CT at 400 KV S/s is 1200-600/1 A and at
220 KV S/s is 800/1 A
 Dead Tank CT :- Below Figure (9) are the Name Plate Detail of 220 KV SCT Make
Dead Tank CT
 Live Tank CT :- Below Figure (10) are the Name Plate Detail of 220 KV CGL Make
Live Tank CT
132 KV Class: CT ratio used for 132 KV Class CT are 800/1 A and 400/1 A
 Dead Tank CT :- Below Figure (11) are the Name Plate Detail of 132KV Mehru Make
Dead Tank CT
 Live Tank CT :- Below Figure (12) are the Name Plate Detail of 132 KV Heptacare
Make Live Tank CT
33 KV Class : CT ratio used for 33 KV Class CT are 1200/1A,800/1 A and 400/1 A

PRE-COMMISSIONING TESTING OF CT
These test are carried out on CT’s preferably after they are erected and before they are
taken in to service. The tests indicated are sufficient to give us information that the CT is OK
and ready to perform its function as desired.

17 Visual Inspection
Prior to any electrical testing, complete a visual inspection on CT , its structure, earthing, etc.
to confirm it is fit for testing.
If the CT is a new installation, confirm that all construction items outlined in the Construction
Tool and manufacturer installation instructions have been completed.

Some basic inspections include:


 Ensure external surfaces are clean, dry and damage free.

197
 Look for oil leaks, Current transfom1ers are normally filled with oil and have oil
impregnated paper insulation for both primary and secondary winding. Careful
inspection is to be made for any trace of oil leakages. Oil leakages are more prone
through cemented joints or secondary terminal box due to improper sealing of
terminal studs. As CTs have less oil quantity small leakage may lead to exposure of
paper insulation and subsequent moisture absorption. If bellows are provided in CTs,
the position of bellow indicates either leakage of oil or expansion due to internal gas
generation. Both the conditions are serious for the life of the CTs and immediate
action to be initiated for rectification
 Confirm oil levels in the oil level indicator are acceptable.
 Confirm primary and secondary connections are correct, selection of Correct
secondary ratio is very important, Secondary ratio selection may be achived by
primary connection in case of 132 KV Class CT and by secondary terminal in case of
220 Kv & 400 KV Class CT.
 Confirm primary and secondary earthing is in place and correct
Caution:
 Confirm the shorting of secondary terminal of the core , which is not to be
used at the time of commissioning
 Tan Delta point shall always be connected to earth. Mechanical Integrity of the
earthing of Tan delta Point with earth shoul be ensured.

18 Continuity Test/Secondary resistance Measurement:


This test is conducted to ensure that the internal connection of the primary and the
secondary winding are intact and not open circuited.
Testing Procedure
Connect leads of ohm meter between different terminal of CT secondary cores. Select the
range of ohm meter as per pre-commissioning/factory test results. Record the winding
resistance values
Evaluation of Test Results
Value of secondary winding resistance should be within acceptable limits. Extreme low value
of resistance indicates turn to turn shorting whereas if the value is high, it indicates some
loose connection which is to be identified and tightened before repeating the measurement

19 Ratio Test.
This test is carried out to verify that there is no damage to the CT winding during transit
and also to ascertain that the CT ration is correctly chosen.

198
Test Procedure
l. Ratio test of CT is also done using Automatic transformer turn ratio tester as
described in Transformer testing section.
m. If Automatic transformer turn ratio kit is not available, then ratio test is done by
Primary current injection PI kit as shown in figure(14) below. The current of max.
possible value of rated current is passed through the primary winding and the
current in the secondary shall be measured using multi meter/clamp meter. The
current in the secondary shall be equal to the primary current divided by the CT
ratio.
Note: During Ratio Test When current is measured at secondary terminal keep the
other secondary terminal shorted

Figure (14) Arrangment for the measurment of Ratio test:

Evaluation of Test Results


No appreciable deviation in the measured current on secondary when compared with
primary current divided by CT ratio .

20 Polarity Test
The DC voltage test momentarily imposes a small DC voltage on one side of a C.T and the
direction of the momentary deflection of a mille-ammeter on the opposite side of the CT is
noted and compared with polarity marks. Figure(15) below show the arrangement for polarity
test

199
Figure (15) Arrangment for Polarity Test

The d. c. source, a dry cell or storage battery of 4-6 V is connected in series with the primary
winding of the CT through switch. The positive pole of the battery is connected to the P1
terminal of the primary winding and the negative pole to the P2 terminal end of the primary.
While closing and then opening switch, watch the indicating instrument connected across the
secondary winding to see in which direction its pointer deflects.
Evaluation of Test Results
When the primary circuit is closed, the pointer deflects to the right and then deflects to the
left when the circuit is broken. It is a sign of like polarity (and correct marking) of the CT
primary and secondary terminals, one of the which connected to the positive pole of the
battery, the other to the positive terminal of the indicating instrument

21 Tan Delta and Capacitance Measurement


Capacitance and tan delta measurement on CTs is done to evaluate the healthiness of solid
insulation. As most of the CTs have oil impregnated paper as solid insulation, capacitance
and tan delta measurement indicates the amount of deterioration.
Measurement is to be carried out by 10 KV or 12 KV Automatic Tan Delta measurement test
kit. As there will be induction at switchyard, kits with induction suppression facility to be used
.
a) CT with Tan Delta point/Test Tap:
Test Procedure

200
 Disconnect CT Tan Delta Point from earth.
 Ensure about the proper cleaning of insulator surface
 Connect HV lead of Tan Delta measurement kit to Primary terminal of CT and LV
lead of Tan Delta measurement kit to Tan Delta Point of CT
 Measurement has to be taken in UST Mode between primary terminal and Test Tap

b) CT without Tan Delt Point/Test TAp


Test Procedure
 Disconnect CT Tan Delta Point from earth.
 Ensure about the proper cleaning of insulator surface
 Connect HV lead of Tan Delta measurement kit to Primary terminal of CT and LV
lead of Tan Delta measurement kit to ground/earth
 Measurement has to be taken in GST Mode between primary terminal and earth

Evaluation of Test Results


The permissible values of capacitance and dissipation factor of class A insulation, e.g.,
Paper insulation impregnated in oil is 0.007 at 20°C. Tan delta value in no case should
exceed the permissible value. It is still more important to monitor the rate of change of Tan
delta and capacitance. Tan delta value should not increase by more than 0.1 % per year and
capacitance value by 1 % per year. Change in capacitance values can be within + I 0%, -5%
of the original value. An increase in only tan delta value (not appreciable change in
capacitance value) indicates deterioration of cellulose insulation whereas increase in both
tan delta and capacitance values indicates entry of moisture in the insulation. Main reason
for increase of tan delta value is because of presence of inherent air voids which are created
during manufacturing process. In course of application of high voltage, these voids are
ionized which result in deterioration of insulating properties of the insulation.
Note: After Tan Delta Measurement ensuring about the earthing of Tan Delta point
before charging the CT.

22 Insulation Resistance Measurement Test.


Insulation resistance IR tests are one of the easiest and quickest ways to confirm phase to
ground and winding to winding insulation integrity. It helps determine the health of the
insulation between components that are not supposed to be electrically connected.
The IR value measurement shall be carried out for following point.
 Between Primary to Earth at 5 KV
 Between Primary to secondary each at 5 KV
 Between Primary to Tan Delta Point at 5 KV

201
 Between Secondary to Earth at 500 V
 Between of secondary’s at 500 V
Test Procedure
 Ensure about the proper cleaning of insulator surface, it should be dust and moisture
free
 Make the measurement of dry day since moist day measurement are not consistent
 Connect HV lead & LV lead of Insulation tester at desired terminal as described
above and take the reading for 1 min at specified voltage range.
Evaluation of Test Results
Changes in the normal IR value of CT indicate abnormal conditions such as presence of
moisture, dirt, dust, crack in insulator of CT and degradation of insulation. Changes in the IR
value of CT are also based on the weather conditions. It is advised to Carry out IR
measurement during summer and dry weather preferably. Insulation Resistance changes
with deterioration in insulating properties. Absolute value of IR is important to monitor but the
rate of change is equally important. The value of IR should not be less than 1000 M ohms If
readings of IR increase with time, the insulation is good. However, if readings remain same
over the time span, insulation is contaminated.

23 Online Partial Discharge Testing


Partial discharge (PD) testing is used to find a number of defects within the devise such as
voids in insulation, loose connections, loose nuts and bolts, poor earthing and many other
defects. Online partial discharge testing is a non-intrusive, in service test method that can be
used for early detection of faults.. Partial Discharge test id being carried out on 400/220/132
KV class CTs in various sub-stations of MPPTCL. The test is done by outsource agency.
The main advantages envisaged in PD tests are as under: -
1. The test is conducted online hence no shutdown is required.
2. The test takes very short time
3. The test results are available immediately at site.
4. The test results are conveyed as low, medium and high PD. The CTs with low and
medium PD are kept under observation and CTs of high PD are replaced after
verifying Tan delta and DGA of CT
5. Portable kit is used which is very handy
6. Manpower required is very less. One or two helper with Tester can carry out testing
Below are Figure(16) & (17) show the PD test result 400 KV Class and 220 KV Class CT

202
Figure (16) PD Test Result of 400 KV Class CT

Top Part is the data of Aquastic Emission AE Sensor & Bottom Part is the data of High
Frequency Current Transforemer HFCT Sensor
Observation : OK
Note:- No PD activities In above Data.

Figure (17) PD Test Result of 220 KV Class CT


Top Part is the data of Aquastic Emission AE Sensor & Bottom Part is the data of High
Frequency Current Transforemer HFCT Sensor
Observation : OK.
In above data Core Vibration activities observed by AE Sensor Which is mechanical
activities.
No activities observed by HFCT sensor.
_________________________________________________________________________

203
CHAPTER-13
SURGE ARRESTERS
Er. P.K. Gargava

Surge arrester plays a very vital role in improving power system reliability by diverting surges
to earth and thus protecting costly switchyard equipments. Proper insulation coordination is
necessary for enhancing life span of costly substation equipments. Since surge arresters
protect other equipments therefore monitoring the health of surge arrester is essential. Surge
arresters are monitored basically using three tests to evaluate its condition.
a. Leakage current monitoring
b. insulation resistance measurement
c. Thermo vision
Out of these, leakage current measurement and the thermovision scanning are on-line
measurement and shut down is required for IR measurement. As system availability is
crucial for utilities, more emphasis is to be given for on-line measurements.
Leakage Current Measurement
As per IEC-60099(5), techniques for the health monitoring of surge arresters in service the
following condition monitoring methods are suggested:
• Total leakage current measurement
• Watt loss measurement
• Insulation resistance measurement
• Third harmonic resistive current monitoring.
• Third harmonic resistive current (THRC) monitoring with compensation for third harmonics
in system voltage.
Total leakage current measurement is not sensitive to the deterioration of the arrester
discs as total leakage current measurement do not indicate severity of ZNO disc degradation
as resistive current is only 20-30% of the total leakage current and a sharp increase in
resistive current due to degradation of arresters discs do not affect the total leakage current
considerably. Watt loss measurement is a useful method but it involves a separate voltage
source and test results are affected by phase shifts introduced by CVT/PT. The harmonics
present in the system voltage may create capacitive harmonic currents, which may be
comparable with the harmonic current generated by the non-linear resistance of the surge
arrester. As a result, the error in the measured harmonic current may be considerable. The
error in the measured third harmonic current may be up to l00% with 1 % third harmonic
present in the system voltage. Hence, reliable monitoring of surge arresters is possible
through such test kits which provide for compensation for harmonics present in the system
voltage.
Testing Principle

204
The zinc oxide elements discs are made by mixing zinc oxide with small amount of additive
materials. The equivalent circuit of surge arrester is parallel combination of capacitance and
variable resistance (as shown in figure).

The current flowing through the zinc oxide discs is the total leakage current (IT )is having
capacitive leakage Current (Ic) and resistive leakage current (IR) components. Normal
operating voltages causes ageing of ZnO discs whereas switching/ lightning over voltages
may cause over loading of all or part of the ZnO blocks. The increase in resistive leakage
current (IR) due to above reasons may bring the arrester to thermal instability and may result
in complete arrester breakdown. Hence, monitoring of leakage resistive current (IR) is very
important.
Harmonics are created in leakage current on application of fundamental frequency, due
to non-linear voltage-current characteristic of surge arresters. Third harmonic is the largest
harmonic component of the resistive current. Third harmonic in system voltage creates
capacitive harmonic Currents which affect the measured value.
Test Procedure
The measurement principle is based on the fact that harmonics are created in the
leakage current by non-linear voltage-current (V-I) characteristics of surge arrester. Resistive
current consists of fundamental, third harmonic, fifth harmonic and seventh harmonic
components. The harmonic current depends on the magnitude of the resistive current and
on the degree of Non-linearity of the voltage-current (V -I) characteristics. The harmonic
content also varies with the voltage and temperature of the surge arrester.
The third harmonic is the largest harmonic component of the resistive current and is most
commonly used for diagnostic measurements. No reference is needed for measurement of
third harmonic resistive current since it is assumed that all harmonics arise from the
nonlinear resistive current. The conversion from harmonic to resistive current level, if
required, relies on information supplied by surge arrester manufacturer or from
measurements in the laboratory. Basic principle of this technique lies in the measurement of
third harmonic resistive current duly compensated for third hamonics present in system

205
voltage. A trend analysis of the 3rd harmonic resistive current is necessary to observe
periodical changes due to normal/abnormal ageing. Sudden rise in THRC or very high value
of third harmonic resistive current indicates degradation of ZnO discs and
inspections/corrective actions are required to be taken in advance to prevent catastrophic
failures .
Method of THRC Measurement
The total current (h) through the Surge Arrester having Capacitive component (Ic) and
Resistive current (IR) flows through the Leakage Current Monitor. The IR component has 3 rd,
5th harmonic and other harmonic present in it. However, when degradation of ZnO discs
occur, the variation of 3rd Harmonic Resistive Current is more pronounced than other
harmonics currents, total current (IT) and total capacitive current (Ic). ,

The connection arrangement for the instrument is quite simple as shown in above
Figure. Connecting a clamp type CT probe to the ground wire allows the leakage current to
be detected. Probe output passes through a shielded cable to the detector unit. A band pass
filter is built into the initial stage to pass the third harmonic and to cut off the fifth and higher
harmonics. After the third harmonic is selected, it is amplified and then displayed.
Compensating antenna is also provided, output of which is fed to the test kit to compensate
for the harmonics present in the system voltage. The harmonics present in the EHV system
are compensated and filter circuits are provided for bypassing undesired currents and only
3rd harmonic resistive current is measured.

206
Insulation Resistance Measurement
Insulation resistance measurement for Surge An-esters also gives the condition of the
arresters. Insulation resistance measurement is to be first carried out on individual stacks
and then carry out the test for the complete arrester. As this is off line test, the arrester is to
be taken out of service for such measurement. IR test proves good to find out any moisture
entry through sealing inside the arrester keeping a stack with low IR value will stress the
other stack also and failure is more prone on the other stacks also. Corrective action is to be
taken immediately.

Thermovision Scanning
Thermo-vision scanning plays a vital part in identifying defects in EHV switchyard. As it
requires no shut down of switchyard equipment, it needs to be widely used on condition
monitoring. Any loose joint, improper isolator contacts and current transfer parts could be
identified using thermo vision scanning. Thermo vision scanniing also helps in identifying
defects in surge arresters. This may not be true always but if there is defect and more
current is passing through the arrester, then the temperature inside arrester will increase and
could be detected by thermo vision scanning. It is advisable to carry out this test during
maximum voltage condition of the switchyard unlike thermo vision scanning of other current
carrying components during maximum current flow condition.

Reference document- CBIP manual 294 (EHV Sub-station Equipment Maintenance)

207
ANNEXURE-1

TAN DELAT CONVERSION FACTOR

208
209
210
211
ANNEXURE-2
IR VALUES CONVERSION FACTOR

MULTIPLYING FACTORS FOR CONVERSION OF IR VALUES AT 60 C


OIL TEMPERATURE

OIL TEMP MF OIL TEMP MF OIL TEMP MF


20 0.088 41 0.3200 61 1.1000
21 0.094 42 0.3400 62 0.1200
22 0.100 43 0.3600 63
23 0.108 44 0.3800 64
24 0.116 45 0.4000 65
25 0.125 46 0.4300 66
26 0.132 47 0.4500 67
27 0.138 48 0.4900 68
28 0.144 49 0.5300 69
29 0.152 50 0.5600 70
30 0.160 51 0.5800 71
31 0.174 52 0.6250 72
32 0.180 53 0.6600 73
33 0.190 54 0.7700 74
34 0.210 55 0.7400 a
35 0.225 56 0.7800 76
36 0.240 57 0.8250 77
37 0.255 58 0.8800 78
38 0.270 59 0.9500 79
39 0.285 60 1.0000 80
40 0.300 61 1.1000 81

212
ANNEXURE-3
Permissible dew point in degree centigrade for N2 filled new transformer

213
DEW POINT ACCEPTANCE CHART
To be checked when new transformer is received and when during vacuum and oil
filling process

_________________________________________________________________________

214

Вам также может понравиться