As per design and details sent by seageo survey length of the major bridge is 50

metre but as per ourGAC experts study and review lenth of the bridge will be 40
metre.

Measurement Sheet

S NO ITEM UNIT NOS LENGTH BREAD HEIGH Quantit Considerations


TH T y

A Concrete

1 PILE Cum 16 0.63585 5 50.868 pile dia 0.9

2 PILE CAP Cum 4 2.5 2.5 1 25 pier dia 1.5

3 PIER Cum 4 1.76625 12 84.78 pile height


assumed =5m.

4 PIER CAP Cum 28 2 2 1 112

5 TRAPEZOIDAL Cum 4 11 1.5 1 25


SECTION

6 SUPPORT BEAM Cum 7 15 0.6 0.8 50.4


FOR 1ST SPAN

7 SUPPORT BEAM Cum 7 20 0.6 0.8 67.2


FOR 2ND SPAN

8 SUPPORT BEAM Cum 7 15 0.6 0.8 50.4


FOR 3RD SPAN

9 SLAB Cum 2 15 11 0.25 82.5

10 SLAB FOR MID cum 1 20 11 0.25 55


SPAN

Total 603.148
B Steel KG 96503.6
8

MT 96.5036
8

C Shuttering

Pier Sqm 4 104 416

Abstract

S no Particular Unit Qty Indian Amount


Rate

A Concrete

1 pile Cum 50.868 20000 1017360

2 pile cap Cum 25 14000 350000

3 pier Cum 84.78 25000 2119500

4 pier cap Cum 112 14000 1568000

5 trapeziodal section Cum 25 14000 350000

6 support beam for Cum 50.4 14000 705600


1st span

7 support beam for cum 67.2 14000 940800


2nd span

8 support beam for cum 50.4 14000 705600


3rd span

7 slab Cum 82.5 14000 1155000

8 slab for mid span cum 55 14000 770000

Total 9681860
B Steel MT 96.50368 65000 6272739.2

C For Liner, 4786379.76


shuttering , all
equipments and
tools and tackles
etc

Total 20740978.96

Grand total 26963272.65

Area of Bridge Sqm 50 11 550

Rate / 49024.13209
Sqm

Note It does not include preparing access to the project site ,


installation of crane , barge etc

It does not include labour camp construction

It does not include electrical costs , DG set cost