Академический Документы
Профессиональный Документы
Культура Документы
Cost Estimate
###
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª
Government of Nepal
Ministry of Federal Affairs and Local Developoment
Office of District Development Committee
District Technical Office
Gorkha
RATE ANALYSIS
Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
1 Site clearance for1Sqm Unskill 0.23 700 161.00 Tools & Plant 3 % of labour cost 4.83 4.83 16.58 1.54 U/D A.(3)
1 Site clearance for1Sqm Unskill 0.04 700 28.00 Tools & Plant 3 % of labour cost 0.84 0.84 28.84 2.68 DoLIDAR 1-1.6
dismentaling of old
bldg(mud mortar) Unskill 1.06 700 742.00 Tools & Plant 3 % of labour cost 22.26 22.26 m3 764.26
Skill 0.054 955 51.57 Tools & Plant 3 % of labour cost 1.55 1.55 53.12
roof dismentaling work Unskill 0.081 700 56.70 Tools & Plant 3 % of labour cost 1.70 1.70 m2 58.40
111.52
2
Earthwork in excavation in
a ordinary soft soil- For 1 m3 Unskill 0.50 700 350.00 Tools & Plant 3 % of labour cost 10.50 10.50 360.50 10.22 5.2-1.2.2(a)
b Hard soil- For 1 m3 Unskill 0.60 700 420.00 Tools & Plant 3 % of labour cost 12.60 12.60 432.60 12.26 5.2-1.2.2(b)
c Soft Rock- For 1 m3 Unskill 1.00 700 700.00 Tools & Plant 3 % of labour cost 21.00 21.00 721.00 20.43 5.2-1.2.2(c)
d Medium Rock- For 1 m3 Unskill 3.00 700 2100.00 Tools & Plant 3 % of labour cost 63.00 63.00 2163.00 61.30 5.2-1.2.2(d)
3 Backfilling in foundation
trenches with excavated
materials Unskill 0.25 700 175.00 Tools & Plant 3 % of labour cost 5.25 5.25 180.25 5.11 U/D B2)2(25)a
Stone Solling in foundation
4
& Leveling Unskill 1.50 700 1050.00 Tools & Plant 3 % of labour cost 31.50 31.50 1081.50
Blockstone 1.00 1602.00 1200.00 1602.00 1200.00 1602.00 DoLIDAR
Bondstone 0.20 1602.00 1200.00 320.40 240.00 320.40
Total 1050.00 1471.50 2521.50 71.46 49)17-6
Formworks of Local wood
5
for Beam/Slab Skill 0.150 955 143.25 Local Wood 0.0070 45000.00 45000.00 315.00 315.00 m3 U/D+DoLIDAR
For 1 Sq.m. Unskill 0.200 700 140.00 Nails 0.25 113.00 100.00 28.25 25.00 kg 39)9.a
Total 283.25 343.25 340.00 626.50 58.23
Quantity of wood required for 1 sqm formwork = 0.0526 cum.
Wood can be used 6 times for the formwork and after then 25% cost
of the wood is recovered. So the quantity of wood required for 1 sqm = 0.00658 cum.
Formworksof Local wood for
6
Beam/Slab Skill 0.375 955 358.13 Local Wood 0.0070 45000.00 45000.00 315.00 315.00 m3 U/D
For 1 Sq.m. Unskill 0.562 700 393.40 Nails 0.25 113.00 100.00 28.25 25.00 kg E1 8(3) Ka
Total 751.53 343.25 340.00 1094.78 101.76
Quantity of wood required for 1 sqm formwork = 0.0526 cum.
Wood can be used 6 times for the formwork and after then 25% cost
of the wood is recovered. So the quantity of wood required for 1 sqm = 0.00658 cum.
7
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.17 21288 19000.00 3618.96 3230.00 MT
M10(P.C.C. 1:4:8) Unskill 4.00 700 2800.00 Agg.40mm 0.65 4262.00 4262.00 2770.30 2770.30 cu.m U/D
and wall - For 1 m3 Agg.20mm 0.24 4262.00 4262.00 1022.88 1022.88 cu.m D1 7-2b
Sand 0.47 2300.00 2300.00 1081.00 1081.00 cu.m
Total 3755.00 8493.14 8104.18 12248.14 347.10
8
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.22 21288 19000 4683.36 4180.00 MT
M10(P.C.C. 1:3:6) Unskill 4.00 700 2800.00 Agg.40mm 0.65 4262.00 4262.00 2770.30 2770.30 cu.m U/D
and wall - For 1 m3 Agg.20mm 0.24 4262.00 4262.00 1022.88 1022.88 cu.m D1 7-2c
Sand 0.47 2300.00 2300.00 1081.00 1081.00 cu.m
Total 3755.00 9557.54 9054.18 13312.54 377.26
9
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.32 21288.0 19000.0 6812.16 6080.00 MT
M15(P.C.C. 1:2:4) Unskill 4.00 700 2800.00 Agg.40mm 0.52 4262.0 4262.0 2216.24 2216.24 cu.m U/D
and wall - For 1 m3 Agg.20mm 0.22 4262.0 4262.0 937.64 937.64 cu.m D1 7-2d
For Foundation Agg.10mm 0.11 4262.0 4262.0 468.82 468.82 cu.m
Sand 0.445 2300.00 2300.00 1023.50 1023.50 cu.m
Total 3755.00 11458.36 10726.20 15213.36 431.13
10 Skill 0.80 955 764.00 Cement 0.32 21288.0 19000.0 6812.16 6080.00 MT
Unskill 7.00 700 4900.00 Agg.40mm 0.52 4262.0 4262.0 2216.24 2216.24 cu.m Nirman tatha Ya.
M15(1:2:4) mix plain cement
concrete works in
superstructure including
material collection &30m
Item Labour (L) Materials (M) Total (L+M)
Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
M15(1:2:4) mix plain cement
concrete works in Agg.20mm 0.22 4262.0 4262.0 937.64 937.64 cu.m 7-4b
superstructure including Agg.10mm 0.11 4262.0 4262.0 468.82 468.82 cu.m
material collection &30m
lead - For 1 m3 Sand 0.445 2300.0 2300.0 1023.50 1023.50 cu.m
Total 5664.00 11458.36 10726.20 17122.36 485.22
11 Skill 0.80 955 764.00 Cement 0.40 21288.0 19000.0 8515.20 7600.00 MT
M20(1:1.5:3) mix plain
cement concrete works in Unskill 7.00 700 4900.00 Agg.20mm 0.57 4262.00 4262.00 2429.34 2429.34 cu.m U/D
superstructure including
material collection &30m Agg.10mm 0.29 4262.00 4262.00 1235.98 1235.98 cu.m D2 7b
lead - For 1 m3
Sand 0.425 2300.00 2300.00 977.50 977.50 cu.m
16 Skill 1.00 955 955.00 Blockstone 1.00 1602.00 1602.00 1602.00 1602.00 cum Urban Devemt
Random rubbel Stone
masonry in mud mortar - Unskill 2.25 700 1575.00 Bondstone 0.10 1602.00 1602.00 160.20 160.20 cum C6 6-2-2
For 1 m3
Mud 0.42 280.00 280.00 117.60 117.60 cum
Total 2530.00 1879.80 1879.80 4409.80 124.97
17 Skill 1.50 955 1432.50 Cement 0.100 21288.0 19000.0 2128.80 1900.00 MT Urban Devemt
Chimney Bhatta Brick
masonry work in 1:4 C/S Unskill 2.20 700 1540.00 Sand 0.28 2300.00 2300.00 644.00 644.00 cu.m 5(1)B-2
mortar - For 1 m3 including
material collection,preparation
of mortar with 30m lead
Brick 560.00 13.56 12.00 7593.60 6720.00 cu.m
Total 2972.50 10366.40 9264.00 cu.m 13338.90 378.01
18 Urban Devemt
Chimney Bhatta Brick Skill 1.50 955 1432.50 Cement 0.070 21288.0 19000.0 1490.16 1330.00 MT
masonry work in 1:6 C/S
mortar in Superstructur- For 1 Unskill 2.20 700 1540.00 Sand 0.30 2300.00 2300.00 690.00 690.00 cu.m 5(1)B-3
m3 including material
collection,preparation of
mortar with 30m lead
Brick 560.00 13.56 12.00 7593.60 6720.00 cu.m
Total 2972.50 9773.76 8740.00 cu.m 12746.26 361.21
Total 5945.00 19547.52 17480.00 cu.m 25492.52 722.42
19 Skill 34.00 955 32470.0 wood 1.10 45000.0 45000.0 49500.0 49500.0 m3 Urban Devemt
Sal wood work in Door Unskill 3.40 700 2380.00 screw 184.00 1.47 1.30 270.48 239.20 no G1 10-1
&Window Frame For 1 m3
Holdfast 92.00 28.25 25.00 2599.00 2300.00 no
Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
38mmx75mm Sal wood Rs. Rs. VAT VAT VAT VAT in m in ft
frame &4mm glazed Shutter Unskill 0.404 700 282.80 4mm Glass 0.48655 723.20 640.00 351.87 311.39 Sq.m G3 10(4)
work in Door &Window For
1 m2 Hinges 3" 3.58744 20.34 18.00 72.97 64.57 No
Tower bolt4" 1.79372 45.20 40.00 81.08 71.75 No
Handle 4" 0.89686 33.90 30.00 30.40 26.91 No
Screw 13.45291 1.47 1.30 19.78 17.49 LS
Total 4137.18 1544.75 1480.76 5681.93 528.14
22 Localwood Beams work For Skill 17.65 955 16855.8 wood 1.050 45000.00 45000.00 47250.00 47250.00 m3 Urban Devemt
1 Cu. m Unskill 1.760 700 1232.00 Nails 1.000 113.00 100.00 113.00 100.00 kg F 19 10(17)
Total 18087.8 47363.00 47350.00 65450.80 1854.8
23 25 mm Locall wood Eaves Skill 0.143 955 136.57 wood 0.0275 45000.00 45000.00 1237.50 1237.50 m3 Urban Devemt
Boards for 1 sq.m Unskill 0.014 700 9.80 Nails 0.1000 113.00 100.00 11.30 10.00 kg F20 10(19)
Total 146.37 1248.80 1247.50 1395.17 129.68
24 25 mm Local wood Skill 0.143 955 136.57 wood 0.0275 45000.00 45000.00 1237.50 1237.50 m3 Urban Devemt
Plankings 1 sq.m Unskill 0.014 700 9.80 Nails 0.1000 113.00 100.00 11.30 10.00 kg F20 10(19)
Total 146.37 1248.80 1247.50 1395.17 129.68
25 3 mm plywood shutter on 2 Skill 3.118 955 2977.69 wood 0.01541 45000.00 45000.00 693.45 693.45 m3 Urban Devemt
sides with 38 mm salwood Unskill 0.312 700 218.40 Plywood 2.07127 218.86 193.68 453.32 401.16 Sq.m G4 10(7)
frame for 1 Sq. m
Hinges 4" 1.33630 33.90 30.00 45.30 40.09 No
Tower bolt 6" 0.89087 50.85 45.00 45.30 40.09 No
Mortise Lock 0.44543 904.00 800.00 402.67 356.34 No
Handle 4" 0.89087 33.90 30.00 30.20 26.73 No
Screw 13.36303 1.47 1.30 19.64 17.37 LS
Total 3196.09 1689.88 1575.23 4885.97 454.15
26 28#Plain Sheet shutter on 2 Skill 3.118 955 2977.69 wood 0.015412 45000.00 45000.00 693.54 693.54 m3 Urban Devemt
sides with 38 mm salwood Unskill 0.312 700 218.40 Plain Sheet 2.071269 384.20 340.00 795.78 704.23 Sq.m G4 10(9)
frame for 1 Sq. m
Hinges 4" 1.336303 33.90 30.00 45.30 40.09 No
Tower bolt 6" 0.890869 50.85 45.00 45.30 40.09 No
L-drop 10"x12" 0.445434 226.00 200.00 100.67 89.09 No
Handle 4" 0.445434 33.90 30.00 15.10 13.36 No
Screw 13.363029 1.47 1.30 19.64 17.37 LS
Total 3196.09 1715.33 1597.77 4911.42 456.52
CGI sheet Roofing for 1 Sq. 0.38 mm th Colour
27 Skill 0.110 955 105.05 CGI Sheet 0.071000 10735.00 9500.00 762.19 674.50 Bundle Urban Devemt
m
Unskill 0.125 700 87.50 Nut Bolt 8 mm 28.25 25.00 0.00 0.00 No F3 9(1)
J-Hook 6" 29.38 26.00 0.00 0.00 No
Bitumin Washer 1.13 1.00 0.00 0.00 No
Total 192.55 762.19 674.50 954.74 88.74
Plain sheet Roofing for 1 m 0.45 mm th Plain
28 Skill 955 Urban Devemt
0.200 191.00 sheet 1.200000 384.20 340.00 461.04 408.00 Rm
Unskill 0.300 700 210.00 Nut Bolt 8 mm 1.000000 28.25 25.00 28.25 25.00 No F2 9(2)
Total
Two coat Enamel Painting 401.00 489.29 433.00 890.29 271.43
29 with one coat Primer in Skill 0.120 955 114.60 Primer 0.0810 329.10 291.40 26.66 23.60 Ltr Urban Devemt
doors & winndows for 1 sq
m Unskill 0.080 700 56.00 Enamel 0.16 474.60 420.00 75.94 67.20 Ltr J5 13(5)a,b,c
Total 170.60 102.60 90.80 m2 273.20 25.39
30 Two Coat waterproof Skill 0.050 955 47.75 Snowcem 0.4850 88.41 78.40 42.88 38.02 Kg Urban Devemt
cement (Snowceme) Paint on
Plastered Surface for 1 Sq m Unskill 0.050 700 35.00 J4 13(4)b
Total 82.75 42.88 38.02 m2 125.63 11.68
31 Skill 0.1200 955 114.60 Cement 0.00538 21288.00 19000.00 114.53 102.22 MT Urban Devemt
12.5 mm Thick 1:4 Cement
sand Plaster work in ceiling
for 1Sq. m Unskill 0.1600 700 112.00 Sand 0.01460 2300.00 2300.00 33.58 33.58 cu.m I1) 12-1c
Total 226.60 148.11 135.80 374.71 34.83
32 Skill 0.1200 955 114.60 Cement 0.00382 21288.00 19000.00 81.32 72.58 MT Urban Devemt
12.5 mm Thick 1:6 Cement
sand Plaster work in ceiling
for 1Sq. M Unskill 0.1600 700 112.00 Sand 0.01570 2300.00 2300.00 36.11 36.11 cu.m I1) 12-1d
Total 226.60 117.43 108.69 344.03 31.98
33 Skill 0.1400 955 133.70 Cement 0.00810 21288.00 19000.00 172.43 153.90 MT Urban Devemt
20 mm Thick 1:4 Cement
sand Plaster work excluding
ceiling for 1Sq. M Unskill 0.1900 700 133.00 Sand 0.02200 2300.00 2300.00 50.60 50.60 cu.m I4) 12(4)b
Total 266.70 223.03 204.50 489.73 45.52
34 Skill 0.1200 955 114.60 Cement 0.00538 21288.00 19000.00 114.53 102.22 MT Urban Devemt
12.5 mm Thick 1:4 Cement
sand Plaster work excluding
ceiling for 1Sq. m Unskill 0.1600 700 112.00 Sand 0.01460 2300.00 2300.00 33.58 33.58 cu.m I1) 12-1c
Total 226.60 148.11 135.80 374.71 34.83
35 Skill 0.080 955 76.40 Cement 0.00110 21288.00 19000.00 23.42 20.90 MT Urban Devemt
Flush ruled pointing in 1:3
C/S mortar On stone
masonry wall For 1 m2
Item Labour (L) Materials (M) Total (L+M)
Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
Flush ruled pointing in 1:3
C/S mortar On stone
masonry wall For 1 m2 Unskill 0.100 700 70.00 Sand 0.00200 2300.00 2300.00 4.60 4.60 cu.m I 10. 14(2)c
Total 146.40 28.02 25.50 m2 174.42 16.21
2 955 1910
2 700 1400 astar 8.000000 327.7 2,621.60 ltr
2 955 1910 1st coat
28 Distemper 2 700 1400 diatemper 6.5 214.7 190 1395.55 kg
1.8 955 1719 2st coat
1.8 700 1260 diatemper 5 214.7 190 1073.5 kg
9599 5,090.65 100 m2 14689.65
m2 146.8965
Item Labour (L) Materials (M) Total (L+M)
Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
3 955 2865
3 700 2100 astar 8.000000 327.7 2,621.60 ltr
5 955 4775
29 inamel paints 2 700 1400 1st coat inamel 9 474.6 190 4271.4 ltr
4 955 3820
3 700 2100 2st coat 7 474.6 190 3322.2 ltr
17060 10,215.20 100 m2 27275.2
m2 272.752
1.56
187.2
Government of Nepal
Ministry of Local Development
Office of District Development Committee
District Technical Office
Gorkha
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM) Amount
1 Skill Labour 955.00 955.00 955.00 md
2 Unskilled Labour 700.00 700.00 700.00 md
3 Painter 955.00 955.00 955.00 md
4 Sand 2300.00 2300.00 2,300.00 m3 1600.00 0.14 0.75 0.00 0.00 0.00
5 Aggregate 40mm 2750.00 4262.00 4,262.00 m3 1800.00 0.14 0.59 6.00 1512.00 0.00 0.00
6 Aggregate 20mm 2750.00 4262.00 4,262.00 m3 1800.00 0.14 0.59 6.00 1512.00 0.00 0.00
7 Aggregate 10mm 2750.00 4262.00 4,262.00 m3 1800.00 0.14 0.59 6.00 1512.00 0.00 0.00
8 Stone 1350.00 1602.00 1,602.00 m3 1800.00 0.14 0.59 1.00 252.00 0.00 0.00
9 Mud for masonry 290.00 290.00 290.00 m3 1400.00 0.14 0.59 0.00 0.00 0.00
10 Sal wood 45000.00 45000.00 45,000.00 m3 600.00 0.14 0.59 0.00 0.00 0.00
11 Local Wood 45000.00 45000.00 45,000.00 m3 600.00 0.14 0.59 0.00 0.00
12 Sisau 70560.00 70560.00 70,560.00 m3 600.00 0.14 0.59 0.00 0.00
13 Cement(NS Mark OPC) 17600.00 2288.00 21288.00 19,000.00 mt 1000.00 0.14 0.59 10.00 1400.00 0.00 0.00
14 Brick(Chimney ) 12.00 1.56 13.56 12.00 Nos 2.50 0.14 0.00 0.00 0.00
15 Nail 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
31 Reinforcement Bar(10-40mm) 86000.00 11180.00 98580.00 87,400.00 mt 1000.00 0.14 0.59 10.00 1400.00 0.00 0.00
32 GI Wire 12Swg (Heavy Coating) 105.00 13.65 118.65 105.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
33 GI Wire 10Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
34 GI Wire 8Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
35 3mm Glass 500.00 65.00 565.00 500.00 m2 8.40 0.14 0.59 0.00 0.00 0.00
36 4mm Glass 640.00 83.20 723.20 640.00 m2 11.20 0.14 0.59 0.00 0.00 0.00
37 5mm Glass 750.00 97.50 847.50 750.00 m2 14.00 0.14 0.59 0.00 0.00 0.00
38 Lime 18.00 2.34 21.74 19.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
39 Gum (Rathicol) 200.00 26.00 227.40 201.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
40 Primer (wood) 290.00 37.70 329.10 291.40 Ltr 1.00 0.14 0.59 10.00 1.40 0.00 0.00
41 Enamel (Tayari) 420.00 54.60 474.60 420.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
42 Alumunium Paint 500.00 65.00 565.00 500.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
43 Sand Paper 10.00 1.30 11.30 10.00 Sheet 0.14 0.59 0.00 0.00 0.00
44 Red Oxide No 1 350.00 45.50 395.50 350.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:4:8
Norms No: 41(7-2)c
Unit : Cu.m.
Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:3:6
Norms No: 42(7-2)c
Unit : Cu.m.
Item: plain cement concrete works in superstructure including material collection &30m lead
B. 1:1.5:3 mix
Norms No: 7(4)b,45
Unit : Cu.m.
A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:4
Norms No : 38.8-A. c DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.24 md 650.00 2,106.00
A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:6
Norms No : 38.8-A. d DoLIDAR
Unit : Cu.m.
C)pointing works with cement sand mortar on brick wall with all required operation including full compensation
for all labour, materials , scafolding and otter incidental required to complete tte works as per the specifications
b.) For every subsequent pipe having length of minimum 1m, Dia 30 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.02 md 870.00 17.40
Un-skill 0.10 md 650.00 65.00
Material Cement 0.001 MT 20,804.00 20.80
Sand 0.002 m3 2,300.00 4.60
Jute, Bitumin LS 30.00 30.00
Sub-Total 82.40
15 % Overhead 12.36
Unit Rate 94.76
b.) For every subsequent pipe having length of minimum 1m Dia 60 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.050 md 870.00 43.50
Un-skill 0.200 md 650.00 130.00
Material Cement 0.003 MT 20,804.00 62.41
Sand 0.004 m3 2,300.00 9.20
Jute, Bitumin LS 40.00 40.00
Sub-Total 285.11
15 % Overhead 42.77
Unit Rate 327.88
Hence,
Total cost of 30cmdia.1m H.P. 94.76
Total cost of 60cmdia.1m H.P. 327.88
Total 45mm dia. H.P.1m(Average cost) 422.64 211.32
44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(2X1X 1) (11 m2)
Unit :Per m3 44.2.a DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.09 md 650.00 58.50
Binding wire
Materials 0.95 kg 121.170 115.11
12swg(Heavy Coated)
Sub-Total 173.61
15 % Overhead -
Rate per Box
Size(2X1X1) 173.61
Rate per m3 86.81
44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(3X1X 1) (16 m2)
Binding wire
Materials 1.3 121.17 157.52
12swg(Heavy Coated)
kg
Sub-Total 242.02
15 % Overhead -
Rate per Box
Size(3X1X1) 242.02
Rate per m3 80.67
item : laying of locally available granular materials for gravelling in Roadway for gravelling including
j10m lead & 1.5m lift-per m3
particular unit Qantity Rate Amount Remarks
subgrade preparation 10 cm depth
labour unskill md 0.05 650.00 32.5
#REF!
sfo{qmdsf] gfd
sfd ug]{ lgsfo pkef]Qmf ;ldlt
cfly{s aif{ 074/075
ljlgof]lht jh]6 #REF!
cg'dflgt nfut #REF!
sG6LGh]G;L 0.00
pkef]Qmf >dbfg #REF!
v'b e'QmfgL x'g;Sg] /sd #REF!
l;=g sfdsf] ljj/0f
gf]6
ufp+kflnsfsf] sfof{non] pkef]Qmf ;ldlt;+u ;Demf}tf
ubf{ lgDgfg';f/sf] zt{x?sf] clgjfo{ kfngf u/fpg] k|ltj4tf lnP/
dfq ;Demf}tf
!=pkef]Qmf u/fpgsf
;ldltn] gS;f tyfnflu
nfut cg'/f]w
Ol:6d]6 adf]lhd lgdf{0f ubf{ k'/fgf
vfg]kfgL, l;+rfO{, ljBfno ejg, lghL 3/, uf]7, cf+“ug cfbL k"jf{wf/ ;+/rgf Iflt
k'¥ofPsf] v08df ;f]xL pkef]Qmf ;ldltn] cfkm";+u ePsf] ;Demf}tf /sd leqsf]
ah]6af6 dd{t, lgdf{0f jf k'glg{df{0f ul/lbg' kg]{5 . ;f] ;DjGwdf s'g} ph'/L
kg{ cfPdf pQm Iflt ePsf] lgdf{0f ug{ nfUg] /sd ;DjlGwt pkef]Qmf ;ldltsf]
vftfaf6 s§f u/]/ dfq clGtd km/kmf/s ug]{ Joj:yf ldnfpg'x'g .
@= ;DjlGwt k|fljlws 6f]nLn] ;fO{6df u/]sf] ;e]{, sfof{nosf] :jLs[t nfut cg'dfg
Pj+ gS;fx? cg';f/ g} lgdf{0f sfo{ u/fpg] k|ltj4tf lng' x'g .
#= :jLs[t nfut cg'dfg / gS;f eGbf km/s sfo{ u/L sfof{non] d"Nof+sg gu/]sf]
v08df s'g} lsl;dsf] ph'/ nfUg]5}g eGg] k|ltj4tf lng'x'g .
$= ;Demf}tf adf]lhdsf] lgdf{0f ubf{ u/fpbf jftfj/0f ;+/If0f P]g @)%# /
jftfj/0f lgodfjnL @)%$adf]lhd jftfj/0fdf gsf/fTds k|efj gkg]{ul/ u/fpg] k|ltj4tf
lng'x'g .
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f
S.N. Description of items No. Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork for pipeline 1 120 0.3 0.3 10.80 m3 432.60 4672.08
2 HDPE Pipe kg/m
(63 mm 6kg/cm2) 1 120 0.851 102.12
Total 102.12 kg 293.8 30002.86
3 Transportation cost dist(km) wt(quintal)
HDPE pipe 17 2.0424 34.72 qnt/km 14.7 510.384
4 Refilling work 1 120 0.3 0.2 7.20 m3 180.25 1297.80
Sub total 36483.12
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f
S.N. Discription of items no. Length Breadth Height Quantity unit Rate
1 Earthwork for
Pit 1 10.00 5.00 1.00 50.00
50.00 m3 432.60
Sub total
gfno
Amount Remarks
21630.00
21630.00
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
S.N. Discription of items no. Length Breadth Height Quantity unit Rate Amount
1 Earthwork for angle post 53 0.30 0.30 0.30 1.43 m3 432.60 618.62
2 Angle purchase kg/m
40*40*5 mm 53 2.1 3 333.90 96.05 32071.10
50*50 mm 10 gauge
5 1 80 1.5 120 m 565.00 67800.00
fencing wire purchase
Sub total 117023.45
Remarks
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f
7 lku Sofr/ 1 1 LS
8 l6y s6/ 1 1 LS
9 kfgL 6\ofªsL !))) ln= 1 1 LS
10 kf7fkf7L v/Lb tyf Jj:yfkg 25 25 LS
11 Hoarding board 1 1 LS
Sub total
{zgfno
te
3.15
1.8
489.73 39168.6054
10000 20000
242.95 58308
7000 7000
2500 17500
11114.49 11670.2145
8000 8000
1500 1500
12000 12000
6000 150000
5000 5000
b total 330146.82
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f
#REF!
sfo{;DkGg k|ltj]bg
kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{ d=n]=k=kmf=g+= M–
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª
S.N. Description of items No. Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork for pipeline 1 110 0.3 0.3 9.90 m3 432.60 4282.74
2 HDPE Pipe kg/m
(63 mm 6kg/cm2) 1 120 0.851 102.12
Total 102.12 kg 293.8 30002.86
3 Transportation cost dist(km) wt(quintal)
HDPE pipe 17 2.0424 34.72 qnt/km 14.7 510.384
4 Refilling work 1 110 0.3 0.2 6.60 m3 180.25 1189.65
Sub total 35985.63
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f
S.N. Discription of items no. Length Breadth Height Quantity unit Rate Amount
1 Earthwork for
Pit 1 10.00 5.00 1.10 55.00
55.00 m3 432.60 23793.00
S.N. Discription of items no. Length Breadth Height Quantity unit Rate Amount
1 Earthwork for angle post 53 0.30 0.30 0.30 1.43 m3 432.60 618.62
2 Angle purchase kg/m
40*40*5 mm 53 2.1 3 333.90 96.05 32071.10
50*50 mm 10 gauge
5 1 80 1.5 120 m 565.00 67800.00
fencing wire purchase
Sub total 117023.45
Remarks
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f
S.N Description of items No Length Breadth Height Quantity Unit Rate Amount Remarks
20 mm Thick 1:4 Cement sand Plaster
1
work
khor
Internal wall 1 16.65 1.55 25.81
floor 1 11.00 5 55.00
80.81 m2 489.73 39575.0813
2 Metal gate 2 2.00 LS 10000 20000
3 Fiber sheet 20 12.00 240.00 rf 242.95 58308
4 Fiber sheet installation cost 1 1.00 LS 7000 7000
5 Partition door 7 7.00 LS 2500 17500
6 Stone masonry wall 1:4 c/s
Partition wall 1 5.00 0.3 0.71 1.07 m3 11114.49 11892.5043
#REF!
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f
gflk lstfa