Вы находитесь на странице: 1из 58

uG8sL k|b]z, kf]v/f

Cost Estimate

###
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª
Government of Nepal
Ministry of Federal Affairs and Local Developoment
Office of District Development Committee
District Technical Office
Gorkha
RATE ANALYSIS

Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
1 Site clearance for1Sqm Unskill 0.23 700 161.00 Tools & Plant 3 % of labour cost 4.83 4.83 16.58 1.54 U/D A.(3)
1 Site clearance for1Sqm Unskill 0.04 700 28.00 Tools & Plant 3 % of labour cost 0.84 0.84 28.84 2.68 DoLIDAR 1-1.6
dismentaling of old
bldg(mud mortar) Unskill 1.06 700 742.00 Tools & Plant 3 % of labour cost 22.26 22.26 m3 764.26
Skill 0.054 955 51.57 Tools & Plant 3 % of labour cost 1.55 1.55 53.12
roof dismentaling work Unskill 0.081 700 56.70 Tools & Plant 3 % of labour cost 1.70 1.70 m2 58.40
111.52

2
Earthwork in excavation in

a ordinary soft soil- For 1 m3 Unskill 0.50 700 350.00 Tools & Plant 3 % of labour cost 10.50 10.50 360.50 10.22 5.2-1.2.2(a)
b Hard soil- For 1 m3 Unskill 0.60 700 420.00 Tools & Plant 3 % of labour cost 12.60 12.60 432.60 12.26 5.2-1.2.2(b)
c Soft Rock- For 1 m3 Unskill 1.00 700 700.00 Tools & Plant 3 % of labour cost 21.00 21.00 721.00 20.43 5.2-1.2.2(c)
d Medium Rock- For 1 m3 Unskill 3.00 700 2100.00 Tools & Plant 3 % of labour cost 63.00 63.00 2163.00 61.30 5.2-1.2.2(d)

e Hard Rock- For 1 m3 (no


chino) Unskill 5.00 700 3500.00 Tools & Plant 3 % of labour cost 105.00 105.00 3605.00 102.16 5.2-1.2.2(e)
with chino Unskill 24.00 700 16800.00 Tools & Plant 4 % of labour cost 504.00 504.00 17304.00 490.37 5.2-1.2.2(e)
f. BMS- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 U/D B1)2-2

3 Backfilling in foundation
trenches with excavated
materials Unskill 0.25 700 175.00 Tools & Plant 3 % of labour cost 5.25 5.25 180.25 5.11 U/D B2)2(25)a
Stone Solling in foundation
4
& Leveling Unskill 1.50 700 1050.00 Tools & Plant 3 % of labour cost 31.50 31.50 1081.50
Blockstone 1.00 1602.00 1200.00 1602.00 1200.00 1602.00 DoLIDAR
Bondstone 0.20 1602.00 1200.00 320.40 240.00 320.40
Total 1050.00 1471.50 2521.50 71.46 49)17-6
Formworks of Local wood
5
for Beam/Slab Skill 0.150 955 143.25 Local Wood 0.0070 45000.00 45000.00 315.00 315.00 m3 U/D+DoLIDAR
For 1 Sq.m. Unskill 0.200 700 140.00 Nails 0.25 113.00 100.00 28.25 25.00 kg 39)9.a
Total 283.25 343.25 340.00 626.50 58.23
Quantity of wood required for 1 sqm formwork = 0.0526 cum.
Wood can be used 6 times for the formwork and after then 25% cost
of the wood is recovered. So the quantity of wood required for 1 sqm = 0.00658 cum.
Formworksof Local wood for
6
Beam/Slab Skill 0.375 955 358.13 Local Wood 0.0070 45000.00 45000.00 315.00 315.00 m3 U/D
For 1 Sq.m. Unskill 0.562 700 393.40 Nails 0.25 113.00 100.00 28.25 25.00 kg E1 8(3) Ka
Total 751.53 343.25 340.00 1094.78 101.76
Quantity of wood required for 1 sqm formwork = 0.0526 cum.
Wood can be used 6 times for the formwork and after then 25% cost
of the wood is recovered. So the quantity of wood required for 1 sqm = 0.00658 cum.

7
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.17 21288 19000.00 3618.96 3230.00 MT
M10(P.C.C. 1:4:8) Unskill 4.00 700 2800.00 Agg.40mm 0.65 4262.00 4262.00 2770.30 2770.30 cu.m U/D
and wall - For 1 m3 Agg.20mm 0.24 4262.00 4262.00 1022.88 1022.88 cu.m D1 7-2b
Sand 0.47 2300.00 2300.00 1081.00 1081.00 cu.m
Total 3755.00 8493.14 8104.18 12248.14 347.10

8
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.22 21288 19000 4683.36 4180.00 MT
M10(P.C.C. 1:3:6) Unskill 4.00 700 2800.00 Agg.40mm 0.65 4262.00 4262.00 2770.30 2770.30 cu.m U/D
and wall - For 1 m3 Agg.20mm 0.24 4262.00 4262.00 1022.88 1022.88 cu.m D1 7-2c
Sand 0.47 2300.00 2300.00 1081.00 1081.00 cu.m
Total 3755.00 9557.54 9054.18 13312.54 377.26

9
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.32 21288.0 19000.0 6812.16 6080.00 MT
M15(P.C.C. 1:2:4) Unskill 4.00 700 2800.00 Agg.40mm 0.52 4262.0 4262.0 2216.24 2216.24 cu.m U/D
and wall - For 1 m3 Agg.20mm 0.22 4262.0 4262.0 937.64 937.64 cu.m D1 7-2d
For Foundation Agg.10mm 0.11 4262.0 4262.0 468.82 468.82 cu.m
Sand 0.445 2300.00 2300.00 1023.50 1023.50 cu.m
Total 3755.00 11458.36 10726.20 15213.36 431.13
10 Skill 0.80 955 764.00 Cement 0.32 21288.0 19000.0 6812.16 6080.00 MT
Unskill 7.00 700 4900.00 Agg.40mm 0.52 4262.0 4262.0 2216.24 2216.24 cu.m Nirman tatha Ya.
M15(1:2:4) mix plain cement
concrete works in
superstructure including
material collection &30m
Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
M15(1:2:4) mix plain cement
concrete works in Agg.20mm 0.22 4262.0 4262.0 937.64 937.64 cu.m 7-4b
superstructure including Agg.10mm 0.11 4262.0 4262.0 468.82 468.82 cu.m
material collection &30m
lead - For 1 m3 Sand 0.445 2300.0 2300.0 1023.50 1023.50 cu.m
Total 5664.00 11458.36 10726.20 17122.36 485.22

11 Skill 0.80 955 764.00 Cement 0.40 21288.0 19000.0 8515.20 7600.00 MT
M20(1:1.5:3) mix plain
cement concrete works in Unskill 7.00 700 4900.00 Agg.20mm 0.57 4262.00 4262.00 2429.34 2429.34 cu.m U/D
superstructure including
material collection &30m Agg.10mm 0.29 4262.00 4262.00 1235.98 1235.98 cu.m D2 7b
lead - For 1 m3
Sand 0.425 2300.00 2300.00 977.50 977.50 cu.m

Total 5664.00 13158.02 12242.82 18822.02 533.39 U/D


12 Skill 1.50 955 1432.50 Cement 0.159 21288 19000 3384.79 3021.00 MT C6 6(a)1-2
Random Rubble Stone
masonry work in 1:4 C/S Unskill 5.00 700 3500.00 Sand 0.45 2300.00 2300.00 1035.00 1035.00 cu.m
mortar - For 1 m3 including
material collection,preparation Blockstone 1.00 1602.00 1602.00 1602.00 1602.00 cu.m
of mortar with 5m lift and 10m
lead
Bondsotne 0.10 1602.00 1602.00 160.20 160.20 cu.m
Total 4932.50 6181.99 5818.20 cu.m 11114.49 314.97
13 Skill 1.50 955 1432.50 Cement 0.106 21288.0 19000.0 2256.53 2014.00 MT U/D
Random Rubble Stone
masonry work in 1:6 cement Unskill 5.00 700 3500.00 Sand 0.47 2300.00 2300.00 1081.00 1081.00 cu.m C6 6(a)1-3
sand mortar - For 1 m3
Blockstone 1.00 1602.00 1602.00 1602.00 1602.00 cu.m
including material
collection,preparation of
mortar with 5m lift and 10m
lead
Bondsotne 0.10 1602.00 1602.00 160.20 160.20 cu.m
Total 4932.50 5099.73 4857.20 cu.m 10032.23 284.30
14 Skill 0.50 955 477.50 Blockstone 1.00 1602 1602 1602.00 1602.00 cu.m DoLIDAR
Dry stone masonry work
with rubble stone For 1 m3 Unskill 1.50 700 1050.00 Bondsotne 0.10 1602 1602 160.20 160.20 cu.m 38. 8
Total 1527.50 1762.20 1762.20 cu.m 3289.70
15 Dry Random rubble Skill 1.00 955 955.00 Blockstone 1.00 1602 1602 1602.00 1602.00 cu.m U/D
Masonary stone masonry
work with rubble stone For 1
m3 Unskill 2.00 700 1400.00 Bondsotne 0.10 1602 1602 160.20 160.20 cu.m C6 6-2-1
Total 2355.00 1762.20 1762.20 cu.m 4117.20 116.68

16 Skill 1.00 955 955.00 Blockstone 1.00 1602.00 1602.00 1602.00 1602.00 cum Urban Devemt
Random rubbel Stone
masonry in mud mortar - Unskill 2.25 700 1575.00 Bondstone 0.10 1602.00 1602.00 160.20 160.20 cum C6 6-2-2
For 1 m3
Mud 0.42 280.00 280.00 117.60 117.60 cum
Total 2530.00 1879.80 1879.80 4409.80 124.97
17 Skill 1.50 955 1432.50 Cement 0.100 21288.0 19000.0 2128.80 1900.00 MT Urban Devemt
Chimney Bhatta Brick
masonry work in 1:4 C/S Unskill 2.20 700 1540.00 Sand 0.28 2300.00 2300.00 644.00 644.00 cu.m 5(1)B-2
mortar - For 1 m3 including
material collection,preparation
of mortar with 30m lead
Brick 560.00 13.56 12.00 7593.60 6720.00 cu.m
Total 2972.50 10366.40 9264.00 cu.m 13338.90 378.01

18 Urban Devemt
Chimney Bhatta Brick Skill 1.50 955 1432.50 Cement 0.070 21288.0 19000.0 1490.16 1330.00 MT
masonry work in 1:6 C/S
mortar in Superstructur- For 1 Unskill 2.20 700 1540.00 Sand 0.30 2300.00 2300.00 690.00 690.00 cu.m 5(1)B-3
m3 including material
collection,preparation of
mortar with 30m lead
Brick 560.00 13.56 12.00 7593.60 6720.00 cu.m
Total 2972.50 9773.76 8740.00 cu.m 12746.26 361.21
Total 5945.00 19547.52 17480.00 cu.m 25492.52 722.42
19 Skill 34.00 955 32470.0 wood 1.10 45000.0 45000.0 49500.0 49500.0 m3 Urban Devemt
Sal wood work in Door Unskill 3.40 700 2380.00 screw 184.00 1.47 1.30 270.48 239.20 no G1 10-1
&Window Frame For 1 m3
Holdfast 92.00 28.25 25.00 2599.00 2300.00 no

Total 34850.0 52369.48 52039.2 87219.5 2471.7


20 Sal wood work in pannelled Skill 4.730 955 4517.15 wood 0.0397 45000.00 45000.0 1786.50 1786.50 m3 Urban Devemt
Door &Window Shutter For Unskill 0.473 700 331.10 Hinges 4" 2.8382 33.90 30.00 96.21 85.15 No G2 10-2
1 m2 (1.07*1.982=2.114)
Tower bolt 6" 0.4730 50.85 45.00 24.05 21.29 No
Tower bolt 10" 0.4730 67.80 60.00 32.07 28.38 No
Handle 6" 0.9461 28.25 25.00 26.73 23.65 No
L-drop 10"x12" 0.4730 226.00 200.00 106.90 94.60 no
Screw 14.1911 1.47 1.30 20.86 18.45 LS
Total 4848.25 2093.32 2058.02 6941.57 645.22
21 38mmx75mm Sal wood Skill 4.036 955 3854.38 wood 0.02197 45000.00 45000.0 988.65 988.65 m3 Urban Devemt
frame &4mm glazed Shutter
work in Door &Window For
1 m2
Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
38mmx75mm Sal wood Rs. Rs. VAT VAT VAT VAT in m in ft
frame &4mm glazed Shutter Unskill 0.404 700 282.80 4mm Glass 0.48655 723.20 640.00 351.87 311.39 Sq.m G3 10(4)
work in Door &Window For
1 m2 Hinges 3" 3.58744 20.34 18.00 72.97 64.57 No
Tower bolt4" 1.79372 45.20 40.00 81.08 71.75 No
Handle 4" 0.89686 33.90 30.00 30.40 26.91 No
Screw 13.45291 1.47 1.30 19.78 17.49 LS
Total 4137.18 1544.75 1480.76 5681.93 528.14
22 Localwood Beams work For Skill 17.65 955 16855.8 wood 1.050 45000.00 45000.00 47250.00 47250.00 m3 Urban Devemt
1 Cu. m Unskill 1.760 700 1232.00 Nails 1.000 113.00 100.00 113.00 100.00 kg F 19 10(17)
Total 18087.8 47363.00 47350.00 65450.80 1854.8
23 25 mm Locall wood Eaves Skill 0.143 955 136.57 wood 0.0275 45000.00 45000.00 1237.50 1237.50 m3 Urban Devemt
Boards for 1 sq.m Unskill 0.014 700 9.80 Nails 0.1000 113.00 100.00 11.30 10.00 kg F20 10(19)
Total 146.37 1248.80 1247.50 1395.17 129.68
24 25 mm Local wood Skill 0.143 955 136.57 wood 0.0275 45000.00 45000.00 1237.50 1237.50 m3 Urban Devemt
Plankings 1 sq.m Unskill 0.014 700 9.80 Nails 0.1000 113.00 100.00 11.30 10.00 kg F20 10(19)
Total 146.37 1248.80 1247.50 1395.17 129.68
25 3 mm plywood shutter on 2 Skill 3.118 955 2977.69 wood 0.01541 45000.00 45000.00 693.45 693.45 m3 Urban Devemt
sides with 38 mm salwood Unskill 0.312 700 218.40 Plywood 2.07127 218.86 193.68 453.32 401.16 Sq.m G4 10(7)
frame for 1 Sq. m
Hinges 4" 1.33630 33.90 30.00 45.30 40.09 No
Tower bolt 6" 0.89087 50.85 45.00 45.30 40.09 No
Mortise Lock 0.44543 904.00 800.00 402.67 356.34 No
Handle 4" 0.89087 33.90 30.00 30.20 26.73 No
Screw 13.36303 1.47 1.30 19.64 17.37 LS
Total 3196.09 1689.88 1575.23 4885.97 454.15
26 28#Plain Sheet shutter on 2 Skill 3.118 955 2977.69 wood 0.015412 45000.00 45000.00 693.54 693.54 m3 Urban Devemt
sides with 38 mm salwood Unskill 0.312 700 218.40 Plain Sheet 2.071269 384.20 340.00 795.78 704.23 Sq.m G4 10(9)
frame for 1 Sq. m
Hinges 4" 1.336303 33.90 30.00 45.30 40.09 No
Tower bolt 6" 0.890869 50.85 45.00 45.30 40.09 No
L-drop 10"x12" 0.445434 226.00 200.00 100.67 89.09 No
Handle 4" 0.445434 33.90 30.00 15.10 13.36 No
Screw 13.363029 1.47 1.30 19.64 17.37 LS
Total 3196.09 1715.33 1597.77 4911.42 456.52
CGI sheet Roofing for 1 Sq. 0.38 mm th Colour
27 Skill 0.110 955 105.05 CGI Sheet 0.071000 10735.00 9500.00 762.19 674.50 Bundle Urban Devemt
m
Unskill 0.125 700 87.50 Nut Bolt 8 mm 28.25 25.00 0.00 0.00 No F3 9(1)
J-Hook 6" 29.38 26.00 0.00 0.00 No
Bitumin Washer 1.13 1.00 0.00 0.00 No
Total 192.55 762.19 674.50 954.74 88.74
Plain sheet Roofing for 1 m 0.45 mm th Plain
28 Skill 955 Urban Devemt
0.200 191.00 sheet 1.200000 384.20 340.00 461.04 408.00 Rm
Unskill 0.300 700 210.00 Nut Bolt 8 mm 1.000000 28.25 25.00 28.25 25.00 No F2 9(2)

Total
Two coat Enamel Painting 401.00 489.29 433.00 890.29 271.43
29 with one coat Primer in Skill 0.120 955 114.60 Primer 0.0810 329.10 291.40 26.66 23.60 Ltr Urban Devemt
doors & winndows for 1 sq
m Unskill 0.080 700 56.00 Enamel 0.16 474.60 420.00 75.94 67.20 Ltr J5 13(5)a,b,c
Total 170.60 102.60 90.80 m2 273.20 25.39
30 Two Coat waterproof Skill 0.050 955 47.75 Snowcem 0.4850 88.41 78.40 42.88 38.02 Kg Urban Devemt
cement (Snowceme) Paint on
Plastered Surface for 1 Sq m Unskill 0.050 700 35.00 J4 13(4)b
Total 82.75 42.88 38.02 m2 125.63 11.68
31 Skill 0.1200 955 114.60 Cement 0.00538 21288.00 19000.00 114.53 102.22 MT Urban Devemt
12.5 mm Thick 1:4 Cement
sand Plaster work in ceiling
for 1Sq. m Unskill 0.1600 700 112.00 Sand 0.01460 2300.00 2300.00 33.58 33.58 cu.m I1) 12-1c
Total 226.60 148.11 135.80 374.71 34.83
32 Skill 0.1200 955 114.60 Cement 0.00382 21288.00 19000.00 81.32 72.58 MT Urban Devemt
12.5 mm Thick 1:6 Cement
sand Plaster work in ceiling
for 1Sq. M Unskill 0.1600 700 112.00 Sand 0.01570 2300.00 2300.00 36.11 36.11 cu.m I1) 12-1d
Total 226.60 117.43 108.69 344.03 31.98
33 Skill 0.1400 955 133.70 Cement 0.00810 21288.00 19000.00 172.43 153.90 MT Urban Devemt
20 mm Thick 1:4 Cement
sand Plaster work excluding
ceiling for 1Sq. M Unskill 0.1900 700 133.00 Sand 0.02200 2300.00 2300.00 50.60 50.60 cu.m I4) 12(4)b
Total 266.70 223.03 204.50 489.73 45.52
34 Skill 0.1200 955 114.60 Cement 0.00538 21288.00 19000.00 114.53 102.22 MT Urban Devemt
12.5 mm Thick 1:4 Cement
sand Plaster work excluding
ceiling for 1Sq. m Unskill 0.1600 700 112.00 Sand 0.01460 2300.00 2300.00 33.58 33.58 cu.m I1) 12-1c
Total 226.60 148.11 135.80 374.71 34.83
35 Skill 0.080 955 76.40 Cement 0.00110 21288.00 19000.00 23.42 20.90 MT Urban Devemt
Flush ruled pointing in 1:3
C/S mortar On stone
masonry wall For 1 m2
Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
Flush ruled pointing in 1:3
C/S mortar On stone
masonry wall For 1 m2 Unskill 0.100 700 70.00 Sand 0.00200 2300.00 2300.00 4.60 4.60 cu.m I 10. 14(2)c
Total 146.40 28.02 25.50 m2 174.42 16.21

36 3 mm thick cement punning


-For 1 m2 Skill 0.10 955 95.50 Cement 0.00532 21288.00 19000.00 113.25 101.08 MT Urban Devemt
Unskill 0.10 700 70.00 H20 11-20
Total 165.50 113.25 101.08 278.75 25.91

37 Porcelain Glazed Tiles work Skill 955 Urban Devemt


On Wall in 1:4 Cement Sand 1.300 1241.50 Porcelain glazed Tile 1.10000 729.79 645.83 802.77 710.41 sqm
mortar for 1 Sq. m Unskill 0.450 700 315.00 Cement 0.00560 21288.00 19000.00 119.21 106.40 MT H6 11-7
Sand 0.01520 2300.00 2300.00 34.96 34.96 cu.m
White Cement 0.32280 29.38 26.00 9.48 8.39 kg
Total 1556.50 966.42 860.16 2522.92 234.51

38 Porcelain Glazed Tiles work Skill 955 Urban Devemt


On Floor in 1:4 Cement 1.300 1241.50 Tile 1.10000 948.74 839.59 1043.61 923.55 sqm
Sand mortar for 1 Sq. m Unskill 0.450 700 315.00 Cement 0.00560 21288.00 19000.00 119.21 106.40 MT H6 11-7
Sand 0.01520 2300.00 2300.00 34.96 34.96 cu.m
White Cement 0.32280 29.38 26.00 9.48 8.39 kg
Total 1556.50 1207.26 1073.30 2763.76 256.89
39 Reinfocement for RCC work Skill 0.012 955 11.46 M.S. Rod 0.001050 98580 87400 104 91.77 MT Urban Devemt
in position and binding of
M.S. rod for R.C.C. works -
for 1 kg D9 7-5
Unskill 0.012 700 8.40 Binding wire 0.01000 113.00 100.00 1.13 1.00 Kg
Total 19.86 105.13 92.77 124.99
40 Making and fixing 3*20 Skill 0.00 Aluminium paint 0 0.00 ltr Urban Devemt
mm Iron Grill including
aluminium paint - for 1
Sqm=(17 kg) M1 24-1a
Unskill 0.00 Iron grill 1.00000 2305.20 2040.00 2305.20 2040.00 sqm
Total 0.00 2305.20 2040.00 2305.20 214.27
38mm dia stainless steel pipe
41 for handrailing, 38 mm dia Skill 0.8503 955 38 mm dia stainless Urban Devemt
stainless steel pipe for 812.04 steel pipe 1.69290 395.50 350.00 669.54 592.52 m
vertical post are placing c/c
spacing 2m and horizontal
Unskill 1.2404 700 25 mm dia stainless M 15
two layer 25 mm dia
868.28 steel pipe 2.18579 226.00 200.00 493.99 437.16 m
stainless steel pipe member
are laying and jointing for
railing work. for 1 Sq. m

Gas welding for


stainless steel pipe 1.00000 150.00 150.00 150.00 150.00 Sqm
Total 1680.32 1313.53 1179.68 2993.85 278.28
42 Providing and fixing Blak Skill 0.0506 955 48.32 Black Iron Pipe 1.00000 107.35 95.00 107.35 95.00 kg Urban Devemt
Iron Pipe Truss including Unskill 0.0674 700 47.18 Nut Bolt 0.91001 28.25 25.00 25.71 22.75 Nos
primer paint for 1 Kg
Primer Paint 3.37041 3.37 0.00 0.00 LS

Total 95.50 133.06 117.75 228.56 21.24


43 3"(75mm) thick cement Skill 0.1250 955 119.38 Cement 0.0260 21288.0 19000.0 553.49 494.00 MT
concrete floor (1:2:4) with Unskill 0.3000 700 210.00 Agg.20mm 0.0680 4262.0 4262.0 289.82 289.82 cu.m U/D
Cement Punning for 1Sq.m
Sand 0.0340 2300.00 2300.00 78.20 78.20 cu.m H1 11-1d
Total 329.38 921.51 862.02 1250.89 116.27
44 38 mm thick cement concrete Skill 0.1250 955 119.38 Cement 0.0130 21288.0 19000.0 276.74 247.00 MT
floor (1:2:4) with Cement Unskill 0.2000 700 140.00 Agg.12mm 0.0360 4262.0 4262.0 153.43 153.43 cu.m U/D
Punning 1 Sq.m
Sand 0.0180 2300.0 2300.0 41.40 41.40 cu.m H1 11-1b
Total 259.38 471.57 441.83 730.95 67.94
CGI sheet Roofing for 1 Sq.
27 m Skill 955 Urban Devemt
0.110 105.05 26 guase CGI Sheet 0.071000 10735.00 10735.00 762.19 762.19 Bundle
Unskill 0.125 700 87.50 Nut Bolt 8 mm 3.000000 0.00 28.25 0.00 84.75 No F3 9(1)
J-Hook 6" 2.500000 0.00 29.38 0.00 73.45 No
Bitumin Washer 5.500000 0.00 1.13 0.00 6.22 No
Total 192.55 762.19 926.61 954.74 88.74

2 955 1910
2 700 1400 astar 8.000000 327.7 2,621.60 ltr
2 955 1910 1st coat
28 Distemper 2 700 1400 diatemper 6.5 214.7 190 1395.55 kg
1.8 955 1719 2st coat
1.8 700 1260 diatemper 5 214.7 190 1073.5 kg
9599 5,090.65 100 m2 14689.65
m2 146.8965
Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft

3 955 2865
3 700 2100 astar 8.000000 327.7 2,621.60 ltr
5 955 4775
29 inamel paints 2 700 1400 1st coat inamel 9 474.6 190 4271.4 ltr
4 955 3820
3 700 2100 2st coat 7 474.6 190 3322.2 ltr
17060 10,215.20 100 m2 27275.2
m2 272.752

1.56
187.2
Government of Nepal
Ministry of Local Development
Office of District Development Committee
District Technical Office
Gorkha
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM) Amount
1 Skill Labour 955.00 955.00 955.00 md
2 Unskilled Labour 700.00 700.00 700.00 md
3 Painter 955.00 955.00 955.00 md
4 Sand 2300.00 2300.00 2,300.00 m3 1600.00 0.14 0.75 0.00 0.00 0.00
5 Aggregate 40mm 2750.00 4262.00 4,262.00 m3 1800.00 0.14 0.59 6.00 1512.00 0.00 0.00
6 Aggregate 20mm 2750.00 4262.00 4,262.00 m3 1800.00 0.14 0.59 6.00 1512.00 0.00 0.00
7 Aggregate 10mm 2750.00 4262.00 4,262.00 m3 1800.00 0.14 0.59 6.00 1512.00 0.00 0.00
8 Stone 1350.00 1602.00 1,602.00 m3 1800.00 0.14 0.59 1.00 252.00 0.00 0.00
9 Mud for masonry 290.00 290.00 290.00 m3 1400.00 0.14 0.59 0.00 0.00 0.00
10 Sal wood 45000.00 45000.00 45,000.00 m3 600.00 0.14 0.59 0.00 0.00 0.00
11 Local Wood 45000.00 45000.00 45,000.00 m3 600.00 0.14 0.59 0.00 0.00
12 Sisau 70560.00 70560.00 70,560.00 m3 600.00 0.14 0.59 0.00 0.00
13 Cement(NS Mark OPC) 17600.00 2288.00 21288.00 19,000.00 mt 1000.00 0.14 0.59 10.00 1400.00 0.00 0.00
14 Brick(Chimney ) 12.00 1.56 13.56 12.00 Nos 2.50 0.14 0.00 0.00 0.00
15 Nail 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
31 Reinforcement Bar(10-40mm) 86000.00 11180.00 98580.00 87,400.00 mt 1000.00 0.14 0.59 10.00 1400.00 0.00 0.00
32 GI Wire 12Swg (Heavy Coating) 105.00 13.65 118.65 105.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
33 GI Wire 10Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
34 GI Wire 8Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
35 3mm Glass 500.00 65.00 565.00 500.00 m2 8.40 0.14 0.59 0.00 0.00 0.00
36 4mm Glass 640.00 83.20 723.20 640.00 m2 11.20 0.14 0.59 0.00 0.00 0.00
37 5mm Glass 750.00 97.50 847.50 750.00 m2 14.00 0.14 0.59 0.00 0.00 0.00
38 Lime 18.00 2.34 21.74 19.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
39 Gum (Rathicol) 200.00 26.00 227.40 201.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
40 Primer (wood) 290.00 37.70 329.10 291.40 Ltr 1.00 0.14 0.59 10.00 1.40 0.00 0.00
41 Enamel (Tayari) 420.00 54.60 474.60 420.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
42 Alumunium Paint 500.00 65.00 565.00 500.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
43 Sand Paper 10.00 1.30 11.30 10.00 Sheet 0.14 0.59 0.00 0.00 0.00
44 Red Oxide No 1 350.00 45.50 395.50 350.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00

______________ _______________ ______________


Prepared By Checked by Approved By
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM) Amount
45 Binding wire 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
46 CGI Sheet 0.38 mm th 9500.00 1235.00 10735.00 9,500.00 bun. 65.00 0.14 0.59 0.00 0.00 0.00
47 CGI Sheet 0.4 mm th Colour 9300.00 1209.00 10509.00 9,300.00 bun. 60.00 0.14 0.59 0.00 0.00 0.00
48 Plain sheet 28 gauge 340.00 44.20 384.20 340.00 rm 1.00 0.14 0.59 0.00 0.00 0.00
49 3mm plywood 193.68 25.18 218.86 193.68 m2 2.00 0.14 0.59 0.00 0.00 0.00
50 Snowcem Paint 77.00 10.01 88.41 78.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
51 Chimney Brick 12.00 1.56 13.56 12.00 nos 2.80 0.14 0.59 0.00 0.00 0.00
52 Wall Tile (Indian) 8"x6" 645.83 83.96 729.79 645.83 m2 12.00 0.14 0.59 0.00 0.00 0.00
53 Tile floor (Indian) 8"x8" 839.59 109.15 948.74 839.59 m2 15.00 0.14 0.59 0.00 0.00 0.00
54 White Cement 26.00 3.38 29.38 26.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
55 2X 500 gauge polythene 83.00 10.79 93.79 83.00 m2 0.14 0.59 0.00 0.00 0.00
56 Railing with GI & Black Pipe 250.00 32.50 282.50 250.00 sqft 2.50 0.14 0.59 0.00 0.00 0.00
57 Nut Bolt 8 mm 25.00 3.25 28.25 25.00 No 0.14 0.59 0.00 0.00 0.00
58 Bitumin Washer 1.00 0.13 1.13 1.00 No 0.14 0.59 0.00 0.00 0.00
59 J-Hook 4" 22.00 2.86 24.86 22.00 No 0.14 0.59 0.00 0.00 0.00
60 J-Hook 6" 26.00 3.38 29.38 26.00 No 0.14 0.59 0.00 0.00 0.00
61 Iron Grill(Ready made) 120.00 15.60 135.60 120.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
38 mm dia 16Gauge thick
62 350.00 45.50 395.50 350.00 Rm 0.14 0.59
stainless steel pipe 2.50 0.00 0.00 0.00
25 mm dia 16Gauge
63 200.00 26.00 226.00 200.00 Rm 0.14 0.59
thickstainless steel pipe 1.50 0.00 0.00 0.00
Gas welding for stainless steel
64 150.00 19.50 169.50 150.00 sq m 0.14
pipe 0.00 0.00 0.00
65 Black Iron Pipe 1.8 mm Thick 95.00 12.35 107.35 95.00 kg 1.00 0.14 0.00 0.00 0.00

______________ _______________ ______________


Prepared By Checked by Approved By
B..Hard Soil
Norms No: 5.2-1.2.2(b) DoLIDAR
Unit :cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 0.000 870.00 -
Unskill Md 0.60 650.00 390.00
Tools andSub-Total
plants 390.00
@3% 11.70
Total 401.70
Item: Dry Stone Pitching/Soling & Levelling Works
Norms No: 49.17-6 DoLIDAR
Unit :m3
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md - 870.00 -
Unskill Md 1.00 650.00 650.00
Material Stone m3 1.10 1,602.00 1,762.20
Sub-Total
Tools and plants 2,412.20
@3% 72.37
Total 2,484.57
15 % Overhead
Unit Rate 2,484.57

Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:4:8
Norms No: 41(7-2)c
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.00 650.00 2,600.00
Material Cement ( OPC NS MT 0.17 - -
mark)
Agg 40 mm cu.m 0.65 - -
Agg 20 mm cu.m 0.24 - -
Coarse sand cu.m 0.47 - -
Total 3,470.00 cft
Unit Rate 3,470.00 98.26

Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:3:6
Norms No: 42(7-2)c
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.00 650.00 2,600.00
Material Cement ( OPC NS MT 0.22 - -
mark)
Agg 40 mm cu.m 0.65 - -
Agg 20 mm cu.m 0.24 - -
Coarse sand cu.m 0.47 - -
Sub-Total 3,470.00
15 % Overhead 520.50
Unit Rate 3,990.50
Item: plain cement concrete works in foundation including material collection &30m lead
B.M 15 Grade (1:2:4 mix by volume)
Norms No: 41.11.b DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.06 650.00 2,639.00
Cement ( OPC NS
Material mark) MT 0.32 20,804.00 6,657.28
Agg 40 mm cu.m 0.52 - -
Agg 20 mm cu.m 0.22 1,850.00 407.00
Agg 10 mm cu.m 0.11 - -
Coarse sand cu.m 0.440 2,300.00 1,012.00
Sub-Total 11,585.28
15 % Overhead 1,737.79
Unit Rate 13,323.07
Item: plain cement concrete works in superstructure including material collection &30m lead
A. 1:2:4 mix
Norms No: 44(7-4)a,
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.80 870.00 696.00
Unskill Md 7.00 650.00 4,550.00
Material Cement ( OPC NS MT 0.32 20,804.00 6,657.28
mark)
Agg 40 mm cu.m 0.52 - -
Agg 20 mm cu.m 0.22 1,850.00 407.00
Agg 10 mm cu.m 0.11 - -
Coarse sand cu.m 0.445 2,300.00 1,023.50
Sub-Total 13,333.78
15 % Overhead 2,000.07
Unit Rate 15,333.85

Item: plain cement concrete works in superstructure including material collection &30m lead
B. 1:1.5:3 mix
Norms No: 7(4)b,45
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.80 870.00 696.00
Unskill Md 7.00 650.00 4,550.00
Material Cement ( OPC NS MT 0.40 20,804.00 8,321.60
mark)
Agg 20 mm cu.m 0.57 1,850.00 1,054.50
Agg 10 mm cu.m 0.29 - -
Coarse sand cu.m 0.425 2,300.00 977.50
Sub-Total 15,599.60
15 % Overhead 2,339.94
Unit Rate 17,939.54
Item: Reinforcement for RCC works including procuring steel, bending, placing, bindibg and fixing in
position all complite RCC works
Norms No: 40-10
Unit : Kg.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.0070 870.00 6.09
Unskill Md 0.0070 650.00 4.55
Material M.S. Rod MT 0.00105 93,790.00 98.48
Binding wire kg 0.01000 113.00 1.13
-
-
Sub-Total 110.25
15 % Overhead 16.54
Unit Rate 126.79

A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:4
Norms No : 38.8-A. c DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.24 md 650.00 2,106.00

Material Cement ( OPC NS


mark) 0.116 MT 20,804.00 2,413.26
RubbleStone 1.10 M3 1,602.00 1,762.20
Sand 0.47 M3 2,300.00 1,081.00
Sub-Total 8,667.46
15 % Overhead 1,300.12
Unit Rate 9,967.58

B. Random rubble Masonary 1:6


Norms No : 6(1)a-3,32
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 5.00 md 650.00 3,250.00
Material Cement ( OPC NS 0.106 MT 20,804.00 2,205.22
mark)
Blockstone 1.00 M3 20,804.00 20,804.00
Bondstone 0.10 M3 1,602.00 160.20
Sand 0.47 M3 2,300.00 1,081.00
Sub-Total 28,805.42
15 % Overhead 4,320.81
Unit Rate 33,126.23

A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:6
Norms No : 38.8-A. d DoLIDAR
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.29 md 650.00 2,138.50
Cement ( OPC NS
Material mark) 0.092 MT 20,804.00 1,913.97
Rubble Stone 1.10 M3 1,602.00 1,762.20
Sand 0.50 M3 2,300.00 1,150.00
Sub-Total 8,269.67
15 % Overhead 1,240.45
Unit Rate 9,510.12
B)12.5 mm thick plastering with cement sand mortar on brick wall or concrete surfaces including full
compensation for all labour, materials , scafolding and otter incidental required to complete tte works as per the
specifications
d). In 1:6 mix ratio
Norms No : 37.7-9.4 d) DoLIDAR
Unit :100 Sq.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 15.00 md 870.00 13,050.00
Un-skill 13.70 md 650.00 8,905.00
Cement ( OPC NS
Material mark) 0.288 MT 20,804.00 5,991.55
Sand 1.58 M3 2,300.00 3,634.00
Sub-Total 31,580.55
15 % Overhead 4,737.08
Total 36,317.63
Unit Rate 363.18

C)pointing works with cement sand mortar on brick wall with all required operation including full compensation
for all labour, materials , scafolding and otter incidental required to complete tte works as per the specifications

c .In 1:3 mix ratio


Norms No : 37.7-9.3d) DoLIDAR
Unit :100 Sq.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 8.00 md 870.00 6,960.00
Un-skill 8.88 md 650.00 5,772.00
Cement ( OPC NS
Material
mark) 0.096 MT 20,804.00 1,997.18
Sand 0.29 M3 2,300.00 667.00
Sub-Total 15,396.18
15 % Overhead 2,309.43
Total 17,705.61
Unit Rate 177.06
Preparation of bedding for pipe with granular materials . It includes all labour,materials.
Norms No : 46 .15-4 DoLIDAR
Unit :1 Cub.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill md 870.00 -
Un-skill 1.00 md 650.00 650.00
Well grage granular
materials passing
Material 4.75mm sieve and
down 1.100 M3 1,400.00 1,540.00
Sub-Total 2,190.00
15 % Overhead 328.50
Unit Rate 2,518.50
Laying,fitting and fixing of hume pipe having a length of 1 m or more. Its includes all operations required to
complete the works upto atrench depth of 2.2 m below the ground level and jointing of pipes with 1:2
cement sand ratio

b.) For every subsequent pipe having length of minimum 1m, Dia 30 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.02 md 870.00 17.40
Un-skill 0.10 md 650.00 65.00
Material Cement 0.001 MT 20,804.00 20.80
Sand 0.002 m3 2,300.00 4.60
Jute, Bitumin LS 30.00 30.00
Sub-Total 82.40
15 % Overhead 12.36
Unit Rate 94.76

b.) For every subsequent pipe having length of minimum 1m Dia 60 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.050 md 870.00 43.50
Un-skill 0.200 md 650.00 130.00
Material Cement 0.003 MT 20,804.00 62.41
Sand 0.004 m3 2,300.00 9.20
Jute, Bitumin LS 40.00 40.00
Sub-Total 285.11
15 % Overhead 42.77
Unit Rate 327.88

Hence,
Total cost of 30cmdia.1m H.P. 94.76
Total cost of 60cmdia.1m H.P. 327.88
Total 45mm dia. H.P.1m(Average cost) 422.64 211.32

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(2X1X 1) (11 m2)
Unit :Per m3 44.2.a DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.09 md 650.00 58.50

Binding wire
Materials 0.95 kg 121.170 115.11
12swg(Heavy Coated)
Sub-Total 173.61
15 % Overhead -
Rate per Box
Size(2X1X1) 173.61
Rate per m3 86.81

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(3X1X 1) (16 m2)

Unit :Per m3 44.1.A.ii.b DoLIDAR


Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.13 md 650.00 84.50

Binding wire
Materials 1.3 121.17 157.52
12swg(Heavy Coated)
kg
Sub-Total 242.02
15 % Overhead -
Rate per Box
Size(3X1X1) 242.02
Rate per m3 80.67

Unit rate/m3 Gabion Box


Size(2x1x1) NRs. 86.81
Gabion Box
Size(3x1x1) NRs. 80.67

Average Unit Rate 167.48 86.81 m3


45) Packing and filling of Gabion crates with stone
Unit :1m3 45.17-6 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.3 md 870.00 261.00
Unskilled 0.75 md 650.00 487.50
Materials Stone 1.10 m3 1602.00 1762.20
Sub-Total 2,510.70
15 % Overhead -
Unit Rate 2,510.70 m3
Providing Mechine Made Heavy coated gabion Box Hexagonal Mesh size 10X12 cm,Mesh wire 10swg
(Heavy Coated),Selvedge wire 8swg (Heavy Coated),Binding wire 12swg(Heavy Coated) at site.

Size Sq.m/box Rate/Sq.


m Rate/Box Rate/Cu.m
Gabion Box 8
Size(1.5x1x1) 297.457 2379.65935 1586.44
Gabion Box 11
Size(2x1x1) 297.457 3272.0316 1,636.02
Gabion Box 16
Size(3x1x1) 297.457 4759.31869 1,586.44
1602.96667

Mechine Made Heavy coated gabion Box 1,602.97 m3


Packing and filling of Gabion crates with stone 2,510.70 m3
Sub Total Cost 4113.67
Assembling 86.81
Total Cost 4200.48
38.8 Dry Uncoursed Rubble Stone Masonry

Norms No : 38-8 DoLIDAR


Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.5 md 870.00 435.00
Unskilled 1.5 md 650.00 975.00
Materials Stone 1.10 m3 1602.00 1762.20
Sub-Total 3,172.20
15 % Overhead -
Unit Rate 3,172.20 m3

26.3-1 Riverbed Material


Unit :1m3 38-8 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 1 md 650.00 650.00
Materials River Bed Materials 1.00 m3 1400.00 1400.00
Sub-Total 2,050.00
15 % Overhead 307.50
Unit Rate 2,357.50 m3

1 .Transportation of BM Soil by truck or Tractor (15 KMpH)


DoLIDAR
Unit: 10 Cu. M. Norms S.N: 56.2
Spec.C No: G-13.2
Lead source Type Quantity Unit Rate Amount
First 1KM Labour Unskill 1.36 md 650.00 884.00
Material Disel 2.35 LTR 86.50 203.28
Truck/Tractor -
Equipment Working Hr. 0.39 Hr. 300 117.00
Idle HR. 2.21 Hr. 150 331.50
Actul Rate 1,535.78
Unit Rate 153.58

item : laying of locally available granular materials for gravelling in Roadway for gravelling including
j10m lead & 1.5m lift-per m3
particular unit Qantity Rate Amount Remarks
subgrade preparation 10 cm depth
labour unskill md 0.05 650.00 32.5

laying of sub base for gravelling 15cm 0


thick 0
labour unskill md 1.5 650.00 975 pouring &
Material kg km levelling
Transportation upto 4
km for 1m3=1800kg/m3

1800 3.5 0.047 296.1


Sub-total 1303.6
15%overhead 195.54
unit rate 1499.14
3.24
Salient Features of Project
#REF!

#REF!
sfo{qmdsf] gfd
sfd ug]{ lgsfo pkef]Qmf ;ldlt
cfly{s aif{ 074/075
ljlgof]lht jh]6 #REF!
cg'dflgt nfut #REF!
sG6LGh]G;L 0.00
pkef]Qmf >dbfg #REF!
v'b e'QmfgL x'g;Sg] /sd #REF!
l;=g sfdsf] ljj/0f

gf]6
ufp+kflnsfsf] sfof{non] pkef]Qmf ;ldlt;+u ;Demf}tf
ubf{ lgDgfg';f/sf] zt{x?sf] clgjfo{ kfngf u/fpg] k|ltj4tf lnP/
dfq ;Demf}tf
!=pkef]Qmf u/fpgsf
;ldltn] gS;f tyfnflu
nfut cg'/f]w
Ol:6d]6 adf]lhd lgdf{0f ubf{ k'/fgf
vfg]kfgL, l;+rfO{, ljBfno ejg, lghL 3/, uf]7, cf+“ug cfbL k"jf{wf/ ;+/rgf Iflt
k'¥ofPsf] v08df ;f]xL pkef]Qmf ;ldltn] cfkm";+u ePsf] ;Demf}tf /sd leqsf]
ah]6af6 dd{t, lgdf{0f jf k'glg{df{0f ul/lbg' kg]{5 . ;f] ;DjGwdf s'g} ph'/L
kg{ cfPdf pQm Iflt ePsf] lgdf{0f ug{ nfUg] /sd ;DjlGwt pkef]Qmf ;ldltsf]
vftfaf6 s§f u/]/ dfq clGtd km/kmf/s ug]{ Joj:yf ldnfpg'x'g .
@= ;DjlGwt k|fljlws 6f]nLn] ;fO{6df u/]sf] ;e]{, sfof{nosf] :jLs[t nfut cg'dfg
Pj+ gS;fx? cg';f/ g} lgdf{0f sfo{ u/fpg] k|ltj4tf lng' x'g .
#= :jLs[t nfut cg'dfg / gS;f eGbf km/s sfo{ u/L sfof{non] d"Nof+sg gu/]sf]
v08df s'g} lsl;dsf] ph'/ nfUg]5}g eGg] k|ltj4tf lng'x'g .
$= ;Demf}tf adf]lhdsf] lgdf{0f ubf{ u/fpbf jftfj/0f ;+/If0f P]g @)%# /
jftfj/0f lgodfjnL @)%$adf]lhd jftfj/0fdf gsf/fTds k|efj gkg]{ul/ u/fpg] k|ltj4tf
lng'x'g .
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

Detailed Quantity Estimate


kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª
Work name - pipe Kharid

S.N. Description of items No. Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork for pipeline 1 120 0.3 0.3 10.80 m3 432.60 4672.08
2 HDPE Pipe kg/m
(63 mm 6kg/cm2) 1 120 0.851 102.12
Total 102.12 kg 293.8 30002.86
3 Transportation cost dist(km) wt(quintal)
HDPE pipe 17 2.0424 34.72 qnt/km 14.7 510.384
4 Refilling work 1 120 0.3 0.2 7.20 m3 180.25 1297.80
Sub total 36483.12
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

Detailed Quantity Estimate

kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{


7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª

Work name - Tarbar nirman

S.N. Discription of items no. Length Breadth Height Quantity unit Rate
1 Earthwork for
Pit 1 10.00 5.00 1.00 50.00
50.00 m3 432.60

Sub total
gfno

Amount Remarks

21630.00

21630.00
kz'kG5L tyf dT:o ljsf; lgb]{zgfno

uG8sL k|b]z, kf]v/f

Detailed Quantity Estimate

kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{


7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª

Work name - Tarbar nirman

S.N. Discription of items no. Length Breadth Height Quantity unit Rate Amount
1 Earthwork for angle post 53 0.30 0.30 0.30 1.43 m3 432.60 618.62
2 Angle purchase kg/m
40*40*5 mm 53 2.1 3 333.90 96.05 32071.10

3 Transportation Cost Qnt


MS Angle 15 6.678 100.17 Qnt/km 14.70 1472.50
4 Plain cement concrete work
M15(P.C.C. 1:2:4) 53 0.25 0.25 0.3 0.99 m3 15213.36 15061.23

50*50 mm 10 gauge
5 1 80 1.5 120 m 565.00 67800.00
fencing wire purchase
Sub total 117023.45
Remarks
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

Detailed Quantity Estimate


kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª
Work name - Khor bebasthapan

S.N Description of items No Length Breadth Height Quantity Unit


20 mm Thick 1:4 Cement sand Plaster
1
work
khor
Internal wall 1 16.65 1.5 24.98
floor 1 11.00 5 55.00
79.98 m2
2 Metal gate 2 2.00 LS
3 Fiber sheet 20 12.00 240.00 rf
4 Fiber sheet installation cost 1 1.00 LS
5 Partition door 7 7.00 LS
6 Stone masonry wall 1:4 c/s
Partition wall 1 5.00 0.3 0.7 1.05 m3

7 lku Sofr/ 1 1 LS
8 l6y s6/ 1 1 LS
9 kfgL 6\ofªsL !))) ln= 1 1 LS
10 kf7fkf7L v/Lb tyf Jj:yfkg 25 25 LS
11 Hoarding board 1 1 LS
Sub total
{zgfno

te

Rate Amount Remarks

3.15
1.8
489.73 39168.6054
10000 20000
242.95 58308
7000 7000
2500 17500

11114.49 11670.2145

8000 8000
1500 1500
12000 12000
6000 150000
5000 5000
b total 330146.82
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

Abstract of Cost Estimate

kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{


7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª

S.N. Discription of items unit Quantity Rate Amount Remarks


1 Earthwork for pipeline m3 62.23 432.60 26920.70
2 HDPE Pipe kg 102.12 293.80 30002.86
3 Transportation cost Qnt/km 134.89 14.70 1982.88
4 Refilling work m3 7.20 180.25 1297.80
5 Angle purchase kg 333.90 96.05 32071.10
6 Plain cement concrete work m3 0.99 15213.36 15061.23
50*50 mm 10 gauge fencing wire
7 m2 120.00 565.00 67800.00
purchase
8 20 mm Thick 1:4 Cement sand Plaster work m2 79.98 489.73 39168.61

9 Metal gate LS 2.00 10000.00 20000.00


10 Fiber sheet Rf 240.00 242.95 58308.00
11 Fiber sheet installation cost LS 1.00 7000.00 7000.00
12 Partition door LS 7.00 2500.00 17500.00

13 Stone masonry wall 1:4 c/s m3 1.05 11114.49 11670.21

14 lku Sofr/ LS 1.00 8000.00 8000.00


15 l6y s6/ LS 1.00 1500.00 1500.00
16 kfgL 6\ofªsL !))) ln= LS 1.00 12000.00 12000.00
17 kf7fkf7L v/Lb tyf Jj:yfkg LS 25.00 6000.00 150000.00
18 Hoarding board LS 1.00 5000.00 5000.00
Total Estimated Amount 505283.39
#REF!
30002.86
#REF!
1297.80
#REF!

#REF!
sfo{;DkGg k|ltj]bg
kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{ d=n]=k=kmf=g+= M–
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª

nfut cfg"dfg /sdM– 505283.39 sfd z'?ePsf] ldltM–


sfo{ ;DkGg ePsf] /sd M– 507577.66 sfd ;DkGg ug'{+kg] ldltM–
Oi6d]6 eGbf 36L jf a9LM– 2294.3 sfd ;DkGg ePsf] ldltM–

nfut sfof{ ;DkGg ePsf] km/s


qm= sfdsf] lhh/0f PsfO{ :jLst kl/df0 :jLst s}lkmot
kl/df0f :jLst b/ nfut ? kl/df0f /sd /sd
b/ f b/
1 Earthwork m3 62.23 432.60 26920.70 66.33 432.60 28694.36 4.100 0.00 1773.66
2 HDPE Pipe kg 102.12 293.80 30002.86 102.12 293.80 30002.86 0.000 0.00 0.00
3 Transportation cost Qnt/km 134.89 14.70 1982.88 134.89 14.70 1982.88 0.000 0.00 0.00
4 Refilling work m3 7.20 180.25 1297.80 6.60 180.25 1189.65 -0.600 0.00 -108.15
5 Angle purchase kg 333.90 96.05 32071.10 333.90 96.05 32071.10 0.000 0.00 0.00
6 Plain cement concrete work m3 0.99 15213.36 15061.23 0.99 15213.36 15061.23 0.000 0.00 0.00
7 50*50 mm 10 gauge fencing wire purchase m2 120.00 565.00 67800.00 120.00 565.00 67800.00 0.000 0.00 0.00
8 20 mm Thick 1:4 Cement sand Plaster work m2 79.98 489.73 39168.61 80.81 489.73 39575.08 0.830 0.00 406.47
9 Metal gate LS 2.00 10000.00 20000.00 2.00 10000.00 20000.00 0.000 0.00 0.00
10 Fiber sheet Rf 240.00 242.95 58308.00 240.00 242.95 58308.00 0.000 0.00 0.00
11 Fiber sheet installation cost LS 1.00 7000.00 7000.00 1.00 7000.00 7000.00 0.000 0.00 0.00
12 Partition door LS 7.00 2500.00 17500.00 7.00 2500.00 17500.00 0.000 0.00 0.00
13 Stone masonry wall 1:4 c/s m3 1.05 11114.49 11670.21 1.07 11114.49 11892.50 0.020 0.00 222.29
14 lku Sofr/ LS 1.00 8000.00 8000.00 1.00 8000.00 8000.00 0.000 0.00 0.00
15 l6y s6/ LS 1.00 1500.00 1500.00 1.00 1500.00 1500.00 0.000 0.00 0.00
16 kfgL 6\ofªsL !))) ln= LS 1.00 12000.00 12000.00 1.00 12000.00 12000.00 0.000 0.00 0.00
17 kf7fkf7L v/Lb tyf Jj:yfkg LS 25.00 6000.00 150000.00 25.00 6000.00 150000.00 0.000 0.00 0.00
18 Hoarding board LS 1.00 5000.00 5000.00 1.00 5000.00 5000.00 0.000 0.00 0.00
s'n /sd 505,283.39 507,577.66 2,294.27

gf]6M–n=O= eGbf a9L eP-±_ jf sd eP-–_ lrGx n]Vg].


!= ljnsf] qmd ;+Vof M clGtd kz'kG5L tyf dT:o ljsf; lgb]{zgfno &= ;Demf}tf ldlt M
kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f uG8sL k|b]z, kf]v/f *= sfd ;dfKt ug'{kg]{ ldlt M
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª
#= pkef]Qmf ;ldltsf] cWoIfsf] gfd M (= sfd gfkL ePsf] ldlt M
$= ;Demf}tf g+= M e'QmfgL ef}r/ g+= M
%= cl3Nnf] e'QmfgL ljnsf] qmd ;+Vof e'QmfgL ldlt M
^= cl3Nnf] e'QmfgL ljnsf] ef}r/ g+= M pkef]Qmf ;DaGwL lan gfkL lstfj g+= M
cfO6 cBfjlws sfd ePsf] cl3Nnf] ljnsf] r9]sf] xfn ePsf] sfd
n=O{=
d sfdsf] ljj/0f PsfO{ s}lkmot
kl/df0f kl/df0f b/ hDdf d"No kl/df0fhDdf d"Nokl/df0f hDdf d"No
g+=
1 Earthwork m3 62.23 66.33 432.60 28694.36 66.33 28694.36
2 HDPE Pipe kg 102.12 102.12 293.80 30002.86 102.12 30002.86
3 Transportation cost Qnt/km 134.89 134.89 14.70 1982.88 134.89 1982.88
4 Refilling work m3 7.20 6.60 180.25 1189.65 6.60 1189.65
5 Angle purchase kg 333.90 333.90 96.05 32071.10 333.90 32071.10
6 Plain cement concrete work m3 0.99
0.99 15213.36 15061.23 0.99 15061.23
50*50 mm 10 gauge fencing wire
7 m2 120.00
purchase 120.00 565.00 67800.00 120.00 67800.00
20 mm Thick 1:4 Cement sand Plaster
8 work
m2 79.98 80.81 489.73 39575.08 80.81 39575.08
9 Metal gate LS 2.00 2.00 10000.00 20000.00 2.00 20000.00
10 Fiber sheet Rf 240.00 240.00 242.95 58308.00 240.00 58308.00
11 Fiber sheet installation cost LS 1.00 1.00 7000.00 7000.00 1.00 7000.00
12 Partition door LS 7.00 7.00 2500.00 17500.00 7.00 17500.00
13 Stone masonry wall 1:4 c/s m3 1.05 1.07 11114.49 11892.50 1.07 11892.50
14 lku Sofr/ LS 1.00 1.00 8000.00 8000.00 1.00 8000.00
15 l6y s6/ LS 1.00 1.00 1500.00 1500.00 1.00 1500.00
16 kfgL 6\ofªsL !))) ln= LS 1.00 1.00 12000.00 12000.00 1.00 12000.00
17 kf7fkf7L v/Lb tyf Jj:yfkg LS 25.00 25.00 6000.00 150000.00 25.00 150000.00
18 Hoarding board LS 1.00 1.00 5000.00 5000.00 1.00 5000.00
hDdf /sd 507,577.66 - 507,577.66
! of] lan jdf]lhd e'QmfgL hDdf ?= 507577.66 $ s§f ug'{ kg]{ ?=
@ hg;|dbfg s= k]ZsL
# afFsL lbg' kg]{ ?= v= dfn;fdfgsf] df]n
u= cGo
% v'b lbg'

k]z ug]{sf] ;xL M hfFr ug]{sf] ;xL M :jLs[t ug]{sf] ;xL M


bhf{ ;a–O{lGhlgo/ bhf{ M bhf{ M
hDdf cIf?kL r]s g+= =======================af6 k||fKt eof] egL ;xL ug]{ .
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

Detailed Quantity Measurement


kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª
Work name - Pipe Kharid

S.N. Description of items No. Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork for pipeline 1 110 0.3 0.3 9.90 m3 432.60 4282.74
2 HDPE Pipe kg/m
(63 mm 6kg/cm2) 1 120 0.851 102.12
Total 102.12 kg 293.8 30002.86
3 Transportation cost dist(km) wt(quintal)
HDPE pipe 17 2.0424 34.72 qnt/km 14.7 510.384
4 Refilling work 1 110 0.3 0.2 6.60 m3 180.25 1189.65
Sub total 35985.63
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

Detailed Quantity Measurement

kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{


7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª

Work name - Mal bebasthapan

S.N. Discription of items no. Length Breadth Height Quantity unit Rate Amount
1 Earthwork for
Pit 1 10.00 5.00 1.10 55.00
55.00 m3 432.60 23793.00

Sub total 23793.00


Remarks
kz'kG5L tyf dT:o ljsf; lgb]{zgfno

uG8sL k|b]z, kf]v/f

Detailed Quantity Measurement

kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{


7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª

Work name - Tarbar nirman

S.N. Discription of items no. Length Breadth Height Quantity unit Rate Amount
1 Earthwork for angle post 53 0.30 0.30 0.30 1.43 m3 432.60 618.62
2 Angle purchase kg/m
40*40*5 mm 53 2.1 3 333.90 96.05 32071.10

3 Transportation Cost Qnt


MS Angle 15 6.678 100.17 Qnt/km 14.70 1472.50
4 Plain cement concrete work
M15(P.C.C. 1:2:4) 53 0.25 0.25 0.3 0.99 m3 15213.36 15061.23

50*50 mm 10 gauge
5 1 80 1.5 120 m 565.00 67800.00
fencing wire purchase
Sub total 117023.45
Remarks
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

Detailed Quantity Measurement


kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{
7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª
Work name - Khor bebasthapan

S.N Description of items No Length Breadth Height Quantity Unit Rate Amount Remarks
20 mm Thick 1:4 Cement sand Plaster
1
work
khor
Internal wall 1 16.65 1.55 25.81
floor 1 11.00 5 55.00
80.81 m2 489.73 39575.0813
2 Metal gate 2 2.00 LS 10000 20000
3 Fiber sheet 20 12.00 240.00 rf 242.95 58308
4 Fiber sheet installation cost 1 1.00 LS 7000 7000
5 Partition door 7 7.00 LS 2500 17500
6 Stone masonry wall 1:4 c/s
Partition wall 1 5.00 0.3 0.71 1.07 m3 11114.49 11892.5043

7 lku Sofr/ 1 1 LS 8000 8000


8 l6y s6/ 1 1 LS 1500 1500
9 kfgL 6\ofªsL !))) ln= 1 1 LS 12000 12000
10 kf7fkf7L v/Lb tyf Jj:yfkg 25 25 LS 6000 150000
11 Hoarding board 1 1 LS 5000 5000
Sub total 330775.59
3.15
1.8
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

Abstract of Cost Measurement

kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{


7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª

S.N. Description of items unit Quantity Rate Amount Remarks


1 Earthwork m3 66.33 432.60 28694.36
2 HDPE Pipe kg 102.12 293.80 30002.86
3 Transportation cost Qnt/km 134.89 14.70 1982.88
4 Refilling work m3 6.60 180.25 1189.65
5 Angle purchase kg 333.90 96.05 32071.10
6 Plain cement concrete work m3 0.99 15213.36 15061.23
50*50 mm 10 gauge fencing wire
7 m2 120.00 565.00 67800.00
purchase
8 20 mm Thick 1:4 Cement sand Plaster work m2 80.81 489.73 39575.08

9 Metal gate LS 2.00 10000.00 20000.00


10 Fiber sheet Rf 240.00 242.95 58308.00
11 Fiber sheet installation cost LS 1.00 7000.00 7000.00
12 Partition door LS 7.00 2500.00 17500.00

13 Stone masonry wall 1:4 c/s m3 1.07 11114.49 11892.50

14 lku Sofr/ LS 1.00 8000.00 8000.00


15 l6y s6/ LS 1.00 1500.00 1500.00
16 kfgL 6\ofªsL !))) ln= LS 1.00 12000.00 12000.00
17 kf7fkf7L v/Lb tyf Jj:yfkg LS 25.00 6000.00 150000.00
18 Hoarding board LS 1.00 5000.00 5000.00
Total Evaluated Amount 507577.66
#REF!
30002.86
#REF!
1297.80
#REF!

#REF!
kz'kG5L tyf dT:o ljsf; lgb]{zgfno
uG8sL k|b]z, kf]v/f

gflk lstfa

kmfd{sf] gfd M ;'o{ a+u'/ tyf df5f kfng kmd{


7]ufgf M sf=uf=kf= $ t+u|fd, afun'ª

Вам также может понравиться