Вы находитесь на странице: 1из 2

Demonstrating the viability of small

scale LNG terminals


Paul Shields Chart Industries

T
he project was intended to create small scale
LNG infrastructure and establish the port
of Klaipeda as an LNG hub for the Baltic
region and northeastern Poland by creating a sin-
gle value chain from LNG delivered from a float-
ing storage and regasification unit (FSRU).

Background
The facility at Klaipeda in Lithuania is the latest
to demonstrate the economic and technological
viability of small scale LNG storage and distri-
bution (see Figure 1). Although unable to provide
the same economies of scale of the megatermi-
nals, such as those in Rotterdam and Barcelona,
which have daily LNG volumes measured in hun-
dreds of thousands of cubic metres, small-scale
terminals can be built at a fraction of the cost,
within a much shorter time frame and provide
operational flexibility. This creates an attractive
business model for terminal operators and own-
ers to quickly address the growing demand for
LNG as a fuel for transportation and energy and
take advantage of new supply, particularly North
American shale.

Configuration Figure 1 The LNG terminal at Klaipeda


LNG off-loaded and stored at Klaipeda can be
decanted into road tankers for onward distribu- pumps for truck filling and bunkering, intercon-
tion to off-grid users. It is utilised for ship fuel- necting pipework, emergency flare and all associ-
ling, bunkering, and is vaporised as a source of ated control and safety systems.
energy for local community usage. Catering for All equipment is shop built with standard pro-
all eventualities enables the terminal to make duction techniques already proven in the field,
best use of landed LNG and immediately respond which minimises engineering and production
to fluctuations in application demand. costs, schedule and risk.
Standardisation and modularisation (design it
Equipment standardisation and modularisation once and duplicate manufacture) is another cru-
The cryogenic section of the terminal comprises cial element in the reduction of cost and sched-
five identical horizontal vacuum insulated, stor- ule. Each of the shop built cryogenic storage
age tanks, each with a capacity of 1000m³, 5 + tanks is much smaller than a site built alterna-
5 ambient air vaporisers for gas delivery, twin tive, which means far less site work, civils and
trailer loading bays, four cryogenic submerged permitting. Modularisation also means that the

www.digitalrefining.com/article/1002295 May 2019 1


planned facility expansion, doubling the storage • Demonstrate the technical and commercial
capacity from the current 5000m³ to 10000m³, viability of small scale LNG
is already built into the base design. • Multifunctional terminal with operational
flexibility
Accomplishments • Shop built, standard, field proven equipment
Chart Industries provided single point accounta- for reduced cost, schedule and risk
bility for project execution. The project also high- • Modularisation reduces logistics and time at
lights the value of close collaboration between site
partners to minimise cost and schedule in ensur- • Base design incorporates a planned expansion
ing timely completion according to budget. that doubles storage capacity.
Essentially, each stakeholder focused on their
area of expertise, but through close collaboration
duplicated engineering effort was avoided and
the project optimised as a whole, rather than by LINKS
section.
More articles from the following categories:
Summary Heat Transfer
• Establish the port of Klaipeda as a regional LNG, NGL and GTL
LNG hub

2 May 2019 www.digitalrefining.com/article/1002295

Вам также может понравиться