Identification of Accident Black Spots and Counter-measures

Based on the accident records, as many as 275 Accident Black Spots have been identified in the State. As per the
MORTH - Protocol for identification of black spots and improvement of the same, 159 Black spots located on National
Highways have been forwarded to Ministry’s Road Safety Cell for approval. Out of the remaining 116 Black spots
located on SH/MDR and other roads, PWD (R&B) had prioritized 46 Black spots spread over 11 districts for
immediate rectification measures.

Following the directions of Supreme Court Committee on Road Safety and as per the decisions taken at a meeting
convened by Principal Secretary, PWD and Transport Secretary on 29/12/2017,KRSA was asked to coordinate joint
inspection of accident black spotsby a team of officers from PWD, MVD, Police and KRSA-TSG. The team analyzed the
causative factors and arrived at appropriate mitigation measures for each location. A schedule of field visit conducted
to black spots in different districts is presented as Annexure-1. Accordingly, joint inspections were held in all districts
except Thrissur, in January 2018. Due to Vahana panimudakku (vehicle strike) on 24/01/2018, Thrissur district
visit is rescheduled on 15th& 16th Feb 2018.

Based on the analysis of accident records and causative factors, TSG suggested multi-sectoral rectification measures
to 40 black spots spread over the state. The mitigative measures include: engineering treatment, traffic calming,
speed control, pedestrian crossing, enforcement measures for each location. As many as 40 black spots were
inspected and appropriate counter-measures recommended during the month of January 2018.

Rectification measures suggested by Joint Inspection Team for improvement of 46 Black Spots on the state road
network (other than NH) are given in below table. A Detailed Report indicating the counter-measures and cost
estimates from concerned road agencies namely: PWD (R&B), KSTP / KRFB, and from other stake holding
departments to be Consolidated by PWD (R&B) and expected to be submitted to KRSA from Chief Engineer PWD
(R&B) at an earliest date.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:
 Majority of deaths & injuries occurred to Pedestrians and bike riders.
 Lack of safe crossing facility is the main causative factor.
 Buses conflict with two wheelers is quite predominant.
Rectification measures/ suggestions are:
 Conflict between Bus-Pedestrian to be addressed - segregation of pedestrian
movement
 Zebra cross marking with thermo-plastic paint, marking of refuge island at
median openings where zebra crossing is provided.
 Provide reflective studs and edge marking near median as well as footpath edge
marking between Pazhavangadi temple Jn.– Gandhi Park Junction.
 Provide 2.5 – 3.0 m wide footpath around City Bus Stand with railing barriers
Thiruvananthapu Location:  The Railing to be extended up to Fort Police Station
ram East Fort – Attakulangara  As a permanent solution, twofoot over bridges are recommended – one at
1 Attakulangara bus stop and the other at starting point of East Fort Bus shelter
City Traffic Police State Highway near Pazhavangadi Junction.
 Retain 6-lane divided carriageway for vehicles and exclusive bus lane on both
side
 Removal of encroachments and street vendors around
AttankulangaratoHotelBuhari, around Fort Entry gate, East Fort Bus stand area
 A mountable median or kerb stone be placed between bus stop lane & main
carriageway
 Unauthorised auto parking to be restricted between East Fort – Kuriyathy
Junction
 Provide Paver block tiles for bus stop portion of East Fort and Attakulangara.
 Continuity of footpath to be maintained from PazhavangadiTemple –
Attakulangara
 As a long-term measure, the main Bus stand waiting shed to be shifted towards
Fort Wall and aparallel arrangement of bus stand platform need to be provided.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:
 Out of 39 accidents reported during the past three years, couple of pedestrian run-
over deaths recorded.
 Tendency of overtaking and over-speeding exist. Road side parking is the main
reason for reduction of capacity of the road.
Rectification measures/ suggestions are:
Location:  Uniform width of 7.5 meter carriageway and footpath of 1.8 - 2.5 meter to be
Thiruvananthapu provided.
Market Jn.(PonnaraSreedhar
ram
Park) - PalayamJunction (SBI  Removal of Telephone/ Signal Junction box at the roundabout near Market
2
Br. NDD) Junction
Nedumangad
OtherDistrict Roads  Removal of Hoardings/ Arch of Pvt Establishments around Market Jn.roundabout
 Taxi parking near Police station hinders pedestrian crossing- Restrict taxi parking
 Removal of unused bus shelter (opposite side of KSRTC stand) and widen
footpath
 Demarcation of carriageway with markings, reflective studs and sign boards
 Provide speed reduction measures – a combination of speed humps and rumble
strips
 The section of the road is proposed as 4 lane divided carriageway under KRFB
funding
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:
 Since it is rural section of ODR, there is no issue of pedestrian movement. The
Black Spot is on ‘S’ curve where lack of visibility of oncoming vehicles is the
Location: main causative factor.
Thiruvananthapu The suggestions are:
Peringamala
ram
(Thaikkavu – Market Jn)
3  Vehicles reach the spot at very high speed and any interference from side road
Palode end up with accidents. Vehicular movement from the side roads to be regulated
OtherDistrict Roads
with speed humps/rumble strips.
 Road marking and sign boards to warn the motorists of S-curve
 Curve treatment with ladder marking and reflective studs are recommended.
 PWD Engineers informed that this section is proposed to be developed under
KIIFB funding
Major Road Safety Issues observed are:
 Substandard Vertical curve blinding oncoming traffic
 Big Banyan tree at Perumpuzha junction, extend beyond the Berm edge and also
obstruct sight distance of turning vehicles at the junction.
 2 Trees on either side of the road narrows the path with tunnel effect; where
Black spots location is at heavy vehicles are forced to travel through the middle of the road to avoid hitting
Perumpuzha; Road Class Type is on protruded tree branches.
Kollam District Kottiyam - Kundara Road  Unsafe Entry/Exit from ‘Harisree Bar’on to main road, which is accident prone.
4 and Police Station (MDR); and blackspot landmark  No proper pedestrian facilities at the junction, and near the Govt. LP School
is Kundara is MGUP School, Perumpuzha- Perumpuzha.
Thampuran finance/ Harisree  Bus Stop is close to the junction, blocking the junction, causing accident on
bar overtaking stopped bus.





Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Rectification measures/ suggestions are:
 At PerumpuzhaJunction both approach currently has equal priority, and hence the
drivers don’t know which approach vehicle should STOP and GIVE WAY.
Hence it is proposed to convert to a ‘2-way STOP’ priority junction with STOP
Sign & STOP Line Marking at the approach on Keralapuram – Nedumankavu
Road.
 Cutting and removing of 2 obstructing tree in the middle of blackspot stretch.
 Relocation of Bus Stop (towards Kundara) away from junction near to school
boundary.
 Providing Footpath & handrail along school side. Also continuous pedestrian
path on opposite side of school till junction.
 Currently always 3 Autos are parked at the junction awayfrom auto-stand. This
need to be avoided and all Auto should park only at the Stand.
 Access to and from the Harisree Bar need to be shifted away from main road to
the side road.
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers.
 Set of 6 lines of thermo plastic rumble strip marking together with reflective
studs is proposed at the beginning and end of the black-spot stretch.
 Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
on left & right side of the road at entrance to black-spot from each end.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:
 Straight road with speeding traffic, tempting to overtake and having curve with
reverse super elevation; vehicle lose control and causing accidents.
Rectification measures/ suggestions are:
Black spots location is at
Bharanikkavu; Road Class Type  Improvement of road geometry by correcting existing negative super elevation
Kollam District and also providing ‘extra widening’.
is Adoor - Sasthamcotta road
5 and Police Station  Speed calming measures with set of 6 lines of thermo plastic rumble strip
(SH 37); and blackspot landmark
is Sasthancotta marking together with reflective studs is proposed at the beginning and end of the
is Mannennamukku -
black-spot stretch.
Padmavathy JN
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers.
 Big ‘Accident Prone Area’ sign board, with speed limit sign inserted, is proposed
on left & right side of the road at entrance to black-spot from each end.
Major Road Safety Issues observed are:
 Straight road with speeding traffic, with narrow bridge, with sunken approaches
and substandard side road access on either side of the bridge approach.
 Bus Stop right at the bridge approach making it more congested. Also no safe
Black spots location is at pedestrian connectivity /path across bridge and to access Bus Stops.
Alappuzha District
Pallathuruthy; Road Class Type  Bridge side wall protection is broken, also no continuous W-Beam crash barriers.
is Alappuzha - Changanassery Rectification measures/ suggestions are:
and Police Station
6 Highway (SH 11); and blackspot
is Alappuzha  Provide extended W-Beam crash barriers covering bridge entry; with proper W-
landmark is 200 m before
Traffic Beam end treatment.
Pallathuruthy Bridge - 200 m
 Object Hazard Marking Sign (OHM) and Reflective Studs to be placed along W-
after pallathuruthy Bridge Beam crash barrier.
 Speed calming measures with set of 6 lines of thermo plastic rumble strip
marking together with reflective studs is proposed at the beginning and end of the
black-spot stretch
 Central Line and Edge Line Road markings together with reflective studs to be
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
provided for entire black-spot stretch.
 The Edge line should be provided straight with same bridge entry width for at
least 25m to 50m on both side and then taper back to approach road width. The
gap spacing for reflective Studs along edge line at the tapered portion and straight
portion near the bridge entry to be half that of on normal edge line (ie; double
quantity of reflective studs).
 Sunken bridge approaches may be raised with proper Geotechnical Soil
Treatments, at the Finishes Road Surface Level should be same as bridge level
for 25m to 50m from bridge Entry.
 Bus Stop at the Bridge approach should be relocated after the side road access on
either side of the bridge.
 ‘Narrow Bridge Ahead’ sign to be reinstated with Solar Traffic Blinker Lights.
 Big ‘Accident Prone Area’ sign board, with ‘Speed Limit’Sign& ‘Narrow Bridge
Ahead’ sign inserted, is proposed on left & right side of the road at entrance to
black-spot (say 200m from bridge) from each end.
 Safe and connected pedestrian walkway to be ensured around the area. Table Top
pedestrian crossing may be provided across the access to side roads.
 STOP Sign & STOP Line to be provided at all side road approaches.
 All encroachment and private advertisement boards on this area need to be
evicted.
 If the bridge is not proposed to be widened in the near future; then dedicated
pedestrian bridge may be considered.
Major Road Safety Issues observed are:

Black spots location is at • At Thalavady Junction, there is lot of cross road traffic with no proper junction
Alappuzha
Thalavady; Road Class Type is control.
District and Police • Hazardous obstructions along the road near to the junction, like electric post,
7 Alappuzha - Madhura road (SH
Station is transformer, vanchi, etc
40); and blackspot landmark is
Alappuzha Traffic Rectification measures/ suggestions are:
Kallath - Thiruvilak
• At Thalavady Junction approach, STOP Sign & STOP Line Marking together
with central water-drop Island, and required hatch marking to be provided.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
• All required Junction Road Marking and Traffic Signs to be provide, including
Pedestrian Crossing Marking and Ghost Islands.
• Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers.
• Set of 6 lines of thermo plastic rumble strip marking together with reflective studs
is proposed at the beginning of the black-spot stretch.
• Speed humps may be provided at the minor road approaches.
Major Road Safety Issues observed are:
• Straight road with speeding traffic, with narrow bridge.
• Bus stop near the junction, without Bus Bay.
• Road edges are at different level than bitumen pavement edge level.
Rectification measures/ suggestions are:
• At all minor road junction approach, STOP Sign & STOP Line Marking to be
Black spots location is at provided. All required Junction Road Marking and Traffic Signs to be provide,
Alappuzha Komalapuram; Road Class Type including Pedestrian Crossing Marking.
District and Police is Alappuzha - Madhura road • At Minor Road junction the left turn radius to be made sharper with the
8
Station is (SH 40); and blackspot landmark approaching traffic oriented 90degrees with the Main Road Traffic.
Alappuzha Traffic is Near PSC Exam Centtre - • Central Line and Edge Line Road markings together with reflective studs to be
Near Komalapuram Bridge provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers. Set of 6 lines of thermo plastic rumble strip
marking together with reflective studs is proposed at the beginning of the black-
spot stretch.
• Bus Stops need to be shifted away from the junction at least 75m to 100m away;
with proper Bus Bay.
• Road Edge treatment to be done to mitigate substandard Slope/ side sinking-
strengthening of road/soil treatment, etc
Major Road Safety Issues observed are:
Alappuzha Black spots location is at
9  Straight road with speeding traffic, with narrow bridge, with sunken approaches
District and Police Nedumudi; Road Class Type is
and substandard side road access on either side of the bridge approach.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Station is Ponga Alappuzha - Changanassery  Bus Stop right at the bridge approach making it more congested. Also no safe
Highway (SH 11); and pedestrian connectivity /path across bridge and to access Bus Stops.
blackspotlandmark is Jyothi Jn  Bridge side wall protection is broken, also no continuous W-Beam crash barriers.
- Ponga bridge Rectification measures/ suggestions are:
 Provide extended W-Beam crash barriers covering bridge entry; with proper W-
Beam end treatment.
 Object Hazard Marking Sign (OHM) and Reflective Studs to be placed along W-
Beam crash barrier.
 Speed calming measures with set of 6 lines of thermo plastic rumble strip
marking together with reflective studs is proposed at the beginning and end of the
black-spot stretch
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire black-spot stretch.
 The Edge line should be provided straight with same bridge entry width for at
least 25m to 50m on both side and then taper back to approach road width. The
gap spacing for reflective Studs along edge line at the tapered portion and straight
portion near the bridge entry to be half that of on normal edge line (ie; double
quantity of reflective studs).
 Bus Stop at the Bridge approach should be relocated after the side road access on
either side of the bridge.
 ‘Narrow Bridge Ahead’ sign to be reinstated with Solar Traffic Blinker Lights.
 Big ‘Accident Prone Area’ sign board, with ‘Speed Limit’Sign& ‘Narrow Bridge
Ahead’ sign inserted, is proposed on left & right side of the road at entrance to
black-spot (say 200m from bridge) from each end.
 Safe and connected pedestrian walkway to be ensured around the area. Table Top
pedestrian crossing may be provided across the access to side roads.
 STOP Sign & STOP Line to be provided at all side road approaches.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:
 Straight road with speeding traffic, with Major Titanic Bridge and its wide open
Junction with SH11, without proper traffic control at the junction.
 Bus Stop & Auto stand right at the bridge approach making it unsafe with lesser
Sight Distance.
 Also no safe pedestrian connectivity /path across bridge approach.
Rectification measures/ suggestions are:
• At Titanic Bridge junction approach, STOP Sign & STOP Line Marking to be
Black spots location is at provided. All required Junction Road Marking and Traffic Signs to be provide,
Alappuzha Ramankary; Road Class Type is including Pedestrian Crossing Marking.
District and Police Alappuzha - Changanassery • Bus Stops need to be shifted away from the junction at least 75m to 100m away;
10 with proper Bus Bay.
Station is Highway (SH 11); and blackspot
• Object Hazard Marking Sign (OHM) and Reflective Studs to be placed along W-
Ramankary landmark is Ramgary Jn-
Beam crash barrier on either side of the bridge junction.
Titanic Jn
• Speed calming measures with set of 6 lines of thermo plastic rumble strip marking
together with reflective studs is proposed at the Titanic Bridge approach.
• Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers. Set of 6 lines of thermo plastic rumble strip
marking together with reflective studs is proposed at the beginning of the black-
spot stretch.
• Safe and connected pedestrian walkway to be ensured around the area. Table Top
pedestrian crossing may be provided across the access to side roads.
Major Road Safety Issues observed are:
Black spots location is at
• Straight road with speeding traffic, tendency of unsafe overtaking.
ParakalKalunku; Road Class • Insufficient Street Lighting for night time visibility; and to reduce usage of ‘high
Kottayam District Type is Alappuzha - beam’ lights.
11 and Police Station Changanassery Highway (SH • Lack of effective speed calming measures.
is Changanassery 11); and blackspot landmark is Rectification measures/ suggestions are:
KBC Petrol Pump -
ParakkalKalungu • Consider providing continues Street Lighting considering the luminous Lux
intensity requirements. Street Light preferably on sustainable green energy
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
concept.
• Traffic Speed EnforcementCamera may be considered at suitable locations on the
black-spot stretch.
• Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers. Set of 6 lines of thermo plastic rumble strip
marking together with reflective studs is proposed at the beginning of the black-
spot stretch.
 Tree pruning need to be done on a regular basis to ensure safe sight distance and
clear right-of-way for the traffic.
 Object Hazard Marking Sign (OHM) and Reflective Studs to be placed along W-
Beam crash barrier.
 ‘Narrow Bridge Ahead’ sign to be reinstated with Solar Traffic Blinker Lights.
 Big ‘Accident Prone Area’ sign board, with ‘Speed Limit’Sign& ‘Narrow Bridge
Ahead’ sign inserted, is proposed on left & right side of the road at entrance to
black-spot (say 200m from bridge) from each end.
Major Road Safety Issues observed are:
• Curved road with speeding traffic, with unsafe overtaking.
• Lack of effective speed calming measures.
Rectification measures/ suggestions are:
Black spots location is at • Big ‘Accident Prone Area’ sign board, with ‘Speed Limit’Sign& ‘Curve Ahead’
Kottayam District
Pattalamukku; Road Class Type sign inserted, is proposed on left & right side of the road at entrance to black-
is Ettumanoor - Ernakulam road spotfrom each end
12 and Police Station
SH 15; and blackspot landmark • Curve treatment by widening the road within the available right of way and
is Kadathuruthy
is Royal Marbles Jn Muttuchira providing double central line marking with ladder hatching and reflective studs on
- Pattalamukku Bus Stop both curves.
• Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers.
• Set of 6 lines of thermo plastic rumble strip marking together with reflective studs
is proposed at the beginning and end of the black-spot stretch.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
• Road Marking at the junction should be as per IRC standards. STOP Sign &
STOP Line Marking to be provided. All required Junction Road Marking and
Traffic Signs to be provide, including Pedestrian Crossing Marking.
• Need of junction improvement with Rotary Island or Mini Roundabout need to be
considered if required based on traffic needs.

Major Road Safety Issues observed are:


 Traffic Safety issues at and around Mutholy Junction.
 Skidding issue to be removed
 Lack of proper Pedestrian crossing.
Black spots location is at  Median needed at bypass to Pala highway
Puliyannur; Road Class Type is Rectification measures/ suggestions are:
Kottayam District Ettumaoor - Poonjar road SH
13 and Police Station 32; and blackspot landmark is  Geometric Improvements at the Mutholy Junction need to be considered. STOP
Sign & STOP Line Marking to be provided. All required Junction Road Marking
is Pala Puliyanoor Temple
and Traffic Signs to be provide, including Pedestrian Crossing Marking.
Kanikkamandapam -
 Central Line and Edge Line Road markings together with reflective studs to be
Mutholy Jn
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers. Set of 6 lines of thermo plastic rumble strip
marking together with reflective studs is proposed at the beginning and end of the
black-spot stretch.
 Consider providing Central Median at bypass to Pala highway.
Major Road Safety Issues observed are:
Black spots location is at
Maygiri; Road Class Type is  Straight road with speeding traffic, with vertical and horizontal curves; and
Kottayam District Ettumaoor - Poonjar road SH unsafe overtaking, and substandard side road access.
Rectification measures/ suggestions are:
14 and Police Station 32; and blackspot landmark is
is Pala Vettukallel Arcade,  Speed calming measures with set of 6 lines of thermo plastic rumble strip
Bharanganam - Spice garden marking together with reflective studs is proposed at the beginning and end of the
Restaurant black-spot stretch. Central Line and Edge Line Road markings together with
reflective studs to be provided for entire black-spot stretch.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
 Big ‘Accident Prone Area’ sign board, with ‘Speed Limit’Signinserted, is
proposed on left & right side of the road at entrance to black-spotfrom each end.
 STOP Sign & STOP Line to be provided at all side road approaches.
 Consider providing Street light along the blackspot stretch to improve night
visibility.

Major Road Safety Issues observed are:


 Straight road with speeding traffic, with curves and gradients.
 Lack of sight distance with encroached tree branches.
Black spots location is at Rectification measures/ suggestions are:
Munnai; Road Class Type is  Speed calming measures with set of 6 lines of thermo plastic rumble strip
Kottayam District marking together with reflective studs is proposed at the beginning and end of the
Ettumaoor - Poonjar road SH
15 and Police Station black-spot stretch. Central Line and Edge Line Road markings together with
32; and blackspot landmark is
is Pala reflective studs to be provided for entire black-spot stretch.
IMA Bhavan , Moonani-
 Big ‘Accident Prone Area’ sign board, with ‘Speed Limit’Signinserted, is
Court Complex Pala proposed on left & right side of the road at entrance to black-spotfrom each end.
 STOP Sign & STOP Line to be provided at all side road approaches.
 Tree branches to be pruned on a regular basis to enhance sight distance.
 Bus bay need to be provided outside the travel lane, with proper treatment.
Major Road Safety Issues observed are:
 City Road with congested traffic and Wide road without proper road marking and
Black spots location is at Adoor functional demarcation.
Central Toll- Parthasarathi Rectification measures/ suggestions are:
Pathanamthitta Temple; Road Class Type is MC  Road Marking needs to be provided in such a way to safely regulates Y Junction
16 District and Police Road (Main Central Road) SH traffic.
Station is Adoor 1; and blackspot landmark is  Continuous pedestrian pathways, Foot path &pedestrianzebra crossings needed
Adoor Central Toll -  Speed calming measures with set of 6 lines of thermo plastic rumble strip
Parthasarathi Temple marking together with reflective studs is proposed at the beginning and end of the
black-spot stretch. Central Line and Edge Line Road markings together with
reflective studs to be provided for entire black-spot stretch.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
 Chevron marking needs to provide to control traffic movement near the junction,
as discussed during site visit.
 On street Parkingto be banned on unmarked area.

Major Road Safety Issues observed are:


• Curve road with Tree encroachment and steep berm ditches.
Rectification measures/ suggestions are:
Black spots location is at 14 • Tree cutting required, for the encroached accident prone tree.
thmile Jn. To Thengumthara; • Berm portion treatment required, if possible widening of road at the blackspot
Pathanamthitta stretch within available right-of-way.
Road Class Type is Kayamkulam
17 District and Police • Delineated Bus Bay to be provided.
- Pathanapuram Road SH 5; and
Station is Adoor • Speed calming measures with set of 6 lines of thermo plastic rumble strip marking
blackspot landmark is 14 th
together with reflective studs is proposed at the beginning and end of the black-
mile Jn. To Thengumthara
spot stretch. Central Line and Edge Line Road markings together with reflective
studs to be provided for entire black-spot stretch.
• Big 'Accident Prone Area' sign board, with 'Speed Limit' Sign inserted, is
proposed on left & right side of the road at entrance to black-spot from each end.
• STOP Sign & STOP Line to be provided at all side road approaches.
Major Road Safety Issues observed are:
Black spots location is at
Kulanada Medical Trust to • Kulanada Jn needs improvements. Need traffic study to determine the junction
Pathanamthitta improvement needs.
Kulanada Curve; Road Class
District and Police • Curve without proper curve treatment.
18 Type is MC Road(Main Central
Station is Rectification measures/ suggestions are:
Road) SH 1; and blackspot
Pandalam
landmark is Kulanada Medical • Speed calming measures with set of 6 lines of thermo plastic rumble strip marking
Trust - Kulanada Jn. Curve together with reflective studs is proposed at the beginning and end of the black-
spot stretch. Central Line and Edge Line Road markings together with reflective
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
studs to be provided for entire black-spot stretch.
• Big 'Accident Prone Area' sign board, with 'Speed Limit' Sign inserted, is
proposed on left & right side of the road at entrance to black-spot from each end.
• STOP Sign & STOP Line to be provided at all side road approaches. All other
required Sign boards needed.
• Curve treatment needed with Double Central Line Marking with Ladder
Hatching, and reflective studs.
 Crash barriers need to provide at locations as discussed during site visit.
Major Road Safety Issues observed are:
• Curve without proper curve treatment, poor sight distance, and very unsafe
junction at curve.
Rectification measures/ suggestions are:
• Curve treatment needed with Double Central Line Marking with Ladder
Black spots location is at Azhoor Hatching, and reflective studs.
Pathanamthitta Jn. to Petrol pump Jn; Road • Widening of paved area at the curve junction needed; with providing right turn
District and Police Class Type is Pathanamthitta - waiting bay.
19
Station is Thazhoorkadavu road (MDR); • Cheveron Hatch Island to segregate opposite traffic safely at the curve junction.
Pathanamthitta and blackspot landmark is • Speed calming measures with set of 6 lines of thermo plastic rumble strip marking
Azhoor Jn. to Petrol pump Jn together with reflective studs is proposed at the beginning and end of the black-
spot stretch. Central Line and Edge Line Road markings together with reflective
studs to be provided for entire black-spot stretch.
• Big 'Accident Prone Area' sign board, with 'Speed Limit' Sign inserted, is
proposed on left & right side of the road at entrance to black-spot from each end.
• STOP Sign & STOP Line to be provided at all side road approaches. All other
required Sign boards needed.
Black spots location is at Major Road Safety Issues observed are:
Ernakulam
Vengoor; Road Class Type is MC
District and Police • Congested road with illegal on-street parking, and vehicles parking on footpath.
20 Road(Main Central Road)SH 1;
Station is Substandard engineering geometry and road facilities making the road unsafe.
and blackspot landmark is
Angamaly Rectification measures/ suggestions are:
Double Palam - Viswajyothi
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
school (After Curve) • Carriageway reduced due to perpendicular parking
• W beam crash barrier proposed to protect deep drain on the side of road
• Parking on footpath to be regulated
• Varying width of footpath to be made uniform
• Trees obstructing carriageway to be removed
• Shoulders to be repaired
• Insufficient turning radius to be corrected
• Transformer to be shifted at Kottichirapadam junction.
• Foot path with hand rails required
• Rumble strips on side roads
• Parking of cars to be rearranged
• Encroachment to be removed
• Shoulders to be repaired
• Traffic calming for buses exiting bus stand
• Check the feasibility of renting out space of court for parking
Major Road Safety Issues observed are:
• Currently road traffic is diverted as Metro construction works are ongoing, and
observed that vehicles parking on footpath, unsafe U-Turn, lowered overhead
cables, lack of safe pedestrian pathway, all need to be rectified.
Black spots location is at GCDA Rectification measures/ suggestions are:
Ernakulam
Jn. To Elamkulam Jn.; Road • Major improvements to be undertaken after construction of metro rail
District and Police
21 Class Type is SA Road (MDR); • Major restrictions already imposed and traffic accidents have come down. Traffic
Station is City
and blackspot landmark is restrictions include-
traffic
GCDA Jn. to Elamkulam Jn. o i) Right turning movement restricted from road on left at GCDA junction
o ii)Free left turn allowed
• Pedestrian footpath and railing required throughout
• U turn to be restricted
• Clearance for overhead cables
• Parking on footpath to be regulated
22 Ernakulam Black spots location is at Major Road Safety Issues observed are:
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
District and Police Pallimukku; Road Class Type is • Lack of safe pedestrian pathway, illegal parking, unsafe Bus-Bay location, Traffic
Station is City MG Road (Old Sign and Road Marking need improvements.
traffic NH 47) SH ; and blackspot Rectification measures/ suggestions are:
landmark is Dwaraka Bus stop - • Overhead facilities to be regulated
Sreekandath Rd Junction • Pedestrian railing to be introduced to channelize movement of pedestrians
• Police aid post on pedestrian walkway to be demolished
• Reconstruction of footpath
• Obstruction on carriage way in front of Dwaraka hotel viz., transformer and
pillars to be removed
• Markings and signs
• Parking to be regulated
• Bus bays to be provided
• Pedestrian crossing to be marked
• Encroachment to be removed opposite to hospital
• Rumble strip, stop lines for side roads
Major Road Safety Issues observed are:
• Traffic Sign and Road Marking need to be provided. Traffic Signal Junction also
need improvements.
Black spots location is at Rectification measures/ suggestions are:
Ernakulam Atlantis Jn. (South - North);
District and Police Road Class Type is MG Road • Signs and markings
23 • Traffic signal
Station is City (Old NH 47) SH ; and blackspot
• Relocation of bus stop and reconstruction of footpath
traffic West PS landmark is Kurushupally Rd Jn
• Right turn from side road to be restricted
- Air Arabia office
• Table top intersection recommended
• Overlay recommended in the stretch after Air Arabia office where skidding is
observed
• Obstructions, including posts for left turning traffic from side road to be removed
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:
• Traffic Sign and Road Marking need to be provided. Lack of safe pedestrian
Black spots location is at BOT pathway, unsafe Bus-Bay location, etc, also need to be addressed.
Ernakulam Rectification measures/ suggestions are:
(W) Jn.; Road Class Type is Old
District and Police
24 NH 47 SH; and blackspot • Traffic Sign and Road Marking need improvements
Station is City
landmark is Pyari Jn - Indus • Bus bay to be relocated from junction
traffic West PS
motors • Footpath and handrail recommended from Indus motors to Pyari Junction
• Redesign of Pyari junction recommended with shifting of bus stop
• Traffic calming required in corporation road
• Street vending during festival season to be restricted
Major Road Safety Issues observed are:
• MC Road stretch with considerable speeding traffic within the black-spot stretch
with back-to-back reverse curves. High activity temple on the side, which is also a
‘Shabarimala edathavalam’ on the side attracting turning traffic. Previously
existed hump is substandard. Also a bridge and a junction also need attention for
road safety improvements.
Black spots location is at Rectification measures/ suggestions are:
Keezhillam; Road Class Type is
Muvattupuzha • Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
MC Road (Main Central Road)
District and Police on left & right side of the road at entrance to black-spot from each end.
25 SH 1; and blackspot landmark is
Station is
KeezhillamMahadeva Temple • Set of 6 lines of thermo plastic rumble strip marking together with reflective studs
Kurupampady is proposed at the beginning and end of the black-spot stretch.
/VVRA Rd Jn - St. Thomas
• Edge Line Road markings near the junction and Bridge need to be with reflective
Chruch
studs; to be provided for at least 50m on either side. The Edge Line 50m before
and after bridge should be aligned straight to effective width available within the
bridge; and should be provided with closely placed studs for clear night visibility.
• OHM signs, were also proposed at both handrail approaches of the bridge.
• STOP Sign & STOP Line at the minor road approach of Kurichilacode Road.
• Traffic Calming measures like thickened thermoplastic rumble strips or even
bituminous rumble humps may also be considered if required.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:
• Straight Road with Speeding Traffic after Odakkali Junction.
Rectification measures/ suggestions are:
Black spots location is at
Odakkali; Road Class Type is • Central Line and Edge Line Road markings together with reflective studs to be
Muvattupuzha Aluva - Munnar Road SH 16; provided for entire stretch of 500m of black-spot, to highlight the black-spot area
District and Police and blackspot landmark is and to visually alert the drivers.
26 • Set of 6 lines of thermo plastic rumble strip marking together with reflective studs
Station is Asammanoor Service
is proposed at the beginning and end of the black-spot stretch.
Kurupampady Cooperative Bank - Aromatic &
• Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
Medicinal plants Research
on left & right side of the road at entrance to black-spot from each end.
Station • Culvert near Aromatic & Medicinal plants Research Station need to be provided
with side protection.
• Vertical curve within the black-spot to be improved with cut-fill if possible.

Major Road Safety Issues observed are:


• City area congested road with narrow width and wider approach at Municipal
Junction.
Black spots location is at Rectification measures/ suggestions are:
Chendamangalam; Road Class • At Municipal Junction approach, STOP Sign & STOP Line Marking together with
Muvattupuzha
Type is Aluva - Paravur road central line marking, and required hatch marking to be provided.
District and Police
27 (MDR); and blackspot landmark • All required Junction Road Marking and Traffic Signs to be provide, including
Station is North
is KottichirappadamRdJn/ Mini Pedestrian Crossing Marking and Ghost Islands.
Pravoor
Civil Station - Hotel CeeCee • Central Line and Edge Line Road markings together with reflective studs to be
Tower provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers.
• Set of 6 lines of thermo plastic rumble strip marking together with reflective studs
is proposed at the beginning of the black-spot stretch near Kottichirappadam
Road.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:
• City Road with congested traffic and unsafe bus turning movement at the junction
from KSRTC Stand.
• At Perumpavoor Jn Traffic Signal, the channelizing island provided is not acting
as pedestrian refuge island for safer pedestrian crossing; with many obstructions.
Black spots location is at
Rectification measures/ suggestions are:
Muvattupuzha Perumpavoor Jn.; Road Class
District and Police Type is MC Road (Main Central • The channelizing island at Perumpavoor Jn Traffic Signal should be provided with
28
Station is Road) SH 1; and blackspot drop-kerb / flush-kerb to allow through passage of pedestrian and to act as
Perumpavoor landmark is Ayyappa Temple pedestrian waiting refuge island for safer pedestrian crossing.
Rd Jn. - KSRTC Bus Stand RD Jn. • All obstrucle with in the central median and channelizing island, including Signal
posts to be relocated away from pedestrian pathway.
• Zebra crossing should be aligned considering pedestrian cut-through passage
through channelizing island and central Median Island.
• At KSRTC Junction approach, STOP Sign & STOP Line Marking together with
central line marking, and required hatch marking to be provided.
Major Road Safety Issues observed are:
 Straight road with speeding traffic on both side of black-spot, & two back-to-
back substandard curves considering the road speed.
Rectification measures/ suggestions are:
Black spots location is at
Muvattupuzha Kanjirakkad; Road Class Type is • Curve treatment by widening the road within the available right of way and
District and Police MC Road (Main Central Road) providing double central line marking with ladder hatching and reflective studs on
29 both curves.
Station is SH 1; and blackspot landmark is
Perumpavoor SN Hotel - Broadway Rd Jn/ • Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
Kaduval Jn
and to visually alert the drivers.
• Set of 6 lines of thermo plastic rumble strip marking together with reflective studs
is proposed at the beginning and end of the black-spot stretch.
• Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
on left & right side of the road at entrance to black-spot from each end.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Major Road Safety Issues observed are:

 Major junction without proper junction control mechanisms.


 Lack of safe pedestrian facilities.
 Unused bus shelter at the junction and Auto stand at the junction causing safety
hazards.
 Access from MapranamCenter opens in to busy junction.
Black-spot location is at Rectification measures/ suggestions are:
Maparanam; Name of Road is
Thrissur District  Junction improvement suggested at Mapranam Junction. Physical water-drop
Kodungallur - Shornur Road SH shaped turn island suggested on minor road approach
30 and Police Station
22; and black-spot landmark is
is Irinjalakkuda
250 mtr stretch towards both  Road markings together with reflective studs to be provided @ stop-line, central
sides from Maparanam Centre line, zebra crossing markings, rumble strip markings, and double yellow central
line markings, etc. suggested at required locations near the junction.
 Traffic Sign Board like STOP sign, Pedestrian Crossing Ahead, Accident prone
area with speed limit sign, etc proposed at required location.
 Suggested changing access of MapranamCenter Parking area away from the
Junction.
 Old bus shelter, which is currently not used can be demolished to improve the
junction and to find safe location for Auto Stand queuing.
Black-spot location is at Major Road Safety Issues observed are:
Narayanamangalam; Name of
Thrissur District  Sharp Curves with very poor sight distance forming blind-spot.
Road is Kodungallur - Shornur
31 and Police Station  No means for physical separation of on-coming traffic to avoid head-on
Road SH 22; and black-spot
is Kodungallur collisions.
landmark is Viyyathukulangara
- Narayanamangalam Rectification measures/ suggestions are:
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers.
 Set of 6 lines of thermo plastic rumble strip marking together with reflective
studs is proposed at the beginning and end of the black-spot stretch.
 Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
on left & right side of the road at entrance to black-spot from each end.
 Treatment of S-curve is also suggested with utilising the available land to the
max.
 Consider providing mountable median at the curve portion, which should be
visible from sufficient distance.
 Also suggested to enquire the possibility of demolishing the opaque side wall and
to re-constructing it with see-through cast iron grills to improve the sight distance
at the curve is also suggested.
Major Road Safety Issues observed are:
Black-spot location is at  Lack of continuation in road median, tempting the drivers to overtake at this
Parembadam; Name of Road is stretch is the mainly attributing to the accidents here.
Thrissur District
Thrissur - Kuttippuram road SH Rectification measures/ suggestions are:
and Police Station
32 69; and black-spot landmark is
is  Land acquisition in this stretch is interrupted with ongoing case at court.
250 mtr stretched towards both
Kunnamangalam  Temporary arrangement to segregate directional traffic with flexible bollards and
sides from Parembadam Bus
saggy chains is proposed until the construction of permanent median.
stop
 Also a set of 6 lines of thermo plastic rumble strip marking together with
reflective studs is proposed at the beginning and end of the black-spot stretch.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station

Black-spot location is at
Peramangalam; Name of Road
Thrissur District This stretch is already improved with central median and with anti-glare boards. The
is Thrissur - Kuttippuram road
33 and Police Station local officials informed that this stretch is no more a black-spot; and hence no
SH 69; and black-spot landmark
is Peramangalam further actions required.
is ICICI Bank ATM - Dakshin
Hotel

Major Road Safety Issues observed are:

 Current central median ends at Mundur junction. So the vehicle coming at higher
speed so far with the 4lane highways is now suddenly opened up at the congested
Black-spot location is at junction area, resulting in most of the accidents.
Thrissur District Mundur; Name of Road is Rectification measures/ suggestions are:
34 and Police Station Thrissur - Kuttippuram road SH
 Tapering of Two lane approach road to one lane before reaching Mundur junction
is Peramangalam 69; and black-spot landmark is
to be considered.
Hotel Rainbow - Subin Bakery
 Thermo plastic rumble strip marking together with reflective studs is proposed at
both side of Mundur junction approach.
 Central Line marking to be redone and also stop line & stop sign at minor road
approaches are proposed.
Major Road Safety Issues observed are:
Black-spot location is at
 The Major accident causing factors here are; wider roads, s-curve, vertical curve
Palappuram; Name of Road is
Palakkad District and competitive racing of private bus.
Palakkad - PonnaniRoad( MDR);
35 and Police Station Rectification measures/ suggestions are:
and black-spot landmark is
is Palappuram
College Bus Stop, Palappuram -
 The black-spots falls on either side of NSS College Main Entrance. It is
P.A.R Bakery Palappuram
suggested to provide footpath with handrail on the side of college until the
adjacent bus stop area.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
 Segregated bus bay to be marked near to the bus shelter opposite to NSS College
Main Entrance.
 Also pedestrian crossing marking to be provided to access the bus stops.
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch starting before the S-curve till Palappuram Post Office,
to highlight the black-spot area and to visually alert the drivers.
 Set of 6 lines of thermo plastic rumble strip marking together with reflective
studs is proposed at the beginning and end of the black-spot stretch.

Major Road Safety Issues observed are:

Black-spot location is at  This stretch is within busy town area near to Government College Malappuram,
Malappuram Munduparampa; Name of Road Munduparamba.
District and Police is Tirur - Manjeri Road (SH 71); Rectification measures/ suggestions are:
36
Station is and black-spot landmark is
 It is proposed to provide proper Road markings and Traffic Sign along the black-
Malappuram Munduparampa Fire station -
spot stretch as well as Munduparamba junction.
Munduparampa Govt. College
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch, together with thermo plastic rumble strip marking &
reflective studs is proposed at the beginning and end of the black-spot stretch.
Major Road Safety Issues observed are:
Black-spot location is at
Malappuram
Ponmala; Name of Road is Tirur  The sharp curve here attributes to most of the accidents happened here.
District and Police
37 - ManjeriRoad (SH 71); and Rectification measures/ suggestions are:
Station is
black-spot landmark is Kodur -
Malappuram  Proper engineering treatment of the curve is suggested here; by best utilising the
Manoor
available land at the curve.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station

 The main aim was to segregate oncoming traffic with wider ladder hatch marking
island of with mountable physical kerb median to avoid head-on collision.
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers.
 Set of 6 lines of thermo plastic rumble strip marking together with reflective
studs is proposed at the beginning and end of the black-spot stretch.
 Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
on left & right side of the road at entrance to black-spot from each end.
 ‘Sharp Curve Ahead’ sign and single chevron signs, Object Hazard Marker
(OHM) signs, were also proposed at required location.
Major Road Safety Issues observed are:

 The main issues are straight road tempting the drivers to over speed, vertical
curve with very poor sight distance, and inclined junction at steep gradient, etc
Black-spot location is at Rectification measures/ suggestions are:
Karyavattom; Name of Road is
Malappuram  The PWD officials suggest that cutting and filling is required to improve the sight
Kavarakundu -
District and Police distance at the vertical curve and also improve safety at Y-junction.
38 PerinthalmannaRoad (OR); and
Station is
Melattur
black-spot landmark is  Relocation of bus stop away from vertical curve portion, with segregated bus bay
Jumamasjid - 200 mtr to markings is also proposed.
Mannarmala Road
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of black-spot, to highlight the black-spot area and to
visually alert the drivers.
 6 lines of thermo plastic rumble strip marking together with reflective studs is
proposed at the beginning and end of the black-spot stretch.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station

 Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
on left & right side of the road at entrance to black-spot from each end.
Major Road Safety Issues observed are:

 There are few schools and other institutes in this stretch without any proper
pedestrian facilities.
 Straight roads followed by curve are another prompt for accidents.
Black-spot location is at Cherur; Rectification measures/ suggestions are:
Name of Road is Vengara -
Malappuram  Footpath with handrail along the side of GMUP school is proposed.
Achanambalm Road (MDR); and
39 District and Police
black-spot landmark is GMUP  Speed Humps on either side of school entrances is also proposed.
Station is Vengara
School Cherur – Yatheemkhana,
Cherur  Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of black-spot. • hermo plastic rumble strip marking
together with reflective studs is proposed at the beginning and end of the black-
spot stretch.
 School Zone sign board, with speed limit sign, is proposed on left & right side of
the road in advance to the entrance to Schools.
Major Road Safety Issues observed are:

Black-spot location is at  The main issue is at the Wandoor junction, with two equal priority roads cross
MalappuramDistri Wandoor Town; Name of Road each other.
ct and Police is Valachery - Nilambur road  Encroachments at the junction like shops, electric post, are also contributing
40
Station is (SH 73 ); and black-spot hazards to road safety.
Wandoor landmark is Federal Bank-
 Improper alignment of approach and exit lanes at the junction also contributes to
Manalimmal bus Stand
road safety hazards.
Rectification measures/ suggestions are:
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station

 Junction improvement with control type; as currently ‘uncontrolled junction’


being changed to ‘priority/STOP controlled junction’ with STOP sign and STOP
Line along Eriyad-Vaniyambalam Road. Set of thermo plastic rumble strip
marking together with reflective studs is also proposed 10m away from STOP
line on both approaches.
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of black-spot.
 Shifting of utilities like obstructing electric post away from the junction bell
mouth area.
 Improvement of pedestrian footpath with tile paving. Also to provide zebra
crossing marking at safe location, also considering pedestrian crossing desire
line.
Major Road Safety Issues observed are:

 Substandard Geometrical Junction Design. Wide open junction without road


markings.

Black-spot location is at  High traffic volume demanding Signal Control Junction, but currently signal not
Kozhikode District
Mankave; Name of Road is Mini in operation, as lack of geometrical improvements to support signal operation.
and Police Station
41 Bypass( SH); and black-spot  Bus stops in close vicinity of the junction adding to the congestion & queuing,
is City Traffic
landmark is Asokapuram Road which even leads to accidents.
Police station
Jn - Petrol Pump Rectification measures/ suggestions are:

 Junction improvement by geometrical re-designing is required as a long term


solution.
 Proposed to relocate bus stop further away (100m) from junction; with segregated
Bus-bay.
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
 Need to make required junction improvements to make the Signal operational,
ensuring the traffic safety and efficiency.
 Need cooperation from KRFB & UCCIDPL, who is the concessionaire
responsible operation and maintenance of this junction for 15years; for
implementing the Road Safety Improvement Proposal.
Major Road Safety Issues observed are:

 Straight road followed by curve is the major location of accidents.


 There is a school in this stretch without proper pedestrian facilities.
Rectification measures/ suggestions are:

 Relocation of bus stop away from curve portion, with segregated bus bay
markings.
Black-spot location is at  Raised Table Top Pedestrian Crossing between the bus stop and school entrance
Kozhikode District Velliparamba; Name of Road is is proposed; together with set of thermo plastic rumble strip marking & reflective
and Police Station Kozhikode - Mavoor Road ( studs on either side of the proposed raised pedestrian crossing.
42
is City Traffic MDR); and black-spot landmark  Pedestrian footpath with handrail alongside the school entrance till the adjacent
Police station is Media One Studio- bus stop is proposed.
Velliparampa School
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of black-spot, to highlight the black-spot area and to
visually alert the drivers.
 6 lines of thermo plastic rumble strip marking together with reflective studs is
proposed at the beginning and end of the black-spot stretch.

 Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
on left & right side of the road at entrance to black-spot from each end.
43 Kozhikode Black-spot location is at Feroke; Major Road Safety Issues observed are:
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
District and Police Name of Road is Other Road;  The black-spot is around Feroke bus stand.
Station is City and black-spot landmark is
 The frequent movement of buses along wide opened area, without clear
Traffic Police Railway Station - Sub treasury
demarcation of ‘in and out’
station
 Higher pedestrian activity near bus-stand with poor pedestrian facilities.

 Junction with through traffic and bus stand traffic is uncontrolled and confusing.
Rectification measures/ suggestions are:

 Proposed to provide uninterrupted footpath on opposite side of bus stand.


 Road paving improvements at the access to bus stand with demarcation for ‘Entry
and Exit’.
 Junction improvement with Traffic Sign and Road Markings proposed.
 Encroachments near the bus stand to be demolished and proper pedestrian
footpath to be provided.
Major Road Safety Issues observed are:

 The approach to the roundabout is not designed properly to have ‘Entry


deflection’ and appropriate ‘conflict angle’.
 No ‘Yield Sign’ or ‘Yield Line Marking’ at roundabout access.
Kozhikode Black-spot location is at  No circulating lane marking provided.
District and Police Arayedathupalam; Name of
 Improper designed channelized island at roundabout exit.
44 Station is City Road is Mini Bypass (SH); and
Traffic Police black-spot landmark is KTC  Lack of sight distance due to the bridge pillars.
station Petrol Pump - Vasan Eye Care Rectification measures/ suggestions are:

 Provide all mandatory signs for roundabout, like Yield Sign, Roundabout Ahead
Sign, Keep Left Sign, etc
 Provide all mandatory road markings for roundabout, like Yield Line, Circulating
Lane, Continuity line, etc
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
 Geometric improvements at the approach of the roundabout to have proper ‘Entry
deflection’ and appropriate ‘conflict angle’.
 Traffic turning movement counts to be taken and intersection control type
warrant study to be carried out to examine the need for Signalised Intersection
here.
 Need cooperation from KRFB & UCCIDPL, who is the concessionaire
responsible operation and maintenance of this junction for 15years; for
implementing the Road Safety Improvement Proposals.
Major Road Safety Issues observed are:

 Straight road with steep downward gradient and longer sight distance, with traffic
signal at the end. This tempts the drivers to accelerate to catch-up the Green Light
at the signal, and might have to make hard braking to stop.
Kozhikode
Black-spot location is at Rectification measures/ suggestions are:
Thondayad; Name of Road is
District and Police
Kozhikode - Mavoor Road
45 Station is City  Proper speed breakers need to be installed to slowdown the downhill traffic.
(MDR); and black-spot landmark
Traffic Police
is Kavu Bus Stop - Vigilance  Table toped speed calming with tactile paving before the approach to the
station
Office intersection is proposed.
 Central Line and Edge Line Road markings together with reflective studs to be
provided.
 Thermo plastic rumble strip marking together with reflective studs is proposed at
the approach to the intersection.
Black-spot location is at Major Road Safety Issues observed are:
wayanad District Puliyarmala; Name of Road is
46 and Police Station Mananthavadi - Kalpetta Road  The black-spots fall in the proposed hill highway stretch. Currently winding
is Kalpetta (SH 59); and black-spot roads with no proper side protection, makes the accident fatal.
landmark is Puliyarmala - Rectification measures/ suggestions are:
Name of the
Location of Black Spot /
No District/ Name of Main causative factors identified and treatment suggested
Classification of Road
Police Station
Puliyarmala ITI road Jn.
 Central Line and Edge Line Road markings together with reflective studs to be
provided for entire stretch of 500m of black-spot, to highlight the black-spot area
and to visually alert the drivers.
 Set of 6 lines of thermo plastic rumble strip marking together with reflective
studs is proposed at the beginning and end of the black-spot stretch.
 Big ‘accident prone area’ sign board, with speed limit sign inserted, is proposed
on left & right side of the road at entrance to black-spot from each end.
 ‘Sharp Curve Ahead’ sign and single chevron signs, Object Hazard Marker
(OHM) signs, were also proposed at required location.

 W-beam barrier protection with side wall is also proposed at 2 critical locations.