Вы находитесь на странице: 1из 238

Proposed (2B+G+2) Shopping Mall

Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.

For M/s. Lulu Hypermarket L.L.C

VOLUME NO IV
BILLS OF QUANTITIES

GENERAL REQUIREMENTS
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS

GENERALLY

General Notes on Preliminaries

A These Preliminaries are applicable to the whole of the Works. If the


Tenderer wishes to price any of the items contained herein then each
such item, clause or sub-clause must be individually priced. The
Tenderer shall not enter any lump sums covering more than one or all
items, clauses or sub-clauses. Where any item, clause or sub-clause of NOTED
the Preliminaries has not been priced are deemed to be included in
your tender sum.

Site Location

B The site is located on Plot No. 24-001, Nadd Hessa, Dubai, UAE. NOTED

Description of Works

C The Contractor's scope of works includes the following works for a


shopping mall building comprising of 2 levels basement (Car
NOTED
Parking), retail space and roof (2B + G + 2): -

a) Complete structure & architectural works


b) Complete finishes
c) Complete fittings as indicated
d) Complete mechanical, electrical & plumbing works
e) Complete landscape works
f) Any other works detailed or implied in the Tender

To Collection 0
B1/1
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

GENERALLY (Cont'd)

Access to Site

A The Contractor shall satisfy himself as to the means of access to, from
and about the site and other relative items affecting access and shall Item NOTED
allow for all costs in connection with same.

Visit to the Site and Site Condition

B The Contractor shall examine the drawings, visit the site, inspect the
existing works on site and the surrounding of the site and carry out all
necessary investigation works to satisfy himself as to the nature of the Item NOTED
Site and the means to execute and complete the works in the contract.

C The Contractor must accept the site 'as is where is' and no claims for
extra payments in this connection will be entertained including Item NOTED
determining and recording all existing on site services routes.

Existing Services

D The Contractor shall be responsible for the protection of all existing


services within the Site and shall make good any damage to existing
services resulting form his carrying out of the Works to the
satisfaction of the Engineer and relevant authority. The Contractor
shall be responsible for giving notice to the relevant authority where
Item NOTED
temporary or permanent re-routing of existing services is found to be
necessary and shall provide attendance upon any contractor employed
to carry out such re-routing.

To Collection 0
B1/2
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONDITIONS OF CONTRACT

Conditions of Contract

A The Contractor shall describe and list below and price herein any
obligations contained in the Conditions of Contract for which he has Item NOTED
not allowed elsewhere and wishes to price separately.

The Clauses in the Conditions of Contract are as follows:

Clause 1 - General Provisions


Clause 2 - The Employer
Clause 3 - The Engineer
Clause 4 - The Contractor
Clause 5 - Nominated Subcontractors
Clause 6 - Staff and Labour
Clause 7 - Plant, Materials, and Workmanship
Clause 8 - Commencement, Delays and Suspension
Clause 9 - Tests on Completion
Clause 10 - Employer's Taking Over
Clause 11 - Defects Liability
Clause 12 - Measurement and Evaluation
Clause 13 - Variations and Adjustments
Clause 14 - Contract Price and Payment
Clause 15 - Termination by Employer
Clause 16 - Suspension and Termination by Contractor
Clause 17 - Risk and Responsibility
Clause 18 - Insurance
Clause 19 - Force Majeure
Clause 20 - Claims, Disputes and Arbitration

Performance Bond / Performance Security

B The Contractor to provide the Performance Guarantee in the amount


in accordance with Conditions of Contract covering the Works from a
Bank approved by the Employer and in accordance with the sample Item 475,000
and specimens forms provided in the Tender Documents.

Advance Payment Guarantee

C The Contractor to provide the Advance Payment Guarantee in the


amount in accordance with Conditions of Contract from a Bank
approved by the employer and in accordance with the sample and Item INCLUDED
specimens forms provided in the Tender Documents.

To Collection 475,000
B1/3
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONDITIONS OF CONTRACT (Cont'd)

Conditions of Contract (Cont'd)

Insurances

A The Contractor shall allow for insurances in accordance with the


Clause 18 of the Conditions of the Contract i.e.:-

a) Contractor's All Risk (CAR) Insurance, BY MAIN


Item
CONTRACTOR

b) Plant and Equipment Insurance; MEP ONLY


for contractor's equipment and machinery Item
INCLUDED

c) 3rd Party / Property Liability Insurance;


for any persons other than Contractor's Personnel for the loss, BY MAIN
Item
damage, death or bodily injury & to any physical property CONTRACTOR

d) Workmen Compensation Insurance;


for Contractor's personnel Item INCLUDED

e) Professional Indemnity Insurance. Item INCLUDED

Green Requirement Regulation

The contractor shall abide by ( DSOA - Dubai Silicon Oasis Authority


) Green Regulation

B The contractor is fully responsible for Green Requirment Regulation


documentation, reporting and submission during the construction INCLUDED
including commissioning and final approval from the Relevant AS PER
Authority. The Contractor shall appoint a qualified PQP during the Item
TENDER
project construction stage. DOCUMENTS

C The main contractor shall hire an Independent Commissioning Agent


(ICA) during the project construction phase to carry out the scope of
work as detailed in Green Requirment Regulation. The ICA shall
possess the required qualifications and experience details in the Green BY MAIN
Requirment guide and shall be independent of the design and Item
CONTRACTOR
construction team.

To Collection 0
B1/4
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

MATERIALS AND SAMPLES

Delivery, Handling and Storage of Materials

A Allow for handling and storage of materials in accordance with


Specifications. Item NOTED

Contractor's Quality Assurance and Laboratory Testing Services

B Allow for fully complying with all Quality Control and laboratory
Testing Requirements as per specifications. Item NOTED

Standards, Materials, Goods and Workmanship

C Allow for ensuring the materials are to the satisfaction of the Engineer
and are of the best quality and comply with the Specification,
Standard, rules and regulations of Statutory Authorities but not limited
NOTED AND
to Civil Defence Department, Dubai Municipality etc, or other similar Item
organisation and provide guarantee to entire satisfaction of the COMPLY
Engineer.

Spare Materials

D Allow for commissioning of spares, subject to and in accordance with


INCLUDED
the Specifications. Item
AS PER
SPECIFICATION

To Collection 0
B1/5
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

BILLS & PRICING

A Where items are not individually priced it will be assumed that their
cost has been included generally in all other prices quoted. Item NOTED

B The Contractor shall set out below and fully describe and price any
works or obligation or anything in the Contract Documents not
included by him in his rates elsewhere, and for which he considers a Item NOTED
separate charge is required.

C The Bills of Quantities contains Provisional Sums which may be


executed by either the Main Contractor, Nominated Sub-contractor or Item NOTED
Suppliers.

D Nominated Sub-Contracts and Nominated Supply contracts shall be


tendered by the Employer unless otherwise clarified. Item NOTED

E The Main Contractor shall be fully responsible for the Works and acts
or omission of the Nominated Sub-contractors. It shall be the
Tenderers responsibility to establish the full extent of the works
included in each Nominated Sub-Contract package to enable the Item NOTED
Tenderers to establish the extent of any associated builders works and
attendance required to complete the works.

F The client reserves the right to omit the PC & Provisional Sum partly
or wholly and the contractor is not allowed to claim for additional Item NOTED
monies or time in conjunction of that.

To Collection 0
B1/6
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

TEMPORARY WORKS

Generally

A The Contractor is responsible for the design, provision, maintenance


and removal on completion of works including any necessary
temporary fencing required for the Works.

The Contractor shall submit to the Engineer his proposals for all BY MAIN
temporary works for approval. The Engineer's approval will in no way Item
CONTRACTOR
relieve the Contractor of his responsibility for the safety of the Works,
operatives, adjoining property, structure or services and compliance
with appropriate regulations and Codes of Practice.

Plant & Equipment

B Allow for all plant & equipment to be transported to, fixed and BY MAIN
removed from site for the proper execution of the site works. Item
CONTRACTOR

Contractor's Offices, Stores, Sheds etc.

C Allow for provision, maintenance and removal on completion


contractors offices, stores and sheds and toilets in accordance with BY MAIN
Item
Engineer's Specification. CONTRACTOR

Site Sign Board

D The Contractor shall be responsible for the provision, maintenance


during construction period and dismantling upon project completion BY MAIN
Item
in accordance with the drawings and Specification. CONTRACTOR

Temporary Hoardings

E The Contractor shall be responsible for the provision, maintenance


during construction period and removal of hoardings upon project
BY MAIN
completion in accordance with the drawings and specification Item
CONTRACTOR
including paying all license fees.

To Collection 0
B1/7
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

TEMPORARY WORKS (Cont'd)

Scaffolding and Cradles

A Allow for the provision, erection, maintenance during construction


period and dismantling upon project completion including making
good the site and in accordance with the drawings and Engineer's BY MAIN
Item
Specifications. The Contractor must allow for inspection of all CONTRACTOR
scaffolding and Cradles at the Start of each lift.

Temporary Roads and Access to Site

B The Contractor shall prepare and maintain such temporary roads as


may be necessary from the Site to the nearest public road /
expressway and also within the Site and shall obtain the necessary
approval from the local Municipality department. The roads shall be BY MAIN
Item
positioned in accordance with the Engineer's instructions and shall be CONTRACTOR
kept free for access at all times.

Site Area

C The Contractor's activities shall be confined to the Site area within the
limits of the Site hoarding. Throughout the period of construction of
the Works, the Contractor shall maintain the whole area of his
operations in a clean, tidy and safe condition by arranging his
materials in an orderly manner. All rubbish, waste material, debris, etc
shall be systematically cleared off the working areas as it accumulates BY MAIN
Item
and, if not removed directly from the Site, shall be deposited at CONTRACTOR
collecting points allocated by the Engineer pending removal from the
Site. This Clause in no way invalidates the Contractor's obligations
under Clauses 4.23 of the Conditions of Contract.

Construction Plant and Tools

D The Contractor shall provide all constructional plant, lifting


equipment, transport facilities, tools and services, required for the
BY MAIN
proper execution of the Works. The facilities shall include the Item
CONTRACTOR
provision of protective clothing and safety equipment.

To Collection 0
B1/8
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

TEMPORARY WORKS (Cont'd)

Employer, Engineer and Consultants Site Office

Employer, Engineer and Consultants Site Office including


maintenance in construction period should be accordance with
Specification section 01505

Site Office

A The Contractor to provide a site office for Employer, Engineer and


Consultants in accordance with the Specification section 01505 and as BY MAIN
Item
per Tender Drawings. CONTRACTOR

B The Site office shall include all facilities on site for the use of the
Employer, Engineer, and Consultants and their site staff, in BY MAIN
Item
accordance with the specification section 01505 and drawings. CONTRACTOR

Site Office maintenance during construction period

C The office shall be maintained in a good state of repair throughout the BY MAIN
construction period. Item
CONTRACTOR

D The Contractor shall provide mobile phone, fixed line telephone, fax
machine, photocopier, plotter etc. for the office all as per the BY MAIN
Item
Specifications. CONTRACTOR

E The Contractor to provide the site furniture and equipment for the
Employer, Engineer and Consultant site office staff all as per the BY MAIN
Item
Specifications. CONTRACTOR

F The Contractor shall provide continuous supply of stationary inclusive


of paper include paper for photocopier, fax and plotter, pencils, tapes BY MAIN
Item
etc., for the Employer, Engineer and Consultant site office staff. CONTRACTOR

Parking

G Allow for provision of sufficient temporary covered parking bays for


the Employer, Engineer and Consultants including maintenance, BY MAIN
Item
cleaning and restoring as per Specifications. CONTRACTOR

To Collection 0
B1/9
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

TEMPORARY WORKS (Cont'd)

Electrical Power and Lighting

A The Contractor shall arrange and provide for an adequate temporary


supply of all necessary electrical power and lighting for the Works
including the works of all Sub-Contractors nominated and otherwise BY MAIN
and for paying all charges for the consumption of electricity or CONTRACTOR
Item
supplying, operating and maintaining generators at his own expense (AS PER SCOPE
including for all testing and commissioning and until final handing MATRIX)
over of the Works.

B Any additional lighting for the construction operations, observations BY MAIN


and inspection of the Works shall be provided as instructed by the CONTRACTOR
Item
Engineer. (AS PER SCOPE
MATRIX)

Water

C The Contractor shall arrange for a temporary supply of water suitable


for the Works, including the works of all Sub-Contractors nominated
and otherwise, throughout the duration of the project and including
for all testing and commissioning and until final handing over.
Furthermore, the contractor shall pay all charges for the consumption
of water used. The Contractor shall be responsible for supplying and BY MAIN
maintaining equipment including any necessary pumps, storage tanks, Item
CONTRACTOR
distribution pipe work, etc., required for the execution of the Works.
The Contractor shall also clear away all temporary works on
completion and make good all work disturbed.

D The Contractor shall give all requisite notices, arrange for the
necessary connections and installation of meters, pay all fees and BY MAIN
charges in connection therewith and all charges for water used. Item
CONTRACTOR

E Any interruption of the water supply is at the Contractor's risk and it


is his responsibility to effect all temporary supplies necessary. BY MAIN
Item
CONTRACTOR

To Collection 0
B1/10
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

TEMPORARY WORKS (Cont'd)

Pest Control

A Engage pest-control service to recommend practices to minimise


attraction and harboring of rodents, roaches, and other pests and to
perform extermination and control procedures at regular intervals so
Project will be free of pests and their residues upon at the issue of the
Taking Over Certificate. Ensure no rodents, roaches and other pets are BY MAIN
Item
present on the site during the Defects Notification Period. Obtain CONTRACTOR
extended warranty for Employer. Perform control operations lawfully,
using environmentally safe materials.

Storm Water Control

B To provide barriers in and around excavations and sub-grade


construction to prevent flooding by runoff of storm water from heavy BY MAIN
Item
rains in accordance with the requirements of Applicable Laws. CONTRACTOR

Protection

C Allow for necessary and sufficient / appropriate protection for on


going, completed works from any damages i.e. protective tapes, BY MAIN
Item
casings, guard rails and the like to Engineer's approval. CONTRACTOR

Site Security

D Allow for 24 hours qualified watchmen / security staff for


safeguarding the site, and plant and for making good and reinstating BY MAIN
Item
after any damages or theft. CONTRACTOR

To Collection 0
B1/11
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONTRACT ADMINISTRATION

Contract Documents

A Preparation of complete Contract Documents in Hardcopies and


Item NOTED
softcopies post contract as required by the Engineer / Employer.

Submittal Procedures

B Allow for providing submittals required to ensure that the


performance requirements of the work related to the project are fully Item NOTED
complied with.

Programme

C Allow for providing scheduling and programme submissions in


accordance with Engineer's scheduling requirements and in Item NOTED
accordance with Sub Clause 8.3 of the Conditions of Contract.

Contract Administration Procedures

D The following Contract Administration Procedures shall be adhered


to, with the exception of emergency works. The Contractor shall BY MAIN
maintain a triplicate book on site and all clarifications or information Item
CONTRACTOR
given by the Engineer / Employer on site shall be recorded therein.

E One copy shall be retained and one copy shall be sent to the
Engineer / Employer on a weekly basis. These sheets shall be
numbered, dated, comprise the information or clarification and be
signed by both parties. It is accepted and understood that this
information shall be given for clarification purposes and shall not
constitute any instruction or agreement to vary the works. Any
instruction to vary the works shall only be given in writing on an BY MAIN
approved Site Works Order form. Where such an order is given, it Item
CONTRACTOR
shall state whether or not the Engineer considers the work to be of no
cost, a cost saving or an additional cost. Where a cost variation is
noted or where the Contractor considers a cost variation occurs, he
shall not commence any works until he has submitted a detailed cost
estimate with a breakdown of said costs.

F All site works orders shall be covered by issue of a variation order


which shall detail the agreed cost of the works or in the event of a BY MAIN
Item
continued dispute as to prices, the Engineer’s assessment thereof. CONTRACTOR

To Collection 0
B1/12
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONTRACT ADMINISTRATION (Cont'd)

Site Organisation Chart

A Allow for providing a Site Organisation Chart for Engineer /


Employer review and approval. Item NOTED

Site Supervision Staff

B Allow for adequate and competent on and off site management and
supervisory staff for the proper coordination and administration of the
works. Such staff shall be properly qualified to perform their
respective duties and shall not be removed from the Site or replaced Item 8,263,000
without the prior permission of the Engineer / Employer approval.

Supervision of Other Works

C The Contractor shall provide staff suitably qualified to supervise each


section of the Works or works of other parties to ensure full
compliance with the Specification and the Tender / Contract Item NOTED
Documents.

D The Contractor shall submit a Curriculum Vitae for the Engineer's


approval for each member of staff to be employed on the Project for Item NOTED
supervision of the Works and the works of other parties.

Working with Other Contractors

E The Contractor is understood to be aware that he will not have the COORDINATION
sole use of the Site and is understood to have allowed for working Item ONLY
with all the other separately employed Contractors. INCLUDED

Local Authority Workmen

F The Contractor shall allow access to workmen employed by the local


or other authorities and providing them with attendance as required. CONSIDERED
Item TILL OUR FINAL
OFFER

To Collection 8,263,000
B1/13
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONTRACT ADMINISTRATION (Cont'd)

Site Layout Plan

A Allow for providing a Site Layout Plan for Engineer / Employer


review and approval. Item NOTED

Setting Out

B The Contractor is responsible for setting out of the whole Works to the
true lines and levels in accordance with the contract drawings,
specifications and Conditions of Contract; the Contractor is also
BY MAIN
responsible for preparing the site for the Works before any work or Item
CONTRACTOR
any section of works is commenced and the necessary levels shall be
taken and agreed with Engineer.

Clearing & Grubbing away Rubbish

C Allow for clearing the site clearing i.e. away rubbish at regular BY MAIN
intervals during the progress of the Works and at completion and for CONTRACTOR
leaving the Site and perimeter tidy at completion, all in accordance Item
(AS PER SCOPE
with the Specification and Engineer's & Local Authority MATRIX)
requirements.

Project Coordination

D Allow for complying fully with the project coordination of BY MAIN


subcontractors, suppliers, Tenant Works and Employer's direct CONTRACTOR
Item
contractors. (AS PER SCOPE
MATRIX)

Project Meetings

E Allow for all types of conferences / meetings that are necessary to BY MAIN
ensure full compliance with all the contract obligations. Item
CONTRACTOR

Site Progress Meeting

F Allow for attendance by all personnel as required by the Engineer for BY MAIN
site progress meetings. Item
CONTRACTOR

To Collection 0
B1/14
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONTRACT ADMINISTRATION (Cont'd)

Progress Reports

A Allow for submitting Monthly Progress Reports as required by the


Engineer including but not limited to proposals for taking advantage
of works ahead of programme, a projected Completion Date and For MEP report
estimated Final Account. Item submit through
main contractor

Construction Photographs

B Allow for all aspects of the construction photographs throughout the For MEP report
contract duration in accordance with the Engineers specification. Item submit through
main contractor

Weekly Returns / Weekly Reports

C The Contractor shall submit a report in writing to the Engineer in an For MEP report
agreed form giving a weekly record of the following : Item submit through
main contractor

a. Number & Names of men employed on the works


divided into categories of skill.

b. Accidents to employees.

c. Progress of the work in general terms.

d. Plant on site.

e. Materials on Site.

f. Materials orders schedule showing date of order,


expected delivery date and present status of all the materials
required for the works.

g. Any Others:

……………………………

……………………………

Daily Reports

D Allow for providing daily reports as per specification and to meet For MEP report
Engineer / Employer requirements. Item submit through
main contractor

To Collection
B1/15 0
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONTRACT ADMINISTRATION (Cont'd)

Shop Drawings

A Allow for preparation and submission of shop drawings for all


elements of the works Engineer's approval. Item 762,000

Samples of Materials

B Allow for preparation and submission of all samples of materials


required to the Engineer for approval. Item INCLUDED

Product Data

C Allow for the collection of product data as per specifications for


Engineer's approval. Item INCLUDED

Site Mock-Ups

D Allow for the execution of site mock-ups as per specifications for


Engineer / Employer approval. Item INCLUDED

Quality Assurance

E Allow for providing and managing a Quality Assurance Programme.


This programme should include all requirements for the works and all
reports must be submitted in accordance with dates agreed previously Item INCLUDED
with the Engineer.

Method Statements

F Allow for providing method statements for Engineer review and


approval as per specification and appropriate requirements. Item INCLUDED

Engineers Specification

G Allow for complying with the Engineers Specification. Item INCLUDED

To Collection 762,000
B1/16
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONTRACT ADMINISTRATION (Cont'd)

Payment Procedures

A Allow for complying fully with the payment procedures. Item NOTED

Cash Flow Programme

B Allow for providing Cash Flow Schedule of the Project and submit to
Engineer / Employer. Item NOTED

Overtime Works

C In the event that the Engineer or the Engineer' s Representative or


their assistants are required to supervise the Contractor's operations in
excess of eight (8) working hours per day, or on Fridays or declared
Public Holidays, the cost to the Engineer of such overtime shall be
agreed between the Engineer and the Contractor, and the Employer Item NOTED
who shall deduct the agreed amount from monies certified for
payment to the Contractor. The rates for Engineer's overtime and the
standard working hours are stated below:-

The Engineer's normal working hours are as follows:-


Saturday to Wednesday 8 AM to 12 PM & 1 PM to 5 PM
Thursday 8 AM to 2 PM

Outside of the Engineer's normal working hours shall be deemed as


overtime.

Engineer : Dhs. 250 for each hour


(Structural/Electrical/Mechanical)

Inspector : Dhs. 100 for each hour


(Structural/Electrical/Mechanical)

Senior staff including professionals, partners, directors, and the like


shall not be entitled to, or eligible for, overtime payments.

To Collection 0
B1/17
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONTRACT ADMINISTRATION (Cont'd)

First Aid

A The Contractor shall provide a temporary first aid post properly


equipped and manned by a competent person. The facility shall
display a large red crescent and prominent lettering "FIRST AID" in Item INCLUDED
English and Arabic, in red on a white background.

Accidents

B The Contractor shall promptly report to the Engineer any accident


whatsoever and he shall make the necessary arrangements to obtain
medical help and transport to a hospital. A full statement, giving full
details of the accident, including statements of witnesses shall be Item INCLUDED
promptly submitted to the Engineer.

C If any claim is made by any one against the Contractor or any Sub-
Contractor, the Contractor shall promptly report the facts in writing to
the Engineer giving full details of the claim. Item INCLUDED

To Collection 0
B1/18
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

CONTRACT ADMINISTRATION (Cont'd)

As Built Drawings

A Allow for preparation and submission of "As Built Drawings" in


copies, Hardcopy and Softcopy as required as per Specification and Item INCLUDED
Engineer's requirements.

B The Contractor shall allow where applicable for providing "As Built
Drawings", schedules of equipment, spares lists, maintenance
manuals and the like for the Specialist Installations. This shall include
but not be limited to the Basic Structural and Architectural drawings
and Electrical, Air Conditioning and Ventilation, Drainage, Sanitary Item INCLUDED
and Plumbing Installation drawings. These shall be duly approved by
the appropriate authorities.

Project Record Documents

C Allow for maintaining and submitting Project Records Documents. Item NOTED

Procedure Manuals

D Allow for implementing, maintaining and submitting Procedure


Manuals in a standard format to be approved by the Engineer. Item NOTED

E The Contractor shall include and itemise hereunder any other General
Requirement items required to complete the Works. Item NOTED

Attendance

F Allow for attendance on specialized sub contractors including power,


hoisting and lifting facilities, scaffolding, loading and unloading of AS PER SCOPE
material and equipment, providing free and proper storage space and Item
MATRIX
working space for the execution of his works.

To Collection 0
B1/19
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

STATUTORY REQUIREMENTS

Maintenance of Public Road and Private Road

A Ensure that all roads adjacent to the Site are kept free from spillage
and droppings from construction traffic; any such spillage or BY MAIN
Item
droppings shall be immediately cleared to the satisfaction of the CONTRACTOR
Engineer.

Building Permits, NOC and others Permits

B Allow for obtaining the building permit, NOC and obtaining all
necessary permits or approvals in accordance with all Dubai laws and
regulations from all concerned statutory authorities/departments and BY MAIN
Item
pay all fees and levies applicable thereto in order for the works to CONTRACTOR
proceed and be completed.

Royalties

C Allow for all compensation and royalties due in respect queried BY MAIN
materials. Item
CONTRACTOR

References

D Allow for fully complying with all the current Codes and Regulations MEP WORKS
of all Government Agencies whether fully listed or not. Item
INCLUDED

Safety

E Allow for providing a Project Safety Programme and for all costs
associated with the provision of site safety, health and welfare
FOR REMCO
requirements in accordance with all statutory requirements for health, Item
TEAM INCLUDED
safety and welfare.

To Collection 0
B1/20
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

STATUTORY REQUIREMENTS (Cont'd)

Environmental Controls

A Allow for provision of environmental controls to prevent and reduce BY MAIN


noise and pollution. Item
CONTRACTOR

Traffic Control

B Allow for ascertaining and complying with any traffic restrictions and
regulations, coordinating with adjacent contractors and provision of a BY MAIN
Item
Traffic Management Plan CONTRACTOR

Handing Over

C Allow for obtaining all approvals and respective completion


Certificates from all the local Government Departments, authorities
and the like that the works have been completed in accordance with BY MAIN
Item
their requirements. Any payments in connection therewith shall be CONTRACTOR
allowed for in this item.

To Collection 0
B1/21
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

COMMISSION AND COMPLETION

Final Cleaning

A Allow for final cleaning of the Works by an industrial cleaning MEP WORKS
specialist sub-contractor, etc. Item
INCLUDED

Commissioning

B Allow for starting systems, demonstrations, instructions, testing, INCLUDED FOR


adjusting and balancing Item
MEP WORKS

Operation and Maintenance Data

C Allow for providing Log Book type operation and maintenance data.
FOR MEP WORK
Item
ONLY INCLUDED

Product Warranties/Guarantees

D Allow for assignable warranties of all kind as specified in the


Specification, Bills of Quantities or elsewhere in the Tender Item INCLUDED
documents.

To Collection 0
B1/22
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM DESCRIPTION UNIT AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

A The tenderer is to list down the quantities and rates for any additional
items that shown on the drawings, mentioned in the specifications but
not included in the BoQ section for the satisfaction and completion of
the works. Should the tenderer fail to insert any items in tender will
be deemed to be a lump sum price including all items and no -
subsequent claim for any additional items will be entertained.

1 DEVELOPMENT OF BIM INTO LOD 500 AS THE FINAL 500,000


OUTPUT

To Collection 500,000
B1/23
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17

ITEM SUMMARY AMOUNT


NO. Dirham's

BILL NO. 1 - GENERAL REQUIREMENTS (Cont'd)

COLLECTION

Page B1/1 0

Page B1/2 0

Page B1/3 475,000

Page B1/4 0

Page B1/5 0

Page B1/6 0

Page B1/7 0

Page B1/8 0

Page B1/9 0

Page B1/10 0

Page B1/11 0

Page B1/12 0

Page B1/13 8,263,000

Page B1/14 0

Page B1/15 0

Page B1/16 762,000

Page B1/17 0

Page B1/18 0

Page B1/19 0

Page B1/20 0

Page B1/21 0

Page B1/22 0

Page B1/23 500,000

Total Bill No. 1 - Carried to Final Summary 10,000,000


B1/24
PART ( 1 )

MALL
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS

FOR MALL

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM

Supply, installation, Testing & Commissioning of HVAC system (Heating


Ventilation and Air Conditioning), in accordance with the Drawings,
Specifications, approval of Engineer and all concern code of practice and
local authority regulations.

CHILLED WATER installation

CHILLED WATER PIPE WORKS (Supply and Return)

Supply, installation, testing & commissioning of ERW as per final agreement


chilled water and condenser water pipes including all necessary pipe fittings,
supports, hangers, joints, vibration, pipe expansion compensator, isolators
( Spring type) for header pipes, fixings and all necessary fixing accessories, all
complete in accordance with the Drawings and Specifications.

A CHW 3/4 inch dia (20 mm dia) m 652 118 76,936


B CHW 1 inch dia (25 mm dia) m 670 144 96,480
C CHW 1 1/4 inch dia (32 mm dia) m 1,050 192 201,600
D CHW 1 1/2 inch dia (40 mm dia) m 850 231 196,350
E CHW 2 inch dia (50 mm dia) m 1,234 284 350,456
F CHW 2 1/2 inch dia (65 mm dia) m 664 445 295,480
G CHW 3 inch dia (80 mm dia) m 700 584 408,800
H CHW 4 inch dia (100 mm dia) m 614 833 511,462
J CHW 5 inch dia (125 mm dia) m 388 1,120 434,560
K CHW 6 inch dia (150 mm dia) m 234 1,460 341,640
L CHW 8 inch dia (200 mm dia) m 216 2,231 481,896
M CHW 10 inch dia (250 mm dia) m 65 3,202 208,130

To Collection 3,603,790
B13/1
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

CHILLED WATER PIPE WORKS (Supply and Return) (Cont'd)

Supply, installation, testing & commissioning of ERW as per final agreement


chilled water and condenser water pipes including all necessary pipe fittings,
supports, hangers, joints, vibration, pipe expansion compensator, isolators
( Spring type) for header pipes, fixings and all necessary fixing accessories, all
complete in accordance with the Drawings and Specifications. (Cont'd)

A CHW 12 inch dia (300 mm dia) m 179 4,283 766,657

B CHW 14 inch dia (350 mm dia) m 124 5,115 634,260

C CHW 16 inch dia (400 mm dia) m 15 6,365 95,475

D CHW 20 inch dia (500 mm dia) m 115 9,646 1,109,290

E CHW 24 inch dia (600 mm dia) m 84 11,062 929,208

F CHW 26 inch dia (650 mm dia) m 14 12,856 179,984

G CHW 30 inch dia (750 mm dia) m 84 14,834 1,246,056

Miscellaneous piping

Chemical treatment piping from dosing pumps to chilled water and condenser
H item 1 213,799 213,799
water headers

J Refrigerant relief piping item 1 7,000 7,000

To Collection 5,181,729
B13/2
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

INSULATION TO PIPE WORKS (Supply and Return)

Supply, installation, testing of chilled water & Condenser water piping


insulation, including adhesive, vapour barrier, canvas cloth with vapour barrier
for the satisfaction of the Engineer for the following (but not limited to) all
complete in accordance with the Drawings and Specifications.

A CHW 3/4 inch dia (20 mm dia) m 652 97 63,244

B CHW 1 inch dia (25 mm dia) m 670 106 71,020

C CHW 1 1/4 inch dia (32 mm dia) m 1,050 140 147,000

D CHW 1 1/2 inch dia (40 mm dia) m 850 164 139,400

E CHW 2 inch dia (50 mm dia) m 1,234 207 255,438

F CHW 2 1/2 inch dia (65 mm dia) m 664 318 211,152

G CHW 3 inch dia (80 mm dia) m 700 423 296,100

H CHW 4 inch dia (100 mm dia) m 614 596 365,944

J CHW 5 inch dia (125 mm dia) m 388 803 311,564

K CHW 6 inch dia (150 mm dia) m 234 1,048 245,232

L CHW 8 inch dia (200 mm dia) m 216 1,600 345,600

M CHW 10 inch dia (250 mm dia) m 65 2,296 149,240

To Collection 2,600,934
B13/3
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

INSULATION TO PIPE WORKS (Supply and Return) (Cont'd)

Supply, installation, testing of chilled water & Condenser water piping


insulation, including adhesive, vapour barrier, canvas cloth with vapour barrier
for the satisfaction of the Engineer for the following (but not limited to) all
complete in accordance with the Drawings and Specifications (Cont'd)

A CHW 12 inch dia (300 mm dia) m 179 3,070 549,530

B CHW 14 inch dia (350 mm dia) m 124 3,665 454,460

C CHW 16 inch dia (400 mm dia) m 15 4,563 68,445

D CHW 20 inch dia (500 mm dia) m 115 5,318 611,570

E CHW 24 inch dia (600 mm dia) m 84 6,100 512,400

F CHW 26 inch dia (650 mm dia) m 14 7,090 99,260

G CHW 30 inch dia (750 mm dia) m 84 8,180 687,120

To Collection 2,982,785
B13/4
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

ALUMINIUM CLADDING TO PIPE WORKS (Supply and Return)

Supply & installation of 0.9 mm thick corrugated aluminium cladding to


chilled water pipe work exposed to view, exposed to outdoor and plant room
complete as per Drawings and Specifications.

A CHW 3/4 inch dia (20 mm dia) m 33 115 3,795


B CHW 1 inch dia (25 mm dia) m 31 125 3,875
C CHW 1 1/4 inch dia (32 mm dia) m 86 130 11,180
D CHW 1 1/2 inch dia (40 mm dia) m 140 190 26,600
E CHW 2 inch dia (50 mm dia) m 107 200 21,400
F CHW 2 1/2 inch dia (65 mm dia) m 290 210 60,900
G CHW 3 inch dia (80 mm dia) m 439 230 100,970
H CHW 4 inch dia (100 mm dia) m 519 250 129,750
J CHW 5 inch dia (125 mm dia) m 388 270 104,760
K CHW 6 inch dia (150 mm dia) m 234 300 70,200
L CHW 8 inch dia (200 mm dia) m 216 350 75,600
M CHW 10 inch dia (250 mm dia) m 65 400 26,000
N CHW 12 inch dia (300 mm dia) m 179 450 80,550
P CHW 14 inch dia (350 mm dia) m 124 500 62,000
Q CHW 16 inch dia (400 mm dia) m 15 550 8,250
R CHW 20 inch dia (500 mm dia) m 115 650 74,750
S CHW 24 inch dia (600 mm dia) m 84 750 63,000
T CHW 26 inch dia (650 mm dia) m 14 800 11,200
U CHW 30 inch dia (750 mm dia) m 84 900 75,600

To Collection 1,010,380
B13/5
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES

Supply, installation testing and commissioning of valves to chilled water


pipes, all complete in accordance with the Drawings and Specifications.

Isolation valve

A IV 3/4 inch dia (20 mm dia) no. 24 87 2,088


B IV 1 inch dia (25 mm dia) no. 16 125 2,000
C IV 1 1/4 inch dia (32 mm dia) no. 74 193 14,282
D IV 1 1/2 inch dia (40 mm dia) no. 71 260 18,460
E IV 2 inch dia (50 mm dia) no. 43 409 17,587
F IV 2 1/2 inch dia (65 mm dia) no. 19 1,067 20,273
G IV 3 inch dia (80 mm dia) no. 6 1,273 7,638
H IV 4 inch dia (100 mm dia) no. 11 1,802 19,822
J IV 5 inch dia (125 mm dia) no. 8 2,493 19,944
K IV 6 inch dia (150 mm dia) no. 2 3,319 6,638
L IV 8 inch dia (200 mm dia) no. 1 4,102 4,102

Variable Orifice Double regulation valve (VODRV)

M VODRV 3/4 inch dia (20 mm dia) no. 24 274 6,576


N VODRV 1 inch dia (25 mm dia) no. 16 298 4,768
P VODRV 1 1/4 inch dia (32 mm dia) no. 74 351 25,974
Q VODRV 1 1/2 inch dia (40 mm dia) no. 71 466 33,086
R VODRV 2 inch dia (50 mm dia) no. 43 577 24,811
S VODRV 2 1/2 inch dia (65 mm dia) no. 19 1,163 22,097

To Collection 250,146
B13/6
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation testing and commissioning of valves to chilled water


pipes, all complete in accordance with the Drawings and Specifications .
(Cont'd)

Variable Orifice Double regulation valve (VODRV)

A VODRV 3 inch dia (80 mm dia) no. 6 1,792 10,752


B VODRV 4 inch dia (100 mm dia) no. 11 2,330 25,630
C VODRV 5 inch dia (125 mm dia) no. 8 3,310 26,480
D VODRV 6 inch dia (150 mm dia) no. 2 3,881 7,762
E VODRV 8 inch dia (200 mm dia) no. 1 7,095 7,095
F VODRV 10 inch dia (300 mm dia) no. 3 9,756 29,268
G VODRV 16 inch dia (400 mm dia) no. 1 11,053 11,053
H Automatic air vent 25 mm dia with Isolating valve no. 25 236 5,900
Drain Cock
J Drain Cock - 10 Inch dia (300 mm dia) no. 2 5,001 10,002
K Drain Cock - 2 Inch dia (50 mm dia) no. 6 293 1,758
L Drain Cock - 5 Inch dia (125 mm dia) no. 6 1,797 10,782
M Drain Cock - 6 Inch dia (150 mm dia) no. 6 2,392 14,352
N Drain Cock - 8 Inch dia (200 mm dia) no. 2 2,950 5,900
Supply, installation testing and commissioning of Ultrasonic type BTU
meters(to be interfaced with BMS ) to chilled water pipes including
necessary fixings, all complete in accordance with the Drawings and
Specifications.
F Ultrasonic type BTU meter 3/4 inch dia (20 mm dia) no. 10 1,100 11,000
G Ultrasonic type BTU meter 1 inch dia (25 mm dia) no. 11 1,200 13,200
H Ultrasonic type BTU meter 1 1/4 inch dia (32 mm dia) no. 73 2,100 153,300

To Collection 344,234
B13/7
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

Supply, installation testing and commissioning of Ultrasonic type BTU


meters(to be interfaced with BMS ) to chilled water pipes including necessary
fixings, all complete in accordance with the Drawings and Specifications.

A Ultrasonic type BTU meter 1 1/2 inch dia (40 mm dia) no. 69 3,200 220,800
B Ultrasonic type BTU meter 2 inch dia (50 mm dia) no. 35 4,400 154,000
C Ultrasonic type BTU meter 2 1/2 inch dia (65 mm dia) no. 18 6,500 117,000
D Ultrasonic type BTU meter 3 inch dia (80 mm dia) no. 2 7,400 14,800
E Ultrasonic type BTU meter 4 inch dia (100 mm dia) no. 4 10,683 42,732
F Ultrasonic type BTU meter 5 inch dia (125 mm dia) no. 1 13,680 13,680

Flow meters
G Flow meter 250 mm dia no. 1 27,868 27,868
H Flow meter (For each Chillers (400mm dia) + Headers (750mm dia)) no. 6 31,701 190,206
Allow for flexible joints at places where the chilled water pipework crosses
J item 1 219,370 219,370
the building expansion joint.

Air outlets

Supply, installation, testing and commissioning of Supply and


return air outlets for air conditioning, fresh air Supply, fresh air
return and extract air, lobby pressurization ducts and smoke
extract with complete duct connection and necessary ancillaries, access doors
etc. in accordance Drawings and Specifications.

Supply air diffuser

K SAD 150X150 mm no. 2 68 136


L SAD 225X225 mm no. 3 101 303
M SAD 300X300 mm no. 112 145 16,240
N SAD 300X300 mm no. 112 145 16,240

To Collection 1,033,375
B13/8
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Air outlets (Cont'd)

Supply, installation, testing and commissioning of Supply and


return air outlets for air conditioning, fresh air Supply, fresh air
return and extract air, lobby pressurization ducts and smoke
extract with complete duct connection and necessary ancillaries, access doors
etc. in accordance Drawings and Specifications. (Cont'd)

Supply air diffuser

A SAD 300X300 mm no. 112 145 16,240

B SAD 375X375 mm no. 73 193 14,089


C SAD 450X450 mm no. 13 231 3,003
D SAD 525X525 mm no. 39 318 12,402
Return air diffuser
E RAD 150X150 mm no. 2 58 116
F RAD 225X225 mm no. 3 77 231
G RAD 300X300 mm no. 104 106 11,024
H RAD 375X375 mm no. 73 145 10,585
J RAD 450X450 mm no. 13 178 2,314
K RAD 525X525 mm no. 39 221 8,619
Exhaust air diffuser
L EAD 225X225 mm no. 169 77 13,013
Supply air grille

M SAG 350X150 mm no. 3 82 246


N SAG 300X200 mm no. 2 77 154

To Collection 92,036
B13/9
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Air outlets (Cont'd)

Supply, installation, testing and commissioning of Supply and


return air outlets for air conditioning, fresh air Supply, fresh air
return and extract air, lobby pressurization ducts and smoke
extract with complete duct connection and necessary ancillaries, access doors
etc. in accordance Drawings and Specifications. (Cont'd)

Supply air grille (Cont'd)

A SAG 500X150 mm no. 1 101 101


B SAG 500X200 mm no. 1 125 125
C SAG 600X150 mm no. 2 116 232
D SAG 600X200 mm no. 2 145 290
E SAG 700X200 mm no. 2 164 328
F SAG 750X250 mm no. 1 202 202
G SAG 800X200 mm no. 2 183 366
H SAG 900X200 mm no. 1 193 193
J SAG 950X300 mm no. 2 308 616
K SAG 1000X250 mm no. 1 260 260
L SAG 1200X200 mm no. 1 269 269
M SAG 1200X250 mm no. 1 303 303
Return air grille

N RAG 300X200 mm no. 2 58 116


P RAG 350X150 mm no. 3 58 174
Q RAG 500X150 mm no. 1 73 73
R RAG 500X200 mm no. 1 92 92

To Collection 3,740
B13/10
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

Air outlets (Cont'd)

Supply, installation, testing and commissioning of Supply and


return air outlets for air conditioning, fresh air Supply, fresh air
return and extract air, lobby pressurization ducts and smoke
extract with complete duct connection and necessary ancillaries,
access doors etc. in accordance Drawings and Specifications. (Cont'd)

Return air grille (Cont'd)

A RAG 600X150 mm no. 2 87 174


B RAG 600X200 mm no. 2 101 202
C RAG 700X200 mm no. 2 116 232
D RAG 750X250 mm no. 1 145 145
E RAG 800X200 mm no. 2 130 260
F RAG 900X200 mm no. 1 145 145
G RAG 950X300 mm no. 2 221 442
H RAG 1000X250 mm no. 1 193 193
J RAG 1200X200 mm no. 1 188 188
K RAG 1200X250 mm no. 1 226 226
Combined grille

L Comb.AG 400X200 mm no. 2 169 338


M Comb.AG 600X150 mm no. 3 202 606
N Comb.AG 750X200 mm no. 6 293 1,758
P Comb.AG 900X150 mm no. 3 279 837

To Collection 5,746
B13/11
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Air outlets (Cont'd)

Supply, installation, testing and commissioning of Supply and


return air outlets for air conditioning, fresh air Supply, fresh air
return and extract air, lobby pressurization ducts and smoke
extract with complete duct connection and necessary ancillaries,
access doors etc. in accordance Drawings and Specifications. (Cont'd)

Exhaust air grille with VCD

A EAG with VCD 500X150 mm no. 1,274 197 250,978


Make up air grille with VCD

B MAG with VCD 1000X150 mm no. 194 313 60,722


Slot diffuser

C SLD&RLD 2 slot 20 mm slot opening m 651 125 81,375


D SLD&RLD 3 slot 20 mm slot opening m 757 173 130,961
E SLD&RLD 4 slot 20 mm slot opening m 1,219 217 264,523
F SLD&RLD 4 slot 25 mm slot opening m 25 217 5,425
G SLD&RLD 6 slot 20 mm slot opening m 1,009 313 315,817
Jet diffuser

H Jet diffuser 250 mm dia no. 80 812 64,960


J Jet diffuser 400 mm dia no. 92 1,144 105,248
Air curtains includes supply ,installation , testing and comissioning

K Air curtain 1200 CFM no. 6 4,804 28,824


L Air curtain 800 CFM no. 42 4,035 169,470
M Air curtain 8000 CFM no. 3 25,937 77,811

To Collection 1,556,114
B13/12
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface with
various other systems i.e. fire alarm, BMS etc. for satisfactory functioning of
all systems in accordance with the Drawings and Specifications .

Sensors

A CO sensor no. 64 1,057 67,648


B CO2 Sensor no. 89 1,057 94,073
Fire damper

C FD 1000X550 mm no. 1 375 375


D FD 1000X600 mm no. 5 380 1,900
E FD 1000X700 mm no. 6 457 2,742
F FD 1000X750 mm no. 1 471 471
G FD 1050X600 mm no. 1 543 543
H FD 1050X750 mm no. 7 659 4,613
J FD 1100X400 mm no. 2 471 942
K FD 1100X500 mm no. 2 524 1,048
L FD 1100X600 mm no. 4 543 2,172
M FD 1100X650 mm no. 5 635 3,175
N FD 1100X750 mm no. 3 668 2,004
P FD 1100X900 mm no. 2 721 1,442
Q FD 1150X700 mm no. 1 659 659
R FD 1200X1000 mm no. 2 788 1,576
S FD 1200X500 mm no. 2 538 1,076

To Collection 186,459
B13/13
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface with
various other systems i.e. fire alarm, BMS etc. for satisfactory functioning of
all systems in accordance with the Drawings and Specifications. (Cont'd)

Fire damper (Cont'd)

A FD 1200X600 mm no. 4 683 2,732


B FD 1200X650 mm no. 4 779 3,116
C FD 1200X750 mm no. 5 822 4,110
D FD 1200X800 mm no. 2 846 1,692
E FD 1250X600 mm no. 1 711 711
F FD 1250X700 mm no. 1 831 831
G FD 1250X750 mm no. 1 855 855
H FD 1250X800 mm no. 3 879 2,637
J FD 1300X550 mm no. 2 716 1,432
K FD 1300X600 mm no. 2 735 1,470
L FD 1300X650 mm no. 2 846 1,692
M FD 1300X750 mm no. 2 889 1,778
N FD 1300X950 mm no. 2 1,004 2,008
P FD 1350X500 mm no. 4 726 2,904
Q FD 1350X750 mm no. 6 923 5,538
R FD 1350X800 mm no. 4 947 3,788
S FD 1350X850 mm no. 1 971 971

To Collection 38,265
B13/14
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface with
various other systems i.e. fire alarm, BMS etc. for satisfactory functioning of
all systems in accordance with the Drawings and Specifications. (Cont'd)

Fire damper (Cont'd)

A FD 1400X600 mm no. 2 793 1,586


B FD 1400X650 mm no. 2 908 1,816
C FD 1400X700 mm no. 1 932 932
D FD 1400X750 mm no. 2 956 1,912
E FD 1400X800 mm no. 2 985 1,970
F FD 1400X850 mm no. 1 1,009 1,009
G FD 1400X900 mm no. 2 1,033 2,066
H FD 1450X750 mm no. 2 990 1,980
J FD 1500X1000 mm no. 2 1,182 2,364
K FD 1500X500 mm no. 6 803 4,818
L FD 1500X600 mm no. 1 851 851
M FD 1500X650 mm no. 5 976 4,880
N FD 1500X700 mm no. 5 1,000 5,000
P FD 1500X750 mm no. 13 1,024 13,312
Q FD 1500X800 mm no. 4 1,052 4,208
R FD 1500X850 mm no. 1 1,081 1,081
S FD 150X100 mm no. 5 183 915

To Collection 50,700
B13/15
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface with
various other systems i.e. fire alarm, BMS etc. for satisfactory functioning of
all systems in accordance with the Drawings and Specifications. (Cont'd)

Fire damper (Cont'd)

A FD 150X150 mm no. 1 188 188


B FD 1550X850 mm no. 1 1,115 1,115
C FD 1600X1000 mm no. 1 1,259 1,259
D FD 1600X600 mm no. 6 908 5,448
E FD 1600X750 mm no. 1 1,096 1,096
G FD 1700X600 mm no. 2 961 1,922
H FD 1750X600 mm no. 4 990 3,960
J FD 200X150 mm no. 30 193 5,790
K FD 200X200 mm no. 43 197 8,471
L FD 250X150 mm no. 17 197 3,349
M FD 250X200 mm no. 59 202 11,918
N FD 250X250 mm no. 7 207 1,449
P FD 300X150 mm no. 1 202 202
Q FD 300X200 mm no. 41 207 8,487
R FD 300X250 mm no. 15 217 3,255
S FD 300X300 mm no. 3 226 678
T FD 350X200 mm no. 10 212 2,120

To Collection 60,707
B13/16
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface with
various other systems i.e. fire alarm, BMS, etc. for satisfactory functioning of
all systems in accordance with the Drawings and Specifications. (Cont'd)

Fire damper (Cont'd)

A FD 350X250 mm no. 7 221 1,547


B FD 350X300 mm no. 4 231 924
C FD 400X200 mm no. 3 217 651
D FD 400X250 mm no. 6 226 1,356
E FD 400X300 mm no. 51 241 12,291
F FD 400X350 mm no. 1 250 250
G FD 450X250 mm no. 12 231 2,772
H FD 450X300 mm no. 3 245 735
J FD 450X350 mm no. 6 255 1,530
K FD 450X500 mm no. 1 298 298
L FD 500X250 mm no. 8 236 1,888
M FD 500X300 mm no. 12 250 3,000
N FD 500X350 mm no. 6 265 1,590
P FD 500X400 mm no. 1 274 274
Q FD 500X450 mm no. 3 279 837
R FD 550X250 mm no. 1 241 241
S FD 550X300 mm no. 11 260 2,860

To Collection 33,044
B13/17
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface with
various other systems i.e. fire alarm, BMS etc. for satisfactory functioning of
all systems in accordance with the Drawings and Specifications. (Cont'd)

Fire damper (Cont'd)

A FD 550X350 mm no. 7 269 1,883


B FD 550X400 mm no. 1 279 279
C FD 600X250 mm no. 1 250 250
D FD 600X300 mm no. 8 265 2,120
E FD 600X350 mm no. 5 279 1,395
F FD 600X400 mm no. 12 289 3,468
G FD 600X450 mm no. 4 298 1,192
H FD 650X300 mm no. 5 279 1,395
J FD 650X350 mm no. 2 284 568
K FD 650X400 mm no. 3 293 879
L FD 650X500 mm no. 2 332 664
M FD 650X550 mm no. 2 342 684
N FD 650X600 mm no. 5 351 1,755
P FD 700X200 mm no. 3 250 750
Q FD 700X250 mm no. 1 260 260
R FD 700X300 mm no. 3 274 822
S FD 700X350 mm no. 1 293 293

To Collection 18,657
B13/18
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface with
various other systems i.e. fire alarm, BMS etc. for satisfactory functioning of
all systems in accordance with the Drawings and Specifications. (Cont'd)

Fire damper (Cont'd)

A FD 700X400 mm no. 1 303 303


B FD 700X600 mm no. 2 361 722
C FD 750X400 mm no. 1 308 308
D FD 750X750 mm no. 1 447 447
E FD 800X600 mm no. 2 375 750
F FD 850X400 mm no. 2 356 712
G FD 900X400 mm no. 1 366 366
H FD 900X450 mm no. 3 380 1,140
J FD 900X550 mm no. 1 423 423
K FD 900X600 mm no. 3 438 1,314
L FD 900X700 mm no. 1 524 524
M FD 900X750 mm no. 1 538 538
N FD 900X850 mm no. 2 572 1,144
P FD 950X800 mm no. 1 567 567

To Collection 9,258
B13/19
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, etc. for satisfactory
functioning of all systems in accordance with the Drawings and
Specifications. (Cont'd)

Volume Control Damper

A VCD 150X100 mm no. 13 92 1,196


B VCD 150X150 mm no. 144 92 13,248
C VCD 200X150 mm no. 41 97 3,977
D VCD 200X200 mm no. 43 101 4,343
E VCD 250X150 mm no. 9 106 954
F VCD 250X200 mm no. 69 116 8,004
G VCD 250X250 mm no. 9 121 1,089
H VCD 300X200 mm no. 42 125 5,250
J VCD 300X250 mm no. 9 145 1,305
K VCD 300X300 mm no. 2 169 338
L VCD 350X200 mm no. 11 145 1,595
M VCD 350X250 mm no. 11 159 1,749
N VCD 400X200 mm no. 1 169 169
P VCD 400X250 mm no. 1 188 188
Q VCD 400X300 mm no. 47 202 9,494
R VCD 400X350 mm no. 1 221 221
S VCD 450X250 mm no. 5 207 1,035

To Collection 54,155
B13/20
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, etc. for satisfactory
functioning of all systems in accordance with the Drawings and
Specifications. (Cont'd)

Volume Control Damper (Cont'd)

A VCD 450X300 mm no. 1 217 217


B VCD 500X250 mm no. 6 231 1,386
C VCD 500X300 mm no. 5 236 1,180
D VCD 500X350 mm no. 2 265 530
E VCD 500X400 mm no. 2 274 548
F VCD 550X300 mm no. 2 255 510
G VCD 550X400 mm no. 1 303 303
H VCD 600X300 mm no. 3 303 909
J VCD 600X350 mm no. 1 332 332
K VCD 600X400 mm no. 1 337 337
L VCD 650X300 mm no. 2 337 674
M VCD 700X300 mm no. 2 366 732
N VCD 750X400 mm no. 1 394 394
P VCD 850X400 mm no. 1 433 433

To Collection 8,485
B13/21
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface with
various other systems i.e. fire alarm, BMS etc. for satisfactory functioning of
all systems in accordance with the Drawings and Specifications. (Cont'd)

Motorized smoke & fire damper

A MSFD 1100X750 mm no. 65 3,459 224,835


B MSFD 1200X750 mm no. 2 3,555 7,110
C MSFD 1400X750 mm no. 2 3,747 7,494
D MSFD 1500X500 mm no. 6 3,555 21,330
E MSFD 1500X900 mm no. 1 4,131 4,131
F MSFD 1600X800 mm no. 9 4,131 37,179
G MSFD 1600X850 mm no. 1 4,131 4,131
H MSFD 1650X800 mm no. 5 4,131 20,655
J MSFD 1700X750 mm no. 1 4,131 4,131
K MSFD 1700X900 mm no. 5 4,323 21,615
L MSFD 800X750 mm no. 1 3,075 3,075
M Motorized damper for FAHU's interface with BMS no. 62 1,922 119,164
N Motorized damper for AHU's interface with BMS no. 94 1,826 171,644
P MSFD for all FM200 Rooms no. 57 1,441 82,137

Motorized damper interfaced with BMS & FACP for FAHU


Q no. 2 1,922 3,844
(HYPERMARKET & DEPARTMENT STORE)

To Collection 732,475
B13/22
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, etc. for satisfactory
functioning of all systems in accordance with the Drawings and Specifications
. (Cont'd)

NON RETURN DAMPER

A NRD 1100X750 mm no. 88 577 50,776


B NRD 1200X750 mm no. 4 635 2,540
C NRD 1400X750 mm no. 4 663 2,652
D NRD 1600X800 mm no. 4 817 3,268
E NRD 1600X850 mm no. 2 865 1,730
F NRD 1650X800 mm no. 8 836 6,688
G NRD 1700X750 mm no. 2 807 1,614
H NRD 1700X900 mm no. 2 971 1,942
J NRD 800X750 mm no. 2 548 1,096
SOUND ATTENUATOR

K Sound Attenuator for AHU's no. 47 4,323 203,181

L Sound Attenuator for FAHU's no. 31 5,284 163,804

M
Sound Attenuator for FAHU (HYPERMARKET & DEPARTMENT STORE) no. 2 5,111 10,222

To Collection 449,513
B13/23
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FRESH AIR LOUVERS

Supply, installation, testing and commissioning of louvers with Stainless steel


wire mesh including all necessary accessories, ancillaries and joints to duct
work complete as per Drawings and Specifications.

A FA louver SS wire mesh with filter 750X100 mm no. 4 106 424


B FA louver SS wire mesh with filter 150X100 mm no. 3 58 174
C Fresh air sand trap louver 1.2m2 no. 1 683 683
D Fresh air sand trap louver 1400x750 mm no. 1 596 596
E Fresh air sand trap louver 1500x800 mm no. 2 673 1,346
F Fresh air sand trap louver 2.6 m2 no. 8 1,461 11,688
G Fresh air sand trap louver 2.84m2 no. 2 1,576 3,152
H Fresh air sand trap louver 2.8m2 no. 2 1,566 3,132
J Fresh air sand trap louver 2m2 no. 1 1,124 1,124
K Fresh air sand trap louver 3.4 m2 no. 11 1,912 21,032
L Fresh air sand trap louver 3.8m2 no. 2 2,123 4,246
M Fresh air sand trap louver 5.2 m2 no. 1 2,911 2,911
N Fresh air sand trap louver 5.3m2 no. 4 2,959 11,836
P Fresh air sand trap louver 5.7m2 no. 3 3,180 9,540
Q Aluminium louver for LPG shaft as per the requirements by authority . item 1 14,410 14,410

Make up Sand trap louver 6 feetX10 feet (HYPERMARKET &


DEPARTMENT STORE) no. 1 2,210 2,210

Sand trap louver for FAHU (HYPERMARKET & DEPARTMENT STORE) no. 1 INCLUDED

Sand trap louver for Kitchen make up fan (HYPERMARKET &


DEPARTMENT STORE) no. 8 INCLUDED

To Collection 88,504
B13/24
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FRESH AIR LOUVERS (Cont'd)

Supply, installation, testing and commissioning of louvers with Stainless steel


wire mesh including all necessary accessories, ancillaries and joints to duct
work complete as per Drawings and Specifications. (Cont'd)

A Fresh air sand trap louver 6.4 m2 no. 2 3,584 7,168


B Fresh air sand trap louver 7.4 m2 no. 1 4,141 4,141
C Fresh air sand trap louver 900x750 mm no. 1 385 385
D Fresh air sand trap louver 11.7 m2 no. 1 6,533 6,533
E Fresh air sand trap louver 5.1 m2 no. 1 2,863 2,863
F Fresh air sand trap louver 6.4 m2 no. 1 3,584 3,584
G Fresh air sand trap louver 7.4 m2 no. 1 4,141 4,141
Flexible duct including insulation, band clips, brackets, barrier supports and
fixing accessories complete; in accordance with Drawings & Specifications.

H Flexible duct 150 mm dia m 61 25 1,525


J Flexible duct 200 mm dia m 21 29 609
K Flexible duct 250 mm dia m 701 39 27,339
Rate Only

L Flexible duct 100 mm dia m 20 Rate only


M Flexible duct 300 mm dia m 44 Rate only

To Collection 58,288
B13/25
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of louvers including all


necessary accessories, ancillaries and joints to duct work complete as per
Drawings and Specifications. (Cont'd)

Bell mouth

A Bell mouth with SS wire mesh 1200X750 mm no. 5 534 2,670


B Bell mouth with SS wire mesh 1300X600 mm no. 1 519 519
C Bell mouth with SS wire mesh 1400X750 mm no. 4 586 2,344
D Bell mouth with SS wire mesh 1600X800 mm no. 2 654 1,308
E Bell mouth with SS wire mesh 1600X850 mm no. 2 668 1,336
F Bell mouth with SS wire mesh 1650X800 mm no. 4 668 2,672
G Bell mouth with SS wire mesh 1700X750 mm no. 3 668 2,004
H Bell mouth with SS wire mesh 1800X750 mm no. 2 692 1,384
J Bell mouth with SS wire mesh 500X250 mm no. 1 207 207
K Bell mouth with SS wire mesh 750X600 mm no. 1 370 370
L Bell mouth with SS wire mesh 800X750 mm no. 2 423 846
M Bell mouth with SS wire mesh 950X800 mm no. 1 476 476
N All the bell mouth inside the building should be with SS wire mesh item 1 40,347 40,347

P Bell mouth with wire mesh (HYPERMARKET & DEPARTMENT STORE) item 1 8,646 8,646

To Collection 65,129
B13/26
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

Duct Work

Supply, fabricate and installation GI / fire rated sheet metal rectangular


ductwork complete with plenum box, turning vanes, flexible duct connector,
cross jointing, jointing materials and sealants, access panels, demountable
sections, brackets, hangers, supports, etc. as per SMACNA standards, all
complete in accordance with the Drawings and Specifications .

Supply & Return air duct

A SAD/RAD, 26 gauge (GI) KG 595 22 13,090


B SAD/RAD, 24 gauge (GI) KG 29,656 22 652,432
C SAD/RAD, 22 gauge (GI) KG 47,334 22 1,041,348
D SAD/RAD, 20 gauge (GI) KG 47,311 22 1,040,842
E SAD/RAD, 18 gauge (GI) KG 10 22 Rate only
F SAD/RAD, 16 gauge (GI) KG 10 22 Rate only
Fresh air duct

G FAD, 26 gauge (GI) KG 2,212 22 48,664


H FAD, 24 gauge (GI) KG 27,742 22 610,324
J FAD, 22 gauge (GI) KG 25,151 22 553,322
K FAD, 20 gauge (GI) KG 10,716 22 235,752
L FAD, 18 gauge (GI) KG 10 22 Rate only
M FAD, 16 gauge (GI) KG 10 22 Rate only
Exhaust air duct

N EAD, 26 gauge (GI) KG 2,374 22 52,228


P EAD, 24 gauge (GI) KG 14,338 22 315,436
Q EAD, 22 gauge (GI) KG 15,230 22 335,060
R EAD, 20 gauge (GI) KG 2,661 22 58,542

To Collection 4,957,040
B13/27
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Duct Work (Cont'd)

A EAD, 18 gauge (GI) KG 10 22 Rate only

B EAD, 16 gauge (GI) KG 10 22 Rate only

Supply, fabricate and installation GI / fire rated sheet metal rectangular


ductwork complete with plenum box, turning vanes, fire rated flexible duct
connector, cross jointing, jointing materials and sealants, access panels,
demountable sections, brackets, hangers, supports, etc. as per SMACNA
standards, all complete in accordance with the Drawings and Specifications.
(Cont'd)

Garbage air duct

C GED, 24 gauge (GI) KG 176 22 3,872

Fire rated duct

D Fire rated ductwork for smoke extract, smoke make up, staircase and lift well KG 481,460 36 17,332,560

E KMAD, 18 gauge (Fire rated) KG 37,039 36 1,333,404

F KED, 18 gauge (Fire rated) (Black steel duct) KG 40,598 42 1,705,116

INCLUDED IN
G Allow for black steel duct from kitchen hood to the main extract duct item
ITEM F

H Black steel duct KG 42 Rate only

To Collection 20,374,952
B13/28
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Insulation to Duct Work

Fibber Glass thermal insulation to ductwork including adhesive, vapour


barrier, canvas cloth, mechanical protection, (cladding for external area and
exposed to view ducts ) forming to all fittings, test holes, access panel and the
like, all complete in accordance with the Drawings and Specifications .

Supply & Return air duct insulation

A SAD/RAD-Thermal insulation 25 mm thick m2 12,053 101 1,217,353

B SAD/RAD-Thermal insulation 50 mm thick m2 6,752 221 1,492,192

Fresh air duct insulation

C FAD-Thermal insulation 25 mm thick m2 4,038 101 407,838

D FAD-Thermal insulation 50 mm thick m2 6,936 221 1,532,856

Exhaust air duct insulation

E EAD-Thermal insulation 25 mm thick m2 3,982 101 402,182

F EAD-Thermal insulation 50 mm thick m2 1,915 221 423,215

Kitchen extract duct insulation

G KED-Thermal insulation 50 mm thick m2 3,929 116 455,764

H Acoustic liner Insulation 25mm thick item 1 254,594 254,594

J Acoustic liner Insulation 25mm thick m2 49 Rate only

To Collection 6,185,994
B13/29
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT

Chilled water systems including operation controls, filters, strainers, control


valves, sensor, thermostat, wiring, vibration isolators, fixing accessories, etc.,
all complete in accordance with the Drawings and Specifications .

Water cooled chiller

Supply and installation of complete Water Cooled Centrifugal Chillers


including (but not limited to), Compressor & Motor Drive Line suitable for
11kV/50Hz power supply, Evaporator, Condenser, Expansion Device, Starter
panel with Control and all other necessary components as per Specifications.
Equipment must include hoisting and setting in positions, thermostats,
vibration isolator wiring, valves, controls, supports, joint fixings, acoustic
lining, final connection and all necessary fixings, fittings and accessories,
interfacing with BMS all complete in accordance with the Drawings and
Specifications.

A
Water cooled chiller with below Specifications:
Capacity - 1800 TR
Chilled Water in/out - 5.5/12.2 C
Condenser Water in/out - 34.4/40.0 C no. 5 1,790,612 8,953,060
Fouling - Evap: 0.0001 FPS/Condenser 0.00025 FPS
Pressure Drop; Less than 80kPa in Evap/70 kPa in Cond
Complete with FCMA Starters suitable to all Authority requirements.

B Sound insulation system for the Chillers either Compressor Acoustic Blankets
or Chiller Plant Room Insulation to limit the chiller sound pressure level to item 1 96,063 96,063
less than 64 dBA

C Refrigerant Recovery and Storage Unit - Suitable to hold refrigerant charge of


no. 1 93,181 93,181
One Chiller as per Project Specifications.

To Collection 9,142,304
B13/30
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's
BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS
(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)
EQUIPMENT (Cont'd)

Refrigerant leak detection system with audible alarm and Self Contained
Breathing apparatus, 1 point per chiller. Refrigerant leak detection system
shall be interlinked with chilled water plant room ventilation system to operate
in case of alarm, also to be interfaced with BMS, as per Project Drawings and
Specifications.

A Refrigerant leak detection system item 1 63,402 63,402

Supply, installation, testing and commissioning of Chiller Plant manager (PLC


BASED) suitable for high voltage chillers, cooling towers, pumps, motorized
valves, sensors, thermostats etc. configuration with inter connecting- control
wiring requiring communication protocols, PLC, interfacing with BMS with
all accessories. The chiller plant manager should comply as I/O list and
schematic of HVAC system as per Drawings and Specifications.

B Chiller plant Manager item 1 96,063 96,063


Supply, installation, testing and commissioning of horizontal split case chilled
water pumps including inertia bases, starter panels with controls, wirings,
mountings, valves in suction & discharge lines, strainers, conduits, interlocks,
flexible connections, gauges, insulation, interfacing with BMS etc. complete
as per Drawings and Specifications.

C Primary Chilled Water Pumps: Ref: PCH.P-1 to P-6 (5 duty + 1 standby with
constant speed) Pump Flow rate - To suit each chiller Pump Head - To be
calculated by contractor to meet project requirement. no. 6 192,126 1,152,756

D Secondary Chilled Water Pumps: Ref: SCH.P-1 to P-6 (5 duty + 1 standby


with VFD) Pump Flow rate - To suit each chiller
Pump Head - To be calculated by contractor to meet project requirement. no. 6 283,386 1,700,316
Pump Specifications - Complete with VFD Starting mechanism.

To Collection 3,012,537
B13/31
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

A Condenser Water Pumps: Ref: CW.P-1 to P-6 (5 duty + 1 standby constant


speed) Pump Flow rate - To suit each chiller
Pump Head - To be calculated by contractor to meet project requirement. no. 6 210,378 1,262,268

B Cooling tower make up water Pumps: Ref: CT.M-1 to M-2 (1 duty + 1 standby
constant speed) Pump Flow rate - To suit each chiller
Pump Head - To be calculated by contractor to meet project requirement. no. 2 38,426 76,852

Cooling Tower

Supply, installation, testing and Commissioning of Cooling Towers based on


592.4 m3/h, Induced Draft, Counter Flow, Single Cell, Factory Fabricated,
Field Assembled, SS316-L Structure, FRP Basin, FRP Casing, CTI Certified,
complete with propeller fan, air inlet louvers, PP hot water distribution
network, PP Fill & Drift Eliminator, mechanical float ball makeup connection
and associated accessories including starter panel with controls ,wiring and
cabling complete as per Drawings and Specifications.

C Induced Draft Counter Flow Cooling Towers: CTI Certified


Cooling Tower water in/out: 40 deg c / 34.5 C
Cooling Tower Flow rate: to suit the chiller no. 10 470,708 4,707,080
Design Wet Bulb Temperature: 31 Deg C.
CT Fans should be with VFDs.

To Collection 6,046,200
B13/32
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

FULL STREAM SCREEN FILTRATION SYSTEM

A Supply, installation, testing and commissioning of Full Stream Screen


no. 5 192,126 960,630
Filtration System with Skid mounted with following parameters:
1. Total Flow rate : 5,925 m3/hr
2. Flow rate per filter : 987.7 m3/hr
3. Filtration degree : 40 micron
4. Operating pressure : 10bar

PLANT ROOM SPECIALIST


Note:

B The Client prefers the specialist agency for complete plant room
INSTALLATIONS that includes Chillers, Chilled water pumps, Condenser
water pumps, Pressurization unit, Chemical dosing system and all the
associated piping and valve packages and for cooling tower pipe connections BY REMCO
and valve packages only. Approved Specialist like ADC energy systems, item
SPECIALIST
Johnson control, Stellar energy, Senoroyo shall be engaged by the Contractor.

INSTALLATION, TESTING AND COMMISIONING STANDARDS

Note:

The equipment installation, testing and commissioning shall comply with all
relevant local regulations, ASHRAE codes, EN standards, British standard
codes of practice (regardless whether referred to in the Contract documents. NOTED
In the event of any contradiction between this standards / specifications, the
Engineer's decision is final.

To Collection 960,630
B13/33
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

Basin cleaning system

Supply, installation, Testing and Commissioning of completely factory


assembled Basin Cleaning System, flow rate 64 m3/h complete with
Separator, pump, complete piping, strainer, pressure gauges, starter panels
with control suitable for BMS provision for bag change out and remote
On/OFF, Solid Recovery Vessel, Nozzles for sweeping action complete as per
Drawings & Specifications.

A Ref: BCS 01 - 10 (Voltage 415/ 3ph / 50Hz) (Horse power more than 10 HP) no. 10 76,851 768,510

B Canopy for Basin Cleaning System no. 10 961 9,610

Chilled Water Pressurization Unit with dynamic expansion vessel

Supply, Installation, testing and commissioning of pressurization units /


expansion tank as per schedule including starter panel with controls,float
switch, power and control wirings, interfacing with BMS and necessary
accessories for chilled water system as per Drawings and Specifications.

C Chilled Water Pressurization Unit complete with built in pump suitable to


maintain up to 8 bar pressure for the complete volume of chilled water.
Combined pressurization system for pressurization, water make-up and
deaeration shall be provided. Local assembled pressurization pump sets shall
not be acceptable. Minimum acceptance factor for vessels shall be 90%. The
expansion vessels shall be equipped with bladder rupture device. Contact Set 1 66,572 66,572
water meters (with BMS connectivity) and back-flow preventer sets shall be
available in water make-up connection.

To Collection 844,692
B13/34
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)
EQUIPMENT (Cont'd)

Supply, Installation, testing and commissioning of Air seprator complete as per


Drawings and Specifications.

A Air seprator no. 1 161,386 161,386

Supply, installation, testing and commissioning of Automatic & Manual


chemical dosing plant corrosion control and micro logical control including
dosing pump set, control panel, sensors, controllers, interfacing with BMS, all
required accessories etc. complete as per Specifications and Drawings

B Chilled Water Manual & Automatic Chemical Dosing Unit. no. 1 30,000 30,000
Chemicals for 1 year of operation for Condenser Water System & Chilled
C no. 1 28,819 28,819
water system.
D Corrosion Rack for Chilled water circuit no 1 28,819 28,819
E Corrosion Rack for Condenser water circuit no 1 28,819 28,819
Chemical Cleaning and Passivation

Pre cleaning, temporary loops, water filling, air venting and pressurization,
chemical cleaning and circulation, flushing, testing and sampling, and
passivation and final testing

(AS PER BSRIA STANDARDS )


F Treatment of chilled water internal network item 1 96,063 96,063
G Treatment of condenser water internal network item 1 48,032 48,032
Note:

Complete Flushing by the Flushing Contractor approved by Consultant and


Noted, Comply and
Engineer. This Flushing Contractor should be one from the list of water Included
treatment specialists.

To Collection 421,938
B13/35
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

NOTE: AHU's and fittings for leasing areas are not in contract, it is for
information only

Air Handling Unit

Supply, installation, testing and commissioning of Chilled water air handling


units with vibration isolators, starter panel with controls, valve package,
necessary supports, flexible connector, connection to piping, ducting
connection, thermostat, temperature sensor, humidity sensors, smoke detectors
interfacing with BMS and FACP etc. ensure suitability for working all in
accordance with the Drawings and Specifications.

A Ref. AHU-1; total cooling capacity 158.16 kw no. 1 120,100 120,100


B Ref. AHU-2, AHU-3.; total cooling capacity 107.44 kw no. 2 79,800 159,600
C Ref. AHU-4; total cooling capacity 157.39 kw no. 1 116,300 116,300
D Ref. AHU-5; total cooling capacity 105.82 kw no. 1 78,800 78,800
E Ref. AHU-6; total cooling capacity 168.33 kw no. 1 118,200 118,200
F Ref. AHU-7; total cooling capacity 132.44 kw no. 1 98,000 98,000
G Ref. AHU-8; total cooling capacity 170.14 kw no. 1 118,200 118,200
H Ref. AHU-9; total cooling capacity 105.14 kw no. 1 78,800 78,800
J Ref. AHU-10; total cooling capacity 119.56 kw no. 1 89,400 89,400
K Ref. AHU-11; total cooling capacity 147.96 kw no. 1 106,700 106,700
L Ref. AHU-12, AHU-13, AHU-14, AHU-15; total cooling capacity 152.69 kw no. 4 110,500 442,000
M Ref. AHU-16; total cooling capacity 119.73 kw no. 1 107,600 107,600
N Ref. AHU-17; total cooling capacity 147.54 kw no. 1 94,200 94,200
P Ref. AHU-18; total cooling capacity 123.34 kw no. 1 76,900 76,900

To Collection 1,804,800
B13/36
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

Air Handling Unit (Cont'd)

Supply, installation, testing and commissioning of Chilled water air handling


units with vibration isolators, starter panel with controls, valve package,
necessary supports, flexible connector, connection to piping, ducting
connection, thermostat, temperature sensor, humidity sensors, smoke detectors
interfacing with BMS and FACP etc. ensure suitability for working all in
accordance with the Drawings and Specifications. (Cont'd)

A Ref. AHU-19; total cooling capacity 75.64 kw no. 1 74,000 74,000


B Ref. AHU-20; total cooling capacity 106.37 kw no. 1 80,700 80,700
C Ref. AHU-21; total cooling capacity 96.15 kw no. 1 75,900 75,900
D Ref. AHU-22; total cooling capacity 129.97 kw no. 1 97,100 97,100
E Ref. AHU-23, AHU-24, AHU-25, AHU-26; total cooling capacity 102.87 kw no. 4 76,900 307,600
F Ref. AHU-27; total cooling capacity 152.7 kw no. 1 109,600 109,600
G Ref. AHU-28, AHU-29; total cooling capacity 102.39 kw no. 2 76,900 153,800
H Ref. AHU-30, AHU-31; total cooling capacity 104.2 kw no. 2 77,900 155,800
J Ref. AHU-32; total cooling capacity 180.72 kw no. 1 129,700 129,700
K Ref. AHU-33; total cooling capacity 70.26 kw no. 1 55,800 55,800
L Ref. AHU-34; total cooling capacity 156.5 kw no. 1 116,300 116,300
M Ref. AHU-35; total cooling capacity 210.82 kw no. 1 145,100 145,100
N Ref. AHU-36; total cooling capacity 141.91 kw no. 1 104,800 104,800
P Ref. AHU-37; total cooling capacity 120.02 kw no. 1 89,400 89,400
Q Ref. AHU-38; total cooling capacity 82.04 kw no. 1 66,300 66,300
R AHU-39 (CINEMA); total cooling capacity 110.47 kw no. 12 By Tenant
S Ref. P2-01, P2-03; total cooling capacity 18.93 kw no. 6 14,500 87,000

To Collection 1,848,900
B13/37
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

Air Handling Unit (Cont'd)

Supply, installation, testing and commissioning of Chilled water air handling


units with vibration isolators, starter panel with controls, valve package,
necessary supports, flexible connector, connection to piping, ducting
connection, thermostat, temperature sensor, humidity sensors, smoke detectors
interfacing with BMS and FACP etc. ensure suitability for working all in
accordance with the Drawings and Specifications. (Cont'd)

Ref. E-015, B-001, B-015, B-018, C-002, C-003, C-004, C-005, C-006, C-007,
A no. 22 By Tenant
C-008, C-009 ; total cooling capacity 18.17 kw
B Ref. P1-17, ; total cooling capacity 18.17 kw no. 2 13,500 27,000
C Ref. A-207, A-209, A-215; total cooling capacity 35.45 kw no. 83 By Tenant
D Ref. AHU-40; total cooling capacity 198.9 kw no. 1 120,100 120,100
Weather Proof Canopy

E Supply and installation of weather proof canopy for exposed AHU's no. 39 961 37,479

F Supply and installation of weather proof canopy for exposed FAHU's no. 33 961 31,713

G Weatherproof canopy for FAHU (HYPERMARKET & DEPARTMENT


STORE) no. 2 961 1,922

To Collection 218,214
B13/38
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

Fresh Air Handling Unit

Supply, installation, testing and commissioning of all Fresh Air Handling


Units ( with heat recovery wheel and heat pipe MERV 13 Filter wherever
applicable) with vibration isolators with suitable foundation, timer controlled
starter panel, necessary supports, connection to piping with necessary valve
packages, ducting connection, thermostat, temperature sensor, humidity
sensors, smoke detectors, electrical/control cabling, interfacing with BMS and
FACP all complete in accordance with the Drawings and Specifications.

A Ref. FAHU-01; total cooling capacity 239.2 kw no. 1 251,700 251,700


B Ref. FAHU-02; total cooling capacity 328.9 kw no. 1 368,000 368,000
C Ref. FAHU-03; total cooling capacity 420.5 kw no. 1 377,500 377,500
D Ref. FAHU-04; total cooling capacity 487.0 kw no. 1 451,600 451,600
E Ref. FAHU-05; total cooling capacity 419.8 kw no. 1 387,400 387,400
F Ref. FAHU-06; total cooling capacity 290.5 kw no. 1 320,900 320,900
G Ref. FAHU-07; total cooling capacity 167.5 kw no. 1 171,200 171,200
H Ref. FAHU-08; total cooling capacity 210.8 kw no. 1 261,600 261,600
J Ref. FAHU-09; total cooling capacity 163.1 kw no. 1 241,800 241,800
K Ref. FAHU-10; total cooling capacity 107.9 kw no. 1 168,800 168,800
Ref. FAHU-11, FAHU-12, FAHU-13, FAHU-14; total cooling capacity 366.8
L no. 4 155,200 620,800
kw (WITHOUT HEAT RECOVERY)
M Ref. FAHU-15; total cooling capacity 60.5 kw no. 1 112,800 112,800
N Ref. FAHU-16; total cooling capacity 125.8 kw no. 1 198,500 198,500
Ref. FAHU-31, FAHU-32; total cooling capacity 271.4 kw (WITHOUT HEAT
P no. 2 120,700 241,400
RECOVERY)

To Collection 4,174,000
B13/39
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)
Fresh Air Handling Unit (Cont'd)

Supply, installation, testing and commissioning of all Fresh Air Handling


Units ( with heat recovery wheel and heat pipe MERV 13 Filter wherever
applicable) with vibration isolators with suitable foundation, timer controlled
starter panel, necessary supports, connection to piping with necessary valve
packages, ducting connection, thermostat, temperature sensor, humidity
sensors, smoke detectors, electrical/control cabling, interfacing with BMS and
FACP all complete in accordance with the Drawings and Specifications.
(Cont'd)

A Ref. FAHU-17A; total cooling capacity 25.7 kw no. 1 88,000 88,000


B Ref. FAHU-17B; total cooling capacity 37.5 kw no. 1 98,000 98,000
C Ref. FAHU-18; total cooling capacity 66.3 kw no. 1 118,700 118,700
D Ref. FAHU-19A; total cooling capacity 25.7 kw no. 1 88,000 88,000
E Ref. FAHU-19B; total cooling capacity 37.5 kw no. 1 98,000 98,000
F Ref. FAHU-21; total cooling capacity 264.2 kw no. 1 328,100 328,100
G Ref. FAHU-22; total cooling capacity 290.2 kw no. 1 333,400 333,400
H Ref. FAHU-23; total cooling capacity 231.5 kw no. 1 293,500 293,500
J Ref. FAHU-24; total cooling capacity 110.3 kw no. 1 152,900 152,900
Ref. FAHU-25A; total cooling capacity 265.2 kw (WITHOUT HEAT
K no. 1 120,700 120,700
RECOVERY)
L Ref. FAHU-26; total cooling capacity 131.1 kw no. 1 186,100 186,100
Ref. FAHU-27; total cooling capacity 542.4 kw (WITHOUT HEAT
M no. 1 219,800 219,800
RECOVERY)
Ref. FAHU-28, FAHU-29; total cooling capacity 272.1 kw (WITHOUT HEAT
N no. 2 190,200 380,400
RECOVERY)
Ref. FAHU-30; total cooling capacity 419.4 kw (WITHOUT HEAT
P no. 1 180,300 180,300
RECOVERY)

Q Ref. FAHU-25 (WITHOUT HEAT RECOVERY) FOR HYPERMARKET no. 1 302,350 302,350

R Ref. FAHU-20 (WITH HEAT RECOVERY) FOR DEPARTMENT STORE no. 1 323,447 323,447
To Collection 3,311,697
B13/40
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)
EQUIPMENT (Cont'd)

NOTE: FCU's and fittings for leasing areas are not in contract, it is for
information only

Fan Coil Unit

Supply, installation, testing and commissioning of Chilled water fan coil units
with vibration isolators, valve package, starter panel with controls, necessary
supports, connection to piping, ducting connection, thermostat, temperature
sensor, humidity sensors, interfacing with BMS etc. ensure suitability for
working; all in accordance with the Drawings and Specifications.

Ducted Fan Coil Unit for 2nd Basement

A Ref. P2-01A, P2-03A, P2-07A; air flow rate 292.64 L/s no. 3 3,900 11,700
B Ref. P2-04; air flow rate 377.6 L/s no. 2 4,500 9,000
C Ref. P2-05; air flow rate 788.24 L/s no. 1 5,800 5,800
D Ref. P2-07; air flow rate 821.28 L/s no. 4 7,400 29,600
E Ref. P2-08; air flow rate 387.04 L/s no. 1 4,000 4,000
Decorative Fan Coil Unit for 2nd Basement

F Ref. P2-02; air flow rate 446.04 L/s no. 2 5,200 10,400
G Ref. P2-06; air flow rate 505.04 L/s no. 2 5,900 11,800
H Ref. P2-09; air flow rate 370.52 L/s no. 4 5,900 23,600
J Ref. P2-10, P2-11; air flow rate 313.88 L/s no. 2 4,900 9,800
K Ref. P2-12; air flow rate 514.48 L/s no. 1 5,900 5,900
L Ref. P2-09A; air flow rate 254.88 L/s no. 1 4,900 4,900
M Ref. P2-13; air flow rate 778.80 L/s no. 1 5,800 5,800

To Collection 132,300
B13/41
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

Fan Coil Unit (Cont'd)

Supply, installation, testing and commissioning of Chilled water fan coil units
with vibration isolators, valve package, starter panel with controls, necessary
supports, connection to piping, ducting connection, thermostat, temperature
sensor, humidity sensors, interfacing with BMS etc. ensure suitability for
working; all in accordance with the Drawings and Specifications. (Cont'd)

Ducted Fan Coil Unit for 1st Basement


A Ref. E-001, E-002; air flow rate 792.96 L/s no. 8 By Tenant

Ref. E-003, E-004, E-005, E-006, E-008, E-009 E-010, E-011, E-012, E-013;
B no. 23 By Tenant
air flow rate 835.44 L/s

C Ref. E-007, E-014; air flow rate 788.24 L/s no. 3 By Tenant
D Ref. P1-03; air flow rate 708 L/s no. 1 5,100 5,100
E Ref. P1-03A, P1-19; air flow rate 505.04 L/s no. 2 4,800 9,600
F Ref. P1-04, P1-05; air flow rate 387.04 L/s no. 2 4,000 8,000
Ref. ,P1-06, P1-07,P1-08, P1-09, P1-10, P1-11, P1-12, P1-21; air flow rate
G no. 18 5,800 104,400
906.24 L/s
H Ref. P1-15, P1-16; air flow rate 627.26 L/s no. 2 5,100 10,200
J Ref. P1-18, P1-20; air flow rate 292.64 L/s no. 2 3,900 7,800
K Ref. P1-22, P1-23; air flow rate 391.76 L/s no. 2 4,000 8,000
Ref. P1-21A; air flow rate 660.8 L/s (Stand-By Split Ducted) including Indoor
L no. 1 23,300 23,300
unit, outdoor unit and refrigerant piping
Decorative Fan Coil Unit for 1st Basement
M Ref. P1-13, P1-14; air flow rate 700.92 L/s no. 2 6,700 13,400
N Ref. P1-24, P1-25; air flow rate 670.24 L/s no. 9 5,400 48,600

To Collection 238,400
B13/42
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

Fan Coil Unit (Cont'd)


Supply, installation, testing and commissioning of Chilled water fan coil units
with vibration isolators, valve package, starter panel with controls, necessary
supports, connection to piping, ducting connection, thermostat, temperature
sensor, humidity sensors, interfacing with BMS etc. ensure suitability for
working; all in accordance with the Drawings and Specifications. (Cont'd)

Ducted Fan Coil Unit for Ground Floor


Ref. A-001, A-005, A-011, B-013, B-025, B-030, B-032, B-035, C-010, C-020,
A no. 144 By Tenant
C-030, C-032, C-042, D-008, D-009;

Ref. A-002, A-003, A-006, A-007, A-008, A-009, A-010; B-002, B-003, B-004,
B-005, B-008, B-010, B-011, B-016, B-017, B-022, B-027, B-033, C-021, C-
B 022, C-023, C-024, C-025, C-026, C-027, C-028, C-029, C-034, C-035, C- no. 121 By Tenant
036, C-037, C-038, C-039, C-040, C-041, D-005, D-006; air flow rate 835.44
L/s
Ref. B-006, B-007, B-009, Anchor (S-V), Anchor (M-Q), B-014, B-021, B-
C no. 58 By Tenant
026, B-031; air flow rate 906.24 L/s

Ref. B-019, B-020, B-024, B-028, B-034, C-001, C-011, C-012, C-013, C-014,
D no. 40 By Tenant
C-015, C-016, C-017, C-018, C-019, C-031, D-003

Ref. B-023, B-029, C-033, C-043, D-001, D-002,D-010 ; air flow rate 915.68
E no. 38 By Tenant
L/s

F Ref. G-02, G-03, G-13; air flow rate 915.68 L/s no. 4 7,800 31,200
G Ref. C-044, C-045, C-046; air flow rate 627.76 L/s no. 3 By Tenant
H Ref. G-14; air flow rate 627.76 L/s no. 2 5,100 10,200
J Ref. D-004, D-007; air flow rate 708 L/s no. 5 By Tenant
K Ref. G-01; air flow rate 708 L/s no. 1 5,400 5,400
L Ref. G-04; air flow rate 391.76 L/s no. 1 4,000 4,000
M Ref. G-05, G-06; air flow rate 505.04 L/s no. 2 4,500 9,000
N Ref. G-07; air flow rate 368.16 L/s no. 1 4,000 4,000
P Ref. G-10,G-11,G-12; air flow rate 292.64 L/s no. 3 3,900 11,700

To Collection 75,500
B13/43
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)
Fan Coil Unit (Cont'd)
Supply, installation, testing and commissioning of Chilled water fan coil units
with vibration isolators, valve package, starter panel with controls, necessary
supports, connection to piping, ducting connection, thermostat, temperature
sensor, humidity sensors, interfacing with BMS etc. ensure suitability for
working; all in accordance with the Drawings and Specifications. (Cont'd)

Decorative Fan Coil Unit for Ground floor


A Ref. G-08; air flow rate 254.88 L/s no. 1 4,900 4,900
B Ref. G-09; air flow rate 387.04 L/s no. 1 4,900 4,900
Ducted Fan Coil Unit for First Floor

Ref. A-100, A-102, A-118, B-107, B-127, B-131, C-115, D-104; air flow rate
C no. 27 By Tenant
835.44 L/s

Ref. A-101, A-110, A-112, A-113, A-119, A-125, A-133, B-123, B-124 ; air
D no. 58 By Tenant
flow rate 906.24 L/s

Ref. A-102A, A-106, A-111, A-122, A-132, B-102, B-103, B-119, B-125, B-
E no. 24 By Tenant
130, B-132, D-108; air flow rate 788.24 L/s

Ref. A-103, A-104, A-107, A-109, A-121, A-123, A-124, A-127, A-128, A-130,
F B-101, B-104, B-108, B-112, B-114, B-135, C-103, C-104, C-105, C-106, C- no. 106 By Tenant
109, C-120, C-121, F-7

Ref. A-108, A-115, A-116, A-117, A-120, A-126, A-129, A-134, A-135, B-
105, B-106, B-109, B-110, B-113, B-115, B-117, B-118, B-122, B-128, B-129,
G no. 104 By Tenant
B-133, C-101, C-102, C-107, C-108, C-110, C-113, C-114, C-119, D-101, D-
102 ; air flow rate 915.68 L/s

H Ref. A-113A, A-127A; air flow rate 627.76 L/s no. 5 5,000 25,000
J Ref. A-116A; air flow rate 391.76 L/s no. 1 By Tenant
Ref. A-131, B-111, B-121, B-126, C-111, C-112, C-116, C-117, C-118, D-103,
K no. 39 By Tenant
D-106, D-107, D-109; air flow rate 745.76 L/s

To Collection 34,800
B13/44
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)
Fan Coil Unit (Cont'd)
Supply, installation, testing and commissioning of Chilled water fan coil units
with vibration isolators, valve package, starter panel with controls, necessary
supports, connection to piping, ducting connection, thermostat, temperature
sensor, humidity sensors, interfacing with BMS etc. ensure suitability for
working; all in accordance with the Drawings and Specifications. (Cont'd)

Ducted Fan Coil Unit for First Floor (Cont'd)


A Ref. B-116, B-120; air flow rate 708 L/s no. 2 By Tenant
B Ref. D-105; air flow rate 670.24 L/s no. 2 By Tenant
C Ref. F-1; air flow rate 505.04 L/s no. 1 4,900 4,900
D Ref. F-3, F-6; air flow rate 292.64 L/s no. 2 3,900 7,800
Decorative Fan Coil Unit for First floor

E Ref. F-2, F-4, F-5; air flow rate 254.88 L/s no. 3 4,900 14,700

F Ref. ST-7, ST-15; air flow rate 313.88 L/s no. 2 4,900 9,800

Ducted Fan Coil Unit for second Floor

G Ref. S-01; air flow rate 915.68 L/s no. 7 7,400 51,800

H Ref. S-02; air flow rate 835.44 L/s no. 3 5,800 17,400

J Ref. S-03, S-06, S-08; air flow rate 292.64 L/s no. 3 3,900 11,700

K Ref. S-04, S-05; air flow rate 391.76 L/s no. 2 4,000 8,000

L Ref. S-07; air flow rate 627.76 L/s no. 1 5,100 5,100

M Ref. S-09; air flow rate 792.96 L/s no. 1 6,200 6,200

To Collection 137,400
B13/45
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FANS
Supply, installation, testing and commissioning of basement extract fan with
vibration isolators, extract louvers, necessary supports, starter panel,
monitoring panel, control switch, wirings, hangers and fittings, flexible
connectors, connection to ducting (l .2mm thick), interfacing with BMS etc.,
complete as per Drawings & Specifications.

2nd Basement Exhaust Fan schedule

Ref. P2 EF-1, P2 EF-2, P2 EF-3, P2 EF-11, P2 EF-12, P2 EF-13; air flow rate
A no. 6 44,000 264,000
1st speed 23000 cfm, 2nd speed 38335 cfm

Ref. P2 EF-4, P2 EF-5, P2 EF-6; air flow rate 1st speed 25670 cfm, 2nd speed
B no. 3 48,200 144,600
42780 cfm

Ref. P2 EF-7,P2 EF-8,P2 EF-9,P2 EF-10; air flow rate 1st speed 25000 cfm,
C no. 4 48,200 192,800
2nd speed 41670 cfm

1st Basement Exhaust Fan schedule

Ref. P1 EF-2, P1 EF-3, P1 EF-4, P1 EF-5, P1 EF-6, P1 EF-7, P1 EF-8; air


F no. 7 53,700 375,900
flow rate 1st speed 28070 cfm, 2nd speed 46700 cfm

Ref. P1 EF-9, P1 EF-10, P1 EF-11 ; air flow rate 1st speed 28070 cfm, 2nd
G no. 3 51,400 154,200
speed 43835 cfm

Ref. P1 EF-13, P1 EF-17 ; air flow rate 1st speed 28070 cfm, 2nd speed 46700
H no. 2 53,700 107,400
cfm

To Collection 1,238,900
B13/46
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FANS (Cont'd)
Supply, installation, testing and commissioning of basement extract fan with
vibration isolators, extract louvers, necessary supports, starter panel,
monitoring panel, control switch, wirings, hangers and fittings, flexible
connectors, connection to ducting (l .2mm thick), interfacing with BMS etc.,
complete as per Drawings & Specifications. (Cont'd)

1st Basement Sub-Station Exhaust air Fan Schedule

A Ref. P1 EF-1; air flow rate 25750 cfm no. 1 34,600 34,600

B Ref. P1 EF-11 ; air flow rate 15450 cfm no. 1 38,800 38,800

B Ref. P1 EF-18; air flow rate 20600 cfm no. 1 57,800 57,800

Supply, installation, testing and commissioning of Generator Room Extract


(Wall Mounted) fan with vibration isolators, necessary supports, control
panels, wirings, hangers and fittings, interfacing with BMS etc.as per
Specifications and Drawings

C Ref. GR EF-1; air flow rate 1650 cfm no. 1 1,800 1,800

D Ref. GR EF-2; air flow rate 1200 cfm no. 1 3,500 3,500

E Ref. GR EF-3; air flow rate 1370 cfm no. 1 1,800 1,800

F Ref. GR EF-4; air flow rate 1440 cfm no. 1 1,800 1,800

Pump Room Exhaust Fans schedule (Wall Mounted)

G Ref. P2 EF-14; air flow rate 1st speed 915 cfm, 2nd speed 1525 cfm no. 1 1,200 1,200

H Ref. P2 EF-15; air flow rate 1st speed 1015 cfm, 2nd speed 1690 cfm no. 1 1,200 1,200

J Ref. P2 EF-16, P2 EF-19, P2 EF-20; air flow rate 100 cfm no. 3 800 2,400

K Ref. P2 EF-17, P2 EF-18; air flow rate 250 cfm no. 5 800 4,000

To Collection 148,900
B13/47
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FANS (Cont'd)

Supply, installation, testing and commissioning of Extract fan with vibration


isolators, extract louvers, necessary supports, starter panel, monitoring panel,
control switch hangers and fittings, connection to ducting), interfacing with
BMS etc. as per Specifications and Drawings

Grease Separator Room Exhaust Fans schedule (Wall Mounted)

A Ref. P1 EF-14; air flow rate 285 cfm no. 2 1,200 2,400

B Ref. P1 EF-15; air flow rate 240 cfm no. 2 800 1,600

C Ref. P1 EF-16; air flow rate 280 cfm no. 3 1,200 3,600

Chiller plant room Exhaust Fans schedule

D Ref. EF-7; air flow rate 26150 cfm no. 1 32,300 32,300

Exhaust Fans schedule (Toilet & Garbage)

E Ref. EF-2; air flow rate 1400 cfm no. 1 2,400 2,400

F Ref. EF-4; air flow rate 400 cfm no. 1 1,800 1,800

G Ref. EF-5; air flow rate 2150 cfm no. 1 3,800 3,800

H Ref. EF-6; air flow rate 1500 cfm no. 1 2,400 2,400

Kitchen Extract fan schedule (Ground Floor) - Inline Ducted

Ref. GF KEF-1, GF KEF-2, GF KEF-3, GF KEF-6, GF KEF-7, GF KEF-8, GF


J no. 9 12,777 114,993
KEF-9, GF KEF-10, GF KEF-11; air flow rate 12000 cfm

K Ref. GF KEF-4, GF KEF-5, GF KEF-12; air flow rate 19000 cfm no. 3 17,292 51,876

To Collection 217,169
B13/48
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

FANS (Cont'd)

Supply, installation, testing and commissioning of Extract fan with vibration


isolators, extract louvers, necessary supports, starter panel, monitoring panel,
control switch hangers and fittings, connection to ducting), interfacing with
BMS etc. as per Specifications and Drawings (Cont'd)

Kitchen Extract fan schedule (First Floor) - Inline Ducted (Cont'd)

Ref. FF KEF-1, FF KEF-4, FF KEF-17, FF KEF-18, FF KEF-19, FF KEF-20,


FF KEF-21, FF KEF-24, FF KEF-25, FF KEF-26, FF KEF-27, FF KEF-28, FF
A no. 20 12,777 255,540
KEF-29, FF KEF-30, FF KEF-31, FF-KEF 32, FF-KEF 33, FF KEF-34, FF
KEF-36, FF KEF-37; air flow rate 12000 cfm

Ref. FF KEF-2, FF KEF-3, FF KEF-5, FF KEF-6, FF KEF-7, FF KEF-8, FF


KEF-9, FF KEF-10, FF KEF-11, FF KEF-12, FF KEF-13, FF KEF-14, FF
B no. 17 17,292 293,964
KEF-15, FF KEF-16, FF KEF-22, FF KEF-23, FF KEF-35; air flow rate
19000 cfm

Supply, installation, testing and commissioning of Staircase Pressurization fan


with vibration isolators, extract louvers, necessary supports, starter panel,
monitoring panel, control switch hangers and fittings, connection to ducting),
interfacing with BMS etc. as per Specifications and Drawings.

Staircase Pressurization fan schedule (Interfacing with FACP)

C Ref. SPF-1 to SPF-11; air flow rate 20660 cfm no. 11 19,100 210,100

D Ref. SPF-12 to SPF-17; air flow rate 20400 cfm no. 6 19,100 114,600

Chemical storage room Exhaust Fans schedule

E Ref. P2 EF-21; air flow rate 350 cfm no. 1 4,800 4,800

Filter room Exhaust Fans schedule

F Ref. P1 EF-17; air flow rate 2000 cfm no. 1 3,700 3,700

To Collection 882,704
B13/49
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

FANS (Cont'd)

Supply, installation, testing and commissioning of Make up fan with vibration


isolators, extract louvers, necessary supports, starter panel with controls,
switch hangers and fittings, connection to ducting), interfacing with BMS etc.
as per Specifications and Drawings (Cont'd)

2nd Basement make-up air Fan schedule

A Ref. P2 MAF-1; air flow rate 1st speed 20330 cfm, 2nd speed 33885 cfm no. 1 37,300 37,300
B Ref. P2 MAF-2; air flow rate 1st speed 23000 cfm, 2nd speed 38335 cfm no. 1 37,300 37,300

1st Basement Sub-Station make-up air Fan Schedule


C Ref. P1 MAF-1 ; air flow rate 15450 cfm no. 1 51,300 51,300
D Ref. P1 MAF-2; air flow rate 25750 cfm no. 1 44,400 44,400
Make-up Fans schedule (Anchor Shop) (1 Duty ) as per final agreement
E Ref. MAF-1; air flow rate 24520 cfm no. 1 10,475 10,475
F Ref. MAF-2, MAF-3; air flow rate 17550 cfm no. 2 8,333 16,666
G Ref. MAF-4, MAF-5; air flow rate 25380 cfm no. 2 10,475 20,950
H Ref. MAF-6; air flow rate 10350 cfm no. 1 5,416 5,416
Make-up Fans schedule (Cinema / FEC) (1 Duty ) as per final agreement
Ref. MAF-14, MAF-15, MAF-16, MAF-17, MAF-18, MAF-19, MAF-29,
J MAF-30, MAF-31, MAF-32, MAF-33, MAF-34; air flow rate 27592 cfm for no. 12 13,867 166,404
FEC

Ref. MAF-20, MAF-21, MAF-22, MAF-23, MAF-25, MAF-26, MAF-27,


K no. 8 10,475 83,800
MAF-28; air flow rate 26110 cfm for CINEMA

Make-up fan (HYPERMARKET) schedule (1 Duty ) as per final agreement

Ref. MAF-7, MAF-8, MAF-9, MAF-10 MAF-11; air flow rate 29047 cfm no. 5 13,867 69,335

Ref. MAF-12, MAF-13; air flow rate 22025 cfm no. 2 9,880 19,760

Ref. MAF-24A ; air flow rate 1500 cfm , MAF-24B ; air flow rate 4050 cfm no. 1 6,071 6,071

To Collection 569,177
B13/50
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

FANS (Cont'd)

Supply, installation, testing and commissioning of Make up fan with vibration


isolators, extract louvers, necessary supports, starter panel with controls,
wirings, hangers and fittings, connection to ducting), interfacing with BMS
etc. as per Specifications and Drawings (Cont'd)

Kitchen Make-up fan schedule (Ground Floor) - Inline Ducted

Ref. GF MAF-1, GF MAF-2, GF MAF-3, GF MAF-6, GF MAF-7, GF MAF-


A no. 9 8,934 80,406
8, GF MAF-9, GF MAF-10, GF MAF-11; air flow rate 9500 cfm

B Ref. GF MAF-4, GF MAF-5, GF MAF-12; air flow rate 15000 cfm no. 3 14,986 44,958

Kitchen Make-up fan schedule (First Floor) - Inline Ducted

Ref. FF MAF-1, FF MAF-4, FF MAF-17, FF MAF-18, FF MAF-19, FF MAF-


20, FF MAF-21, FF MAF-24, FF MAF-25, FF MAF 26, FF MAF-27, FF
C no. 20 8,934 178,680
MAF-28, FF MAF-29, FF MAF-30, FF MAF-31, FF MAF-32, FF MAF-33,
FF MAF-34, FF MAF-36, FF MAF-37; air flow rate 9500 cfm

Ref. FF MAF-2, FF MAF-3, FF MAF-5, FF MAF-6, FF MAF-7, FF MAF-8,


FF MAF-9, FF MAF-10, FF MAF-11, FF MAF-12, FF MAF-13, FF MAF-14,
D no. 17 14,986 254,762
FF MAF-15, FF MAF-16, FF MAF-22, FF MAF-23, FF MAF-35; air flow
rate 15000 cfm

To Collection 558,806
B13/51
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

FANS (Cont'd)

Supply, installation, testing and commissioning of Smoke extract fan with


vibration isolators, extract louvers, necessary supports, starter panel with
controls, wirings, hangers and fittings, connection to ducting), interfacing with
BMS etc. as per Specifications and Drawings (Cont'd)

Smoke Fans schedule (Mall common area) (1 Duty ) as per final agreement

A Ref. SE-1 to SE-54 and SE-85 to SE-90 ; air flow rate 15000 cfm no. 60 9,166 549,960

Smoke Fans schedule (Anchor Shop) (1 Duty ) as per final agreement

B Ref. SE-55, SE-65, SE-83, SE-84; air flow rate 11500 cfm no. 4 6,190 24,760

C Ref. SE-56, SE-57; air flow rate 19500 cfm no. 2 8,511 17,022

D Ref. SE-58; air flow rate 27250 cfm no. 1 12,856 12,856

E Ref. SE-59, SE-60, SE-61, SE-62; air flow rate 28400 cfm no. 4 12,856 51,424

F Ref. SE-63, SE-64; air flow rate 28200 cfm no. 2 12,856 25,712

G Ref. SE-66 to SE-72; air flow rate 30045 cfm no. 7 12,856 89,992

Smoke Fans schedule (Cinema / FEC) (1 Duty ) as per final agreement

Ref. SE-73, SE-74, SE-75, SE-76, SE-77, SE-78, SE-95, SE-96, SE-97, SE-
H no. 12 12,856 154,272
98, SE-99, SE-100; air flow rate 30658 cfm for FEC

Ref. SE-79, SE-80, SE-81, SE-82, SE-91, SE-92, SE-93, SE-94; air flow rate
J no. 8 12,856 102,848
29010 cfm for CINEMA

To Collection 1,028,846
B13/52
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)
SYSTEM (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators.


2. Mechanical contractor shall include the entire balance works for connecting
Included in
A to their mechanical equipment. item
Electrical
3. By this way, mechanical contractor to supply, installation etc. required
cables, wires, containments like cable tray, supports including termination.

WORK INCIDENTAL TO AIR CONDITIONING installation

BY MAIN
CONTRACTOR
B Allow for making holes ,mortices, chases and the like item
Refer to Scope of
Matrix item 1

C Allow for supports , including fixings , anchors and anti-vibration devices . item INCLUDED

D Allow for providing sleeves item Included

BY MAIN
CONTRACTOR
E Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2
Protection
F Allow for protection of work in this section item Included
Clause for kW/TR for Chiller Section
Note:

The Supplier is responsible to deliver the overall efficiency of the Chillers as


0.67 KW/TR at zero tolerance.
In the event of the Chillers pair failing to provide the defined capacity and/or
efficiency, the supplier shall take all the necessary actions to meet the criteria
Noted and Comply
and all the cost of rectifying the defects as well as any claim raised by the
client to the Contractor due to such failure, shall be borne by the Contractor
and the supplier.

To Collection 0
B13/53
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)
Sundries
Allow for all identification labels including plates, charts and identification of
A item Included
plant, equipment, cable, switches and colour coding.

Allow for tools and spares, which shall include loose keys and consumable
B item Included
spares.

Allow for Third party witnessing, testing and commissioning, which shall
wild air is optional
C include operating complete INSTALLATIONS, supply of wild air as per item
price
specification .

Note:

Third party for entire HVAC Testing and Commissioning engaged by the
Contractor must be approved by the Client and Consultant. Noted, Comply
Third party should be a CSA affiliated and member of Emirates green and Included
building council.

Allow for documents, which shall include shop Drawings, as built Drawings,
D item Included
operating instructions and maintenance manual as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


E item Included
parts of each piece of equipment.

F Allow for protective painting item Included

G Seismic supports calculation and verification of supports from specialist for all
item 1 390,000 390,000
Chilled water pipes.

H DCL (Dubai central laboratory) approved material usage for insulation and Noted, Comply
item
ducting as per DM requirements. and Included

Radiographic test report for Chilled water pipe welding for random selection
G item 1 80,000 80,000
1% to 10% of the fitting

H Indoor Air Quality Tested and Certified by Third party (for 1 sample) item 1 3,000 3,000

To Collection 473,000
B13/54
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Sundries

BY MAIN
CONTRACTOR
A Allow for structural steel support for all MEP services running in roof item
Refer to Scope of
Matrix item 26

BY MAIN
Allow for walk way bridges / cross over bridges to cross over roof MEP CONTRACTOR
B item
services Refer to Scope of
Matrix item 26

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as CONTRACTOR
C item
per acceptable material system approved by the Engineer. Refer to Scope of
Matrix item 28

Steel Base as per Structural Design and Cooling Tower manufacturer


D item 1 77,000 77,000
requirements

Maintenance catwalk at cooling tower basin level of the new cooling towers to
E item 1 58,000 58,000
be provided by cooling tower (CT) Manufacturer.

Maintenance catwalk at cooling tower fan level. Maintenance catwalk should


F item 1 39,000 39,000
be provided between the cooling towers.

Warranty services and maintenance to be 24 months for Chiller and Cooling


Towers, Chillers, Cooling towers, all pumps in chilled water system, Side item INCLUDED
stream filtration system, Basin cleaning system from take over Certificate.

Allow for Training the employer's staff to operate and maintain the MEP
H item INCLUDED
INSTALLATIONS

Factory visit for major equipment including but not limited to chiller, cooling
J item INCLUDED
towers .

Any external MEP services and works in respect of connection to main


Included if shown
K incoming services (tie-ins) outside the plot limits including all associated civil item
in tender drawings
works.

Allow for Performance guarantee ,warranty and comprehensive service during Included as
L item
defects liability period Specifications
Included as
M Allow for provision of Sample item
Specifications

To Collection 174,000
B13/55
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Sundries

By Main
A Mono rail for Chillers, pumps as per project Specification item
Contractor

B The contractor must employ an independent third-party Commissioning


Specialist, CSA certified member and a member of Emirates green building
council, Mechanical and Electrical Commissioning Engineer for the duration NOTED AND
item
of the Tests on completion (commissioning) who will affectively be COMPLY
responsible for planning and executing the entire commissioning process on
behalf of the contractor.

The Contractor Commissioning specialist will be involved in reviewing the


operation of the building with operations and maintenance (O&M) staff and
occupants within 10 months after substantial completion. A plan for resolving NOTED AND
item
outstanding commissioning and energy related defects will be issued. The COMPLY
Contractor shall allow in costs for all necessary attendances and remedial
recommissioning works as required to resolve the finding of the review.

D
The contractor shall perform “enhanced commissioning” after project
NOTED AND
completion to meet specifications, any modification or maintenance to item
COMPLY
commissioning is performed shall be included in this item.

E Air Flush the Building after Completion. item 1 268,976 268,976

Included as Per
Any Green Building requirement as per latest issued "Green Building Plan"
F item Consultant
and Consultant specifications.
drawings

To Collection 268,976
B13/56
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

1 Silencers for exhaust fans and make up fans in basements 1 and 2 no. 28 5,889 164,892

2 Ref. P2 MAF-1A; air flow rate 1st speed 14670 cfm, 2nd speed 24450 cfm no. 1 27,184 27,184

3 Ref. P1 MAF-3 ; air flow rate 30900 cfm no. 1 91,500 91,500

4 Automatic Dosing for condeser water treatment system no. 1 100,000 100,000

5 MOTOR DAVIT SYSTEM FOR COOLING TOWERS: no. 1 150,000 150,000

6 Airflow monitoring station FOR FAHU no. 23 5,000 115,000

To Collection 648,576
B13/57
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM

Include Supply, installation and testing & commissioning of all equipment,


pipes, fixture, fittings of the drainage system in accordance with the
Drawings, Specifications, approval of Engineer and all concerned code of
practice and local authority regulations.

Supply, installation and testing & commissioning of (soil & waste)


underground installation, connection, termination of drainage piping (UPVC)
along with all necessary fittings, supports, adhesive etc. coordination with
authority for connection as deemed necessary in line with regulations,
Drawings and Specifications .

A UPVC pipe 200 mm dia (UG) m 198 126 24,948

Supply, installation, testing and commissioning of Soil & Waste Pipe work
(UPVC) (Above Ground), pipes and fittings, including all supports,
accessories, rodding eyes, coordination with authority for connection as
deemed necessary in line with regulations, Drawings and Specifications .

Soil / waste pipes installation

B WP 32 mm dia m 90 49 4,410

C WP 75 mm dia m 219 78 17,082

D WP pipe 100 mm dia m 167 92 15,364

E WP pipe 150 mm dia m 1476 106 156,456

F WP pipe 200 mm dia m 113 126 14,238

G SP 40 mm dia m 15 58 870

H SP 100 mm dia m 133 92 12,236

J SP 150 mm dia m 1228 106 130,168

K SP 200 mm dia m 597 126 75,222

L SP pipe 200 mm dia m 42 126 5,292

M UPVC pipe 82 mm dia m 226 68 15,368

To Collection 471,654
B13/58
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

Supply, installation, testing and commissioning of Soil & waste Pipe


work(UPVC), pipes and fittings including all supports, accessories, rodding
eyes, etc., coordination with authority for connection as deemed necessary in
line with regulations, Drawings and Specifications .

A UPVC pipe 110 mm dia m 797 92 73,324

B UPVC pipe 150 mm dia m 5416 106 574,096

C UPVC pipe 200 mm dia m 208 131 27,248

D Allow for final Connections to sanitary ware item 26,500

E Allow for Water heater drain pipe complete as required. item 6,200

Supply, installation, testing and commissioning of Vent Pipe work(UPVC),


pipes and fittings including all supports, accessories, rodding eyes, etc.,
coordination with authority for connection as deemed necessary in line with
regulations, Drawings and Specifications .

Vent Pipes

F 75 mm dia. m 221 78 17,238

G 110 mm dia. m 5121 92 471,132

H Vent cowl 110 mm dia no. 10 49 490

Supply, installation, testing and commissioning of Rain water Pipe


work(UPVC), pipes and fittings including all supports, accessories, rodding
eyes, etc., coordination with authority for connection as deemed necessary in
line with regulations, Drawings and Specifications .

J 100 mm dia m 829 92 76,268

K 150 mm dia. m 1612 106 170,872

Supply, installation, testing and commissioning of Cooling tower drain piping,


pipes and fittings (UPVC) including all supports, accessories, rodding eyes,
etc., coordination with authority for connection as deemed necessary in line
with regulations, Drawings and Specifications .

L Cooling tower drain pipe 150 mm dia m 147 106 15,582

To Collection 1,458,950
B13/59
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

Supply, installation, testing and commissioning of Pressure pipe work, pipes


and fittings including all supports, accessories, rodding eyes, etc., coordination
with authority for connection as deemed necessary in line with regulations,
Drawings and Specifications.

A Pressure pipe 50 mm dia m 22 68 1,496

B Pressure pipe 100 mm dia m 400 116 46,400

C Pressure pipe 200 mm dia m 214 155 33,170

Supply, installation, testing and commissioning of Condensate Drain Pipe


work (UPVC class E) for FCU's and galvanized steel for AHU/FAHU'S, pipes
and fittings with insulation including all supports, accessories, coordination
with authority for connection as deemed necessary in line with regulations ,
Drawings and Specifications.

D CDP 25 mm dia (UPVC class E) m 604 49 29,596

E CDP 32 mm dia (UPVC class E) m 45 58 2,610

F CDP 40 mm dia (Galvanized steel) m 645 73 47,085

G CDP 80 mm dia (Galvanized steel) m 3108 87 270,396

H CDP 100 mm dia (Galvanized steel) m 3782 126 476,532

Supply, installation, testing and commissioning of HDPE pipe for Kitchen,


pipes and fittings including all supports, accessories, rodding eyes, etc.,
coordination with authority for connection as deemed necessary in line with
regulations, Drawings and Specifications.

J GTP 75 mm dia m 25 145 3,625

K GTP 100 mm dia m 64 193 12,352

L GTP 150 mm dia m 1395 241 336,195

M Grating pipe 110 mm dia m 22 116 2,552

N Grating pipe 150 mm dia m 528 145 76,560

To Collection 1,338,569
B13/60
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

ACCESSORIES

Supply, installation, testing and commissioning of associated drainage works


including installation of accessories, fittings, covers, etc., in connection with
the following all as detailed in Drawings & Specifications complete to meet
performance criteria (but not limited to) (Note: All related Civil works shall be
allowed in the civil work bills) as clarified in Specifications, Drawings
coordination with authority for connection as deemed necessarily in line with
regulations, Drawings and Specifications.

A Floor traps no. 660 39 25,740

B Floor clean out with cover no. 76 241 18,316

C SS floor drain with cover no. 660 338 223,080

D Cast Iron channel grating m 1165 290 337,850

E Soak away no. 126 579 72,954

F Sediment Bucket no. 18 964 17,352

G Rodding Eye item 15,827

Grease Trap complete as shown in the drawing

H Automatic Grease Separator, capacity 10 l/s (with 1 lifting station) no. 2 48,175 96,350

J Automatic Grease Separator, capacity 10 l/s no. 3 38,540 115,620

K Automatic Grease Separator, capacity 20 l/s (with 1 lifting station) no. 2 57,810 115,620

Oil interceptor including manhole, cover and frame complete as per Drawings
and Specifications.

L Oil interceptor no. 4 28,424 113,696

Sand trap including cover and frame complete as per Drawings and
Specifications.

M Sand trap with bucket (Cover size: 600x600 mm) no. 6 964 5,784

N Gully Trap (cast iron manhole cover size: 300x300 mm) no. 8 771 6,168

Catch basin with cover and PVC bucket (HDDI grating size: 450x450x50
P no. 387 482 186,534
mm )

To Collection 1,350,891
B13/61
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
2. DRAINAGE SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Rain water inlet / outlet including connection to pipework, all complete in


accordance with the Drawings and Specifications

A Cast iron Rain water outlet (Dome type) no. 100 386 38,600

B Cast iron Rain water outlet (Parapet type) no. 46 386 17,756

Allow for flexible joints at places where the Drainage pipework crosses the
C item 50,000
building expansion joint.

Receive, store, protect and installation , testing and commissioning of Sanitary


wares and accessories including necessary fixings, connectors, pipe
extensions, conical nuts, flexible tubes, final connections, etc., complete as per
Drawings and Specifications.

D Wash basin no. 75 97 7,275

E Wash basin mixer no. 75 44 3,300

F Soap dispenser no. 75 25 1,875

G Water closet including concealed cistern no. 82 97 7,954

H Toilet roll holder no. 85 25 2,125

J Robe hook no. 82 5 410

K Bidet no. 4 97 388

L Bidet mixer no. 4 44 176

M Urinal no. 13 97 1,261

N Wash basin for disabled toilet no. 3 97 291

P Wash basin mixer for disabled toilet no. 3 97 291

Q Water closet for disabled no. 3 97 291

R Grab bar no. 6 25 150

S Hinged grab rail no. 3 25 75

T Shattaf hand spray no. 85 15 1,275

BY MAIN
U Hand dryer no. 10
CONTRACTOR

V Paper Dispenser no. 10 44 440

BY MAIN
W Mirrors item
CONTRACTOR

BY MAIN
X Urinal partition item
CONTRACTOR
To Collection 133,933
B13/62
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Manhole Covers as shown in the Drawings

Heavy duty ductile. Iron manhole covers with frame and GRP lining ( FIC-01)
A no. 15 675 10,125
(60 cm x 60 cm)

Heavy duty ductile. Iron manhole covers with frame and GRP lining ( FIC-02)
B no. 2 675 1,350
(60 cm x 60 cm)

ACOUSTIC LAGGING

Allow for Acoustic lagging for Drainage pipework for all horizontal soil,
C waste and rain water pipes in false ceiling areas (including tenant area) item 270,000
complete as per Drawings and Specifications.

Equipment

Supply, installation , testing and commissioning of working and Standby sump


pumps including all pipe work, interconnections, level indicators, low/high
level/float switches with alarm , control panels, wirings, mountings, valves,
strainers, conduits, interlocks, flexible connections, all complete in
accordance with the Drawings and Specifications .

D Lifting station Sump Pump; Ref 01 to 06 (1 working + 1 standby) @ 7 L/S no. 6 24,088 144,528

E Lift Pit Sump Pump; (1 working) @ 3.5 m3/Hr no. 8 15,000 120,000

To Collection 546,003
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
B13/63
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

WORK INCIDENTAL TO DRAINAGE INSTALLATION

BY MAIN
CONTRACTOR
A Allow for making holes, mortices, chases and the like item
Refer to Scope of
Matrix item 1

B Allow for supports, including fixings, anchors and anti-vibration devices item INCLUDED

C Allow for providing sleeves item INCLUDED

BY MAIN
CONTRACTOR
D Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators 2.


Mechanical contractor shall include the entire balance works for connecting to NOTED,
E their mechanical equipment. 3. By this way, mechanical item COMPLIED AND
contractor to supply, installation etc. required cables, wires, containments like INCLUDED
cable tray, supports including termination.

To Collection -
B13/64
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

GREY WATER TREATMENT PLANT

Design, Engineering, Supply, installation, testing and commissioning of grey


water system including but not limited to basket strainer, valve support, air
blower for holding tank, air diffuser for holding tank, UF feed pump, pre-
chlorine dosing pump, pre-chlorine dosing tank, self cleaning filter, UF unit,
UF skid, automatic pneumatic valves for UF skid, manual & sampling valve,
A air blower for UF back wash air scoring, backwash pump with VFD, Biocide item 400,000
dosing pump, biocide dosing tank, CEB oxidizer dosing pump & tank, CEB
acid dosing pump & tank, CEB alkali dosing pump & tank, UF instruments,
Cleaning (CIP) system all fittings, supports, accessories etc., coordination
with authority for connection as deemed necessary in line with regulations,
Drawings and Specifications.

BLOWDOWN WATER NEUTRALIZATION SYSTEM

Design, Engineering, Supply, installation, testing and commissioning of blow


down water neutralization system including but not limited to inlet/outlet
motorized valves, level transmitter for collection tank, reaction cum settling
tank, mixer for reaction tank, acid dosing pump & tank, Caustic dosing pump
B & tank, pH controller with sensor, sludge transfer pump, bag filter, sludge item 100,000
motorized valve, control panel, all interconnecting piping, fittings & valves,
all cables & cable trays within plant area, coordination with authority for
connection as deemed necessary in line with regulations, Drawings and
Specifications

To Collection 500,000
B13/65
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

TSE POLISHING PLANT SYSTEM

Design, Engineering, Supply, installation, testing and commissioning of TSE


polishing plant system including but not limited to basket strainer, valve
support, air blower for holding tank, air diffuser for holding tank, UF feed
pump, pre-chlorine dosing pump, pre-chlorine dosing tank, self cleaning filter,
UF unit, UF skid, automatic pneumatic valves for UF skid, manual &
sampling valve, air blower for UF back wash air scoring, backwash pump with
A item 1,150,000
VFD, Biocide dosing pump, biocide dosing tank, CEB oxidizer dosing pump
& tank, CEB acid dosing pump & tank, CEB alkali dosing pump & tank, UF
instruments, Reverse osmosis system, instruments for RO system, cleaning
(CIP) system with all interconnecting pipes, fittings, supports, accessories,
control panels ,wiring, coordination with authority for connection as deemed
necessary in line with local regulations , Drawings and Specifications.

CONDENSATE WATER FILTERATION SYSTEM

Supply, installation, testing and commissioning of Condensate treatment


system with all pipes,fittings,supports,accessories,control panels ,wiring,
B item 50,000
coordination with authority for connection as deemed necessary in line with
regulations, drawings and specifications

ONLY
Liaising, Co-ordination charges for authority approval to get the drainage
C item APPLICATION
connection
FEES INCLUDED

SCADA SYSTEM

Supply, installation, testing and commissioning of SCADA system and


D item 200,000
integration with the central BMS system

To Collection 1,400,000
B13/66
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1.Electrical contractor scope of work is limited up to the isolators


2.Mechanical contractor shall include the entire balance works for connecting NOTED,
A to their mechanical equipment. 3. By this way, mechanical contractor to item COMPLIED AND
supply, installation etc. required cables, wires, containments like cable tray, INCLUDED
supports including termination.

Sundries

Allow for all identification labels including plates, charts and identification of
B item INCLUDED
plant, equipment, cable, switches and colour coding.

Allow for tools and spares, which shall include loose keys and consumable
C item INCLUDED
spares

Allow for testing and commissioning, which shall include operating complete
D item INCLUDED
INSTALLATIONS

Allow for documents, which shall include shop Drawings, as built Drawings,
E item INCLUDED
operating instructions and maintenance manual as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


F item INCLUDED
parts of each piece of equipment

G Allow for protective painting item INCLUDED

Any external MEP services and works in respect of connection to main ONLY CONNECTION
H incoming services (tie-ins) outside the plot limits including all associated civil item INCLUDED WITHIN PLOT
works. LIMITS

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as CONTRACTOR
J item
per acceptable material system approved by the Engineer. Refer to Scope of
Matrix item 28

K Allow for provision of Samples item INCLUDED

To Collection -
B13/67
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B13/68
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

3. WATER SUPPLY SYSTEM

DOMESTIC WATER SERVICES

Supply, installation and testing & commissioning of the domestic water


services in accordance with the Drawings, Specifications, approval of
Engineer and all concerned code of practice and local authority regulations

UPVC pressure main pipe work with solvent welded fittings for main water
meter to water tank, all necessary fittings and accessories, all complete in
accordance with Drawings and Specifications.

NORMAL WATER SYSTEM

A CWS 100 mm dia (UPVC) m 188 270 50,760

P.P.R. Pipe

Supply, installation, testing and commissioning of Normal Water piping (PPR,


PN 20), fittings, pipe expansion compensator, supports, hangers,
identification, pipe drops and making good etc. as per Drawings and
Specifications

B NWS 15 mm dia (PPR) m 2089 29 60,581

C NWS 20 mm dia (PPR) m 2486 39 96,954

D NWS 25 mm dia (PPR) m 3489 49 170,961

E NWS 32 mm dia (PPR) m 385 58 22,330

F NWS 40 mm dia (PPR) m 10 73 730

G NWS 50 mm dia (PPR) m 320 97 31,040

H NWS 65 mm dia (PPR) m 227 174 39,498

J NWS 75 mm dia (PPR) m 987 184 181,608

K NWS 80 mm dia (PPR) m 10 184 1,840

L NWS 100 mm dia (PPR) m 985 212 208,820

M Ring pipe as shown on the Drawings m 1576 58 91,408

Connection to Sanitary wares/sinks including support accessories, fixtures, etc


N item 35,000
for functioning .

To Collection 991,530
B13/69
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

Pex Pipe

PEX pipe with PVC box, elbow, adapter, all necessary fittings, hangers,
sleeves, joints, fixings and accessories, all complete in accordance with
Drawings and Specifications.

A 15 mm dia with 20 mm flexible conduit. m 1732 16 27,712

HOT WATER SYSTEM

P.P.R. Pipe

Supply, installation, testing and commissioning of Hot Water piping (PPR, PN


20), fittings, pipe expansion compensator, supports, hangers, identification,
pipe drops and making good etc. as per Drawings and Specifications.

B HWS&R 20 mm dia (PPR) m 372 39 14,508

C HWS&R 25 mm dia (PPR) m 132 49 6,468

D HWS&R 32 mm dia (PPR) m 172 N/A

E HWS&R 40 mm dia (PPR) m 1071 N/A

F HWS&R 50 mm dia (PPR) m 53 N/A

G HWS&R 75 mm dia (PPR) m 33 N/A

To Collection 48,688
B13/70
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

INSULATION

Supply, installation, of hot water piping insulation, including adhesive, canvas


cloth with vapour barrier, mechanical protection, support, accessories as
clarified in specification and drawings for the satisfaction of the engineer for
the following (but not limited to).

A NWS 15 mm dia (PPR) m 485 5 2,425

B NWS 20 mm dia (PPR) m 388 8 3,104

C NWS 25 mm dia (PPR) m 649 10 6,490

D NWS 32 mm dia (PPR) m 50 12 600

E NWS 40 mm dia (PPR) m 143 15 2,145

F NWS 50 mm dia (PPR) m 181 16 2,896

G NWS 65 mm dia (PPR) m 947 18 17,046

H NWS 75 mm dia (PPR) m 297 20 5,940

J NWS 80 mm dia (PPR) m 8 20 160

K NWS 100 mm dia (PPR) m 570 25 14,250

L HWS&R 20 mm dia (PPR) m 381 8 3,048

M HWS&R 25 mm dia (PPR) m 204 10 2,040

N HWS&R 32 mm dia (PPR) m 153 N/A

P HWS&R 40 mm dia (PPR) m 1073 N/A

Q HWS&R 50 mm dia (PPR) m 52 N/A

To Collection 60,144
B13/71
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

ALUMINIUM CLADDING

Supply, installation, of 0.70 mm thick aluminum cladding on pipework


running in roof / in exposed area/ exposed to view complete as per Drawings
and Specifications.

A NWS 15 mm dia (PPR) m 485 10 4,850

B NWS 20 mm dia (PPR) m 388 12 4,656

C NWS 25 mm dia (PPR) m 649 15 9,735

D NWS 32 mm dia (PPR) m 50 18 900

E NWS 40 mm dia (PPR) m 143 20 2,860

F NWS 50 mm dia (PPR) m 181 22 3,982

G NWS 65 mm dia (PPR) m 947 25 23,675

H NWS 75 mm dia (PPR) m 297 27 8,019

J NWS 80 mm dia (PPR) m 8 29 232

K NWS 100 mm dia (PPR) m 570 31 17,670

L HWS&R 40 mm dia (PPR) m 1014 N/A

M HWS&R 50 mm dia (PPR) m 52 N/A

To Collection 76,579
B13/72
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
3. WATER SUPPLY SYSTEM (Cont'd)

ACCESSORIES

Supply, installation, testing and commissioning of various piping accessories


including support, fixing, identification, access panels for satisfactory
functioning of all systems in accordance with authority requirement, Drawings
and Specifications.

ONLY
A Water Meter with fitting (interfaced with BMS) no. 98 INSTALLATION
INCLUDED

Isolation valve / Gate valves

B GV 20 mm dia no. 23 145 3,335

C GV 25 mm dia no. 55 179 9,845

D GV 32 mm dia no. 3 212 636

E GV 40 mm dia no. 41 270 11,070

F GV 50 mm dia no. 34 290 9,860

G IV 100 mm dia no. 1 434 434

H IV 15 mm dia no. 212 116 24,592

J IV 20 mm dia no. 80 145 11,600

K IV 25 mm dia no. 124 179 22,196

L IV 32 mm dia no. 22 212 4,664

M IV 40 mm dia no. 5 270 1,350

N IV 50 mm dia no. 12 290 3,480

P IV 65 mm dia no. 4 338 1,352

Q IV 75 mm dia no. 10 386 3,860

R IV 80 mm dia no. 3 482 1,446

S Lock shield valve 20 mm dia no. 26 82 2,132

T Lock shield valve 25 mm dia no. 55 121 6,655

U Lock shield valve 32 mm dia no. 1 145 145

V Lock shield valve 65 mm dia no. 1 193 193

To Collection 118,845
B13/73
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of various piping accessories


including support, fixing, identification, access panels for satisfactory
functioning of all systems in accordance with authority requirement, Drawings
and Specifications. (Cont'd)

Pressure reducing valve

A PRV station on 32 mm dia line no. 5 771 3,855

B PRV station on 40 mm dia line no. 7 964 6,748

C PRV station on 50 mm dia line no. 13 1,446 18,798

D PRV station on 65 mm dia line no. 4 2,409 9,636

Float valve

E Float valve on 75 mm dia line no. 8 290 2,320

F Float valve on 100 mm dia line no. 1 386 386

G Pressure gauge (size vary) no. 16 482 7,712

H All connection & valves required for RCC water tanks item 12,010

J Angle valve (CP) for sanitary ware 15 mm dia no. 242 39 9,438

K Water Hammer Arrestor on 15 mm dia pipe no. 60 145 8,700

L Automatic Air vents with isolating valves 25 mm dia no. 5 145 725

M Bib Taps with fittings 16 mm dia no. 320 39 12,480

N Main water meter chamber cover (Size: 600X600 mm) no. 1 771 771

Allow for flexible joints at places where the Water supply pipework crosses
P item 25,000
the building expansion joint.

To Collection 118,579
B13/74
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
3. WATER SUPPLY SYSTEM (Cont'd)

EQUIPMENT

Supply, installation, testing and commissioning of booster pumps with


pressure vessel including all pipe work, interconnections level indicators
float switch inertia bases, starter panel with controls, wirings, mountings,
valves, strainers, conduits, interlocks, flexible connections, gauges, interfacing
with BMS etc. complete as per Specifications and Drawings

Booster pump set for overhead water tanks (1 duty + 1 standby), 36m3/hr. as
A set 3 28,905 86,715
shown in the Drawings

B Pressure Vessel (500 Liters) no. 3 482 1,446

Supply, installation, testing and commissioning of transfer pumps including all


pipe work, interconnections, level indicators, float switch, inertia bases, starter
panel with controls, wirings, mountings, valves, strainers, conduits, interlocks,
flexible connections, gauges, interfacing with BMS etc. complete as per
Specifications and Drawings

Transfer pump set for over head domestic water tanks, (1 duty + 1 stand by)
C set 1 38,540 38,540
45m3/hr. as shown in Drawings

Transfer pump set for over head domestic water tanks, (1 duty + 1 assistive +
D set 1 67,445 67,445
1 stand by) 30m3/hr. as shown in Drawings

Transfer pump set for over head make-up water tank suitable for 12 Full Load
E Hours of Operation interlinked with cooling tower and PLC systems, (1 duty + set 1 38,540 38,540
1 stand by) 200 m3/hr. as shown in Drawings

DOSING SYSTEM

Supply, installation, testing and commissioning of Dosing system for domestic


water chlorination including dosing tank, dosing pump, circulating pumps,
F chlorine controller, starter panel with controls, interconnecting pipes, fittings, item 2 28,905 57,810
supports, accessories, wiring, coordination with authority for connection as
deemed necessary in line with local regulations, drawings and specifications.

To Collection 290,496
B13/75
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
3. WATER SUPPLY SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

Supply, installation, testing and commissioning of hot water heater including


all pipe work, interconnections, level indicators, control switch, wirings,
mountings, valves, conduits, interlocks, flexible connections, etc. complete as
per Specifications and Drawings.

A Water Heater, 50 Lit with Safety Valve no. 24 482 11,568

B Water Heater, 80 Lit with Safety Valve no. 38 579 22,002

Supply, installation, testing and commissioning of GRP water tank including


pipe connections, valves, level indicators, ,float valves, vent pipes,lowlevel
and high level switches, overflow drains, necessary foundations etc. making
good as per Specifications and Drawings

GRP hot pressed Insulated Panel water Tank with accessories (7.0 X 5.0 X
C no. 2 117,551 235,102
2.5 m )

GRP hot pressed Insulated Panel water Tank with accessories (5.0 X 4.0 X 2.5
D no. 4 81,898 327,592
m)

GRP hot pressed Insulated Panel water Tank with accessories (16.5 X 11.0 X
E no. 1 240,875 240,875
3.0 m)

To Collection 837,139
B13/76
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
3. WATER SUPPLY SYSTEM (Cont'd)

EQUIPMENT (Cont'd)

IRRIGATION SYSTEM

ONLY
Allow for complete irrigation system including piping, valves, necessary
A item PROVISION
fittings & fixings, etc., complete as per Drawings & Specifications.
INCLUDED

IRRIGATION TANKS

Irrigation water tank GRP panel type OG water tanks each tank size
(14.00x4.00x2.00 m), each tank capacity 22,000 imp. Gal including necessary
fixings, supports, vents, etc., complete as per Drawings and Specifications.

BY MAIN
CONTRACTOR
AS PER TENDER
B GRP water tanks (14 x 4 x 2) m no. 2 CLARIFICATION
09R / POST
TENDER ITEM
333

IRRIGATION PUMP

Supply, installation , testing and commissioning of working and Standby


irrigation pumps including all interconnections, control panels, wirings,
mountings, valves, strainers, conduits, interlocks, flexible connections, all
complete in accordance with the Drawings and Specifications .

BY MAIN
CONTRACTOR
AS PER TENDER
C Irrigation pump (1 Duty + 1 Stand-by) (As per specialist requirement) set 1 CLARIFICATION
09R / POST
TENDER ITEM
333

Note:

Scope of Irrigation System includes the Design, Supply, Installation, Testing BY IRRIGATION
and Commissioning by Specialist Irrigation Contractor. SPECIALIST

To Collection -
B13/77
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

ONLY
Liasioning, Co-ordination charges for the authority approval for the
A item APPLICATION
completed Water system installation .
FEES INCLUDED

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1.Electrical contractor scope of work is limited up to the isolators


2.Mechanical contractor shall include the entire balance works for connecting NOTED,
B to their mechanical equipment's. item COMPLIED AND
3.By this way, mechanical contractor to supply, installation etc. required INCLUDED
cables, wires, containments like cable tray, supports etc.,.

WORK INCIDENTAL TO WATER SUPPLY INSTALLATION


Builders work

BY MAIN
Allow for making holes ,mortices, chases and the like and making good CONTRACTOR
C item
finishing . Refer to Scope of
Matrix item 1

D Allow for supports, including fixings, anchors and anti-vibration devices item INCLUDED

E Allow for providing sleeves item INCLUDED

BY MAIN
CONTRACTOR
F Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

G Coordination with other engineering INSTALLATIONS item INCLUDED

To Collection -
B13/78
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
3. WATER SUPPLY SYSTEM (Cont'd)

Sundries

Allow for all identification labels including plates, charts and identification of
A item INCLUDED
plant, equipment, cable, switches and colour coding.

Allow for tools and spares, which shall include loose keys and consumable
B item INCLUDED
spares

Allow for testing and commissioning, which shall include operating complete
C item INCLUDED
INSTALLATIONS

Allow for documents, which shall include shop Drawings, as built Drawings,
D item INCLUDED
operating instructions and maintenance manuals as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


E item INCLUDED
parts of each piece of equipment

Allow for protective painting to mechanical engineering systems including


F item INCLUDED
cleaning and polishing exposed surfaces .

Any external Plumbing services and works in respect of connection to main ONLY CONNECTION
G incoming services (tie-ins) outside the plot limits including all associated civil item INCLUDED WITHIN PLOT
works. LIMITS

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as CONTRACTOR
H item
per acceptable material system approved by the Engineer. Refer to Scope of
Matrix item 28

J Allow for Domestic water piping sterilization by application of Chlorine. item INCLUDED

Seismic supports calculation and verification of supports from specialist for all
K item INCLUDED
Water supply pipes.

L Allow for provision of Samples item INCLUDED

Services Connection

ONLY
Permanent Connection of water pipes ,including builders work in connection
M item CONNECTION
and other requirements
INCLUDED

To Collection -
B13/79
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B13/80
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM

Supply, installation, testing & commissioning of the fire fighting system in


accordance with the Drawings, Specifications, approved authority Drawings,
relevant NFPA standards including necessary coordination with other services
and in compliance to authority regulations

FIRE FIGHTING PIPE WORK

Fire fighting pipe ERW AS PER FINAL AGREEMENT work in conformity


with NFPA requirements including all necessary supports, fittings threaded
and grooved, fixings and accessories, expansion joints, painting, sleeves
complete; all in accordance with Drawings and Specifications and Authority
requirements.

A Pipe 25 mm dia m 15,265 58 885,370

B Pipe 32 mm dia m 8,091 66 534,006

C Pipe 40 mm dia m 5,023 89 447,047

D Pipe 50 mm dia m 2,282 122 278,404

E Pipe 65 mm dia m 1,996 203 405,188

F Pipe 80 mm dia m 3,844 244 937,936

G Pipe 100 mm dia m 1,718 284 487,912

H Pipe 150 mm dia m 7,720 405 3,126,600

J Pipe 200 mm dia m 157 486 76,302

K HDPE Fire hydrant pipe 150 mm dia (UG) m 999 386 385,614

L HDPE Fire hydrant pipe 200 mm dia (UG) m 1,450 434 629,300

To Collection 8,193,679
B13/81
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

ACCESSORIES

Supply installation testing and commissioning of sprinkler heads including


fittings and accessories required for completion of work all in accordance
with the authority regulations, Drawings and Specifications (UL listed / FM
approved).

A Upright Sprinkler Head no. 13333 55 733,315

B Concealed Pendent Sprinkler Head no. 2480 58 143,840

C Side Extended Sprinkler Head no. 1032 63 65,016

D Window sprinkler no. 155 63 9,765

Supply installation, testing and commissioning of Fire hose cabinet (Recessed


SS mirror finish) with door including 1 no 25 mm x30 m automatic fire hose
reel, 65 mm dia landing valve with built in pressure reducing valve, 1 no 25
mm Lock shield valve, 1 no 25 mm PRV & related accessories i.e. 6.0 kg
CO2 fire extinguisher, 5.0 kg Dry powder fire extinguisher, 65mm dia. hose
and accessories required for completion of the work ,fixing in position as
listed in line with authority regulations, relevant NFPA standards, Drawings
and Specifications.

E FHC cabinets (Recessed type) no. 65 5,781 375,765

Supply installation, testing and commissioning of Fire hose cabinet surface


type with door including 1 no 25 mm x 30 m automatic fire hose reel, 65 mm
dia landing valve with built in pressure reducing valve, 1 no 25 mm Lock
shield valve, 1 no 25 mm PRV & related accessories i.e. 6.0 kg CO2 fire
extinguisher, 6.0 kg Dry powder fire extinguisher, 65mm dia. hose etc., with
extinguishers as listed in line with authority regulations, relevant NFPA
standards, Drawings and Specifications.

F FHC cabinets (Surface type) no. 85 6,745 573,325

Supply installation, testing and commissioning of valves (UL listed / FM


approved) associated with the fire fighting system, all in accordance with
Drawings and Specifications.
Isolation valve

G IV 40 mm dia no. 6 386 2,316

H IV 50 mm dia no. 47 771 36,237

J IV 65 mm dia no. 67 1,157 77,519

To Collection 2,017,098
B13/82
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
4. FIRE FIGHTING SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of valves (UL listed / FM


approved) and its accessories associated with the fire fighting system, all in
accordance with Drawings and Specifications. (Cont'd)

OS &Y valve with tamper switch

A IV 80 mm dia no. 77 1,349 103,873

B IV 100 mm dia no. 2 1,542 3,084

C IV 150 mm dia no. 19 1,927 36,613

D IV 200 mm dia no. 2 2,409 4,818

Gate valve

E GV 150 mm dia no. 16 1,927 30,832

Pressure reducing valve

F PRV 200 mm dia no. 2 17,343 34,686

Supervisory valve (UL listed / FM approved)

G SV 40 mm dia no. 6 193 1,158

H SV 50 mm dia no. 47 386 18,142

J SV 65 mm dia no. 80 579 46,320

K SV 80 mm dia no. 74 723 53,502

L SV 100 mm dia no. 4 771 3,084

M SV 150 mm dia no. 5 1,157 5,785

To Collection 341,897
B13/83
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of valves associated with the


fire fighting system all in accordance with Drawings and Specifications.
(Cont'd)

Zone control valve assembly (UL Listed/FM approved) , including Butterfly


valve, Water Flow Switch, Test valve & Drain Valve, sight glass, with all
necessary fittings and accessories required for completion of work ,and to be
interfaced with FACP complete all as per Drawings and Specifications.
(Cont'd)

A ZCV 80 mm dia no. 3 2,891 8,673

B ZCV 100 mm dia no. 3 3,854 11,562

C ZCV 150 mm dia no. 57 4,336 247,152

D ZCV 200 mm dia no. 17 4,818 81,906

Non return valve

E NRV 150 mm dia no. 9 1,927 17,343

Alarm check valve assembly including (UL listed / FM approved) Alarm


check valve, system pressure gauge, retard chamber, O.S & Y gate valve &
main drain valve complete as per Drawings & Specifications.

F ACV assembly 200 mm dia no. 2 8,672 17,344

G Air release valve 25 mm dia no. 26 290 7,540

To Collection 391,520
B13/84
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

EQUIPMENT

Supply, installation, testing and commissioning of fire extinguishers (UL


listed / FM approved) independently mounted including brackets ,supports
,instruction signs in accordance with the authority regulations, Specifications
and Drawings to the satisfaction of the Engineer.

A 6 Kg dry powder extinguisher no. 462 290 133,980

B 5.0 kg CO2 fire extinguisher no. 799 386 308,414

C 9.0 kg water pressurized fire extinguisher no. 991 241 238,831

D Automatic fire extinguisher no. 53 193 10,229

BREECHING INLET

4-way x 150 mm instantaneous inlets, 150 mm flanged outlet vertical pattern


inlet breeching unit for external hydrant system complete with 25 mm drain
E valve, caps & chains, integral check valve. inlet breeching unit to be no. 2 4,818 9,636
installationed in stainless steel box with stainless steel architrave & stainless
steel wired glass door.

4-way x 150 mm instantaneous inlets, 150 mm flanged outlet vertical pattern


inlet breeching unit for external hydrant system complete with 25 mm drain
F valve, caps & chains, integral check valve. inlet breeching unit to be no. 2 4,818 9,636
installationed in stainless steel box with stainless steel architrave & stainless
steel wired glass door.

FIRE HYDRANT

Supply and installation of Fire hydrant pillar type with protecting shell, valves
G as per French Standard NFS 61213 or equivalent British Standard no. 21 14,453 303,513
Manufacturer and shall be approved by the Local Civil Defense Authority.

Non raising system OS & Y gate valve 200mm Dia. for Fire hydrant interfaced
H no. 21 1,446 30,366
with FACP.

Allow for flexible joints at places where the fire fighting pipework crosses the
J item 59,414
building expansion joint.

To Collection 1,104,019
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
B13/85
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

Supply, installation, testing and commissioning of Fire fighting and sprinkler


set consisting of Vertical turbine electrical pump ,diesel engine driven, electric
driven, jockey, pump set minimum capacity of pump shall be as per details
below & as indicated in this Specifications at related sections. (note : all fire
pumps duty, stand by & jockey pumps shall be mounted on concrete plinths
with vibration isolation, engine discharge) including automatic control panel,
fuel tank , pressure vessel, valves, pressure gauge, accessories, to be
interfaced with BMS,FACP etc. complete as per Engineer's approval,
Specifications and all complete in accordance with Drawings and
Specifications. (UL listed / FM Approved)

A Electrical Pump (1500 U.S. GPM @ 6.9 Bar head) no. 1 134,890 134,890

B Diesel Pump (1500 U.S. GPM @ 6.9 Bar head) no. 1 134,890 134,890

C Jockey Pump (50 U.S. GPM @ 6.9 Bar head) no. 1 43,358 43,358

D Electrical Pump (1000 U.S. GPM @ 6.9 Bar head) no. 1 144,525 144,525

E Diesel Pump (1000 U.S. GPM @ 6.9 Bar head) no. 1 144,525 144,525

F Jockey Pump (50 U.S. GPM @ 6.9 Bar head) no. 1 43,358 43,358

G Sch 40 carbon steel Exhaust pipe line from pump room to exhaust outlet item 16,928

Connections (to Fire Water tanks) only including incidental labour and material

Connection to RCC water tank including inlet, outlet, drainage, backwash line,
H item 20,000
overflow pipe, etc. complete

To Collection 682,474
B13/86
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
4. FIRE FIGHTING SYSTEM (Cont'd)

FM 200 system

Supply, installation, testing & commissioning including room integrity test of


FM 200 system including cylinder racks, concrete reinforced base with
vibration isolator(if required ),filled with gas capacities as per the floor area
requirement ,pipework ,valves,nozzles,control panels wiring interfaced FACP
for following listed areas complete; all complete in accordance with
Drawings, Specifications and authority regulation and approval.(smoke and
heat detector measured elsewhere ) (UL listed / FM Approved)

A Clean agent system @ CCTV room(CCTV.R.1B.1) at Basement 1 item 1 57,810 57,810

B Clean agent system @ Control room(CON.R.1B.1) at Basement 1 item 1 57,810 57,810

C Clean agent system @ Electrical room at First floor (Area 10.37m2) item 1 63,591 63,591

D Clean agent system @ Electrical room at First floor (Area 24.07m2) item 1 72,263 72,263

E Clean agent system @ Electrical room at First floor (Area 3.48m2) item 1 10,000 10,000

F Clean agent system @ Electrical room at First floor (Area 32.41m2) item 1 81,898 81,898

G Clean agent system @ Electrical room at First floor (Area 8.8m2) item 1 61,664 61,664

H Clean agent system @ Electrical room at First floor (Area 8.91m2) item 1 62,628 62,628

J Clean agent system @ Electrical room at First floor (Area 9.74m2) item 1 62,628 62,628

K Clean agent system @ Electrical room at Ground floor (Area 10.69m2) item 1 63,591 63,591

L Clean agent system @ Electrical room at Ground floor (Area 11.6m2) item 1 64,555 64,555

To Collection 658,438
B13/87
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
4. FIRE FIGHTING SYSTEM (Cont'd)

FM 200 system (Cont'd)

Supply, installation, testing & commissioning including room integrity test of


FM 200 system including cylinder racks,concrete reinforced base with
vibration isolator(if required ),filled with gas capacities as per the floor area
requirement ,pipework ,valves,nozzles,control panels wiring interfaced FACP
for following listed areas complete; all complete in accordance with
Drawings, Specifications and authority regulation and approval.(smoke and
heat detector measured elsewhere ) (UL listed / FM Approved) (Cont'd)

A Clean agent system @ Electrical room at Ground floor (Area 14.24m2) item 1 66,482 66,482

B Clean agent system @ Electrical room at Ground floor (Area 16.2m2) item 1 67,445 67,445

C Clean agent system @ Electrical room at Ground floor (Area 46m2) item 1 81,898 81,898

D Clean agent system @ Electrical room at Ground floor (Area 8.8m2) item 1 61,664 61,664

E Clean agent system @ Electrical room at Ground floor (Area 9.4m2) item 1 62,628 62,628

F Clean agent system @ Electrical room at Second floor (Area 250 m2) item 1 207,700 207,700

G Clean agent system @ Electrical room at Second floor (Area 29.10 m2) item 1 77,080 77,080

H Clean agent system @ Electrical room at Second floor (Area 6.25 m2) item 1 59,737 59,737

Clean agent system @ Electrical room chiller isolator at Second floor (Area
J item 1 115,620 115,620
100 m2)

K Clean agent system @ Electrical room(ELE.1B.1) at Basement 1 item 1 57,810 57,810

L Clean agent system @ Electrical room(ELE.1B.2) at Basement 1 item 1 57,810 57,810

M Clean agent system @ Electrical room(ELE.1B.3) at Basement 1 item 1 57,810 57,810

To Collection 973,684
B13/88
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
4. FIRE FIGHTING SYSTEM (Cont'd)

FM 200 system (Cont'd)

Supply, installation, testing & commissioning including room integrity test of


FM 200 system including cylinder racks,concrete reinforced base with
vibration isolator(if required ),filled with gas capacities as per the floor area
requirement ,pipework ,valves,nozzles,control panels wiring interfaced FACP
for following listed areas complete; all complete in accordance with
Drawings, Specifications and authority regulation and approval.(smoke and
heat detector measured elsewhere ) (UL listed / FM Approved) (Cont'd)

A Clean agent system @ Electrical room(ELE.FF.3) at First floor (Area 8.86m2) item 1 61,664 61,664

Clean agent system @ Electrical room(ELE.FF.4) at First floor (Area


B item 1 63,591 63,591
10.89m2)

Clean agent system @ Electrical room(ELE.FF.4) at First floor (Area


C item 1 67,445 67,445
16.18m2)

Clean agent system @ Electrical room(ELE.FF.8) at First floor (Area


D item 1 65,518 65,518
12.94m2)

E Clean agent system @ Electrical room(ELE.G.12) at Ground floor (Area 9m2) item 1 62,628 62,628

F Clean agent system @ Electrical room(G.04) at Ground floor (Area 22m2) item 1 71,299 71,299

G Clean agent system @ GSM room at Basement 1 item 2 57,810 115,620

H Clean agent system @ GSM room at Second floor (Area 9 m2) item 1 62,628 62,628

J Clean agent system @ IDT room at First floor (Area 5.81m2) item 1 58,774 58,774

K Clean agent system @ IT room at First floor (Area 7.37m2) item 1 60,701 60,701

L Clean agent system @ IT room at Second floor (Area 10.20 m2) item 1 63,591 63,591

M Clean agent system @ IT room at Second floor (Area 5.75 m2) item 1 58,774 58,774

N Clean agent system @ IT room at Second floor (Area 8.40 m2) item 1 61,664 61,664

P Clean agent system @ IT Room(IT.R.1B.1) at Basement 1 item 1 57,810 57,810

To Collection 931,707
B13/89
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
4. FIRE FIGHTING SYSTEM (Cont'd)

FM 200 system (Cont'd)

Supply, installation, testing & commissioning including room integrity test of


FM 200 system including cylinder racks,concrete reinforced base with
vibration isolator(if required ),filled with gas capacities as per the floor area
requirement ,pipework ,valves,nozzles,control panels wiring interfaced FACP
for following listed areas complete; all complete in accordance with
Drawings, Specifications and authority regulation and approval.(smoke and
heat detector measured elsewhere ) (UL listed / FM Approved) (Cont'd)

A Clean agent system @ LCS room(LCS.1B.1) at Basement 1 item 1 57,810 57,810

B Clean agent system @ LCS room(LCS.1B.2) at Basement 1 item 1 57,810 57,810

C Clean agent system @ LCS room(LCS.1B.3) at Basement 1 item 1 57,810 57,810

D Clean agent system @ LCS.2B.1 at Basement 2 (Area 8 m2) item 1 61,664 61,664

E Clean agent system @ LCS.2B.2 at Basement 2 (Area 9 m2) item 1 62,628 62,628

F Clean agent system @ LCS.2B.3 at Basement 2 (Area 18.56 m2) item 1 69,372 69,372

G Clean agent system @ Tel. room(TELE.1B.1) at Basement 1 item 1 57,810 57,810

H Clean agent system @ Telephone room at First floor (Area 16m2) item 1 67,445 67,445

J Clean agent system @ Telephone room at First floor (Area 6m2) item 1 59,737 59,737

K Clean agent system @ Telephone room at First floor (Area 7.5m2) item 1 60,701 60,701

L Clean agent system @ Telephone room at First floor (Area 9.36m2) item 1 62,628 62,628

M Clean agent system @ Telephone room at Ground floor (Area 12.96m2) item 1 65,518 65,518

N Clean agent system @ Telephone room at Ground floor (Area 18m2) item 1 69,372 69,372

P Clean agent system @ Telephone room at Ground floor (Area 7.5m2) item 1 60,701 60,701

To Collection 871,006
B13/90
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FM 200 system (Cont'd)

Supply, installation, testing & commissioning including room integrity test of


FM 200 system including cylinder racks,concrete reinforced base with
vibration isolator(if required ),filled with gas capacities as per the floor area
requirement ,pipework ,valves,nozzles,control panels wiring interfaced FACP
for following listed areas complete; all complete in accordance with
Drawings, Specifications and authority regulation and approval.(smoke and
heat detector measured elsewhere ) (UL listed / FM Approved) (Cont'd)

A Clean agent system @ Telephone room at Ground floor (Area 8.7m2) item 1 61,664 61,664

B Clean agent system @ Telephone room(G.05) at Ground floor (Area 9.3m2) item 1 62,628 62,628

Clean agent system @ Telephone room(TEL.FF.2) at First floor (Area


C item 1 63,591 63,591
10.75m2)

Clean agent system @ Telephone room(TEL.FF.4) at First floor (Area


D item 1 67,445 67,445
16.85m2)

Clean agent system @ Telephone room(TEL.G.6) at Ground floor (Area


E item 1 64,555 64,555
11m2)

To Collection 319,883
B13/91
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
4. FIRE FIGHTING SYSTEM (Cont'd)

DELUGE SYSTEM

Supply, installation, testing & commissioning including room integrity test of


Deluge system including cylinder racks,concrete reinforced base with
vibration isolator(if required ),filled with gas capacities as per the floor area
requirement ,pipework ,valves,nozzles,control panels wiring interfaced FACP
for following listed areas complete; all complete in accordance with
Drawings, Specifications and authority regulation and approval.(smoke and
heat detector measured elsewhere ) (UL listed / FM Approved)

Foam deluge system @ Generator room(GENE.1B.1) at Basement 1 (Area


A item 1 250,510 250,510
55.73m2)

Foam deluge system @ Generator room(GENE.1B.2) at Basement 1 (Area


B item 1 154,160 154,160
27.75m2)

Foam deluge system @ Generator room(GENE.1B.3) at Basement 1 (Area


C item 1 192,700 192,700
46.52m2)

Foam deluge system @ Generator room(GENE.1B.4) at Basement 1 (Area


D item 1 221,605 221,605
51.13m2)

Supply, installation, testing and commissioning including room integrity test


E of Deluge systems per Drawings and Specifications & in accordance with
relevant NFPA standards, Authority Regulations.

F Deluge system for LPG tanks @ Second Floor Level item 1 57,810 57,810

G Deluge system for LPG tanks @ Roof Level item 1 57,810 57,810

Supply and installation of Double bundle protection systems per Drawings and
H Specifications & in accordance with relevant NFPA standards, Authority
Regulations.

J Double Bundle protection system for Diesel Tanks capacity 1000 Ltr item 1 20,000

K Double Bundle protection system for Diesel Tanks capacity 800 Ltr item 1 20,000

To Collection 974,595
B13/92
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators 2.


Mechanical contractor shall include the entire balance works for connecting to NOTED,
A their mechanical equipment's. 3. By this way, mechanical contractor to supply, item COMPLIED AND
installation etc. required cables, wires, containments like cable tray, supports INCLUDED
etc.,.

B Liaisoning, Co-ordination charges for the local CD approval item INCLUDED

Builders work

BY MAIN
Allow for making holes ,mortices,chases and the like and making good CONTRACTOR
C item
finishing . Refer to Scope of
Matrix item 1

D Allow for supports, including fixings, anchors and anti-vibration devices item INCLUDED

E Allow for providing sleeves as per Authority requirements / NFPA standards. item INCLUDED

BY MAIN
CONTRACTOR
F Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

Note:

NOTED,
Contractor to appoint Civil defense approved Firefighting contractor upon
COMPLIED AND
approval from Client and Consultant for entire Mall.
INCLUDED

Sundries

Allow for Seismic supports calculation and verification of supports from


G item 600,000
specialist for all Water supply pipes.

H Allow for training of client and the contractors item INCLUDED

J Allow for provision of Samples item INCLUDED

To Collection 600,000
B13/93
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
4. FIRE FIGHTING SYSTEM (Cont'd)

Sundries (Cont'd)

Allow for liasion,coordination and attendance with DCD,DSOA authorities


A item INCLUDED
till getting the final TOC for the complete mall .

Allow for third party certificate from authorised company for handing over
B item INCLUDED
the system for the complete mall.

Allow for all identification labels including plates, charts and identification of
C item INCLUDED
plant, equipment, cable, switches and colour coding

Allow for tools and spares, which shall include loose keys and consumable
D item INCLUDED
spares that has to be handed over to client

Allow for testing and commissioning of the complete fire fighting


E INSTALLATIONS which must include operation of complete fire fighting item INCLUDED
system

Allow for testing the complete fire fighting installation in the presence of
F engineer ,repeat test as may be required and leave in perfect order and to the item INCLUDED
satisfaction of the engineer and the local authority

Allow for documents, which shall include submittals, shop Drawings, as built
G item INCLUDED
Drawings, samples operation and maintenance manual as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


H item INCLUDED
parts of each piece of equipment /items /materials

J Allow for protective painting item INCLUDED

Allow for connection to mains including pipework and all necessary


K accessories, complete all in accordance with the drawings ,Specifications ,as item INCLUDED
per DCD requirements .

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as
CONTRACTOR
L per acceptable material system approved by the Engineer. Fire stopping item
Refer to Scope of
specialist approved by Consultant and Client.
Matrix item 28

To Collection -
B13/94
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B13/95
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM

Supply, installation , testing and commissioning of LPG Gas pipe work


including fittings, supports, accessories, protection, fire sealant of pipes
through crossing walls etc., complete as listed in line with authority
regulations , relevant accepted codes of practice (NFPA 58 &54/LPG IT A) ,
Specifications and Drawings

GAS Pipework

Supply and installation of LPG pipework including all necessary pipe


expansion joints, hangers, sleeves, accessories, fittings, support and etc.,
complete; all in accordance with the Drawings, Specifications and as per
NFPA standards

32 mm dia Carbon Steel pipe to ASTM A53 Grade-B. schedule 80 Seamless


A cleaned and painted with redoxide primer and two coats of yellow ochre m 24 60 1,440
colour to BS 1710 , LPG filling line up to storage tank

B 50 mm dia Sch 40 pipe m 7 80 560

C 3/4'' Carbon steel pipe m 2868 30 86,040

D 1'' Carbon steel pipe m 3664 40 146,560

E 1/4'' Carbon steel pipe m 324 50 16,200

F 50 mm dia Sch 80 pipe m 56 70 3,920

G 2'' Sch 40 pipe m 7 80 560

H Vapor out line m 73 80 5,840

To Collection 261,120
B13/96
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

Supply and installation of insulation to LPG pipework on roof including all


necessary accessories, etc., complete; all in accordance with the Drawings and
Specifications

A 3/4'' Carbon steel pipe m 2868 8 22,944

B 1'' Carbon steel pipe m 3664 10 36,640

C 1/4'' Carbon steel pipe m 324 15 4,860

D 50 mm dia Sch 80 pipe m 56 80 4,480

E Vapor out line m 73 30 2,190

LPG Filling Point Includes

F Protective aluminum box (400x400x200 mm) no. 1 1000 1,000

G 32 mm dia double check filler valve no. 1 120 120

H 32 mm dia Globe valve no. 1 150 150

J 32 mm dia Safety relief valve no. 1 200 200

K 32 mm dia Ball valve no. 1 65 65

L 32 mm dia Back Check valve no. 1 85 85

LPG Electrical Installations

Fireproof cabling for main Gas detection panel (Interface with all selenoid
M item INCLUDED
valves)

N Wiring for Vaporizer with Isolator item INCLUDED

P Remote Gas monitoring wiring item INCLUDED

Q Interface cabling between BMS and LPG item INCLUDED

R Interface cabling between FACP and LPG item INCLUDED

S Gas meter Interface with BMS item INCLUDED

T Gas Control Panel (DCD approved) item INCLUDED

To Collection 72,734
B13/97
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

Equipment

Supply, installation, testing and commissioning of LPG storage tanks as per


ASME standards, municipality standards and Engineer’s approval; including
all necessary supports, joints, fixings and fittings accessories etc., all complete
in accordance with the Drawings and Specifications and as per NFPA
standards .

A LPG Storage tank (3000 US gallons) no. 2 43,000 86,000

Supply, installation, testing and commissioning of Pressure reducing &


Distribution panel including automatic changeover 10 kg/hr, manifold for 3
cylinders, isolating valves, solenoid valve, pressure switch, isolating valve for
riser, service reserve indicator, etc., complete in accordance with the Drawings
and Specifications and as per NFPA standards ..

B Pressure reducing & distribution panel no. 1 5,000 5,000

Supply, installation, testing and commissioning of the following including all


accessories, fittings, fixtures, etc., complete as per Drawings and
Specifications.

C Vaporizer assembly no. 1 2000 2,000

D Ball valve 32 mm dia no. 1 120 120

E Control panel interfaced with FACP no. 1 5000 5,000

F Emergency gas on off switch no. 51 500 25,500

G Excess flow valve 32 mm dia no. 2 200 400

H Explosion proof gas detector 24V (DCD approved ) interfaced with FACP no. 49 600 29,400

J Gas leak detector (24 V) Interfaced with FACP as per DCD approval no. 143 800 114,400

K Gas meter assembly (BMS compatible) no. 51 2000 102,000

L Hydrostatic relief valve 32 mm dia no. 2 250 500

M Gas leak detector inside Vertical Shaft item 9,000

N Gas leak detector inside Horizontal Shaft item 6,631

To Collection 385,951
B13/98
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

Equipment (Cont'd)

CONTAINMENT PIPE

Supply & installation of Containment for gas pipe in vertical risers and pipes
running horizontally outside the kitchen complete as per Drawings and
Specifications. (Note: Copper pipe measured separately)

A Containment pipe m 314 50 15,700

Supply, installation, testing and commissioning of the following including all


accessories, fittings, fixtures, etc., complete as per Drawings and
Specifications and as per NFPA standards .

B Shut off valve 32 mm dia no. 5 300 1,500

C Sounder no. 1 500 500

D Isolation valve 20 mm dia no. 47 85 3,995

E Pressure regulator no. 47 500 23,500

F Heat Detector no. 2 1,500 3,000

TANK FENCE

Supply & installation of fence (2000mm Height) around the tank with door BY MAIN
G item
complete as per Drawings & Specifications. CONTRACTOR

H Provision of Signages for LPG yard item 5,000

J LPG Tank first fill by the Contractor item 5,000

K Radiographic test for LPG system (only 20%) item 10,000

Note:

NOTED,
LPG pipe sizes and quantities are indicative only. Actual LPG sizes to be
COMPLIED AND
designed by civil defense approved LPG specialist.
INCLUDED

To Collection 68,195
B13/99
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

ONLY
Liasoning, Co-ordination charges for the local DCD approval for the
A item APPLICATION
completed LPG installation .
FEES INCLUDED

1. Electrical contractor scope of work is limited up to the isolators


2.Mechanical contractor shall include the entire balance works for connecting NOTED,
B to their mechanical equipment.3.By this way, mechanical contractor to supply, item COMPLIED AND
installation etc. required cables, wires, containments like cable tray, supports INCLUDED
etc.,.

WORK INCIDENTAL TO LPG installation

Builders work

BY MAIN
Allow for making holes ,mortices,chases and the like and making good CONTRACTOR
C item
finishing . Refer to Scope of
Matrix item 1

D Allow for support, including fixings, anchors and anti-vibration devices item INCLUDED

E Allow for providing sleeves as per codes and regulations item INCLUDED

BY MAIN
CONTRACTOR
F Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

G Coordination with other engineering INSTALLATIONS item INCLUDED

Note:

NOTED,
LPG contractor should be Dubai Civil defense approved. COMPLIED AND
INCLUDED

NOTED,
LPG contractor should be approved by the Client and Consultant. COMPLIED AND
INCLUDED

To Collection -
B13/100
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)
5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)
Sundries
Allow for all identification labels including plates, charts and identification of
A item INCLUDED
plant, equipment, cable, switches and colour coding.

Allow for tools and spares, which shall include loose keys and consumable
B item INCLUDED
spares

Allow for Third party specialist agency for LPG installation, approved by
C local authority to undertake such works. Third party should be approved by the INCLUDED
Client and Consultant.

Allow for Third party Approval with testing and commissioning, which shall
D item INCLUDED
include operating complete INSTALLATIONS

Allow for documents, which shall include shop Drawings, as built Drawings,
E item INCLUDED
operating instructions and maintenance manuals as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


F item INCLUDED
parts of each piece of equipment

Allow for protective painting to mechanical engineering systems including


G item INCLUDED
cleaning and polishing exposed surfaces .

Any external MEP services and works in respect of connection to main ONLY CONNECTION
H incoming services (tie-ins) outside the plot limits including all associated civil item INCLUDED WITHIN PLOT
works. LIMITS

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as CONTRACTOR
J item
per acceptable material system approved by the DCD. Refer to Scope of
Matrix item 28

K Allow for provision of Samples item INCLUDED

L Third party Certificate for LPG Installation, testing and commissioning. item INCLUDED

Allow for coordination of LPG contractor with BMS contractor, Fire alarm
M item INCLUDED
contractor

To Collection -
B13/101
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

Notes:

NOTED,
The LPG system shall be installationed by a specialist agency approved by the
COMPLIED AND
relevant local authority to undertake such works .
INCLUDED

All drawings and submittals shall be submitted for the approval of the NOTED,
Engineer and local authority wherever applicable ,prior to the commencement COMPLIED AND
of any work . INCLUDED

The Central LPG system shall be executed in accordance with the relevant
NOTED,
intentionally accepted codes of practice (NFPA 58 &54/LPG IT A ) and also in
COMPLIED AND
conformity with the requirements of local civil defense and /or any other
INCLUDED
agency who has jurisdiction over such works .

To Collection -
B13/102
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B13/103
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

COLLECTION

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM

Page B13/1 3,603,790


Page B13/2 5,181,729
Page B13/3 2,600,934
Page B13/4 2,982,785
Page B13/5 1,010,380
Page B13/6 250,146
Page B13/7 344,234
Page B13/8 1,033,375
Page B13/9 92,036
Page B13/10 3,740
Page B13/11 5,746
Page B13/12 1,556,114
Page B13/13 186,459
Page B13/14 38,265
Page B13/15 50,700
Page B13/16 60,707
Page B13/17 33,044
Page B13/18 18,657
Page B13/19 9,258
Page B13/20 54,155
Page B13/21 8,485

19,124,739
B13/104
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)
19,124,739
Page B13/22 732,475
Page B13/23 449,513
Page B13/24 88,504
Page B13/25 58,288
Page B13/26 65,129
Page B13/27 4,957,040
Page B13/28 20,374,952
Page B13/29 6,185,994
Page B13/30 9,142,304
Page B13/31 3,012,537
Page B13/32 6,046,200
Page B13/33 960,630
Page B13/34 844,692
Page B13/35 421,938
Page B13/36 1,804,800
Page B13/37 1,848,900
Page B13/38 218,214
Page B13/39 4,174,000
Page B13/40 3,311,697
Page B13/41 132,300
Page B13/42 238,400
Page B13/43 75,500
Page B13/44 34,800

84,303,546
B13/105
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's
84,303,546
Page B13/45 137,400

Page B13/46 1,238,900

Page B13/47 148,900

Page B13/48 217,169

Page B13/49 882,704

Page B13/50 569,177

Page B13/51 558,806

Page B13/52 1,028,846

Page B13/53 0

Page B13/54 473,000

Page B13/55 174,000

Page B13/56 268,976

Page B13/57 648,576

TOTAL HVAC (HEATING VENTILATION AND AIR CONDITIONING)


90,650,000
SYSTEM
B13/106
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

2. DRAINAGE SYSTEM

Page B13/58 471,654

Page B13/59 1,458,950

Page B13/60 1,338,569

Page B13/61 1,350,891

Page B13/62 133,933

Page B13/63 546,003

Page B13/64 -

Page B13/65 500,000

Page B13/66 1,400,000

Page B13/67 -

Page B13/68 -

TOTAL DRAINAGE SYSTEM 7,200,000


B13/107
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

3. WATER SUPPLY SYSTEM

Page B13/69 991,530

Page B13/70 48,688

Page B13/71 60,144

Page B13/72 76,579

Page B13/73 118,845

Page B13/74 118,579

Page B13/75 290,496

Page B13/76 837,139

Page B13/77 -

Page B13/78 -

Page B13/79 -

Page B13/80 -

TOTAL WATER SUPPLY SYSTEM 2,542,000


B13/108
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

4. FIRE FIGHTING SYSTEM

Page B13/81 8,193,679

Page B13/82 2,017,098

Page B13/83 341,897

Page B13/84 391,520

Page B13/85 1,104,019

Page B13/86 682,474

Page B13/87 658,438

Page B13/88 973,684

Page B13/89 931,707

Page B13/90 871,006

Page B13/91 319,883

Page B13/92 974,595

Page B13/93 600,000

Page B13/94 -

Page B13/95 -

TOTAL FIRE FIGHTING SYSTEM 18,060,000


B13/109
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM

Page B13/96 261,120

Page B13/97 72,734

Page B13/98 385,951

Page B13/99 68,195

Page B13/100 -

Page B13/101 -

Page B13/102 -

Page B13/103 -

TOTAL LIQUIFIED PETROLEUM GAS (LPG) SYSTEM 788,000


B13/110
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATIONS


(Cont'd)

1 HVAC (HEATING VENTILATION AND AIR CONDITIONING) SYSTEM 90,650,000

2 DRAINAGE SYSTEM 7,200,000

3 WATER SUPPLY SYSTEM 2,542,000

4 FIRE FIGHTING SYSTEM 18,060,000

5 LIQUIFIED PETROLEUM GAS (LPG) SYSTEM 788,000

Total Bill No. 13 - Carried to Summary 119,240,000


B13/111
PART ( 2 )

HYPERMARKET & DEPARTMENT STORE


Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM

FOR HYPERMARKET
Supply, installation and Testing & Commissioning of HVAC system (Heating
Ventilation and Air Conditioning), in accordance with the Drawings,
Specifications, approval of Engineer and all concern code of practice and
local authority regulations

CHILLED WATER installation


CHILLED WATER PIPE WORKS (Supply and Return)

Supply, installation, testing & commissioning of ERW as per final agreement


chilled water and condenser water pipes including all necessary pipe fittings,
supports, hangers, joints, vibration, pipe expansion compensator, isolators
( Spring type) for header pipes, fixings and all necessary fixing accessories,
all complete in accordance with the Drawings and Specifications.

A CHW 3/4 inch dia (20 mm dia) m 82 118 9,676


B CHW 1 inch dia (25 mm dia) m 20 144 2,880
C CHW 1 1/4 inch dia (32 mm dia) m 143 192 27,456
D CHW 1 1/2 inch dia (40 mm dia) m 77 231 17,787
E CHW 2 inch dia (50 mm dia) m 273 284 77,532
F CHW 2 1/2 inch dia (65 mm dia) m 177 445 78,765
G CHW 3 inch dia (80 mm dia) m 96 584 56,064
H CHW 4 inch dia (100 mm dia) m 61 833 50,813
J CHW 5 inch dia (125 mm dia) m 33 1,120 36,960
K CHW 6 inch dia (150 mm dia) m 55 1,460 80,300
L CHW 8 inch dia (200 mm dia) m 70 2,231 156,170

To Collection 594,403
B16/21
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

INSULATION TO PIPE WORKS (Supply and Return)

Supply, installation, testing of chilled water & Condenser water piping


insulation, including adhesive, vapour barrier, canvas cloth with vapour
barrier for the satisfaction of the Engineer for the following (but not limited
to) all complete in accordance with the Drawings and Specifications.

A CHW 3/4 inch dia (20 mm dia) m 82 87 7,134


B CHW 1 inch dia (25 mm dia) m 20 106 2,120
C CHW 1 1/4 inch dia (32 mm dia) m 143 140 20,020
D CHW 1 1/2 inch dia (40 mm dia) m 77 164 12,628
E CHW 2 inch dia (50 mm dia) m 273 207 56,511
F CHW 2 1/2 inch dia (65 mm dia) m 177 318 56,286
G CHW 3 inch dia (80 mm dia) m 96 423 40,608
H CHW 4 inch dia (100 mm dia) m 61 596 36,356
J CHW 5 inch dia (125 mm dia) m 33 803 26,499
K CHW 6 inch dia (150 mm dia) m 55 1,048 57,640
L CHW 8 inch dia (200 mm dia) m 70 1,600 112,000

To Collection 427,802
B16/22
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Supply, installation, testing and commissioning of chilled water & Condenser


water piping insulation, including adhesive, vapour barrier, canvas cloth with
vapour barrier for the satisfaction of the Engineer for the following (but not
limited to) all complete in accordance with the Drawings and Specifications.

ACCESSORIES

Supply, installation testing and commissioning of valves to chilled water


pipes, all complete in accordance with the Drawings and Specifications.

Isolation valve

A IV 3/4 inch dia (20 mm dia) no. 6 87 522

B IV 8 inch dia (200 mm dia) no. 1 4,102 4,102

Variable Orifice Double regulation valve (VODRV)

C VODRV 3/4 inch dia (20 mm dia) no. 3 274 822

D VODRV 8 inch dia (200 mm dia) no. 1 8,382 8,382

E Automatic air vent 25 mm dia with Isolating valve no. 2 236 472

F Ultrasonic type BTU meter compatible with BMS no. 1 13,737 13,737

To Collection 28,037
B16/23
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Air outlets

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels for satisfactory
functioning of all systems in accordance with the Drawings and
Specifications .

Supply air diffuser


A SAD 225X225 mm no. 18 101 1,818
B SAD 300X300 mm no. 45 145 6,525
C SAD 375X375 mm no. 67 193 12,931
D SAD 450X450 mm no. 279 231 64,449
E SAD 525X525 mm no. 30 318 9,540
F SAD 600X600 mm no. 10 394 3,940
Return air diffuser
G RAD 225X225 mm no. 18 77 1,386
H RAD 300X300 mm no. 45 106 4,770
J RAD 375X375 mm no. 67 145 9,715
K RAD 450X450 mm no. 279 178 49,662
L RAD 525X525 mm no. 30 221 6,630
M RAD 600X600 mm no. 10 274 2,740
Exhaust air diffuser

N Ex Diffuser 225x225 mm no. 3 77 231

To Collection 174,337
B16/24
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Air outlets (Cont'd)

Supply, installation, testing and commissioning of Supply and


return air outlets for air conditioning, fresh air Supply, fresh air
return and extract air, lobby pressurization ducts and smoke
extract with complete duct connection and necessary ancillaries,
access doors etc. in accordance Drawings and Specifications. (Cont'd)

Fresh air diffuser


A Fresh air diffuser 525x525 mm no. 37 318 11,766
Supply air grille
B SAG 600X150 mm no. 1 116 116
C SAG 750X200 mm no. 4 173 692
D SAG 900X250 mm no. 1 231 231
Return air grille
E RAG 600X150 mm no. 1 87 87
F RAG 750X200 mm no. 4 125 500
G RAG 900X250 mm no. 1 169 169
Combined grille
H Comb.AG 1000X200 mm no. 3 380 1,140
J Comb.AG 1050X250 mm no. 1 490 490
K Comb.AG 500X150 mm no. 1 173 173
Exhaust air grille
L EAG 600X200 mm no. 2 101 202
M EAG 700X300 mm no. 8 159 1,272

To Collection 16,838
B16/25
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ACCESSORIES

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, actuator, interface
with various other systems i.e. fire alarm,BMS etc. for satisfactory
functioning of all systems in accordance with the Drawings and
Specifications .

Fire damper

A FD 150X150 mm no. 12 188 2,256


B FD 250X200 mm no. 1 202 202
C FD 300X150 mm no. 1 202 202
D FD 300X300 mm no. 1 226 226
E FD 350X200 mm no. 3 212 636
F FD 350X300 mm no. 1 231 231
G FD 400X250 mm no. 1 226 226
H FD 650X350 mm no. 2 284 568
J FD 700X350 mm no. 1 293 293
K FD 750X500 mm no. 1 346 346
Volume control damper
L VCD 150X150 mm no. 2 92 184
M VCD 400X200 mm no. 12 169 2,028
N VCD 700X500 mm no. 72 428 30,816

To Collection 38,214
B16/26
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ACCESSORIES

Sensors

A CO2 Sensor interface with BMS no. 20 1,057 21,140


Air curtains includes supply ,installation , testing and comissioning

B Air curtain 800 CFM no. 11 4,035 44,385


C Air curtain 1200 CFM no. 4 4,804 19,216
D Air curtain 2400 CFM no. 1 9,511 9,511
Louvers

E Make up Sand trap louver 6 feetX10 feet no. 1

F Sand trap louver for FAHU no. 1

G Sand trap louver for Kitchen make up fan no. 8

H Motorized damper interfaced with BMS & FACP for FAHU no. 2
INCLUDED IN MALL
J Sound Attenuator for FAHU no. 2

K Bell mouth with wire mesh item

L Weatherproof canopy for FAHU no. 1

M Aluminium louver for LPG shaft as per the requirements by authority. item

To Collection 94,252
B16/27
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Duct Work

Supply, fabricate and installation GI / fire rated sheet metal rectangular


ductwork complete with plenum box, turning vanes, cross jointing, jointing
materials and sealants, access panels, demountable sections, brackets,
hangers, supports, etc. as per SMACNA standards, all complete in accordance
with the Drawings and Specifications .

Supply & Return air duct

A SAD/RAD, 26 gauge (GI) KG 36 22 792


B SAD/RAD, 24 gauge (GI) KG 17077 22 375,694
C SAD/RAD, 22 gauge (GI) KG 4453 22 97,966
D SAD/RAD, 20 gauge (GI) KG 1730 22 38,060
Fresh air duct

E FAD, 26 gauge (GI) KG 287 22 6,314


F FAD, 24 gauge (GI) KG 1,721 22 37,862
G FAD, 22 gauge (GI) KG 4,299 22 94,578
H FAD, 20 gauge (GI) KG 931 22 20,482
Exhaust air duct
J EAD, 26 gauge (GI) KG 430 22 9,460
K EAD, 24 gauge (GI) KG 459 22 10,098
L EAD, 22 gauge (GI) KG 1,007 22 22,154

To Collection 713,460
B16/28
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Duct Work

Supply, fabricate and installation GI / fire rated sheet metal rectangular


ductwork complete with plenum box, turning vanes, cross jointing, jointing
materials and sealants, access panels, demountable sections, brackets,
hangers, supports, etc. as per SMACNA standards, all complete in accordance
with the Drawings and Specifications .

Fire rated duct

A Fire rated ductwork for smoke extract & smoke make up KG 73,567 36 2,648,412

B KMAD (Fire rated) KG 1,597 36 57,492

C KED (MS Black steel) KG 9,451 42 396,942

Flexible duct with band clips, brackets, barrier supports and fixing
accessories complete; in accordance with Drawings & Specifications.

D Flexible Duct 150mm m 54 25 1,350

E Flexible Duct 200mm m 18 29 522

F Flexible duct connector for fire rated duct item INCLUDED

To Collection 3,104,718
B16/29
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Insulation to Duct Work

Fiber Glass thermal insulation to ductwork including adhesive, vapour


barrier, canvas cloth, mechanical protection, forming to all fittings, test holes,
access panel and the like, all complete in accordance with the Drawings and
Specifications .

Supply & Return air duct insulation

A SAD/RAD-Thermal insulation 25 mm thick m2 3,832 101 387,032

Fresh air duct insulation

B FAD-Thermal insulation 25 mm thick m2 1,094 101 110,494

Exhaust air duct insulation

C EAD-Thermal insulation 25 mm thick m2 344 101 34,744

D Acoustic liner Insulation 25mm thick item 1 25,494 25,494

E Acoustic liner Insulation 25mm thick m2 40 Rate only

Kitchen extract duct insulation

F KED-Thermal insulation 50 mm thick m ft2 10,017 12 120,204

To Collection 677,968
B16/30
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Air Handling Unit

Supply, installation, testing and commissioning of Chilled water air handling


units with vibration isolators, starter panel with controls, valve package,
necessary supports, flexible connector, connection to piping, ducting
connection, thermostat, temperature sensor, humidity sensors, smoke
detectors interfacing with BMS and FACP etc. ensure suitability for working
all in accordance with the Drawings and Specifications.

A Ref. HM-2, HM-9, HM-12, HM-18, HM-19, HM-20, HM-23, HM-25 ; total
cooling capacity 18.17 kw no. 12 16,300 195,600

B Ref. HM-22; total cooling capacity 35.45 kw no. 2 27,500 55,000

C Ref. HM-10; total cooling capacity 50.10 kw no. 25 34,100 852,500

D Ref. HM-11; total cooling capacity 69.70 kw no. 4 44,600 178,400

E Ref. HM-21; total cooling capacity 46.88 kw no. 2 34,500 69,000

F Ref. HM-26; total cooling capacity 24.70 kw no. 5 19,300 96,500

G Ref. HM-27; total cooling capacity 21.70 kw no. 3 15,000 45,000

To Collection 1,492,000
B16/31
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Fresh Air Handling Unit

Supply, installation, testing and commissioning of all Fresh Air Handling


Units ( with heat recovery wheel and heat pipe MERV 13 Filter wherever
applicable) with vibration isolators with suitable foundation, timer controlled
starter panel with controls, necessary supports, connection to piping with
necessary valve packages, flexible duct connector, thermostat, temperature
sensor, humidity sensors, smoke detectors, electrical/control cabling,
interfacing with BMS and FACP all complete in accordance with the
Drawings and Specifications.

A Ref. FAHU-25 (WITHOUT HEAT RECOVERY)


no. 1 INCLUDED IN MALL

To Collection 0
B16/32
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Fan Coil Unit

Supply, installation, testing and commissioning of Chilled water fan coil units
with vibration isolators, flexible duct connector, valve package, starter panel
with controls, necessary supports, connection to piping, ducting connection,
thermostat, temperature sensor, humidity sensors, interfacing with BMS etc.
ensure suitability for working; all in accordance with the Drawings and
Specifications.

Ducted Fan Coil Unit

A Ref. HM-1, HM-6, HM-8; air flow rate 391.76 L/s no. 3 3,900 11,700
B Ref. HM-3, HM-13, HM-14, HM-15, HM-28; air flow rate 627.26 L/s no. 5 5,000 25,000
C Ref. HM-4 ; air flow rate 505.04 L/s no. 1 4,400 4,400
D Ref. HM-5, HM-7, HM-24; air flow rate 835.44 L/s no. 3 5,700 17,100

HM-26 INCLUDED
E Ref. HM-16, HM-26; air flow rate 788.24 L/s no. 6 IN B16/13 ITEM F
F Ref. HM-27A; air flow rate 906.24 L/s no. 1 5,700 5,700
HM-27 INCLUDED
G Ref. HM-27, HM-27B; air flow rate 792.96 L/s no. 4 IN B16/13 ITEM G

Decorative Fan Coil Unit

H Ref. HM-17; air flow rate 254.88 L/s no. 1 4,900 4,900

To Collection 68,800
B16/33
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

FANS

Supply, installation, testing and commissioning of Extract fan with vibration


isolators, extract louvers, necessary supports, starter panel, monitoring panel,
control switch, hangers and fittings, connection to ducting), interfacing with
BMS etc. as per Specifications and Drawings (Cont'd)

Kitchen Exhaust Fan schedule


A Ref. KEH-1; air flow rate 2000 cfm no. 1 7,686 7,686
B Ref. KEH-2, KEH-8; air flow rate 1800 cfm no. 2 7,013 14,026
C Ref. KEH-3 no. 1 7,397 7,397
D Ref. KEH-4, KEH-10; air flow rate 1200 cfm no. 2 6,725 13,450
E Ref. KEH-5; air flow rate 1400 cfm no. 1 7,205 7,205
F Ref. KEH-6; air flow rate 2800 cfm no. 1 7,013 7,013
G Ref. KEH-7; air flow rate 800 cfm no. 1 6,245 6,245
H Ref. KEH-9; air flow rate 2600 cfm no. 1 6,149 6,149
J Ref. KEH-11; air flow rate 3200 cfm no. 1 DELETED
K Ref. KEH-12; air flow rate 5000 cfm no. 1 DELETED

To Collection 69,171
B16/34
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

FANS (Cont'd)

Supply, installation, testing and commissioning of Make up fan with vibration


isolators, extract louvers, necessary supports, starter panel with controls,
wirings, hangers and fittings, connection to ducting), interfacing with BMS
etc. as per Specifications and Drawings.

Make-up fan schedule (1 Duty + 1 Stand-by)

A Ref. MAF-7, MAF-8, MAF-9, MAF-10 MAF-11; air flow rate 29047 cfm set 5

B Ref. MAF-12, MAF-13; air flow rate 22025 cfm set 2

C Ref. MAF-24; air flow rate 5550 cfm (1 DUTY FAN) set 1

Supply, installation testing and commissioning of smoke extract fan with


vibration isolators, extract louvers, necessary supports, starter panel with
controls, wirings, hangers and fittings, flexible connectors, connection to INCLUDED IN MALL
ducting (Fire rated), interfacing with BMS etc. per Specifications and
Drawings.

Smoke Fans schedule (1 Duty + 1 Stand-by)

D Ref. SE-66, SE-67, SE-68; SE-69, SE-70, SE-71, SE-72 air flow rate 30045
cfm no. 7

To Collection 0
B16/35
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators 2.


Mechanical contractor shall include the entire balance works for connecting
A to their mechanical equipment's. 3. By this way, Included in Electrical
mechanical contractor to supply, installation etc. required cables, wires,
containments like cable tray, supports including termination. item

WORK INCIDENTAL TO AIR CONDITIONING installation

Builders work

BY MAIN
CONTRACTOR
B Allow for making holes ,mortices,chases and the like item
Refer to Scope of
Matrix item 1

C Allow for supports, including fixings, anchors and anti-vibration devices . item INCLUDED

D Allow for providing sleeves item Included

BY MAIN
CONTRACTOR
E Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

Protection

F Allow for protection of work in this section item Included

To Collection 0
B16/36
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Sundries

Allow for all identification labels including plates, charts and identification of
A item Included
plant, equipment, cable, switches and colour coding.

Allow for tools and spares, which shall include loose keys and consumable
B item Included
spares.

Allow for Third party witnessing, testing and commissioning, which shall
wild air is optional
C include operating complete INSTALLATIONS, supply of wild air as per item
price
specification .

Allow for documents, which shall include shop Drawings, as built Drawings,
D item Included
operating instructions and maintenance manual as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


E item Included
parts of each piece of equipment.

F Allow for protective painting item INCLUDED

Included as
G Allow for provision of samples item
Specifications

To Collection 0
B16/37
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ADDITIONAL ITEMS

A The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
-
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B16/38
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM

FOR HYPERMARKET (Cont'd)

DRAINAGE INSTALLATIONS

Include Supply, installation and testing & commissioning of all equipment's,


pipes, fixture, fittings of the drainage system in accordance with the
Drawings, Specifications, approval of Engineer and all concerned code of
practice and local authority regulations.

Supply, installation, testing and commissioning of Soil & Waste Pipe work
(UPVC) (Above Ground), pipes and fittings, including all supports,
accessories, rodding eyes, coordination with authority for connection as
deemed necessary in line with regulations, Drawings and Specifications .

Soil / waste pipes installation

A WP 32 mm dia m 30 49 1,470

B WP 40 mm dia m 93 58 5,394

C WP 50 mm dia m 18 63 1,134

D WP 75 mm dia m 35 78 2,730

E WP 100 mm dia m 85 92 7,820

F WP 150 mm dia m 793 106 84,058

G SP 100 mm dia m 20 92 1,840

H SP 150 mm dia m 190 106 20,140

J SP 200 mm dia m 85 126 10,710

K Allow for Connections to sanitary ware with pipes item 8,000

L Allow for Water heater drain pipe complete as required. item 3,000

M 75mm Dia. Cold room condensate pipe m 20 97 1,940

To Collection 148,236
B16/39
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Supply, installation, testing and commissioning of HDPE pipe for Kitchen,


pipes and fittings all in accordance with Drawings and Specifications
including all supports, accessories, fittings, fire sealant crossing through wall,
etc., coordination with authority for connection as deemed necessary in line
with regulations, design Drawings and Specifications.

A GTP 75 mm dia m 30 145 4,350

B GTP 150 mm dia m 419 241 100,979

C Grating pipe 150 mm dia m 136 145 19,720

Supply, installation, testing and commissioning, of Vent Pipe work(UPVC),


pipes and fittings, all in accordance with Drawings and Specifications
including all supports, accessories, fittings, fire sealant crossing through wall,
etc., coordination with authority for connection as deemed necessary in line
with regulations, design Drawings and Specifications.

D VP 75 mm dia m 35 78 2,730

E VP 100 mm dia m 650 92 59,800

Supply, installation, testing and commissioning, of Rain water Pipe


work(UPVC), pipes and fittings, all in accordance with Drawings and
Specifications including all supports, accessories, fittings, fire sealant
crossing through wall, etc., coordination with authority for connection as
deemed necessary in line with regulations, design Drawings and
Specifications.

F RWP 100 mm dia m 60 92 5,520

To Collection 193,099
B16/40
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Supply, installation, testing and commissioning of Condensate Drain Pipe


work (UPVC class E) for FCU's and galvanized steel for AHU/FAHU'S, pipes
and fittings with insulation including all supports, accessories, coordination
with authority for connection as deemed necessary in line with regulations ,
Drawings and Specifications.

A CDP 25 mm dia (UPVC class E) m 134 49 6,566

B CDP 32 mm dia (UPVC class E) m 280 58 16,240

C CDP 40 mm dia (Galvanized steel) m 346 73 25,258

D CDP 80 mm dia (Galvanized steel) m 276 87 24,012

E CDP 100 mm dia (Galvanized steel) m 693 126 87,318

ACOUSTIC LAGGING

Allow for Acoustic lagging for Drainage pipework for all horizontal soil,
F waste and rain water pipes in false ceiling areas and shafts complete as per item 95,635
Drawings and Specifications.

To Collection 255,029
B16/41
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Supply, installation, testing and commissioning of associated drainage


works including installation of accessories, fittings, covers, etc., in
connection with the following all as detailed in Drawings & Specifications
complete to meet performance criteria (but not limited to) (Note: All related
Civil works shall be allowed in the civil work bills) as clarified in
Specifications, Drawings coordination with authority for connection as
deemed necessarily in line with regulations, Drawings and Specifications.

A Floor traps no. 44 39 1,716

B Stainless Steel channel grating for preparation area m 28 241 6,748

C SS floor drain with cover no. 44 338 14,872

D Rodding Eye item 11,596

Receive, store, protect and installation Sanitary wares and accessories


including necessary fixings, connectors, pipe extensions, conical nuts,
flexible tubes, final connections, etc., complete as per Drawings and
Specifications.

E Wash basin no. 2 97 194

F Wash basin mixer no. 2 44 88

G Soap dispenser no. 2 25 50

H Water closet including cistern no. 2 97 194

J Toilet roll holder no. 2 25 50

K Robe hook no. 2 5 10

L Shattaf hand spray no. 2 15 30

M Toilet paper dispenser no. 2 44 88

BY MAIN
N Hand dryer no. 2
CONTRACTOR

BY MAIN
P Mirror no. 2
CONTRACTOR

BY MAIN
Q Urinal partition item
CONTRACTOR

To Collection 35,636
B16/42
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators


2. Mechanical contractor shall include the entire balance works for
NOTED, COMPLIED
A connecting to their mechanical equipment's. item
AND INCLUDED
3. By this way, mechanical contractor to supply, installation etc. required
cables, wires, containments like cable tray, supports including termination.

WORK INCIDENTAL TO DRAINAGE installation

BY MAIN
CONTRACTOR
B Allow for making holes ,mortices,chases and the like item
Refer to Scope of
Matrix item 1

C Allow for supports including fixings, anchors and anti-vibration devices item INCLUDED

D Allow for providing sleeves item INCLUDED

BY MAIN
CONTRACTOR
E Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

To Collection -
B16/43
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

Sundries

Allow for supports, including fixings, anchors, insulating blocks and anti-
A item INCLUDED
vibration devices and noise suppression measures

Allow for all identification labels including plates, charts and identification of
B item INCLUDED
plant, equipment, cable, switches and colour coding.

Allow for tools and spares, which shall include loose keys and consumable
C item INCLUDED
stores

Allow for testing and commissioning, which shall include operating complete
D item INCLUDED
INSTALLATIONS

Allow for documents, which shall include shop Drawings, as built Drawings,
E item INCLUDED
operating instructions and maintenance manual as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


F item INCLUDED
parts of each piece of equipment

G Allow for protective painting item INCLUDED

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as CONTRACTOR
H item
per acceptable material system approved by the Engineer. Refer to Scope of
Matrix item 28

J Allow for provision of samples item INCLUDED

To Collection -
B16/44
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B16/45
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM

FOR HYPERMARKET (Cont'd)

DOMESTIC WATER SERVICES

Supply, installation and testing & commissioning of the domestic water


services in accordance with the Drawings, Specifications, approval of
Engineer and all concerned code of practice and local authority regulations.

NORMAL WATER SYSTEM

P.P.R. Pipe

Supply, installation, testing and commissioning of Normal Water piping


(PPR, PN 20), fittings, supports, hangers, identification, pipe expansion
compensator, pipe drops and making good etc. as per Drawings and
Specifications.

A NWS 15 mm dia (PPR) m 28 29 812

B NWS 20 mm dia (PPR) m 240 39 9,360

C NWS 25 mm dia (PPR) m 50 49 2,450

D NWS 32 mm dia (PPR) m 211 58 12,238

E NWS 40 mm dia (PPR) m 43 73 3,139

F NWS 50 mm dia (PPR) m 39 97 3,783

G NWS 65 mm dia (PPR) m 211 174 36,714

To Collection 68,496
B16/46
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM

FOR HYPERMARKET (Cont'd)

DOMESTIC WATER SERVICES

HOT WATER SYSTEM

P.P.R. Pipe

Supply, installation, testing and commissioning of Hot Water piping (PPR,


PN 20), fittings, supports, hangers, identification, pipe expansion
compensator, pipe drops and making good etc. as per Drawings and
Specifications.

A HWS&R 20 mm dia (PPR) m 87 39 3,393

B HWS&R 25 mm dia (PPR) m 70 49 3,430

C HWS&R 32 mm dia (PPR) m 73 N/A

D Connection to Sanitary wares/sinks etc. item 3,453

Pex Pipe

PEX pipe with PVC box, elbow, adapter, all necessary fittings, fixings and
accessories, all complete in accordance with Drawings and Specifications.

E 15 mm dia. with conduit m 12 16 192

To Collection 10,468
B16/47
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

INSULATION

Supply, installation, testing and commissioning of elastomeric foam


insulation on pipework complete as per Drawings and Specifications.

A HWS&R 20 mm dia (PPR) m 87 8 696

B HWS&R 25 mm dia (PPR) m 55 10 550

C HWS&R 32 mm dia (PPR) m 58 N/A

To Collection 1,246
B16/48
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ACCESSORIES

Supply, installation, testing and commissioning of various piping accessories


including support, fixing, identification, access panels for satisfactory
functioning of all systems in accordance with authority requirement,
Drawings and Specifications.

Isolation valve

A IV 15 mm dia no. 7 116 812

B IV 20 mm dia no. 11 145 1,595

C IV 25 mm dia no. 7 179 1,253

D IV 32 mm dia no. 4 212 848

Pressure reducing valve

E PRV 50 mm dia no. 1 771 771

F PRV station on 32 mm dia line no. 1 771 771

G Water Hammer Arrestor no. 24 145 3,480

H Bib Taps with fittings no. 7 39 273

J Angle valve for sanitary ware no. 6 39 234

K BMS compatible water meter no. 1 ONLY INSTALLATION


INCLUDED
L Automatic air vent with isolating valve 1" dia no. 2 145 290

To Collection 10,327
B16/49
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

EQUIPMENT

Supply, installation, testing and commissioning of hot water heater including


all pipe work, interconnections, level indicators, wirings, control switch,
mountings, valves, conduits, interlocks, flexible connections, etc. complete as
per Specifications and Drawings.

A Water Heater, 50 Lit with Safety Valve no. 5 482 2,410

B Water Heater, 80 Lit with Safety Valve no. 7 579 4,053

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators


2. Mechanical contractor shall include the entire balance works for
NOTED, COMPLIED
C connecting to their mechanical equipment's. item
AND INCLUDED
3. By this way, mechanical contractor to supply, installation etc. required
cables, wires, containments like cable tray, supports including termination.

WORK INCIDENTAL TO WATER SUPPLY installation

BY MAIN
Allow for making holes ,mortices,chases and the like and making good CONTRACTOR
D item
finishing . Refer to Scope of
Matrix item 1

E Allow for supports, including fixings, anchors and anti-vibration devices item INCLUDED

F Allow for providing sleeves item INCLUDED

BY MAIN
CONTRACTOR
G Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

H Coordination with other engineering INSTALLATIONS item INCLUDED

To Collection 6,463
B16/50
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

Sundries

Allow for all identification labels including plates, charts and identification of
A item INCLUDED
plant, equipment, cable, switches and colour coding.

Allow for tools and spares, which shall include loose keys and consumable
B item INCLUDED
spares

Allow for testing and commissioning, which shall include operating complete
C item INCLUDED
INSTALLATIONS

Allow for documents, which shall include shop Drawings, as built Drawings,
D item INCLUDED
operating instructions and maintenance manuals as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


E item INCLUDED
parts of each piece of equipment

Allow for protective painting to mechanical engineering systems including


F item INCLUDED
cleaning and polishing exposed surfaces .

Any external Plumbing services and works in respect of connection to main


ONLY CONNECTION INCLUDED
G incoming services (tie-ins) outside the plot limits including all associated item
WITHIN PLOT LIMITS
civil works.

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as CONTRACTOR
H item
per acceptable material system approved by the Engineer. Refer to Scope of
Matrix item 28

J Allow for Domestic water piping sterilization by application of Chlorine. item INCLUDED

K Allow for provision of samples item INCLUDED

To Collection -
B16/51
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B16/52
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)


HYPERMARKET AND DEPARTMENT STORE

4. FIRE FIGHTING SYSTEM

FOR HYPERMARKET

Supply, installation, testing & commissioning of the fire fighting system in


accordance with the Drawings, Specifications, approved authority Drawings,
relevant NFPA standards including necessary coordination with other services
and in compliance to authority regulations

FIRE FIGHTING PIPE WORK

Fire fighting pipe ERW AS PER FINAL AGREEMENT work in


conformity with NFPA requirements including all necessary supports, fittings
threaded and grooved, fixings and accessories, expansion joints, pipe
expansion coupler, painting, sleeves complete; all in accordance with
Drawings and Specifications and Authority requirements.

A Pipe 25 mm dia m 219 58 12,702

B Pipe 32 mm dia m 721 66 47,586

C Pipe 40 mm dia m 651 89 57,939

D Pipe 50 mm dia m 510 122 62,220

E Pipe 65 mm dia m 125 203 25,375

F Pipe 80 mm dia m 223 244 54,412

G Pipe 100 mm dia m 105 284 29,820

H Pipe 150 mm dia m 175 405 70,875

J Pipe 200 mm dia m 113 486 54,918

To Collection 415,847
B16/53
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)


MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4.FIRE FIGHTING SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ACCESSORIES

Supply installation testing and commissioning of sprinkler heads including


fittings and accessories required for completion of work all in accordance
with the authority regulations, Drawings and Specifications (UL listed / FM
approved).

A Upright Sprinkler Head no. 848 53 44,944

B Concealed Pendent Sprinkler Head no. 900 58 52,200

C Side Extended Sprinkler Head no. 14 63 882

D Special Sprinklers no. 29 78 2,262

Supply installation, testing and commissioning of Fire hose cabinet (Recessed


SS mirror finish) with door including 1 no 25 mm x30 m automatic fire hose
rack, 65 mm dia landing valve with built in pressure reducing valve, 1 no 25
mm Lock shield valve, 1 no 25 mm PRV & related accessories i.e. 6.0 kg
CO2 fire extinguisher, 5.0 kg Dry powder fire extinguisher, 65mm dia. hose
and accessories required for completion of the work ,fixing in position as
listed in line with authority regulations, relevant NFPA standards, Drawings
and Specifications.

E FHC cabinets (Recessed type) no. 7 5,781 40,467

To Collection 140,755
B16/54
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ACCESSORIES (Cont'd)

Supply, installation, testing and commissioning of valves associated with the


fire fighting system, pipework complete; all in accordance with Drawings and
Specifications. (Cont'd)

Zone control valve assembly (UL Listed/FM approved) , including Butterfly


valve, Water Flow Switch, Test valve & Drain Valve, sight glass, with all
necessary fittings and accessories required for completion of work ,and to be
interfaced with FACP complete all as per Drawings and Specifications.
(Cont'd)

A ZCV 150 mm dia no. 6 4,336 26,016

B ZCV 200 mm dia no. 1 4,818 4,818

To Collection 30,834
B16/55
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

EQUIPMENT

FIRE EXTINGUISHERS

Supply, installation, testing and commissioning of fire extinguishers (UL


listed / FM approved) independently mounted including brackets ,supports
,instruction signs in accordance with the authority regulations, Specifications
and Drawings to the satisfaction of the Engineer.

A 6 Kg dry powder extinguisher no. 19 290 5,510

B 5.0 kg CO2 fire extinguisher no. 19 386 7,334

C Automatic fire extinguisher no. 1 193 193

D Fire Blankets no. 6 145 870

To Collection 13,907
B16/56
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

FIRE FM 200 system

Supply, installation, testing & commissioning including room integrity test of


FM 200 system including cylinder racks, concrete reinforced base with
vibration isolator(if required ),filled with gas capacities as per the floor area
requirement ,pipework ,valves,nozzles,control panels wiring interfaced
FACP for following listed areas complete; all complete in accordance with
Drawings, Specifications and authority regulation and approval.(smoke and
heat detector measured elsewhere ) (UL listed / FM Approved)

A Clean agent system @ Electrical room at Ground floor (Area 24m2) item 1 77,080 77,080

B Clean agent system @ Electrical room at Ground floor (Area 9.85m2) item 1 67,746 67,746

C Clean agent system @ Telephone room at Ground floor (Area 5.65m2) item 1 61,492 61,492

D Clean agent system @ Telephone room at Ground floor (Area 7.49m2) item 1 65,518 65,518

To Collection 271,836
B16/57
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)


MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Kitchen hood fire suppression system

Supply, installation, testing and commissioning of automatic wet chemical


fire suppression system including piping ,detectors , supervised alarm siren,
warning signs, interlocked with the fire alarm system, including dry pendent
sprinklers, complete with control panel including control wiring ,electrical
wiring and connections ,complete in all aspects ready to operate as per DCD
requirement and by a DCD approved Contractor (By Specialist). (UL listed /
FM Approved).

A Rack oven, Hood size: 1800x2000 mm no. 1 24,088 24,088

B Arabic oven, Hood size: 1600x800 mm no. 1 17,343 17,343

C Bake off oven, Hood size: 1400x800 mm no. 1 12,526 12,526

D Tandoor & Arabic grill, Hood size: 4400x1300 mm no. 1 33,155 33,155

E Shawarma, Hood size: 2000x1200 mm no. 1 19,270 19,270

F Chicken grill, Hood size: 1400x1200 mm no. 1 16,380 16,380

G Burner & griddle, Hood size: 4000x1350 mm no. 1 31,796 31,796

H Fryer & Broaster, Hood size: 3000x1200 mm no. 1 26,978 26,978

J Indian & Chinese, Hood size: 4200x1350 mm no. 1 28,905 28,905

K Smart oven, Hood size: 1400x1200 mm no. 1 16,380 16,380

To Collection 226,821
B16/58
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators


2. Mechanical contractor shall include the entire balance works for
NOTED, COMPLIED
A connecting to their mechanical equipment's. item
AND INCLUDED
3. By this way, mechanical contractor to supply, installation etc. required
cables, wires, containments like cable tray, supports including termination.

WORK INCIDENTAL TO FIRE FIGHTING installation

BY MAIN
Allow for making holes ,mortices,chases and the like and making good CONTRACTOR
B item
finishing . Refer to Scope of
Matrix item 1

C Allow for supports, including fixings, anchors and anti-vibration devices item INCLUDED

D Allow for providing sleeves item INCLUDED

BY MAIN
CONTRACTOR
E Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

To Collection -
B16/59
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
B13/34 DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)


Sundries

Allow for third party certificate from authorised company for handing over
A item INCLUDED
the system for the complete mall.

Allow for all identification labels including plates, charts and identification of
B item INCLUDED
plant, equipment, cable, switches and colour coding

Allow for tools and spares, which shall include loose keys and consumable
C item INCLUDED
spares that has to be handed over to client

Allow for testing and commissioning of the complete fire fighting


D INSTALLATIONS which must include operation of complete fire fighting item INCLUDED
system

Allow for testing the complete fire fighting installation in the presence of
E engineer ,repeat test as may be required and leave in perfect order and to the item INCLUDED
satisfaction of the engineer and the local authority

Allow for documents, which shall include submittals, shop Drawings, as built
F item INCLUDED
Drawings, samples operation and maintenance manual as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


G item INCLUDED
parts of each piece of equipment /items /materials

H Allow for protective painting item INCLUDED

Allow for connection to mains including pipework and all necessary


J accessories, complete all in accordance with the drawings, Specifications, as item INCLUDED
per DCD requirements .

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as
CONTRACTOR
K per acceptable material system approved by the Engineer. Fire stopping by item
Refer to Scope of
specialist approved by the Engineer & Client.
Matrix item 28

L Allow for training of client and the contractors item INCLUDED

M Allow for submission of samples item INCLUDED

To Collection -
B16/60
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B16/61
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)


MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM

FOR HYPERMARKET (Cont'd)

Supply, installation , testing and commissioning of LPG Gas pipe work


including fittings, supports, accessories, protection, fire sealant of pipes
through crossing walls etc., complete as listed in line with authority
regulations relevant standards , Specifications and Drawings.

GAS Pipework

Supply and installation of LPG pipework including all necessary pipe


expansion joints, hangers, sleeves, accessories, fittings, support and etc.,
complete; all in accordance with the Drawings, Specifications and as per
NFPA standards

32 mm dia Carbon Steel pipe schedule 80 , LPG filling line up to storage


A m 26 60 1,560
tank

B 20 mm dia copper pipe m 177 50 8,850

C 20 mm dia copper pipe (pipe in pipe) m 65 70 4,550

D 50 mm dia Sch 80 carbon steel pipe m 69 70 4,830

Supply and installation of LPG pipework on roof including all necessary


accessories, etc., complete; all in accordance with the Drawings and
Specifications

E 20 mm dia copper pipe m 151 10 1,510

F 50 mm dia Sch 80 carbon steel pipe m 69 15 1,035

LPG Filling Point Includes

G Protective aluminum box (400x400x200 mm) no. 1 1,000 1,000

H 32 mm dia double check filler valve no. 1 120 120

J 32 mm dia Globe valve no. 1 150 150

K 32 mm dia Safety relief valve no. 1 200 200

L 32 mm dia Ball valve no. 1 65 65

M 32 mm dia Back Check valve no. 1 85 85

To Collection 23,955
B16/62
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)


MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Equipment

Supply, installation, testing and commissioning of LPG storage tanks as per


local standards and engineer’s approval; including all necessary supports,
joints, fixings and fittings accessories etc., all complete in accordance with
the Drawings and Specifications.

A LPG Storage tank (1500 US gallons) no. 1 30,000 30,000

B LPG Storage tank (1000 US gallons) no. 1 25,000 25,000

Pressure reducing & Distribution panel including automatic changeover 10


kg/hr., manifold for 3 cylinders, isolating valves, solenoid valve, pressure
switch, isolating valve for riser, service reserve indicator, etc., complete in
accordance with the Drawings and Specifications.

C Pressure reducing & distribution panel no. 1 5,000 5,000

Supply and installation of the following including all accessories, fittings,


fixtures, etc., complete as per Drawings and Specifications.
D Vaporizer assembly no. 1 2,000 2,000

E Ball valve 32 mm dia no. 2 120 240

F Control panel no. 1 5,000 5,000

G 32 mm dia Safety relief valve no. 2 250 500

H Shut off valve 32 mm dia no. 2 300 600


Note:

LPG pipe sizes and quantities are indicative only. Actual LPG sizes to be NOTED, COMPLIED
J
designed by civil defense approved LPG specialist. AND INCLUDED

To Collection 68,340
B16/63
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

Supply and installation of the following including all accessories, fittings,


fixtures, etc., complete as per Drawings and Specifications.

A Explosion proof gas detector no. 3 600 1,800

B Hydrostatic relief valve 32 mm dia no. 2 250 500

C Back check valve 32 mm dia no. 2 200 400

D Pressure regulator no. 2 500 1,000

E Sounder no. 1 500 500

F Gas leak detector in vertical shaft item 3,105

G Gas leak detector in horizontal shaft item 2,000

H Heat Detector no. 2 1,500 3,000

TANK FENCE

Supply & installation of fence (2000mm H) around the tank with door BY MAIN
J item
complete as per Drawings & Specifications. CONTRACTOR

K Provision of Signages for LPG yard item 2,100

L LPG Tank first fill by the Contractor item 2,100

M Radiographic test for LPG system (only 20%) item 3,200

LPG Electrical INSTALLATIONS

Fireproof cabling for main Gas detection panel (Interface with all solenoid
N item INCLUDED
valves)

P Wiring for Vaporizer with Isolator item INCLUDED

Q Remote Gas monitoring wiring item INCLUDED

R Interface cabling between BMS and LPG item INCLUDED

S Interface cabling between FACP and LPG item INCLUDED

T Gas meter Interface with BMS item INCLUDED

To Collection 19,705
B16/64
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

A Third party testing and commissioning and certificate item INCLUDED

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators 2.


Mechanical contractor shall include the entire balance works for connecting
NOTED, COMPLIED
B to their mechanical equipment's. 3. By this way, item
AND INCLUDED
mechanical contractor to supply, installation etc. required cables, wires,
containments like cable tray, supports etc.,.

WORK INCIDENTAL TO LPG installation

BY MAIN
CONTRACTOR
C Allow for any Builder's work in connection with LPG installation item
Refer to Scope of
Matrix item 1

To Collection -
B16/65
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

Sundries

Allow for supports, including fixings, anchors, insulating blocks and anti-
A item INCLUDED
vibration devices and noise suppression measures

Allow for all identification labels including plates, charts and identification of
B item INCLUDED
plant, equipment, cable, switches and colour coding.

Allow for tools and spares, which shall include loose keys and consumable
C item INCLUDED
spares

Allow for Third party testing and commissioning, which shall include
D item INCLUDED
operating complete INSTALLATIONS

Allow for documents, which shall include shop Drawings, as built Drawings,
E item INCLUDED
operating instructions and maintenance manuals as specified.

Allow for preparing schedule of manufacturers recommended tools and spare


F item INCLUDED
parts of each piece of equipment

G Allow for protective painting item INCLUDED

Any external MEP services and works in respect of connection to main


ONLY CONNECTION INCLUDED
H incoming services (tie-ins) outside the plot limits including all associated item
WITHIN PLOT LIMITS
civil works.

BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as CONTRACTOR
J item
per acceptable material system approved by the Engineer. Refer to Scope of
Matrix item 28

K Allow for samples provision item INCLUDED

To Collection -
B16/66
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM (Cont'd)

FOR HYPERMARKET (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B16/67
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

COLLECTION

FOR HYPER MARKET

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM

Page B16/21 594,403


Page B16/22 427,802
Page B16/23 28,037
Page B16/24 174,337
Page B16/25 16,838
Page B16/26 38,214
Page B16/27 94,252
Page B16/28 713,460
Page B16/29 3,104,718
Page B16/30 677,968
Page B16/31 1,492,000
Page B16/32 0
Page B16/33 68,800
Page B16/34 69,171
Page B16/35 0
Page B16/36 0
Page B16/37 0
Page B16/38 -

TOTAL HVAC (HEATING VENTILATION AND AIR CONDITIONING) SYSTEM 7,500,000


B16/68
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

FOR HYPER MARKET (Cont'd)

2. DRAINAGE SYSTEM

Page B16/39 148,236

Page B16/40 193,099

Page B16/41 255,029

Page B16/42 35,636

Page B16/43 -

Page B16/44 -

Page B16/45 -

TOTAL DRAINAGE SYSTEM 632,000


B16/69
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

FOR HYPER MARKET (Cont'd)

3. WATER SUPPLY SYSTEM

Page B16/46 68,496

Page B16/47 10,468

Page B16/48 1,246

Page B16/49 10,327

Page B16/50 6,463

Page B16/51 -

Page B16/52 -

TOTAL WATER SUPPLY SYSTEM 97,000


B16/70
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

FOR HYPER MARKET (Cont'd)

4. FIRE FIGHTING SYSTEM

Page B16/53 415,847

Page B16/54 140,755

Page B16/55 30,834

Page B16/56 13,907

Page B16/57 271,836

Page B16/58 226,821

Page B16/59 -

Page B16/60 -

Page B16/61 -

1,100,000
B16/71
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

FOR HYPER MARKET (Cont'd)

5. LIQUIFIED PETROLEUM GAS (LPG) SYSTEM

Page B16/62 23,955

Page B16/63 68,340

Page B16/64 19,705

Page B16/65 -

Page B16/66 -

Page B16/67 -

TOTAL FIRE FIGHTING SYSTEM 112,000


B16/72
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

TOTAL FOR HYPERMARKET

HVAC (HEATING VENTILATION AND AIR CONDITIONING) SYSTEM


1 7,500,000

2 DRAINAGE SYSTEM 632,000

3 WATER SUPPLY SYSTEM 97,000

4 FIRE FIGHTING SYSTEM 1,100,000

5 LIQUIFIED PETROLEUM GAS (LPG) SYSTEM 112,000

Carried to Hypermarket Summary 9,441,000


B16/73
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM

FOR DEPARTMENT STORE

Supply, installation and Testing & Commissioning of HVAC system (Heating


Ventilation and Air Conditioning), in accordance with the Drawings,
Specifications, approval of Engineer and all concern code of practice and
local authority regulations

CHILLED WATER installation

CHILLED WATER PIPE WORKS (Supply and Return)

Supply, installation, testing & commissioning of ERW as per final agreement


chilled water and condenser water pipes including all necessary pipe fittings,
supports, hangers, joints, vibration, pipe expansion compensator, isolators
( Spring type) for header pipes, fixings and all necessary fixing accessories, all
complete in accordance with the Drawings and Specifications.

A CHW 3/4 inch dia (20 mm dia) m 22 118 2,596

B CHW 1 inch dia (25 mm dia) m 31 144 4,464


C CHW 1 1/4 inch dia (32 mm dia) m 20 192 3,840
D CHW 1 1/2 inch dia (40 mm dia) m 16 231 3,696

E CHW 2 inch dia (50 mm dia) m 215 284 61,060


F CHW 2 1/2 inch dia (65 mm dia) m 58 445 25,810

G CHW 3 inch dia (80 mm dia) m 73 584 42,632


H CHW 4 inch dia (100 mm dia) m 66 833 54,978
J CHW 5 inch dia (125 mm dia) m 20 1,120 22,400
K CHW 6 inch dia (150 mm dia) m 38 1,460 55,480

L CHW 8 inch dia (200 mm dia) m 62 2,231 138,322

To Collection 415,278
B16/140
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

INSULATION TO PIPE WORKS (Supply and Return)

Supply, installation, testing of chilled water & Condenser water piping


insulation, including adhesive, vapour barrier, canvas cloth for the satisfaction
of the Engineer for the following (but not limited to) all complete in
accordance with the Drawings and Specifications.

A CHW 3/4 inch dia (20 mm dia) m 22 87 1,914

B CHW 1 inch dia (25 mm dia) m 31 106 3,286

C CHW 1 1/4 inch dia (32 mm dia) m 20 140 2,800

D CHW 1 1/2 inch dia (40 mm dia) m 16 164 2,624

E CHW 2 inch dia (50 mm dia) m 215 207 44,505

F CHW 2 1/2 inch dia (65 mm dia) m 58 318 18,444

G CHW 3 inch dia (80 mm dia) m 73 423 30,879

H CHW 4 inch dia (100 mm dia) m 66 596 39,336

J CHW 5 inch dia (125 mm dia) m 20 803 16,060

K CHW 6 inch dia (150 mm dia) m 38 1,048 39,824

L CHW 8 inch dia (200 mm dia) m 62 1,600 99,200

To Collection 298,872
B16/141
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

ACCESSORIES

Supply, installation, testing and commissioning of valves to chilled water

pipes, all complete in accordance with the Drawings and Specifications .

Isolation valve

A IV 1 1/4 inch dia (32 mm dia) no. 2 193 386

B IV 8 inch dia (200 mm dia) no. 1 3,319 3,319

Variable Orifice Double regulation valve (VODRV)

C VODRV 1 1/4 inch dia (32 mm dia) no. 1 351 351

D VODRV 8 inch dia (200 mm dia) no. 1 8,382 8,382

E Automatic air vent 25 mm dia with Isolating valve no. 2 236 472

To Collection 12,910
B16/142
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's
BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)


Air outlets
Supply, installation, testing and commissioning of Supply and
return air outlets for air conditioning, fresh air Supply, fresh air
return and extract air, lobby pressurization ducts and smoke
extract with complete duct connection and necessary ancillaries,
access doors etc. in accordance Drawings and Specifications.

Supply air diffuser


A SAD 300X300 mm no. 9 145 1,305
B RAD 300X300 mm no. 9 106 954
Return air diffuser
C SAG 750X200 mm no. 5 173 865
D RAG 750X200 mm no. 5 125 625
Supply round diffuser
E Supply round diffuser 355 mm dia no. 300 550 165,000
Return round diffuser
F Return round diffuser 355 mm dia no. 300 450 135,000

Exhaust air diffuser

G Ex Diffuser 225x225 mm no. 20 77 1,540


H Ex Diffuser 300x300 mm no. 4 106 424
J Ex Diffuser 375x375 mm no. 1 193 193
K Exhaust air round diffuser 355 mm dia no. 34 450 15,300
Fresh air diffuser

L Fresh air diffuser 300X300 mm no. 1 145 145


M Fresh air diffuser 375X375 mm no. 1 193 193
N Fresh air round diffuser 355 mm dia no. 34 550 18,700

To Collection 340,244
B16/143
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)


Supply, installation, testing and commissioning of various ducting accessories
including support, fixing , identification, access panels, flexible duct
connector, actuator, interface with various other systems i.e. fire alarm, BMS
etc. for satisfactory functioning of all systems in accordance with the
Drawings and Specifications .
Fire damper
A FD 300X150 mm no. 8 202 1,616
B FD 300X200 mm no. 6 207 1,242
C FD 300X250 mm no. 2 217 434
D FD 400X250 mm no. 1 226 226
E FD 500X250 mm no. 1 236 236
Volume control damper
F VCD 150X100 mm no. 2 92 184
G VCD 300X200 mm no. 3 125 375
H VCD 300X250 mm no. 34 145 4,930
J VCD 400X200 mm no. 34 169 5,746
Sensors
K CO2 Sensor no. 15 1,057 15,855

Supply, installation, testing and commissioning of louvers including all


necessary accessories, ancillaries and joints to duct work complete as per
Drawings and Specifications.
L Bell mouth with SS wire mesh 1500X900 mm no. 4 654 2,616
M Bell mouth with SS wire mesh 1600X800 mm no. 2 654 1,308
N Bell mouth with SS wire mesh 1700X900 mm no. 7 707 4,949

To Collection 39,717
B16/144
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

Supply, installation, testing and commissioning of various ducting accessories


including support, fixing , identification, access panels, flexible duct
connection, actuator, interface with various other systems i.e. fire alarm etc.
for satisfactory functioning of all systems in accordance with the Drawings
and Specifications (Cont'd) .

NON RETURN DAMPER

A NRD 1700X900 mm no. 3 423 1,269

B NRD 1600X800 mm no. 4 481 1,924

To Collection 3,193
B16/145
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

Duct Work
Supply, fabricate and installation GI/fire rated sheet metal rectangular
ductwork complete with plenum box, turning vanes, cross jointing, jointing
materials and sealants, access panels, demountable sections, brackets, hangers,
supports, etc., as per SMACNA standards, all complete in accordance with the
Drawings and Specifications.
Supply & Return air duct
A SAD/RAD, 26 gauge (GI) KG 22 Rate Only
B SAD/RAD, 24 gauge (GI) KG 17,777 22 391,094
C SAD/RAD, 22 gauge (GI) KG 12,292 22 270,424
Fresh air duct
D FAD, 26 gauge (GI) KG 165 22 3,630
E FAD, 24 gauge (GI) KG 3,816 22 83,952
F FAD, 22 gauge (GI) KG 3,246 22 71,412
Exhaust air duct
G EAD, 26 gauge (GI) KG 63 22 1,386
H EAD, 24 gauge (GI) KG 2,897 22 63,734
J EAD, 22 gauge (GI) KG 4,720 22 103,840
K EAD, 20 gauge (GI) KG 266 22 5,852
Fire rated duct
L Fire rated ductwork for smoke extract & smoke make up KG 11,898 36 428,328

To Collection 1,423,652
B16/146
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

Insulation to Duct Work

Fiber Glass thermal insulation to ductwork including adhesive, vapor barrier,


canvas cloth, mechanical protection, forming to all fittings, test holes, access
panel and the like, all complete in accordance with the Drawings and
Specifications .

Supply & Return air duct insulation

A SAD/RAD-Thermal insulation 25 mm thick m2 2,597 101 262,297

Fresh air duct insulation

B FAD-Thermal insulation 25 mm thick m2 1,236 101 124,836

Exhaust air duct insulation

C EAD-Thermal insulation 25 mm thick m2 1,292 101 130,492

D Acoustic liner Insulation 25mm thick item 1 17,209 17,209

E Acoustic liner Insulation 25mm thick m2 44 Rate only

To Collection 534,834
B16/147
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

EQUIPMENT

Air Handling Unit

Supply, installation, testing and commissioning of Chilled water air handling


units with vibration isolators, starter panel with controls, valve package,
necessary supports, flexible connector, connection to piping, ducting
connection, thermostat, temperature sensor, humidity sensors, smoke detectors
interfacing with BMS and FACP etc. ensure suitability for working all in
accordance with the Drawings and Specifications.

A Ref. A-105; total cooling capacity 58.40 kw no. 30 27,600 828,000

B Ref. A-105E, ; total cooling capacity 35.45 kw no. 3 19,200 57,600

To Collection 885,600
B16/148
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

Fresh Air Handling Unit

Supply, installation, testing and commissioning of all Fresh Air Handling


Units ( with heat recovery wheel and heat pipe MERV 13 Filter wherever
applicable) with vibration isolators with suitable foundation, timer controlled
starter panel with controls, necessary supports, connection to piping with
necessary valve packages, ducting connection, thermostat, temperature sensor,
humidity sensors, smoke detectors, electrical/control cabling, interfacing with
BMS and FACP all complete in accordance with the Drawings and
Specifications.

A INCLUDED IN
Ref. FAHU-20 (WITH HEAT RECOVERY) no. 1
MALL

To Collection 0
B16/149
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

Fan Coil Unit

Supply, installation, testing and commissioning of Chilled water fan coil units
with vibration isolators, valve package, starter panel with controls, necessary
supports, connection to piping, ducting connection, thermostat, temperature
sensor, humidity sensors, interfacing with BMS etc. ensure suitability for
working; all in accordance with the Drawings and Specifications.

Ducted Fan Coil Unit

A Ref. 105A, A-114C; air flow rate 708 L/s no. 2 5,300 10,600

B Ref. A-105B; air flow rate 627.26 L/s no. 1 5,000 5,000
C Ref. A-105C, A-105D; air flow rate 292.64 L/s no. 2 3,800 7,600
D Ref. A-114A, A-114B; air flow rate 505.04 L/s no. 2 4,700 9,400
E Ref. A-114D; air flow rate 906.24 L/s no. 1 6,100 6,100
FANS

Supply, installation, testing and commissioning of Extract fan with vibration


isolators, extract louvers, necessary supports, starter panel, monitoring panel,
control switch including wiring, hangers and fittings, connection to ducting),
interfacing with BMS etc. as per Specifications and Drawings (Cont'd)

Kitchen Extract fan schedule (First Floor) - Inline Ducted

G Ref. FF KEF-38; air flow rate 200 cfm no. 1 7,000 7,000

To Collection 45,700
B16/150
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

A 1. Electrical contractor scope of work is limited up to the isolators.


2. Mechanical contractor shall include the entire balance works for connecting

to their mechanical equipment.


3. By this way, mechanical contractor to supply, installation etc. required Included in Electrical

cables, wires, containments like cable tray, supports including termination.


item

WORK INCIDENTAL TO AIR CONDITIONING installation

BY MAIN
CONTRACTOR
B Allow for making holes ,mortices, chases and the like item
Refer to Scope of
Matrix item 1

C
Allow for supports , including fixings, anchors and anti-vibration devices . item INCLUDED

D Allow for providing sleeves item Included

BY MAIN
CONTRACTOR
E Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

Protection

F Allow for protection of work in this section item Included

To Collection 0
B16/151
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

Sundries

A
Allow for all identification labels including plates, charts and identification of
Included
plant, equipment, cable, switches and colour coding.
item

Allow for tools and spares, which shall include loose keys and consumable
B Included
spares. item

C Allow for Third party witnessing, testing and commissioning, which shall
wild air is optional
include operating complete INSTALLATIONS, supply of wild air as per
price
specification . item

Allow for documents, which shall include shop Drawings, as built Drawings,
D Included
operating instructions and maintenance manual as specified.
item

Allow for preparing schedule of manufacturers recommended tools and spare


E Included
parts of each piece of equipment. item

F Allow for protective painting item Included

To Collection 0
B16/152
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

ADDITIONAL ITEMS

A
The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.
-

To Collection -
B16/153
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM

FOR DEPARTMENT STORE (Cont'd)

DRAINAGE INSTALLATIONS

Include Supply, installation and testing & commissioning of all equipment's,


pipes, fixture, fittings of the drainage system in accordance with the
Drawings, Specifications, approval of Engineer and all concerned code of
practice and local authority regulations

Supply, installation, testing and commissioning of Soil & Waste Pipe work
(UPVC) (Above Ground), pipes and fittings, all in accordance with Drawings
and Specifications including all supports, accessories, fittings, rodding eyes,
fire sealant crossing through wall, etc., coordination with authority for
connection as deemed necessary in line with regulations, design Drawings
and Specifications .

A WP 32 mm dia m 13 49 637

B WP 75 mm dia m 8 78 624

C WP 100 mm dia m 47 92 4,324

D WP 150 mm dia m 68 106 7,208

E SP 40 mm dia m 1 58 58

F SP 100 mm dia m 16 92 1,472

G SP 150 mm dia m 11 106 1,166

To Collection 15,489
B16/154
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

Supply, installation, testing and commissioning, of Vent Pipe work(UPVC),


pipes and fittings, all in accordance with Drawings and Specifications
including all supports, accessories, fittings, fire sealant crossing through wall,
etc., coordination with authority for connection as deemed necessary in line
with regulations, design Drawings and Specifications .

Vent Pipes

A VP 100 mm dia m 98 92 9,016

Supply, installation, testing and commissioning of Condensate Drain Pipe


work (PVC), pipes and fittings with insulation all in accordance with
Drawings and Specifications including all supports, accessories, fittings, fire
sealant crossing through wall etc., coordination with authority for connection
as deemed necessary in line with regulations , design Drawings and
Specifications.

B CDP 32 mm dia m 110 58 6,380

C CDP 40 mm dia m 214 73 15,622

ACOUSTIC LAGGING

D
Allow for Acoustic lagging for Drainage pipework for all horizontal soil,
waste and rain water pipes in false ceiling areas and pipes running inside item 30,000
shafts complete as per Drawings and Specifications.

To Collection 61,018
B16/155
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

Supply, installation, testing and commissioning of associated drainage works


including installation of accessories, fittings, covers, etc., in connection with
the following all as detailed in Drawings & Specifications complete to meet
performance criteria (but not limited to) (Note: All related Civil works shall be
allowed in the civil work bills) as clarified in Specifications, Drawings
coordination with authority for connection as deemed necessarily in line with
regulations, design Drawings and Specifications.

A Floor traps no. 24 39 936

B SS floor drain with cover no. 24 338 8,112

C Rodding Eye item 9,145

Receive, store, protect and installation Sanitary wares and accessories


including necessary fixings, connectors, pipe extensions, angle valves, conical
nuts, flexible tubes, final connections, etc., complete as per Drawings and
Specifications.

D Wash basin no. 9 97 873

E Wash basin mixer no. 9 44 396

F Soap dispenser no. 9 25 225

G Water closet including concealed cistern no. 8 97 776

H Toilet roll holder no. 8 25 200

J Robe hook no. 8 5 40

K Urinal no. 6 97 582

L Shattaf hand spray no. 8 15 120

M Toilet paper dispenser no. 2 44 88

BY MAIN
N Hand dryer no. 2
CONTRACTOR

BY MAIN
P Mirror item
CONTRACTOR

BY MAIN
Q Urinal partition item
CONTRACTOR

To Collection 21,493
B16/156
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators


2. Mechanical contractor shall include the entire balance works for connecting NOTED,
A to their mechanical equipment's. COMPLIED AND
3. By this way, mechanical contractor to supply, installation etc. required INCLUDED
cables, wires, containments like cable tray, supports including termination.

item

WORK INCIDENTAL TO DRAINAGE installation

BY MAIN
B Allow for making holes ,mortices, chases and the like item CONTRACTOR
Refer to Scope of
Matrix item 1

C Allow for supports including fixings, anchors, and anti-vibration devices item INCLUDED

D Allow for providing sleeves item INCLUDED

BY MAIN
CONTRACTOR
E Allow for providing insulation and waterproofing for holes in slabs and walls item
Refer to Scope of
Matrix item 2

To Collection -
B16/157
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

Sundries

Allow for supports, including fixings, anchors, insulating blocks and anti-
A item INCLUDED
vibration devices and noise suppression measures

Allow for all identification labels including plates, charts and identification of
B item INCLUDED
plant, equipment, cable, switches and colour coding

Allow for tools and spares, which shall include loose keys and consumable
C item INCLUDED
stores

Allow for testing and commissioning, which shall include operating complete
D item INCLUDED
INSTALLATIONS

Allow for documents, which shall include shop Drawings, as built Drawings,
E item INCLUDED
operating instructions and maintenance manual as specified

Allow for preparing schedule of manufacturers recommended tools and spare


F item INCLUDED
parts of each piece of equipment

G Allow for protective painting item INCLUDED

To Collection -
B16/158
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

2. DRAINAGE SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B16/159
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (cont'd)

HYPERMARKET AND DEPARTMENT STORE

3. WATER SUPPLY SYSTEM

FOR DEPARTMENT STORE (Cont'd)

DOMESTIC WATER SERVICES

Supply, installation and testing & commissioning of the domestic water


services in accordance with the Drawings, Specifications, approval of
Engineer and all concerned code of practice and local authority regulations

NORMAL WATER SYSTEM

P.P.R. Pipe

Supply, installation, testing and commissioning of Normal Water piping (PPR,


PN 20), fittings, pipe expansion compensator, supports, hangers,
identification, pipe drops and making good etc. as per Drawings and
Specifications
A NWS 20 mm dia (PPR) m 38 39 1482

B NWS 25 mm dia (PPR) m 20 49 980

D NWS 32 mm dia (PPR) m 165 58 9570

E NWS 40 mm dia (PPR) m 31 73 2263

F NWS 50 mm dia (PPR) m 28 97 2716

G NWS 65 mm dia (PPR) m 80 174 13920

To Collection 30,931
B16/160
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

DOMESTIC WATER SERVICES

HOT WATER SYSTEM

P.P.R. Pipe

Supply, installation, testing and commissioning of Hot Water piping (PPR, PN


20), fittings, pipe expansion compensator, supports, hangers, identification,
pipe drops and making good etc. as per Drawings and Specifications.

A HWS&R 20 mm dia (PPR) m 95 39 3,705

B HWS&R 25 mm dia (PPR) m 36 49 1,764

C Connection to Sanitary wares/sinks etc. item 885

Pex Pipe

PEX pipe with PVC box, elbow, adapter, all necessary fittings, fixings and
accessories, all complete in accordance with Drawings and Specifications.

D 15 mm dia. with conduit m 130 16 2,080

To Collection 8,434
B16/161
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

HOT WATER SYSTEM

P.P.R. Pipe

Supply, installation, testing and commissioning of Hot Water piping (PPR, PN


20), fittings, supports, hangers, identification, pipe drops and making good etc.
as per Drawings and Specifications.

A HWS&R 20 mm dia (PPR) m 95 INCLUDED IN


PAGE B16/161
B HWS&R 25 mm dia (PPR) m 36 INCLUDED IN
PAGE B16/161

INSULATION

Supply, installation, testing and commissioning of elastomeric foam insulation


on pipework complete as per Drawings and Specifications.

C HWS&R 20 mm dia (PPR) m 95 8 760

D HWS&R 25 mm dia (PPR) m 36 10 360

To Collection 1,120
B16/162
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

ACCESSORIES

Supply, installation, testing and commissioning of various piping accessories


including support, fixing, identification, access panels for satisfactory
functioning of all systems in accordance with authority requirement, Drawings
and Specifications.

Isolation valve

A IV 20 mm dia no. 5 145 725

B IV 40 mm dia no. 4 270 1,080

Pressure reducing valve

C PRV 40 mm dia no. 1 482 482

D Water Hammer Arrestor no. 16 145 2,320

E Angle valve for sanitary ware no. 26 39 1,014

F Automatic air vent with isolating valve 1" dia no. 2 145 290

To Collection 5,911
B16/163
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

EQUIPMENT

Supply, installation, testing and commissioning of hot water heater including


all pipe work, interconnections, level indicators, wirings, control switch,
mountings, valves, conduits, interlocks, flexible connections, etc. complete as
per Specifications and Drawings.

A Water Heater, 50 Lit with Safety Valve no. 3 482 1,446

B Water Heater, 80 Lit with Safety Valve no. 2 579 1,158

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

C 1. Electrical contractor scope of work is limited up to the isolators 2.


Mechanical contractor shall include the entire balance works for connecting to NOTED,
their mechanical equipment's. 3. By this COMPLIED AND
way, mechanical contractor to supply, installation etc. required cables, wires, INCLUDED
containments like cable tray, supports including termination. item

WORK INCIDENTAL TO WATER SUPPLY installation

BY MAIN
CONTRACTOR
D Allow for any Builder's work in connection with Water Supply installation item
Refer to Scope of
Matrix item 1

To Collection 2,604
B16/164
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

3. WATER SUPPLY SYSTEM (Cont'd)

Sundries

Allow for supports, including fixings, anchors, insulating blocks and anti-
A item
vibration devices and noise suppression measures INCLUDED

Allow for all identification labels including plates, charts and identification of
B item
plant, equipment, cable, switches and colour coding INCLUDED

Allow for tools and spares, which shall include loose keys and consumable
C item
stores INCLUDED

Allow for testing and commissioning, which shall include operating complete
D item
INSTALLATIONS INCLUDED

Allow for documents, which shall include shop Drawings, as built Drawings,
E item
operating instructions and maintenance manuals as specified. INCLUDED

Allow for preparing schedule of manufacturers recommended tools and spare


F item
parts of each piece of equipment INCLUDED

G Allow for protective painting item INCLUDED

H Allow for Domestic water piping sterilization by application of Chlorine. item INCLUDED

J Allow for provision of samples item INCLUDED

To Collection -
B16/165
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

ADDITIONAL ITEMS

A The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B16/166
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM

FOR DEPARTMENT STORE

Supply, installation, testing & commissioning of the fire fighting system in


accordance with the design Drawings, Specifications, approved authority
Drawings, relevant NFPA standards including necessary coordination with
other services compliances to authority regulations and Drawings

FIRE FIGHTING PIPE WORK

Fire fighting pipe ERW AS PER FINAL AGREEMENT work in conformity


with NFPA requirements including all necessary supports, fittings threaded
and grooved, fixings and accessories, expansion joints, pipe expansion
compensator, painting, sleeves complete; all in accordance with Drawings and
Specifications and Authority requirements.

A Pipe 25 mm dia m 576 58 33,408

B Pipe 32 mm dia m 7 66 462

C Pipe 40 mm dia m 459 89 40,851

D Pipe 50 mm dia m 453 122 55,266

E Pipe 65 mm dia m 97 203 19,691

F Pipe 80 mm dia m 116 244 28,304

G Pipe 100 mm dia m 83 284 23,572

H Pipe 150 mm dia m 612 405 247,860

To Collection 449,414
B16/167
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

ACCESSORIES

Supply installation testing and commissioning of sprinkler heads including


fittings and accessories required for completion of work all in accordance
with the authority regulations, Drawings and Specifications (UL listed / FM
approved).

A Upright Sprinkler Head no. 596 53 31,588

B Concealed Pendent Sprinkler Head no. 589 58 34,162

C Side Extended Sprinkler Head no. 2 63 126

Supply installation, testing and commissioning of Fire hose cabinet (Recessed


SS mirror finish) with door including 1 no 25 mm x30 m automatic fire hose
reel, 65 mm dia landing valve with built in pressure reducing valve, 1 no 25
mm Lock shield valve, 1 no 25 mm PRV & related accessories i.e. 6.0 kg
CO2 fire extinguisher, 5.0 kg Dry powder fire extinguisher, 65mm dia. hose
and accessories required for completion of the work ,fixing in position as
listed in line with authority regulations, relevant NFPA standards, Drawings
and Specifications.

D FHC cabinets (Recessed type) no. 3 5,781 17,343

To Collection 83,219
B16/168
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

Supply, installation, testing and commissioning of valves associated with the


fire fighting system, pipework complete; all in accordance with Drawings and
Specifications. (Cont'd)

Zone control valve assembly (UL Listed/FM approved) , including Butterfly


valve, Water Flow Switch, Test valve & Drain Valve, sight glass, with all
necessary fittings and accessories required for completion of work ,and to be
interfaced with FACP complete all as per Drawings and Specifications.
(Cont'd)

A ZCV 150 mm dia no. 2 4,336 8,672

To Collection 8,672
B16/169
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

EQUIPMENT

FIRE EXTINGUISHERS

Supply, installation, testing and commissioning of fire extinguishers (UL


listed / FM approved) independently mounted including brackets ,supports
,instruction signs in accordance with the authority regulations, Specifications
and Drawings to the satisfaction of the Engineer.

A 6 Kg dry powder extinguisher no. 21 290 6,090

B 5.0 kg CO2 fire extinguisher no. 21 386 8,106

C Automatic fire extinguisher no. 3 193 579

FIRE FM 200 system

Supply, installation, testing & commissioning including room integrity test of


FM 200 system including cylinder racks, concrete reinforced base with
vibration isolator(if required ),filled with gas capacities as per the floor area
requirement ,pipework ,valves,nozzles,control panels wiring interfaced FACP
for following listed areas complete; all complete in accordance with
Drawings, Specifications and authority regulation and approval.(smoke and
heat detector measured elsewhere ) (UL listed / FM Approved)

D FM 200 system @ Electrical room at First floor (Area 18m2) item 1 65,920 65,920

To Collection 80,695
B16/170
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

MECHANICAL SCOPE OF WORKS FOR ALL THE EQUIPMENTS

1. Electrical contractor scope of work is limited up to the isolators 2.


Mechanical contractor shall include the entire balance works for connecting to NOTED,
A their mechanical equipment's. 3. By this way, mechanical contractor to supply, item COMPLIED AND
installation etc. required cables, wires, containments like cable tray, supports INCLUDED
including termination.

WORK INCIDENTAL TO FIRE FIGHTING installation

BY MAIN
Allow for making holes ,mortices, chases and the like and making good CONTRACTOR
B item
finishing . Refer to Scope of
Matrix item 1

C Allow for supports including fixings, anchors and anti-vibration devices item INCLUDED

D Allow for providing sleeves item INCLUDED

BY MAIN
E Allow for providing insulation and waterproofing for holes in slabs and walls item CONTRACTOR
Refer to Scope of
Matrix item 2

To Collection -
B16/171
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

WORK INCIDENTAL TO FIRE FIGHTING installation

BY MAIN
A Allow for any Builder's work in connection with Fire fighting installation item CONTRACTOR
Refer to Scope of
Matrix item 1

To Collection -
B16/172
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

Sundries

Allow for third party certificate from authorised company for handing over
A item
the system for the complete mall. INCLUDED

Allow for all identification labels including plates, charts and identification of
B item
plant, equipment, cable, switches and colour coding INCLUDED

Allow for tools and spares, which shall include loose keys and consumable
C item
spares that has to be handed over to client INCLUDED

Allow for testing and commissioning of the complete fire fighting


D INSTALLATIONS which must include operation of complete fire fighting item
system INCLUDED

Allow for testing the complete fire fighting installation in the presence of
E engineer ,repeat test as may be required and leave in perfect order and to the item
satisfaction of the engineer and the local authority INCLUDED

Allow for documents, which shall include submittals, shop Drawings, as built
F item
Drawings, samples operation and maintenance manual as specified. INCLUDED

Allow for preparing schedule of manufacturers recommended tools and spare


G item
parts of each piece of equipment /items /materials INCLUDED

H Allow for protective painting item INCLUDED

Allow for connection to mains including pipework and all necessary


J accessories, complete all in accordance with the drawings, Specifications, as item
per DCD requirements . INCLUDED

K BY MAIN
Allow for fire stopping as per DCD requirements for floors, wall, ceiling as
CONTRACTOR
per acceptable material system approved by the Engineer. Fire stopping by item
Refer to Scope of
specialist approved by the Engineer & Client.
Matrix item 28

L Allow for training of client and the contractors item INCLUDED

To Collection -
B16/173
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
NO. dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

4. FIRE FIGHTING SYSTEM (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

ADDITIONAL ITEMS

The tenderer is to list down the quantities and rates for any additional items
that shown on the Drawings, mentioned in the Specifications but not included
in the BoQ section for the satisfaction and completion of the works. Should
A
the tenderer fail to insert any items have will be deemed that this lump sum
price for the tender includes all items and no subsequent claim for any
additional item will be entertained.

To Collection -
B16/174
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

COLLECTION

FOR DEPARTMENT STORE

1. HVAC (HEATING VENTILATION AND AIR CONDITIONING)


SYSTEM

Page B16/140 415,278

Page B16/141 298,872

Page B16/142 12,910

Page B16/143 340,244

Page B16/144 39,717

Page B16/145 3,193

Page B16/146 1,423,652

Page B16/147 534,834

Page B16/148 885,600

Page B16/149 0

Page B16/150 45,700

Page B16/151 0

Page B16/152 0

Page B16/153 0

TOTAL HVAC (HEATING VENTILATION AND AIR CONDITIONING) SYSTEM 4,000,000


B16/175
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

2. DRAINAGE SYSTEM

Page B16/154 15,489

Page B16/155 61,018

Page B16/156 21,493

Page B16/157 -

Page B16/158 -

Page B16/159 -

TOTAL DRAINAGE SYSTEM 98,000


B16/176
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

3. WATER SUPPLY SYSTEM

Page B16/160 30,931

Page B16/161 8,434

Page B16/162 1,120

Page B16/163 5,911

Page B16/164 2,604

Page B16/165 -

Page B16/166 -

TOTAL WATER SUPPLY SYSTEM 49,000


B16/177
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

FOR DEPARTMENT STORE (Cont'd)

4. FIRE FIGHTING SYSTEM

Page B16/167 449,414

Page B16/168 83,219

Page B16/169 8,672

Page B16/170 80,695

Page B16/171 -

Page B16/172 -

Page B16/173 -

Page B16/174 -

TOTAL FIRE FIGHTING SYSTEM 622,000


B16/178
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C
Rev.01
SUMMARY AMOUNT
dirham's

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE, (cont'd.)

MECHANICAL ENGINEERING INSTALLATIONS (Cont'd)

TOTAL FOR DEPARTMENT STORE

1 HVAC (HEATING VENTILATION AND AIR CONDITIONING) SYSTEM 4,000,000

2 DRAINAGE SYSTEM 98,000

3 WATER SUPPLY SYSTEM 49,000

4 FIRE FIGHTING SYSTEM 622,000

Carried to Department Store Summary 4,769,000


B16/179
Proposed (2B+G+2) Shopping Mall
Plot No. (24-001) Nadd Hessa (Dubai Silicon Oasis), Dubai, U.A.E.
For M/s. Lulu Hypermarket L.L.C Dec-17
Rev.01

FINAL SUMMARY

BILL DESCRIPTION TOTAL AMOUNT


(in Dirhams)

BILL NO. 1 - GENERAL REQUIREMENTS 10,000,000.00

PART -1 : MALL

BILL NO. 13 - MECHANICAL ENGINEERING INSTALLATION 119,240,000.00

BILL NO. 14 - ELECTRICAL ENGINEERING INSTALLATION 54,420,000.00

PART - 2 : HYPERMARKET & DEPARTMENT STORE

BILL NO. 16 - HYPERMARKET & DEPARTMENT STORE

HYPERMARKET MECHANICAL ENGINEERING INSTALLATION 9,441,000.00

DEPARTMENT STORE MECHANICAL ENGINEERING


4,769,000.00
INSTALLATION

HYPERMARKET ELECTRICAL ENGINEERING INSTALLATION 4,650,000.00

DEPARTMENT STORE ELECTRICAL ENGINEERING


2,480,000.00
INSTALLATION

SUB-TOTAL 205,000,000.00

Adjustment Item (if any)


Add* / Delete* ____________ %

BILL NO. 17 - PRIME COST AND PROVISIONAL SUMS ---

* - Tenderer to specify

TOTAL AMOUNT TO FORM OF TENDER 205,000,000.00


Amount in Words : (DIRHAMS TWO HUNDRED FIVE MILLION ONLY)
GS/1

Вам также может понравиться