Вы находитесь на странице: 1из 80

DAFTAR BERAT BESI BETON POLOS DAN ULIR

BERAT /M' BERAT /M'


NO DIAMETER PANJANG BERAT/BTG BERAT/BTG
POLOS ULIR
(mm) (m') (kg) (Kg) (Kg) (Kg)

1 4 11 1.00 0.09
2 6 12 2.66 0.22
3 8 12 4.74 0.40
4 9 12 6.00 0.50
5 10 12 7.40 0.62 7.40 0.62
6 11 12 9.00 0.75
7 12 12 10.70 0.89
8 13 12 12.50 1.04 12.50 1.04
9 15 12 14.50 1.21
10 16 12 19.00 1.58
11 19 12 26.70 2.23 26.70 2.23
12 22 12 35.80 2.98 35.80 2.98
13 23 12 39.10 3.26
14 24 12 42.62 3.55
15 25 12 46.20 3.85 46.20 3.85
16 29 12 60.50 5.04
17 28 12 58.00 4.83
18 31 12 71.10 5.93
19 32 12 75.77 6.31 75.77 6.31
20 35 12 90.10 7.51
21 38 12 107.00 8.92
22 41 12 126.00 10.50

Spesifikasi
Spesification
Type Penampang Jarak Panjang
Diameter Spacing Length
10 mm 150 mm 5,40 mm
M 10
10 mm 150 mm 2,10 mm
9 mm 150 mm 5,40 mm
M 9 / DM 9
9 mm 150 mm 2,10 mm
8 mm 150 mm 5,40 mm
M 8 / DM 8
8 mm 150 mm 2,10 mm
7 mm 150 mm 5,40 mm
M 7 / DM 7
7 mm 150 mm 2,10 mm
6 mm 150 mm 5,40 mm
M 6 / DM 6
6 mm 150 mm 2,10 mm
5 mm 150 mm 5,40 mm
M 5 / DM 5
5 mm 150 mm 2,10 mm
4 mm 150 mm 5,40 mm
M4
4 mm 150 mm 2,10 mm
Berat
Weight
Kg / lbr.
Kg / m2
Kg / Sheet
96.55
8.51
78.21
6.9
61.79
5.45
47.31
4.17
34.76
3.07
24.14
2.13
15.45
1.36
E F G H I J K L
2
3
4 LAMPIRAN II : PERATURAN WALIKOTA PONTIANAK
5 NOMOR : …………………... TAHUN 2014
6 TANGGAL : ……………-…………2014
7
8
9 TENTANG
10 STANDAR HARGA SATUAN UPAH, BAHAN
11 ANALISA BIAYA KONSTRUKSI STANDAR NASIONAL INDONESIA (ABK-SNI)
12 DAN ANALISA E KOTA PONTIANAK
13
14 ( Periode Januari s/d Desember 2014 )
15
16
17
HARGA
18
19 TANPA HARGA TERMASUK
20 NO TENAGA KERJA SATUAN KODE KEUNTUNGAN KEUNTUNGAN KEUNTUNGAN
21 (OVERHEAD) (OVERHEAD) (OVERHEAD)
22 (Rp) (Rp) (Rp)
23
24
25 A. UPAH
26 1 Mandor Lapangan Org/hari L.061 #REF! #REF!
27 2 Mekanik Org/hari L.071 #REF! #REF!
28 3 Kepala Tukang Org/hari L.073 #REF! #REF!
29 4 Tukang Batu / Kayu / Gali / Besi / Cor / Semen / Cat / Listrik / Panca Org/hari L.079 #REF! #REF!
30 5 Operator terlatih Org/hari L.081 #REF! #REF!
31 6 Operator semi terlatih Org/hari L.082 75,000.00 75,000.00
32 7 Sopir Org/hari L.091 85,000.00 85,000.00
33 8 Pekerja / Buruh Lapangan Tak terlatih Org/hari L.101 #REF! #REF!
34 9 Pekerja / Buruh Lapangan terlatih Org/hari L.106 #REF! #REF!
35
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
44 B. BAHAN PENGISI
45 1 Batu Kong M³ M.101 210,800.00
46 2 Batu Sap Pinang M³ - 230,000.00
47 3 Batu pecah 15-20 cm M³ - 354,600.00
48 4 Batu pecah 10-15 cm M³ M.020 383,300.00
49 5 Batu pecah 5-7 cm M³ M.022 402,500.00
50 6 Batu pecah 3-5 cm M³ M.023 413,800.00
51 7 Batu pecah 2-3 cm M³ M.024 449,900.00
52 8 Batu pecah 1-2 cm M³ M.025 457,800.00
53 9 Batu pecah 1-1 cm M³ - 493,500.00
54 10 Batu pecah 0,5 cm M³ M.026 569,400.00
55 11 Stone Dust M³ - 408,600.00
56 12 Aspal Kg - 13,900.00
57 13 Pasir M³ M.040 92,700.00
58 14 Semen PC Zak M.080 79,300.00
59 15 Semen PC Kg - 1,586.00
60 16 Tanah Ex. Peniraman M³ M.050.a 219,900.00
61 17 Tanah EX. Peladis M³ M.050 284,800.00
62 18 Paving Block Bh - 2,500.00
63 19 Paving Stone Bh - 4,600.00
64 20 Paving Segi Enam Bh 4,000.00
65 21 Batu Bata 5 x 11 x 22cm Bh - 1,700.00
66 22 Bataco 15 x 30 x 7 cm Bh - 1,100.00
67 23 Bataco 15 x 30 x 6 cm 900.00
68 24 Bataco 20 x 40 x 9 cm ( press ) Bh - 2,900.00
69 25 Bataco 20 x 40 x 7 cm ( press ) Bh - 2,400.00
70 26 Kerawang ( roster ) 18 x 18 cm Bh - 13,800.00
71 27 Kerawang press ( roster ) 30 x 30 cm Bh - 61,800.00
72 28 Keramik 20 x 20 cm ex Roman Kotak - 81,100.00
73 29 Keramik 30 x 30 cm ex Roman Kotak - 95,200.00
74 30 Keramik 30 x 30 cm Unpolished Kotak - 98,500.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
75 31 Keramik 30 x 30 cm Polish 103,500.00
76 32 Keramik 30 x 30 cm Artistik Kotak - 107,000.00
77 33 Keramik 40 x 40 cm ex Roman Kotak - 109,300.00
78 34 Keramik 40 x 40 cm Polished (setaraf Indogress) Kotak - 257,300.00
79 35 Keramik 40 x 40 cm Polished (setaraf Decogress) Kotak - 156,200.00
80 36 Keramik 40 x 40 cm Unpolished (setaraf Indogress) Kotak - 256,500.00
81 37 Keramik 40 x 40 cm Unpolished (setaraf Decogress) Kotak - 162,900.00
82 38 Keramik 60 x 60 cm Polished (setaraf Indogress) Kotak - 367,400.00
83 39 Keramik 60 x 60 cm Polished (setaraf Decogress) Kotak - 360,000.00
84 40 Keramik 60 x 60 cm Unpolished (setaraf Indogress) Kotak 371,500.00
85 41 Keramik 60 x 60 cm Unpolished (setaraf Decogress) Kotak 333,500.00
86 42 Granit 60 x 60 cm ex Essenza Polished Kotak 326,600.00
87 43 Granit 60 x 60 cm ex Essenza Unpolished Kotak 333,500.00
88 44 Granit 40 x 40 cm ex Essenza Polished Kotak 256,500.00
89 45 Granit 40 x 40 cm ex Essenza Unpolished Kotak - 264,500.00
90 46 Marmer M² - 977,500.00
91 47 Wood Flooring M² - 301,900.00
92 48 List Keramik WC. 8 x 20 cm Bh - 9,600.00
93 49 Plint Kayu uk. 2 x 10 cm Bh - 60,500.00
94 50 Keramik dinding 20 x 20 cm ex Roman Kotak - 87,400.00
95 51 Keramik dinding 20 x 25 cm ex Roman Kotak - 99,400.00
96 52 Floor Hardener Kg - 11,000.00
97 53 Beton Ready Mix B 0 M³ - 1,085,600.00
98 54 Beton Ready Mix 125 M³ 1,140,000.00
99 55 Beton Ready Mix 150 M³ 1,178,800.00
100 56 Beton Ready Mix 175 M³ 1,218,200.00
101 57 Beton Ready Mix 200 M³ 1,304,100.00
102 58 Beton Ready Mix 225 M³ 1,367,700.00
103 59 Beton Ready Mix 250 M³ 1,408,800.00
104 60 Beton Ready Mix 275 M³ 1,426,000.00
105 61 Beton Ready Mix 300 M³ 1,456,700.00
106 62 Beton Ready Mix 325 M³ 1,502,500.00
107 63 Beton Ready Mix 350 M³ 1,542,700.00
108 64 Beton Ready Mix 375 M³ 1,584,100.00
109 65 Beton Ready Mix 400 M³ 1,617,500.00
110 66 Beton Ready Mix 425 M³ - 1,647,400.00
111 67 Beton Ready Mix 450 M³ - 1,687,600.00
112 68 Beton Ready Mix 475 M³ - 1,729,600.00
113 69 Beton Ready Mix 500 M³ - 1,767,000.00
114 70 Additive Ready Mix Liter - 44,000.00
115 71 Karung Goni Curing Beton ( 0.7m² ) Lembar - 13,000.00
116 72 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 20 x 20, K 300 - 6m Btg - 1,104,000.00
117 73 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 25 x 25, K 300 - 6m Btg - 1,380,000.00
118 74 Tiang Pancang (Mini Pile / Ready Mix) uk. Δ 28 x 28 x 28, K 300 - 6m Btg - 875,000.00
119 75 Tiang Pancang (Mini Pile / Ready Mix) uk. Δ 32 x 32 x 32, K 300 - 6m Btg - 1,035,000.00
120 76 Pemancangan Mini Pile - 6m Btg - 125,000.00
121 77 Sewa Pompa Ready Mix (Min. 100 M³) M³ - 28,800.00
122 78 Bahan Plastik Cor Beton M² - 3,500.00
123 79 Kansteen / kerb beton 60x30x20 bh 74,800.00
124 80 Kansteen / kerb beton 60x30x10 bh 66,000.00
125 C. BAHAN KAYU
126 1 Ky. Belian tdk ketam Uk. 6/6 - 4 M M³ - 11,663,900.00
127 2 Ky. Belian tdk ketam Uk. 7/7 - 4 M M³ - 10,883,400.00
128 3 Ky. Belian tdk ketam Uk. 8/8 - 4 M M³ - 9,126,500.00
129 4 Ky. Belian tdk ketam Uk. 8/16 - 4 M M³ - 8,759,800.00
130 5 Ky. Belian tdk ketam Uk. 9/9 - 4 M M³ M.181.a 11,003,100.00
131 6 Ky. Belian tdk ketam Uk. 10/10 - 4 M M³ M.181.b 10,823,800.00
132 7 Ky. Belian tdk ketam Uk. 12/12 - 4 M M³ - 14,974,000.00
133 8 Ky. Belian tdk ketam Uk. 18/18 - 4 M M³ - 11,979,200.00
134 9 Ky. Belian tdk ketam Uk. 5/10 - 4 M M³ - 11,500,000.00
135 10 Ky. Belian ketam Uk. 6/6 - 4 M M³ - 12,827,700.00
136 11 Ky. Belian ketam Uk. 7/7 - 4 M M³ - 11,558,700.00
137 12 Ky. Belian ketam Uk. 8/8 - 4 M M³ - 12,668,000.00
138 13 Ky. Belian ketam Uk. 5/10 - 4 M M³ - 12,567,900.00
139 14 Ky. Belian ketam Uk. 4/8 - 4 M M³ - 11,629,800.00
140 15 Papan belian ketam (4m) M³ M.181.e 15,240,200.00
141 16 Papan belian tdk ketam (4m) M³ M.181.d 14,584,700.00
142 17 Ky. klas I Bengkirai uk. 8/8 - 4 M ( ketam ) M³ M.181.f 7,704,100.00
143 18 Ky. klas I Bengkirai uk. 8/8 - 4 M ( tdk ketam ) M³ M.181.g 7,487,000.00
144 19 Ky. klas I Bengkirai uk. 7/7 - 4 M ( tdk ketam ) M³ - 6,011,700.00
145 20 Ky. klas I Bengkirai uk. 7/7 - 4 M ( ketam ) M³ - 6,600,800.00
146 21 Ky. klas I Bengkirai uk. 5/10 - 4 M ( ketam / untuk kusen ) M³ - 9,315,000.00
147 22 Kusen Ky Belian uk. 5/10 22,425,000.00
148 23 Kusen Ky Kelas I Bangkirai uk. 5/10 M³ - 17,250,000.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
149 24 Kusen Ky Kelas II uk. 5/11 13,225,000.00
150 25 Ky. klas II Mabang uk. 8/8 - 4 M ( tdk ketam ) M³ M.181.h 4,402,300.00
151 26 Ky. klas II Mabang uk. 8/8 - 4 M ( ketam ) M³ M.181.i 4,567,100.00
152 27 Ky. klas II Mabang uk. 7/7 - 4 M ( tdk ketam ) M³ - 4,540,200.00
153 28 Ky. klas II Mabang uk. 7/7 - 4 M ( ketam ) M³ - 4,776,800.00
154 29 Ky. klas II Mabang uk. 4/6 - 4 M ( tdk ketam ) M³ - 3,363,100.00
155 30 Ky. klas II Mabang uk. 5/7 - 4 M ( tdk ketam ) M³ - 3,605,200.00
156 31 Ky. klas II Mabang uk. 5/10 - 4 M ( tdk ketam ) M³ - 4,358,100.00
157 32 Ky. klas II Mabang uk. 6/10 - 4 M ( tdk ketam ) M³ - 4,671,900.00
158 33 Ky. klas II Mabang uk. 6/12 - 4 M ( tdk ketam ) M³ - 4,458,900.00
159 34 Ky. klas II Mabang uk. 4/8 - 4 M ( tdk ketam ) M³ - 4,528,500.00
160 35 Ky. klas II Mabang uk. 8/15 - 4 M ( tdk ketam ) M³ - 4,592,000.00
161 36 Ky. klas II Mabang uk. 8/12 - 4 M ( tdk ketam ) M³ - 4,342,400.00
162 37 Ky klas III uk. 3/5 - 4 M ( tdk ketam) M³ - 2,389,400.00
163 38 Ky klas III uk. 4/6 - 4 M ( tdk ketam) M³ - 1,991,500.00
164 39 Papan kayu klas II (mabang) tdk ketam M³ M.181.j 7,187,500.00
165 40 Papan kayu klas II (mabang) ketam M³ M.181.k 7,240,700.00
166 41 Papan kayu klas I tdk ketam M³ - 12,442,800.00
167 42 Papan kayu klas I ketam M³ - 12,866,500.00
168 43 Papan mal klas III M³ M.181.l 2,430,100.00
169 44 Papan Simpiran M³ - 1,197,900.00
170 45 Renglat kayu klas I uk 1/8 cm Btg - 19,600.00
171 46 Kayu profil 10cm Btg - 35,300.00
172 47 Kayu cerucuk /dolken ø 4 - 6 - Pj. 4 M Btg - 5,800.00
173 48 Kayu cerucuk /dolken ø 6 - 8 - Pj. 4 M Btg - 7,000.00
174 49 Kayu cerucuk /dolken ø 8 - 10 - Pj. 4 M Btg - 8,900.00
175 50 Kayu cerucuk /dolken ø12 - Pj. 8 M Btg - 86,300.00
176 51 Kayu cerucuk /dolken ø 15 - Pj. 12 M Btg - 104,900.00
177 52 Kayu Simpiran / Bakar M³ - 268,300.00
178 53 Alas laci Btg - 8,500.00
179 54 Wood Plank M' - 60,500.00
180 55 Bambu Pj. 10 m Btg 8,600.00
181
182 D. BAHAN CAT
183 1 Amplas Lbr - 3,200.00
184 2 Minyak cat Kg - 17,000.00
185 3 Cat kilat Kg - 60,200.00
186 4 Plamur Kg - 36,200.00
187 5 Cat dasar Kg - 36,800.00
188 6 Cat tembok Kg - 14,900.00
189 7 Cat tembok type weather shield Kg - 107,200.00
190 8 Cat tembok type weather coat (acrylic) Kg - 96,300.00
191 9 Cat Dasar Emulsion Setara Dulux Kg 61,500.00
192 10 Cat Akhir Emulsion setara Dulux Kg 82,600.00
193 11 Cat Akhir Weather Shield setara Dulux Kg 113,000.00
194 12 Cat Dasar Emulsion setara Mowilex Kg 56,300.00
195 13 Cat Akhir Emulsion setara Mowilex Kg 70,900.00
196 14 Cat Weather Shield setara Mowilex Kg 97,800.00
197 15 Cat Dasar Emulsion setara Vinilex Kg 27,300.00
198 16 Cat Akhir Emulsion setara Vinilex Kg 30,600.00
199 17 Cat Weather Shield setara Vinilex Kg 36,800.00
200 18 Cat Alkali (Undercoat) Kg 59,600.00
201 19 Cat seng (Zinc Chromate) Kg - 50,500.00
202 20 Dempul Kg - 17,500.00
203 21 Plitur Kg - 46,900.00
204 22 Thiner Ltr M.090.f 18,900.00
205 23 Thiner ND Ltr - 24,000.00
206 24 Melamic Ltr - 65,400.00
207 25 Vernis Ltr - 45,200.00
208 26 Meni Kg - 43,100.00
209 27 Oker Kg - 13,700.00
210 28 Lem Kayu Kg - 19,700.00
211 29 Sealent Tube - 33,800.00
212 30 Soda Api Kg - 24,300.00
213 31 Sabun / cream pembersih kotoran Kg - 13,800.00
214 32 Teak Oil Ltr - 48,400.00
215 33 Ter / Residu Ltr - 12,800.00
216 34 Kuas 4" Bh - 24,900.00
217 35 Road Line Paint ( Cat Marka ) Kg M.090.e 84,000.00
218 36 Glass Bit Kg M.090.g 40,200.00
219 37 Weatherbond Emulsion ( cat kerb ) Kg M.090.h 103,500.00
220 38 Termoplast Kg - 23,000.00
221 39 Water Proofing M² - 51,400.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
222 E. BAHAN BESI DAN ALUMINIUM
223 1 Besi Tulangan Beton Kg M.167 13,500.00
224 2 Besi wire mesh ø 5 Kg - 16,800.00
225 3 Kawat baja/bendrat Kg M.168 21,300.00
226 4 Simpai roll Kg - 20,600.00
227 5 Kawat simpai Kg - 17,800.00
228 6 Baut dia 4/8 " pj = 20 cm Btg M.163 4,900.00
229 7 Besi Penahan bh - 18,400.00
230 8 Beugel plat L. 3 cm bh - 17,300.00
231 9 Plat 1,2 x 2,4 x 12 Bh - 356,500.00
232 10 Besi Konstruksi (I, H) Kg - 15,000.00
233 11 Besi Konstruksi ( C ) Kg - 11,500.00
234 12 Besi Konstruksi (siku ) Kg - 12,700.00
235 13 Kawat Las Btg - 6,100.00
236 14 Kawat Las Kg - 32,800.00
237 15 Kawat harmonika M² - 30,300.00
238 16 Kawat kasa M² - 11,500.00
239 17 Pipa galvanis dia 3/4" Btg - 136,000.00
240 18 Pipa galvanis dia 1/2" Btg - 107,100.00
241 19 Pipa galvanis dia 1" Btg - 160,800.00
242 20 Pipa galvanis dia 1 1/4" Btg - 235,800.00
243 21 Pipa galvanis dia 1 1/2" Btg - 283,300.00
244 22 Pipa galvanis dia 2" Btg - 348,300.00
245 23 Pipa galvanis dia 2,5" 448,500.00
246 24 Pipa galvanis dia 3" Btg - 669,900.00
247 25 Pipa galvanis dia 4" Btg - 1,063,800.00
248 26 Pipa galvanis dia 5" Btg 1,100,000.00
249 27 Pipa galvanis dia 6,5" Btg 1,980,000.00
250 28 Folding gate M² - 715,000.00
251 29 Rangka Aluminium 1 1/2" x 3" Meter - 97,800.00
252 30 Rangka Aluminium 1 3/4" x 4" Meter - 109,300.00
253 31 Pintu Aluminium std IKP, lengkap 4" Unit - 1,725,000.00
254 32 Kusen Aluminium 3" Putih Meter 138,000.00
255 33 Kusen Aluminium 3" Hitam Meter 74,800.00
256 34 Kusen Aluminium 3" Silver Meter 74,800.00
257 35 Rangka Baja Ringan Zincalume (truss/color) (Tanpa Jurai Dalam - Bentang s/d 16 m) M² - 264,500.00
258 36 Rangka Baja Ringan Zincalume (truss/color) (Tanpa Jurai Dalam - Bentang 17 m s/d 30 m) M² - 290,400.00
259 37 Rangka Baja Ringan Zincalume (truss/color) (Dengan Jurai Dalam - Bentang s/d 16m) M² - 247,500.00
260 38 Rangka Baja Ringan Zincalume (truss/color) (Dengan Jurai Dalam - Bentang 17 m s/d 30 m) M² - 326,700.00
261 39 Rangka Baja Ringan Zincalume (truss/polos) (Tanpa Jurai Dalam - Bentang s/d 16 m) M² - 184,000.00
262 40 Rangka Baja Ringan Zincalume (truss/polos) (Tanpa Jurai Dalam - Bentang 17 m s/d 30 m) M² - 242,000.00
263 41 Rangka Baja Ringan Zincalume (truss/polos) (Dengan Jurai Dalam - Bentang s/d 16m) M² - 205,700.00
264 42 Rangka Baja Ringan Zincalume (truss/polos) (Dengan Jurai Dalam - Bentang 17 m s/d 30 m) M² - 278,300.00
265 43 Reng Rangka Baja Ringan (Polos) uk. 0.40 - 0.45 Pjg 6 m btg 60,400.00
266 44 Rangka baja truss (0,75-6m) btg 94,300.00
267 45 Rangka baja truss (0,65-6m) btg 86,300.00
268 46 Dinabolt bh 6,600.00
269 47 L. Braket bh 6,600.00
270 48 Baut truss bh 900.00
271 49 Baut reng bh 900.00
272 50 Baut atap 5 cm bh 900.00
273 51 Alumunium Komposit + Rangka Besi M² - 1,045,000.00
274 52 Alumunium Komposit 1,24 x 2,44 m (setara alumatec) Lbr 1,540,000.00
275 53 Rangka Plafond Metal Furing + Pemasangan M² - 148,500.00
276 54 Besi stainles 1" btg 137,500.00
277 55 Besi tempa btg 80,000.00
278 F. BAHAN PENGANTUNG
279 1 Pintu Plastik untuk WC Bh - 281,100.00
280 2 Kait angin Bh - 12,000.00
281 3 Handle Jendela Bh - 11,400.00
282 4 Handle Pintu Bh - 148,500.00
283 5 Engsel jendela Bh - 12,300.00
284 6 Engsel pintu Bh - 21,100.00
285 7 Slot pintu Bh - 19,600.00
286 8 Slot jendela Bh - 7,300.00
287 9 Kunci tanam 2 slag (setaraf Belluci) Bh - 206,000.00
288 10 Kunci tanam 1 slag Bh - 186,900.00
289 11 Kunci tanam antik Bh - 54,600.00
290 12 Kunci tanam biasa Bh - 47,900.00
291 13 Kunci silinder Bh - 69,900.00
292 14 Door Closer Bh - 196,800.00
293 15 Door Stoper Bh - 60,400.00
294 16 Paku Seng Kg M.166.a 24,000.00
295 17 Paku campuran 1" - 5 " Kg M.166.b 22,900.00
296 18 Paku beton Kg - 36,100.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
297 19 Paku triplek Kg - 20,800.00
298 20 Paku GRC Kg - 23,900.00
299 21 Paku Zincalum Kg 12,300.00
300 22 Paku Onduline Bh 1,500.00
301 23 Sekrup Onduline Bh 1,700.00
302 24 Sekrup Gibsum Kg 55,600.00
303 25 Sekrup Fixer Bh 1,200.00
304 26 Sekrup Steel Sheet Bh - 600.00
305 27 Sekrup Zincalume Bh 600.00
306 28 Pintu Tempered Polos 12 mm - uk. 87 x 213,5 cm Unit - 4,840,000.00
307 29 Pintu Alumunium + Engsel Tanam - uk. 90 x 215 cm Unit - 2,420,000.00
308 30 Pintu Alumunium + Engsel Kupu-kupu - uk. 90 x 215 cm Unit - 1,815,000.00
309 31 Jendela Casement - uk. 60 x 120 cm (Lengkap - Tanpa Kaca) Unit - 726,000.00
310
311 G. BAHAN ATAP
312 1 Sirap belian Lbr - 6,100.00
313 2 Asbes Lbr - 65,800.00
314 3 Eternit M² - 78,700.00
315 4 Genteng Metal Type Permata 0.35 Lbr 56,400.00
316 5 Genteng Metal Type Prima 0.35 Lbr - 59,100.00
317 6 Genteng Metal Type Royal 0.35 Lbr - 59,900.00
318 7 Genteng Metal Type Classic 0.35 Lbr - 60,500.00
319 8 Genteng Metal Type Permata 0.25 Lbr 40,300.00
320 9 Genteng Metal Type Classic 0.25 Lbr 40,300.00
321 10 Genteng Metal Type Royal 0.26 Lbr 40,300.00
322 11 Atap Genteng Onduline Transparan 2 x 0,95 m Lbr 310,500.00
323 12 Atap Genteng Onduline Warna 2 x 0,95 m (merah,hijau,coklat & hitam) Lbr 177,100.00
324 13 Atap Genteng Onduline Warna 2 x 0,95 m (Biru /Premium) Lbr 222,000.00
325 14 Atap Genteng Onduvilla Warna 1,06 x 0,4 m (merah,hijau,coklat & hitam) Lbr 55,800.00
326 15 Atap Genteng Onduvilla Warna 1,06 x 0,4 m (teracota 3D & florentino) Lbr 62,100.00
327 16 Perabung Onduline Warna 90 x 50 cm (merah, coklat, hijau & hitam) Lbr 108,700.00
328 17 Perabung Onduline Warna 90 x 50 cm (biru/premium) Lbr 109,300.00
329 18 Perabung Onduline Warna 90 x 50 cm (florentino) Lbr 110,400.00
330 19 Siku Onduline Warna 110 x 40 cm (merah,coklat,hijau & hitam) Lbr 97,800.00
331 20 Apron Piece Onduvilla 102 x 14 cm Lbr 102,900.00
332 21 Verge Piece Onduline/Onduvilla 104 x 10,5 cm tinggi 11,4 cm Lbr 102,900.00
333 22 Onduband M 63,300.00
334 23 Atap Seng Metal Soka Abadi Lbr 105,800.00
335 24 Atap Seng Metal Soka Jempol Lbr 73,600.00
336 25 Atap Seng Metal Soka Tiara Lbr 61,000.00
337 26 Genteng Metal Stone ( Type Classic 0.35 ) Lbr - 86,300.00
338 27 Genteng Metal Stone ( Type Prima 0.35 ) Lbr - 86,300.00
339 28 Atap Metal Supersheet 0.35 (polos) M² - 93,500.00
340 29 Atap Metal Supersheet 0.35 (colour) M² - 128,700.00
341 30 Atap Metal Supersheet 0.25 (polos) M² 54,100.00
342 31 Atap Metal Supersheet 0.25 (colour) M² 73,600.00
343 32 Atap Trim Deck 0.3 (polos) M² - 115,000.00
344 33 Atap Trim Deck 0.35 (color) M² - 129,200.00
345 34 Atap polycarbonat M² 90,000.00
346 35 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm) Bh - 52,900.00
347 36 Nok bubungan genteng metal stone 1/2 lingkaran 0.35 (pj 40cm) Bh - 80,500.00
348 37 Nok bubungan genteng metal kotak 0.35 M' - 57,500.00
349 38 Nok bubungan genteng metal stone kotak 0.35 M' - 111,400.00
350 39 Nok bubungan Trim Deck (polos) M' - 125,900.00
351 40 Nok bubungan Trim Deck (color) M' - 141,600.00
352 41 Nok bubungan Steel Sheet 0.33 (color) (pj 50 cm) M' - 50,900.00
353 42 Nok bubungan Steel Sheet 0.43 (color) (pj 50 cm) M' - 58,100.00
354 43 Nok bubungan Steel Sheet 0.35 (polos) (pj 50 cm) M' - 47,200.00
355 44 Nok bubungan Steel Sheet 0.40 (polos) (pj 50 cm) M' - 50,900.00
356 45 Seng Gelombang Bjls 30 Lbr - 73,200.00
357 46 Seng Gelombang Bjls 20 Lbr - 44,300.00
358 47 Seng Plat Bjls 20 Lbr - 46,200.00
359 48 Seng Plat Bjls 30 Lbr - 76,300.00
360 49 Seng Plat Bjls 30 (lebar 45 cm) M' - 23,000.00
361 50 Plat Datar Color 0.35 Lbr - 62,400.00
362 51 Zincalume Gelombang Persegi 0.40 (polos) M² 87,300.00
363 52 Zincalume Gelombang Persegi 0.35 (polos) M² - 138,100.00
364 53 Zincalume Gelombang Persegi 0.30 (polos) M² - 80,500.00
365 54 Zincalume Gelombang Persegi 0.40(color) M² 96,400.00
366 55 Zincalume Gelombang Persegi 0.35 (color) M² - 92,000.00
367 56 Zincalume Gelombang Persegi 0.30 (color) M² - 63,300.00
368 57 Zincalume Plat 0.2 Lbr - 53,500.00
369 58 Aluminium Foil M² - 60,500.00
370 59 Atap Steel Sheet 0.33 (color) M² - 128,200.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
371 60 Atap Steel Sheet 0.40 (polos) M² - 128,200.00
372 61 Papan Belian utk Atap uk. 1/15 pj. 50 cm Lbr - 17,500.00
373 62 Atap Gelombang Bitumen Warna Lbr - 151,800.00
374 63 Atap Gelombang Bitumen Bening Lbr - 304,800.00
375
376 H. BAHAN KACA
377 1 Kaca Polos, t = 5 mm M² - 162,900.00
378 2 Kaca Polos, t = 12mm M² - 632,500.00
379 3 Kaca Rayben, t = 5 mm M² - 192,600.00
380 4 Kaca Cermin t = 3mm M² - 276,000.00
381 5 Kaca Repsol, t=5mm M² 517,500.00
382 6 Kaca Patri M² - 2,702,500.00
383 7 Sealent Kg - 122,900.00
384 8 Nako + Bingkai (80 x 15) x 10 daun polos Bh - 287,500.00
385 9 Nako + Bingkai (80 x 15) x 10 daun rayben Bh - 345,000.00
386 10 Kaca Es M² - 241,500.00
387 11 Kaca Polos, t = 8 mm M² - 402,500.00
388 12 Kaca Raindown, t = 5 mm M² - 253,000.00
389 13 Kaca Buram, t = 5 mm M² - 159,500.00
390
391 I. BAHAN TRIPLEK
392 1 Triplek t = 3 mm Lbr - 63,200.00
393 2 Triplek t = 6 mm Lbr - 125,500.00
394 3 Triplek t =9 mm Lbr - 196,300.00
395 4 Triplex t = 12 mm Lbr 259,700.00
396 5 Teakwood t = 3 mm Lbr 161,000.00
397 6 Formika t = 0,03 mm Lbr 126,500.00
398 7 Multiplex t = 6 mm Lbr 117,300.00
399 8 Multiplex t = 9 mm Lbr 204,100.00
400 9 Multiplex t = 10 mm Lbr 205,700.00
401 10 Multiplek t = 12 mm Lbr - 224,300.00
402 11 Plywood 4' x 8' x 4mm Lbr - 114,400.00
403 12 Panel GRC 120 x 240 x 40 Lbr - 78,600.00
404 13 GypsumBoard t = 9mm Lbr - 68,700.00
405 14 Super Plank 10 x 240 x 9 cm Lbr 43,100.00
406 15 Super Plank 20 x 240 x 9 cm Lbr 66,100.00
407 16 Super Plank 30 x 240 x 9 cm Lbr 86,300.00
408
409 J. BAHAN SANITASI
410 1 Wastafel setara Toto Bh - 1,111,000.00
411 2 Kloset duduk monoblok Bh 1,092,500.00
412 3 Kloset duduk putih (setaraf TOTO) Bh - 2,385,400.00
413 4 Kloset duduk warna (setaraf TOTO) Bh - 2,702,500.00
414 5 Kloset jongkok (setaraf TOTO) Bh - 339,000.00
415 6 Kloset jongkok (setaraf INA) Bh - 178,000.00
416 7 Urinoir type U 57 M ex Toto Unit 2,160,000.00
417 8 Bak air fibreglass uk. 55x55x60 cm Bh 310,500.00
418 9 Shower Spray setara Toto Unit 265,000.00
419 10 Sliding rail setara Toto Unit 378,000.00
420 11 Floordrain setara Toto Bh 367,000.00
421 12 Tempat Sabun Setara Toto Bh 75,000.00
422 13 Kran zink setara Toto Bh 353,000.00
423 14 Kitchenzink stainless steel 1 lubang Unit 747,500.00
424 15 Kran dinding setara Toto Bh 172,500.00
425 16 Kaca Cermin M² 345,000.00
426 17 Kran air uk 1/2" Bh - 29,800.00
427 18 Pipa paralon dia 1/2" Btg - 21,600.00
428 19 Pipa paralon dia 3/4" Btg - 26,500.00
429 20 Pipa paralon dia 1" Btg - 40,900.00
430 21 Pipa paralon dia 2" Btg - 76,500.00
431 22 Pipa paralon dia 3" Btg - 131,100.00
432 23 Pipa paralon dia 4" Btg - 215,800.00
433 24 Pipa paralon dia 8" Btg - 753,500.00
434 25 Pipa PVC dia 1/2" AW ex Wavin Btg 19,700.00
435 26 Pipa PVC dia 3/4" AW ex Wavin Btg 25,900.00
436 27 Pipa PVC dia 1" AW ex Wavin Btg 36,700.00
437 28 Pipa PVC dia 2" AW ex Wavin Btg 80,200.00
438 29 Pipa PVC dia 3" AW ex Wavin Btg 153,000.00
439 30 Pipa PVC dia 4" AW ex Wavin Btg 253,100.00
440 31 Pipa PVC dia 3/4" D ex Wavin Btg 19,700.00
441 32 Pipa PVC dia 1" D ex Wavin Btg 25,900.00
442 33 Pipa PVC dia 2" D ex Wavin Btg 52,200.00
443 34 Pipa PVC dia 3" D ex Wavin Btg 88,500.00
444 35 Pipa PVC dia 4" D ex Wavin Btg 134,400.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
445 36 Stop kran dia 1/2" ex onda Bh 45,700.00
446 37 Stop kran dia 3/4" ex onda Bh 58,900.00
447 38 Stop kran dia 1" ex onda Bh 132,800.00
448 39 Tangki air 1000 liter Bh 1,607,100.00
449 40 Tangki air 500 liter Bh 935,300.00
450 41 Pelampung otomatis Bh 79,100.00
451 42 Roof Drain Metal Bh 86,300.00
452 43 Septicktank Biosel kap. 6,00 m3 Unit 132,300.00
453 44 Mesin Jet Pump kap.250 watt Unit 1,656,000.00
454 45 Mesin Pompa tekan kap. 150 watt Unit 502,200.00
455
456 K. BAHAN MINYAK (TANPA KEUNTUNGAN)
457 1 Minyak solar Ltr M.183 6,500.00
458 2 Minyak solar industri Ltr - 11,500.00
459 3 Bensin premium Ltr M.184 6,500.00
460 4 Minyak pelumas setara Meditran SX Ultra 15W-40 C14 Plus Ltr M.185 30,250.00
461 5 Oli Diesel setara Meditran SX 15W-40API CH-4/SJ Ltr - 39,800.00
462 6 Minyak tanah Ltr M.064 11,700.00
463 7 Gas Elpiji Refill 12 kg Kg - 8,400.00
464 8 Alat-alat bantu Set M.170 62,700.00
465 9 Sewa Alat Untuk Pengelasan Jam - 68,800.00
466 10 Sewa Molen Set - 165,000.00
467 11 Sewa kuali termasuk angkutan Set - 69,700.00
468
469 L. BATU ALAM
470 1 Batu Andesit Ukuran 10 x 20 cm M² - 201,300.00
471 2 Batu Andesit Ukuran 15 x 30 cm M² - 241,500.00
472 3 Batu Andesit Ukuran 20 x 40 cm M² - 264,500.00
473 4 Batu Andesit Ukuran 30 x 60 cm M² - 310,500.00
474 5 Batu Candi Ukuran 10 x 20 cm M² - 195,500.00
475 6 Batu Candi Ukuran 15 x 30 cm M² - 235,800.00
476 7 Batu Candi Ukuran 20 x 40 cm M² - 258,800.00
477 8 Batu Pacitoroso Ukuran 10 x 20 cm M² 201,300.00
478 9 Batu Pacitoroso Ukuran 15 x 30 cm M² 241,500.00
479 10 Batu Pacitoroso Ukuran 20 x 40 cm M² 264,500.00
480 11 Batu Bali Green Ukuran 10 x 20 cm M² 201,300.00
481 12 Batu Bali Green Ukuran 15 x 30 cm M² 241,500.00
482 13 Batu Bali Green Ukuran 20 x 40 cm M² 264,500.00
483 14 Batu Prasasti Peresmian (batu hitam) ukuran 40 x 60 buah 2,875,000.00
484 15 Batu Prasasti Peresmian (batu hitam) ukuran 60 x 80 buah 5,175,000.00
485 16 Batu Koral (batu taman) bungkus 86,300.00
486 17 Batu Granit Ukuran Lebar 60 cm M² 2,300,000.00
487
488 M. BAHAN ALAT-ALAT LISTRIK
489 1 Armatur lampu High Mass Holovent 400 watt (lengkap) Unit 16,410,100.00
490 2 Armatur lampu SGP 338 / SONT 400 Watt Unit - 6,803,000.00
491 3 Armatur lampu SGP 328 / SONT 250 Watt Unit - 4,642,500.00
492 4 Armatur lampu SGP 338 / SONT 400 Watt (lengkap) Unit - 6,362,500.00
493 5 Armatur lampu SGP 368 / SONT 250 Watt (lengkap) Unit - 5,328,000.00
494 6 Armatur lampu LVD 100 Watt (lengkap) Unit - 6,155,500.00
495 7 Armatur lampu Ekorola TRX 800 - 20 Watt (set) Set - 678,700.00
496 8 Armatur lampu Sorot HPIT 250 Watt (lengkap) Set - 8,320,200.00
497 9 Sorot HPIT 250 watt (lengkap) Set - 6,933,500.00
498 10 XKS SON T 250 watt (lengkap) Set - 4,486,400.00
499 11 Tiang Artagonal Cabang 2 T = 11 M Tiang - 9,665,000.00
500 12 Tiang Artagonal Cabang 1 T = 11 M Tiang - 8,482,200.00
501 13 Tiang Oktagonal Cabang 2 T = 11 M Btg - 9,019,500.00
502 14 Tiang Oktagonal Cabang 1 T = 11 M Btg - 9,473,200.00
503 15 Tiang high mass 22 m cab. 5 ring Tiang - 110,772,800.00
504 16 Tiang high mass 22 m cab. 4 ring Tiang - 100,526,200.00
505 17 Tiang lampu oktagonal 11 m Btg - 13,508,100.00
506 18 Tiang lampu oktagonal 12 m Btg - 15,407,000.00
507 19 Tiang lampu oktagonal cab. 4 Ring 12 Mtr Btg - 13,507,800.00
508 20 Tiang lampu oktagonal cab. 2 (11m) Btg - 14,193,300.00
509 21 Stang Ornamen Galvanis dia 2" Pj. 7 M + Klem Tiang Btg - 1,225,200.00
510 22 Stang Ornamen Galvanis dia 2" Pj. 6 M + Klem Tiang Btg - 1,225,100.00
511 23 Stang Ornamen Galvanis dia 2" Pj. 5 M + Klem Tiang Btg - 1,140,700.00
512 24 Stang Ornamen Galvanis dia 2" Pj. 3 M + Klem Tiang 12 - 850,000.00
513 25 Stang Ornamen Galvanis dia 2" Pj. 2 M + Klem Tiang Btg - 644,400.00
514 26 Box Panel PJU Uk. 60x90x30 Cm lengkap Time Swich Set - 5,812,800.00
515 27 Box Panel PJU Uk. 50x45x25 Cm lengkap Time Swich Set - 4,207,800.00
516 28 Box KWH Meter Uk. 35 x 50 x 25 cm Buah - 994,000.00
517 29 Traffo HPL 400 Watt Buah - 311,300.00
518 30 Traffo HPL 250 Watt Buah - 200,800.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
519 31 Traffo HPL 125 Watt Buah - 155,600.00
520 32 Traffo SON T 400 Watt Buah - 466,600.00
521 33 Traffo SON T 250 Watt Buah - 371,800.00
522 34 Traffo SON T 125 Watt Buah - 180,200.00
523 35 Traffo SON T 70 Watt Buah - 510,100.00
524 36 Traffo SON H 400 Watt Buah - 350,200.00
525 37 Traffo SON H 250 Watt Buah - 309,500.00
526 38 Traffo SON H 125 Watt Buah - 232,100.00
527 39 Traffo SON H 70 Watt Buah - 29,700.00
528 40 Traffo HPiT 400 Buah - 24,500.00
529 41 Traffo Neon 40 Watt Buah - 20,400.00
530 42 Traffo Neon 20 Watt Buah - 18,000.00
531 43 Traffo Neon 10 Watt Buah - 20,400.00
532 44 Traffo 400 Watt Buah - 18,000.00
533 45 HPL 250 Watt Buah - 253,000.00
534 46 HPL 125 Watt Buah - 184,900.00
535 47 HPL 135 Watt Buah - 87,500.00
536 48 SOX 180 Watt Buah - 605,200.00
537 49 SOX 160 Watt Buah - 605,200.00
538 50 MLL Buah - 87,500.00
539 51 Bola SON T 1000 Watt Buah - 925,400.00
540 52 Bola SON T 400 Watt Buah - 419,500.00
541 53 Bola SON T 250 Watt Buah - 404,500.00
542 54 Bola SON T 150 Watt Buah - 309,500.00
543 55 Bola Lampu SON 70 Watt Buah - 210,100.00
544 56 SON H 400 Watt Buah - 350,200.00
545 57 SON H 250 Watt Buah - 350,200.00
546 58 SON H 125 Watt Buah - 309,500.00
547 59 SON H 70 Watt Buah - 187,000.00
548 60 Bola Lampu HPIT 400 Watt Buah - 448,100.00
549 61 Seri 200 Biji Kotak - 73,800.00
550 62 Seri Kuning Kotak - 73,800.00
551 63 Neon Sen Meter - 55,400.00
552 64 Pijar 5 Watt Buah - 2,800.00
553 65 Pijar 20 Watt Buah - 4,700.00
554 66 Pijar 25 Watt Buah - 4,700.00
555 67 Pijar 40 Watt Buah - 4,700.00
556 68 Pijar 60 Watt Buah - 6,600.00
557 69 Pijar 75 Watt Buah - 6,600.00
558 70 Pijar 80 Watt Buah - 5,300.00
559 71 Pijar 100 Watt Buah - 8,300.00
560 72 Pijar 200 Watt Buah - 18,500.00
561 73 Neon 40 Watt Buah - 54,300.00
562 74 Neon 20 Watt Buah - 29,500.00
563 75 Neon 10 Watt Buah - 15,400.00
564 76 Lampu Ekorola TRX 800 - 20 watt (set) Set - 716,200.00
565 77 Lampu Light Grick Buah - 175,500.00
566 78 Lampu Genite 16 Watt Buah - 55,400.00
567 79 Lampu XL 14 Watt Buah - 46,100.00
568 80 Lampu Sorot 300 Watt Buah - 183,000.00
569 81 Lampu Nepalos 25 Watt Buah - 46,200.00
570 82 Lampu Superlox 25 Watt Buah - 7,400.00
571 83 Lampu Superlox 40 Watt Buah - 8,300.00
572 84 Lampu Fisikom 25 Watt Buah - 46,200.00
573 85 Lampu Fisikom 23 Watt Buah - 46,200.00
574 86 Lampu Fisikom 18 Watt Buah - 37,000.00
575 87 Lampu Mercury 125 Watt Buah - 93,500.00
576 88 Lampu Mercury 250 Watt Buah - 197,300.00
577 89 Lampu Sunyco 45 Watt Buah - 110,800.00
578 90 Lampu Matsuka 8 Watt Buah - 27,700.00
579 91 Lampu Matsuka 14 Watt Buah - 29,600.00
580 92 Lampu Matsuka 18 Watt Buah - 42,500.00
581 93 Lampu Matsuka 20 Watt Buah - 49,900.00
582 94 Lampu Matsuka 25 Watt Buah - 51,800.00
583 95 Lampu Par 38 Watt Buah - 68,400.00
584 96 Lampu Taman Buah - 165,000.00
585 97 SL 15 Watt Buah - 53,800.00
586 98 SL 18 Watt Buah - 59,900.00
587 99 SL 25 Watt Buah - 77,500.00
588 100 TL Rina 32 Watt Buah - 36,900.00
589 101 Bola Essetial Buah - 44,400.00
590 102 Bola Spot Light Buah - 69,200.00
591 103 Bola Lampu Sorot 300 Watt Buah - 183,100.00
592 104 Hologen 500 Watt Buah - 53,600.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
593 105 Hologen 1.000 Watt Buah - 105,300.00
594 106 NYY 1 x 1.5 mm roll - 120,000.00
595 107 NYY 1 x 2.5 mm Meter - 4,000.00
596 108 NYY 1 x 4 mm Meter - 6,200.00
597 109 NYY 1 x 6 mm Meter - 9,700.00
598 110 NYY 2 x 2.5 mm Meter - 16,300.00
599 111 NYY 2 x 4 mm Meter - 23,300.00
600 112 NYY 2 x 6 mm Meter - 25,100.00
601 113 NYY 2 x 10 mm Meter - 33,000.00
602 114 NYY 3 x 4 mm Meter - 31,600.00
603 115 NYY 4 x 2.5 mm Meter - 31,200.00
604 116 NYY 4 x 4 mm Meter - 46,200.00
605 117 NYY 4 x 6 mm Meter - 74,900.00
606 118 NYY 4 x 10 mm Meter - 87,800.00
607 119 NYY 4 x 16 mm Meter - 101,900.00
608 120 NYY 4 x 25 mm Meter - 363,900.00
609 121 NYY 4 x 35 mm Meter - 406,300.00
610 122 NYY 4 x 50 mm Meter - 498,600.00
611 123 NYN 2 x 2,5 mm Meter - 20,700.00
612 124 NYN 3 x 1,5 mm Meter - 16,900.00
613 125 NYN 3 x 2,5 mm Meter - 24,700.00
614 126 NYA 1 x 1,5 mm Meter - 23,100.00
615 127 NYA 1 x 2,5 mm Meter - 35,300.00
616 128 NYA 1 x 4 mm Meter - 40,200.00
617 129 NYA 1 x 6 mm Meter - 60,100.00
618 130 NYF6BY 4 x 10 mm Meter - 221,700.00
619 131 NYF6BY 4 x 16 mm Meter - 272,900.00
620 132 NYF6BY 4 x 25 mm Meter - 324,800.00
621 133 NYF6BY 4 x 35 mm Meter - 363,700.00
622 134 NYF6BY 4 x 50 mm Meter - 443,400.00
623 135 NYF6BY 4 x 70 mm Meter - 471,400.00
624 136 NYM 3 x 4 mm Meter - 26,300.00
625 137 NYM 2 x 2 mm Meter - 8,000.00
626 138 NYM 2 x 4 mm Meter - 19,600.00
627 139 NYM 2 x 2,5 mm Meter - 13,600.00
628 140 NYM 2 x 1,5 mm Meter - 5,900.00
629 141 NYM 3 x 1,5 mm Meter - 7,400.00
630 142 NYM 3 x 2,5 mm Meter - 10,500.00
631 143 NYM 3 x 10 mm Meter - 36,900.00
632 144 NYM 4 x 2,5 mm Meter - 13,500.00
633 145 NYM 4 x 4 mm Meter - 34,000.00
634 146 NYMHYM 2 x 0,75 mm Meter - 4,200.00
635 147 NYMHYM 2 x 1,5 mm Meter - 7,100.00
636 148 Traffo SON T 1000 Watt Buah - 1,237,200.00
637 149 Kabel Snur Roll - 73,800.00
638 150 Kabel Tester Meter - 36,900.00
639 151 Kabel Box Meter - 73,800.00
640 152 Kabel Mic Transparan Roll - 240,000.00
641 153 Kabel 3 x 2,5 mm Meter - 10,500.00
642 154 Kabel Antena Roll - 104,500.00
643 155 Kabel H / M Meter - 2,700.00
644 156 Kabel Transparan Meter - 3,700.00
645 157 Kabel Telepon Meter - 2,200.00
646 158 Kabel TC 2 x 10 mm Meter - 9,500.00
647 159 Kabel TC 2 x 16 mm Meter - 13,200.00
648 160 Box TL 20 Watt Buah - 11,000.00
649 161 Box MCB 1 Group Buah - 5,500.00
650 162 Cal Gulung Buah - 73,800.00
651 163 Contactor 100 A Buah - 1,472,200.00
652 164 Conector Buah - 10,700.00
653 165 Dop 3" Buah - 9,300.00
654 166 Esensial Buah - 46,200.00
655 167 Fitting Gantung Buah - 3,900.00
656 168 Fitting Duduk Buah - 9,400.00
657 169 Fitting Atom Buah - 38,500.00
658 170 Fitting Gantung E 27 Buah - 23,300.00
659 171 Fitting Duduk E 27 Buah - 23,300.00
660 172 Fitting Duduk E 40 Buah - 29,500.00
661 173 Fitting Hologen Buah - 3,300.00
662 174 Full Breket Buah - 18,700.00
663 175 Gulung Spul Buah - 92,400.00
664 176 Gulung Coil Contactor Buah - 92,400.00
665 177 Isolasi Unibel Buah - 7,200.00
666 178 Icnitor SN 58 Buah - 133,000.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
667 179 Inector Buah - 59,400.00
668 180 Ignator Buah - 128,700.00
669 181 Indiktor Buah - 173,300.00
670 182 Insuluk Buah - 500.00
671 183 Kapasitor Buah - 207,900.00
672 184 Kap Hijau E 27 Buah - 36,600.00
673 185 Kap Hijau E 40 Buah - 58,600.00
674 186 Kap Lampu Buah - 129,200.00
675 187 Kap To2 Buah - 129,200.00
676 188 Kop Skring Buah - 5,600.00
677 189 Klem Tiang Buah - 14,800.00
678 190 k. Skum 10-8 Buah - 1,100.00
679 191 MCB 1.A Buah - 40,000.00
680 192 MCB 2.A Buah - 46,600.00
681 193 MCB 25 A Buah - 203,400.00
682 194 MCB 63 A Buah - 333,200.00
683 195 MCB 40 A Buah - 273,000.00
684 196 MCB 45 A Buah - 295,000.00
685 197 MCB 50 A Buah - 313,700.00
686 198 MCB 10 A Buah - 149,100.00
687 199 MCB 16 A Buah - 159,800.00
688 200 MCB 6 A Buah - 235,920.00
689 201 MCB 32 A Buah - 375,400.00
690 202 MCB Box Buah - 4,700.00
691 203 Multi Tester Buah - 368,500.00
692 204 MC Se-3 N Buah - 1,213,400.00
693 205 Macon Mec gmg-50 aC Buah - 664,900.00
694 206 Magnetic Contactor 100 A Buah - 1,766,600.00
695 207 NH Fuse 80 A Buah - 33,300.00
696 208 Ornamen Pijar Buah - 433,500.00
697 209 Ornamen Gantung Buah - 64,700.00
698 210 Obeng Plus Buah - 46,600.00
699 211 Obeng Minus Buah - 46,600.00
700 212 Open Steker Buah - 40,000.00
701 213 On - Off Buah - 8,400.00
702 214 Pat 38 Buah - 69,300.00
703 215 Solar Seal / Photo Seal Buah - 166,200.00
704 216 Opstic 1/2" lengkap klem Batang - 304,900.00
705 217 Pipa Paralon 1/2" Batang - 10,200.00
706 218 Pipa L 1/2" Batang - 2,800.00
707 219 Pipa Paralon 1' Batang - 12,100.00
708 220 Pipa Paralon 3/4" Batang - 11,100.00
709 221 Pipa Paralon 3' Batang - 22,200.00
710 222 Pipa PVC 1,5" Batang - 57,900.00
711 223 Pipa PVC Galvanis 1,5" Batang - 199,700.00
712 224 Pipa Besi Batang - 110,800.00
713 225 Pipa Galvanis Batang - 129,300.00
714 226 Pondasi tiang lampu oktagonal (11 meter) Unit - 1,916,500.00
715 227 Pres Conector Buah - 3,800.00
716 228 Rangka Ring 32 Watt Buah - 18,500.00
717 229 Rel MCB Buah - 27,700.00
718 230 Roset Telpon Buah - 6,600.00
719 231 Saklar Tunggal setara Broco Buah 11,000.00
720 232 Saklar Tunggal setara Panasonic Buah 33,000.00
721 233 Saklar Double setara Broco Buah - 14,900.00
722 234 Saklar Double setara Panasonic Buah 49,500.00
723 235 Saklar Engkel setara Broco Buah - 5,800.00
724 236 Saklar Tripel setara Broco Buah - 18,700.00
725 237 Saklar Tripel setara Panasonic Buah 66,000.00
726 238 Spul Contactor Buah - 73,800.00
727 239 Sekring 63 A Buah - 12,100.00
728 240 Solder Pistol Buah - 406,300.00
729 241 Solder Buah - 27,700.00
730 242 Solar Seal / Photo Seal Buah - 166,200.00
731 243 Stop Kontak Buah - 12,700.00
732 244 Steker Arde Buah - 11,100.00
733 245 Steker T Buah - 13,000.00
734 246 Steker PH Buah - 3,800.00
735 247 Sadel No. 6 Bungkus - 1,300.00
736 248 Sadel No. 8 Bungkus - 1,800.00
737 249 Sadel No. 9 Bungkus - 2,000.00
738 250 Sadel No. 10 Bungkus - 3,800.00
739 251 Sadel No. 12 Bungkus - 5,200.00
740 252 Sadel No. 14 Bungkus - 5,600.00
E F G H I J K L
36
37 NO
38 HARGA TERMASUK
39 MATERIAL SATUAN KODE KEUNTUNGAN
40 (OVERHEAD)
41 (Rp)
42
43
741 253 Sadel No. 19 Bungkus - 6,600.00
742 254 Sadel No. 22 Bungkus - 11,200.00
743 255 Skun RS-16 Buah - 1,300.00
744 256 Stater Buah - 3,800.00
745 257 Ston 63 A Buah - 166,300.00
746 258 Stost 40 A + Ip Buah - 70,300.00
747 259 Stost 32 A + Ip Buah - 46,200.00
748 260 Tedus Hitam Buah - 1,000.00
749 261 Tali Tester Buah - 27,700.00
750 262 Tang Amper Buah - 1,200,500.00
751 263 Tang Buaya Buah - 37,000.00
752 264 Tang Potong Buah - 37,000.00
753 265 Tang Kombinasi Buah - 37,000.00
754 266 Tang Jepit Buah - 37,000.00
755 267 Tang Skun Buah - 369,400.00
756 268 Time Swicht Theben Buah - 788,200.00
757 269 Taping Conector 1 baut Buah - 14,300.00
758 270 Taping Conector 2 baut Buah - 23,300.00
759 271 Tespen Buah - 9,300.00
760 272 Timah Solder Buah - 27,700.00
761 273 Terminal 25 ml Buah - 46,200.00
762 274 Tolkit Buah - 83,100.00
763 275 Wide Klem Buah - 8,600.00
764 276 WD 40 Buah - 46,200.00
765 277 Klem Tiang uk. 5" s/d 8" x 2" Set - 256,300.00
766
PERHITUNGAN VOLUME GEDUNG

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME TOTAL


JENIS MATERIAL PANJANG LEBAR TINGGI LUAS/ JUMLAH KUBIKASI KOEFISIENSI/
JUMLAH ITEM KG
I PEKERJAAN PENDAHULUAN

1 Pembersihan Lokasi x = - M2 - M2

2 Bowplank 35.30 + 35.30 + 21.00 + 21.0 112.60 M' 112.60 M'

3 Papan Nama Proyek

II PEKERJAAN PONDASI
1 Pondasi Type P1 42.000
Galian Tanah 1.25 x 1.25 x 1.50 = 2.3 m3x 42.00 = 98.44 m3 98.44 m3

Urugan Pasir t = 15 cm 1.25 x 1.25 x 0.15 = 0.2 m3x 42.00 = 9.84 m3 9.84 m3

Lantai Kerja t = 5 cm 1.25 x 1.25 x 0.05 = 0.1 m3x 42.00 = 3.28 m3 3.28 m3

Cerucuk Dia 12 - 10 m + Pemancangan 3.00 x 3.00 x = 9.0 Btgx 42.00 378.00 btg 378.00 Btgx

beton tapak 1.25 x 1.25 x 0.15 = 0.2 m3x 42.00 = 9.84 m3


beton kolom 0.40 x 0.40 x 1.10 = 0.2 m3x 42.00 = 7.39 m3 17.24 m3

dia.12-150 1.15 + 0.10 x 2.00 sisi 12.0 btg 42.00 = 1,260.00 kg x 0.89 kg 1,121.40 Kg
4 dia.12 1.10 + 4.0 btg 42.00 = 184.80 kg x 0.89 kg 164.47 Kg
dia.8-150 0.35 + x 4.00 sisi 7.3 btg 42.00 = 431.20 kg x 0.40 kg 172.48 Kg 1,458.35 Kg

bekisting tapak 1.25 x 4.00 x 0.15 = 0.8 m2x 42.00 = 31.50 m2


bekisting kolom 0.35 x 4.00 x 1.10 = 1.5 m2x 42.00 = 64.68 m2 96.18 m2

2 Pondasi Type P2
Galian Tanah 0.90 x 0.90 x 12.00 = 9.7 m3x - = - m3 - m3

Urugan Pasir t = 15 cm 0.90 x 0.90 x 0.15 = 0.1 m3x - = - m3 - m3

Lantai Kerja t = 5 cm 0.90 x 0.90 x 0.05 = 0.0 m3x - = - m3 - m3

#REF! 3.00 x 3.00 x = 9.0 Btgx - - btg - Btgx

beton tapak 0.90 x 0.90 x 0.15 = 0.1 m3x - = - m3


beton kolom 0.50 x 0.50 x 1.15 = 0.3 m3x - = - m3 - m3

dia.12-150 0.85 + 0.10 x 2.00 sisi 12.0 btg - = - kg x 0.89 kg - Kg


4 dia.12 1.10 + 4.0 btg - = - kg x 0.89 kg - Kg
dia.8-150 0.25 + x 4.00 sisi 7.3 btg - = - kg x 0.40 kg - Kg - Kg

bekisting tapak 0.90 x 4.00 x 0.15 = 0.5 m2x - = - m2


bekisting kolom 0.35 x 4.00 x 1.15 = 1.6 m2x - = - m2 - m2

2 Sloof 20 x 40 cm beton 15.00 x 4.00 x 1.00 x 0.2 0.40 = 4.80 m3


17.00 x 3.00 x 1.00 x 0.2 0.40 = 4.08

14
PERHITUNGAN VOLUME GEDUNG

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME TOTAL


14.00 x 6.00 x 1.00 x 0.2 0.40 = 6.72
5.00 x 2.00 x 1.00 x 0.2 0.40 = 0.80
3.20 x 2.00 x 1.00 x 0.2 0.40 = 0.51
4.70 x 1.00 x 1.00 x 0.2 0.40 = 0.38
7.00 x 1.00 x 1.00 x 0.2 0.40 = 0.56

17.85 -

9 dia.13 223.10 + 9.0 btg = 2,007.90 kg x 1.04 kg 2,088.22 Kg


dia.8-150 1.55 + 1,115.5 btg = 1,729.03 kg x 0.40 kg 691.61 Kg 2,779.83 Kg

bekisting 223.10 x 0.75 x 2.00 = 334.65 m2 334.65 m2

3 Tutup Kolong 8 x 20 cm tutup kolong 112.60 x 0.08 x 0.25 = - = 2.25 m3 2.25

2 dia.10 112.60 + 2.0 btg = 225.20 kg x 0.40 kg 90.08 Kg


dia.8-150 1.00 + 563.0 btg = 563.00 kg x 0.40 kg 225.20 Kg 315.28 Kg

bekisting 112.60 x 0.20 x 2.00 = = 45.04 m2 45.04 m2

4 Sloof 15 x 35 Cm beton x 0.20 x 0.40 = - = - m3 -

4 dia.13 - + 4.0 btg = - kg x 1.04 kg - Kg


dia.8-150 0.90 + - btg = - kg x 0.40 kg - Kg - Kg

bekisting - x 0.75 x 1.00 = = - m2 - m2

5 Plesteran Tutup Kolong 112.60 0.30 = 33.78 m2 33.78 m2

15
PERHITUNGAN VOLUME GEDUNG

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME TOTAL


III. PEKERJAAN STRUKTUR
1 Kolom 40 x 40 cm 42.000 beton
t=4m 0.30 x 0.30 x 4.50 = 0.4 m3x 42.00 = 17.01
+
17.01 M3

8 D 13 4.00 x 8.00 42.00 = 1,344.00 kg 1.04 1,397.76


dia 8-150 1.40 x 53.3 42.00 = 3,136.00 kg 0.40 1,254.40 + 2,652.16 kg

4 D 13 4.00 x - - = - kg 1.04 -
dia8-150 1.40 x - - = - kg 0.40 - + - kg

bekisting 4.00 x 0.35 x 4.00 = 42.00 = 235.20


- x 0.40 x 0.40 = - = - + 235.20 m2

Plesteran kolom 4.00 x 0.30 x 1.00 = 42.00 = 50.40


- x 0.40 x 0.40 = 42.00 = - kg 50.40 -

2 Kolom 8 x 8 Cm 20.00 beton


t = 3,5 m 0.08 x 0.08 x 4.50 = 0.03 m3x 20.00 = 0.58
= - + 0.58 M3

4D6 4.00 x 4.50 20.00 = 360.00 kg 0.22 79.20


dia 6-150 0.32 x 22.5 20.00 = 144.00 kg 0.22 31.68 + 110.88 kg

4D8 4.00 x - 20.00 = - kg 0.22 -


dia 6-150 0.32 x - 20.00 = - kg 0.22 - + - kg

bekisting 4.50 x 0.16 x 1.00 = 20.00 = 14.40


- x 0.16 x 1.00 = - = - + 14.40 m2

3 Ring Balok 15 x 30 Cm 223.10 beton 0.85


446.20 x 0.15 x 0.30 = 20.1 m3x 1.00 = 20.08 20.08 M3

4 D 13 446.20 x 4.00 = 1,784.80 kg 1.04 1,856.19


dia 8-150 0.90 x 2,231.00 = 2,007.90 kg 0.22 441.74 + 2,297.93 kg

bekisting 446.20 x 0.75 x 1.00 = = 334.65 m2 334.65 m2

4 Ring Balok 8 x 8 Cm 74.37 beton 0.85


63.21 x 0.15 x 0.30 = 2.8 m3x 1.00 = 2.84 2.84 M3

4 D 13 63.21 x 4.00 = 252.85 kg 1.04 262.96


dia 8-150 0.90 x 316.06 = 284.45 kg 0.22 62.58 + 325.54 kg

bekisting 63.21 x 0.45 x 0.45 = = 56.89 m2 56.89 m2

5 Balok jengot 8/20 utk 10.450 beton


nama 8.000 10.45 x 0.10 x 0.30 = 0.3 m3x 1.00 = 0.31
8.50 1.00 0.10 0.9 2.00 1.70 2.01

16
PERHITUNGAN VOLUME GEDUNG

NO URAIAN PEKERJAAN PERHITUNGAN VOLUME TOTAL


4 D 12 10.45 x 4.0 btg 41.80 1.05 43.89
dia 8-150 0.75 x 52.0 btg 39.00 0.40 15.60
10 D 8 8.50 10.00 = 85.00 kg 0.22 18.70
dia 6-150 1.90 x 42.00 = 79.80 kg 0.22 17.56 - 95.75 kg

bekisting 10.45 x 0.45 x 0.45 = = 9.41 m2


8.50 x 2.10 17.85 m2 27.26

7 lantai dan dak Beton 485.00 x 1.00 + x 0.10 48.50 m3


dak 23.00 x 2.00 + 29.00 x 1.0 0.10 7.50 m3 56.00 m3
0.10 - m3
0.10 - m3
0.10 - m3
0.10 - m3

Tulangan 7.00 : 0.15 46.67 0.68 472.83


14.90 : 0.15 99.33 0.68 472.83
945.653 kg

8.00 : 0.15 53.33 0.68 761.60


21.00 : 0.15 140.00 0.68 761.60
1,523.200 kg

5.00 : 0.15 33.33 0.68 340.00


15.00 : 0.15 100.00 0.68 340.00
680.000 kg

10.30 : 0.15 68.67 0.68 560.32


12.00 : 0.15 80.00 0.68 560.32 ### 8,237.07 kg
2,241.280 kg

5.00 : 0.15 33.33 0.68 113.33


5.00 : 0.15 33.33 0.68 113.33
453.333 kg

16.00 : 0.15 106.67 0.68 435.20


6.00 : 0.15 40.00 0.68 435.20
1,740.800 kg

3.00 : 0.15 20.00 0.68 163.20


12.00 : 0.15 80.00 0.68 163.20
652.800 kg

8,237.07 kg

Bekisting 485.00 123.60 25.00 96.0 36.00 974.20 974.20 m2

Dikurangi Sloof 20 x 40 cm 15.00 x 0.20 = 3.0

8 Lantai Ramp beton 3.00 x 12.00 17 0.20 7.20


ENGGINEER ESTIMATE (EE)

NAMA KEGIATAN :

Perencanaan Pembangunan Puskesmas


Sungai Melayu

LOKASI :

KECAMATAN KENDAWANGAN

SUMBER DANA APBN KABUPATEN KETAPANG


TAHUN ANGGARAN 2017
RINCIAN BIAYA PEKERJAAN
PEKERJAAN : Perencanaan Pembangunan Gedung Rehabilitasi Narkoba (Rehabilitasi Intensif) Kendawangan Kecamatan Kendawangan
LOKASI : Kecamatan Kendawangan Kabupaten Ketapang
SUMBER DANA : APBN
TAHUN : 2018

HARGA
VOLUME KODE TOTAL HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN UNIT SATUAN
2016 ANALISA ( Rp. ) HARGA ( Rp. )
( Rp. )
1 2 3 4 5 6 7 8
I. PEKERJAAN PENDAHULUAN
1 Papan Nama Proyek 1.00 bh (LA. 03) 1,350,849.32 1,350,849.32
2 Pembersihan Lokasi 735.00 M2 1,000.00 735,000.00
3 Pengukuran dan Pemasangan Bowplank 116.00 M' A.2.2.1.4 47,842.06 5,549,679.10
Sub Total I 7,635,528.42
II. PEKERJAAN PONDASI
1 Pondasi Type P1
- Galian Tanah 98.44 M³ A.2.3.1.1 67,184.91 6,613,514.21
- Cerucuk Dia 12 - 10 m + Pemancangan 378.00 Btg - 150,000.00 56,700,000.00
- Urugan Pasir t = 15 cm 9.84 M³ A.2.3.1.11 222,661.46 2,191,823.77
- Lantai Kerja t = 5 cm 3.28 M³ A.4.1.1.4 1,048,637.56 3,440,842.00
- Beton K-225 MOLEN 17.24 M³ A.4.1.1.7 1,350,789.23 23,281,865.55
- Tulangan 1,458.35 Kg A.4.1.1.17 20,338.83 29,661,171.94
- Bekisting Pondasi 48.09 M² A.4.1.20 171,656.48 8,254,959.99
2 Pondasi Type P2
3 Sloof 20 x 40 Cm + Tutup Kolong 10 X 20 CM
- Beton K-225 MOLEN 17.85 M³ A.4.1.1.7 1,350,789.23 24,108,886.26
- Tulangan 2,779.83 Kg A.4.1.1.17 20,338.83 56,538,405.65
- Bekisting Sloof 167.33 M² A.4.1.1.21 182,438.98 30,526,601.87
4 Sloof 15 x 30 Cm
- Beton K-225 MOLEN 2.25 M³ A.4.1.1.7 1,350,789.23 3,041,977.36
- Tulangan 315.28 Kg A.4.1.1.17 20,338.83 6,412,426.01
- Bekisting Sloof 22.52 M² A.4.1.1.21 182,438.98 4,108,525.77
5 Sloof 15 x 35 Cm
6 Plesteran Tutup Kolong 33.78 M² A.4.4.2.3 57,938.34 1,957,156.99

Sub Total II 256,838,157.36


III. PEKERJAAN STRUKTUR
1 Kolom 40 x 40 Cm
- Beton K-225 MOLEN 17.01 m3 A.4.1.1.7 1,350,789.23 22,976,924.88
- Tulangan 2,652.16 Kg A.4.1.1.17 20,338.83 53,941,828.71
- Bekisting Kolom MULTIPLEK 9 MM 58.80 M2 A.4.1.1.22 244,322.78 14,366,179.58
2 Kolom 8 x 8 Cm
- Beton K-225 MOLEN 0.58 M³ A.4.1.1.7 1,350,789.23 778,054.60
- Tulangan 110.88 Kg A.4.1.1.17 20,338.83 2,255,169.36
- Bekisting Kolom 7.20 M² A.4.1.1.22 171,656.48 1,235,926.64
3 Plesteran Acian Kolom 40 x 40 50.40 M² A.4.4.2.27 36,900.76 1,859,798.29
4 Ring Balok 15 x 30 Cm
- Beton K-225 MOLEN 20.08 M³ A.4.1.1.7 1,350,789.23 27,122,497.04
- Tulangan 2,297.93 Kg A.4.1.1.17 20,338.83 46,737,205.31
- Bekisting Balok MULTIPLEK 9 MM 83.66 M² A.4.1.1.22 253,516.28 21,209,805.94
5 Ring Balok 8 x 8 Cm
- Beton K-225 MOLEN 2.84 M³ A.4.1.1.7 1,350,789.23 3,842,353.75
- Tulangan 325.54 Kg A.4.1.1.17 20,338.83 6,621,104.09
- Bekisting Balok MULTIPLEK 9 MM 14.22 M² A.4.1.1.22 253,516.28 3,605,667.01
6 Plat Lantai dan Dak
- Beton K-225 MOLEN 56.00 M³ A.4.1.1.7 1,350,789.23 75,644,197.13
- Wiremesh M5 16,474.13 Kg A.4.1.1.19 23,888.74 393,546,232.80
- Bekisting Lantai 153.00 M² A.4.1.1.24.b 195,770.93 29,952,952.09
7 Lantai Ramp
- Beton K-225 MOLEN 7.20 M³ A.4.1.1.22 253,516.28 1,825,317.23
- Wiremesh M5 162.56 Kg A.4.1.1.19 23,888.74 3,883,391.25
- Bekisting Lantai 20.00 M² A.4.1.1.24.b 195,770.93 3,915,418.57
Sub Total III 715,320,024.27
HARGA
VOLUME KODE TOTAL HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN UNIT SATUAN
2016 ANALISA ( Rp. ) HARGA ( Rp. )
( Rp. )
1 2 3 4 5 6 7 8
IV. PEKERJAAN LANTAI, DINDING DAN PLAFOND
1 Lantai Keramik 60 x 60 Cm 485.00 M² P.LD. 04 318,035.90 154,247,409.36
2 Lantai Keramik 20 x 20 Cm 6.00 M² A.4.4.3.36 251,381.85 1,508,291.13
3 Keramik Dinding 20 x 25 Cm 24.00 M² (P.LD. 08) 257,550.99 6,181,223.71
4 Dinding Lapis HPL 50.00 M² A.4.6.1.12 934,194.54 46,709,727.05
5 Dinding Batako 7 x 15 x 30 653.16 M² P.Dnd. 01 99,511.24 64,996,758.55
6 Dinding Bata Merah (variasi facade) untuk Taman
7 Plesteran Dinding Batako 1,306.32 M² A.4.4.2.3 57,938.34 75,686,006.99
8 Urugan tanah 291.00 M3 (A.2.3.1.12) 203,677.50 59,270,152.50
9 Plesteran Pola Garis dan kotak kotak
10 Rangka Hollow dan Dinding Ekspo ACP 125.00 M² - 648,525.77 81,065,721.76
11 Plesteran Acian Balok, Kolom dan Sirip entrance (profil nama) 50.00 M' A.4.4.2.3 57,938.34 2,896,916.80
13 Plafond rangka besi hollow 1 x 40 x 40. 2mm, modul 60 x 60 485.00 M² A.4.2.1.21 195,586.85 94,859,621.97
13 Plafond Gypsum 485.00 M² A.4.5.1.7. 51,969.59 25,205,252.24
14 Sunscreen Aluminium utk pencahayaan dan lobby entrance tangga M² A.4.2.1.9 544,519.21 -
Sub Total IV 612,627,082.05
V. PEKERJAAN KUDA - KUDA DAN ATAP
1 Kuda - kuda ringan (truss) 547.40 M² - 215,432.25 117,928,489.00
2 Atap Spandek Aluminium 0,35 547.40 M² A.4.5.2.32 121,884.96 66,720,324.24
3 Nok Aluminium 57.00 M' A.4.5.2.42 188,078.46 10,720,472.05
4 Lisplank Rangka Hollow ACP 495.55 M' - 648,525.77 321,376,947.35
Sub Total V 516,746,232.64
VI. PEKERJAAN PINTU, JENDELA DAN VENTILASI
1 Kaca Tempered Polos 12 mm + handle stainless 2.00 unit - 4,840,750.43 9,681,500.87
2 Kaca Tempered Polos 12 mm + Aksesoris 1.00 unit - 36,700,000.00 36,700,000.00
3 Bingkai ACP Pintu Tempret 6.23 M² (P.L.D.01) 721,534.26 4,495,158.41
4 Kusen Aluminium 491.37 M' A.4.2.1.11 177,822.52 87,376,650.72
5 Daun Pintu Multiplek Finish HPL 21.60 M² A.4.6.1.12 934,194.54 20,178,602.08
6 Jendela dan Ventilasi Kaca Rangka Aluminium 28.14 M² A.4.2.1.13 610,769.12 17,187,043.05
7 Kaca Mati Polos t = 5 mm 86.76 M² A.4.6.2.17 220,755.26 19,152,726.46
Sub Total VI 194,771,681.59
VII PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Handle Pintu 10.00 bh A.4.6.2.13 181,915.96 1,819,159.56
2 Kunci tanam 10.00 bh A.4.6.2.2 206,714.43 2,067,144.29
3 Engsel Pintu 52.00 bh A.4.6.2.5 31,408.34 1,633,233.90
4 Door stopper 7.00 bh A.4.6.2.5 135,452.89 948,170.20
5 Pemasangan Door Closer 7.00 bh A.4.6.2.10 287,653.36 2,013,573.52
6 Handle Jendela 52.00 bh A.4.6.2.13 30,836.11 1,603,477.49
7 Engsel Jendela dan ventilasi 104.00 bh A.4.6.2.6 22,448.46 2,334,639.39
8 Slot Pintu 54.00 bh A.4.6.2.11 53,432.11 2,885,334.01
9 Slot utk Jendela 52.00 bh A.4.6.2.12.a 36,679.51 1,907,334.59
10 Kait Angin 1 set 2 bh 52.00 bh A.4.6.2.9 29,386.00 1,528,072.07
Sub Total VI 18,740,139.00
VIII. SISTEM PUMBING DAN SANITASI
1 Kloset Jongkok 3.00 bh A.5.1.1.2 780,493.98 2,341,481.93
2 Kran Air 3.00 bh A.5.1.1.19 71,652.42 214,957.26
3 Jet Shower 3.00 A.5.1.1.19 114,214.92 342,644.76
4 Floor drain (setara Toto) 3.00 A.5.1.1.14 191,412.84 574,238.53
5 Westafle Zing 2.00 A.5.1.1.12 1,977,266.34 3,954,532.68
6 Septictank 2 x 1,2 x 1,2
- Pek. Galian Tanah 2.40 m3 A.2.3.1.1 67,184.91 161,243.78
- Cerucuk dia 8-10 p. 4 m 15.00 btg 150,000.00 2,250,000.00
- Mengurug Pasir Alas t. 15 cm 0.36 m3 A.2.3.1.11 222,661.46 80,158.13
- Mengerjakan Lantai Kerja t. 5cm 0.12 m3 A.4.1.1.4 1,048,637.56 125,836.51
- Beton K175 1.87 m3 A.4.1.1.5 1,266,248.64 2,370,417.46
- Tulangan wiremesh M 5 2 lapis 53.16 kg A.4.1.1.19 23,888.74 1,270,039.91
- Bekisting 24.96 m2 A.4.1.20 171,656.48 4,284,545.67
7 Instalasi Air Bersih Pipa pvc 1" 32.00 m A.5.7.1.27 266,270.63 8,520,660.00
8 Instalasi Air Kotor
- Pipa pvc 2" 72.00 m A.5.1.1.29 304,570.29 21,929,060.98
- Pipa pvc 3" kloset 12.00 m A.5.1.1.31 601,128.81 7,213,545.66
9 Mesin Jet Pump Kap. 250 watt 1.00 unit 4,752,000.00 4,752,000.00
10 Ground Tank 2 x 1,5 x 1,5 4 (empat unit)
- Pek. Galian Tanah 7.43 m3 A.2.3.1.1 67,184.91 498,847.93
- Cerucuk dia 8-10 p. 4 m 60.00 btg - 75,000.00 4,500,000.00
- Tulangan wiremesh M 5 2 lapis 210.87 kg A.4.1.1.19 23,888.74 5,037,417.90
- Bekisting 24.75 m2 A.4.1.20 171,656.48 4,248,497.81
Sub Total VII 74,670,126.89
HARGA
VOLUME KODE TOTAL HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN UNIT SATUAN
2016 ANALISA ( Rp. ) HARGA ( Rp. )
( Rp. )
1 2 3 4 5 6 7 8
IX. PEKERJAAN SISTEM ELEKTRIKAL
1 Pekerjaan Panel Daya
- Instalasi kabel power (dari MDP ke SDP tiap ruang) NYM 3 x 2,5 c 5.00 roll 600,000.00 3,000,000.00
- MDP box panel uk. 40 x 60 x 20 + Busbar/ lengkap time swicth 1.00 bh 650,000.00 650,000.00
- Volltmeter 1.00 Unit 55,000.00 55,000.00
- Lampu Indikator RST + Fuse 2A 1.00 Unit 15,000.00 15,000.00
- MCB 16 A 1 phase setara panasonic 1.00 bh 37,500.00 37,500.00
- MCB 10 A 1 phase ex panasonic 1.00 bh 37,500.00 37,500.00
- NFB 3 x 35 A 1.00 bh 235,000.00 235,000.00
- NFB 3 x 20 A 1.00 bh 205,000.00 205,000.00
- Grounding BC 35 mm2 ex tembaga 10.00 bh 35,000.00 350,000.00
- Grounding BC 16 mm2 ex tembaga 5.00 bh 18,000.00 90,000.00
- Kabel Tray 300 x 100 untuk listrik 20.00 m1 47,000.00 940,000.00
2 Pekerjaan Penerangan dan Stop Kontak
- Instalasi Lampu/ penerangan (NYM 3 x 1,5) 68.00 bh 70,000.00 4,760,000.00
- Instalasi stop kontak (NYM 3 x 2,5) + pasang pipa d 1" 20.00 bh 70,000.00 1,400,000.00
- Fitting Downlight 4" (setara panasonic) 30.00 bh 68,000.00 2,040,000.00
- Lampu LED SL 18 watt (setara Philips) 30.00 bh 180,000.00 5,400,000.00
- Lampu LED SL 8 watt (setara Philips) 20.00 bh 55,000.00 1,100,000.00
- TL Box inbow 36 Watt 76.00 bh 140,000.00 10,640,000.00
- Stop Kontak inbow 16 A (setara panasonic) 15.00 bh 31,130.00 466,950.00
- Saklar 1 / tunggal ( setara panasonic ) 10.00 bh 20,000.00 200,000.00
- Saklar 2 ( setara panasonic ) 5.00 bh 25,000.00 125,000.00
- Pipa PVC Ø = 1" x 4 M' 15.00 m1 53,350.22 800,253.32
Sub Total VIII 32,547,203.32
X. PEKERJAAN PENGECATAN
1 Cat Plafond 970.00 M² A.4.7.1.10 36,796.19 35,692,306.88
2 Cat Tembok 1,306.32 M² A.4.7.1.10 36,796.19 48,067,602.39
3 Cat Kilat 214.28 M² A.4.7.1.4 65,651.00 14,067,761.93
Sub Total IX 97,827,671.20
XI PEKERJAAN LAIN - LAIN
1 Interior dan mebluer front office pendaftaran 1.00 Ls 45,000,000.00 45,000,000.00
2 Profil Nama Gedung 1.00 set 12,000,000.00 12,000,000.00
Sub Total X 57,000,000.00
JUMLAH TOTAL 2,584,723,846.72
REKAPITULASI ENGINEER'S ESTIMATE

PEKERJAAN : Perencanaan Pembangunan Gedung Rehabilitasi Narkoba (Rehabilitasi Intensif)


Kendawangan Kecamatan Kendawangan
LOKASI : Kecamatan Kendawangan Kabupaten Ketapang
SUMBER DANA : APBN
TAHUN ANGGARAN : 2018

BIAYA TOTAL
NO. URAIAN PEKERJAAN
(Rp.)
1 2 4

I PEKERJAAN PENDAHULUAN 7,635,528.42


II PEKERJAAN PONDASI 256,838,157.36
III PEKERJAAN STRUKTUR 715,320,024.27
IV PEKERJAAN LANTAI, DINDING DAN PLAFOND 612,627,082.05
V PEKERJAAN KUDA - KUDA DAN ATAP 516,746,232.64
VI PEKERJAAN PINTU, JENDELA DAN VENTILASI 194,771,681.59
VII PEKERJAAN PENGUNCI DAN PENGGANTUNG 18,740,139.00
VIII SISTEM PUMBING DAN SANITASI 74,670,126.89
IX PEKERJAAN SISTEM ELEKTRIKAL 32,547,203.32
X PEKERJAAN PENGECATAN 97,827,671.20
XI PEKERJAAN LAIN - LAIN 57,000,000.00

JUMLAH TOTAL 2,584,723,846.72


PPN 10 % 258,472,384.67
JUMLAH TOTAL + PPN 10 % 2,843,196,231.39
DIBULATKAN 2,843,196,000.00
TERBILANG : DUA MILYAR DELAPAN RATUS JUTA EMPAT PULUH TIGA JUTA SERATUS SEMBILAN PULUH ENAM RIBU
RUPIAH

Ketapang, 2018
HARGA SATUAN
NO URAIAN PEKERJAAN (KODE ANALISA SNI 2016)
(Rp)
1 2 3
A. PEKERJAAN PENDAHULUAN
1 1m1 Pengukuran dan Pemasangan Bouwplank (A.2.2.1.4) 47,501.76
2 1m2 pemasangan pagar jaring panjang 240 cm (A.2.2.1.15) 23,241.83
3 1m2 Membersihkan Lapangan dan Perataan (A.2.2.1.9) 14,241.41
4 1m2 Pembuatan Direksi Keet / Bedeng Pekerja (A.2.2.1.8) 854,634.06
5 1 buah Pembuatan papan nama pekerjaan (LA. 03) analisa ketapang 1,356,957.76
B. PEKERJAAN TANAH
1 Menggali 1m3 Tanah Biasa sedalam 1 meter (A.2.3.1.1) 67,184.91
2 Mengurug Kembali 1m3 Galian (A.2.3.1.9) 48,563.81
3 Mengurug 1m3 dengan Pasir Urug (A.2.3.1.11) 160,009.46
D. PEKERJAAN BETON
1 Membuat 1m3 Beton Mutu f'c = 7,4 Mpa (K 100), slump (12 ± 2) cm, w/c = 0,87 (A.4.1.1.1) 1,125,357.25
2 Membuat 1m3 Beton Mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm, w/c = 0,78 (A.4.1.1.2) 1,180,272.16
3 Membuat 1m3 Beton Mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm, w/c = 0,72 (A.4.1.1.3) 1,221,857.39
4 Membuat 1m3 Beton Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K 100), slump (3-6) cm, w/c = 0,87 (A.4.1.1.4) 1,057,619.83
5 Membuat 1m3 Beton Mutu f'c = 14,5 Mpa (K 175), slump (12 ± 2) cm, w/c = 0,66 (A.4.1.1.5) 1,272,875.72
6 Membuat 1m3 Beton Mutu f'c = 16,9 Mpa (K 200), (A.4.1.1.6) 1,318,639.71
7 Membuat 1m3 Beton Mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0,58 (A.4.1.1.7) 1,357,297.85
8 Membuat 1m3 Beton Mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0,58 (A.4.1.1.7)/molen 1,385,672.85
9 Membuat 1m3 Beton Mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm, w/c = 0,56 (A.4.1.1.8) 1,377,045.71
10 Membuat 1m3 Beton Mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm, w/c = 0,52 (A.4.1.1.10) 1,421,222.53
11 Membuat 1m3 Beton Mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm, w/c = 0,52 (A.4.1.1.10)/ molen 1,449,597.53
12 Pembesian 10Kg dengan Besi Polos atau Ulir (A.4.1.1.17) 20,682.07
13 Memasang 10Kg Jaring Kawat Baja/Wire Mesh (A.4.1.1.19) 23,953.86
14 Memasang 1m2 Bekisting untuk Pondasi (A.4.1.1.20) 153,499.44
15 Memasang 1m2 Bekisting untuk Pondasi (A.4.1.1.20) papan mal 155,201.94
16 Memasang 1m2 Bekisting untuk Sloof (A.4.1.1.21) 162,011.94
17 Memasang 1m2 Bekisting untuk Kolom (A.4.1.1.22) MULTIPLEK 9 MM 271,330.15
18 Memasang 1m2 Bekisting untuk Kolom (A.4.1.1.22) PAPAN 250,048.90
19 Memasang 1m2 Bekisting untuk Balok (A.4.1.1.23)/ MULTIPLEK 9 MM 280,523.65
20 1m2 Pasang Bekisting untuk Balok (A.4.1.1.23)/ PAPAN 259,242.40
21 Memasang 1m2 Bekisting untuk Lantai (A.4.1.1.24)/MULTIPLEK 325,810.15
22 1m2 Pasang Bekisting untuk Lantai (A.4.1.1.24) PAPAN 301,123.90
23 Memasang 1m2 Bekisting untuk Tangga (A.4.1.1.26) MULTIPLEK 267,925.15

Rekap SNI 2016 23


HARGA SATUAN
NO URAIAN PEKERJAAN (KODE ANALISA SNI 2016)
(Rp)
1 2 3

1 Pemasangan Kg besi profil (A.4.2.1.1) 58,694.29


2 Pemasangan 1 kg Rangka Kuda-kuda baja IWF/ Struktur (A.4.2.1.2) 84,799.29
3 Pengerjaan 100 Kg Pekerjaan Perakitan (A.4.2.1.3) 42,714.02
4 Pengerjaan 10 cm Pengelasan dengan las listrik (A.4.2.1.5) 68,321.89
5 Pengerjaan 1 m2 pintu rolling/ folding door (A.4.2.1.7) 537,692.06
6 Pengerjaan 1 m2 sunscreen alluminium (A.4.2.1.9) 545,770.96
7 Memasang 1m kusen pintu alluminium (A.4.2.1.11) 177,830.45
8 Pemasangan 1m2 pintu alluminium (A.4.2.1.12) 829,659.03
9 Memasang 1m2 pintu kaca rangka alluminium (A.4.2.1.13) 611,588.15
10 Memasang 1m' talang datar/ jurai seng bjls 30 lebar 90 cm (A.4.2.1.18) 174,581.62
11 1m2 Pasang Talang Miring Seng BJLS 30 / Jurai Dalam (P.BA. 11) 199,067.19
12 10m1 Talang Cucuran Atap 1/2 Lingkaran Ø 15cm BJLS 30 (P.BA. 12) 130,087.32
13 10m1 Pemasangan Pipa Pembuangan dari Talang Atap Ø 8cm BJLS 30 (P.BA. 13) 84,278.43
14 Pemasangan 1 m2 rangka besi hollow 1 x 40 x 40. 2mm, modul 60 x 60 cm partisi (A.4.2.1.20) 159,047.32
15 1m2 Pemasangan rangka besi hollow 1 x 40 x 40. 2mm, modul 60 x 60 cm plafond (A.4.2.1.21) 195,646.29
16 Pemasangan 1 m2 atap pelana rangka baja ringan canai profil C57 (A.4.2.1.22) 235,216.52
17 Pemasangan 1 m2 jurai / gording atap rangka baja ringan canai profil c57 (A.4.2.1.23) 209,295.08

1 Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 batu campuran 1 SP : 3 PP (A.4.4.1.8) 158,284.03
2 1m2 Pasang Batako uk. 15/30/7(P.Dnd. 01) 100,178.09
3 1m2 Pasang Batako uk. 15/30/8 (P.Dnd. 02) 100,178.09
PEKERJAAN PLESTERAN
1 Memasang 1m2 Plesteran 1PC : 2PP, tebal 15 mm (A.4.4.2.2) 64,689.09
2 Memasang 1m2 Plesteran Traso 1PC : 2 traso, tebal 10 mm (A.4.4.2.22) 136,486.30
3 Pemasang 1m2 finishing siar bata merah (A.4.4.2.24) 28,948.46
4 Memasang 1m2 Acian (A.4.4.2.27) 36,649.15
5 Memasang 1m2 Plesteran 1PC : 3PP, tebal 15 mm (A.4.4.2.3) 57,454.39

Rekap SNI 2016 24


HARGA SATUAN
NO URAIAN PEKERJAAN (KODE ANALISA SNI 2016)
(Rp)
1 2 3
PEKERJAAN LANTAI & DINDING
1 Memasang 1m2 Lantai Keramik ukuran (20 x 20) cm (A.4.4.3.36) 250,644.43
2 Memasang 1m2 Lantai Keramik ukuran (30 x 30) cm (A.4.4.3.35) 252,939.62
3 Pemasang 1m2 Lantai parquet kayu (A.4.4.3.46) 345,355.85
4 Pemasang 1m2 Lantai dan dinding ACP 648,525.77
5 1m2 Pasang Lantai Keramik 60 x 60cm Polished (setaraf Decogress) (P.LD. 04) 317,216.40
6 1m2 Pasang Lantai Keramik 30 x 60cm Polished (setaraf Decogress) (P.LD. 03) 375,064.74
7 1m2 Pasang Lantai Keramik 40 x 40cm Unpolished (setaraf Indogress) (P.LD. 5) 280,679.14
8 Memasang 1 m2 dinding keramik ukuran (20 x 20) cm (A.4.4.3.50) 257,677.46
9 1m2 Pasang Dinding Keramik 20 x 25cm (P.LD. 08) 257,568.15
10 1m2 Pasang Dinding Keramik 30 x 30cm (P.LD. 09) 215,762.07
11 1m2 Pasang Dinding Keramik 40 x 40cm (P.LD. 10) 224,853.15
12 1m2 Pemasangan Paving Block (P.LD. 12) 165,215.00
13 1m2 Pemasangan Paving Stone (P.LD. 13) 270,215.00
14 Pemasangan 1 m2 lantai vynil ukuran 30 x 30 (A.4.4.3.59) 657,784.82
15 Pemasangan 1 m' plint vynil ukuran 15 x 30 (A.4.4.3.62) 110,797.00
16 Pemasangan 1 m2 paving block natural tebal 8 cm (A.4.4.3.65) 163,454.08
PEKERJAAN PLAFOND
1 Memasang 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9 mm (A.4.5.1.7) 59,528.27
2 Memasang 1 m' list langit-langit kayu/ gypsum profil (A.4.5.1.9) 27,209.85
3 1m2 Langit-langit GRC (A.4.5.1.7.a) 53,165.91
PEKERJAAN PENUTUP ATAP
1 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana (A.4.5.2.32) 122,257.66
2 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai (A.4.5.2.33) 170,614.34
3 Pemasangan 1 m2 Nok genteng metal (A.4.5.2.37) 87,426.43
4 Pemasangan 1 m2 atap aluminium (A.4.5.2.41) 202,193.30
5 Pemasangan 1 m2 Nok atap aluminium (A.4.5.2.42) 188,385.31
6 1m2 Pasang Aluminium Foil / Sealation (A.4.5.2.43) 92,104.40
PEKERJAAN KAYU
1 Membuat dan Memasang 1m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas Belian (A.4.6.1.1) 13,107,399.95
2 1m3 Pekerjaan Rangka Badan Kayu Belian (P.K. 06) 13,770,212.54
3 Membuat dan Memasang 1m2 Daun Pintu Panel, Kayu Kelas I dan II (A.4.6.1.5) 610,927.94
4 Membuat dan Memasang 1m2 Pintu dan Jendela Jalusi Kayu Kelas I Belian (P.K. 16) 1,071,283.94
5 Membuat dan Memasang 1m2 Pintu dan Jendela Jalusi Kayu Kelas II (P.K. 17) 567,797.94
6 923,073.95
7 Pemasangan 1 m' lisplank kayu belian ukuran 3 x 30 cm (A.4.6.1.22) 137,869.51

Rekap SNI 2016 25


HARGA SATUAN
NO URAIAN PEKERJAAN (KODE ANALISA SNI 2016)
(Rp)
1 2 3
PEKERJAAN KUNCI DAN KACA
1 1 Buah Pemasangan Kunci Tanam (A.4.6.2.2) 144,566.09
2 Pemasangan 1 buah kunci kamar mandi (A.4.6.2.3) 144,566.09
3 1 Buah Pemasangan Kunci Silinder (A.4.6.2.4) 153,423.35
4 1 Buah Pemasangan Engsel Pintu (A.4.6.2.5) 31,422.18
5 1 Buah Pemasangan Engsel Jendela kupu-kupu (A.4.6.2.6) 22,462.29
6 1 Buah Pemasangan Kait Angin (A.4.6.2.9) 32,235.60
7 1 Buah Pemasangan Door Closer (A.4.6.2.10) 135,657.82
8 1 Buah Pemasangan Slot Pintu (A.4.6.2.11) 53,708.77
9 1 Buah Pemasangan Slot Jendela (A.4.6.2.11.a) 36,679.51
10 1 Buah Pemasangan Handle Pintu (A.4.6.2.13) 181,915.96
11 1 Buah Pemasangan Handle jendela (A.4.6.2.13) 30,836.11
12 1 Buah Pemasangan Door Stoper (A.4.6.2.13) 81,922.46
13 1 m2 Pemasangan Kaca Tebal 5mm (A.4.6.2.17) 244,788.34
14 1 m2 Pemasangan Kaca Tebal 12mm (P.KK. 10) 306,785.10
PEKERJAAN PENGECATAN
1 1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 2Lapis Cat KIlat Penutup) (A.4.7.1.4) 69,365.75
2 1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 3 Lapis Cat Kilat Penutup) (A.4.7.1.5) 85,978.32
3 1m2 Pelaburan Bidang Kayu dengan Teak Oil (A.4.7.1.6) 37,847.96
4 1m2 Pelaburan Bidang Kayu dengan Politur (A.4.7.1.7) 43,591.07
5 1m2 Pelaburan Bidang Kayu Dengan Vernis (A.4.7.1.9) 43,213.20
1m2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) Dengan Cat Mutu
6 Baik. (A.4.7.1.10) 37,503.11
1m2 Pengecatan Tembok Lama (1 Lapis Cat Dasar, 2 Lapis Cat Penutup) Dengan Cat Mutu Baik.
7 (A.4.7.1.11) 27,529.00
8 1m2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah (A.4.7.1.17) 79,257.48
9 pemasangan 1 m2 wallpaper (A.4.7.1.15) 32,581.74
PEKERJAAN SANITASI
1 Pemasangan 1 Buah Kloset Duduk / Monoblok (A.5.1.1.1) 1,868,812.97
2 Pemasangan Kloset Jongkok Keramik (A.5.1.1.2) 782,596.69
3 Pemasangan 1 buah westafel (A.5.1.1.5) 1,287,595.08
4 Pemasangan 1 buah bak fiberglass vol 1 m3 (A.5.1.1.10) 2,466,982.09
5 Pemasangan 1 buah bak cuci piring stainlessteel (A.5.1.1.12) 1,980,355.66
6 Pemasangan 1 buah floor drain (A.5.1.1.14) 38,847.93
7 Pemasangan 1 bh kran diamter 1/2" atau 3/4 " (A.5.1.1.19) 76,723.59
8 Pemasangan 1 bh kranJet Spray 1/2" atau 3/4 " (A.5.1.1.19) 123,400.46
9 Pemasangan 1 m' pipa galvanis diameter 3/4 " (A.5.1.1.20) 221,609.00
10 Pemasangan 1 m' pipa galvanis diameter 1 " (A.5.1.1.21) 460,523.43
11 Pemasangan 1 m' pipa galvanis diameter 1,1 /5 " (A.5.1.1.22) 676,834.21
12 Pemasangan 1 m' pipa PVC tipe AW diameter 1/2" (A.5.1.1.25) 176,310.56
13 Pemasangan 1 m' pipa PVC tipe AW diameter 3/4" (A.5.1.1.26) 231,521.72
14 Memasang 1m1 Pipa PVC Tipe AW Ø 1" (A.5.7.1.27) 266,324.98
15 Memasang 1m1 Pipa PVC Tipe AW Ø 2" (A.5.1.1.29) 304,762.96
16 Memasang 1m1 Pipa PVC Tipe AW Ø 3" (A.5.1.1.31) 601,576.76

1 1m3 Pekerjaan Bongkaran Beton Bertulang (P.Bkr. 01) 609,769.61


2 1m2 Pekerjaan Bongkaran Plesteran Dinding 7,120.71
3 1m2 Pekerjaan Bongkaran Lantai Papan 5,422.46
4 1m2 Pekerjaan membongkar plafond (bongkaran tidak di pakai) 11,291.83
5 1m2 Pekerjaan Bongkaran Atap Genteng / Sirap (bongkaran tidak di pakai) 2,848.28
6 1m2 Pekerjaan Bongkaran reng kaso (bongkaran tidak di pakai) 5,258.60
7 Pembongkaran 1 m3 beton bertulang (A. 2.2.1.13) 1,181,838.22
8 1m2 Pekerjaan Bongkaran Dinding Tembok Plesteran Simpai (P. Bkr. 02) 91,466.81
9 1m2 Pekerjaan Bongkaran Lantai Ubin / Keramik (P.Bkr. 03) 4,573.34

Rekap SNI 2016 26


A. PEKERJAAN PERSIAPAN (P.Ps)

1m1 Pengukuran dan Pemasangan Bouwplank (A.2.2.1.4)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 99,750.00 0.100 9,975.00
2 Pekerja OH 75,600.00 0.100 7,560.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 19,031.25
B BAHAN
1 Kayu Bulat Ø 6 - 8 Cm / 4 M' Btg 9,500.00 1.000 9,500.00
2 Paku Besi uk. 2" - 4 " Kg 16,017.29 0.020 320.35
3 Papan Kayu Camp. ( Klas III ) M3 1,900,000.00 0.007 13,300.00
Jumlah 23,120.35
C Jumlah A + B 42,151.60
D Overhead & Profit 13.50% 5,690.47
F Harga Satuan 47,842.06

1m2 pemasangan pagar jaring panjang 240 cm (A.2.2.1.15)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang OH 99,750.00 0.100 9,975.00
2 Pekerja OH 75,600.00 0.100 7,560.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 19,031.25
B BAHAN
1 Jaring Kasa debu lbr 10,056.28 0.143 1,442.07
Jumlah 1,442.07
C Jumlah A + B 20,473.32
D Overhead & Profit 13.500% 2,763.90
F Harga Satuan 23,237.22

1m2 Membersihkan Lapangan dan Perataan (A.2.2.1.9)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.100 7,560.00
2 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 12,547.50
C Jumlah A + B 12,547.50
D Overhead & Profit 13.50% 1,693.91
F Harga Satuan 14,241.41

1m2 Pembuatan Direksi Keet / Bedeng Pekerja (A.2.2.1.8)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 99,750.00 2.000 199,500.00
2 Pekerja OH 75,600.00 1.000 75,600.00
3 Kepala Tukang OH 99,750.00 0.200 19,950.00
4 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 300,037.50
B BAHAN
1 Kayu Bulat Ø 8 - 12 Cm / 4 M' Btg 9,500.00 1.250 11,875.00
2 Papan Kayu Camp. ( Klas III ) M3 1,900,000.00 0.186 353,400.00
3 Paku Besi uk. 2" - 4 " Kg 16,017.29 0.300 4,805.19
4 Seng Gelombang BJLS 0.20 Lbr 44,432.25 1.500 66,648.38
5 Plywood 4 mm Lbr 62,029.00 1.3500 83,739.15
Jumlah 520,467.71
C Jumlah A + B 820,505.21
D Overhead & Profit 13.50% 110,768.20
F Harga Satuan 931,273.42

1 buah Pembuatan papan nama pekerjaan (LA. 03) analisa ketapang

Persiapan 27
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja Tak terlatih OH 75,600.00 1.000 75,600.00
2 Tukang OH 99,750.00 1.000 99,750.00
3 kepala tukang OH 99,750.00 0.100 9,975.00
4 tukang cat dan tulis OH 99,750.00 1.500 149,625.00
5 Mandor OH 99,750.00 0.100 9,975.00
Jumlah 344,925.00
B BAHAN
1 Multiplek 12 mm lbr 231,729.00 1.000 231,729.00
2 Balok Kayu Klas II Ketam M3 3,000,000.00 0.077 231,000.00
3 Paku Besi uk. 2" - 4 " kg 16,017.29 1.250 20,021.61
4 Cat Meni Kayu kg 145,000.00 2.500 362,500.00
Jumlah 845,250.61
C Jumlah A + B 1,190,175.61
D Overhead & Profit 13.50% 160,673.71
F Harga Satuan 1,350,849.32

Persiapan 28
B. PEKERJAAN TANAH (P.T.)

Menggali 1m3 Tanah Biasa sedalam 1 meter (A.2.3.1.1)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.750 56,700.00
2 Mandor OH 99,750.00 0.025 2,493.75
Jumlah 59,193.75
B Jumlah A 59,193.75
C Overhead & Profit 13.50% 7,991.16
D Harga Satuan 67,184.91

Mengurug Kembali 1m3 Galian (A.2.3.1.9)


Mengurug kembali 1m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.500 37,800.00
2 Mandor OH 99,750.00 0.0500 4,987.50
Jumlah 42,787.50
B Jumlah A 42,787.50
C Overhead & Profit 13.50% 5,776.31
D Harga Satuan 48,563.81

Mengurug 1m3 dengan Pasir Urug (A.2.3.1.11)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.300 22,680.00
2 Mandor OH 99,750.00 0.010 997.50
Jumlah 23,677.50
B BAHAN
1 Pasir Beton M3 143,750.00 1.200 172,500.00
Jumlah 172,500.00
C Jumlah A + B 196,177.50
D Overhead & Profit 13.50% 26,483.96
E Harga Satuan 222,661.46

Tanah 29
D. PEKERJAAN BETON

Membuat 1m3 Beton Mutu f'c = 7,4 Mpa (K 100), slump (12 ± 2) cm, w/c = 0,87 (A.4.1.1.1)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 247.000 412,047.87
2 Pasir Kg 102.68 869.000 89,227.68
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 999.000 320,885.69
4 Air Liter 0.00 0.000 0.00
Jumlah 822,161.24
C Jumlah A + B 985,404.74
D Overhead & Profit 13.50% 133,029.64
E Harga Satuan 1,118,434.38

Membuat 1m3 Beton Mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm, w/c = 0,78 (A.4.1.1.2)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 276.000 460,425.96
2 Pasir Kg 102.68 828.000 85,017.86
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,012.000 325,061.38
4 Air Liter 0.00 215.000 0.00
Jumlah 870,505.20
C Jumlah A + B 1,033,748.70
D Overhead & Profit 13.50% 139,556.07
E Harga Satuan 1,173,304.77

Membuat 1m3 Beton Mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm, w/c = 0,72 (A.4.1.1.3)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 299.000 498,794.79
2 Pasir Kg 102.68 799.000 82,040.18
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,017.000 326,667.41
4 Air Liter 0.00 215.000 0.00
Jumlah 907,502.38
C Jumlah A + B 1,070,745.88
D Overhead & Profit 13.500% 144,550.69
E Harga Satuan 1,215,296.58

Membuat 1m3 Beton Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K 100), slump (3-6) cm, w/c = 0,87 (A.4.1.1.4)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.200 90,720.00
2 Tukang Batu OH 99,750.00 0.200 19,950.00
3 Kepala Tukang OH 99,750.00 0.020 1,995.00
4 Mandor OH 99,750.00 0.060 5,985.00
Jumlah 118,650.00
B BAHAN
1 Semen Portland Kg 1,668.21 230.000 383,688.30
2 Pasir Kg 102.68 893.000 91,691.96
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,027.000 329,879.48
4 Air Liter 0.00 200.000 0.00
Jumlah 805,259.75
C Jumlah A + B 923,909.75
D Overhead & Profit 13.500% 124,727.82
E Harga Satuan 1,048,637.56

Membuat 1m3 Beton Mutu f'c = 14,5 Mpa (K 175), slump (12 ± 2) cm, w/c = 0,66 (A.4.1.1.5)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00

Beton 30
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 326.000 543,836.46
2 Pasir Kg 102.68 760.000 78,035.71
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,029.000 330,521.90
4 Air Liter 0.00 215.000 0.00
Jumlah 952,394.07
C Jumlah A + B 1,115,637.57
D Overhead & Profit 13.500% 150,611.07
E Harga Satuan 1,266,248.64

CATATAN : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20%

Beton 31
Membuat 1m3 Beton Mutu f'c = 16,9 Mpa (K 200), (A.4.1.1.6)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 352.000 587,209.92
2 Pasir Kg 102.68 731.000 75,058.04
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,031.000 331,164.31
4 Air Liter 0.00 215.000 0.00
Jumlah 993,432.27
C Jumlah A + B 1,156,675.77
E Overhead & Profit 13.500% 156,151.23
F Harga Satuan 1,312,826.99

Membuat 1m3 Beton Mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0,58 (A.4.1.1.7)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 371.000 618,905.91
2 Pasir Kg 102.68 698.000 71,669.64
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,047.000 336,303.62
4 Air Liter 0.00 215.000 0.00
Jumlah 1,026,879.17
C Jumlah A + B 1,190,122.67
E Overhead & Profit 13.500% 160,666.56
F Harga Satuan 1,350,789.23
CATATAN : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20%

Membuat 1m3 Beton Mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0,58 (A.4.1.1.7)/molen
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 371.000 618,905.91
2 Pasir Kg 102.68 698.000 71,669.64
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,047.000 336,303.62
4 Air Liter 0.00 0.000 0.00
Jumlah 1,026,879.17
C PERALATAN
Molen sewa/hari 0.25 100,000 25,000.00
D Jumlah A + B 1,215,122.67
E Overhead & Profit 13.500% 164,041.56
F Harga Satuan 1,379,164.23
CATATAN : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20%

Membuat 1m3 Beton Mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm, w/c = 0,56 (A.4.1.1.8)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 384.000 640,592.64
2 Pasir Kg 102.68 692.000 71,053.57
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,039.000 333,733.97
4 Air Liter 0.00 215.000 0.00
Jumlah 1,045,380.18
C Jumlah A + B 1,208,623.68
D Overhead & Profit 13.500% 163,164.20
E Harga Satuan 1,371,787.87

Membuat 1m3 Beton Mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm, w/c = 0,52 (A.4.1.1.10)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA

Beton 32
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 413.000 688,970.73
2 Pasir Kg 102.68 681.000 69,924.11
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,021.000 327,952.24
4 Air Liter 0.00 215.000 0.00
Jumlah 1,086,847.08
C Jumlah A + B 1,250,090.58
D Overhead & Profit 13.500% 168,762.23
E Harga Satuan 1,418,852.81
CATATAN : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20%

Beton 33
Membuat 1m3 Beton Mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm, w/c = 0,52 (A.4.1.1.10)/ molen
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.650 124,740.00
2 Tukang Batu OH 99,750.00 0.275 27,431.25
3 Kepala Tukang OH 99,750.00 0.028 2,793.00
4 Mandor OH 99,750.00 0.083 8,279.25
Jumlah 163,243.50
B BAHAN
1 Semen Portland Kg 1,668.21 413.000 688,970.73
2 Pasir Kg 102.68 681.000 69,924.11
3 Batu pecah 1-2 cm (Kerikil) Kg 321.21 1,021.000 327,952.24
4 Air Liter 0.00 215.000 0.00
Jumlah 1,086,847.08
C BAHAN
Molen sewa/hari 0.25 100,000 25,000.00
Jumlah 25,000.00
C Jumlah A + B + C 1,275,090.58
D Overhead & Profit 13.500% 172,137.23
E Harga Satuan 1,447,227.81

Pembesian 10Kg dengan Besi Polos atau Ulir (A.4.1.1.17)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.070 5,292.00
2 Tukang Besi OH 99,750.00 0.070 6,982.50
3 Kepala Tukang OH 99,750.00 0.007 698.25
4 Mandor OH 99,750.00 0.004 399.00
Jumlah 13,371.75
B BAHAN
1 Besi Beton (polos/ulir) Kg 13,685.52 10.500 143,697.91
2 Kawat Ikat Beton (bendrat) Kg 20,524.01 0.150 3,078.60
Jumlah 146,776.51
C Jumlah A + B 160,148.26
D Overhead & Profit 13.500% 21,620.02
E Harga Satuan 181,768.27
F Harga Satuan/ KG 20,338.83

Memasang 10Kg Jaring Kawat Baja/Wire Mesh (A.4.1.1.19)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.0250 1,890.00
2 Tukang Besi OH 99,750.00 0.0250 2,493.75
3 Kepala Tukang OH 99,750.00 0.0250 2,493.75
4 Mandor OH 99,750.00 0.0010 99.75
Jumlah 6,977.25
B BAHAN
1 Besi Wire Mesh M 5 Kg 19,850.00 10.200 202,470.00
2 Kawat Ikat Beton (bendrat) Kg 20,524.01 0.050 1,026.20
Jumlah 203,496.20
C Jumlah A + B 210,473.45
D Overhead & Profit 13.500% 28,413.92
E Harga Satuan 238,887.37
E Harga Satuan per 1 Kg 23,888.74

Beton 34
Memasang 1m2 Bekisting untuk Pondasi (A.4.1.1.20)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.520 39,312.00
2 Tukang Kayu OH 99,750.00 0.260 25,935.00
3 Kepala Tukang OH 99,750.00 0.026 2,593.50
4 Mandor OH 99,750.00 0.026 2,593.50
Jumlah 70,434.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M 3
1,900,000.00 0.040 76,000.00
2 Paku 2" - 5" Kg 16,017.29 0.300 4,805.19
3 Minyak Bekisting Lt 0.100 0.00
Jumlah 80,805.19
C Jumlah A + B 151,239.19
D Overhead & Profit 13.500% 20,417.29
E Harga Satuan 171,656.48

Memasang 1m2 Bekisting untuk Pondasi (A.4.1.1.20) papan mal


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.520 39,312.00
2 Tukang Kayu OH 99,750.00 0.260 25,935.00
3 Kepala Tukang OH 99,750.00 0.026 2,593.50
4 Mandor OH 99,750.00 0.026 2,593.50
Jumlah 70,434.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M 3
1,900,000.00 0.040 76,000.00
2 Paku 2" - 5" Kg 16,017.29 0.300 4,805.19
3 Cerucuk Ǿ 6 - 8cm / 4m Btg 9,500.00 0.125 1,187.50
Jumlah 81,992.69
C Jumlah A + B 152,426.69
D Overhead & Profit 13.500% 20,577.60
E Harga Satuan 173,004.29

Memasang 1m2 Bekisting untuk Sloof (A.4.1.1.21)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.520 39,312.00
2 Tukang Kayu OH 99,750.00 0.260 25,935.00
3 Kepala Tukang OH 99,750.00 0.026 2,593.50
4 Mandor OH 99,750.00 0.026 2,593.50
Jumlah 70,434.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 1,900,000.00 0.045 85,500.00
2 Paku 2" - 5" Kg 16,017.29 0.300 4,805.19
3 Minyak Bekisting Lt 0.100 0.00
Jumlah 90,305.19
C Jumlah A + B 160,739.19
D Overhead & Profit 13.500% 21,699.79
E Harga Satuan 182,438.98

Memasang 1m2 Bekisting untuk Kolom (A.4.1.1.22) MULTIPLEK 9 MM


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 0.040 0.00
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.00 0.200 0.00
4 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.015 40,500.00
5 Multiplek 9 mm Lbr 171,309.85 0.350 59,958.45
6 Cerucuk Ǿ 6 - 8cm / 4m Btg 9,500.00 2.000 19,000.00
Jumlah 125,865.36
C Jumlah A + B 215,262.36
D Overhead & Profit 13.500% 29,060.42
E Harga Satuan 244,322.78

Beton 35
Memasang 1m2 Bekisting untuk Kolom (A.4.1.1.22) PAPAN
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M 3
1,900,000.00 0.040 76,000.00
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.00 0.000 0.00
4 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.015 40,500.00
5 Multiplek 9 mm Lbr 0.350 0.00
6 Cerucuk Ǿ 6 - 8cm / 4m Btg 9,500.00 2.000 19,000.00
Jumlah 141,906.92
C Jumlah A + B 231,303.92
D Overhead & Profit 13.500% 31,226.03
E Harga Satuan 262,529.94

Memasang 1m2 Bekisting untuk Balok (A.4.1.1.23)/ MULTIPLEK 9 MM


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 0.00 0.040 0.00
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.200 0.00
4 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.018 48,600.00
5 Multiplek 9 mm Lbr 171,309.85 0.350 59,958.45
6 Cerucuk Ǿ 8 - 10cm / 4m Btg 9,500.00 2.000 19,000.00
Jumlah 133,965.36
C Jumlah A + B 223,362.36
D Overhead & Profit 13.500% 30,153.92
E Harga Satuan 253,516.28

1m2 Pasang Bekisting untuk Balok (A.4.1.1.23)/ PAPAN


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 1,900,000.00 0.040 76,000.00
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.200 0.00
4 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.018 48,600.00
5 Multiplek 9 mm Lbr 0.00 0.350 0.00
6 Cerucuk Ǿ 8 - 10cm / 4m Btg 9,500.00 2.000 19,000.00
Jumlah 150,006.92
C Jumlah A + B 239,403.92
D Overhead & Profit 13.500% 32,319.53
E Harga Satuan 271,723.44

Memasang 1m2 Bekisting untuk Lantai (A.4.1.1.24) /MULTIPLEK


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 0.040 0
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.200 0.00
3 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.015 40,500.00
4 Multiplek 9 mm Lbr 171,309.85 0.350 59,958.45
5 Cerucuk Ǿ 8 - 10cm / 4m Btg 9,500.00 6.000 57,000.00
Jumlah 163,865.36
C Jumlah A + B 253,262.36
D Overhead & Profit 13.500% 34,190.42
E Harga Satuan 287,452.78

Memasang 1m2 Bekisting untuk Lantai dasar (A.4.1.1.24.a)/ MULTIPLEK


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KUANTITAS

Beton 36
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 0.040 0
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.200 0.00
3 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.015 40,500.00
4 Multiplek 9 mm Lbr 171,309.85 0.350 59,958.45
5 Cerucuk Ǿ 8 - 10cm / 4m Btg 6.000 0.00
Jumlah 106,865.36
C Jumlah A + B 196,262.36
D Overhead & Profit 13.500% 26,495.42
E Harga Satuan 222,757.78

Beton 37
1m2 Pasang Bekisting untuk Lantai (A.4.1.1.24) PAPAN
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 1,900,000.00 0.040 76,000
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.00 0.200 0.00
4 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.015 40,500.00
5 Multiplek 9 mm lbr 0.00 0.350 0.00
6 Cerucuk Ǿ 6 - 8cm / 4m Btg 9,500.00 6.000 57,000.00
Jumlah 179,906.92
C Jumlah A + B 269,303.92
D Overhead & Profit 13.500% 36,356.03
E Harga Satuan 305,659.94

1m2 Pasang Bekisting untuk Lantai Dasar (A.4.1.1.24.b) PAPAN


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 1,900,000.00 0.040 76,000
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.00 0.200 0.00
4 Balok Kayu Klas II Tidak Ketam M3 45,432.25 0.015 681.48
5 Multiplek 9 mm lbr 0.350 0.00
6 Cerucuk Ǿ 6 - 8cm / 4m Btg 6.000 0.00
Jumlah 83,088.40
C Jumlah A + B 172,485.40
D Overhead & Profit 13.500% 23,285.53
E Harga Satuan 195,770.93

Memasang 1m2 Bekisting untuk Tangga (A.4.1.1.26) NULTIPLEK


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.660 49,896.00
2 Tukang Kayu OH 99,750.00 0.330 32,917.50
3 Kepala Tukang OH 99,750.00 0.033 3,291.75
4 Mandor OH 99,750.00 0.033 3,291.75
Jumlah 89,397.00
B BAHAN
1 Papan Kayu Camp. ( Klas III ) M3 0.030 -
2 Paku 2" - 5" Kg 16,017.29 0.400 6,406.92
3 Minyak Bekisting Lt 0.150 0.00
4 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.015 40,500.00
5 Triplek t = 9mm Lbr 171,309.85 0.350 59,958.45
6 Cerucuk Ǿ 8 - 10cm / 4m Btg 9,500.00 2.000 19,000.00
Jumlah 125,865.36
C Jumlah A + B 215,262.36
D Overhead & Profit 13.500% 29,060.42
E Harga Satuan 244,322.78

Beton 38
K. PEKERJAAN BESI DAN ALUMINIUM (P. BA.)

Pemasangan Kg besi profil (A.4.2.1.1)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.060 4,536.00
2 Tukang Besi kontruksi OH 99,750.00 0.060 5,985.00
3 Kepala Tukang OH 99,750.00 0.006 598.50
4 Mandor OH 99,750.00 0.003 299.25
Jumlah 11,418.75
B BAHAN
1 Baja Profil Kg 35,025.61 1.150 40,279.45
Jumlah 40,279.45
C Jumlah A + B 51,698.20
D Overhead & Profit 13.500% 6,979.26
E Harga Satuan 58,677.46

Pemasangan 1 kg Rangka Kuda-kuda baja IWF/ Struktur (A.4.2.1.2)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.060 4,536.00
2 Tukang Besi kontruksi OH 99,750.00 0.060 5,985.00
3 Kepala Tukang OH 99,750.00 0.006 598.50
4 Mandor OH 99,750.00 0.003 299.25
Jumlah 11,418.75
B BAHAN
1 Besi Baja IWF/ struktur Kg 55,025.61 1.150 63,279.45
Jumlah 63,279.45
C Jumlah A + B 74,698.20
D Overhead & Profit 13.500% 10,084.26
E Harga Satuan 84,782.46

Pengerjaan 100 Kg Pekerjaan Perakitan (A.4.2.1.3)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.100 7,560.00
2 Tukang Besi kontruksi OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.001 99.75
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 18,133.50
B BAHAN
1 Solar liter 13,500.00 1.000 13,500.00
2 Minyak pelumas liter 60,000.00 0.100 6,000.00
Jumlah 19,500.00
C PERALATAN
1 Sewa alat jam 0.800 0.00
Jumlah 0.00
C Jumlah A + B 37,633.50
D Overhead & Profit 13.500% 5,080.52
E Harga Satuan 42,714.02

Pengerjaan 10 cm Pengelasan dengan las listrik (A.4.2.1.5)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.040 3,024.00
2 Tukang Besi kontruksi OH 99,750.00 0.020 1,995.00
3 Kepala Tukang OH 99,750.00 0.002 199.50
4 Mandor OH 99,750.00 0.002 199.50
Jumlah 5,418.00
B BAHAN
1 Kawat las listrik kg 35,000.00 0.400 14,000.00
2 solar liter 13,500.00 0.300 4,050.00
3 Minyak pelumas liter 60,000.00 0.040 2,400.00
Jumlah 20,450.00
C PERALATAN
1 Sewa alat jam 0.170 0.00
Jumlah 0.00
C Jumlah A + B 25,868.00
D Overhead & Profit 13.500% 3,492.18
E Harga Satuan 29,360.18

Besi & Aluminium 39


Pengerjaan 1 m2 pintu rolling/ folding door (A.4.2.1.7)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.440 33,264.00
2 Tukang Besi kontruksi OH 99,750.00 0.440 43,890.00
3 Kepala Tukang OH 99,750.00 0.044 4,389.00
4 Mandor OH 99,750.00 0.022 2,194.50
Jumlah 83,737.50
B BAHAN
1 Pintu besi m2 390,000.00 1.000 390,000.00

Jumlah 390,000.00
C PERALATAN

Jumlah 0.00
C Jumlah A + B 473,737.50
D Overhead & Profit 13.500% 63,954.56
E Harga Satuan 537,692.06

Pengerjaan 1 m2 sunscreen alluminium (A.4.2.1.9)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.080 6,048.00
2 Tukang OH 99,750.00 0.800 79,800.00
3 Kepala Tukang OH 99,750.00 0.080 7,980.00
4 Mandor OH 99,750.00 0.004 399.00
Jumlah 94,227.00
B BAHAN
1 sunscreen alluminium m2 385,525.61 1.000 385,525.61

Jumlah 385,525.61
C PERALATAN

Jumlah 0.00
C Jumlah A + B 479,752.61
D Overhead & Profit 13.500% 64,766.60
E Harga Satuan 544,519.21

Memasang 1m kusen pintu alluminium (A.4.2.1.11)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.043 3,250.80
2 Tukang Besi kontruksi OH 99,750.00 0.043 4,289.25
3 Kepala Tukang OH 99,750.00 0.0043 428.93
4 Mandor OH 99,750.00 0.0021 209.48
Jumlah 8,178.45
B BAHAN
1 Profil Kusen Aluminium YKK 3" m' 130,025.61 1.100 143,028.17
2 Skrup fixer Buah 1,500.00 2.000 3,000.00
3 Sealant Tube 41,086.74 0.060 2,465.20
Jumlah 148,493.37
C Jumlah A + B 156,671.82
D Overhead & Profit 13.500% 21,150.70
E Harga Satuan 177,822.52

Pemasangan 1m2 pintu alluminium (A.4.2.1.12)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.085 6,426.00
2 Tukang Besi kontruksi OH 99,750.00 0.085 8,478.75
3 Kepala Tukang OH 99,750.00 0.0085 847.88
4 Mandor OH 99,750.00 0.0042 418.95
Jumlah 16,171.58
B BAHAN
1 Profil Aluminium m' 12,525.61 4.400 55,112.67
2 Alluminium strip/ profil kaca m' 45,025.61 14.600 657,373.87
Jumlah 712,486.54
C Jumlah A + B 728,658.11
D Overhead & Profit 13.500% 98,368.85
E Harga Satuan 827,026.96

Besi & Aluminium 40


Memasang 1m2 pintu kaca rangka alluminium (A.4.2.1.13)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.085 6,426.00
2 Tukang OH 99,750.00 0.085 8,478.75
3 Kepala Tukang OH 99,750.00 0.0090 897.75
4 Mandor OH 99,750.00 0.0050 498.75
Jumlah 16,301.25
B BAHAN
1 Profil Pintu Aluminium m' 70,025.61 4.400 308,112.67
2 profil kaca m' 45,025.61 4.500 202,615.23
3 Sealant Tube 41,086.74 0.270 11,093.42
Jumlah 521,821.32
C Jumlah A + B 538,122.57
D Overhead & Profit 13.500% 72,646.55
E Harga Satuan 610,769.12

Memasang 1m' talang datar/ jurai seng bjls 30 lebar 90 cm (A.4.2.1.18)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.200 15,120.00
2 Tukang OH 99,750.00 0.200 19,950.00
3 Kepala Tukang OH 99,750.00 0.002 199.50
4 Mandor OH 99,750.00 0.001 99.75
Jumlah 35,369.25
B BAHAN
1 Seng Plat BJLS 0.30 lbr 56,432.25 1.050 59,253.86
2 Paku 1/2" - 1" Kg 22,917.29 0.015 343.76
3 Papan Kayu Klas II Ketam M3 3,250,000.00 0.019 61,750.00

Jumlah 121,347.62
C Jumlah A + B 156,716.87
D Overhead & Profit 13.500% 21,156.78
E Harga Satuan 177,873.65

1m2 Pasang Talang Miring Seng BJLS 30 / Jurai Dalam (P.BA. 11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.040 3,024.00
2 Tukang Kayu OH 99,750.00 0.400 39,900.00
3 Kepala Tukang OH 99,750.00 0.025 2,493.75
4 Mandor OH 99,750.00 0.00125 124.69
Jumlah 45,542.44
B BAHAN
1 Seng Plat BJLS 0.30 Lbr 56,432.25 0.50 28,216.13
2 Paku 1/2" - 1" Kg 22,917.29 0.015 343.76
3 Papan Kayu Klas II Ketam M3 3,250,000.00 0.019 61,750.00
4 Cat Meni Besi Kg 160,000.00 0.300 48,000.00
Jumlah 138,309.88
C Jumlah A + B 183,852.32
D Overhead & Profit 13.500% 24,820.06
E Harga Satuan 208,672.39

10m1 Talang Cucuran Atap 1/2 Lingkaran Ø 15cm BJLS 30 (P.BA. 12)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 99,750.00 5.000 498,750.00
2 Kepala Tukang Kayu OH 99,750.00 0.500 49,875.00
3 Pekerja OH 75,600.00 3.000 226,800.00
4 Mandor OH 99,750.00 0.150 14,962.50
Jumlah 790,387.50
B BAHAN
1 Seng Plat BJLS 30 Lbr 56,432.25 3.000 169,296.75
2 Besi Penahan Bh 18,425.61 9.000 165,830.47
Jumlah 335,127.22
C Jumlah A + B 1,125,514.72
D Overhead & Profit 13.500% 151,944.49
E Harga Satuan 1,277,459.20
Jadi 1m1 127,745.92

Besi & Aluminium 41


10m1 Pemasangan Pipa Pembuangan dari Talang Atap Ø 8cm BJLS 30 (P.BA. 13)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 99,750.00 3.750 374,062.50
2 Kepala Tukang Kayu OH 99,750.00 0.375 37,406.25
3 Pekerja OH 75,600.00 2.250 170,100.00
4 Mandor OH 99,750.00 0.110 10,972.50
Jumlah 592,541.25
B BAHAN
1 Seng Plat BJLS 30 Lbr 56,432.25 2.500 141,080.63
Jumlah 141,080.63
C Jumlah A + B 733,621.88
D Overhead & Profit 13.500% 99,038.95
E Harga Satuan 832,660.83
Jadi 1m1 83,266.08

Pemasangan 1 m2 rangka besi hollow 1 x 40 x 40. 2mm, modul 60 x 60 cm partisi (A.4.2.1.20)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.250 18,900.00
2 Tukang OH 99,750.00 0.250 24,937.50
3 Kepala Tukang OH 99,750.00 0.025 2,493.75
4 Mandor OH 99,750.00 0.013 1,296.75
Jumlah 47,628.00
B BAHAN
1 Rangka Metal hollow 40.40.2 mm m' 26,025.61 3.500 91,089.63
2 assesoris ls 91,089.63 0.015 1,366.34
Jumlah 92,455.97
C Jumlah A + B 140,083.97
D Overhead & Profit 13.500% 18,911.34
E Harga Satuan 158,995.31

1m2 Pemasangan rangka besi hollow 1 x 40 x 40. 2mm, modul 60 x 60 cm plafond (A.4.2.1.21)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.350 26,460.00
2 Tukang OH 99,750.00 0.350 34,912.50
3 Kepala Tukang OH 99,750.00 0.035 3,491.25
4 Mandor OH 99,750.00 0.018 1,795.50
Jumlah 66,659.25
B BAHAN
1 Rangka Metal hollow 40.40.2 mm m' 26,025.61 4.000 104,102.43
2 assesoris ls 104,102.43 0.015 1,561.54
Jumlah 105,663.97
C Jumlah A + B 172,323.22
D Overhead & Profit 13.500% 23,263.63
E Harga Satuan 195,586.85

Pemasangan 1 m2 atap pelana rangka baja ringan canai profil C57 (A.4.2.1.22)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.734 55,490.40
2 Tukang besi OH 99,750.00 0.734 73,216.50
3 Kepala Tukang OH 99,750.00 0.073 7,281.75
4 Mandor OH 99,750.00 0.037 3,690.75
Jumlah 139,679.40
B BAHAN
1 kuda2 baja ringan kg 20,025.61 3.065 61,378.49

Jumlah 61,378.49
C PERALATAN
1 peralatan % 10% 6,137.85
Jumlah 6,137.85
C Jumlah A + B 207,195.73
D Overhead & Profit 13.500% 27,971.42
E Harga Satuan 235,167.16

Besi & Aluminium 42


Pemasangan 1 m2 jurai / gording atap rangka baja ringan canai profil c57 (A.4.2.1.23)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.734 55,490.40
2 Tukang besi OH 99,750.00 0.734 73,216.50
3 Kepala Tukang OH 99,750.00 0.073 7,281.75
4 Mandor OH 99,750.00 0.037 3,690.75
Jumlah 139,679.40
B BAHAN
1 gording/ jurai baja ringan kg 10,025.61 4.050 40,603.71

Jumlah 40,603.71
C PERALATAN
1 peralatan % 10% 4,060.37
Jumlah 4,060.37
C Jumlah A + B 184,343.48
D Overhead & Profit 13.500% 24,886.37
E Harga Satuan 209,229.85

Besi & Aluminium 43


E. PEKERJAAN DINDING (P.Dnd.)

Pemasangan 1 m2 dinding bata merah (5 x 11 x 22) cm tebal 1/2 batu campuran 1 SP : 3 PP (A.4.4.1.8)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.300 22,680.00
2 Tukang OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.015 1,496.25
Jumlah 35,148.75
B BAHAN
1 bata merah Bh 1,071.07 70.000 74,974.90
2 Semen Portland Kg 1,668.21 14.370 23,972.18
3 Pasir Beton / Pasang M3 102.68 0.040 4.11
Jumlah 98,951.18
C Jumlah A + B 134,099.93
D Overhead & Profit 13.500% 18,103.49
E Harga Satuan 152,203.43

1m2 Pasang Batako uk. 15/30/7(P.Dnd. 01)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.320 24,192.00
2 Tukang Batu OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.015 1,496.25
Jumlah 36,660.75
B BAHAN
1 batako 5/30/7 Bh 1,750.00 22.000 38,500.00
2 Semen Portland Kg 1,668.21 7.500 12,511.58
3 Pasir Beton / Pasang M3 102.68 0.027 2.77
Jumlah 51,014.35
C Jumlah A + B 87,675.10
D Overhead & Profit 13.500% 11,836.14
E Harga Satuan 99,511.24

1m2 Pasang Batako uk. 15/30/8 (P.Dnd. 02)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.32 24,192.00
2 Tukang Batu OH 99,750.00 0.10 9,975.00
3 Kepala Tukang OH 99,750.00 0.01 997.50
4 Mandor OH 99,750.00 0.015 1,496.25
Jumlah 36,660.75
B BAHAN
1 batako 15/30/7 Bh 1,750.00 22.000 38,500.00
2 Semen Portland Kg 1,668.21 7.500 12,511.58
3 Pasir Beton / Pasang M3 102.68 0.027 2.77
Jumlah 51,014.35
C Jumlah A + B 87,675.10
D Overhead & Profit 13.500% 11,836.14
E Harga Satuan 99,511.24

Dinding 44
F. PEKERJAAN Plesteran (P.Pls)

Memasang 1m2 Plesteran 1PC : 2PP, tebal 15 mm (A.4.4.2.2)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.300 22,680.00
2 Tukang Batu OH 99,750.00 0.150 14,962.50
3 Kepala Tukang OH 99,750.00 0.015 1,496.25
4 Mandor OH 99,750.00 0.015 1,496.25
Jumlah 40,635.00
B BAHAN
1 Semen Portland Kg 1,668.21 10.224 17,055.78
2 Pasir M3 102.68 0.020 2.05
Jumlah 17,057.83
C Jumlah A + B 57,692.83
D Overhead & Profit 13.500% 7,788.53
E Harga Satuan 65,481.37

Memasang 1m2 Plesteran Traso 1PC : 2 traso, tebal 10 mm (A.4.4.2.22)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.450 34,020.00
2 Tukang Batu OH 99,750.00 0.225 22,443.75
3 Kepala Tukang OH 99,750.00 0.023 2,294.25
4 Mandor OH 99,750.00 0.023 2,294.25
Jumlah 61,052.25
B BAHAN
1 Semen Portland Kg 1,668.21 10.000 16,682.10
2 batu traso kg 2,880.00 15.000 43,200.00
Jumlah 59,882.10
C Jumlah A + B 120,934.35
D Overhead & Profit 13.500% 16,326.14
E Harga Satuan 137,260.49

Pemasang 1m2 finishing siar bata merah (A.4.4.2.24)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.150 11,340.00
2 Tukang Batu OH 99,750.00 0.075 7,481.25
3 Kepala Tukang OH 99,750.00 0.008 798.00
4 Mandor OH 99,750.00 0.008 798.00
Jumlah 20,417.25
B BAHAN
1 Semen Portland Kg 1,668.21 3.180 5,304.91

Jumlah 5,304.91
C Jumlah A + B 25,722.16
D Overhead & Profit 13.500% 3,472.49
E Harga Satuan 29,194.65

Memasang 1m2 Acian (A.4.4.2.27)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.200 15,120.00
2 Tukang Batu OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.010 997.50
Jumlah 27,090.00
B BAHAN
1 Semen Portland Kg 1,668.21 3.250 5,421.68
Jumlah 5,421.68

Plesteran 45
C Jumlah A + B 32,511.68
D Overhead & Profit 13.500% 4,389.08
E Harga Satuan 36,900.76

Memasang 1m2 Plesteran 1PC : 3PP, tebal 15 mm (A.4.4.2.3)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.300 22,680.00
2 Tukang Batu OH 99,750.00 0.150 14,962.50
3 Kepala Tukang OH 99,750.00 0.015 1,496.25
4 Mandor OH 99,750.00 0.015 1,496.25
Jumlah 40,635.00
B BAHAN
1 Semen Portland Kg 1,668.21 6.240 10,409.63
2 Pasir M3 102.68 0.023 2.36
Jumlah 10,411.99
C Jumlah A + B 51,046.99
D Overhead & Profit 13.500% 6,891.34
E Harga Satuan 57,938.34
Acuan : SNI 2013 cipta karya

Plesteran 46
M. PEKERJAAN LANTAI & DINDING (P.LD.)

Memasang 1m2 Lantai Keramik ukuran (20 x 20) cm (A.4.4.3.36)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.700 52,920.00
2 Tukang Batu OH 99,750.00 0.350 34,912.50
3 Kepala Tukang OH 99,750.00 0.035 3,491.25
4 Mandor OH 99,750.00 0.035 3,491.25
Jumlah 94,815.00
B BAHAN
1 Keramik 20x20 ( Motif ) Doos 97,530.02 1.050 102,406.52
2 Portland Cement (PC) Kg 1,668.21 10.400 17,349.38
3 Pasir Beton M3 102.68 0.045 4.62
4 Oker Pengisi Nat Keramik Kg 13,812.57 0.500 6,906.29
126,666.81
C Jumlah A + B 221,481.81
D Overhead & Profit 13.5% 29,900.04
E Harga Satuan 251,381.85

Memasang 1m2 Lantai Keramik ukuran (30 x 30) cm (A.4.4.3.35)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.700 52,920.00
2 Tukang Batu OH 99,750.00 0.350 34,912.50
3 Kepala Tukang OH 99,750.00 0.035 3,491.25
4 Mandor OH 99,750.00 0.035 3,491.25
Jumlah 94,815.00
B BAHAN
1 Keramik 30x30 ( Polos ) doos 100,020.07 1.050 105,021.07
2 Portland Cement (PC) Kg 1,668.21 10.000 16,682.10
3 Pasir Beton M3 102.68 0.045 4.62
4 Oker Pengisi Nat Keramik Kg 13,812.57 0.5000 6,906.29
128,614.08
C Jumlah A + B 223,429.08
D Overhead & Profit 13.5% 30,162.93
E Harga Satuan 253,592.00

Pemasang 1m2 Lantai parquet kayu (A.4.4.3.46)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.700 52,920.00
2 Tukang Batu OH 99,750.00 0.350 34,912.50
3 Kepala Tukang OH 99,750.00 0.035 3,491.25
4 Mandor OH 99,750.00 0.035 3,491.25
Jumlah 94,815.00
B BAHAN
1 parquet m2 185,112.57 1.050 194,368.20
2 lem Kg 26,309.85 0.600 15,785.91
210,154.11
C Jumlah A + B 304,969.11
D Overhead & Profit 13.5% 41,170.83
E Harga Satuan 346,139.94

Pemasang 1m2 Lantai dan dinding ACP (P.L.D.01)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.700 52,920.00
2 Tukang Batu OH 99,750.00 0.450 44,887.50
3 Kepala Tukang OH 99,750.00 0.035 3,491.25
4 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 106,286.25
B BAHAN
1 Alumunium Komposit 0,4 setara seven 1,2 x 2,4 m' 220,000.00 0.340 74,800.00
2 rangka besi hollow 40 x 60 x 2,1 m' 29,549.13 3.500 103,421.94
3 rangka besi hollow 40 x 60 x 1,1 m' 14,333.13 3.500 50,165.94
4 Bracket Besi Siku 40 x 40 x 4 mm m' 5,716.13 3.500 20,006.44
5 Brazing 44,216.13 1.000 44,216.13
6 Sealent tube 41,086.74 0.060 2,465.20
7 Sekrup bh 1,500.00 2.000 3,000.00

Lantai 47
8 Bracket ACP m' 1,716.13 12.000 20,593.50
C ALAT 318,669.14
1 Sewa scafolding + Bongkar pasang set/hari 45,000 2.400 108,000.00
108,000.00
C Jumlah A + B 532,955.39
D Overhead & Profit 13.5% 71,948.98
E Harga Satuan 604,904.37

1m2 Pasang Lantai Keramik 60 x 60cm Polished (setaraf Decogress) (P.LD. 04)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.700 52,920.00
2 Tukang Batu OH 99,750.00 0.450 44,887.50
3 Kepala Tukang OH 99,750.00 0.035 3,491.25
4 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 106,286.25
B BAHAN
1 Keramik Anti Gores 60x60 ( Polos ) Bh 55,030.02 2.778 152,861.16
2 Semen Portland Kg 1,668.21 11.380 18,984.23
3 Pasir Beton M3 102.68 0.042 4.31
4 Oker Pengisi Nat Keramik Kg 13,812.57 0.1500 2,071.89
173,921.59
C Jumlah A + B 280,207.84
D Overhead & Profit 13.5% 37,828.06
E Harga Satuan 318,035.90

1m2 Pasang Lantai Keramik 30 x 60cm Polished (setaraf Decogress) (P.LD. 03)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.700 52,920.00
2 Tukang Batu OH 99,750.00 0.450 44,887.50
3 Kepala Tukang OH 99,750.00 0.035 3,491.25
4 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 106,286.25
B BAHAN
1 Keramik 30 x 60 Bh 36,686.68 5.556 203,814.86
2 Semen Portland Kg 1,668.21 11.380 18,984.23
3 Pasir Beton M3 102.68 0.042 4.31
4 Oker Pengisi Nat Keramik Kg 13,812.57 0.1500 2,071.89
224,875.29
C Jumlah A + B 331,161.54
D Overhead & Profit 13.5% 44,706.81
E Harga Satuan 375,868.34

1m2 Pasang Lantai Keramik 40 x 40cm Unpolished (setaraf Indogress) (P.LD. 5)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.620 46,872.00
2 Tukang Batu OH 99,750.00 0.350 34,912.50
3 Kepala Tukang OH 99,750.00 0.035 3,491.25
4 Mandor OH 99,750.00 0.030 2,992.50
Jumlah 88,268.25
B BAHAN
1 Keramik 40 x 40cm Unpolished (setaraf Indogress) Bh 22,186.68 6.250 138,666.74
2 Semen Portland Kg 1,668.21 11.380 18,984.23
3 Pasir Beton M3 102.68 0.042 4.31
4 Oker Pengisi Nat Keramik Kg 13,812.57 0.1500 2,071.89
159,727.17
C Jumlah A + B 247,995.42
D Overhead & Profit 13.500% 33,479.38
E Harga Satuan 281,474.80

Memasang 1 m2 dinding keramik ukuran (20 x 20) cm (A.4.4.3.50)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.900 68,040.00
2 Tukang Batu OH 99,750.00 0.450 44,887.50

Lantai 48
3 Kepala Tukang OH 99,750.00 0.045 4,488.75
4 Mandor OH 99,750.00 0.045 4,488.75
Jumlah 121,905.00
B BAHAN
1 Keramik Bh 3,366.54 26.000 87,530.02
2 Portland Cement (PC) Kg 1,668.21 9.300 15,514.35
3 Pasir Beton M3 102.68 0.018 1.85
4 Oker Pengisi Nat Keramik Kg 13,812.57 0.1940 2,679.64
105,725.86
C Jumlah A + B 227,630.86
D Overhead & Profit 13.500% 30,730.17
E Harga Satuan 258,361.03

1m2 Pasang Dinding Keramik 20 x 25cm (P.LD. 08)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.600 45,360.00
2 Tukang Batu OH 99,750.00 0.450 44,887.50
3 Kepala Tukang OH 99,750.00 0.045 4,488.75
4 Mandor OH 99,750.00 0.030 2,992.50
Jumlah 97,728.75
B BAHAN
1 Keramik 20 x 25 cm Bh 5,501.50 20.000 110,030.02
2 Semen Kg 1,586.00 9.300 14,749.80
3 Pasir Pasang M3 92,700.00 0.018 1,668.60
4 Oker Pengisi Nat Keramik Kg 13,700.00 0.200 2,740.00
129,188.42
C Jumlah A + B 226,917.17
D Overhead & Profit 13.500% 30,633.82
E Harga Satuan 257,550.99
Acuan : ABK Bangunan Gedung dan Perumahan - 6.63

1m2 Pasang Dinding Keramik 30 x 30cm (P.LD. 09)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.600 45,360.00
2 Tukang Batu OH 99,750.00 0.450 44,887.50
3 Kepala Tukang OH 99,750.00 0.045 4,488.75
4 Mandor OH 99,750.00 0.030 2,992.50
Jumlah 97,728.75
B BAHAN
1 Keramik 30 x 30cm Bh 11,113.34 9.000 100,020.07
2 Semen Kg 1,668.21 9.300 15,514.35
3 Pasir Beton M3 102.68 0.018 1.85
4 Oker Pengisi Nat Keramik Kg 13,812.57 0.200 2,762.51
118,298.79
C Jumlah A + B 216,027.54
D Overhead & Profit 0.135% 291.64
E Harga Satuan 216,319.17

1m2 Pasang Dinding Keramik 40 x 40cm (P.LD. 10)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.600 45,360.00
2 Tukang Batu OH 99,750.00 0.450 44,887.50
3 Kepala Tukang OH 99,750.00 0.045 4,488.75
4 Mandor OH 99,750.00 0.030 2,992.50
Jumlah 97,728.75
B BAHAN
1 Keramik 40 x 40cm Bh 18,200.00 6.000 109,200.00
2 Semen Kg 1,668.21 9.300 15,514.35
3 Pasir Pasang M3 102.68 0.018 1.85
4 Oker Pengisi Nat Keramik Kg 13,700.00 0.200 2,740.00
127,456.20
C Jumlah A + B 225,184.95
D Overhead & Profit 0.135% 304.00
E Harga Satuan 225,488.95

Lantai 49
I. PEKERJAAN PLAFOND (P.Pf.)

Memasang 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9 mm (A.4.5.1.7)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.100 7,560.00
2 Tukang Kayu OH 99,750.00 0.050 4,987.50
3 Kepala Tukang OH 99,750.00 0.005 498.75
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 13,545.00
B BAHAN
1 Gypsum Board (120 x 240 x 9) Lbr 71,729.00 0.364 26,109.36
2 Paku Sekrup Gypsum Kg 55,762.10 0.110 6,133.83
Jumlah 32,243.19
C Jumlah A + B 45,788.19
D Overhead & Profit 13.500% 6,181.41
E Harga Satuan 51,969.59

Memasang 1 m' list langit-langit kayu/ gypsum profil (A.4.5.1.9)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.050 3,780.00
2 Tukang Kayu OH 99,750.00 0.050 4,987.50
3 Kepala Tukang OH 99,750.00 0.005 498.75
4 Mandor OH 99,750.00 0.003 299.25
Jumlah 9,565.50
B BAHAN
1 List kayu profil/ gypsum m' 12,319.00 1.050 12,934.95
2 Paku kg 55,762.10 0.010 557.62
Jumlah 13,492.57
C Jumlah A + B 23,058.07
D Overhead & Profit 13.500% 3,112.84
E Harga Satuan 26,170.91

1m2 Langit-langit GRC (A.4.5.1.7.a)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.100 7,560.00
2 Tukang Kayu OH 99,750.00 0.050 4,987.50
3 Kepala Tukang OH 99,750.00 0.005 498.75
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 13,545.00
B BAHAN
1 GRC Board (120 x 240 x 4) Lbr 73,729.00 0.364 26,837.36
2 Paku GRC Kg 55,762.10 0.110 6,133.83
Jumlah 32,971.19
C Jumlah A + B 46,516.19
D Overhead & Profit 13.500% 6,279.69
E Harga Satuan 52,795.87

Plafond 50
H. PEKERJAAN PENUTUP ATAP (P.PA.)

Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana (A.4.5.2.32)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.200 15,120.00
2 Tukang kayu OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.001 99.75
Jumlah 26,192.25
B BAHAN
1 Atap Spandek Zincalume 0,35 lebar 1 m Bh 58,932.25 1.300 76,611.93
2 Paku 1/2" - 1" Kg 22,917.29 0.200 4,583.46
Jumlah 81,195.38
C Jumlah A + B 107,387.63
D Overhead & Profit 13.500% 14,497.33
E Harga Satuan 121,884.96

Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai (A.4.5.2.33)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.200 15,120.00
2 Tukang kayu OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.001 99.75
Jumlah 26,192.25
B BAHAN
1 genteng metal Bh 59,532.25 2.000 119,064.50
2 Paku 1/2" - 1" Kg 22,917.29 0.200 4,583.46
Jumlah 123,647.96
C Jumlah A + B 149,840.21
D Overhead & Profit 13.500% 20,228.43
E Harga Satuan 170,068.64

Pemasangan 1 m2 Nok genteng metal (A.4.5.2.37)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.250 18,900.00
2 Tukang kayu OH 99,750.00 0.150 14,962.50
3 Kepala Tukang OH 99,750.00 0.015 1,496.25
4 Mandor OH 99,750.00 0.013 1,296.75
Jumlah 36,655.50
B BAHAN
1 nok genteng metal Bh 35,432.25 1.100 38,975.48
2 Paku 1/2" - 1" Kg 22,917.29 0.050 1,145.86
Jumlah 40,121.34
C Jumlah A + B 76,776.84
D Overhead & Profit 13.500% 10,364.87
E Harga Satuan 87,141.71

Pemasangan 1 m2 atap aluminium (A.4.5.2.41)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.150 11,340.00
2 Tukang kayu OH 99,750.00 0.750 74,812.50
3 Kepala Tukang OH 99,750.00 0.080 7,980.00
4 Mandor OH 99,750.00 0.006 598.50
Jumlah 94,731.00
B BAHAN
1 atap aluminium tebal 0,55 Bh 75,432.25 1.050 79,203.86
2 Paku 1"- 2" Kg 22,917.29 0.020 458.35
Jumlah 79,662.21
C Jumlah A + B 174,393.21
D Overhead & Profit 13.500% 23,543.08
E Harga Satuan 197,936.29

Pemasangan 1 m2 Nok atap aluminium (A.4.5.2.42)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KUANTITAS

Penutup Atap 51
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.100 7,560.00
2 Tukang kayu OH 99,750.00 1.000 99,750.00
3 Kepala Tukang OH 99,750.00 0.100 9,975.00
4 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 122,272.50
B BAHAN
1 nok atap aluminium Bh 35,432.25 1.200 42,518.70
2 Paku 1"- 2" Kg 22,917.29 0.040 916.69
Jumlah 43,435.39
C Jumlah A + B 165,707.89
D Overhead & Profit 13.500% 22,370.57
E Harga Satuan 188,078.46

Penutup Atap 52
G. PEKERJAAN KAYU (P.K.)

Membuat dan Memasang 1m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas Belian (A.4.6.1.1)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 7.000 529,200.00
2 Tukang Kayu OH 99,750.00 21.000 2,094,750.00
3 Kepala Tukang OH 99,750.00 2.100 209,475.00
4 Mandor OH 99,750.00 0.350 34,912.50
Jumlah 2,868,337.50
B BAHAN
1 Balok Belian Ketam M3 7,250,000.00 1.100 7,975,000.00
2 Paku 10 cm kg 16,017.29 1.250 20,021.61
3 Lem Kayu kg 26,309.85 1.000 26,309.85
Jumlah 8,021,331.46
C Jumlah A + B 10,889,668.96
D Overhead & Profit 13.500% 1,470,105.31
E Harga Satuan 12,359,774.27

1m3 Pekerjaan Rangka Badan Kayu Belian (P.K. 06)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 12.000 907,200.00
2 Tukang Kayu OH 99,750.00 36.000 3,591,000.00
3 Kepala Tukang OH 99,750.00 3.600 359,100.00
4 Mandor OH 99,750.00 0.600 59,850.00
Jumlah 4,917,150.00
B BAHAN
1 Balok Belian Ketam M3 7,250,000.00 1.100 7,975,000.00
2 Paku belian kg 36,262.10 6.000 217,572.60
Jumlah 8,192,572.60
C Jumlah A + B 13,109,722.60
D Overhead & Profit 0.000% 0.00
E Harga Satuan 13,109,722.60

Membuat dan Memasang 1m2 Daun Pintu Panel, Kayu Kelas I dan II (A.4.6.1.5)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.000 75,600.00
2 Tukang Kayu OH 99,750.00 3.000 299,250.00
3 Kepala Tukang OH 99,750.00 0.300 29,925.00
4 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 409,762.50
B BAHAN
1 Papan Kayu Klas II Ketam M3 3,250,000.00 0.040 130,000.00
2 Lem Kayu kg 26,309.85 0.500 13,154.92
Jumlah 143,154.92
C Jumlah A + B 552,917.42
D Overhead & Profit 13.500% 74,643.85
E Harga Satuan 627,561.28

Membuat dan Memasang 1m2 Pintu dan Jendela Jalusi Kayu Kelas I Belian (P.K. 16)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.000 75,600.00
2 Tukang Kayu OH 99,750.00 3.000 299,250.00
3 Kepala Tukang OH 99,750.00 0.300 29,925.00
4 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 409,762.50
B BAHAN
1 Papan Kayu Belian Ketam M3 8,350,000.00 0.064 534,400.00
2 Lem Kayu kg 26,309.85 0.500 13,154.92
Jumlah 547,554.92
C Jumlah A + B 957,317.42
D Overhead & Profit 13.500% 129,237.85
E Harga Satuan 1,086,555.28

Kayu 53
Membuat dan Memasang 1m2 Pintu dan Jendela Jalusi Kayu Kelas II (P.K. 17)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 1.000 75,600.00
2 Tukang Kayu OH 99,750.00 3.000 299,250.00
3 Kepala Tukang OH 99,750.00 0.300 29,925.00
4 Mandor OH 99,750.00 0.050 4,987.50
Jumlah 409,762.50
B BAHAN
1 Papan Kayu Kelas II (Ketam) M3 3,250,000.00 0.024 78,000.00
2 Lem Kayu kg 26,309.85 0.500 13,154.92
Jumlah 91,154.92
C Jumlah A + B 500,917.42
D Overhead & Profit 13.500% 67,623.85
E Harga Satuan 568,541.28

A.4.6.1.12. Pemasangan 1 m2 teakwood rangkap lapis formika/ hpl, rangka expose


kayu kelas II HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Kayu OH 99,750.00 0.850 84,787.50
2 Pekerja OH 75,600.00 2.550 192,780.00
3 Kepala Tukang OH 99,750.00 0.255 25,436.25
4 Mandor OH 99,750.00 0.430 42,892.50
Jumlah 345,896.25
B BAHAN
1 Papan kayu kelas II tidak ketam m3 7,950,000.00 0.025 198,750.00
2 Paku 1 -2,5 kg 16,000.00 0.030 480.00
3 Lem kayu kg 26,309.85 0.800 21,047.88
4 plywood 4 mm lbr 60,300.00 0.529 31,904.76
5 hpl lbr 450,000.00 0.500 225,000.00
Jumlah 477,182.64
C Jumlah A + B 823,078.89
D Overhead & Profit 13.500% 111,115.65
E Harga Satuan 934,194.54

Kayu 54
L. PEKERJAAN KUNCI DAN KACA (P.KK.)

1 Buah Pemasangan Kunci Tanam (A.4.6.2.2)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.010 756.00
2 Tukang Kayu OH 99,750.00 0.500 49,875.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 52,127.25
B BAHAN
1 Kunci Tanam Biasa Bh 75,162.10 1.000 75,162.10
Jumlah 75,162.10
C Jumlah A + B 127,289.35
D Overhead & Profit 13.500% 17,184.06
E Harga Satuan 144,473.41

Pemasangan 1 buah kunci kamar mandi (A.4.6.2.3)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.010 756.00
2 Tukang Kayu OH 99,750.00 0.500 49,875.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 52,127.25
B BAHAN
1 Kunci Tanam Bh 75,162.10 1.000 75,162.10
Jumlah 75,162.10
C Jumlah A + B 127,289.35
D Overhead & Profit 13.500% 17,184.06
E Harga Satuan 144,473.41

1 Buah Pemasangan Kunci Silinder (A.4.6.2.4)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.005 378.00
2 Tukang Kayu OH 99,750.00 0.500 49,875.00
3 Kepala Tukang OH 99,750.00 0.005 498.75
4 Mandor OH 99,750.00 0.003 299.25
Jumlah 51,051.00
B BAHAN
1 Kunci Tanam Silinder Bh 84,042.10 1.000 84,042.10
Jumlah 84,042.10
C Jumlah A + B 135,093.10
D Overhead & Profit 13.500% 18,237.57
E Harga Satuan 153,330.67

1 Buah Pemasangan Engsel Pintu (A.4.6.2.5)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.015 1,134.00
2 Tukang Kayu OH 99,750.00 0.150 14,962.50
3 Kepala Tukang OH 99,750.00 0.015 1,496.25
4 Mandor OH 99,750.00 0.0008 79.80
Jumlah 17,672.55
B BAHAN
1 Engsel Pintu Bh 10,008.10 1.000 10,008.10
Jumlah 10,008.10
C Jumlah A + B 27,680.65
D Overhead & Profit 13.500% 3,736.89
E Harga Satuan 31,417.54

1 Buah Pemasangan Engsel Jendela kupu-kupu (A.4.6.2.6)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.010 756.00
2 Tukang Kayu OH 99,750.00 0.100 9,975.00

Kunci & Kaca 55


3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.0005 49.88
Jumlah 11,778.38
B BAHAN
1 Engsel Jendela Bh 8,008.10 1.000 8,008.10
Jumlah 8,008.10
C Jumlah A + B 19,786.48
D Overhead & Profit 13.500% 2,671.17
E Harga Satuan 22,457.65

1 Buah Pemasangan Kait Angin (A.4.6.2.9)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.015 1,134.00
2 Tukang Kayu OH 99,750.00 0.150 14,962.50
3 Kepala Tukang OH 99,750.00 0.015 1,496.25
4 Mandor OH 99,750.00 0.0080 798.00
Jumlah 18,390.75
B BAHAN
1 Kait Angin Bh 10,162.10 1.000 10,162.10
Jumlah 10,162.10
C Jumlah A + B 28,552.85
D Overhead & Profit 13.500% 3,854.63
E Harga Satuan 32,407.48

1 Buah Pemasangan Door Closer (A.4.6.2.10)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.05 3,780.00
2 Tukang Kayu OH 99,750.00 0.500 49,875.00
3 Kepala Tukang OH 99,750.00 0.05 4,987.50
4 Mandor OH 99,750.00 0.0030 299.25
Jumlah 58,941.75
B BAHAN
1 Door Closer Bh 60,400.00 1.000 60,400.00
Jumlah 60,400.00
C Jumlah A + B 119,341.75
D Overhead & Profit 13.500% 16,111.14
E Harga Satuan 135,452.89

1 Buah Pemasangan Slot Pintu (A.4.6.2.11)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.020 1,512.00
2 Tukang Kayu OH 99,750.00 0.200 19,950.00
3 Kepala Tukang OH 99,750.00 0.020 1,995.00
4 Mandor OH 99,750.00 0.001 99.75
Jumlah 23,556.75
B BAHAN
1 Slot Pintu Bh 23,528.10 1.000 23,528.10
Jumlah 23,528.10
C Jumlah A + B 47,084.85
D Overhead & Profit 13.500% 6,356.45
E Harga Satuan 53,441.30

1 Buah Pemasangan Slot Jendela (A.4.6.2.11.a)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.020 1,512.00
2 Tukang Kayu OH 99,750.00 0.200 19,950.00
3 Kepala Tukang OH 99,750.00 0.020 1,995.00
4 Mandor OH 99,750.00 0.001 99.75
Jumlah 23,556.75
B BAHAN
1 Slot Jendela Bh 8,760.00 1.000 8,760.00
Jumlah 8,760.00
C Jumlah A + B 32,316.75
D Overhead & Profit 13.500% 4,362.76
E Harga Satuan 36,679.51

1 Buah Pemasangan Handle Pintu (A.4.6.2.13)

Kunci & Kaca 56


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.010 756.00
2 Tukang Kayu OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.0005 49.88
Jumlah 11,778.38
B BAHAN
1 handle pintu Bh 148,500.00 1.000 148,500.00
Jumlah 148,500.00
C Jumlah A + B 160,278.38
D Overhead & Profit 13.500% 21,637.58
E Harga Satuan 181,915.96

1 Buah Pemasangan Handle jendela (A.4.6.2.13)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.010 756.00
2 Tukang Kayu OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.0005 49.88
Jumlah 11,778.38
B BAHAN
1 handle jendela Bh 15,390.00 1.000 15,390.00
Jumlah 15,390.00
C Jumlah A + B 27,168.38
D Overhead & Profit 13.500% 3,667.73
E Harga Satuan 30,836.11

1 Buah Pemasangan Door Stoper (A.4.6.2.13)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.010 756.00
2 Tukang Kayu OH 99,750.00 0.100 9,975.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.0005 49.88
Jumlah 11,778.38
B BAHAN
1 Door Stoper Bh 60,400.00 1.000 60,400.00
Jumlah 60,400.00
C Jumlah A + B 72,178.38
D Overhead & Profit 13.500% 9,744.08
E Harga Satuan 81,922.46

1 m2 Pemasangan Kaca Tebal 5mm (A.4.6.2.17)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.015 1,134.00
2 Tukang Kayu OH 99,750.00 0.150 14,962.50
3 Kepala Tukang OH 99,750.00 0.015 1,496.25
4 Mandor OH 99,750.00 0.00080 79.80
Jumlah 17,672.55
B BAHAN
1 Kaca tebal 5mm M2 160,750.43 1.100 176,825.48
Jumlah 176,825.48
C Jumlah A + B 194,498.03
D Overhead & Profit 13.500% 26,257.23
E Harga Satuan 220,755.26

1 m2 Pemasangan Kaca Tebal 12mm (P.KK. 10)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.025 1,890.00
2 Tukang Kayu OH 99,750.00 0.250 24,937.50
3 Kepala Tukang OH 99,750.00 0.025 2,493.75
4 Mandor OH 99,750.00 0.00130 129.68
Jumlah 29,450.93
B BAHAN
1 Kaca tebal 12mm M2 210,750.43 1.100 231,825.48

Kunci & Kaca 57


2 Sealent Kg 123,260.21 0.070 8,628.21
Jumlah 240,453.69
C Jumlah A + B 269,904.62
D Overhead & Profit 13.500% 36,437.12
E Harga Satuan 306,341.74

Kunci & Kaca 58


N. PEKERJAAN PENGECATAN (P.Ct.)

1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 2Lapis Cat KIlat Penutup) (A.4.7.1.4)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.070 5,292.00
2 Tukang Cat OH 99,750.00 0.009 897.75
3 Kepala Tukang OH 99,750.00 0.006 598.50
4 Mandor OH 99,750.00 0.003 299.25
Jumlah 7,087.50
B BAHAN
1 Cat Meni Kg 145,000.00 0.200 29,000.00
2 Dempul Kg 17,556.28 0.150 2,633.44
3 Cat Dasar Kg 42,000.00 0.170 7,140.00
4 Cat Kilat Penutup 2 Kali Kg 55,000.00 0.260 14,300.00
5 Kuas bh 20,150.09 0.010 201.50
6 Tinner kg 20,000.00 0.030 600.00
7 Amplas lbr 3,150.09 0.200 630.02
53,073.44
C Jumlah A + B 60,160.94
D Overhead & Profit 13.500% 8,121.73
E Harga Satuan 68,282.67

1m2 Pengecatan Bidang Kayu Baru (1Lapis Plamir, 1Lapis Cat Dasar, 3 Lapis Cat Kilat Penutup) (A.4.7.1.5)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.070 5,292.00
2 Tukang Cat OH 99,750.00 0.105 10,473.75
3 Kepala Tukang OH 99,750.00 0.004 399.00
4 Mandor OH 99,750.00 0.0025 249.38
Jumlah 16,414.13
B BAHAN
1 Cat Meni Kg 145,000.00 0.200 29,000.00
2 Dempul Kg 17,556.28 0.150 2,633.44
3 Cat Dasar Kg 42,000.00 0.170 7,140.00
4 Cat Kilat Penutup 3 Kali Kg 55,000.00 0.350 19,250.00
5 Kuas bh 20,150.09 0.010 201.50
6 Pengencer kg 20,000.00 0.030 600.00
7 Amplas lbr 3,150.09 0.200 630.02
58,023.44
C Jumlah A + B 74,437.57
D Overhead & Profit 13.500% 10,049.07
E Harga Satuan 84,486.64

1m2 Pelaburan Bidang Kayu dengan Teak Oil (A.4.7.1.6)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.040 3,024.00
2 Tukang Cat OH 99,750.00 0.063 6,284.25
3 Kepala Tukang OH 99,750.00 0.063 6,284.25
4 Mandor OH 99,750.00 0.0030 299.25
Jumlah 15,891.75
B BAHAN
1 Teak Oil Ltr 48,456.28 0.360 17,444.26
17,444.26
C Jumlah A + B 33,336.01
D Overhead & Profit 13.500% 4,500.36
E Harga Satuan 37,836.37

1m2 Pelaburan Bidang Kayu dengan Politur (A.4.7.1.7)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.040 3,024.00
2 Tukang Cat OH 99,750.00 0.060 5,985.00
3 Kepala Tukang OH 99,750.00 0.016 1,596.00
4 Mandor OH 99,750.00 0.0030 299.25
Jumlah 7,880.25
B BAHAN
1 Politur Kg 46,956.28 0.150 7,043.44
2 Politur Jadi Kg 46,956.28 0.372 17,467.74
3 Ampelas Lbr 3,150.09 2.000 6,300.17
30,811.35

Pengecatan 59
C Jumlah A + B 38,691.60
D Overhead & Profit 13.500% 5,223.37
E Harga Satuan 43,914.97

1m2 Pelaburan Bidang Kayu Dengan Vernis (A.4.7.1.9)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.160 12,096.00
2 Tukang Cat OH 99,750.00 0.160 15,960.00
3 Kepala Tukang OH 99,750.00 0.016 1,596.00
4 Mandor OH 99,750.00 0.0025 249.38
Jumlah 29,901.38
B BAHAN
1 Vernis Ltr 45,256.28 0.150 6,788.44
2 Dempul Kg 17,556.28 0.050 877.81
3 Ampelas Lbr 3,150.09 0.100 315.01
4 Kuas Bh 20,150.09 0.010 201.50
8,182.77
C Jumlah A + B 38,084.14
D Overhead & Profit 13.500% 5,141.36
E Harga Satuan 43,225.50

1m2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Dengan Cat Mutu Baik. (A.4.7.1.10)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.020 1,512.00
2 Tukang Cat OH 99,750.00 0.063 6,284.25
3 Kepala Tukang OH 99,750.00 0.0063 628.43
4 Mandor OH 99,750.00 0.0030 299.25
Jumlah 8,723.93
B BAHAN
1 Plamur (dempul tembok) Kg 17,556.28 0.100 1,755.63
2 Cat Dasar tembok Kg 42,000.00 0.120 5,040.00
3 Cat Tembok Penutup 2 x Kg 65,000.00 0.260 16,900.00
23,695.63
C Jumlah A + B 32,419.55
D Overhead & Profit 13.500% 4,376.64
E Harga Satuan 36,796.19

1m2 Pengecatan Tembok Lama (1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Dengan Cat Mutu Baik. (A.4.7.1.11)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.028 2,116.80
2 Tukang Cat OH 99,750.00 0.042 4,189.50
3 Kepala Tukang OH 99,750.00 0.0042 418.95
4 Mandor OH 99,750.00 0.0025 249.38
Jumlah 6,974.63
B BAHAN
1 Cat Dasar tembok Kg 42,000.00 0.120 5,040.00
2 Cat Tembok Penutup 2 x Kg 65,000.00 0.180 11,700.00
16,740.00
C Jumlah A + B 23,714.63
D Overhead & Profit 13.500% 3,201.47
E Harga Satuan 26,916.10

1m2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah (A.4.7.1.17)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Cat OH 99,750.00 0.250 24,937.50
2 Kepala Tukang OH 99,750.00 0.225 22,443.75
3 Pekerja OH 75,600.00 0.0225 1,701.00
4 Mandor OH 99,750.00 0.0075 748.13
Jumlah 49,830.38
B BAHAN
1 Meni Besi Kg 160,000.00 0.100 16,000.00
2 Kuas Bh 20,150.09 0.010 201.50
3 Balok Kayu Klas II Tidak Ketam M3 2,700,000.00 0.002 5,400.00
21,601.50
C Jumlah A + B 71,431.88

Pengecatan 60
D Overhead & Profit 13.500% 9,643.30
E Harga Satuan 81,075.18

Pengecatan 61
J. PEKERJAAN SANITASI (P. Snt.)

Pemasangan 1 Buah Kloset Duduk / Monoblok (A.5.1.1.1)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Batu OH 99,750.00 1.100 109,725.00
2 Pekerja OH 75,600.00 3.300 249,480.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.160 15,960.00
Jumlah 376,162.50
B BAHAN
1 Kloset Duduk Monoblok EX TOTO (colour) Bh 1,207,153.13 1.000 1,207,153.13
2 Perlengkapan Ls 1,207,153.13 5% Harga Kloset 60,357.66
Jumlah 1,267,510.79
C Jumlah A + B 1,643,673.29
D Overhead & Profit 13.500% 221,895.89
E Harga Satuan 1,865,569.18
Acuan : SNI 2013 cipta karya

Pemasangan Kloset Jongkok Keramik (A.5.1.1.2)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Batu OH 99,750.00 1.500 149,625.00
2 Pekerja OH 75,600.00 1.000 75,600.00
3 Kepala Tukang OH 99,750.00 1.500 149,625.00
4 Mandor OH 99,750.00 0.160 15,960.00
Jumlah 390,810.00
B BAHAN
1 Kloset Jongkok warna Bh 285,403.13 1.000 285,403.13
2 Semen Portland Kg 1,668.21 6.000 10,009.26
3 Pasir Pasang/Beton M3 143,750.00 0.010 1,437.50
Jumlah 296,849.89
C Jumlah A + B 687,659.89
D Overhead & Profit 13.500% 92,834.09
E Harga Satuan 780,493.98

Pemasangan 1 buah westafel (A.5.1.1.5)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Batu OH 99,750.00 1.200 119,700.00
2 Pekerja OH 75,600.00 1.450 109,620.00
3 Kepala Tukang OH 99,750.00 0.150 14,962.50
4 Mandor OH 99,750.00 0.060 5,985.00
Jumlah 250,267.50
B BAHAN
1 wastafel lengkap Bh 555,403.13 1.200 666,483.76
2 Semen Portland Kg 1,668.21 6.000 10,009.26
3 Pasir Pasang/Beton M3 143,750.00 0.010 1,437.50
4 perlengkapan % 666,483.76 12.000 79,978.05
Jumlah 757,908.57
C Jumlah A + B 1,008,176.07
D Overhead & Profit 13.500% 136,103.77
E Harga Satuan 1,144,279.84

Pemasangan 1 buah bak fiberglass vol 1 m3 (A.5.1.1.10)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang Batu OH 99,750.00 0.450 44,887.50
2 Pekerja OH 75,600.00 0.300 22,680.00
3 Kepala Tukang OH 99,750.00 0.045 4,488.75
4 Mandor OH 99,750.00 0.015 1,496.25
Jumlah 73,552.50
B BAHAN
1 Tong Air Vol. 1 M³ unit 2,121,612.50 1.000 2,121,612.50
2 perlengkapan ls 2,121,612.50 0.120 254,593.50
Jumlah 2,121,612.50
C Jumlah A + B 2,195,165.00
D Overhead & Profit 13.500% 296,347.28
E Harga Satuan 2,491,512.28

Sanitasi 62
Pemasangan 1 buah bak cuci piring stainlessteel (A.5.1.1.12)
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang OH 99,750.00 0.300 29,925.00
2 Pekerja OH 75,600.00 0.030 2,268.00
3 Kepala Tukang OH 99,750.00 0.030 2,992.50
4 Mandor OH 99,750.00 0.015 1,496.25
Jumlah 36,681.75
B BAHAN
1 bak cuci piring unit 1,705,403.13 1.000 1,705,403.13
2 waterdrain bh 355,403.13 1.000 355,403.13
Jumlah 1,705,403.13
C Jumlah A + B 1,742,084.88
D Overhead & Profit 13.500% 235,181.46
E Harga Satuan 1,977,266.34

Pemasangan 1 buah floor drain (A.5.1.1.14)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang OH 99,750.00 0.100 9,975.00
2 Pekerja OH 75,600.00 0.010 756.00
3 Kepala Tukang OH 99,750.00 0.010 997.50
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 12,227.25
B BAHAN
1 Floordrain unit 15,033.25 1.000 15,033.25

Jumlah 15,033.25
C Jumlah A + B 27,260.50
D Overhead & Profit 13.500% 3,680.17
E Harga Satuan 30,940.67

Pemasangan 1 bh kran diamter 1/2" atau 3/4 " (A.5.1.1.19)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.010 756.00
2 Tukang Batu OH 99,750.00 0.400 39,900.00
3 Kepala Tukang OH 99,750.00 0.040 3,990.00
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 45,144.75
B BAHAN
1 Kran Air RRC Uk. 3/4" M 17,600.06 1.000 17,600.06
2 Seatlape bh 15,403.13 0.025 385.08
Jumlah 17,985.14
C Jumlah A + B 63,129.89
D Overhead & Profit 13.500% 8,522.53
E Harga Satuan 71,652.42

Pemasangan 1 bh kranJet Spray 1/2" atau 3/4 " (A.5.1.1.19)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.010 756.00
2 Tukang Batu OH 99,750.00 0.400 39,900.00
3 Kepala Tukang OH 99,750.00 0.040 3,990.00
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 45,144.75
B BAHAN
1 kran Jet Spray M 55,100.06 1.000 55,100.06
2 Seatlape bh 15,403.13 0.025 385.08
Jumlah 55,485.14
C Jumlah A + B 100,629.89
D Overhead & Profit 13.500% 13,585.03
E Harga Satuan 114,214.92

Pemasangan 1 m' pipa galvanis diameter 3/4 " (A.5.1.1.20)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.054 4,082.40
2 Tukang Batu OH 99,750.00 0.090 8,977.50

Sanitasi 63
3 Kepala Tukang OH 99,750.00 0.009 897.75
4 Mandor OH 99,750.00 0.027 2,693.25
Jumlah 16,650.90
B BAHAN
1 pipa galvanis 3/4" M 110,163.92 1.200 132,196.70
2 perlengkapan % 132,196.70 35% 46,268.85
Jumlah 178,465.55
C Jumlah A + B 195,116.45
D Overhead & Profit 13.500% 26,340.72
E Harga Satuan 221,457.17

Pemasangan 1 m' pipa galvanis diameter 1 " (A.5.1.1.21)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.054 4,082.40
2 Tukang Batu OH 99,750.00 0.090 8,977.50
3 Kepala Tukang OH 99,750.00 0.009 897.75
4 Mandor OH 99,750.00 0.027 2,693.25
Jumlah 16,650.90
B BAHAN
1 pipa galvanis 1" M 240,121.76 1.200 288,146.11
2 perlengkapan % 288,146.11 35% 100,851.14
Jumlah 388,997.25
C Jumlah A + B 405,648.15
D Overhead & Profit 13.500% 54,762.50
E Harga Satuan 460,410.65

Pemasangan 1 m' pipa galvanis diameter 1,1 /5 " (A.5.1.1.22)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.108 8,164.80
2 Tukang Batu OH 99,750.00 0.180 17,955.00
3 Kepala Tukang OH 99,750.00 0.018 1,795.50
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 28,414.05
B BAHAN
1 pipa galvanis 1,5" M 350,375.87 1.200 420,451.04
2 perlengkapan % 420,451.04 35% 147,157.87
Jumlah 567,608.91
C Jumlah A + B 596,022.96
D Overhead & Profit 13.500% 80,463.10
E Harga Satuan 676,486.06

Pemasangan 1 m' pipa PVC tipe AW diameter 1/2" (A.5.1.1.25)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.036 2,721.60
2 Tukang Batu OH 99,750.00 0.060 5,985.00
3 Kepala Tukang OH 99,750.00 0.006 598.50
4 Mandor OH 99,750.00 0.002 199.50
Jumlah 9,504.60
B BAHAN
1 Pipa PVC Ø = 1/2" x 6 M' M 90,014.41 1.200 108,017.29
2 perlengkapan % 108,017.29 35% 37,806.05
Jumlah 145,823.34
C Jumlah A + B 155,327.94
D Overhead & Profit 13.500% 20,969.27
E Harga Satuan 176,297.21

Pemasangan 1 m' pipa PVC tipe AW diameter 3/4" (A.5.1.1.26)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.036 2,721.60
2 Tukang Batu OH 99,750.00 0.060 5,985.00
3 Kepala Tukang OH 99,750.00 0.006 598.50
4 Mandor OH 99,750.00 0.002 199.50
Jumlah 9,504.60
B BAHAN
1 Pipa PVC Ø = 3/4" x 6 M' M 120,032.55 1.200 144,039.06
2 perlengkapan % 144,039.06 35% 50,413.67
Jumlah 194,452.73
C Jumlah A + B 203,957.33
D Overhead & Profit 13.500% 27,534.24

Sanitasi 64
E Harga Satuan 231,491.57

Memasang 1m1 Pipa PVC Tipe AW Ø 1" (A.5.7.1.27)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.036 2,721.60
2 Tukang Batu OH 99,750.00 0.060 5,985.00
3 Kepala Tukang OH 99,750.00 0.006 598.50
4 Mandor OH 99,750.00 0.0020 199.50
Jumlah 9,504.60
B BAHAN
1 Pipa PVC Ø = 1" x 6 M' M1 150,063.38 1.200 180,076.06
2 Perlengkapan % 180,076.06 25% 45,019.01
Jumlah 225,095.07
C Jumlah A + B 234,599.67
D Overhead & Profit 13.500% 31,670.96
E Harga Satuan 266,270.63

Memasang 1m1 Pipa PVC Tipe AW Ø 2" (A.5.1.1.29)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.054 4,082.40
2 Tukang Batu OH 99,750.00 0.090 8,977.50
3 Kepala Tukang OH 99,750.00 0.009 897.75
4 Mandor OH 99,750.00 0.0030 299.25
Jumlah 14,256.90
B BAHAN
1 Pipa PVC Ø = 2" x 6 M' M1 175,232.39 1.200 210,278.87
2 Perlengkapan % 175,232.39 25% 43,808.10
Jumlah 254,086.97
C Jumlah A + B 268,343.87
D Overhead & Profit 13.500% 36,226.42
E Harga Satuan 304,570.29

Memasang 1m1 Pipa PVC Tipe AW Ø 3" (A.5.1.1.31)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.081 6,123.60
2 Tukang Batu OH 99,750.00 0.135 13,466.25
3 Kepala Tukang OH 99,750.00 0.0135 1,346.63
4 Mandor OH 99,750.00 0.0041 408.98
Jumlah 21,345.45
B BAHAN
1 Pipa PVC Ø = 3" x 6 M' M1 350,540.31 1.200 420,648.38
2 Perlengkapan % 350,540.31 25% 87,635.08
Jumlah 508,283.45
C Jumlah A + B 529,628.90
D Overhead & Profit 13.500% 71,499.90
E Harga Satuan 601,128.81

Sanitasi 65
O. PEKERJAAN BONGKARAN (P. Bkr.)

1m3 Pekerjaan Bongkaran Beton Bertulang (P.Bkr. 01)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 6.667 504,025.20
2 Mandor OH 99,750.00 0.333 33,216.75
Jumlah 537,241.95
B Jumlah A 537,241.95
C Overhead & Profit 13.500% 72,527.66
D Harga Satuan 609,769.61

1m2 Pekerjaan Bongkaran Plesteran Dinding


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.050 3,780.00
2 Mandor OH 99,750.00 0.025 2,493.75
Jumlah 6,273.75
B Jumlah A 6,273.75
C Overhead & Profit 13.500% 846.96
D Harga Satuan 7,120.71

1m2 Pekerjaan Bongkaran Lantai Papan


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.050 3,780.00
2 Mandor OH 99,750.00 0.0100 997.50
Jumlah 4,777.50
B Jumlah A 4,777.50
C Overhead & Profit 13.500% 644.96
D Harga Satuan 5,422.46

1m2 Pekerjaan membongkar plafond (bongkaran tidak di pakai)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.125 9,450.00
2 Mandor OH 99,750.00 0.0050 498.75
3 Papan Kls III Campuran OH 0.00
Jumlah 9,948.75
B Jumlah A 9,948.75
C Overhead & Profit 13.500% 1,343.08
D Harga Satuan 11,291.83

1m2 Pekerjaan Bongkaran Atap Genteng / Sirap (bongkaran tidak di pakai)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 75,600.00 0.020 1,512.00
2 Mandor OH 99,750.00 0.010 997.50
Jumlah 2,509.50
B Jumlah A 2,509.50
C Overhead & Profit 13.500% 338.78
D Harga Satuan 2,848.28

1m2 Pekerjaan Bongkaran reng kaso (bongkaran tidak di pakai)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Tukang kayu OH 99,750.00 0.020 1,995.00
2 pekerja OH 75,600.00 0.025 1,890.00
3 kepala tukang OH 99,750.00 0.003 249.38
4 Mandor OH 99,750.00 0.005 498.75
Jumlah 4,633.13
B Jumlah A 4,633.13
C Overhead & Profit 13.500% 625.47

Bongkar 66
D Harga Satuan 5,258.60

Bongkar 67
HARGA SATUAN
NO KODE ANALISA URAIAN PEKERJAAN
(Rp)
1 2 3 4
A. PEKERJAAN PERSIAPAN
1 (LA. 03) Papan Nama Proyek 1,350,849.32
2 0 Pembersihan Lokasi 1,000.00
3 A.2.2.1.4 Pengukuran dan Pemasangan Bowplank 47,842.06
B. PEKERJAAN TANAH
1 A.2.3.1.1 Galian Tanah #REF!
2 P. T. 02 Cerucuk Dia 12 - 10 m + Pemancangan #REF!
3 P. T. 03 Urugan Pasir t = 15 cm #REF!
4 P. T. 04 Urugan Pasir t = 15 cm #REF!
5 P. T. 05 Lantai Kerja t = 5 cm #REF!
6 P. T. 06 #REF! #REF!
7 P. T. 07 #REF! #REF!
8 P. T. 08 #REF! #REF!
9 P. T. 09 #REF! #REF!
10 P. T. 10 #REF! #REF!
11 P. T. 11 #REF! #REF!
12 P. T. 12 #REF! #REF!
13 P. T. 13 #REF! #REF!
C. PEKERJAAN PONDASI BATU
1 P. PB. 01 #REF! #REF!
2 P. PB. 02 #REF! #REF!
#REF!
3 P. PB. 03 #REF!
#REF!
D. PEKERJAAN BETON BERTULANG
1 P. BB. 01 #REF! #REF!
2 P. BB. 02 #REF! #REF!
3 P. BB. 03 #REF! #REF!
4 P. BB. 03.a #REF! #REF!
5 P. BB. 04 #REF! #REF!
6 P. BB. 04.a #REF! #REF!
7 P. BB. 05 #REF! #REF!
8 P. BB. 06 #REF! #REF!
9 P. BB. 06.a #REF! #REF!
10 P. BB. 07 #REF! #REF!
11 P. BB. 08 #REF! #REF!
12 P. BB. 09 #REF! #REF!
13 P. BB. 09.a #REF! #REF!
14 P. BB. 10 #REF! #REF!
15 P. BB. 11 #REF! #REF!
16 P. BB. 11.a #REF! #REF!
17 P. BB. 12 #REF! #REF!
18 P. BB. 12.a #REF! #REF!
19 P. BB. 13 #REF! #REF!
20 P. BB. 13.a #REF! #REF!
21 P. BB. 14 #REF! #REF!
22 P. BB. 15 #REF! #REF!
23 P. BB. 16 #REF! #REF!
24 P. BB. 17 #REF! #REF!
25 P. BB. 18 #REF! #REF!
26 P. BB. 19 #REF! #REF!
27 P. BB. 20 #REF! #REF!
28 P. BB. 21 #REF! #REF!
29 P. BB. 22 #REF! #REF!
30 P. BB. 23 #REF! #REF!
31 P. BB. 24 #REF! #REF!
32 P. BB. 25 #REF! #REF!

Rekap SNI 68
HARGA SATUAN
NO KODE ANALISA URAIAN PEKERJAAN
(Rp)
1 2 3 4
E. PEKERJAAN DINDING
1 P. Dnd. 01 #REF! #REF!
2 P. Dnd. 02 #REF! #REF!
3 P. Dnd. 03 #REF! #REF!
4 P. Dnd. 04 #REF! #REF!
5 P. Dnd. 05 #REF! #REF!
6 P. Dnd. 06 #REF! #REF!
F. PEKERJAAN PLESTERAN
1 P. Pls. 01 #REF! #REF!
2 P. Pls. 02 #REF! #REF!
3 P. Pls. 03 #REF! #REF!
4 P. Pls. 04 #REF! #REF!
5 P. Pls. 05 #REF! #REF!
6 P. Pls. 06 #REF! #REF!
7 P. Pls. 07 #REF! #REF!
8 P. Pls. 08 #REF! #REF!
G. PEKERJAAN KAYU
#REF!
1 P. K. 01 #REF!
#REF!
#REF!
2 P. K. 02 #REF! #REF!
#REF!
3 P. K. 03 #REF! #REF!
#REF!
#REF!
4 P. K. 04 #REF! #REF!
#REF!
5 P. K. 05 #REF! #REF!
6 P. K. 06 #REF! #REF!
7 P. K. 07 #REF! #REF!
8 P. K. 08 #REF! #REF!
9 P. K. 09 #REF! #REF!
10 P. K. 10 #REF! #REF!
11 P. K. 11 #REF! #REF!
12 P. K. 12 #REF! #REF!
13 P. K. 12.a #REF! #REF!
14 P. K. 13 #REF! #REF!
15 P. K. 14 #REF! #REF!
16 P. K. 15 #REF! #REF!
17 P. K. 16 #REF! #REF!
18 P. K. 17 #REF! #REF!
#REF!
19 P.K. 18 #REF! #REF!
20 P. K. 19 #REF! #REF!
21 P. K. 20 #REF! #REF!
22 P. K. 21 #REF! #REF!
23 P. K. 22 #REF! #REF!
#REF!
24 P. K. 23 #REF! #REF!
25 P. K. 24 #REF! #REF!
26 P. K. 25 #REF! #REF!
27 P. K. 26 #REF! #REF!
28 P. K. 27 #REF! #REF!
29 P. K. 28 #REF! #REF!
30 P. K. 29 #REF! #REF!
31 P. K. 30 #REF! #REF!
32 P. K. 30.a #REF! #REF!
33 P. K. 31 #REF! #REF!
34 P. K. 32 #REF! #REF!
35 P. K. 33 #REF! #REF!
36 P. K. 34 #REF! #REF!
37 P. K. 35 #REF! #REF!
38 P. K. 36 #REF! #REF!
39 P. K. 37 #REF! #REF!
40 P. K. 38 #REF! #REF!
41 P. K. 39 #REF! #REF!
42 P. K. 40 #REF! #REF!
43 P. K. 41 #REF! #REF!
44 P. K. 42 #REF! #REF!
45 P. K. 43 #REF! #REF!
46 P. K. 44 #REF! #REF!
47 P. K. 45 #REF! #REF!
48 P. K. 46 #REF! #REF!
50 P. K. 47 #REF! #REF!
49 P. K. 47.a #REF! #REF!
51 P. K. 48 #REF! #REF!
52 P. K. 49 #REF! #REF!

Rekap SNI 69
HARGA SATUAN
NO KODE ANALISA URAIAN PEKERJAAN
(Rp)
1 2 3 4
53 P. K. 50 #REF! #REF!
54 P. K. 51 #REF! #REF!

Rekap SNI 70
HARGA SATUAN
NO KODE ANALISA URAIAN PEKERJAAN
(Rp)
1 2 3 4
H. PEKERJAAN PENUTUP ATAP
1 P. PA. 01 #REF! #REF!
2 P. PA. 02 #REF! #REF!
3 P. PA. 03 #REF! #REF!
4 P. PA. 04 #REF! #REF!
5 P. PA. 05 #REF! #REF!
6 P. PA. 06 #REF! #REF!
7 P. PA. 07 #REF! #REF!
8 P. PA. 08 #REF! #REF!
9 P. PA. 09 #REF! #REF!
10 P. PA. 10 #REF! #REF!
11 P. PA. 11 #REF! #REF!
12 P. PA. 12 #REF! #REF!
13 P. PA. 12.a #REF! #REF!
14 P. PA. 12.b #REF! #REF!
15 P. PA. 13 #REF! #REF!
16 P. PA. 14 #REF! #REF!
17 P. PA. 15 #REF! #REF!
18 P. PA. 16 #REF! #REF!
19 P. PA. 17 #REF! #REF!
20 P. PA. 18 #REF! #REF!
21 P. PA. 19 #REF! #REF!
22 P. PA. 20 #REF! #REF!
23 P. PA. 21 #REF! #REF!
I. PEKERJAAN PLAFOND
1 P. Pf. 01 #REF! #REF!
2 P. Pf. 02 #REF! #REF!
3 P. Pf. 03 #REF! #REF!
4 P. Pf. 04 #REF! #REF!
5 P. Pf. 05 #REF! #REF!
6 P. Pf. 06 #REF! #REF!
J. PEKERJAAN SANITASI
1 P. Snt. 01 #REF! #REF!
2 P. Snt. 02 #REF! #REF!
3 P. Snt. 03 #REF! #REF!
4 P. Snt. 04 #REF! #REF!
5 P. Snt. 05 #REF! #REF!
6 P. Snt. 06 #REF! #REF!
7 P. Snt. 07 #REF! #REF!
8 P. Snt. 08 #REF! #REF!
9 P. Snt. 09 #REF! #REF!
10 P. Snt. 10 #REF! #REF!
11 P. Snt. 11 #REF! #REF!
12 P. Snt. 12 #REF! #REF!
13 P. Snt. 13 #REF! #REF!
14 P. Snt. 14 #REF! #REF!
15 P. Snt. 15 #REF! #REF!
K. PEKERJAAN BESI DAN ALUMINIUM
1 P. BA. 01 #REF! #REF!
2 P. BA. 02 #REF! #REF!
3 P. BA. 03 #REF! #REF!
4 P. BA. 04 #REF! #REF!
5 P. BA. 05 #REF! #REF!
6 P. BA. 06 #REF! #REF!
7 P. BA. 07 #REF! #REF!
8 P. BA. 08 #REF! #REF!
9 P. BA. 09 #REF! #REF!
10 P. BA. 10 #REF! #REF!
11 P. BA. 11 #REF! #REF!
12 P. BA. 12 #REF! #REF!
13 P. BA. 13 #REF! #REF!

Rekap SNI 71
HARGA SATUAN
NO KODE ANALISA URAIAN PEKERJAAN
(Rp)
1 2 3 4
L. PEKERJAAN KUNCI DAN KACA
1 P. KK. 01 #REF! #REF!
2 P. KK. 02 #REF! #REF!
3 P. KK. 03 #REF! #REF!
4 P. KK. 04 #REF! #REF!
5 P. KK. 04.a #REF! #REF!
6 P. KK. 05 #REF! #REF!
7 P. KK. 06 #REF! #REF!
8 P. KK. 07 #REF! #REF!
9 P. KK. 07.a #REF! #REF!
10 P. KK. 08 #REF! #REF!
11 P. KK. 09 #REF! #REF!
12 P. KK. 10 #REF! #REF!
13 P. KK. 11 #REF! #REF!
14 P. KK. 12 #REF! #REF!
M. PEKERJAAN PENUTUP LANTAI DAN DINDING
1 P. LD. 01 #REF! #REF!
2 P. LD. 02 #REF! #REF!
3 P. LD. 03 #REF! #REF!
4 P. LD. 04 #REF! #REF!
5 P. LD. 04.a #REF! #REF!
6 P. LD. 05 #REF! #REF!
7 P. LD. 05.a #REF! #REF!
8 P. LD. 06 #REF! #REF!
9 P. LD. 07 #REF! #REF!
10 P. LD. 08 #REF! #REF!
11 P. LD. 09 #REF! #REF!
12 P. LD. 10 #REF! #REF!
13 P. LD. 11 #REF! #REF!
14 P. LD. 12 #REF! #REF!
15 P. LD. 13 #REF! #REF!
N. PEKERJAAN PENGECATAN
1 P. Ct. 01 #REF! #REF!
2 P. Ct. 02 #REF! #REF!
3 P. Ct. 03 #REF! #REF!
4 P. Ct. 04 #REF! #REF!
5 P. Ct. 05 #REF! #REF!
6 P. Ct. 06 #REF! #REF!
7 P. Ct. 07 #REF! #REF!
8 P. Ct. 08 #REF! #REF!
9 P. Ct. 09 #REF! #REF!
10 P. Ct. 10 #REF! #REF!
#REF!
11 P. Ct. 11 #REF!
#REF!
#REF!
12 P. Ct. 12 #REF! #REF!
13 P. Ct. 13 #REF! #REF!
14 P. Ct. 14 #REF! #REF!
15 P. Ct. 15 #REF! #REF!
O. PEKERJAAN BONGKARAN
1 P. Bkr. 01 #REF! #REF!
2 P. Bkr. 02 #REF! #REF!
3 P. Bkr. 03 #REF! #REF!
4 P. Bkr. 04 #REF! #REF!
5 P. Bkr. 05 #REF! #REF!
6 P. Bkr. 06 #REF! #REF!
7 P. Bkr. 07 #REF! #REF!

WALIKOTA PONTIANAK,

SUTARMIDJI

Rekap SNI 72
DAFTAR HARGA DASAR SATUAN BAHAN DAN UPAH TAHUN ANGGARAN 2017
KECAMATAN SUNGAI MELAYU RAYAK
HARGA PAJAK MINERAL JUMLAH ONGKOS ANGKUTAN
NO. NAMA BARANG SAT DASAR BUKAN LOGAM HARGA /ESKALASI
( Rp. ) ( Rp. ) ( Km ) ( Rp. )
1 2 3 4 5 = (15 % x 4) 6 = (4 + 5) 7
A. BAHAN PENGISI
1 Tanah Urug ( Timb. Biasa ) M³ 95,000.00 14,250.00 109,250.00
2 Tanah Urug ( laterit / gravel ) M³ 115,000.00 17,250.00 132,250.00
3 Pasir Beton M³ 125,000.00 18,750.00 143,750.00
4 Batu Balok M³ 310,000.00 46,500.00 356,500.00
5 Batu Pecah 20-25 Cm M³ 315,000.00 47,250.00 362,250.00
6 Batu Pecah 15-20 Cm M³ 325,000.00 48,750.00 373,750.00
7 Batu Pecah 10-15 Cm M³ 335,000.00 50,250.00 385,250.00
8 Batu Pecah 5-7 Cm M³ 340,000.00 51,000.00 391,000.00
9 Batu Pecah 3-5 Cm M³ 355,000.00 53,250.00 408,250.00
10 Batu Pecah 2-3 cm M³ 375,000.00 56,250.00 431,250.00
11 Batu Pecah 1-2 cm M³ 405,000.00 60,750.00 465,750.00
12 Batu Pecah 0,5-1 Cm M³ 600,000.00 90,000.00 690,000.00
13 Debu Batu ( Stone Dust ) M³ 640,000.00 96,000.00 736,000.00
14 Semen (1 Zak @ 50 kg) Kg 1,600.00 1,600.00 68.21
15 Semen Putih Kg 2,600.00 2,600.00 68.21
16 Semen MU - 380 ( 40 Kg /Zak) Kg 4,700.00 4,700.00 85.26
17 Aspal Penetrasi 60/70 (Netto 155 Kg) Kg 16,129.03 16,129.03 23.24
B. BAHAN KAYU
1 Balok Belian Ketam M³ 7,250,000.00 7,250,000.00
2 Balok Belian Tidak Ketam M³ 6,750,000.00 6,750,000.00
3 Balok Belian Untuk Jembatan M³ 7,750,000.00 7,750,000.00
4 Papan Kayu Belian Ketam M³ 8,350,000.00 8,350,000.00
5 Papan Kayu Belian Tidak Ketam M³ 7,950,000.00 7,950,000.00
6 Balok Kayu Klas II Ketam M³ 3,000,000.00 3,000,000.00
7 Balok Kayu Klas II Tidak Ketam M³ 2,700,000.00 2,700,000.00
8 Papan Kayu Klas II Ketam M³ 3,250,000.00 3,250,000.00
9 Papan Kayu Klas II Tidak Ketam M³ 2,850,000.00 2,850,000.00
10 Papan Kayu Camp. ( Klas III ) M³ 1,900,000.00 1,900,000.00
11 Kayu Bulat Ø 8 - 12 Cm / 4 M' Btg 9,500.00 9,500.00
12 Kayu Bulat Ø 6 - 8 Cm / 4 M' Btg 6,200.00 6,200.00
Kayu cerucuk /dolken ø12 - Pj. 8 M btg 86,300.00 86,300.00
Kayu cerucuk /dolken ø 15 - Pj. 12 M btg 104,900.00 104,900.00
13 Upah pemancangan bh 15,000.00 15,000.00
14 Kayu Bakar M³ 230,000.00 230,000.00
C. BAHAN ATAP
1 Atap Sirap Aspal 3 mm M2 343,500.00 343,500.00 49.12
2 Genteng Bh 850.40 850.40 1,360.64
Atap genteng metal prima 0,35 bh 59,100.00 59,100.00 432.25
Rangka Baja Ringan Zincalume (Truss / Polos) (Tanpa Jurai Dalam - Bentang s/d 16 m) m2 215,000.00 215,000.00 432.25
nok atap zincalum bh 35,000.00 35,000.00 432.25
Atap Spandek Zincalume 0,35 lebar 1 m bh 58,500.00 58,500.00 432.25
Mini pile UK. 20x20x6M K350 btg 1,120,000.00 1,120,000.00 432.25
Upah Pemancangan Mini File Btg 125,000.00 125,000.00 432.25
3 Bumbungan ( Genteng ) Bh 1,860.25 1,860.25 2,976.40
4 Seng Plat BJLS 0.20 Kpg 45,000.00 45,000.00 432.25
5 Seng Plat BJLS 0.30 Kpg 56,000.00 56,000.00 432.25
6 Seng Gelombang BJLS 0.20 Kpg 44,000.00 44,000.00 432.25
7 Seng Gelombang BJLS 0.30 Kpg 57,000.00 57,000.00 432.25
8 Seng Alcan Gel. Kecil 0.25 Mm Kpg 55,500.00 55,500.00 432.25
9 Seng Alcan Gel. Besar 0.25 Mm Kpg 45,000.00 45,000.00 432.25
10 Alumunium Genteng Metal
( Uk. 135 x 40 cm Kualitas A ) Kpg 75,000.00 75,000.00 432.25
11 Alumunium Plat 0.20 mm Kpg 78,000.00 78,000.00 432.25
12 Alumunium Plat 0.30 mm Kpg 90,000.00 90,000.00 432.25
13 Seng Metal Plat 0.30 mm Kpg 90,000.00 90,000.00 72.04
14 Metal Pooring (Zincalume ) Kpg 70,000.00 70,000.00 72.04
D. BAHAN CAT
1 Cat Kilat Kg 55,000.00 55,000.00
2 Cat Tembok Kg 65,000.00 65,000.00
3 Cat Dasar Kg 42,000.00 42,000.00
4 Cat Meni Besi Kg 160,000.00 160,000.00
5 Cat Meni Kayu Kg 145,000.00 145,000.00
6 Pelamur Kayu Kg 135,000.00 135,000.00
7 Pelamur Air Kg 50,000.00 50,000.00
Dempul kg 17,500.00 17,500.00 56.28
Teak Oil ltr 48,400.00 48,400.00 56.28
Politur ltr 46,900.00 46,900.00 56.28
Cat Water Proofing kg 224,770.00 224,770.00 56.28
Pernis kg 45,200.00 45,200.00 56.28
Jaring Kasa debu lbr 10,000.00 10,000.00 56.28
8 Teer Ltr 15,000.00 15,000.00
9 Tineer Ltr 20,000.00 20,000.00
E. BAHAN BAKAR
1 Solar Industri Ltr 13,500.00 13,500.00 18.01
2 Minyak Tanah Ltr 15,000.00 15,000.00 18.01
3 Premium Industri Ltr 12,000.00 12,000.00 18.01
4 Pelumas SAE 10 Ltr 60,000.00 60,000.00 18.01
5 Pelumas SAE 30 Ltr 55,000.00 55,000.00 18.01
6 Pelumas SAE 40 Ltr 60,000.00 60,000.00 18.01
7 Oli 2T Ltr 55,000.00 55,000.00 18.01
8 Oli SAE 140 ( Oli Gardan ) Ltr 50,000.00 50,000.00 18.01
9 Oli SAE 90 Ltr 45,000.00 45,000.00 18.01
10 Oli SAE 20w-50 ( Bensin ) Ltr 55,000.00 55,000.00 18.01
11 Minyak Gemuk Ltr 70,000.00 70,000.00 18.01
12 Flux Oil Ltr 65,000.00 65,000.00 18.01
F. BAHAN PENUTUP LANTAI
1 Paving 20x20 Keping 2,400.00 2,400.00
2 Paving 18x18 Keping 2,200.00 2,200.00
3 Bataco 8x15x30 Keping 2,000.00 2,000.00
4 Bataco 7x15x30 Keping 1,750.00 1,750.00
5 Bataco 6x15x30 Keping 1,500.00 1,500.00
Bata Merah bh 958.50 958.50 112.57
Batu tempel hitam bh 395,000.00 395,000.00 112.57
batu traso kg 2,880.00 2,880.00 112.57
parquet kayu m2 185,000.00 185,000.00 112.57
vynil bh 45,475.00 45,475.00 112.57
oker kg 13,700.00 13,700.00 112.57
6 Keramik Anti Gores 60x60 ( Motif ) M2 (Ktk) 320,000.00 320,000.00 120.07
7 Keramik Anti Gores 60x60 ( Polos ) M2 (Ktk) 220,000.00 220,000.00 120.07
8 Keramik 40x40 M2 (Ktk) 133,000.00 133,000.00 120.07
9 Keramik 30x30 ( Polos ) M2 (Ktk) 99,900.00 99,900.00 120.07
10 Keramik 30x30 ( Motif ) M2 (Ktk) 122,100.00 122,100.00 120.07
11 Keramik 20x20 ( Polos ) M2 (Ktk) 87,500.00 87,500.00 30.02
12 Keramik 20x20 ( Motif ) M2 (Ktk) 97,500.00 97,500.00 30.02
HARGA PAJAK MINERAL JUMLAH ONGKOS ANGKUTAN
NO. NAMA BARANG SAT DASAR BUKAN LOGAM HARGA /ESKALASI
( Rp. ) ( Rp. ) ( Km ) ( Rp. )
1 2 3 4 5 = (15 % x 4) 6 = (4 + 5) 7
13 Keramik 20x25 ( Polos ) M2 (Ktk) 90,000.00 90,000.00 30.02
14 Keramik Dinding 20 x 25 cm M2 (Ktk) 110,000.00 110,000.00 30.02
G. BAHAN PENGGANTUNG
1 Paku Alumunium Kg 65,000.00 65,000.00 17.29
Paku Besi uk. 1/2" - 1 " Kg 22,900.00 22,900.00 17.29
2 Paku Besi uk. 2" - 4 " Kg 16,000.00 16,000.00 17.29
3 Paku Sirap Kg 18,000.00 18,000.00
4 Paku Payung ( Utk Atap Seng ) Kg 26,000.00 26,000.00 17.29
5 Paku Tripleks Kg 22,000.00 22,000.00 17.29
6 Paku S Pcs 1,000.00 1,000.00 17.29
paku gypsum kg 55,600.00 55,600.00 162.10
Paku campuran 5 - 7 cm kg 12,500.00 12,500.00 162.10
paku belian kg 36,100.00 36,100.00 162.10
7 Kait Angin Jendela Bh 10,000.00 10,000.00 162.10
Handle pintu bh 148,500.00 148,500.00 162.10
handle jendela bh 15,390.00 15,390.00 162.10
8 Gagang Pintu Bh 80,000.00 80,000.00 162.10
9 Kunci Tanam Biasa Bh 75,000.00 75,000.00 162.10
10 Kunci Tanam Besar Bh 150,000.00 150,000.00 162.10
Kunci Tanam Silinder Bh 83,880.00 83,880.00 162.10
11 Engsel Jendela Psg 8,000.00 8,000.00 8.10
12 Engsel Pintu Psg 10,000.00 10,000.00 8.10
Slot Pintu bh 23,520.00 23,520.00 8.10
Slot Jendela bh 8,760.00 8,760.00 8.10
13 Grendel 10" Bh 40,000.00 40,000.00
14 Grendel 3" Bh 10,000.00 10,000.00
15 Grendel 2" Bh 7,000.00 7,000.00
H. SANITASI
1 Kloset duduk CW868NJ Bh 5,170,000.00 5,170,000.00 5,403.13
2 Kloset Jongkok CE9/TV150NWV12 Bh 3,443,000.00 3,443,000.00 5,403.13
Kloset Duduk Monoblok EX TOTO (colour) bh 1,201,750.00 1,201,750.00 5,403.13
3 Kloset Jongkok warna Bh 280,000.00 280,000.00 5,403.13
4 Kloset Jongkok putih Bh 230,000.00 230,000.00 5,403.13
westapel spoelhoek (setara toto) bh 2,620,000.00 2,620,000.00 5,403.13
Soap dsih Taman ex lokal bh 70,000.00 70,000.00 5,403.13
5 Wastafel LW242J/LW242HF Bh 1,648,900.00 1,648,900.00 5,403.13
6 wastafel lengkap Bh 550,000.00 550,000.00 5,403.13
westapel lengkap setara toto bh 947,500.00 947,500.00 5,403.13
bak cuci piring stainlees unit 1,700,000.00 1,700,000.00 5,403.13
waterdrain bh 350,000.00 350,000.00 5,403.13
sealtape bh 10,000.00 10,000.00 5,403.13
7 Wall Shower Bh 170,000.00 170,000.00 5,403.13
8 Kran Air RRC Uk. 3/4" Bh 17,500.00 17,500.00 100.06
9 Kran Air Biasa Uk. 3/4" Bh 8,000.00 8,000.00 100.06
10 Kran Air Kuningan Uk. 3/4" Bh 30,000.00 30,000.00 100.06
Jet Spray untuk Kloset Duduk (setara Toto) bh 55,000.00 55,000.00 100.06
11 Floordrain Bh 15,000.00 15,000.00 33.25
12 ESL Bord Tebal 7,5 cm M2 260,000.00 260,000.00 360.21
I BAHAN PLAFOND
12 Tripleks 2.5 mm Lbr 55,000.00 55,000.00 360.21
13 Multiplek 5 mm Lbr 95,000.00 95,000.00 360.21
14 Multiplek 9 mm Lbr 170,000.00 170,000.00 1,309.85
15 Multiplek 12 mm Lbr 230,000.00 230,000.00 1,729.00
16 Papan Gypsum ( 122 x 244 ) cm Lbr 70,000.00 70,000.00 1,729.00
GRC Board (120 x 240 x 3,5) Lbr 72,000.00 72,000.00 1,729.00
17 Akustik 60 x 120 Lbr 90,000.00 90,000.00 1,729.00
Lis Gypsum/ kayu m' 10,590.00 10,590.00 1,729.00
18 Casting Jaya ( Tepung Gypsum ) Kg 6,000.00 6,000.00 1,729.00
J BAHAN KACA
19 Kaca 3 mm ( Polos ) M² 135,000.00 135,000.00 750.43
20 Kaca 5 mm ( Polos ) M² 160,000.00 160,000.00 750.43
Kaca Tebal 12 mm M² 210,000.00 210,000.00 750.43
21 Kaca Raiben 3 mm M² 155,000.00 155,000.00 750.43
22 Kaca Raiben 5 mm M² 185,000.00 185,000.00 750.43
K BAHAN BESI DAN ALUMINIUM
23 Kaca Stopsol 8 mm Silver Green Ex. Asaimas M² 632,500.00 632,500.00 750.43
24 Pintu Tempered Polos 12 mm - Uk. 87 x 213,5 cm Unit 4,840,000.00 4,840,000.00 750.43
25 Baut Besi Uk. D = 1/2 - 10 cm Btg 3,000.00 3,000.00 4.63
26 Baut Besi Uk. D = 1/2 - 20 cm Btg 7,500.00 7,500.00 4.63
27 Baut Besi Uk. D = 1/2 - 30 cm Btg 15,000.00 15,000.00 4.63
28 Baut Besi Uk. D = 5/8 - 10 cm Btg 8,000.00 8,000.00 8.21
29 Baut Besi Uk. D = 5/8 - 20 cm Btg 15,000.00 15,000.00 8.21
30 Baut Besi Uk. D = 5/8 - 30 cm Btg 24,000.00 24,000.00 8.21
31 Baut Besi Uk. D = 3/4 - 10 cm Btg 11,000.00 11,000.00 11.59
32 Baut Besi Uk. D = 3/4 - 20 cm Btg 18,000.00 18,000.00 11.59
33 Baut Besi Uk. D = 3/4 - 30 cm Btg 26,000.00 26,000.00 11.59
34 Beugel Plat L = 3 cm Bh 22,000.00 22,000.00 185.52
35 Besi Tulangan Beton ulir Kg 18,000.00 18,000.00 216.13
36 Besi Tulangan Beton polos Kg 13,500.00 13,500.00 185.52
Wiremesh Kg 19,850.00 19,850.00 24.01
37 Kawat Bendrat Kg 20,500.00 20,500.00 24.01
38 Kawat Simpai Kg 17,500.00 17,500.00 24.01
39 Kawat dia 4 mm Kg 16,000.00 16,000.00 25.61
40 Baja Profil Kg 35,000.00 35,000.00 25.61
41 Baja Struktur Kg 55,000.00 55,000.00 25.61
42 Baja Ringan Untuk Kuda Kuda M' 20,000.00 20,000.00 25.61
43 Baja Ringan Untuk Gording M' 10,000.00 10,000.00 25.61
44 Profil Allum " T " M' 12,500.00 12,500.00 25.61
45 Profil Kusen Aluminium YKK 3" M' 130,000.00 130,000.00 25.61
46 Profil Pintu Aluminium M' 70,000.00 70,000.00 25.61
Sunscreen Aluminium M2 385,500.00 385,500.00 25.61
47 Profil Kaca M' 45,000.00 45,000.00 25.61
Besi Penahan Talang M' 18,400.00 18,400.00 25.61
48 Rangka Metal hollow 40.40.2 mm M' 26,000.00 26,000.00 25.61
Rangka Metal hollow 40.40.2,1 mm M' 29,333.00 29,333.00 216.13
Rangka Metal hollow 40.40.1,1 mm M' 14,117.00 14,117.00 216.13
Braket siku 40 x 40 x 4 mm M' 5,500.00 5,500.00 216.13
Bracket ACP M' 1,500.00 1,500.00 216.13
Brazing M' 44,000.00 44,000.00 216.13
49 Besi L ( untuk Jembatan) M' 60,000.00 60,000.00 5,763.33
50 Kabel Seling Ø 1/2" (Blue Strand/Full Baja) M' 80,000.00 80,000.00 2,753.18
51 Kabel Seling Ø 3/4" (Blue Strand/Full Baja) M' 140,000.00 140,000.00
52 Kabel Selling Ø 1,3/4" (Blue Strand/Full Baja) M' 0.00 0.00 11,682.43
53 Kabel Selling Ø 1" (Multi Strand Roof) M' 46,000.00 46,000.00 5,763.33
54 Kabel Selling Biasa Ø 1/2" M' 10,000.00 10,000.00 2,753.18
55 Kabel Selling Biasa Ø 3/4" M' 17,000.00 17,000.00 22.48
56 Jarum Keras 1,5"x24" Bh 165,000.00 165,000.00 22.48
57 Jarum Keras 5/8"x12" Bh 145,000.00 145,000.00 22.48
58 Jarum Keras 1/2"x6" Bh 20,000.00 20,000.00 22.48
HARGA PAJAK MINERAL JUMLAH ONGKOS ANGKUTAN
NO. NAMA BARANG SAT DASAR BUKAN LOGAM HARGA /ESKALASI
( Rp. ) ( Rp. ) ( Km ) ( Rp. )
1 2 3 4 5 = (15 % x 4) 6 = (4 + 5) 7
59 Jarum Keras M - 16 Bh 165,000.00 165,000.00 22.48
60 Klem Kabel Ukr. 1/2 Bh 9,000.00 9,000.00 22.48
61 Klem Label Uk. 1/2" Bh 9,000.00 9,000.00 22.48
62 Klem Label Uk. 3/4" Bh 11,235.00 11,235.00 22.48
63 Klem Label Uk. 1" Bh 16,000.00 16,000.00 1,108.33
64 Meteran Air Bersih Set 390,000.00 390,000.00 22.48
65 Sealtape Bh 5,000.00 5,000.00 22.48
66 Shower TX4235 Bh 710,000.00 710,000.00 1,108.33
67 Mesin Jet Pump Kap. 250 watt Bh 4,752,000.00 4,752,000.00
68 Septictank Biosel Kap. 6 m3 Unit 7,000,000.00 7,000,000.00 33,250.00
69 Alumunium Komposit + Rangka Besi M2 1,145,000.00 1,145,000.00 33,250.00
Alumunium Komposit 0,4 setara seven 1,2 x 2,4 lbr 220,000.00 220,000.00
70 Curtain Wall Kaca green stopsol 8 mm ex. Asaimas M2 1,450,000.00 1,450,000.00
71 Ramset Bh 11,000.00 11,000.00
72 Skrup Fixer Bh 1,500.00 1,500.00
73 Sandblast M2 85,000.00 85,000.00
74 Sealant Kg 122,900.00 122,900.00 360.21
75 Lem Kayu Kg 25,000.00 25,000.00 1,309.85
76 Plywood 4 mm Lbr 60,300.00 60,300.00 1,729.00
77 Plywood 9 mm Lbr 262,000.00 262,000.00 1,729.00
78 Phenol film 12 mm Lbr 300,000.00 300,000.00 1,309.85
79 HPL 1,22 m x 2,44 m x 0,7 mm Lbr 450,000.00 450,000.00
80 List Metal stainless steel M' 100,000.00 100,000.00
81 Door Stoper Bh 250,000.00 250,000.00
Door Stoper/ ptk + ongkir Bh 60,400.00 60,400.00
Door Closer Bh 196,800.00 196,800.00
82 Realing stainless steel Bh 600,000.00 600,000.00
83 Plafond Alumunium Strip Celing Rangka Metal Furing M2 1,160,000.00 1,160,000.00
84 Dinabolt dia 12 mm (10 - 15) cm Bh 5,000.00 5,000.00 400.23
85 Kuas Bh 20,000.00 20,000.00 150.09
86 Amplas Bh 3,000.00 3,000.00 150.09
87 Kawat Las Kg 35,000.00 35,000.00 150.09
88 Talang Paralon Type U Btg 65,000.00 65,000.00 601.85
89 Tutup Talang Bh 15,000.00 15,000.00 225.69
90 Corong Talang Bh 15,000.00 15,000.00 225.69
91 Kait Talang Bh 4,000.00 4,000.00 225.69
I. PIPA PVC KLAS A (SNI. PRJ. S. 12.5 )
1 Pipa PVC Ø = 1/2" x 6 M' Btg 90,000.00 90,000.00 14.41
2 Pipa PVC Ø = 3/4" x 6 M' Btg 120,000.00 120,000.00 32.55
3 Pipa PVC Ø = 1" x 6 M' Btg 150,000.00 150,000.00 63.38
4 Pipa PVC Ø = 2" x 6 M' Btg 175,000.00 175,000.00 232.39
5 Pipa PVC Ø = 2½" x 6 M" Btg 225,000.00 225,000.00 432.25
6 Pipa PVC Ø = 3" x 6 M' Btg 350,000.00 350,000.00 540.31
7 Pipa PVC Ø = 4" x 6 M" Btg 550,000.00 550,000.00 960.56
8 Pipa PVC Ø = 6" x 6 M" Btg 1,300,000.00 1,300,000.00 2,161.25
9 Elbow PVC Ø 1/2" Bh 3,000.00 3,000.00 4.50
10 Elbow PVC Ø 3/4" Bh 3,500.00 3,500.00 4.50
11 Elbow PVC Ø 1" Bh 5,500.00 5,500.00 4.50
12 Elbow PVC Ø 2" Bh 14,000.00 14,000.00 5.40
13 Elbow PVC Ø 3" Bh 35,000.00 35,000.00 17.15
14 Elbow PVC Ø 4" Bh 60,000.00 60,000.00 24.01
15 All Socket Pipa PVC Ø 2" Bh 11,000.00 11,000.00 21.61
16 All Socket Pipa PVC Ø 3" Bh 25,000.00 25,000.00 57.63
17 All Socket Pipa PVC Ø 4" Bh 45,000.00 45,000.00 148.20
18 All Socket Tee PVC Ø 2" Bh 18,000.00 18,000.00 441.07
19 All Socket Tee PVC Ø 3" Bh 40,000.00 40,000.00 441.07
20 All Socket Tee PVC Ø 4" Bh 80,000.00 80,000.00 441.07
21 Pipa Galvanis Ø 1/2" - 6 M' Btg 95,000.00 95,000.00 126.57
22 Pipa Galvanis Ø 3/4" - 6 M' Btg 110,000.00 110,000.00 163.92
23 Pipa Galvanis Ø 1" - 6 M' Btg 240,000.00 240,000.00 121.76
24 Pipa Galvanis Ø 1,25" - 6 M' Btg 380,000.00 380,000.00 327.46
25 Pipa Galvanis Ø 1,5" - 6 M' Btg 350,000.00 350,000.00 375.87
26 Pipa Galvanis Medium Ø 2" - 6 M' Btg 470,000.00 470,000.00 533.64
27 Pipa Galvanis Medium Ø 2,5" - 6 M' Btg 600,000.00 600,000.00 675.39
28 Pipa Galvanis Medium Ø 3" - 6 M' Btg 900,000.00 900,000.00 882.14
29 Pipa Galvanis Medium Ø 6" - 6 M' Btg 1,550,000.00 1,550,000.00 2,058.33
30 Elbow Pipa Galvanis Ø 1/2" Bh 18,000.00 18,000.00 103.91
31 Elbow Pipa Galvanis Ø 3/4" Bh 21,000.00 21,000.00 103.91
32 Elbow Pipa Galvanis Ø 1" Bh 45,000.00 45,000.00 103.91
33 Elbow Pipa Galvanis Ø 1,25" Bh 16,000.00 16,000.00 103.91
34 Elbow Pipa Galvanis Ø 1,5" Bh 19,000.00 19,000.00 103.91
35 Elbow Pipa Galvanis Medium Ø 2" Bh 43,000.00 43,000.00 81.44
36 Elbow Pipa Galvanis Medium Ø 2,5" Bh 44,000.00 44,000.00 159.50
37 Elbow Pipa Galvanis Medium Ø 3" Bh 60,000.00 60,000.00 159.50
38 Elbow Pipa Galvanis Medium Ø 4" Bh 90,000.00 90,000.00 277.08
39 Flange Pipa GIV Ø 2" Bh 147,000.00 147,000.00 51.89
40 Flange Pipa GIV Ø 3" Bh 242,000.00 242,000.00 51.89
41 Flange Pipa GIV Ø 4" Bh 333,000.00 333,000.00 51.89
42 Flange Pipa GIV Ø 5" Bh 345,000.00 345,000.00 51.89
43 Pakin Karet Ø 2" Bh 5,500.00 5,500.00 225.13
44 Pakin Karet Ø 3" Bh 6,500.00 6,500.00 225.13
45 Pakin Karet GIV Ø 4" Bh 7,500.00 7,500.00 225.13
46 Reducer 3" - 2 " Bh 115,500.00 115,500.00 568.75
47 Reducer 4" - 3 " Bh 133,000.00 133,000.00 568.75
48 Filter Pipa GIV Ø 3" Bh 150,000.00 150,000.00 568.75
49 Filter Pipa GIV Ø 4" Bh 200,000.00 200,000.00 568.75
50 Pipa GIV Ø 2" - 6 Btg 741,500.00 741,500.00 882.14
51 Pipa GIV Ø 4" - 6 Btg 2,200,000.00 2,200,000.00 1,271.32
52 Pipa GIV Ø 5" - 6 Btg 2,264,000.00 2,264,000.00 1,729.00
53 Pipa GIV Ø 6" - 6 Btg 3,000,000.00 3,000,000.00 103.91
54 Pipa HDPE Ø 2" x 6 Btg 580,000.00 580,000.00 38.39
55 Pipa HDPE Ø 2,5" x 6 Btg 660,000.00 660,000.00 59.13
56 Pipa HDPE Ø 3" x 6 Btg 1,128,000.00 1,128,000.00 84.10
57 Pipa HDPE Ø 4" x 6 Btg 1,600,000.00 1,600,000.00 112.27
58 Pipa HDPE Ø 6" x 6 Btg 3,000,000.00 3,000,000.00 432.25
J. PIPA PVC KLAS B ( STANDARD AW )
1 Pipa PVC Ø = 1/2" x 4 M' Btg 25,000.00 25,000.00 14.41
2 Pipa PVC Ø = 3/4" x 4 M' Btg 30,000.00 30,000.00 32.55
3 Pipa PVC Ø = 1" x 4 M' Btg 35,000.00 35,000.00 63.38
4 Pipa PVC Ø = 2" x 4 M' Btg 80,000.00 80,000.00 232.39
5 Pipa PVC Ø = 2½" x 4 M' Btg 112,500.00 112,500.00 432.25
6 Pipa PVC Ø = 3" x 4 M' Btg 150,000.00 150,000.00 540.31
7 Pipa PVC Ø = 4" x 4 M' Btg 240,000.00 240,000.00 960.56
8 Elbow PVC Ø 1/2" Bh 3,000.00 3,000.00 4.50
9 Elbow PVC Ø 3/4" Bh 3,000.00 3,000.00 4.50
10 Elbow PVC Ø 1" Bh 5,000.00 5,000.00 4.50
11 Elbow PVC Ø 2" Bh 15,000.00 15,000.00 5.40
12 Elbow PVC Ø 3" Bh 18,000.00 18,000.00 17.15
HARGA PAJAK MINERAL JUMLAH ONGKOS ANGKUTAN
NO. NAMA BARANG SAT DASAR BUKAN LOGAM HARGA /ESKALASI
( Rp. ) ( Rp. ) ( Km ) ( Rp. )
1 2 3 4 5 = (15 % x 4) 6 = (4 + 5) 7
13 Elbow PVC Ø 4" Bh 30,000.00 30,000.00 24.01
14 All Socket Pipa PVC Ø 2" Bh 13,000.00 13,000.00 21.61
15 All Socket Pipa PVC Ø 3" Bh 18,000.00 18,000.00 57.63
16 All Socket Pipa PVC Ø 4" Bh 24,000.00 24,000.00 148.20
17 All Socket Tee PVC Ø 2" Bh 17,000.00 17,000.00 441.07
18 All Socket Tee PVC Ø 3" Bh 21,000.00 21,000.00 441.07
19 All Socket Tee PVC Ø 4" Bh 38,000.00 38,000.00 441.07
K. PIPA PVC KLAS C ( STANDARD C )
1 Pipa PVC Ø = 1/2" x 4 M' Btg 13,000.00 13,000.00 14.41
2 Pipa PVC Ø = 3/4" x 4 M' Btg 17,000.00 17,000.00 32.55
3 Pipa PVC Ø = 1" x 4 M' Btg 22,500.00 22,500.00 63.38
4 Pipa PVC Ø = 2" x 4 M' Btg 32,000.00 32,000.00 232.39
5 Pipa PVC Ø = 2½" x 4 M' Btg 45,000.00 45,000.00 432.25
6 Pipa PVC Ø = 3" x 4 M' Btg 60,000.00 60,000.00 540.31
7 Pipa PVC Ø = 4" x 4 M' Btg 80,000.00 80,000.00 960.56
8 Pipa PVC Ø = 8" x 4 M' Btg 230,000.00 230,000.00 3,087.50
9 Elbow PVC Ø 1/2" Bh 3,000.00 3,000.00 4.50
10 Elbow PVC Ø 3/4" Bh 3,500.00 3,500.00 4.50
11 Elbow PVC Ø 1" Bh 7,000.00 7,000.00 4.50
12 Elbow PVC Ø 2" Bh 12,500.00 12,500.00 5.40
13 Elbow PVC Ø 3" Bh 27,000.00 27,000.00 17.15
14 Elbow PVC Ø 4" Bh 32,000.00 32,000.00 24.01
15 All Socket Pipa PVC Ø 2" Bh 12,500.00 12,500.00 21.61
16 All Socket Pipa PVC Ø 3" Bh 27,000.00 27,000.00 57.63
17 All Socket Pipa PVC Ø 4" Bh 32,000.00 32,000.00 148.20
18 All Socket Tee PVC Ø 2" Bh 5,500.00 5,500.00 441.07
19 All Socket Tee PVC Ø 3" Bh 16,000.00 16,000.00 441.07
20 All Socket Tee PVC Ø 4" Bh 28,000.00 28,000.00 441.07
21 Alat Bantu (@ 3 set) Set 150,000.00 150,000.00
L. TONG AIR FIBER
1 Tong Air Vol. 1 M³ Bh 2,100,000.00 2,100,000.00 21,612.50
2 Tong Air Vol. 1,6 M³ Bh 2,900,000.00 2,900,000.00 21,612.50
3 Tong Air Vol. 2 M³ Bh 3,600,000.00 3,600,000.00 21,612.50
4 Bak Air Fiber Sudut ( Untuk WC) Bh 650,000.00 650,000.00 7,204.17
M. INSTALASI LISTRIK
1 Kabel NY 4 x 2.5 mm Rol 1,100,000.00 1,100,000.00 108.06
2 Kabel NY 3 x 2.5 mm Rol 850,000.00 850,000.00 108.06
3 Kabel NY 2 x 2.5 mm Rol 675,000.00 675,000.00 108.06
4 Kabel NY 1 x 2.5 mm Rol 580,000.00 580,000.00 108.06
5 Kabel NY 3 x 1.5 mm Rol 600,000.00 600,000.00 108.06
6 Kabel NY 2 x 1.5 mm Rol 500,000.00 500,000.00 108.06
7 Kabel NY 1 x 1.5 mm Rol 400,000.00 400,000.00 108.06
N SAKLAR
10 Saklar Tunggal Bh 20,000.00 20,000.00 6.77
11 Saklar Ganda Bh 25,000.00 25,000.00 6.77
12 Saklar Triple Bh 35,000.00 35,000.00 6.77
O STOP KONTAK
1 Stop Kontak Outbow 3L Bh 17,500.00 17,500.00 13.54
Stop Kontak inbow 12 A bh 31,130.00 31,130.00 13.54
Box Panel PJU Uk. 40 x 60 x 30 Cm lengkap Time Swich bh 475,000.00 475,000.00 60.03
Lampu LED SL 18 watt (setara Philips) bh 180,000.00 180,000.00 60.03
2 Fitting lampu Bh 12,500.00 12,500.00 60.03
3 Bola Lampu 9 - 11 watt Bh 40,000.00 40,000.00 60.03
4 Bola Lampu 15 - 25 watt Bh 55,000.00 55,000.00 60.03
5 Lampu TL bambu 20 Watt + Kapasitor Bh 100,000.00 100,000.00 60.03
6 Lampu TL bambu 40 Watt + Kapasitor Bh 140,000.00 140,000.00 60.03
7 Sekring 6 A Bh 20,000.00 20,000.00 60.03
8 Down Light Ø 2,5 " Bh 45,000.00 45,000.00 60.03
9 Down Light Ø 3,5 " Bh 55,000.00 55,000.00 60.03
Downlight 6 " (setara panasonic) bh 81,600.00 81,600.00 60.03
10 Down Light Ø 4 " Bh 68,000.00 68,000.00 60.03
P MCB ( STUD )
1 MCB 2 A + BOX Bh 35,000.00 35,000.00 13.54
2 MCB 4 A + BOX Bh 35,000.00 35,000.00 13.54
3 MCB 6 A + BOX Bh 35,000.00 35,000.00 13.54
4 MCB 10 A + BOX Bh 35,000.00 35,000.00 13.54
5 MCB 16 A + BOX Bh 40,000.00 40,000.00 13.54
Q PAKU SADEL DLL
1 Paku Sadel Beton Bh 12,000.00 12,000.00 2.77
2 Paku Sadel Biasa Bh 5,000.00 5,000.00 2.77
3 Isolasi Bungkus 10,000.00 10,000.00 2.77
4 T - Dus Bh 12,500.00 12,500.00 6.77
5 Klem Sadel Beton Bh 12,000.00 12,000.00 6.77

NO TENAGA KERJA SATUAN BIAYA UPAH / HARI BIAYA UPAH / JAM

1 Pekerja Orang / Hari Rp. 75,600.00


2 Pekerja agak terlatih Orang / Hari Rp.
3 Pekerja Terlatih Orang / Hari Rp. 99,750.00
4 Tenaga Ahli Orang / Hari Rp.
5 Tukang Orang / Hari Rp. 99,750.00
6 Kepala Tukang Orang / Hari Rp. 99,750.00
7 Mandor Orang / Hari Rp. 99,750.00
8 Operator Terlatih Orang / Hari Rp.
9 Pembantu Operator Orang / Hari Rp.
10 Mekanik Terlatih Orang / Hari Rp.
11 Pembantu Mekanik Orang / Hari Rp.
12 Supir Personil Orang / Hari Rp.
13 Supir Truk Orang / Hari Rp.
14 Pembantu Supir Orang / Hari Rp.
15 Penjaga Malam Orang / Hari Rp.
DAFTAR HARGA DASAR SATUAN BAHAN DAN UPAH TAHUN ANGGARAN 2017
KECAMATAN SUNGAI MELAYU RAYAK
HARGA PAJAK MINERAL JUMLAH ONGKOS ANGKUTAN KETERANGAN
JUMLAH TOTAL
NO. NAMA BARANG SAT DASAR BUKAN LOGAM HARGA /ESKALASI Kg / M¹
( Rp. ) ( Rp. ) ( Km ) ( Rp. ) ( Rp. ) LOKASI HARGA
1 2 3 4 5 = (15 % x 4) 6 = (4 + 5) 7 8 = (6 + 7) 9
A. BAHAN PENGISI
1 Tanah Urug ( Timb. Biasa ) M³ 95,000.00 14,250.00 109,250.00 109,250.00 64.26
2 Tanah Urug ( laterit / gravel ) M³ 115,000.00 17,250.00 132,250.00 132,250.00 77.79
3 Pasir Beton M³ 125,000.00 18,750.00 143,750.00 143,750.00 102.68
4 Batu Balok M³ 310,000.00 46,500.00 356,500.00 356,500.00 245.86
5 Batu Pecah 20-25 Cm M³ 315,000.00 47,250.00 362,250.00 362,250.00 249.83
6 Batu Pecah 15-20 Cm M³ 325,000.00 48,750.00 373,750.00 373,750.00 257.76
7 Batu Pecah 10-15 Cm M³ 335,000.00 50,250.00 385,250.00 385,250.00 265.69
8 Batu Pecah 5-7 Cm M³ 340,000.00 51,000.00 391,000.00 391,000.00 269.66
9 Batu Pecah 3-5 Cm M³ 355,000.00 53,250.00 408,250.00 408,250.00 281.55
10 Batu Pecah 2-3 cm M³ 375,000.00 56,250.00 431,250.00 431,250.00 297.41
11 Batu Pecah 1-2 cm M³ 405,000.00 60,750.00 465,750.00 465,750.00 321.21
12 Batu Pecah 0,5-1 Cm M³ 600,000.00 90,000.00 690,000.00 690,000.00 475.86
13 Debu Batu ( Stone Dust ) M³ 640,000.00 96,000.00 736,000.00 736,000.00 507.59
14 Semen (1 Zak @ 50 kg) Kg 1,600.00 1,600.00 68.21 1,668.21 1-13 kendawangan
15 Semen Putih Kg 2,600.00 2,600.00 68.21 2,668.21 ketapang
16 Semen MU - 380 ( 40 Kg /Zak) Kg 4,700.00 4,700.00 85.26 4,785.26 ketapang
17 Aspal Penetrasi 60/70 (Netto 155 Kg) Kg 16,129.03 16,129.03 23.24 16,152.27 ketapang
B. BAHAN KAYU
1 Balok Belian Ketam M³ 7,250,000.00 7,250,000.00 7,250,000.00 kendawangan
2 Balok Belian Tidak Ketam M³ 6,750,000.00 6,750,000.00 6,750,000.00 kendawangan
3 Balok Belian Untuk Jembatan M³ 7,750,000.00 7,750,000.00 7,750,000.00 kendawangan
4 Papan Kayu Belian Ketam M³ 8,350,000.00 8,350,000.00 8,350,000.00 kendawangan
5 Papan Kayu Belian Tidak Ketam M³ 7,950,000.00 7,950,000.00 7,950,000.00 kendawangan
6 Balok Kayu Klas II Ketam M³ 3,000,000.00 3,000,000.00 3,000,000.00 kendawangan
7 Balok Kayu Klas II Tidak Ketam M³ 2,700,000.00 2,700,000.00 2,700,000.00 kendawangan
8 Papan Kayu Klas II Ketam M³ 3,250,000.00 3,250,000.00 3,250,000.00 kendawangan
9 Papan Kayu Klas II Tidak Ketam M³ 2,850,000.00 2,850,000.00 2,850,000.00 kendawangan
10 Papan Kayu Camp. ( Klas III ) M³ 1,900,000.00 1,900,000.00 1,900,000.00 kendawangan
11 Kayu Bulat Ø 8 - 12 Cm / 4 M' Btg 9,500.00 9,500.00 9,500.00 kendawangan
12 Kayu Bulat Ø 6 - 8 Cm / 4 M' Btg 6,200.00 6,200.00 6,200.00 kendawangan
Kayu cerucuk /dolken ø12 - Pj. 8 M btg 86,300.00 86,300.00 86,300.00 kendawangan
Kayu cerucuk /dolken ø 15 - Pj. 12 M btg 104,900.00 104,900.00 104,900.00 kendawangan
13 Upah pemancangan bh 15,000.00 15,000.00 15,000.00 kendawangan
14 Kayu Bakar M³ 230,000.00 230,000.00 230,000.00 kendawangan
C. BAHAN ATAP
1 Atap Sirap Aspal 3 mm M2 343,500.00 343,500.00 49.12 343,549.12 ketapang
2 Genteng Bh 850.40 850.40 1,360.64 2,211.04 harga 2014 +
Atap genteng metal prima 0,35 bh 59,100.00 59,100.00 432.25 59,532.25 ketapang
Rangka Baja Ringan Zincalume (Truss / Polos) (Tanpa Jurai Dalam - Bentang s/d 16 m) m2 215,000.00 215,000.00 432.25 215,432.25 ketapang
nok atap zincalum bh 35,000.00 35,000.00 432.25 35,432.25 ketapang
Atap Spandek Zincalume 0,35 lebar 1 m bh 58,500.00 58,500.00 432.25 58,932.25 ketapang
Mini pile UK. 20x20x6M K350 btg 1,120,000.00 1,120,000.00 432.25 1,120,432.25 ketapang
Upah Pemancangan Mini File Btg 125,000.00 125,000.00 432.25 125,432.25 ketapang
3 Bumbungan ( Genteng ) Bh 1,860.25 1,860.25 2,976.40 4,836.65 harga 2014 +
4 Seng Plat BJLS 0.20 Kpg 45,000.00 45,000.00 432.25 45,432.25 ketapang
5 Seng Plat BJLS 0.30 Kpg 56,000.00 56,000.00 432.25 56,432.25 ketapang
6 Seng Gelombang BJLS 0.20 Kpg 44,000.00 44,000.00 432.25 44,432.25 ketapang
7 Seng Gelombang BJLS 0.30 Kpg 57,000.00 57,000.00 432.25 57,432.25 ketapang
8 Seng Alcan Gel. Kecil 0.25 Mm Kpg 55,500.00 55,500.00 432.25 55,932.25 ketapang
9 Seng Alcan Gel. Besar 0.25 Mm Kpg 45,000.00 45,000.00 432.25 45,432.25 ketapang
10 Alumunium Genteng Metal
( Uk. 135 x 40 cm Kualitas A ) Kpg 75,000.00 75,000.00 432.25 75,432.25 ketapang
11 Alumunium Plat 0.20 mm Kpg 78,000.00 78,000.00 432.25 78,432.25 ketapang
12 Alumunium Plat 0.30 mm Kpg 90,000.00 90,000.00 432.25 90,432.25 ketapang
13 Seng Metal Plat 0.30 mm Kpg 90,000.00 90,000.00 72.04 90,072.04 ketapang
14 Metal Pooring (Zincalume ) Kpg 70,000.00 70,000.00 72.04 70,072.04 ketapang
D. BAHAN CAT
1 Cat Kilat Kg 55,000.00 55,000.00 55,000.00 kendawangan
2 Cat Tembok Kg 65,000.00 65,000.00 65,000.00 kendawangan
3 Cat Dasar Kg 42,000.00 42,000.00 42,000.00 kendawangan
4 Cat Meni Besi Kg 160,000.00 160,000.00 160,000.00 kendawangan
5 Cat Meni Kayu Kg 145,000.00 145,000.00 145,000.00 kendawangan
6 Pelamur Kayu Kg 135,000.00 135,000.00 135,000.00 kendawangan
7 Pelamur Air Kg 50,000.00 50,000.00 50,000.00 kendawangan
Dempul kg 17,500.00 17,500.00 56.28 17,556.28 ketapang
Teak Oil ltr 48,400.00 48,400.00 56.28 48,456.28 ketapang
Politur ltr 46,900.00 46,900.00 56.28 46,956.28 ketapang
Cat Water Proofing kg 224,770.00 224,770.00 56.28 224,826.28 ketapang
Pernis kg 45,200.00 45,200.00 56.28 45,256.28 ketapang
Jaring Kasa debu lbr 10,000.00 10,000.00 56.28 10,056.28 ketapang
8 Teer Ltr 15,000.00 15,000.00 15,000.00 kendawangan
9 Tineer Ltr 20,000.00 20,000.00 20,000.00 kendawangan
E. BAHAN BAKAR
1 Solar Industri Ltr 13,500.00 13,500.00 18.01 13,518.01 ketapang
2 Minyak Tanah Ltr 15,000.00 15,000.00 18.01 15,018.01 ketapang
3 Premium Industri Ltr 12,000.00 12,000.00 18.01 12,018.01 ketapang
4 Pelumas SAE 10 Ltr 60,000.00 60,000.00 18.01 60,018.01 ketapang
5 Pelumas SAE 30 Ltr 55,000.00 55,000.00 18.01 55,018.01 ketapang
6 Pelumas SAE 40 Ltr 60,000.00 60,000.00 18.01 60,018.01 ketapang
7 Oli 2T Ltr 55,000.00 55,000.00 18.01 55,018.01 ketapang
8 Oli SAE 140 ( Oli Gardan ) Ltr 50,000.00 50,000.00 18.01 50,018.01 ketapang
9 Oli SAE 90 Ltr 45,000.00 45,000.00 18.01 45,018.01 ketapang
10 Oli SAE 20w-50 ( Bensin ) Ltr 55,000.00 55,000.00 18.01 55,018.01 ketapang
11 Minyak Gemuk Ltr 70,000.00 70,000.00 18.01 70,018.01 ketapang
12 Flux Oil Ltr 65,000.00 65,000.00 18.01 65,018.01 ketapang
F. BAHAN PENUTUP LANTAI
1 Paving 20x20 Keping 2,400.00 2,400.00 2,400.00 kendawangan
2 Paving 18x18 Keping 2,200.00 2,200.00 2,200.00 kendawangan
3 Bataco 8x15x30 Keping 2,000.00 2,000.00 2,000.00 kendawangan
4 Bataco 7x15x30 Keping 1,750.00 1,750.00 1,750.00 kendawangan
5 Bataco 6x15x30 Keping 1,500.00 1,500.00 1,500.00 kendawangan
Bata Merah bh 958.50 958.50 112.57 1,071.07 ketapang
Batu tempel hitam bh 395,000.00 395,000.00 112.57 395,112.57 ketapang
batu traso kg 2,880.00 2,880.00 112.57 2,992.57 ketapang
parquet kayu m2 185,000.00 185,000.00 112.57 185,112.57 ketapang
vynil bh 45,475.00 45,475.00 112.57 45,587.57 ketapang
oker kg 13,700.00 13,700.00 112.57 13,812.57 ketapang
6 Keramik Anti Gores 60x60 ( Motif ) M2 (Ktk) 320,000.00 320,000.00 120.07 320,120.07 ketapang
7 Keramik Anti Gores 60x60 ( Polos ) M2 (Ktk) 220,000.00 220,000.00 120.07 220,120.07 ketapang
8 Keramik 40x40 M2 (Ktk) 133,000.00 133,000.00 120.07 133,120.07 ketapang
9 Keramik 30x30 ( Polos ) M2 (Ktk) 99,900.00 99,900.00 120.07 100,020.07 ketapang
10 Keramik 30x30 ( Motif ) M2 (Ktk) 122,100.00 122,100.00 120.07 122,220.07 ketapang
11 Keramik 20x20 ( Polos ) M2 (Ktk) 87,500.00 87,500.00 30.02 87,530.02 ketapang
12 Keramik 20x20 ( Motif ) M2 (Ktk) 97,500.00 97,500.00 30.02 97,530.02 ketapang
HARGA PAJAK MINERAL JUMLAH ONGKOS ANGKUTAN KETERANGAN
JUMLAH TOTAL
NO. NAMA BARANG SAT DASAR BUKAN LOGAM HARGA /ESKALASI Kg / M¹
( Rp. ) ( Rp. ) ( Km ) ( Rp. ) ( Rp. ) LOKASI HARGA
1 2 3 4 5 = (15 % x 4) 6 = (4 + 5) 7 8 = (6 + 7) 9
13 Keramik 20x25 ( Polos ) M2 (Ktk) 90,000.00 90,000.00 30.02 90,030.02 ketapang
14 Keramik Dinding 20 x 25 cm M2 (Ktk) 110,000.00 110,000.00 30.02 110,030.02 ketapang
G. BAHAN PENGGANTUNG
1 Paku Alumunium Kg 65,000.00 65,000.00 17.29 65,017.29 ketapang
Paku Besi uk. 1/2" - 1 " Kg 22,900.00 22,900.00 17.29 22,917.29 ketapang
2 Paku Besi uk. 2" - 4 " Kg 16,000.00 16,000.00 17.29 16,017.29 ketapang
3 Paku Sirap Kg 18,000.00 18,000.00 18,000.00 kendawangan
4 Paku Payung ( Utk Atap Seng ) Kg 26,000.00 26,000.00 17.29 26,017.29 ketapang
5 Paku Tripleks Kg 22,000.00 22,000.00 17.29 22,017.29 ketapang
6 Paku S Pcs 1,000.00 1,000.00 17.29 1,017.29 ketapang
paku gypsum kg 55,600.00 55,600.00 162.10 55,762.10 ketapang
Paku campuran 5 - 7 cm kg 12,500.00 12,500.00 162.10 12,662.10 ketapang
paku belian kg 36,100.00 36,100.00 162.10 36,262.10 ketapang
7 Kait Angin Jendela Bh 10,000.00 10,000.00 162.10 10,162.10 ketapang
Handle pintu bh 148,500.00 148,500.00 162.10 148,662.10 ketapang
handle jendela bh 15,390.00 15,390.00 162.10 15,552.10 ketapang
8 Gagang Pintu Bh 80,000.00 80,000.00 162.10 80,162.10 ketapang
9 Kunci Tanam Biasa Bh 75,000.00 75,000.00 162.10 75,162.10 ketapang
10 Kunci Tanam Besar Bh 150,000.00 150,000.00 162.10 150,162.10 ketapang
Kunci Tanam Silinder Bh 83,880.00 83,880.00 162.10 84,042.10 ketapang
11 Engsel Jendela Psg 8,000.00 8,000.00 8.10 8,008.10 ketapang
12 Engsel Pintu Psg 10,000.00 10,000.00 8.10 10,008.10 ketapang
Slot Pintu bh 23,520.00 23,520.00 8.10 23,528.10 ketapang
Slot Jendela bh 8,760.00 8,760.00 8.10 8,768.10 ketapang
13 Grendel 10" Bh 40,000.00 40,000.00 40,000.00 kendawangan
14 Grendel 3" Bh 10,000.00 10,000.00 10,000.00 kendawangan
15 Grendel 2" Bh 7,000.00 7,000.00 7,000.00 kendawangan
H. SANITASI
1 Kloset duduk CW868NJ Bh 5,170,000.00 5,170,000.00 5,403.13 5,175,403.13 ketapang
2 Kloset Jongkok CE9/TV150NWV12 Bh 3,443,000.00 3,443,000.00 5,403.13 3,448,403.13 ketapang
Kloset Duduk Monoblok EX TOTO (colour) bh 1,201,750.00 1,201,750.00 5,403.13 1,207,153.13 ketapang
3 Kloset Jongkok warna Bh 280,000.00 280,000.00 5,403.13 285,403.13 ketapang
4 Kloset Jongkok putih Bh 230,000.00 230,000.00 5,403.13 235,403.13 ketapang
westapel spoelhoek (setara toto) bh 2,620,000.00 2,620,000.00 5,403.13 2,625,403.13 ketapang
Soap dsih Taman ex lokal bh 70,000.00 70,000.00 5,403.13 75,403.13 ketapang
5 Wastafel LW242J/LW242HF Bh 1,648,900.00 1,648,900.00 5,403.13 1,654,303.13 ketapang
6 wastafel lengkap Bh 550,000.00 550,000.00 5,403.13 555,403.13 ketapang
westapel lengkap setara toto bh 947,500.00 947,500.00 5,403.13 952,903.13 ketapang
bak cuci piring stainlees unit 1,700,000.00 1,700,000.00 5,403.13 1,705,403.13 ketapang
waterdrain bh 350,000.00 350,000.00 5,403.13 355,403.13 ketapang
sealtape bh 10,000.00 10,000.00 5,403.13 15,403.13 ketapang
7 Wall Shower Bh 170,000.00 170,000.00 5,403.13 175,403.13 ketapang
8 Kran Air RRC Uk. 3/4" Bh 17,500.00 17,500.00 100.06 17,600.06 ketapang
9 Kran Air Biasa Uk. 3/4" Bh 8,000.00 8,000.00 100.06 8,100.06 ketapang
10 Kran Air Kuningan Uk. 3/4" Bh 30,000.00 30,000.00 100.06 30,100.06 ketapang
Jet Spray untuk Kloset Duduk (setara Toto) bh 55,000.00 55,000.00 100.06 55,100.06 ketapang
11 Floordrain Bh 15,000.00 15,000.00 33.25 15,033.25 ketapang
12 ESL Bord Tebal 7,5 cm M2 260,000.00 260,000.00 360.21 260,360.21 ketapang
I BAHAN PLAFOND
12 Tripleks 2.5 mm Lbr 55,000.00 55,000.00 360.21 55,360.21 ketapang
13 Multiplek 5 mm Lbr 95,000.00 95,000.00 360.21 95,360.21 ketapang
14 Multiplek 9 mm Lbr 170,000.00 170,000.00 1,309.85 171,309.85 ketapang
15 Multiplek 12 mm Lbr 230,000.00 230,000.00 1,729.00 231,729.00 ketapang
16 Papan Gypsum ( 122 x 244 ) cm Lbr 70,000.00 70,000.00 1,729.00 71,729.00 ketapang
GRC Board (120 x 240 x 3,5) Lbr 72,000.00 72,000.00 1,729.00 73,729.00 ketapang
17 Akustik 60 x 120 Lbr 90,000.00 90,000.00 1,729.00 91,729.00 ketapang
Lis Gypsum/ kayu m' 10,590.00 10,590.00 1,729.00 12,319.00 ketapang
18 Casting Jaya ( Tepung Gypsum ) Kg 6,000.00 6,000.00 1,729.00 7,729.00 ketapang
J BAHAN KACA
19 Kaca 3 mm ( Polos ) M² 135,000.00 135,000.00 750.43 135,750.43 ketapang
20 Kaca 5 mm ( Polos ) M² 160,000.00 160,000.00 750.43 160,750.43 ketapang
Kaca Tebal 12 mm M² 210,000.00 210,000.00 750.43 210,750.43 ketapang
21 Kaca Raiben 3 mm M² 155,000.00 155,000.00 750.43 155,750.43 ketapang
22 Kaca Raiben 5 mm M² 185,000.00 185,000.00 750.43 185,750.43 ketapang
K BAHAN BESI DAN ALUMINIUM
23 Kaca Stopsol 8 mm Silver Green Ex. Asaimas M² 632,500.00 632,500.00 750.43 633,250.43 ketapang
24 Pintu Tempered Polos 12 mm - Uk. 87 x 213,5 cm Unit 4,840,000.00 4,840,000.00 750.43 4,840,750.43 ketapang
25 Baut Besi Uk. D = 1/2 - 10 cm Btg 3,000.00 3,000.00 4.63 3,004.63 ketapang
26 Baut Besi Uk. D = 1/2 - 20 cm Btg 7,500.00 7,500.00 4.63 7,504.63 ketapang
27 Baut Besi Uk. D = 1/2 - 30 cm Btg 15,000.00 15,000.00 4.63 15,004.63 ketapang
28 Baut Besi Uk. D = 5/8 - 10 cm Btg 8,000.00 8,000.00 8.21 8,008.21 ketapang
29 Baut Besi Uk. D = 5/8 - 20 cm Btg 15,000.00 15,000.00 8.21 15,008.21 ketapang
30 Baut Besi Uk. D = 5/8 - 30 cm Btg 24,000.00 24,000.00 8.21 24,008.21 ketapang
31 Baut Besi Uk. D = 3/4 - 10 cm Btg 11,000.00 11,000.00 11.59 11,011.59 ketapang
32 Baut Besi Uk. D = 3/4 - 20 cm Btg 18,000.00 18,000.00 11.59 18,011.59 ketapang
33 Baut Besi Uk. D = 3/4 - 30 cm Btg 26,000.00 26,000.00 11.59 26,011.59 ketapang
34 Beugel Plat L = 3 cm Bh 22,000.00 22,000.00 185.52 22,185.52 ketapang
35 Besi Tulangan Beton ulir Kg 18,000.00 18,000.00 216.13 18,216.13 ketapang
36 Besi Tulangan Beton polos Kg 13,500.00 13,500.00 185.52 13,685.52 ketapang
Wiremesh Kg 19,850.00 19,850.00 24.01 19,874.01 ketapang
37 Kawat Bendrat Kg 20,500.00 20,500.00 24.01 20,524.01 ketapang
38 Kawat Simpai Kg 17,500.00 17,500.00 24.01 17,524.01 ketapang
39 Kawat dia 4 mm Kg 16,000.00 16,000.00 25.61 16,025.61 ketapang
40 Baja Profil Kg 35,000.00 35,000.00 25.61 35,025.61 ketapang
41 Baja Struktur Kg 55,000.00 55,000.00 25.61 55,025.61 ketapang
42 Baja Ringan Untuk Kuda Kuda M' 20,000.00 20,000.00 25.61 20,025.61 ketapang
43 Baja Ringan Untuk Gording M' 10,000.00 10,000.00 25.61 10,025.61 ketapang
44 Profil Allum " T " M' 12,500.00 12,500.00 25.61 12,525.61 ketapang
45 Profil Kusen Aluminium YKK 3" M' 130,000.00 130,000.00 25.61 130,025.61 ketapang
46 Profil Pintu Aluminium M' 70,000.00 70,000.00 25.61 70,025.61 ketapang
Sunscreen Aluminium M2 385,500.00 385,500.00 25.61 385,525.61 ketapang
47 Profil Kaca M' 45,000.00 45,000.00 25.61 45,025.61 ketapang
Besi Penahan Talang M' 18,400.00 18,400.00 25.61 18,425.61 ketapang
48 Rangka Metal hollow 40.40.2 mm M' 26,000.00 26,000.00 25.61 26,025.61 ketapang
Rangka Metal hollow 40.40.2,1 mm M' 29,333.00 29,333.00 216.13 29,549.13 ketapang
Rangka Metal hollow 40.40.1,1 mm M' 14,117.00 14,117.00 216.13 14,333.13 ketapang
Braket siku 40 x 40 x 4 mm M' 5,500.00 5,500.00 216.13 5,716.13 ketapang
Bracket ACP M' 1,500.00 1,500.00 216.13 1,716.13 ketapang
Brazing M' 44,000.00 44,000.00 216.13 44,216.13 ketapang
49 Besi L ( untuk Jembatan) M' 60,000.00 60,000.00 5,763.33 65,763.33 ketapang
50 Kabel Seling Ø 1/2" (Blue Strand/Full Baja) M' 80,000.00 80,000.00 2,753.18 82,753.18 ketapang
51 Kabel Seling Ø 3/4" (Blue Strand/Full Baja) M' 140,000.00 140,000.00 140,000.00 ketapang
52 Kabel Selling Ø 1,3/4" (Blue Strand/Full Baja) M' 0.00 0.00 11,682.43 11,682.43 ketapang
53 Kabel Selling Ø 1" (Multi Strand Roof) M' 46,000.00 46,000.00 5,763.33 51,763.33 ketapang
54 Kabel Selling Biasa Ø 1/2" M' 10,000.00 10,000.00 2,753.18 12,753.18 ketapang
55 Kabel Selling Biasa Ø 3/4" M' 17,000.00 17,000.00 22.48 17,022.48 ketapang
56 Jarum Keras 1,5"x24" Bh 165,000.00 165,000.00 22.48 165,022.48 ketapang
57 Jarum Keras 5/8"x12" Bh 145,000.00 145,000.00 22.48 145,022.48 ketapang
58 Jarum Keras 1/2"x6" Bh 20,000.00 20,000.00 22.48 20,022.48 ketapang
HARGA PAJAK MINERAL JUMLAH ONGKOS ANGKUTAN KETERANGAN
JUMLAH TOTAL
NO. NAMA BARANG SAT DASAR BUKAN LOGAM HARGA /ESKALASI Kg / M¹
( Rp. ) ( Rp. ) ( Km ) ( Rp. ) ( Rp. ) LOKASI HARGA
1 2 3 4 5 = (15 % x 4) 6 = (4 + 5) 7 8 = (6 + 7) 9
59 Jarum Keras M - 16 Bh 165,000.00 165,000.00 22.48 165,022.48 ketapang
60 Klem Kabel Ukr. 1/2 Bh 9,000.00 9,000.00 22.48 9,022.48 ketapang
61 Klem Label Uk. 1/2" Bh 9,000.00 9,000.00 22.48 9,022.48 ketapang
62 Klem Label Uk. 3/4" Bh 11,235.00 11,235.00 22.48 11,257.48 ketapang
63 Klem Label Uk. 1" Bh 16,000.00 16,000.00 1,108.33 17,108.33 ketapang
64 Meteran Air Bersih Set 390,000.00 390,000.00 22.48 390,022.48 ketapang
65 Sealtape Bh 5,000.00 5,000.00 22.48 5,022.48 ketapang
66 Shower TX4235 Bh 710,000.00 710,000.00 1,108.33 711,108.33 ketapang
67 Mesin Jet Pump Kap. 250 watt Bh 4,752,000.00 4,752,000.00 4,752,000.00 ketapang
68 Septictank Biosel Kap. 6 m3 Unit 7,000,000.00 7,000,000.00 33,250.00 7,033,250.00 ketapang
69 Alumunium Komposit + Rangka Besi M2 1,145,000.00 1,145,000.00 33,250.00 1,178,250.00 ketapang
Alumunium Komposit 0,4 setara seven 1,2 x 2,4 lbr 220,000.00 220,000.00 220,000.00 ketapang
70 Curtain Wall Kaca green stopsol 8 mm ex. Asaimas M2 1,450,000.00 1,450,000.00 1,450,000.00 ketapang
71 Ramset Bh 11,000.00 11,000.00 11,000.00 ketapang
72 Skrup Fixer Bh 1,500.00 1,500.00 1,500.00 ketapang
73 Sandblast M2 85,000.00 85,000.00 85,000.00 ketapang
74 Sealant Kg 122,900.00 122,900.00 360.21 123,260.21 ketapang
75 Lem Kayu Kg 25,000.00 25,000.00 1,309.85 26,309.85 ketapang
76 Plywood 4 mm Lbr 60,300.00 60,300.00 1,729.00 62,029.00 ketapang
77 Plywood 9 mm Lbr 262,000.00 262,000.00 1,729.00 263,729.00 ketapang
78 Phenol film 12 mm Lbr 300,000.00 300,000.00 1,309.85 301,309.85 ketapang
79 HPL 1,22 m x 2,44 m x 0,7 mm Lbr 450,000.00 450,000.00 450,000.00 ketapang
80 List Metal stainless steel M' 100,000.00 100,000.00 100,000.00 ketapang
81 Door Stoper Bh 250,000.00 250,000.00 250,000.00 ketapang
Door Stoper/ ptk + ongkir Bh 60,400.00 60,400.00 60,400.00 ketapang
Door Closer Bh 196,800.00 196,800.00 196,800.00 ketapang
82 Realing stainless steel Bh 600,000.00 600,000.00 600,000.00 ketapang
83 Plafond Alumunium Strip Celing Rangka Metal Furing M2 1,160,000.00 1,160,000.00 1,160,000.00 ketapang
84 Dinabolt dia 12 mm (10 - 15) cm Bh 5,000.00 5,000.00 400.23 5,400.23 ketapang
85 Kuas Bh 20,000.00 20,000.00 150.09 20,150.09 ketapang
86 Amplas Bh 3,000.00 3,000.00 150.09 3,150.09 ketapang
87 Kawat Las Kg 35,000.00 35,000.00 150.09 35,150.09 ketapang
88 Talang Paralon Type U Btg 65,000.00 65,000.00 601.85 65,601.85 ketapang
89 Tutup Talang Bh 15,000.00 15,000.00 225.69 15,225.69 ketapang
90 Corong Talang Bh 15,000.00 15,000.00 225.69 15,225.69 ketapang
91 Kait Talang Bh 4,000.00 4,000.00 225.69 4,225.69 ketapang
I. PIPA PVC KLAS A (SNI. PRJ. S. 12.5 )
1 Pipa PVC Ø = 1/2" x 6 M' Btg 90,000.00 90,000.00 14.41 90,014.41 15,002.40
2 Pipa PVC Ø = 3/4" x 6 M' Btg 120,000.00 120,000.00 32.55 120,032.55 20,005.42
3 Pipa PVC Ø = 1" x 6 M' Btg 150,000.00 150,000.00 63.38 150,063.38 25,010.56
4 Pipa PVC Ø = 2" x 6 M' Btg 175,000.00 175,000.00 232.39 175,232.39 29,205.40
5 Pipa PVC Ø = 2½" x 6 M" Btg 225,000.00 225,000.00 432.25 225,432.25 37,572.04
6 Pipa PVC Ø = 3" x 6 M' Btg 350,000.00 350,000.00 540.31 350,540.31 58,423.39
7 Pipa PVC Ø = 4" x 6 M" Btg 550,000.00 550,000.00 960.56 550,960.56 91,826.76
8 Pipa PVC Ø = 6" x 6 M" Btg 1,300,000.00 1,300,000.00 2,161.25 1,302,161.25 217,026.88
9 Elbow PVC Ø 1/2" Bh 3,000.00 3,000.00 4.50 3,004.50 ketapang
10 Elbow PVC Ø 3/4" Bh 3,500.00 3,500.00 4.50 3,504.50 ketapang
11 Elbow PVC Ø 1" Bh 5,500.00 5,500.00 4.50 5,504.50 ketapang
12 Elbow PVC Ø 2" Bh 14,000.00 14,000.00 5.40 14,005.40 ketapang
13 Elbow PVC Ø 3" Bh 35,000.00 35,000.00 17.15 35,017.15 ketapang
14 Elbow PVC Ø 4" Bh 60,000.00 60,000.00 24.01 60,024.01 ketapang
15 All Socket Pipa PVC Ø 2" Bh 11,000.00 11,000.00 21.61 11,021.61 ketapang
16 All Socket Pipa PVC Ø 3" Bh 25,000.00 25,000.00 57.63 25,057.63 ketapang
17 All Socket Pipa PVC Ø 4" Bh 45,000.00 45,000.00 148.20 45,148.20 ketapang
18 All Socket Tee PVC Ø 2" Bh 18,000.00 18,000.00 441.07 18,441.07 ketapang
19 All Socket Tee PVC Ø 3" Bh 40,000.00 40,000.00 441.07 40,441.07 ketapang
20 All Socket Tee PVC Ø 4" Bh 80,000.00 80,000.00 441.07 80,441.07 ketapang
21 Pipa Galvanis Ø 1/2" - 6 M' Btg 95,000.00 95,000.00 126.57 95,126.57 ketapang
22 Pipa Galvanis Ø 3/4" - 6 M' Btg 110,000.00 110,000.00 163.92 110,163.92 18,360.65
23 Pipa Galvanis Ø 1" - 6 M' Btg 240,000.00 240,000.00 121.76 240,121.76 40,020.29
24 Pipa Galvanis Ø 1,25" - 6 M' Btg 380,000.00 380,000.00 327.46 380,327.46 ketapang
25 Pipa Galvanis Ø 1,5" - 6 M' Btg 350,000.00 350,000.00 375.87 350,375.87 58,395.98
26 Pipa Galvanis Medium Ø 2" - 6 M' Btg 470,000.00 470,000.00 533.64 470,533.64 ketapang
27 Pipa Galvanis Medium Ø 2,5" - 6 M' Btg 600,000.00 600,000.00 675.39 600,675.39 ketapang
28 Pipa Galvanis Medium Ø 3" - 6 M' Btg 900,000.00 900,000.00 882.14 900,882.14 ketapang
29 Pipa Galvanis Medium Ø 6" - 6 M' Btg 1,550,000.00 1,550,000.00 2,058.33 1,552,058.33 ketapang
30 Elbow Pipa Galvanis Ø 1/2" Bh 18,000.00 18,000.00 103.91 18,103.91 ketapang
31 Elbow Pipa Galvanis Ø 3/4" Bh 21,000.00 21,000.00 103.91 21,103.91 ketapang
32 Elbow Pipa Galvanis Ø 1" Bh 45,000.00 45,000.00 103.91 45,103.91 ketapang
33 Elbow Pipa Galvanis Ø 1,25" Bh 16,000.00 16,000.00 103.91 16,103.91 ketapang
34 Elbow Pipa Galvanis Ø 1,5" Bh 19,000.00 19,000.00 103.91 19,103.91 ketapang
35 Elbow Pipa Galvanis Medium Ø 2" Bh 43,000.00 43,000.00 81.44 43,081.44 ketapang
36 Elbow Pipa Galvanis Medium Ø 2,5" Bh 44,000.00 44,000.00 159.50 44,159.50 ketapang
37 Elbow Pipa Galvanis Medium Ø 3" Bh 60,000.00 60,000.00 159.50 60,159.50 ketapang
38 Elbow Pipa Galvanis Medium Ø 4" Bh 90,000.00 90,000.00 277.08 90,277.08 ketapang
39 Flange Pipa GIV Ø 2" Bh 147,000.00 147,000.00 51.89 147,051.89 ketapang
40 Flange Pipa GIV Ø 3" Bh 242,000.00 242,000.00 51.89 242,051.89 ketapang
41 Flange Pipa GIV Ø 4" Bh 333,000.00 333,000.00 51.89 333,051.89 ketapang
42 Flange Pipa GIV Ø 5" Bh 345,000.00 345,000.00 51.89 345,051.89 ketapang
43 Pakin Karet Ø 2" Bh 5,500.00 5,500.00 225.13 5,725.13 ketapang
44 Pakin Karet Ø 3" Bh 6,500.00 6,500.00 225.13 6,725.13 ketapang
45 Pakin Karet GIV Ø 4" Bh 7,500.00 7,500.00 225.13 7,725.13 ketapang
46 Reducer 3" - 2 " Bh 115,500.00 115,500.00 568.75 116,068.75 ketapang
47 Reducer 4" - 3 " Bh 133,000.00 133,000.00 568.75 133,568.75 ketapang
48 Filter Pipa GIV Ø 3" Bh 150,000.00 150,000.00 568.75 150,568.75 ketapang
49 Filter Pipa GIV Ø 4" Bh 200,000.00 200,000.00 568.75 200,568.75 ketapang
50 Pipa GIV Ø 2" - 6 Btg 741,500.00 741,500.00 882.14 742,382.14 ketapang
51 Pipa GIV Ø 4" - 6 Btg 2,200,000.00 2,200,000.00 1,271.32 2,201,271.32 ketapang
52 Pipa GIV Ø 5" - 6 Btg 2,264,000.00 2,264,000.00 1,729.00 2,265,729.00 ketapang
53 Pipa GIV Ø 6" - 6 Btg 3,000,000.00 3,000,000.00 103.91 3,000,103.91 ketapang
54 Pipa HDPE Ø 2" x 6 Btg 580,000.00 580,000.00 38.39 580,038.39 ketapang
55 Pipa HDPE Ø 2,5" x 6 Btg 660,000.00 660,000.00 59.13 660,059.13 ketapang
56 Pipa HDPE Ø 3" x 6 Btg 1,128,000.00 1,128,000.00 84.10 1,128,084.10 ketapang
57 Pipa HDPE Ø 4" x 6 Btg 1,600,000.00 1,600,000.00 112.27 1,600,112.27 ketapang
58 Pipa HDPE Ø 6" x 6 Btg 3,000,000.00 3,000,000.00 432.25 3,000,432.25 ketapang
J. PIPA PVC KLAS B ( STANDARD AW )
1 Pipa PVC Ø = 1/2" x 4 M' Btg 25,000.00 25,000.00 14.41 25,014.41 6,253.6
2 Pipa PVC Ø = 3/4" x 4 M' Btg 30,000.00 30,000.00 32.55 30,032.55 7,508.1
3 Pipa PVC Ø = 1" x 4 M' Btg 35,000.00 35,000.00 63.38 35,063.38 8,765.8
4 Pipa PVC Ø = 2" x 4 M' Btg 80,000.00 80,000.00 232.39 80,232.39 20,058.1
5 Pipa PVC Ø = 2½" x 4 M' Btg 112,500.00 112,500.00 432.25 112,932.25 28,233.0
6 Pipa PVC Ø = 3" x 4 M' Btg 150,000.00 150,000.00 540.31 150,540.31 37,635.0
7 Pipa PVC Ø = 4" x 4 M' Btg 240,000.00 240,000.00 960.56 240,960.56 60,240.1
8 Elbow PVC Ø 1/2" Bh 3,000.00 3,000.00 4.50 3,004.50 ketapang
9 Elbow PVC Ø 3/4" Bh 3,000.00 3,000.00 4.50 3,004.50 ketapang
10 Elbow PVC Ø 1" Bh 5,000.00 5,000.00 4.50 5,004.50 ketapang
11 Elbow PVC Ø 2" Bh 15,000.00 15,000.00 5.40 15,005.40 ketapang
12 Elbow PVC Ø 3" Bh 18,000.00 18,000.00 17.15 18,017.15 ketapang
HARGA PAJAK MINERAL JUMLAH ONGKOS ANGKUTAN KETERANGAN
JUMLAH TOTAL
NO. NAMA BARANG SAT DASAR BUKAN LOGAM HARGA /ESKALASI Kg / M¹
( Rp. ) ( Rp. ) ( Km ) ( Rp. ) ( Rp. ) LOKASI HARGA
1 2 3 4 5 = (15 % x 4) 6 = (4 + 5) 7 8 = (6 + 7) 9
13 Elbow PVC Ø 4" Bh 30,000.00 30,000.00 24.01 30,024.01 ketapang
14 All Socket Pipa PVC Ø 2" Bh 13,000.00 13,000.00 21.61 13,021.61 ketapang
15 All Socket Pipa PVC Ø 3" Bh 18,000.00 18,000.00 57.63 18,057.63 ketapang
16 All Socket Pipa PVC Ø 4" Bh 24,000.00 24,000.00 148.20 24,148.20 ketapang
17 All Socket Tee PVC Ø 2" Bh 17,000.00 17,000.00 441.07 17,441.07 ketapang
18 All Socket Tee PVC Ø 3" Bh 21,000.00 21,000.00 441.07 21,441.07 ketapang
19 All Socket Tee PVC Ø 4" Bh 38,000.00 38,000.00 441.07 38,441.07 ketapang
K. PIPA PVC KLAS C ( STANDARD C )
1 Pipa PVC Ø = 1/2" x 4 M' Btg 13,000.00 13,000.00 14.41 13,014.41 3,253.6
2 Pipa PVC Ø = 3/4" x 4 M' Btg 17,000.00 17,000.00 32.55 17,032.55 4,258.1
3 Pipa PVC Ø = 1" x 4 M' Btg 22,500.00 22,500.00 63.38 22,563.38 5,640.8
4 Pipa PVC Ø = 2" x 4 M' Btg 32,000.00 32,000.00 232.39 32,232.39 8,058.1
5 Pipa PVC Ø = 2½" x 4 M' Btg 45,000.00 45,000.00 432.25 45,432.25 11,358.0
6 Pipa PVC Ø = 3" x 4 M' Btg 60,000.00 60,000.00 540.31 60,540.31 15,135.0
7 Pipa PVC Ø = 4" x 4 M' Btg 80,000.00 80,000.00 960.56 80,960.56 20,240.1
8 Pipa PVC Ø = 8" x 4 M' Btg 230,000.00 230,000.00 3,087.50 233,087.50 58,271.8
9 Elbow PVC Ø 1/2" Bh 3,000.00 3,000.00 4.50 3,004.50 ketapang
10 Elbow PVC Ø 3/4" Bh 3,500.00 3,500.00 4.50 3,504.50 ketapang
11 Elbow PVC Ø 1" Bh 7,000.00 7,000.00 4.50 7,004.50 ketapang
12 Elbow PVC Ø 2" Bh 12,500.00 12,500.00 5.40 12,505.40 ketapang
13 Elbow PVC Ø 3" Bh 27,000.00 27,000.00 17.15 27,017.15 ketapang
14 Elbow PVC Ø 4" Bh 32,000.00 32,000.00 24.01 32,024.01 ketapang
15 All Socket Pipa PVC Ø 2" Bh 12,500.00 12,500.00 21.61 12,521.61 ketapang
16 All Socket Pipa PVC Ø 3" Bh 27,000.00 27,000.00 57.63 27,057.63 ketapang
17 All Socket Pipa PVC Ø 4" Bh 32,000.00 32,000.00 148.20 32,148.20 ketapang
18 All Socket Tee PVC Ø 2" Bh 5,500.00 5,500.00 441.07 5,941.07 ketapang
19 All Socket Tee PVC Ø 3" Bh 16,000.00 16,000.00 441.07 16,441.07 ketapang
20 All Socket Tee PVC Ø 4" Bh 28,000.00 28,000.00 441.07 28,441.07 ketapang
21 Alat Bantu (@ 3 set) Set 150,000.00 150,000.00 150,000.00 ketapang
L. TONG AIR FIBER
1 Tong Air Vol. 1 M³ Bh 2,100,000.00 2,100,000.00 21,612.50 2,121,612.50 ketapang
2 Tong Air Vol. 1,6 M³ Bh 2,900,000.00 2,900,000.00 21,612.50 2,921,612.50 ketapang
3 Tong Air Vol. 2 M³ Bh 3,600,000.00 3,600,000.00 21,612.50 3,621,612.50 ketapang
4 Bak Air Fiber Sudut ( Untuk WC) Bh 650,000.00 650,000.00 7,204.17 657,204.17 ketapang
M. INSTALASI LISTRIK
1 Kabel NY 4 x 2.5 mm Rol 1,100,000.00 1,100,000.00 108.06 1,100,108.06 ketapang
2 Kabel NY 3 x 2.5 mm Rol 850,000.00 850,000.00 108.06 850,108.06 ketapang
3 Kabel NY 2 x 2.5 mm Rol 675,000.00 675,000.00 108.06 675,108.06 ketapang
4 Kabel NY 1 x 2.5 mm Rol 580,000.00 580,000.00 108.06 580,108.06 ketapang
5 Kabel NY 3 x 1.5 mm Rol 600,000.00 600,000.00 108.06 600,108.06 ketapang
6 Kabel NY 2 x 1.5 mm Rol 500,000.00 500,000.00 108.06 500,108.06 ketapang
7 Kabel NY 1 x 1.5 mm Rol 400,000.00 400,000.00 108.06 400,108.06 ketapang
N SAKLAR
10 Saklar Tunggal Bh 20,000.00 20,000.00 6.77 20,006.77 ketapang
11 Saklar Ganda Bh 25,000.00 25,000.00 6.77 25,006.77 ketapang
12 Saklar Triple Bh 35,000.00 35,000.00 6.77 35,006.77 ketapang
O STOP KONTAK
1 Stop Kontak Outbow 3L Bh 17,500.00 17,500.00 13.54 17,513.54 ketapang
Stop Kontak inbow 12 A bh 31,130.00 31,130.00 13.54 31,143.54 ketapang
Box Panel PJU Uk. 40 x 60 x 30 Cm lengkap Time Swich bh 475,000.00 475,000.00 60.03 475,060.03 ketapang
Lampu LED SL 18 watt (setara Philips) bh 180,000.00 180,000.00 60.03 180,060.03 ketapang
2 Fitting lampu Bh 12,500.00 12,500.00 60.03 12,560.03 ketapang
3 Bola Lampu 9 - 11 watt Bh 40,000.00 40,000.00 60.03 40,060.03 ketapang
4 Bola Lampu 15 - 25 watt Bh 55,000.00 55,000.00 60.03 55,060.03 ketapang
5 Lampu TL bambu 20 Watt + Kapasitor Bh 100,000.00 100,000.00 60.03 100,060.03 ketapang
6 Lampu TL bambu 40 Watt + Kapasitor Bh 140,000.00 140,000.00 60.03 140,060.03 ketapang
7 Sekring 6 A Bh 20,000.00 20,000.00 60.03 20,060.03 ketapang
8 Down Light Ø 2,5 " Bh 45,000.00 45,000.00 60.03 45,060.03 ketapang
9 Down Light Ø 3,5 " Bh 55,000.00 55,000.00 60.03 55,060.03 ketapang
Downlight 6 " (setara panasonic) bh 81,600.00 81,600.00 60.03 81,660.03 ketapang
10 Down Light Ø 4 " Bh 68,000.00 68,000.00 60.03 68,060.03 ketapang
P MCB ( STUD )
1 MCB 2 A + BOX Bh 35,000.00 35,000.00 13.54 35,013.54 ketapang
2 MCB 4 A + BOX Bh 35,000.00 35,000.00 13.54 35,013.54 ketapang
3 MCB 6 A + BOX Bh 35,000.00 35,000.00 13.54 35,013.54 ketapang
4 MCB 10 A + BOX Bh 35,000.00 35,000.00 13.54 35,013.54 ketapang
5 MCB 16 A + BOX Bh 40,000.00 40,000.00 13.54 40,013.54 ketapang
Q PAKU SADEL DLL
1 Paku Sadel Beton Bh 12,000.00 12,000.00 2.77 12,002.77 ketapang
2 Paku Sadel Biasa Bh 5,000.00 5,000.00 2.77 5,002.77 ketapang
3 Isolasi Bungkus 10,000.00 10,000.00 2.77 10,002.77 kendawangan
4 T - Dus Bh 12,500.00 12,500.00 6.77 12,506.77 ketapang
5 Klem Sadel Beton Bh 12,000.00 12,000.00 6.77 12,006.77 ketapang

NO TENAGA KERJA SATUAN BIAYA UPAH / HARI BIAYA UPAH / JAM KETERANGAN

1 Pekerja Orang / Hari Rp. 75,600.00


2 Pekerja agak terlatih Orang / Hari Rp.
3 Pekerja Terlatih Orang / Hari Rp. 99,750.00
4 Tenaga Ahli Orang / Hari Rp.
5 Tukang Orang / Hari Rp. 99,750.00
6 Kepala Tukang Orang / Hari Rp. 99,750.00
7 Mandor Orang / Hari Rp. 99,750.00
8 Operator Terlatih Orang / Hari Rp.
9 Pembantu Operator Orang / Hari Rp.
10 Mekanik Terlatih Orang / Hari Rp.
11 Pembantu Mekanik Orang / Hari Rp.
12 Supir Personil Orang / Hari Rp.
13 Supir Truk Orang / Hari Rp.
14 Pembantu Supir Orang / Hari Rp.
15 Penjaga Malam Orang / Hari Rp.

Вам также может понравиться