S.No. : 01 SK1_CE_C_270519
Reinforced Cement Concrete
Delhi | Noida | Bhopal | Hyderabad | Jaipur | Lucknow | Indore | Pune | Bhubaneswar | Kolkata | Patna
Web: www.madeeasy.in | E-mail: info@madeeasy.in | Ph: 011-45124612
CLASS TEST
2019-2020
CIVIL ENGINEERING
Reinforced Cement Concrete
Date of Test : 27/05/2019
Answer Key
1. (a) 7. (a) 13. (b) 19. (a) 25. (c)
D E TA I L E D E X P L A N AT I O N S
4. (c)
frequency
1.65 σ 1.65 σ
5% 95% 5%
fm fck
fck = fm + 1.65σ
6. (b)
L D
emin = +
500 30 Max
20 mm
3500 350
emin = + = 18.67 mm
500 30 max
20 mm
emin = 20 mm
7. (a)
Leff = 1.2 L
Leff = 1.2 × 6 = 7.2 m
9. (c)
As per IS 456
w Lclear
w
www.madeeasy.in © Copyright :
CT-2019 | CE • Reinforced Cement Concrete 9
11. (b)
5 × 12
Vu at xx = − 5 × 3 = 15 kN
2
5×3×3
Mu xx = 30 × 3 − = 67.5 kNm
2
400 − 200
dxx = 200 + × 3 = 300 mm
6
M 67.5 200
Vu design = Vu − u tan β = 15 − × = 7.5 kN
d 0.3 6000
12. (a)
1.5(DL + LL)
Design moment = max 1.5(DL+ EQL)
1.2(DL + LL + EQL)
1.5(50 + 40) = 135 kNm
= max 1.5(50 + 10) = 90 kNm = 135 kNm
1.2(50 + 40 + 10) = 120 kNm
14. (d)
200 × 103
Initial stress in steel wires = = 1000 N/mm2
200
300
e = − 100 = 50 mm
2
stress in concrete at the level of prestress wire
P Pe
+
200 × 103 200 × 103 × 502
= e = +
A I 150 × 300 3003
150 ×
12
Fc = 5.926 N/mm2
Es 210
m = = =6
Ec 35
Loss of stress = m . Fc = 6 × 5.926 = 35.56 N/mm2
35.56
% loss = × 100 = 3.556%
1000
15. (a)
d 0.40
Leff = Lclear + = 4+ = 4.2 m
2 2
Leff 4200
final deflection as per IS : 456 = = = 16.8 mm
250 250
www.madeeasy.in © Copyright :
10 Civil Engineering
16. (d)
h 3h
tanθ = =
l/3 l
3 Ph
So upward force = P sin θ =
l
So balance load wx
3 Ph
= w
l
wl
⇒ h =
3P
17. (a)
Permissible bearing stress in footing as per LSM is 0.45 fck.
18. (b)
Case:1 xu < Df 0.36 fck Bxu = 0.87 fy Ast
n
0.36 × 25 × xu × 1000 = 0.87 × 415 × 8 × × 202
4
xu = 100.824 mm > Df
Case:2
xu > Df > 3/7 xu
y f = 0.15 xu + 0.65 Df = 0.15 xu + 65
0.36 fck xu bw + 0.45 fck(Bf – bw) yf = 0.87 fy Ast
n
0.36 × 25 × xu × 250 + 0.45 × 25(1000 – 250)[65 + 0.15 xu] = 0.87 × 415 × 8 × × 202
4
2250 xu + 1265.625 xu + 548437.5 = 90787.622
xu = 102.11 mm > Df
3
xu = 43.76 mm < DB
7
So, xu = 102.11 mm
20. (c)
As per IS 456 : 2000
Least lateral dimension
spacing = min 16φmain(min)
300 mm
400
Diameter = min 16 × 16 = 256
300 mm
So provide, S = 250 mm.
21. (a)
b 2
where, kB = 0.5 + >/ 1 = 0.5 + = 0.9 >/ 1
a 5
Tup = 0.9 × 0.25 × 25
Tup = 1.125 N/mm2
www.madeeasy.in © Copyright :
CT-2019 | CE • Reinforced Cement Concrete 11
22. (a)
m = 8, j = 6, r = 4
Ds = m – (2j – r) = 8 – (6 × 2 – 4) = 0
So truss is stable and determinate.
23. (d)
5000 fck
Long term, E =
1+ θ
θ(for 28 days loading) = 1.6
500 25
E = = 9615.4 N/mm2
1+ 1.6
25. (c)
Lclear + d
For simply supported beam, leff = min.
Lclear + w
Lclear + 450
6000 = L min.
clear + 200
⇒ Lclear = 5800 mm
w = 4 kN/m
⇒ wu = 1.5 w = 1.5 × 4 = 6 kN/m
w u Lclear 6 × 5.8
vu = = = 17.4 kN
2 2
Vu 17.4 × 103
w = = = 0.154 N/mm2
Bd 250 × 450
26. (b)
M30/Fe415
Case-I
Consider neutral axis within flange
0.36 Fck xu B = 0.87 fy Ast
n
0.36 × 30 × xu × 400 = 0.87 × 415 × 4 ×× 202
4
xu = 105.025 mm < 120 mm
So, our assumption was correct.
MR = 0.36 fck xuB (d – 0.42 xu)
MR = 0.36 × 30 × (05.025 × 400 × (500 – 0.42 × 105.25)
MR = 229.526 kNm
27. (c)
Effective depth, d = 400 – 35 = 365 mm
π
100 Ast 100 × 5 × × 252
Percentage tension steel, pt = = 4
bd 300 × 365
f x 20
= 2.24% > pt lim = 41.61 ck · u lim = 41.61 × (0.48) = 0.96%
fy d 415
∴ Doubly reinforced section is required.
www.madeeasy.in © Copyright :
12 Civil Engineering
5 × 1500 × 103 × (50 + 200) × 100002 1500 × 103 × 50 × 100002 5 × 8.75 × 100004
δ = − +
48 × 35000 × 1.43 × 10 10
8 × 35000 × 1.43 × 1010
384 × 35000 × 1.43 × 104
δ = 7.8047 – 1.873 + 2.2763 = 8.208 mm
δ = 8.208 mm
30. (d)
P = Cr[σcc Ac + σsc Asc]
leff 0.8 × 9000
= = 14.4 > 12 long column
B 500
leff 7200
Cr = 1.25 − = 1.25 − = 0.95
48B 48 × 500
2500 × 103 = 0.95[8 × (500 × 500 – Asc )+ 190 × Asc]
⇒ Asc = 3470.2 mm2