Вы находитесь на странице: 1из 35

Kathekhola Rural Municipality

Office Of The Rural Municipality Executive


Bihunkot, Baglung
Gandaki Province, Nepal

Measurement Book

cfof]hgfsf] gfd M k/f]ksf/ k|fylds ljBfno

7]ufgf M sf=uf=kf= & /]z


Fiscal Year : 2075 - 2076
Name of Project : F./Y.:-
Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft

2
Earthwork in excavation in

a
ordinary soft soil- For 1 m3 Unskill 0.70 700 490.00 Tools & Plant 3 % of labour cost 14.70 14.70 504.70 14.30 5.2-1.2.2(a)
b Hard soil- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 5.2-1.2.2(b)
c Soft Rock- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 5.2-1.2.2(c)
d Medium Rock- For 1 m3 Unskill 3.00 700 2100.00 Tools & Plant 3 % of labour cost 63.00 63.00 2163.00 61.30 5.2-1.2.2(d)

e Hard Rock- For 1 m3 (no


chino) Unskill 5.00 700 3500.00 Tools & Plant 3 % of labour cost 105.00 105.00 3605.00 102.16 5.2-1.2.2(e)
with chino Unskill 24.00 700 16800.00 Tools & Plant 4 % of labour cost 504.00 504.00 17304.00 490.37 5.2-1.2.2(e)
f. BMS- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 U/D B1)2-2

9
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.32 21988.0 19700.0 7036.16 6304.00 MT
M15(P.C.C. 1:2:4) Unskill 4.00 700 2800.00 Agg.40mm 0.52 2750.0 2750.0 1430.00 1430.00 cu.m U/D
and wall - For 1 m 3
Agg.20mm 0.22 2750.0 2750.0 605.00 605.00 cu.m D1 7-2d
For Foundation Agg.10mm 0.11 2750.0 2750.0 302.50 302.50 cu.m
Sand 0.445 5660.00 5660.00 2518.70 2518.70 cu.m
Total 3755.00 11892.36 11160.20 15647.36 443.42
Government of Nepal
Ministry of Local Development
Office of District Development Committee
District Technical Office
Gorkha
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM) Amount
1 Skill Labour 955.00 955.00 955.00 md
2 Unskilled Labour 700.00 700.00 700.00 md
3 Painter 955.00 955.00 955.00 md
4 Sand 2300.00 5660.00 5,660.00 m3 1600.00 0.14 0.75 15.00 3360.00 0.00 0.00
5 Aggregate 40mm 2750.00 2750.00 2,750.00 m3 1800.00 0.14 0.59 0.00 0.00 0.00 0.00
6 Aggregate 20mm 2750.00 2750.00 2,750.00 m3 1800.00 0.14 0.59 0.00 0.00 0.00 0.00
7 Aggregate 10mm 2750.00 2750.00 2,750.00 m3 1800.00 0.14 0.59 0.00 0.00 0.00 0.00
8 Stone 1350.00 1375.20 1,375.20 m3 1800.00 0.14 0.59 0.10 25.20 0.00 0.00
9 Mud for masonry 280.00 280.00 280.00 m3 1400.00 0.14 0.59 0.00 0.00 0.00
10 Sal wood 45000.00 45000.00 45,000.00 m3 600.00 0 0.59 3.00 0.00 0.00 0.00
11 Local Wood 45000.00 45000.00 45,000.00 m3 600.00 0 0.59 3.00 0.00 0.00
12 Sisau 70560.00 70560.00 70,560.00 m3 600.00 0 0.59 0.00 0.00
13 Cement(NS Mark OPC) 17600.00 2288.00 21988.00 19,700.00 mt 1000.00 0.14 0.59 15.00 2100.00 0.00 0.00
14 Brick(Chimney ) 12.00 1.56 18.61 17.05 Nos 2.50 0.14 0.59 14.00 4.90 0.10 0.15
15 Nail 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
16 Iron Holdfast 25.00 3.25 28.25 25.00 No. 2.10 0.14 0.59 0.00 0.00 0.00
17 Screw 1.30 0.17 1.47 1.30 No. 0.14 0.59 0.00 0.00 0.00
18 Hinge 3" 18.00 2.34 20.34 18.00 No. 0.20 0.14 0.59 0.00 0.00 0.00
19 Hinge 4" 30.00 3.90 33.90 30.00 No. 0.25 0.14 0.59 0.00 0.00 0.00
20 Tower bolt 4" 40.00 5.20 45.20 40.00 No. 0.05 0.14 0.59 0.00 0.00 0.00
21 Tower bolt 6" 45.00 5.85 50.85 45.00 No. 0.08 0.14 0.59 0.00 0.00 0.00
22 Tower bolt 10" 60.00 7.80 67.80 60.00 No. 0.10 0.14 0.59 0.00 0.00 0.00
23 Handle 6" 25.00 3.25 28.25 25.00 No. 0.15 0.14 0.59 0.00 0.00 0.00
24 Handle 4" 30.00 3.90 33.90 30.00 No. 0.10 0.14 0.59 0.00 0.00 0.00
25 Mortise lock 800.00 104.00 904.00 800.00 No. 0.25 0.14 0.59 0.00 0.00 0.00
26 L-drop 10"x12" 200.00 26.00 226.00 200.00 set 0.12 0.14 0.59 0.00 0.00 0.00
27 L-drop 8"x10" 150.00 19.50 169.50 150.00 set 0.10 0.14 0.59 0.00 0.00 0.00
28 Door spring Good 475.00 61.75 536.75 475.00 set 0.10 0.14 0.59 0.00 0.00 0.00
29 Door spring Heavy 790.00 102.70 892.70 790.00 set 0.12 0.14 0.59 0.00 0.00 0.00

______________ _______________ ______________


Prepared By Checked by Approved By
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM) Amount
30 Wooden listi 9.00 1.17 10.17 9.00 mt. 0.05 0.14 0.59 0.00 0.00 0.00
31 Reinforcement Bar(10-40mm) 79000.00 10270.00 90670.00 80,400.00 mt 1000.00 0.14 0.59 10.00 1400.00 0.00 0.00
32 GI Wire 12Swg (Heavy Coating) 105.00 13.65 118.65 105.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
33 GI Wire 10Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
34 GI Wire 8Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
35 3mm Glass 500.00 65.00 565.00 500.00 m2 8.40 0.14 0.59 0.00 0.00 0.00
36 4mm Glass 640.00 83.20 723.20 640.00 m2 11.20 0.14 0.59 0.00 0.00 0.00
37 5mm Glass 750.00 97.50 847.50 750.00 m2 14.00 0.14 0.59 0.00 0.00 0.00
38 Lime 18.00 2.34 21.74 19.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
39 Gum (Rathicol) 200.00 26.00 227.40 201.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
40 Primer (wood) 290.00 37.70 329.10 291.40 Ltr 1.00 0.14 0.59 10.00 1.40 0.00 0.00
41 Enamel (Tayari) 420.00 54.60 474.60 420.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
42 Alumunium Paint 500.00 65.00 565.00 500.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
43 Sand Paper 10.00 1.30 11.30 10.00 Sheet 0.14 0.59 0.00 0.00 0.00
44 Red Oxide No 1 350.00 45.50 395.50 350.00 Ltr 1.00 0.14 0.59 0.00 0.00 0.00
45 Binding wire 100.00 13.00 113.00 100.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
46 CGI Sheet 0.38 mm th Colour 8930.00 1160.90 10090.90 8,930.00 bun. 65.00 0.14 0.59 0.00 0.00 0.00
47 CGI Sheet 0.4 mm th Colour 9300.00 1209.00 10509.00 9,300.00 bun. 60.00 0.14 0.59 0.00 0.00 0.00
48 Plain sheet 28 gauge 340.00 44.20 384.20 340.00 rm 1.00 0.14 0.59 0.00 0.00 0.00
49 3mm plywood 193.68 25.18 218.86 193.68 m2 2.00 0.14 0.59 0.00 0.00 0.00
50 Snowcem Paint 77.00 10.01 88.41 78.40 kg 1.00 0.14 0.59 10.00 1.40 0.00 0.00
51 Chimney Brick 12.00 1.56 15.91 14.35 nos 2.80 0.14 0.59 6.00 2.35 0.00 0.00
52 Wall Tile (Indian) 8"x6" 645.83 83.96 729.79 645.83 m2 12.00 0.14 0.59 0.00 0.00 0.00
53 Tile floor (Indian) 8"x8" 839.59 109.15 948.74 839.59 m2 15.00 0.14 0.59 0.00 0.00 0.00
54 White Cement 26.00 3.38 29.38 26.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
55 2X 500 gauge polythene 83.00 10.79 93.79 83.00 m2 0.14 0.59 0.00 0.00 0.00
56 Railing with GI & Black Pipe 250.00 32.50 282.50 250.00 sqft 2.50 0.14 0.59 0.00 0.00 0.00
57 Nut Bolt 8 mm 25.00 3.25 28.25 25.00 No 0.14 0.59 5.00 0.00 0.00 0.00
58 Bitumin Washer 1.00 0.13 1.13 1.00 No 0.14 0.59 0.00 0.00 0.00
59 J-Hook 4" 22.00 2.86 24.86 22.00 No 0.14 0.59 0.00 0.00 0.00
60 J-Hook 6" 26.00 3.38 29.38 26.00 No 0.14 0.59 0.00 0.00 0.00
61 Iron Grill(Ready made) 120.00 15.60 135.60 120.00 kg 1.00 0.14 0.59 0.00 0.00 0.00
38 mm dia 16Gauge thick
62 350.00 45.50 395.50 350.00 Rm 0.14 0.59
stainless steel pipe 2.50 0.00 0.00 0.00

______________ _______________ ______________


Prepared By Checked by Approved By
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM) Amount
25 mm dia 16Gauge
63 200.00 26.00 226.00 200.00 Rm 0.14 0.59
thickstainless steel pipe 1.50 0.00 0.00 0.00
Gas welding for stainless steel
64 150.00 19.50 169.50 150.00 sq m 0.14
pipe 0.00 0.00 0.00
65 Black Iron Pipe 1.8 mm Thick 95.00 12.35 107.35 95.00 kg 1.00 0.14 0.00 0.00 0.00

______________ _______________ ______________


Prepared By Checked by Approved By
Salient Features of Project
Project Name :-Sabik gabisa ko dharmik mandir ko marmat sudhar
Location :- Resha 7

sfo{qmdsf] gfd
sfd ug]{ lgsfo pkef]Qmf ;ldlt
cfly{s aif{ 074/075
ljlgof]lht jh]6 #REF!
cg'dflgt nfut #REF!
sG6LGh]G;L 0.00
pkef]Qmf >dbfg #REF!
v'b e'QmfgL x'g;Sg] /sd #REF!
l;=g sfdsf] ljj/0f

gf]6
ufp+kflnsfsf] sfof{non] pkef]Qmf ;ldlt;+u ;Demf}tf
ubf{ lgDgfg';f/sf] zt{x?sf] clgjfo{ kfngf u/fpg] k|ltj4tf lnP/
dfq ;Demf}tf
!=pkef]Qmf u/fpgsf
;ldltn] gS;f tyfnflu
nfut cg'/f]w
Ol:6d]6 adf]lhd lgdf{0f ubf{ k'/fgf
vfg]kfgL, l;+rfO{, ljBfno ejg, lghL 3/, uf]7, cf+“ug cfbL k"jf{wf/ ;+/rgf Iflt
k'¥ofPsf] v08df ;f]xL pkef]Qmf ;ldltn] cfkm";+u ePsf] ;Demf}tf /sd leqsf]
ah]6af6 dd{t, lgdf{0f jf k'glg{df{0f ul/lbg' kg]{5 . ;f] ;DjGwdf s'g} ph'/L
kg{ cfPdf pQm Iflt ePsf] lgdf{0f ug{ nfUg] /sd ;DjlGwt pkef]Qmf ;ldltsf]
vftfaf6 s§f u/]/ dfq clGtd km/kmf/s ug]{ Joj:yf ldnfpg'x'g .
@= ;DjlGwt k|fljlws 6f]nLn] ;fO{6df u/]sf] ;e]{, sfof{nosf] :jLs[t nfut cg'dfg
Pj+ gS;fx? cg';f/ g} lgdf{0f sfo{ u/fpg] k|ltj4tf lng' x'g .
#= :jLs[t nfut cg'dfg / gS;f eGbf km/s sfo{ u/L sfof{non] d"Nof+sg gu/]sf]
v08df s'g} lsl;dsf] ph'/ nfUg]5}g eGg] k|ltj4tf lng'x'g .
$= ;Demf}tf adf]lhdsf] lgdf{0f ubf{ u/fpbf jftfj/0f ;+/If0f P]g @)%# /
jftfj/0f lgodfjnL @)%$adf]lhd jftfj/0fdf gsf/fTds k|efj gkg]{ul/ u/fpg] k|ltj4tf
lng'x'g .
B..Hard Soil
Norms No: 5.2-1.2.2(b) DoLIDAR
Unit :cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 0.000 870.00 -
Unskill Md 0.60 650.00 390.00
Tools andSub-Total
plants 390.00
@3% 11.70
Total 401.70
Item: Dry Stone Pitching/Soling & Levelling Works
Norms No: 49.17-6 DoLIDAR
Unit :m3
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md - 870.00 -
Unskill Md 1.00 650.00 650.00
Material Stone m3 1.10 1,602.00 1,762.20
Sub-Total
Tools and plants 2,412.20
@3% 72.37
Total 2,484.57
15 % Overhead
Unit Rate 2,484.57

Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:4:8
Norms No: 41(7-2)c
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.00 650.00 2,600.00
Material Cement ( OPC NS MT 0.17 - -
mark)
Agg 40 mm cu.m 0.65 - -
Agg 20 mm cu.m 0.24 - -
Coarse sand cu.m 0.47 - -
Total 3,470.00 cft
Unit Rate 3,470.00 98.26

Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:3:6
Norms No: 42(7-2)c
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.00 650.00 2,600.00
Material Cement ( OPC NS MT 0.22 - -
mark)
Agg 40 mm cu.m 0.65 - -
Agg 20 mm cu.m 0.24 - -
Coarse sand cu.m 0.47 - -
Sub-Total 3,470.00
15 % Overhead 520.50
Unit Rate 3,990.50
Item: plain cement concrete works in foundation including material collection &30m lead
B.M 15 Grade (1:2:4 mix by volume)
Norms No: 41.11.b DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.06 650.00 2,639.00
Cement ( OPC NS
Material mark) MT 0.32 20,804.00 6,657.28
Agg 40 mm cu.m 0.52 - -
Agg 20 mm cu.m 0.22 1,850.00 407.00
Agg 10 mm cu.m 0.11 - -
Coarse sand cu.m 0.440 2,300.00 1,012.00
Sub-Total 11,585.28
15 % Overhead 1,737.79
Unit Rate 13,323.07
Item: plain cement concrete works in superstructure including material collection &30m lead
A. 1:2:4 mix
Norms No: 44(7-4)a,
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.80 870.00 696.00
Unskill Md 7.00 650.00 4,550.00
Material Cement ( OPC NS MT 0.32 20,804.00 6,657.28
mark)
Agg 40 mm cu.m 0.52 - -
Agg 20 mm cu.m 0.22 1,850.00 407.00
Agg 10 mm cu.m 0.11 - -
Coarse sand cu.m 0.445 2,300.00 1,023.50
Sub-Total 13,333.78
15 % Overhead 2,000.07
Unit Rate 15,333.85

Item: plain cement concrete works in superstructure including material collection &30m lead
B. 1:1.5:3 mix
Norms No: 7(4)b,45
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.80 870.00 696.00
Unskill Md 7.00 650.00 4,550.00
Material Cement ( OPC NS MT 0.40 20,804.00 8,321.60
mark)
Agg 20 mm cu.m 0.57 1,850.00 1,054.50
Agg 10 mm cu.m 0.29 - -
Coarse sand cu.m 0.425 2,300.00 977.50
Sub-Total 15,599.60
15 % Overhead 2,339.94
Unit Rate 17,939.54
Item: Reinforcement for RCC works including procuring steel, bending, placing, bindibg and fixing in
position all complite RCC works
Norms No: 40-10
Unit : Kg.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.0070 870.00 6.09
Unskill Md 0.0070 650.00 4.55
Material M.S. Rod MT 0.00105 93,790.00 98.48
Binding wire kg 0.01000 113.00 1.13
-
-
Sub-Total 110.25
15 % Overhead 16.54
Unit Rate 126.79

A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:4
Norms No : 38.8-A. c DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.24 md 650.00 2,106.00

Material Cement ( OPC NS


mark) 0.116 MT 20,804.00 2,413.26
RubbleStone 1.10 M3 1,602.00 1,762.20
Sand 0.47 M3 2,300.00 1,081.00
Sub-Total 8,667.46
15 % Overhead 1,300.12
Unit Rate 9,967.58

B. Random rubble Masonary 1:6


Norms No : 6(1)a-3,32
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 5.00 md 650.00 3,250.00
Material Cement ( OPC NS 0.106 MT 20,804.00 2,205.22
mark)
Blockstone 1.00 M3 20,804.00 20,804.00
Bondstone 0.10 M3 1,602.00 160.20
Sand 0.47 M3 2,300.00 1,081.00
Sub-Total 28,805.42
15 % Overhead 4,320.81
Unit Rate 33,126.23

A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:6
Norms No : 38.8-A. d DoLIDAR
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.29 md 650.00 2,138.50
Cement ( OPC NS
Material mark) 0.092 MT 20,804.00 1,913.97
Rubble Stone 1.10 M3 1,602.00 1,762.20
Sand 0.50 M3 2,300.00 1,150.00
Sub-Total 8,269.67
15 % Overhead 1,240.45
Unit Rate 9,510.12
B)12.5 mm thick plastering with cement sand mortar on brick wall or concrete surfaces including full
compensation for all labour, materials , scafolding and otter incidental required to complete tte works as per the
specifications
d). In 1:6 mix ratio
Norms No : 37.7-9.4 d) DoLIDAR
Unit :100 Sq.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 15.00 md 870.00 13,050.00
Un-skill 13.70 md 650.00 8,905.00
Cement ( OPC NS
Material mark) 0.288 MT 20,804.00 5,991.55
Sand 1.58 M3 2,300.00 3,634.00
Sub-Total 31,580.55
15 % Overhead 4,737.08
Total 36,317.63
Unit Rate 363.18

C)pointing works with cement sand mortar on brick wall with all required operation including full compensation
for all labour, materials , scafolding and otter incidental required to complete tte works as per the specifications

c .In 1:3 mix ratio


Norms No : 37.7-9.3d) DoLIDAR
Unit :100 Sq.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 8.00 md 870.00 6,960.00
Un-skill 8.88 md 650.00 5,772.00
Cement ( OPC NS
Material
mark) 0.096 MT 20,804.00 1,997.18
Sand 0.29 M3 2,300.00 667.00
Sub-Total 15,396.18
15 % Overhead 2,309.43
Total 17,705.61
Unit Rate 177.06
Preparation of bedding for pipe with granular materials . It includes all labour,materials.
Norms No : 46 .15-4 DoLIDAR
Unit :1 Cub.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill md 870.00 -
Un-skill 1.00 md 650.00 650.00
Well grage granular
materials passing
Material 4.75mm sieve and
down 1.100 M3 1,400.00 1,540.00
Sub-Total 2,190.00
15 % Overhead 328.50
Unit Rate 2,518.50
Laying,fitting and fixing of hume pipe having a length of 1 m or more. Its includes all operations required to
complete the works upto atrench depth of 2.2 m below the ground level and jointing of pipes with 1:2
cement sand ratio

b.) For every subsequent pipe having length of minimum 1m, Dia 30 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.02 md 870.00 17.40
Un-skill 0.10 md 650.00 65.00
Material Cement 0.001 MT 20,804.00 20.80
Sand 0.002 m3 2,300.00 4.60
Jute, Bitumin LS 30.00 30.00
Sub-Total 82.40
15 % Overhead 12.36
Unit Rate 94.76

b.) For every subsequent pipe having length of minimum 1m Dia 60 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.050 md 870.00 43.50
Un-skill 0.200 md 650.00 130.00
Material Cement 0.003 MT 20,804.00 62.41
Sand 0.004 m3 2,300.00 9.20
Jute, Bitumin LS 40.00 40.00
Sub-Total 285.11
15 % Overhead 42.77
Unit Rate 327.88

Hence,
Total cost of 30cmdia.1m H.P. 94.76
Total cost of 60cmdia.1m H.P. 327.88
Total 45mm dia. H.P.1m(Average cost) 422.64 211.32

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(2X1X 1) (11 m2)
Unit :Per m3 44.2.a DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.09 md 650.00 58.50

Binding wire
Materials 0.95 kg 121.170 115.11
12swg(Heavy Coated)
Sub-Total 173.61
15 % Overhead -
Rate per Box
Size(2X1X1) 173.61
Rate per m3 86.81

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(3X1X 1) (16 m2)

Unit :Per m3 44.1.A.ii.b DoLIDAR


Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.13 md 650.00 84.50

Binding wire
Materials 1.3 121.17 157.52
12swg(Heavy Coated)
kg
Sub-Total 242.02
15 % Overhead -
Rate per Box
Size(3X1X1) 242.02
Rate per m3 80.67

Unit rate/m3 Gabion Box


Size(2x1x1) NRs. 86.81
Gabion Box
Size(3x1x1) NRs. 80.67

Average Unit Rate 167.48 86.81 m3


45) Packing and filling of Gabion crates with stone
Unit :1m3 45.17-6 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.3 md 870.00 261.00
Unskilled 0.75 md 650.00 487.50
Materials Stone 1.10 m3 1602.00 1762.20
Sub-Total 2,510.70
15 % Overhead -
Unit Rate 2,510.70 m3
Providing Mechine Made Heavy coated gabion Box Hexagonal Mesh size 10X12 cm,Mesh wire 10swg
(Heavy Coated),Selvedge wire 8swg (Heavy Coated),Binding wire 12swg(Heavy Coated) at site.

Size Sq.m/box Rate/Sq.


m Rate/Box Rate/Cu.m
Gabion Box 8
Size(1.5x1x1) 297.457 2379.65935 1586.44
Gabion Box 11
Size(2x1x1) 297.457 3272.0316 1,636.02
Gabion Box 16
Size(3x1x1) 297.457 4759.31869 1,586.44
1602.96667

Mechine Made Heavy coated gabion Box 1,602.97 m3


Packing and filling of Gabion crates with stone 2,510.70 m3
Sub Total Cost 4113.67
Assembling 86.81
Total Cost 4200.48
38.8 Dry Uncoursed Rubble Stone Masonry

Norms No : 38-8 DoLIDAR


Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.5 md 870.00 435.00
Unskilled 1.5 md 650.00 975.00
Materials Stone 1.10 m3 1602.00 1762.20
Sub-Total 3,172.20
15 % Overhead -
Unit Rate 3,172.20 m3

26.3-1 Riverbed Material


Unit :1m3 38-8 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 1 md 650.00 650.00
Materials River Bed Materials 1.00 m3 1400.00 1400.00
Sub-Total 2,050.00
15 % Overhead 307.50
Unit Rate 2,357.50 m3

1 .Transportation of BM Soil by truck or Tractor (15 KMpH)


DoLIDAR
Unit: 10 Cu. M. Norms S.N: 56.2
Spec.C No: G-13.2
Lead source Type Quantity Unit Rate Amount
First 1KM Labour Unskill 1.36 md 650.00 884.00
Material Disel 2.35 LTR 86.50 203.28
Truck/Tractor -
Equipment Working Hr. 0.39 Hr. 300 117.00
Idle HR. 2.21 Hr. 150 331.50
Actul Rate 1,535.78
Unit Rate 153.58

item : laying of locally available granular materials for gravelling in Roadway for gravelling including
j10m lead & 1.5m lift-per m3
particular unit Qantity Rate Amount Remarks
subgrade preparation 10 cm depth
labour unskill md 0.05 650.00 32.5

laying of sub base for gravelling 15cm 0


thick 0
labour unskill md 1.5 650.00 975 pouring &
Material kg km levelling
Transportation upto 4
km for 1m3=1800kg/m3

1800 3.5 0.047 296.1


Sub-total 1303.6
15%overhead 195.54
unit rate 1499.14
3.24
Kathekhola Rural Municipality
Office Of Rural Municipal Executive
Bihunkot, Baglung
Gandaki Province, Nepal

Measurement Book
cfof]hgfsf] gfd M k/f]ksf/ k|fylds ljBfno
7]ufgf M sf=uf=kf= & /]z
S.N Description of items No. Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork for
MS angle 52 0.30 0.3 0.3 1.40
total 1.40 m3 576.8 807.52
50*50 mm 10 gauge fencing
2 1 76.00 1.5 114.00 m2 565 64410.00
wire purchase
3 MS angle kg/m
40*40*5 52 1.6 3 249.60
total 249.60 kg 96.05 23,974.08

4 Transportation cost dis(km) wt(kg) wt(quintal) 27246


qnt/k
Ms Angle 15 499.20 4.992 74.88 14.7 1100.74 48960
m
Concreting work in M15 mix
5 (c/s/a 1/2/4)
Ms Angle 52 0.25 0.27 0.27 0.95 m3 15647 14864.992
Total Estimated Amount 105157.33
Amount without UC 90,000.00
UC Contribution 15157.33
14.41%
15 67.5

47

26.666667
Kathekhola Rural Municipality
Office Of Rural Municipal Executive
Bihunkot, Baglung
Gandaki Province, Nepal

Measurement Book
cfof]hgfsf] gfd M k/f]ksf/ k|fylds ljBfno
7]ufgf M sf=uf=kf= & /]z
S.N Description of items No. Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork for
MS angle 52 0.30 0.3 0.3 1.40
total 1.40 m3 576.8 807.52
50*50 mm 10 gauge fencing
2 1 76.00 1.5 114.00 m2 565 64410.00
wire purchase
3 MS angle kg/m
40*40*5 52 1.6 3 249.60
total 249.60 kg 96.05 23,974.08

4 Transportation cost dis(km) wt(kg) wt(quintal)


qnt/k
Ms Angle 15 499.20 4.992 74.88 14.7 1100.74
m
Concreting work in M15 mix
5 (c/s/a 1/2/4)
Ms Angle 52 0.25 0.25 0.25 0.81 m3 15647 12674.3616
Total Estimated Amount 102966.70
Amount without UC 90,000.00
UC Contribution 12966.70
12.59%
sfo{;DkGg k|ltj]bg
sfof{nosf] gfd M– ufp+kflnsfsf] sfo{fno d=n]=k=kmf=g+= M–
cfof]hgfsf] gfd M k/f]ksf/ k|fylds ljBfno
7]ufgf M sf=uf=kf= & /]z
nfut cfg"dfg /sdM– 102966.70 sfd z'?ePsf] ldltM– @)&%.)*.!)
sfo{ ;DkGg ePsf] /sd 105157.30 sfd ;DkGg ug'{+kg] ldltM– @)&%.!).#)
Oi6d]6 eGbf 36L jf a92190.6 sfd ;DkGg ePsf] ldltM– @)&%.!).)(
nfut sfof{ ;DkGg ePsf] km/s
qm= sfdsf] lhh/0f PsfO{ s}lkmot
kl/df0f :jLst b/ nfut ? kl/df0f :jLst b/ /sd kl/df0f :jLst b/ /sd
1 Earthwork for m3 1.4000 576.80 807.52 1.40000 576.80 807.52 0.000 0.00 0.00
50*50 mm 10 gauge fencing wire
2 m2 565.00 64410.00 114.00000 565.00 64410.00 0.000 0.00 0.00
purchase 114.0000
3 MS angle kg 249.6000 96.05 23974.08 249.60000 96.05 23974.08 0.000 0.00 0
4 Transportation cost qnt/km 74.8800 14.70 1100.74 74.88000 14.70 1100.74 0.000 0.00 0.00
Concreting work in M15 mix
5 m3 15647.36 12674.36 0.95000 15647.36 14864.99 0.140 0.00 2190.63
(c/s/a 1/2/4) 0.8100
s'n /sd 102,966.7 105,157.3 2,190.63

gf]6M–n=O= eGbf a9L eP-±_ jf sd eP-–_ lrGx n]Vg].


!= ljnsf] qmd ;+Vof M clGtd Kathekhola Rural Municipality &= ;Demf}tf ldlt M @)&%.)*.!)
cfof]hgfsf] gfd M k/f]ksf/ k|fyld Office Of Rural Municipal Executive *= sfd ;dfKt ug'{kg]{ ldlt M @)&%.!).#)
#= pkef]Qmf ;ldltsf] cWoIfsf] gfd M Bihunkot, Baglung (= sfd gfkL ePsf] ldlt M
$= ;Demf}tf g+= M Gandaki Province, Nepal e'QmfgL ef}r/ g+= M
%= cl3Nnf] e'QmfgL ljnsf] qmd ;+V e'QmfgL ldlt M
^= cl3Nnf] e'QmfgL ljnsf] ef}r/ g pkef]Qmf ;DaGwL lan gfkL lstfj g+= M
cfO6 cBfjlws sfd ePsf] cl3Nnf] ljnsf] r9]sf] xfn ePsf] sfd
n=O{=
d sfdsf] ljj/0f PsfO{ s}lkmot
kl/df0f kl/df0f b/ hDdf d"No kl/df0fhDdf d"Nokl/df0f hDdf d"No
g+=
1 Earthwork for m3 1.40 1.4000 576.80 807.52 1.40 807.52

2 50*50 mm 10 gauge fencing wire purchase m2 114.00 114.0000


565.00 64,410.00 114.00 64,410.00
3 MS angle kg 249.60 249.6000 96.05 23,974.08 249.60 23,974.08
4 Transportation cost qnt/km 74.88 74.8800 14.70 1,100.74 74.88 1,100.74

5 Concreting work in M15 mix (c/s/a 1/2/4) m3 0.81 0.9500


15647.36 14,864.99 0.95 14,864.99
hDdf /sd 105,157.3 - 105,157.3
! of] lan jdf]lhd e'QmfgL hDdf 105157.30 $ s§f ug'{ kg]{ ?=
@ hg;|dbfg 15157.33 s= k]ZsL
# afFsL lbg' kg]{ ?= 90000.00 v= dfn;fdfgsf] df]n
u= cGo
% v'b lbg'

k]z ug]{sf] ;xL M hfFr ug]{sf] ;xL M :jLs[t ug]{sf] ;xL M


bhf{ ;a–O{lGhlgo/ bhf{ M bhf{ M
hDdf cIf?kL r]s g+= =======================af6 k||fKt eof] egL ;xL ug]{ .
M @)&%.!).#)

t eof] egL ;xL ug]{ .

Вам также может понравиться