CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

ID Task Task Name May 13, '19 Jun 17, '19 Jul 22, '19 Aug 26, '19 Sep 30, '19 Nov 4, '19
Mode M T W T F S S M T W T F
0 CONSTRUCTION OF EGBEMA 8X
300KM NAG WELL
1 PRE-ACTIVITIES 7/4
2 PRE-ACTIVITIES 7/1
3 Community Assurance/ FTO
4 PROCUREMENT
5 PROCUREMENT 7/1
6 Welding Accessories
7 Tools and Materials
8 Line Pipe and Concreat
Coated Pipes
9 90◦,45◦ Induction Bend 5D
10 Weldneck Flange
11 Gaskets
12 Steel support/Plates
13 Tie-In Flanges
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

ID Task Task Name May 13, '19 Jun 17, '19 Jul 22, '19 Aug 26, '19 Sep 30, '19 Nov 4, '19
Mode M T W T F S S M T W T F
14 Studs & Bolts
15 Mechanical
16 Pig Launcher / Reciver
17 Chemical Injection Package

18 Vent Stack Material


19 Valves
20 Electrical/Instrumentation
21 Electrical cable
22 Electrical equipment
23 Earthing Materials
24 Bulk Materials
25 Isolating Joint (Monolithic)

26 Tubing/Field Instruments
27 Cable Tiles

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

ID Task Task Name May 13, '19 Jun 17, '19 Jul 22, '19 Aug 26, '19 Sep 30, '19 Nov 4, '19
Mode M T W T F S S M T W T F
28 Corrosion
29 CP System Electrical Cables

30 Blasting/Paint
31 Coating Materials
32 Sacrifical Anodes
33 Civil
34 Cements
35 Sand and Gravel
36 Rods
37 MOBILIZATION
38 MOBILIZATION 7/1
39 Mobilzation of Personnels
and Equipment
40 Safety Induction
41 Welders Qualification test

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

ID Task Task Name May 13, '19 Jun 17, '19 Jul 22, '19 Aug 26, '19 Sep 30, '19 Nov 4, '19
Mode M T W T F S S M T W T F
42 CIVIL WORKS
43 CIVIL WORKS 7/1
44 Pig Launcher Foundation
45 Pig Receiver Foundation
46 Chemical Injection Package
Foundation
47 Pipe Supports Foundation
48 Electrical Cable Inspection
Chamber
49 Vent Stack Foundation
50 Opened Drain Pit Foundation

51 PIPELINE
CONSTRUCTION/MECHANICAL
WORKS

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

ID Task Task Name May 13, '19 Jun 17, '19 Jul 22, '19 Aug 26, '19 Sep 30, '19 Nov 4, '19
Mode M T W T F S S M T W T F
52 PIPELINE 7/1
CONSTRUCTION/MECHANICAL
WORKS
53 Surveying/ Bush Clearing &
Excavation
54 Pipe Stringing
55 Pipeline Welding/ Tie-In
56 Fabrication of Hook up Arm,
Vent Stack and Support

57 Radiography and NDT


58 Insulators
59 Pipeline Lowering
60 CORROSION/ ELECTRICAL
INSTALLATIONS
61 CORROSION/ ELECTRICAL 7/1
INSTALLATIONS
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

ID Task Task Name May 13, '19 Jun 17, '19 Jul 22, '19 Aug 26, '19 Sep 30, '19 Nov 4, '19
Mode M T W T F S S M T W T F
62 Cp Installation,Electrical Cable
Laying, Test & Sign Post
Erection
63 Sacrifical Anodes Installation

64 Blasting & Painting


65 MECHANICAL WORKS
66 MECHANICAL WORKS 7/1
67 Installation of Chemical
Injection System
68 Installation of Pig
Launcher/Receiver
69 Installation of Vent stack
70 Valves Installation
71 Installation of Hook up Arm
and Support

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

ID Task Task Name May 13, '19 Jun 17, '19 Jul 22, '19 Aug 26, '19 Sep 30, '19 Nov 4, '19
Mode M T W T F S S M T W T F
72 INSTRUMENTATION WORKS
73 INSTRUMENTATION WORKS 7/1

74 Installation of Field
Instruments: Tubings, Guages
etc
75 PRE-COMMISSIONING/
COMMISSIONING
76 PRE-COMMISSIONING 7/1
77 Flushing, Hydrotest and
Pigging
78 Dry and Nitrogen Purging
79 Backfilling & Site Restoration
80 DEMOBILIZATION
81 DEMOBILIZATION 7/1

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

ID Task Task Name May 13, '19 Jun 17, '19 Jul 22, '19 Aug 26, '19 Sep 30, '19 Nov 4, '19
Mode M T W T F S S M T W T F
82 Demolization of Personnel &
Equipment

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

'19 Nov 4, '19 Dec 9, '19 Jan 13, '20 Feb 17, '20 Mar 23, '20 Apr 27, '20 Jun 1, '20 Jul 6, '20
F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

'19 Nov 4, '19 Dec 9, '19 Jan 13, '20 Feb 17, '20 Mar 23, '20 Apr 27, '20 Jun 1, '20 Jul 6, '20
F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

'19 Nov 4, '19 Dec 9, '19 Jan 13, '20 Feb 17, '20 Mar 23, '20 Apr 27, '20 Jun 1, '20 Jul 6, '20
F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

'19 Nov 4, '19 Dec 9, '19 Jan 13, '20 Feb 17, '20 Mar 23, '20 Apr 27, '20 Jun 1, '20 Jul 6, '20
F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

'19 Nov 4, '19 Dec 9, '19 Jan 13, '20 Feb 17, '20 Mar 23, '20 Apr 27, '20 Jun 1, '20 Jul 6, '20
F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

'19 Nov 4, '19 Dec 9, '19 Jan 13, '20 Feb 17, '20 Mar 23, '20 Apr 27, '20 Jun 1, '20 Jul 6, '20
F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

'19 Nov 4, '19 Dec 9, '19 Jan 13, '20 Feb 17, '20 Mar 23, '20 Apr 27, '20 Jun 1, '20 Jul 6, '20
F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15 KENOZIGA NIGERIA LIMITED


CONSTRUCTION OF EGBEMA WEST 8" X 300KM NAG WELL FLOWLINE IN OML 20

'19 Nov 4, '19 Dec 9, '19 Jan 13, '20 Feb 17, '20 Mar 23, '20 Apr 27, '20 Jun 1, '20 Jul 6, '20
F S S M T W T F S S M T W T F S S M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CONSTRUCTION OF EG
Summary Manual Summary Rollup Progress
Date: Sun 8/18/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16 KENOZIGA NIGERIA LIMITED