Вы находитесь на странице: 1из 3

FLOORS AND SCREEDS

Superflat floor construction -


how easy is it?
Superf lat floors are required where very fications pertaining to very flat, defined movement floors,
narrow aisle trucks are employed to including DIN I5-185121, which is widely specified by
place and pick goods stacked to heights materials handling equipment manufacturers throughout
mainland Europe. The term Superllat will therefore be
over 12-13m, where the path of the
used genetically for the purposes of this article.
truck is fixed and the truck is floor
supported, i.e. it runs on the floor. Methods of construction
Sup erfI at floors are not required where There are a number of methods used in the construction of
the materials handling system runs on a these floors. There arc three fundamentally different
crane rail - in fact floor tolerances to approaches to achieving these tolerances:

support these sorts of systems are quite • construction in narrow strips with the aim ofinstalling
and finishing the concrete floor itself directly to Ihc
often not very onerous at all.
required tolerances
• construction of a base concrete slab and subsequenlly
applying a finish to achieve the required tolerances
Neil Williamson. MonofloorTechnoiogvLtd • construction of the concrete slab to 'normal' toler
ances and using manual or laser-guided grinding to
achieve the desired flatness.
Where the Imcks lift to over 8m, but less Hum 13m, a
very flat floor is siill required, but these arc not The first of these melhods is the most cost-effective and
strictly dclined as 'Superfiai' in the UK. For instance. the one that is most widely used. However, the oiher Iwo
Concrete Society Technical Report 34 (TR 34)' "describes options should also be discussed briefly. In a number of
Figure 1: Completed floors where the lift height is in the range of 8-13m as countries a base slab is constructed and products such as
Superflat floor. Category 1. There are a number of oilier worldwide speci- Magnacite are applied to provide Ihc Supcrflai wearing
■ i
course. This product is extremely free-flowing and experi
enced installers can achieve DIN 15-185 lolerances.
However, (he product is unsuitable where die floor is likely
lo be Constantly damp and. of course, there are two sepa
rate operations involved in the process. Similarly, with
Other products such as pumpable polymer-modified
cementitious overlays, these are normally a minimum of
7mm thick, k is necessary lo install levelling points care
fully throughout the area lo be casl. and while application
of (he product is straightforward, considerable care and
skill is needed to achieve Supcrllat results (see Figure 1).
This method is particularly suited to renovation of existing
floors, where there is surface damage or major variations in
level exist, or headroom restrictions prevent the use of con
crete overlay. In ihc ease of renovation, only ihc aisles and
free movement areas can be 'up-graded'.
The practice of grinding of the aisles to convert large
area slabs from the widely used TR 34 'FM2\ or (prefer-
ablyj 'FM2 Special' to 'Category |' is now widely
acknowledged. The extent of grinding varies considerably,
depending on the overall standard of the original Moor.
However, if conversion of a 'normal' floor to Superllat is
required, or it is decided to cast the slab deliberately to a
lower standard and then use grinding to achieve the
Superfiat specification, more significant amounts of grind
ing will almost certainly be necessary. This may result in
'rutting' along Ihe wheel paths of the trucks or, alterna
tively, full uisle-widih grinding. The original finish will be
lost, the aggregate will be exposed, and ihe concrete will
normally require sealing. This method may be cost-effee-
live for upgrading existing floors, new (e.g. in speculative
units) or old, but it is the author's opinion that it is more
cost-effective, and certainly more aesthetically pleasing, to
plan and prepare to install new floors to the correct specifi
cation at the outset.
It is very likely that most .Superfiai floors will need
some grinding, even when great care is taken to achieve (he
tolerances directly through the easting process itself.
Opinions vary on the amounts to he expected, bill :\ figure
in the order of 3-5% of aisle length overall is often quoted.

1
©The Concrete Society Reprinted from CONCRETE September 2005
FLOORS AND SCREEDS

Anything less than this would be considered a success, par


ticularly as Superflat floors are not as common as large Wheel track
area pours, and installation crews have to ascend a learning positions
curve rapidly at the start of each project. However, many

LA
floors have been installed to Superflat specifications
throughout the world, without the need for any grinding.
Some basic procedures that will help to achieve such a suc

1
cessful installation are discussed in the following para
graphs.

Concrete consistency Joints located under centre of racks result in wheel tracks being symmetrically located
Much of the success of a Superflat floor installation is
determined in advance of the installation. The concrete
mix and its consistent delivery are critical. The mix
requirements for a Superflat installation may be different of course, be armoured, including those across the end of Figure 2; Effect of Joint
to normal. In order to achieve the desired tolerances, par the aisle strips. Transverse construction joints within location.

ticular operations of 'cutting' and filling' need to be under aisles should be avoided. Joints are normally levelled
taken. As a result, bleed rates, finishability, setting charac using a precise level fitted with a parallel plate.
teristics and workability may all need to be modified. But There are many other factors to take into account when
most important is the consistency of concrete within and planning and designing Superflat floors. These are too
between loads of concrete. Variations in setting between numerous to list in this article, but the other most impor
loads make the achievement of Superflat tolerances very tant preparation issues are to ensure that adequate
difficult, if not effectively impossible in extreme cases. resources, in terms of labour and specialist equipment are
available, and that the floor can be constructed within a "Much ofthe
Joint location weather-proofed environment.
The location of the joints is also important. Clearly these success ofa
need to be located under the racking system, but the pre Procedures Superflatfloor
ferred location for achievement of the tolerances (midway Once installation is under way, concrete quality control is installation is
between the back-to-back racking legs) is not necessarily critical. After conventional placement of the concrete, a
the preferred location for the slab designer. However, sequence of strike-off, rechecking of formwork, trans
determined in
locating the joints here is preferred because the 'strip' will verse sawing, longitudinal straight-edging, application of advance ofthe
then be symmetrical about the centre line of the aisle (see topping (where specified), repeated sawing, straight-edg installation. Vie
Figure 2). Therefore, any concave or convex shape that ing and, if necessary, rechecking of formwork, follows at
may result from the screeding operations will not show as intervals regulated by the workability and setting rate of
concrete mix and
a difference in elevation across the aisle. The DIN 15-185 the concrete. Finishing, initially by 'panning' using a its consistent
specification is particularly onerous in relation to the small, non-overlapping, ride-on trowel, takes place much delivery are
transverse tolerances. As can be seen from Figure 2, by later than usual, to minimise disturbance to the surface. In
locating the strip equally about the centre line of the fork- some cases, it may be necessary to restraighten the floor
critical. The mix
lift truck path, variations that may occur due to 'floating' after the first pass of the power-float, but if the mix design requirementsfor a
or 'sinking' of the straight edge, or plastic settlement of and working of the surface has been done correctly, it is Superflat
the concrete do not affect the transverse tolerances. If the possible to have just one very late pass of the float pans
joint was located close to one track of the fork-lift (for prior to commencing power-trowelling. Curing is done in
installation may
example at point A), there would be an 'automatic' slope the normal way, but care needs to be taken with the appli be different to
across the aisle. In addition, plastic settlement of lmm is cation of spray-applied membranes to ensure an even cov normal. In order
not uncommon, thus most of the TR 34 Superflat or DIN erage so as not to have an effect on the surface tolerances
15-185 tolerance is lost immediately. achieved. Prompt surveying of the floor, particularly dur
to achieve the
Similarly when pouring infill strips, there can easily be ing the early stages ofa project, with informed feedback to desired
lmm variation at the edge of the concrete already placed. the operatives from the supervisors is critical. tolerances,
This will then be reflected in the concrete placed against it.
If, for example, at the other side of the strip being placed Dry-shake toppings
particular
the concrete also has a 1 mm variation, the further the truck Sometimes, there may be a requirement to install coloured operations of
runs away from the joints the better. Sequencing of place Superflat floors. This can be achieved using dry-shake 'cutting and
ment should be arranged such that the number of infill toppings incorporated into the surface during the sawing
strips is limited. The most accurate pours are likely to be or straight-edging process. However, although the better
filling'need to be
those constructed with formwork either side. As far as products are helpful in providing 'fat' to aid the cutting undertaken. As a
possible, subsequent pours should be arranged such that and filling operation, which is an integral part of the result, bleed rates,
one edge of the pour comprises adjustable accurate form- straight-edging, there is an increased risk of delamination
work. with most of the products available in the UK due to the
finishability,
fineness of their gradation. If inadequate topping is setting
Formwork systems applied, grinding may expose the 'natural* concrete characteristics
There are a number of different systems used for the form below. In addition, the application of the topping needs to
work: metal, timber and a combination of the two.
and workability
be done very evenly, and most contractors consider it
Whatever type is selected, it should be adjustable to more difficult to achieve Superflat tolerances when a dry- may all need to be
0.5mm or better. Diamond or similar plate dowels are pre shake is specified. modified."
ferred to round dowels both from a shrinkage crack con It is not necessarily the case that dry-shake toppings
trol point of view but also to make the screeding process make the achievement of Superflat tolerances more diffi
easier (no projecting dowels) and to facilitate easy strip cult, but a common method of achieving Superflat floors
ping. There is no need to use armoured joints below the in Europe and the eastern Mediterranean countries is by
racking system, but some contractors use these as a matter the application of a 'fresh-on-fresh' topping. This method
of individual choice. All joints in trafficked areas should, comprises laying of the base concrete, readjusting the

©The Concrete Society Reprinteo from CONCRETE September 2005


AND SCREEDS

; ...the best trained teams can achieve Superjlat tolerances


without the need for grinding, t
fbrmwork, carrying oat an early initial power-floating Conducting remarks
Operation ;intl ilicn applying a 'slurry' of lopping iiuucrinl In tlie USA post-iensioning ofSuperfJfli floors is common,
up lo 10mm iliick. The aggregates used in tha Lopping have and the techniques vary slightly compared with European
a larger maximum size and different grading ui dry-shake practice. Common in all parts tif the world is the need to
loppings, bin [he blend wilh cemeni is similar. The select the right mix. employ tight concrete quality control
WHtBr/cement ratio of the lopping lends (0 Iw in liie order of and to carry out every Operation diligently. Levelling of the
0.35. 'I his results in a very narrow window in which to formwork is critical, but so is the skill and attention to
carry out Ihe sawing and straight-edging operations. detail of every operative involved. Hand edging is important
However, the best trained teams can achieve Supeiflai tol for example, even though the joint is located under the
erances without the need for grinding. Nat only is this sys racks. This is to ensure that the level of the edge, which
tem advantageous in the case of coloured floors, but it also becomes the support for the strike-off mi) .sawing beams for
results in a flbre-ftw surface where steel fibres are used for the adjacent pour, is tightly controlled. If any one operation
StructuraJ purposes in the base concrete. is not correctly done, or the job is under-resourced, achiev
ing Supertiat tolerances becomes almost impossible. ■
Superflal jointless floors
At least one eastern European contractor can install tloors
to the tightest DIN 15-185 tolerances using a combination
of the standard methods and "wet-screeding' controlled by
precise level. This is helpful in order to provide ■jointless'
slcel-fibre floors, when compared with the normal 'long-
strip' method, which normally results in unacceptable References:
aspect ratios for such Door designs. Another method of
1. THECONCRETE SOCIETY. Technical Report 34, Concrefo
achieving 'Supcrtlai jointless' floors is by placing an accu industrial ground floois - n guide to design and
rate large pour slab and bonding, typically. 70mm-thick constmction. Thini Edition, Camberiey, 3003.
'Superllal strips' to this using a special bonding agent and
2. DEUTSCHESINSTITUTFUHNOHMUNG. DIN 15-185:
employing particularly highly skilled labour. Being struc Warehouse systems with guidod industrial tracks:
turally bonded, the overall deptli of the slab is unaltered requirements on tltoground, tlto warehouse and other
requiramonts. Berlin, 19S1.
using this method.

Industrial Flooring Consultants & Project Managers


PROVIDE A FLOOR
CONSTRUCTION AND REPAIR MANAGEMENT
PACKAGE TAILORED TO YOUR SPECIFIC REQUIREMENTS

Our service is dedicated to maximising


warehouse efficiency 3
03

SUPERFLAT FLOOR DESIGN & PROJECT MANAGEMENT


ON-SITE TRAINING, QUALITY CONTROL & SUPERVISION
|o
SPECIFICATION FOR NEW CONSTRUCTION & REPAIRS
DEFECTS INVESTIGATION & EXPERT WITNESS REPORTS Eo

Specialists In line tolerance Hoar design,


3
o
advice and supervision to nil
international standards including:
TR34, DIN 15-185 &ASTM 1155

go

Tel: 01953 681846


Post Office Barn, The Street, Gasthorpe, Diss, Norfolk. IP22 2TL o
Offices in:
• United Kingdom • Eastern Europe • Asia •
3

e ©The Concrete Society Reprinted from CONCRETE September 2005

Вам также может понравиться