Вы находитесь на странице: 1из 19

Clause

C. Scope of
work

1.1

1.2

1.3

1.4

1.5

1.6
1.0 Basic Engineering Services CONSULTING ENGINEERS# scope for providing Basic
Engineering Services for the PROJECT will be as follows:

Review basic engineering data/information/drawings with respect to all major technological


and auxiliary facilities, provided by…..... to ascertain adequacy of the same for carrying out
procurement and engineering services based on the same.

Develop plant general layout drawing showing the relative dispositions of PROJECT facilities,
together with associated auxiliary facilities, ancillary units and construction facilities.

Prepare layout for the individual areas/shops and finalize the same in consultation with …..

Prepare single line diagram for electric power distribution system.

Develop basic schemes for raw material and product handling and storage, water system,
utilities, pollution control, ventilation & air-conditioning system, firefighting & fire detection
alarm system, communication system & automation configuration diagram, plant road and
drainage system and associated facilities for the PROJECT.

Prepare project implementation schedule showing all the major activities which will be the
basis for developing the detailed master project schedule for control and monitoring of the
PROJECT during design, engineering, procurement and manufacturing, construction, erection
and commissioning work.
Weightage Remarks

20%

20%

Balance Layout
Filterpress building
Fire fighting Pump house
15% HP/LP water tanks
Blunger
HC, Sprial classifier house

10%

Balance schemes
Pollution control
Detection alarm system, communication
15% system

20%
STATUS OF BASIC EN
Drawing/
Sl. Clause Discipline Drawing /Document No Document
No. Type

PROJECT

1 1.2 Project 28842-000-000-PRJ-0002 Layout

2 1.1 Project 28842-DOC-PRJ-03 List

3 1.1 Project 28842-DOC-PRJ-02 List

BASIC ENGINEERING DRAWINGS/DOCUMENTS

1 1.5 Process 28842-10A-000-PRM-0001 Flow Diagram

2 1.5 Process 28842-10A-000-PRM-0002 Flow Diagram

3 1.5 Process 28842-10A-000-PRM-0003 Flow Diagram

4 1.5 Process 28842-10A-000-PRM-0004 Flow Diagram

5 1.5 Process 28842-10A-000-PRM-0005 Flow Diagram

6 1.5 Process 28842-10A-000-PRM-0006 Flow Diagram

7 1.5 Process 28842-10A-000-PRM-0007 Flow Diagram

8 1.5 Process 28842-10A-000-PRM-0010 Symbols

Material
9 1.1 Process 28842-000-000-PRF-0003 Balance
Material
10 1.1 Process 28842-000-000-PRF-0004 Balance
Material
11 1.1 Water 28842-10A-ACA-WTS-001 Balance
Material
12 1.1 Water 28842-10A-ACA-WTS-002 Balance
Material
13 1.1 Water 28842-10A-ACA-WTS-006 Balance

14 1.5 Water 28842-10A-ACA-WTS-003 Flow Diagram

15 1.5 Water 28842-10A-ACA-WTS-005 Scheme


16 1.4 Electrical 28842-000-00-ELE-0002 Scheme

Instrument
17 1.5 28842-000-000-ELI-001 Scheme
ation

18 1.5 Process 28842-10A-000-UTL-0001 Scheme

19 1.5 Process 28842-10A-VBM-UTL-0002 Scheme

20 1.5 Process 28842-10A-VBN-UTL-0003 Scheme

PIPING AND INSTRUMENTATION DIAGRAM

1 1.5 Process 28842-10A-000-PRM-0011 P&I Diagram

2 1.5 Process 28842-10A-000-PRM-0012 P&I Diagram

3 1.5 Process 28842-10A-000-PRM-0013 P&I Diagram

4 1.5 Process 28842-10A-000-PRM-0014 P&I Diagram

5 1.5 Process 28842-10A-000-PRM-0015 P&I Diagram

6 1.5 Process 28842-10A-000-PRM-0016 P&I Diagram

7 1.5 Process 28842-10A-000-PRM-0017 P&I Diagram

8 1.5 Process 28842-10A-000-PRM-0018 P&I Diagram

9 1.5 Process 28842-10A-000-PRM-0019 P&I Diagram

10 1.5 Process 28842-10A-000-PRM-0020 P&I Diagram

11 1.5 Process 28842-10A-000-PRM-0021 P&I Diagram

12 1.5 Process 28842-10A-000-PRM-0022 P&I Diagram

13 1.5 Process 28842-10A-000-PRM-0023 P&I Diagram

14 1.5 Process 28842-10A-000-PRM-0024 P&I Diagram

15 1.5 Process 28842-10A-000-PRM-0025 P&I Diagram

16 1.5 Process 28842-10A-000-PRM-0026 P&I Diagram


17 1.5 Process 28842-10A-000-PRM-0027 P&I Diagram

18 1.5 Process 28842-10A-000-PRF-0001 P&I Diagram

19 1.5 Process 28842-10A-000-PRF-0002 P&I Diagram

20 1.5 Process 28842-10A-000-PRF-0003 P&I Diagram

21 1.5 Process 28842-10A-000-PRF-0004 P&I Diagram

22 1.5 Process 28842-10A-000-PRF-0005 P&I Diagram

23 1.5 Process 28842-10A-000-PRF-0006 P&I Diagram

24 1.5 Process 28842-10A-000-PRF-0007 P&I Diagram

25 1.5 Process 28842-10A-000-PRF-0008 P&I Diagram

26 1.5 Utility 28842-10A-VBM-UTL-0003 P&I Diagram

27 1.5 Utility 28842-10A-VBN-UTL-0004 P&I Diagram

28 1.5 Utility 28842-10A-000-UTL-0002 P&I Diagram

1 1.3 Civil List

GA Drawings

1 1.3 Process 28842-10A-VEV-PRJ-0002 GA Drawing

2 1.3 Water 28842-10A-ACA-WTS-0008 GA Drawing

3 1.3 Water 28842-10A-ACA-WTS-0007 GA Drawing


1. P&ID yet to finalize, please note that the serial nos. of Lines, Valves and Instruments Tag, Interlock details, Equipment tag ,equipme
After incoporation, EICL will approve the drawing.
2. Layout for the individual areas to be prepared(1.3 clause)
STATUS OF BASIC ENGINEERING DOCUMENTS
First Latest
Drawing Submission Revision
Date

Plant General Layout 11.09.2018 Rev.0

Load List 15.10.2018 Rev.1

Master Equipment list Rev.1

Flow Diagram for Refining Section 17.09.2018 Rev.B

Flow Diagram for Centrifuging and Delamination Section 17.09.2018 Rev.B

Flow Diagram for Bleaching Section 17.09.2018 Rev.A

Flow Diagram for Filter pressing and Kneading Section 17.09.2018 Rev.A

Flow Diagram for Spray Dryer Plant & Pre-Pulverizations 28.09.2018 Rev.B
Section
Flow Diagram for Calciner Plant 1 & Post-Pulverizations 28.09.2018 Rev.B
Section
Flow Diagram for Calciner Plant 2 & Post-Pulverizations 28.09.2018 Rev.B
Section

Legends and Symbol Rev.0

Material Balance for Wet Section for 60,000 TPA Clay 24.08.2018 Rev.B
Calcination Plant
Material Balance for Dry Section for 60,000 TPA Clay
Calcination Plant 24.08.2018 Rev.0

Water Balance Diagram 80% Recycling 10.10.2018 Rev.0

Water Balance Diagram 100% Recycling 23.10.2018 Rev.0

Water Balance Diagram for Sewerage Treatment Plant 24.10.2018 Rev.0

Flow Diagram for Effluent Treatment Plant 12.10.2018 Rev.0

Scheme for 7.5 KLD Sewerage Treatment Plant 24.10.2018 Rev.0


Single Line Diagram 22.10.2018 Rev.A

DCS Configuration Diagram 03.08.2018 Rev.0

Schematic diagram for compressed air system and Rev.0


distribution

Schematic diagram for LNG distribution system Rev.0

Schematic diagram for HSD distribution system Rev.0

P&I Diagram for Refining Section -Sheet 1 of 2 05.11.2018 Rev.A

P&I Diagram for Refining Section -Sheet 2 of 2 05.11.2018 Rev.B

P&I Diagram for Centrifuging and Delamination Section- 12.11.2018 Rev.A


Sheet 1 of 3

P&I Diagram for Centrifuging and Delamination Section- 13.11.2018 Rev.A


Sheet 2 of 3

P&I Diagram for Centrifuging and Delamination Section 14.11.2018 Rev.A


Sheet 3 of 3

P&I Diagram for Bleaching Section 19.11.2018 Rev.A

P&I Diagram for Filter pressing and Kneading Section- 27.11.2018 Rev.A
Sheet 1 of 3

P&I Diagram for Filter pressing and Kneading Section- 27.11.2018 Rev.A
Sheet 2 of 3

P&I Diagram for Filter pressing and Kneading Section- 27.11.2018 Rev.A
Sheet 3 of 3

P&I Diagram for HP Water and LP Water Storage and 21.11.2018 Rev.A
Distribution system

P&I Diagram for Tank Farm Area 13.12.2018 Rev.0

P&I Diagram for Spray Dryer Plant 30.11.2018 Rev.0

P&I Diagram for Caustic Lye Storage and Distribution 30.11.2018 Rev.A
System

P&I Diagram for Flosperse Storage and Distribution 30.11.2018 Rev.A


System

P&I Diagram for Sulphuric Acid Storage and Distribution 30.11.2018 Rev.A
System

P&I Diagram for Chemical Mixing and Dosing System 10.12.2018 Rev.0
P&I Diagram for Residue Filtration 13.12.2018 Rev.0

P&I Diagram for Spray Dried Clay Pulverizations Section 30.11.2018 Rev.A

P&I Diagram for Calciner Plant 1 Sheet 1 of 3 03.12.2018 Rev.A

P&I Diagram for Calciner Plant 1 Sheet 2 of 3 03.12.2018 Rev.A

P&I Diagram for Calciner Plant 1 Sheet 3 of 3 03.12.2018 Rev.A

P&I Diagram for Calcined Clay Pulverizations Section


(Sheet 1 of 2) 05.12.2018 Rev.A

P&I Diagram for Calcined Clay Pulverizations Section 05.12.2018 Rev.A


(Sheet 2 of 2)

P&I Diagram for Product Storage and Packing Sheet 1 of 2 07.12.2018 Rev.0

P&I Diagram for Product Storage and Packing Sheet 2 of 2 07.12.2018 Rev.0

P&I Diagram for LNG Distribution System 07.12.2018 Rev.A

P&I Diagram for HSD Distribution System 10.12.2018 Rev.A

P&I Diagram for Compressed Air System and Distribution 06.12.2018 Rev.A

Building List

GA Drawing for Tank farm 16.11.2018 Rev.0

GA Drawing for Effluent Treatment Plant 21.11.2018 Rev.0

GA Drawing for Sewage Treatment Plant 17.11.2018 Rev.0


nstruments Tag, Interlock details, Equipment tag ,equipment capacity etc. needs to be finalized & incorporated in the P&ID
Status EICL Remarks

Latest Plant general layout submitted by MND on 11th


Sep'18

List Prepared by EICL and vetted by MND

List Prepared by EICL and vetted by MND

Prepared by EICL and vetted by MND

Prepared by EICL and vetted by MND

Prepared by EICL and vetted by MND

Prepared by EICL and vetted by MND

Prepared by EICL and vetted by MND

Prepared by EICL and vetted by MND

Prepared by EICL and vetted by MND

Instrument and equipmet tagging philosophy not


mentioned.
Motor tagging philosophy to be revised w.r.t sections.
Missing symbols and legends w.r.t P&ID to be mentioned

Finalized

Finalized

Finalized

Finalized

prepared for statutory purpose

Prepared for statutory purpose

Prepared for Statutory Purpose


Prepared for Statutory Purpose

Finalized

Finalized

Finalized

Finalized

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate
EICL provided the comments
and MND to incorporate Refer attached sheet- P&ID
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments
and MND to incorporate Refer attached sheet- P&ID

EICL provided the comments Refer attached sheet- P&ID


and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments Refer attached sheet- P&ID
and MND to incorporate
EICL provided the comments
and MND to incorporate Refer attached sheet- P&ID

Prepared for statutory purpose

EICL provided the comments Comments incorporated and finalized.

Prepared for statutory purpose

Prepared for statutory purpose


zed & incorporated in the P&ID
Dastur Reply

Updated Plant General Layout sent to EICL on 28th


December 2018 along with Basic engineering documents
Load list submitted on 28th December 2018 . This was
prepared based on the offers received, Dastur estimate and
EICL inputs.
Master Equipment list submitted on 28th December 2018.
This was updated based on PFD, P&ID, offers received and
EICL inputs..

The mentioned drawing was prepared by Dastur based on


the input provided by EICL.

The mentioned drawing was prepared by Dastur based on


the input provided by EICL.

The mentioned drawing was prepared by Dastur based on


the input provided by EICL.
The mentioned drawing was prepared by Dastur based on
the input provided by EICL.
The mentioned drawing was prepared by Dastur based on
the input provided by EICL.
The mentioned drawing was prepared by Dastur based on
the input provided by EICL.
The mentioned drawing was prepared by Dastur based on
the input provided by EICL.

Will be updated and send along with revised P&ID.

Ok

OK

Ok

Ok
This drawing will be updated upon finalisation of STP
package.
This drawing will be updated upon finalisation of ETP
package.
This drawing will be updated upon finalisation of STP
package.
This drawing is also applicable for Basic Engineering.

Ok

Ok

OK

OK

The comments furnished by EICL shall be suitably


incorporated during revision of the P&ID with inputs from
Vendors.
This list is also applicable for Basic Enginnering and will be
updated after finalisation of various packages.

OK

This Drawing is also applicable for Basic Enginnering and


will be updated after finalisation of ETP package.

This Drawing is also applicable for Basic Enginnering and


will be updated after finalisation of STP package.
1. Serial nos. of Lines, Valves and Instruments Tag, Interlock
details etc shall be suitably incorporated during revision of
the P&ID with inputs from Vendors after finalisation of
various packages.
2. GA drawings of major buildings are attached herewith.
This will be updated upon finalisation of various packages.

Вам также может понравиться