CHECKLIST FOR FINISHING ACTIVITIES

ROOM DESCRIPTION: PROJECT DESCRIPTION: TA

STATUS OF COMPLETION
SR.NO. ACTIVITY DESCRIPTION
YES
ROOM AREA

1 MEP First Fix (Walls).

2 Fixing of Gypsum Board (WALLS) with Jointing Compound.

3 Installation of MEP services First & Second fix (Ceiling)

4 Installation of Ceiling Suspension for the Room.

5 Clearance for Closing of Ceiling from MEP.

6 Installation of Ceiling Board/tiles for the Room.

7 Installation of Access panel for Ceiling if applicable.

8 Fixing of Grills etc, on Ceiling

9 Application of Primer Coat.

10 Application of Stucco.

11 Application of First Coat Paint.

12 Fixing of wooden wall cladding (if applicable)

13 Installation of MEP Finishing (Switches, Sockets, Lights etc.,)

14 Installation of Glass Partition.

15 Self Levelling for floor areas (if applicable)

16 Installation of Flooring (Carpet/Marble/Tile)

17 Fixing of Main Door Frame


18 Installation of Door Shutter with Iron Mongeries

19 Installation of Skirting (if applicable)

20 Installation of Joinery

21 Installation of Accessories for Joinery.

22 Installation of Counter Top with Sanitary ware(if applicable)

23 Fixing of Glass Sticker (if applicable)

24 Installation of MEP Final Fix.

25 Application of Final Coat Paint.

26 Cleaning