RESUMEN DE INSUMOS PÁGINA :1

FECHA :

Rep. Ruta M-50, Chanco - Constitución, Tramo 3


Constructora FV S.A.

ITEM : T80001, REP. RUTA M-50, S: CHANCO-CONSTITUCIÓN, TRAMO 3


CÓDIGO NOMBRE UNI CANT P.U. TOTAL

1 : MANO DE OBRA
1CN14 CAMIÓN TOLVA 14 M3 HR 38,652.22210320 15,000 579,783,332
1MN85 MOTONIVELADORA HR 5,875.97600000 32,000 188,031,232
1PILOTERA PILOTERA HR 660.45787500 250,000 165,114,469
1RE220 EXCAVADORA 20 TONS HR 6,141.70256190 24,000 147,400,861
1CNGRUA CAMION GRUA HR 5,401.92997071 22,500 121,543,424
1CNA10 CAMIÓN ALGIBE 15 M3 HR 8,942.81574032 12,500 111,785,197
1POWER POWER CURBER HR 1,344.57000000 80,000 107,565,600
1CF950 CARGADOR TIPO CAT 950 HR 4,460.14499188 24,000 107,043,480
1PASF PLANTA DE ASFALTO HR 729.10486957 133,333 97,213,740
1CH120 PLANTA CHANCADO HR 1,188.93130616 75,000 89,169,848
1RA10 RODILLO LISO 10 TONS. HR 3,980.82066667 22,000 87,578,055
1RE300 EXCAVADORA 30 TONS HR 2,225.52100000 32,000 71,216,672
1RECH RETRO CHICA HR 5,065.43647008 14,000 70,916,111
1CN14A CAMIÓN TTE ASFALTO HR 4,050.58260870 15,000 60,758,739
1FI110 FINISHER HR 729.10486957 56,000 40,829,873
1RA100 RODILLO LISO ASFALTO HR 927.78089663 30,000 27,833,427
1HINCA HINCADORA HR 965.00000000 25,000 24,125,000
1DA3 CAMIÓN REGADOR ETNYRE AUTOMÁTICO HR 801.22882756 30,000 24,036,865
1GR18 GRÚA 18 TN AUTOPROPULSADA HR 918.63824191 25,000 22,965,956
1BH BOMBA HORMIGÓN HR 642.56000000 30,000 19,276,800
1RN27 RODILLO NEUMÁTICO HR 582.25289663 26,000 15,138,575
1EQMEN EQUIPO MENOR MES 36.17175789 400,000 14,468,703
1GN300 GENERADOR 300 KVA HR 1,486.16413270 9,000 13,375,477
1SENSOR SENSOR MOTONIVELADORA HR 1,255.76166667 10,000 12,557,617
1BAUTO BARREDORA HR 801.22882756 12,500 10,015,360
1GR300 GRUA 300 TON AUTOPROPULSADA HR 96.00000000 100,000 9,600,000
1GN300A GENERADOR 300 KVA PLANTA DE ASFALTO HR 947.83633043 9,000 8,530,527
1BOMBA BOMBA AGOTAMIENTO DÍA 282.87500000 26,000 7,354,750
1PINTA MAQUINA PINTADORA ML 72,263.18181818 60 4,335,791
1GR45 GRÚA 45 TN AUTOPROPULSADA HR 64.00000000 50,000 3,200,000
1SELLAD SELLADORA HR 270.32000000 10,000 2,703,200
1GN50 GENERADOR 50 KVA HR 742.78062635 3,000 2,228,342
1SOLDA SOLDADORA DIA 109.55600000 20,000 2,191,120
1GRAV1 GRAVILLADORA ETNYRE HR 25.91202707 46,667 1,209,237
1CNMIXER CAMIÓN MIXER HR 30.77045277 30,556 940,222
1PLH35 PLANTA DOSIFICADORA DE HORMIGON FV MES 0.06837878 5,000,000 341,894
1VOGEL CERCHA PAIMENTADORA MES 0.48437500 500,000 242,188
1CLARG ALISADORA PAVIMENTOS MES 0.48437500 400,000 193,750
1BETON BETONERA 0.5 M3 MES 0.36000000 400,000 144,000
1CO150 COMPRESOR 150 HR 3.90600000 6,000 23,436
SUB-TOTAL DE MANO DE OBRA 2,272,982,870
2 : MATERIALES
2ASF01 CEMENTO ASFÁLTICO LT 1,872,876.52173913 305 571,227,339
2BASE SUMINISTRO DE BASE CHANCADA M3S 49,444.33800000 5,900 291,721,594
2ASF02 CEMENTO ASFÁLTICO MODIFICADO CON POLÍMEROS KG 604,674.00000000 417 252,149,058
2PETRL PETROLEO CON I/E LT 592,586.49287043 390 231,108,732
2PETRO PETROLEO SIN I/E LT 682,003.56645330 320 218,241,141
2HOH30 SUMINISTRO HORMIGON H-30 M3 2,393.80000000 67,284 161,064,439
2SBASE SUMINISTRO DE SUBBASE M3S 52,870.24400000 3,000 158,610,732
2ACERO ACERO PARA ARMADURAS KG 345,722.78929412 436 150,735,136
2DEPUE4 SUM. INTEGRAL DE RÍO M3S 47,623.59573913 2,800 133,346,068
2ARRMOLD ARRIENDO DE MOLDAJES M2 11,734.45000000 10,680 125,323,926
2PETROA PETROLEO ASFALTO M3 364,552.43478261 320 116,656,779
2VIGAMET VIGA METÁLICA (PUESTA EN OBRA) TON 111.00000000 1,000,000 111,000,000
2HOH20C SUMINISTRO HORMIGON H-20 PARA CUNETAS M3H 1,487.16000000 66,750 99,267,930
2LOSETAF LOSETA FOSO L=0.5M UN 23,364.70588235 4,000 93,458,824
2ROCA SUMINISTRO ROCA PARA ENROCADOS M3 3,690.75000000 22,500 83,041,875
2HOH20 SUMINISTRO HORMIGON H-20 M3 1,304.35218824 57,405 74,876,337
2VIGPRET SUMINISTRO VIGA PRETENSADA L=40M UN 4.00000000 18,000,000 72,000,000
2PINT PINTURA GAL 2,167.89545455 33,000 71,540,550
2PLSIST SISTEMA DE APOYO C/N PLACA ELASTOMERICA Nº 24.00000000 2,547,873 61,148,952
2HOH35 HORMIGÓN H-35 M3 734.38400000 80,100 58,824,158
2MC30 IMPRIMANTE KG 182,482.30000000 234 42,700,858
2VALLA VALLA PEATONAL M 479.00000000 80,000 38,320,000
2HOH30P SUMINISTRO HORMIGÓN PARA PILOTES M3 462.00000000 80,100 37,006,200
2HOH30C SUMINISTRO HORMIGON H-30 PARA SOLERAS M3H 489.37200000 74,760 36,585,451
2LUMINARIA LUMINARIA 250 WATTS UN 45.00000000 750,000 33,750,000
2TBP100 TUBO BASE PLANA D= 1,00 M ML 470.40000000 68,544 32,243,098
2CSS1E EMULSIÓN RIEGO DE LIGA MOD. LT 95,976.00000000 331 31,768,056
2FILLER FILLER KG 633,468.00000000 50 31,673,400
2HOH25 SUMINISTRO HORMIGÓN H-25 M3 466.80400000 62,745 29,289,617
2DEFMA1 BARRERA METALICA LAT. NC ALTO W5 ML 440.00000000 65,000 28,600,000
2DEFMA BARRERA METALICA LAT. NC MEDIO ALTO W5 ML 1,016.00000000 28,000 28,448,000
2JUNTAEL2 JUNTA ELASTOMÉRICA ML 27.00000000 1,050,000 28,350,000
2SE001 SEÑAL M2 480.50000000 50,000 24,025,000
2AGUA SUMINISTRO DE AGUA M3 45,299.51759260 500 22,649,759
2MATVS MATERIALES VARIOS GL 22,346,350.00000000 1 22,346,350
2POSTE POSTE METALICO UN 33.00000000 650,000 21,450,000
2ARMERIA SUMINISTRO ARMERIA MARINA N° 1,848.00000000 11,300 20,882,400
2CSS1 EMULSIÓN CSS-1 LT 77,858.40000000 264 20,554,618
2TUBERIA TUBERIA PCV TIRA 6 M ML 287.00000000 70,000 20,090,000
2BARAND BARANDAS METALICAS ML 295.00000000 65,000 19,175,000
2DEPUE DERECHO A PUERTA M3 68,296.20000000 250 17,074,050
2PINPRG POSTE IMPREGNADO UNI 5,848.70000000 2,300 13,452,010
2JUNTAEL JUNTA ELASTOMÉRICA M 22.00000000 470,000 10,340,000
2SELLOJUNTURAMATERIAL SELLO JUNTURAS M 27,032.00000000 360 9,731,520
2JUNTAE3 JUNTA ELASTOMÉRICA ML 18.00000000 533,000 9,594,000
2EQUIPTOPO EQUIPOS DE TOPOGRAFIA MES 10.65000000 800,000 8,520,000
2CONDUCTOR CONDUCTOR M 5,100.00000000 1,500 7,650,000
2COLEX COLACIONES DE TERRENO HD 2,430.34956522 3,000 7,291,049
2AL001 ALAMBRE DE PÚAS 16 M 87,730.50000000 80 7,018,440
2MAO MADERA PARA MOLDAJES M2 6,473.45000000 1,000 6,473,450
2CEM CEMENTO ESPECIAL SC 2,183.65588235 2,933 6,404,663
2DOCA DOCA M2 1,248.00000000 5,000 6,240,000
2DELIN ELEM. DE CANALIZACION Y BALIZAMIENTO UN 206.00000000 30,000 6,180,000
2MORTER0 MORTERO NIVELACION GROUT M3 9.80800000 629,417 6,173,322
2TA001 TUBO ACERO CORRUGADO 1/2 CAÑA D=0.60 M ML 239.40000000 24,750 5,925,150
2MAOP MATERIALES PARA MOLDAJES M2 2,830.50000000 2,000 5,661,000
2SE010 POSTE OMEGA UN 282.00000000 20,000 5,640,000
2PLARBO PLANTA DE ARBOL UN 4,560.00000000 1,200 5,472,000
2ACEES ACERO ESTRUCTURAL KG 2,695.00000000 2,000 5,390,000
2SOLE_ SOLERAS UN 948.08000000 5,500 5,214,440
2HOH10 SUMINISTRO HORMIGÓN H-10 M3 90.68500000 55,002 4,987,856
2GANCHO GANCHO L=400 M N° 45.00000000 110,000 4,950,000
2TBP80 TUBO BASE PLANA D= 0,80 M ML 111.30000000 43,270 4,815,951
2TUBERIAAC TUBERIA DE ACERO GALVANIZADO TIRA 3 M M 70.00000000 65,000 4,550,000
2PAN PANTALLA ACUSTICA PAN 125.00000000 35,000 4,375,000
2PINTU PINTURA PARA ELEMENTOS METÁLICOS M2 1,266.00000000 3,450 4,367,700
2AL003 ALAMBRE NEGRO Nº 18 KG 8,735.28529412 500 4,367,643
2BOLON BOLON M3 360.00000000 10,000 3,600,000
2POLIETIL POLIETILENO M2 2,209.00000000 1,500 3,313,500
2ATRIPLEX SUMINISTRO ATRIPLEX N° 131.00000000 25,000 3,275,000
2ANCLAJES SUMINISTRO ELEMENTOS ANCLAJES GL 36.00000000 90,000 3,240,000
2SE011 POSTE UN 206.00000000 15,000 3,090,000
2ACACIA SUMINISTRO ACACIA BLANCA N° 61.00000000 50,000 3,050,000
2AMOB AMOBLADO OFICINAS GL 1.00000000 3,000,000 3,000,000
2TACHA TACHA REFLECTANTE CON PEGAMENTO UN 1,858.00000000 1,415 2,629,070
2LAVANDA SUMINISTRO LAVANDA N° 148.00000000 17,500 2,590,000
2ARHO SUMINISTRO DE ARIDOS HORMIGÓN M3 255.66908824 10,000 2,556,691
2TABLERO TABLERO TDA N° 1.00000000 2,500,000 2,500,000
2JUNTAEL1 CANTONERA ELÁSTICA ML 16.00000000 150,000 2,400,000
2BARAND1 PASAMANOS ML 60.00000000 40,000 2,400,000
2PROTECCION PROTECCION N° 45.00000000 50,000 2,250,000
2GEO03 GEOTEXTIL PARA DRENAJE M2 4,443.10000000 500 2,221,550
2HOH05 SUMINISTRO HORMIGÓN H-5 M3 42.55000000 50,730 2,158,562
2BANCAPREF BANCA PREFABRICADA UN 6.00000000 350,000 2,100,000
2LADFI LADRILLO UN 20,000.00000000 100 2,000,000
2MUCOC MUEBLES DE COCINA GL 1.00000000 2,000,000 2,000,000
2ARTBA ARTEFACTOS DE BAÑO GL 1.00000000 2,000,000 2,000,000
2RIPIO SUMINISTRO RIPIO M3 141.91600000 12,000 1,702,992
2MADERA MADERA IMPREGNADA 3,20 M PLG 168.00000000 10,000 1,680,000
2PLARBU PLANTA DE ARBUSTO UN 7,600.95000000 200 1,520,190
2MATAP MATERIALES AGUA POTABLE Y ALCANTARILLADO GL 1.00000000 1,500,000 1,500,000
2CRS2 EMULSIÓN CRS-2 LT 3,790.80000000 385 1,459,458
2MATTECH MATERIALES TECHUMBRE GL 1.00000000 1,200,000 1,200,000
2BARRA BARRA C/W CON CONECTOR N° 33.00000000 35,000 1,155,000
2MADDI MADERA DIMENSIONADA PLG 740.00000000 1,500 1,110,000
2BALDOSAS BALDOSAS M2 69.00000000 15,000 1,035,000
2ARENA ARENA PUESTA EN OBRA M3 82.22400000 12,000 986,688
2AS002 MEMBRANA DE CURADO KG 1,897.00000000 500 948,500
2CONDUCTOR1 CONDUCTOR AWG N° 12 M 75.00000000 12,000 900,000
2AC100 ANCLAJE BAJADA DE AGUA UN 152.00000000 5,900 896,800
2ESCOB ESCOBA GL 1.60245766 500,000 801,229
2BARBA SUMINISTRO DE BARBACANAS GL 3.00000000 250,000 750,000
2TERMINAL1 TERMINAL DE COMPRESION 33 MM N° 315.00000000 2,000 630,000
2PORTON PORTON 1 HOJA DE MADERA, TIPO 1 UN 2.00000000 300,000 600,000
2CUERPO CUERPO CAMARA TIPO A UN 9.00000000 59,814 538,326
2PORTOND PORTON 2 HOJAS DE MADERA UN 1.00000000 500,000 500,000
2SONDA SONDA DE INMERSIÓN UN 2.38470959 200,000 476,942
2SOLC SOLERA TIPO C ML 124.00000000 3,547 439,828
2TERMINAL TERMINAL DE COMPRESION 25 MM N° 210.00000000 2,000 420,000
2TEJA TEJAS UN 1,350.00000000 300 405,000
2REJS1 REJILLA PARA SUMIDERO UN 4.00000000 100,000 400,000
2BALDOSANEGRSUINISTRO BALDOSA NEGRA M2 23.00000000 17,000 391,000
2TBC120 TUBO CC D=1,2 M ML 5.25000000 63,438 333,050
2VENT VENTANAS UN 10.00000000 30,000 300,000
2MADBR MADERA EN BRUTO PLG 125.00000000 2,000 250,000
2PUERT PUERTAS UN 8.00000000 30,000 240,000
2MASTIC MASTIC ASFALTICO KG 145.82400000 1,300 189,571
2AS003 ADITIVOS PARA HORMIGON LT 142.60000000 1,000 142,600
2ATIEZAD BARRA DE ACERO UN 9.00000000 15,000 135,000
2TP001 TUBO PVC 200 MM, RANURADO ML 20.00000000 5,000 100,000
2MATEL MATERIALES ELECTRICOS GL 1.00000000 77,000 77,000
2GRAV1-2 GRAVILLA 1/2" M3S 5.76000000 7,055 40,637
2SOLD SOLDADURA KG 24.00000000 1,530 36,720
SUB-TOTAL DE MATERIALES 3,969,776,525

3 : MAQUINARIA Y EQUIPOS
3JOROC JORNAL OOCC HD 7,842.48863987 35,000 274,487,102
3MA1 MAESTRO PRIMERA HD 6,344.13043773 38,500 244,249,022
3MA1OC MAESTRO PRIMERA OOCC HD 5,125.18009384 45,500 233,195,694
3JOR JORNAL HD 8,037.24903558 26,250 210,977,787
3CAP CAPATAZ HD 2,408.27404689 49,000 118,005,428
3ENF ENFIERRADOR HD 2,052.75766650 49,000 100,585,126
3AYUD AYUDANTE HD 2,225.25724008 28,000 62,307,203
3SEÑ SEÑALERO HD 2,337.90912992 26,600 62,188,383
3MA1S MAESTRO PRIMERA SEG. VIAL HD 1,588.84318182 38,500 61,170,463
3MELEC MAESTRO ELECTRICO HD 1,001.84000000 40,000 40,073,600
3CCH CARD CHECKER HD 1,199.79795445 28,000 33,594,343
3BIOLOGO ARQUEOLOGO HD 180.00000000 99,000 17,820,000
3JORELEC JORNAL ELECTRICO HD 401.25000000 25,000 10,031,250
3MAPAIS MAESTRO PAISAJISMO HD 181.30000000 35,000 6,345,500
3CAPOC CAPATAZ OOCC HD 80.50320000 63,000 5,071,702
3MA1P MAESTRO PINTOR HD 94.95000000 49,000 4,652,550
3TOPO TOPOGRAFO HD 53.25000000 70,000 3,727,500
3ALARI ALARIFE HD 106.50000000 24,500 2,609,250
3SOLD SOLDADOR CALIFICADO HD 24.00000000 70,000 1,680,000
SUB-TOTAL DE MAQUINARIA Y EQUIPOS 41,285.48062668 1,492,771,903

TOTAL COSTO DIRECTO $/GL 7,735,531,298


GASTOS GENERALES (%) $/GL 44.50 3,442,311,428
TOTAL NETO $/GL 11,177,842,726