AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Valorizado Metrado Valorizado Valorizado Valorizado
Und. Metrado P. Unit. Presup. Metrado Metrado % Metrado %
S/. S/. S/. S/.
1 ESTRUCTURAS
1.1 OBRAS PROVISIONALES
1.1.1 CASETA Y ALMACÉN DE GUARDIANÍA m2 18.00 44.37 798.66 - 18.00 799 18.00 799 1.00 0.00 - 0.00%
1.1.2 CERCO C/ PANELES DE TRIPLAY m2 60.90 29.53 1,798.38 - 60.90 1,798 60.90 1,798 1.00 0.00 - 0.00%
1.2 OBRAS PRELIMINARES
1.2.1 LIMPIEZA DEL TERRENO MANUAL m2 104.65 3.79 396.62 - 104.65 397 104.65 397 1.00 0.00 - 0.00%
1.2.2 TRAZO, NIVELES Y REPLANTEO m2 104.65 3.75 392.44 - 104.65 392 104.65 392 1.00 0.00 - 0.00%
1.3 MOVIMIENTO DE TIERRAS
1.3.1 EXCAVACIÓN SIMPLE EN TERRENO NATURAL m3 104.21 59.50 6,200.50 - 104.21 6,201 104.21 6,201 1.00 0.00 - 0.00%
1.3.2 EXCAVACIÓN SIMPLE EN MATERIAL DE PRÉSTAMO m3 3.67 37.19 136.49 - 3.67 136 3.67 136 1.00 0.00 - 0.00%
1.3.3 CORTE DE TERRENO NATURAL h = 0.50 m m3 6.00 18.60 111.60 - 6.00 112 6.00 112 1.00 0.00 - 0.00%
1.3.4 RELLENO CON MATERIAL DE PRÉSTAMO m3 57.44 47.51 2,728.97 - 57.44 2,729 57.44 2,729 1.00 0.00 - 0.00%
1.3.5 NIVELACION INTERIOR Y APISONADO m2 79.90 3.43 274.06 - 79.90 274 79.90 274 1.00 0.00 - 0.00%
1.3.6 ELIMINACION DE MATERIAL EXCEDENTE m3 135.47 27.28 3,695.62 - 135.47 3,696 135.47 3,696 1.00 0.00 - 0.00%
1.4 CONCRETO SIMPLE
1.4.1 CONCRETO SOLADO (C:H 1:12; e=0.05 m) m2 64.20 27.54 1,768.07 - 64.20 1,768 64.20 1,768 1.00 0.00 - 0.00%
1.4.2 CONCRETO CICLOPEO CIMIENTO CORRIDO MEZCLA 1:12 + 30% P.G. m3 5.92 186.32 1,103.01 - 5.92 1,103 5.92 1,103 1.00 0.00 - 0.00%
1.4.3 CONCRETO FALSOPISO (f'c= 140 kg/cm2; e=0.10 m) m2 73.27 26.06 1,909.42 - 0.00 - 0.00 - 0.00 73.27 1,909 100.00%
1.4.4 CONCRETO GRADAS f'c=140 kg/cm2 m3 0.36 298.22 107.36 - 0.00 - 0.00 - 0.00 0.36 107 100.00%
1.4.5 ENCOFRADO GRADAS m 1.43 25.04 35.81 - 0.00 - 0.00 - 0.00 1.43 36 100.00%
1.5 CONCRETO ARMADO
1.5.1 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 26.57 314.68 8,361.05 - 26.57 8,361 26.57 8,361 1.00 0.00 - 0.00%
1.5.2 ACERO ZAPATAS fy= 4200 kg/cm2 kg 1,340.65 4.39 5,885.45 - 1,340.65 5,885 1,340.65 5,885 1.00 0.00 - 0.00%
1.5.3 CONCRETO VIGAS DE CIMENTACION f'c=210 kg/cm2 m3 8.39 335.81 2,817.45 - 8.39 2,817 8.39 2,817 1.00 0.00 - 0.00%
1.5.4 ENCOFRADO EN VIGA DE CIMENTACION m2 47.05 82.65 3,888.68 - 47.05 3,889 47.05 3,889 1.00 0.00 - 0.00%
1.5.5 ACERO VIGAS CIMENTACIÓN fy= 4200 kg/cm2 kg 834.03 4.35 3,628.03 - 834.03 3,628 834.03 3,628 1.00 0.00 - 0.00%
1.5.6 CONCRETO SOBRECIMIENTO f'c=210 kg/cm2 m3 8.01 305.02 2,443.21 - 0.00 - 0.00 - 0.00 8.01 2,443 100.00%
1.5.7 ACERO SOBRECIMIENTO FY= 4200 kg/cm2 kg 297.58 4.35 1,294.47 - 89.27 388 89.27 388 0.30 208.31 906 70.00%
1.5.8 ENCOFRADO DE SOBRECIMIENTO h=0.60 m m2 78.99 51.43 4,062.46 - 0.00 - 0.00 - 0.00 78.99 4,062 100.00%
1.5.9 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 16.39 348.10 5,705.36 - 0.00 - 0.00 - 0.00 16.39 5,705 100.00%
1.5.10 LADRILLO LOSA ALIGERADA (0.30*0.30*0.15) mll 1.56 1,916.24 2,989.33 - 0.00 - 0.00 - 0.00 1.56 2,989 100.00%
1.5.11 ENCOFRADO LOSA ALIGERADA m2 187.32 56.88 10,654.76 - 0.00 - 0.00 - 0.00 187.32 10,655 100.00%
1.5.12 ACERO LOSA ALIGERADA fy= 4200 kg/cm2 kg 1,152.39 4.35 5,012.90 - 0.00 - 0.00 - 0.00 1,152.39 5,013 100.00%
1.5.13 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 16.23 455.44 7,391.79 - 0.00 - 0.00 - 0.00 16.23 7,392 100.00%
1.5.14 ACERO COLUMNAS fy= 4200 kg/cm2 kg 2,773.30 4.32 11,980.66 - 554.66 2,396 554.66 2,396 0.20 2,218.64 9,585 80.00%
1.5.15 ENCOFRADO CARAVISTA COLUMNAS m2 186.81 79.70 14,888.76 - 0.00 - 0.00 - 0.00 186.81 14,889 100.00%
1.5.16 CONCRETO COLUMNETAS f'c=210 kg/cm2 m3 9.24 444.93 4,111.15 - 0.00 - 0.00 - 0.00 9.24 4,111 100.00%
1.5.17 ENCOFRADO COLUMNETAS m2 126.28 60.56 7,647.52 - 0.00 - 0.00 - 0.00 126.28 7,648 100.00%
1.5.18 ACERO COLUMNETAS fy= 4200 kg/cm2 kg 1,151.54 4.51 5,193.45 - 230.31 1,039 230.31 1,039 0.20 921.23 4,155 80.00%
1.5.19 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.91 373.32 6,312.84 - 0.00 - 0.00 - 0.00 16.91 6,313 100.00%
1.5.20 ENCOFRADO DE VIGAS m2 100.50 70.68 7,103.34 - 0.00 - 0.00 - 0.00 100.50 7,103 100.00%
1.5.21 ACERO VIGAS fy= 4200 kg/cm2 kg 2,256.76 4.35 9,816.91 - 0.00 - 0.00 - 0.00 2,256.76 9,817 100.00%
1.5.22 CONCRETO VIGAS DE BORDE f'c=210 kg/cm2 m3 2.32 330.08 765.79 - 0.00 - 0.00 - 0.00 2.32 766 100.00%
1.5.23 ENCOFRADO DE VIGA DE BORDE Y FRISO h= 0.20 m2 45.09 40.13 1,809.46 - 0.00 - 0.00 - 0.00 45.09 1,809 100.00%
1.5.24 ACERO VIGAS DE BORDE fy= 4200 kg/cm2 kg 336.19 4.32 1,452.34 - 0.00 - 0.00 - 0.00 336.19 1,452 100.00%
1.5.25 CONCRETO VIGAS COLLARÍN f'c=210 kg/cm2 m3 3.98 356.42 1,418.55 - 0.00 - 0.00 - 0.00 3.98 1,419 100.00%
1.5.26 ENCOFRADO DE VIGA COLLARÍN m2 44.66 40.29 1,799.35 - 0.00 - 0.00 - 0.00 44.66 1,799 100.00%
1.5.27 ACERO VIGA COLLARÍN fy= 4200 kg/cm2 kg 557.50 4.32 2,408.40 - 0.00 - 0.00 - 0.00 557.50 2,408 100.00%
1.5.28 CONCRETO ESCALERAS f´c=210 kg/cm2 m3 4.03 442.60 1,783.68 - 0.00 - 0.00 - 0.00 4.03 1,784 100.00%
1.5.29 ENCOFRADO NORMAL EN ESCALERA m2 29.59 89.88 2,659.55 - 0.00 - 0.00 - 0.00 29.59 2,660 100.00%
1.5.30 ACERO ESCALERA fy= 4200 kg/cm2 kg 381.22 4.32 1,646.87 - 0.00 - 0.00 - 0.00 381.22 1,647 100.00%
1.5.31 JUNTA DE DILATACION e=1/4" m 331.15 35.30 11,689.60 - 0.00 - 0.00 - 0.00 331.15 11,690 100.00%
1.5.32 CONCRETO PREMEZCLADO CISTERNA f'c=280 kg/cm2 (aditivo plastificante) m3 1.34 277.20 371.45 - 1.34 371 1.34 371 1.00 0.00 - 0.00%
1.5.33 ENCOFRADO METALICO CISTERNA m2 8.70 36.12 314.24 - 8.70 314 8.70 314 1.00 0.00 - 0.00%
1.5.34 ACERO CISTERNA fy= 4200 kg/cm2 kg 93.51 4.32 403.96 - 93.51 404 93.51 404 1.00 0.00 - 0.00%
1.5.35 CONCRETO PREMEZCLADO PISCINA f'c=280 kg/cm2 (aditivo plastificante) m3 6.30 277.20 1,746.36 - 6.30 1,746 6.30 1,746 1.00 0.00 - 0.00%
1.5.36 ENCOFRADO METALICO PISCINA m2 45.24 29.96 1,355.39 - 45.24 1,355 45.24 1,355 1.00 0.00 - 0.00%
1.5.37 ACERO PISCINA fy= 4200 kg/cm2 kg 361.28 4.32 1,560.73 - 361.28 1,561 361.28 1,561 1.00 0.00 - 0.00%
2 ARQUITECTURA
MUROS Y TABIQUES DE ALBAÑILERÍA
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO SOGA; C:A 1:4 (J= 1.5 cm) m2 309.30 55.60 17,197.08 - 0.00 - 0.00 - 0.00 309.30 17,197 100.00%
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO CABEZA; C:A 1:4 (J= 1.5 cm) m2 25.84 91.36 2,360.74 - 0.00 - 0.00 - 0.00 25.84 2,361 100.00%
REVOQUES Y REVESTIMIENTOS
TARRAJEO RAYADO PRIMARIO (C:A 1:4; e= 2 cm) m2 26.51 21.20 562.01 - 0.00 - 0.00 - 0.00 26.51 562 100.00%
TARRAJEO EN INTERIORES (C:A 1:5; e= 2cm) m2 293.28 22.53 6,607.60 - 0.00 - 0.00 - 0.00 293.28 6,608 100.00%
TARRAJEO EN COLUMNAS (C:A 1:5; e= 2 cm) m2 178.20 32.14 5,727.35 - 0.00 - 0.00 - 0.00 178.20 5,727 100.00%
TARRAJEO EN VIGAS (C:A 1:5; e= 2 cm) m2 136.57 36.15 4,937.01 - 0.00 - 0.00 - 0.00 136.57 4,937 100.00%
TARRAJEO CON INPERMEABILIZANTE (C:A 1:3; e= 2 cm) m2 36.76 25.55 939.22 - 0.00 - 0.00 - 0.00 36.76 939 100.00%
VESTIDURA DE DERRAMES (C:A 1:5; e= 2 cm) m 192.83 13.43 2,589.71 - 0.00 - 0.00 - 0.00 192.83 2,590 100.00%
TARRAJEO DE DUCTOS (C:A 1:5; e= 2 cm) m2 14.64 36.13 528.94 - 0.00 - 0.00 - 0.00 14.64 529 100.00%
BRUÑAS 5 mm*5 mm m 514.31 8.97 4,613.36 - 0.00 - 0.00 - 0.00 514.31 4,613 100.00%
TARRAJEO EN FONDO DE ESCALERAS (C:A 1:5; e= 2 cm) m2 15.80 34.87 550.95 - 0.00 - 0.00 - 0.00 15.80 551 100.00%
PREPARACIÓN DE GRADAS DE CONCRETO (C:A 1:4; e= 2 cm) m 17.00 24.70 419.90 - 0.00 - 0.00 - 0.00 17.00 420 100.00%
PREPARACIÓN DE DESCANSOS (C:A 1;4; e= 2 cm) m2 3.10 20.60 63.86 - 0.00 - 0.00 - 0.00 3.10 64 100.00%
GRADAS - VINILO 1.5 mm m 20.10 45.95 923.60 - 0.00 - 0.00 - 0.00 20.10 924 100.00%
ENCHAPE GRESITE NIEBLA AZUL 0.33*0.33 m2 36.76 90.25 3,317.59 - 0.00 - 0.00 - 0.00 36.76 3,318 100.00%
ENCHAPE TABLAS MACHIHEMBRADAS m2 8.40 45.32 380.69 - 0.00 - 0.00 - 0.00 8.40 381 100.00%
CIELO RASOS
CIELORRASO CON MEZCLA C:A 1:5; e= 1.5 cm m2 187.32 19.21 3,598.42 - 0.00 - 0.00 - 0.00 187.32 3,598 100.00%
PISOS Y PAVIMENTOS
CONTRAPISO C:4 1:3 e= 2'' m2 81.10 31.29 2,537.62 - 0.00 - 0.00 - 0.00 81.10 2,538 100.00%
PISO DE PORCELANATO NAVIA ACERO 0.30*0.90; ALTO TRÁNSITO e= 12 mm m2 24.98 84.97 2,122.55 - 0.00 - 0.00 - 0.00 24.98 2,123 100.00%
PISO DE PORCELANATO TEXAS 0.15*0.90; ALTO TRÁNSITO e= 12 mm m2 11.74 155.42 1,824.63 - 0.00 - 0.00 - 0.00 11.74 1,825 100.00%
PISO DE PORCELANATO MADERA 0.23*1.20; MEDIO TRÁNSITO e= 8 mm m2 35.98 93.93 3,379.60 - 0.00 - 0.00 - 0.00 35.98 3,380 100.00%
PISO DE TABLAS MACHIHEMBRADAS CHANUL m2 8.40 89.56 752.30 - 0.00 - 0.00 - 0.00 8.40 752 100.00%
PISO DE CEMENTO PULIDO e= 2'' S/COLOREAR m2 146.00 24.11 3,520.06 - 0.00 - 0.00 - 0.00 146.00 3,520 100.00%
ACABADO ALISADO S/COLOREAR Y S/BRUÑADO m2 146.00 10.06 1,468.76 - 0.00 - 0.00 - 0.00 146.00 1,469 100.00%
SARDINEL - LADRILLO PANDERETA (0.09*0.11*0.23); APAREJO DE CANTO (C:A 1:5; J= 2 cm) m 47.90 9.39 449.78 - 0.00 - 0.00 - 0.00 47.90 450 100.00%
ZÓCALOS Y CONTRAZÓCALOS
ZOCALO CERAMICO AVELLANO 45 X 45 m2 26.51 48.37 1,282.29 - 0.00 - 0.00 - 0.00 26.51 1,282 100.00%
CONTRAZOCALO CERÁMICO MARMOLIZADO h=0.095 m m 101.10 15.43 1,559.97 - 0.00 - 0.00 - 0.00 101.10 1,560 100.00%
CARPINTERIA DE MADERA
PUERTA PARA GARAJE EN MADERA CEDRO und 1.00 6,599.25 6,599.25 - 0.00 - 0.00 - 0.00 1.00 6,599 100.00%
PUERTA PRINCIPAL 1 ENCHAPADA und 1.00 574.40 574.40 - 0.00 - 0.00 - 0.00 1.00 574 100.00%
PUERTA INTERIOR 2 ENCHAPADA und 1.00 393.90 393.90 - 0.00 - 0.00 - 0.00 1.00 394 100.00%
PUERTA INTERIOR 3 Y 8 ENCHAPADA und 2.00 381.19 762.38 - 0.00 - 0.00 - 0.00 2.00 762 100.00%
PUERTA INTERIOR 5 Y 6 ENCHAPADA und 8.00 368.48 2,947.84 - 0.00 - 0.00 - 0.00 8.00 2,948 100.00%
PUERTA INTERIOR 7 ENCHAPADA und 2.00 393.90 787.80 - 0.00 - 0.00 - 0.00 2.00 788 100.00%
VENTANA 1 und 1.00 184.87 184.87 - 0.00 - 0.00 - 0.00 1.00 185 100.00%
VENTANA 2, 3 Y 5 und 3.00 167.92 503.76 - 0.00 - 0.00 - 0.00 3.00 504 100.00%
VENTANA 4 Y 7 und 2.00 150.97 301.94 - 0.00 - 0.00 - 0.00 2.00 302 100.00%
MAMPARA 1 und 1.00 716.96 716.96 - 0.00 - 0.00 - 0.00 1.00 717 100.00%
MAMPARA 2 und 1.00 214.60 214.60 - 0.00 - 0.00 - 0.00 1.00 215 100.00%
MAMPARA 3 und 1.00 214.60 214.60 - 0.00 - 0.00 - 0.00 1.00 215 100.00%
MAMPARA 4 und 2.00 600.50 1,201.00 - 0.00 - 0.00 - 0.00 2.00 1,201 100.00%
MAMPARA 5 und 1.00 197.65 197.65 - 0.00 - 0.00 - 0.00 1.00 198 100.00%
MAMPARA 6 und 1.00 231.55 231.55 - 0.00 - 0.00 - 0.00 1.00 232 100.00%
CARPINTERIA METALICA
BARANDA DE FIERRO EN ESCALERA m 11.15 482.58 5,380.77 - 0.00 - 0.00 - 0.00 11.15 5,381 100.00%
ESCALERA DE GATO und 1.00 868.36 868.36 - 0.00 - 0.00 - 0.00 1.00 868 100.00%
VIDRIOS, CRISTALES Y SIMILARES
VENTANA - SISTEMA DIRECTO CON VIDRIO CRUDO e= 8 mm m2 5.84 125.00 730.00 - 0.00 - 0.00 - 0.00 5.84 730 100.00%
MAMPARA EN CRISTAL TEMPLADO DE 10 mm m2 64.67 200.73 12,981.21 - 0.00 - 0.00 - 0.00 64.67 12,981 100.00%
PINTURAS
PINTURA LATEX EN CIELO RASO, VIGA Y VOLADOS m2 338.52 8.33 2,819.87 - 0.00 - 0.00 - 0.00 338.52 2,820 100.00%
PINTURA LATEX EN MUROS, COLUMNAS Y DERRAMES m2 59.59 7.04 419.51 - 0.00 - 0.00 - 0.00 59.59 420 100.00%
PINTURA ESMALTE EN MUROS, COLUMNAS Y DERRAMES m2 134.43 7.68 1,032.42 - 0.00 - 0.00 - 0.00 134.43 1,032 100.00%
PINTURA OLEOMATE EN MUROS, COLUMNAS Y DERRAMES m2 18.74 8.03 150.48 - 0.00 - 0.00 - 0.00 18.74 150 100.00%
EMPASTADO MICROCEMENTO EN MUROS, COLUMNAS Y DERRAMES m2 72.72 29.26 2,127.79 - 0.00 - 0.00 - 0.00 72.72 2,128 100.00%
PINTURA DE CONTRAZÓCALOS Y BARANDAS DE ACERO LIVIANO m 379.10 7.94 3,010.05 - 0.00 - 0.00 - 0.00 379.10 3,010 100.00%
VARIOS, LIMPIEZA Y JARDINERÍA
LIMPIEZA DURANTE LA EJECUCION DE LA OBRA glb 1.00 130.69 130.69 - 0.25 33 0.25 33 0.25 0.75 98 75.00%
LIMPIEZA FINAL glb 1.00 130.69 130.69 - 0.00 - 0.00 - 0.00 1.00 131 100.00%
LIMPIEZA DE VIDRIOS m2 70.51 1.64 115.64 - 0.00 - 0.00 - 0.00 70.51 116 100.00%
ENCERADO DE PISOS m2 146.00 5.18 756.28 - 0.00 - 0.00 - 0.00 146.00 756 100.00%
SEMBRADO DE GRASS m2 10.92 16.99 185.53 - 0.00 - 0.00 - 0.00 10.92 186 100.00%
TRABAJOS DE JARDINERÍA pza 48.00 69.64 3,342.72 - 0.00 - 0.00 - 0.00 48.00 3,343 100.00%
COSTO DIRECTO (CD) 310,062.40 0.00 53,593.04 53,593.04 256,469.35
Gastos Generales (10%) 31,006.24 0.00 5,359.30 5,359.30 25,646.94
UTILIDAD (8% ) 31,006.24 0.00 5,359.30 5,359.30 25,646.94
SUB TOTAL (VM=VALORIZACION DEL MES) 372,074.88 0.00 64,311.64 64,311.64 307,763.23
IGV 18% 66,973.48 0.00 11,576.10 11,576.10 55,397.38
TOTAL VALORIZADO S/. 439,048.36 0.00 75,887.74 75,887.74 363,160.61

COSTO DIRECTO (CD) 53,560.37


Gastos Generales (10%) 5,356.04
UTILIDAD (8% ) 5,356.04
SUB TOTAL (VM=VALORIZACION DEL MES) 64,272.45
IGV 18% 11,569.04
TOTAL VALORIZADO S/. 75,841.49

COSTO DIRECTO (CD) 32.67


Gastos Generales (10%) 3.27
UTILIDAD (8% ) 3.27
SUB TOTAL (VM=VALORIZACION DEL MES) 39.21
IGV 18% 7.06
TOTAL VALORIZADO S/. 46.27
VALORIZACION DE OBRA N° 02
del 01 Julio al 31 Julio de 2019

OBRA: Vivienda multifamiliar de 3 niveles


PROPIETARIO: Soberon Monja, Brayan Brandon PLAZO DE EJECUCION: 120 días calendario
CONTRATISTA: USAT VALOR REFERENCIAL Con IGV
RESIDENTE: Soberon Monja, Brayan Brandon PRESUPUESTO CONTRATADO: Con IGV
SUPERVISOR Ing. Cachay Lazo, César Eduardo
UBICACIÓN: Chiclayo
FECHA: Saturday, June 01, 2019

AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Valorizado Metrado Valorizado Valorizado Valorizado
Und. Metrado P. Unit. Presup. Metrado Metrado % Metrado %
S/. S/. S/. S/.
1 ESTRUCTURAS
1.1 OBRAS PROVISIONALES
1.1.1 CASETA Y ALMACÉN DE GUARDIANÍA m2 18.00 44.37 798.66 18.00 799 - 18.00 799 1.00 0.00 - 0.00%
1.1.2 CERCO C/ PANELES DE TRIPLAY m2 60.90 29.53 1,798.38 60.90 1,798 - 60.90 1,798 1.00 0.00 - 0.00%
1.2 OBRAS PRELIMINARES
1.2.1 LIMPIEZA DEL TERRENO MANUAL m2 104.65 3.79 396.62 104.65 397 - 104.65 397 1.00 0.00 - 0.00%
1.2.2 TRAZO, NIVELES Y REPLANTEO m2 104.65 3.75 392.44 104.65 392 - 104.65 392 1.00 0.00 - 0.00%
1.3 MOVIMIENTO DE TIERRAS
1.3.1 EXCAVACIÓN SIMPLE EN TERRENO NATURAL m3 104.21 59.50 6,200.50 104.21 6,201 - 104.21 6,201 1.00 0.00 - 0.00%
1.3.2 EXCAVACIÓN SIMPLE EN MATERIAL DE PRÉSTAMO m3 3.67 37.19 136.49 3.67 136 - 3.67 136 1.00 0.00 - 0.00%
1.3.3 CORTE DE TERRENO NATURAL h = 0.50 m m3 6.00 18.60 111.60 6.00 112 - 6.00 112 1.00 0.00 - 0.00%
1.3.4 RELLENO CON MATERIAL DE PRÉSTAMO m3 57.44 47.51 2,728.97 57.44 2,729 - 57.44 2,729 1.00 0.00 - 0.00%
1.3.5 NIVELACION INTERIOR Y APISONADO m2 79.90 3.43 274.06 79.90 274 - 79.90 274 1.00 0.00 - 0.00%
1.3.6 ELIMINACION DE MATERIAL EXCEDENTE m3 135.47 27.28 3,695.62 135.47 3,696 - 135.47 3,696 1.00 0.00 - 0.00%
1.4 CONCRETO SIMPLE
1.4.1 CONCRETO SOLADO (C:H 1:12; e=0.05 m) m2 64.20 27.54 1,768.07 64.20 1,768 - 64.20 1,768 1.00 0.00 - 0.00%
1.4.2 CONCRETO CICLOPEO CIMIENTO CORRIDO MEZCLA 1:12 + 30% P.G. m3 5.92 186.32 1,103.01 5.92 1,103 - 5.92 1,103 1.00 0.00 - 0.00%
1.4.3 CONCRETO FALSOPISO (f'c= 140 kg/cm2; e=0.10 m) m2 73.27 26.06 1,909.42 0.00 - 73.27 1,909 73.27 1,909 1.00 0.00 - 0.00%
1.4.4 CONCRETO GRADAS f'c=140 kg/cm2 m3 0.36 298.22 107.36 0.00 - 0.36 107 0.36 107 1.00 0.00 - 0.00%
1.4.5 ENCOFRADO GRADAS m 1.43 25.04 35.81 0.00 - 1.43 36 1.43 36 1.00 0.00 - 0.00%
1.5 CONCRETO ARMADO
1.5.1 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 26.57 314.68 8,361.05 26.57 8,361 - 26.57 8,361 1.00 0.00 - 0.00%
1.5.2 ACERO ZAPATAS fy= 4200 kg/cm2 kg 1,340.65 4.39 5,885.45 1340.65 5,885 - 1,340.65 5,885 1.00 0.00 - 0.00%
1.5.3 CONCRETO VIGAS DE CIMENTACION f'c=210 kg/cm2 m3 8.39 335.81 2,817.45 8.39 2,817 - 8.39 2,817 1.00 0.00 - 0.00%
1.5.4 ENCOFRADO EN VIGA DE CIMENTACION m2 47.05 82.65 3,888.68 47.05 3,889 - 47.05 3,889 1.00 0.00 - 0.00%
1.5.5 ACERO VIGAS CIMENTACIÓN fy= 4200 kg/cm2 kg 834.03 4.35 3,628.03 834.03 3,628 - 834.03 3,628 1.00 0.00 - 0.00%
1.5.6 CONCRETO SOBRECIMIENTO f'c=210 kg/cm2 m3 8.01 305.02 2,443.21 0.00 - 8.01 2,443 8.01 2,443 1.00 0.00 - 0.00%
1.5.7 ACERO SOBRECIMIENTO FY= 4200 kg/cm2 kg 297.58 4.35 1,294.47 89.27 388 208.31 906 297.58 1,294 1.00 0.00 - 0.00%
1.5.8 ENCOFRADO DE SOBRECIMIENTO h=0.60 m m2 78.99 51.43 4,062.46 0.00 - 78.99 4,062 78.99 4,062 1.00 0.00 - 0.00%
1.5.9 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 16.39 348.10 5,705.36 0.00 - 16.39 5,705 16.39 5,705 1.00 0.00 - 0.00%
1.5.10 LADRILLO LOSA ALIGERADA (0.30*0.30*0.15) mll 1.56 1,916.24 2,989.33 0.00 - 1.56 2,989 1.56 2,989 1.00 0.00 - 0.00%
1.5.11 ENCOFRADO LOSA ALIGERADA m2 187.32 56.88 10,654.76 0.00 - 187.32 10,655 187.32 10,655 1.00 0.00 - 0.00%
1.5.12 ACERO LOSA ALIGERADA fy= 4200 kg/cm2 kg 1,152.39 4.35 5,012.90 0.00 - 1,152.39 5,013 1,152.39 5,013 1.00 0.00 - 0.00%
1.5.13 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 16.23 455.44 7,391.79 0.00 - 16.23 7,392 16.23 7,392 1.00 0.00 - 0.00%
1.5.14 ACERO COLUMNAS fy= 4200 kg/cm2 kg 2,773.30 4.32 11,980.66 554.66 2,396 2,218.64 9,585 2,773.30 11,981 1.00 0.00 - 0.00%
1.5.15 ENCOFRADO CARAVISTA COLUMNAS m2 186.81 79.70 14,888.76 0.00 - 186.81 14,889 186.81 14,889 1.00 0.00 - 0.00%
1.5.16 CONCRETO COLUMNETAS f'c=210 kg/cm2 m3 9.24 444.93 4,111.15 0.00 - - 0.00 - 0.00 9.24 4,111 100.00%
1.5.17 ENCOFRADO COLUMNETAS m2 126.28 60.56 7,647.52 0.00 - - 0.00 - 0.00 126.28 7,648 100.00%
1.5.18 ACERO COLUMNETAS fy= 4200 kg/cm2 kg 1,151.54 4.51 5,193.45 230.31 1,039 - 230.31 1,039 0.20 921.23 4,155 80.00%
1.5.19 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.91 373.32 6,312.84 0.00 - 16.91 6,313 16.91 6,313 1.00 0.00 - 0.00%
1.5.20 ENCOFRADO DE VIGAS m2 100.50 70.68 7,103.34 0.00 - 100.50 7,103 100.50 7,103 1.00 0.00 - 0.00%
1.5.21 ACERO VIGAS fy= 4200 kg/cm2 kg 2,256.76 4.35 9,816.91 0.00 - 2,256.76 9,817 2,256.76 9,817 1.00 0.00 - 0.00%
1.5.22 CONCRETO VIGAS DE BORDE f'c=210 kg/cm2 m3 2.32 330.08 765.79 0.00 - 2.32 766 2.32 766 1.00 0.00 - 0.00%
1.5.23 ENCOFRADO DE VIGA DE BORDE Y FRISO h= 0.20 m2 45.09 40.13 1,809.46 0.00 - 45.09 1,809 45.09 1,809 1.00 0.00 - 0.00%
1.5.24 ACERO VIGAS DE BORDE fy= 4200 kg/cm2 kg 336.19 4.32 1,452.34 0.00 - 336.19 1,452 336.19 1,452 1.00 0.00 - 0.00%
1.5.25 CONCRETO VIGAS COLLARÍN f'c=210 kg/cm2 m3 3.98 356.42 1,418.55 0.00 - - 0.00 - 0.00 3.98 1,419 100.00%
1.5.26 ENCOFRADO DE VIGA COLLARÍN m2 44.66 40.29 1,799.35 0.00 - - 0.00 - 0.00 44.66 1,799 100.00%
1.5.27 ACERO VIGA COLLARÍN fy= 4200 kg/cm2 kg 557.50 4.32 2,408.40 0.00 - - 0.00 - 0.00 557.50 2,408 100.00%
1.5.28 CONCRETO ESCALERAS f´c=210 kg/cm2 m3 4.03 442.60 1,783.68 0.00 - - 0.00 - 0.00 4.03 1,784 100.00%
1.5.29 ENCOFRADO NORMAL EN ESCALERA m2 29.59 89.88 2,659.55 0.00 - - 0.00 - 0.00 29.59 2,660 100.00%
1.5.30 ACERO ESCALERA fy= 4200 kg/cm2 kg 381.22 4.32 1,646.87 0.00 - 114.37 494 114.37 494 0.30 266.85 1,153 70.00%
1.5.31 JUNTA DE DILATACION e=1/4" m 331.15 35.30 11,689.60 0.00 - - 0.00 - 0.00 331.15 11,690 100.00%
1.5.32 CONCRETO PREMEZCLADO CISTERNA f'c=280 kg/cm2 (aditivo plastificante) m3 1.34 277.20 371.45 1.34 371 - 1.34 371 1.00 0.00 - 0.00%
1.5.33 ENCOFRADO METALICO CISTERNA m2 8.70 36.12 314.24 8.70 314 - 8.70 314 1.00 0.00 - 0.00%
1.5.34 ACERO CISTERNA fy= 4200 kg/cm2 kg 93.51 4.32 403.96 93.51 404 - 93.51 404 1.00 0.00 - 0.00%
1.5.35 CONCRETO PREMEZCLADO PISCINA f'c=280 kg/cm2 (aditivo plastificante) m3 6.30 277.20 1,746.36 6.30 1,746 - 6.30 1,746 1.00 0.00 - 0.00%
1.5.36 ENCOFRADO METALICO PISCINA m2 45.24 29.96 1,355.39 45.24 1,355 - 45.24 1,355 1.00 0.00 - 0.00%
1.5.37 ACERO PISCINA fy= 4200 kg/cm2 kg 361.28 4.32 1,560.73 361.28 1,561 - 361.28 1,561 1.00 0.00 - 0.00%
2 ARQUITECTURA
MUROS Y TABIQUES DE ALBAÑILERÍA
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO SOGA; C:A 1:4 (J= 1.5 cm) m2 309.30 55.60 17,197.08 0.00 - - 0.00 - 0.00 309.30 17,197 100.00%
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO CABEZA; C:A 1:4 (J= 1.5 cm) m2 25.84 91.36 2,360.74 0.00 - - 0.00 - 0.00 25.84 2,361 100.00%
REVOQUES Y REVESTIMIENTOS 0.00
TARRAJEO RAYADO PRIMARIO (C:A 1:4; e= 2 cm) m2 26.51 21.20 562.01 0.00 - - 0.00 - 0.00 26.51 562 100.00%
TARRAJEO EN INTERIORES (C:A 1:5; e= 2cm) m2 293.28 22.53 6,607.60 0.00 - - 0.00 - 0.00 293.28 6,608 100.00%
TARRAJEO EN COLUMNAS (C:A 1:5; e= 2 cm) m2 178.20 32.14 5,727.35 0.00 - - 0.00 - 0.00 178.20 5,727 100.00%
TARRAJEO EN VIGAS (C:A 1:5; e= 2 cm) m2 136.57 36.15 4,937.01 0.00 - - 0.00 - 0.00 136.57 4,937 100.00%
TARRAJEO CON INPERMEABILIZANTE (C:A 1:3; e= 2 cm) m2 36.76 25.55 939.22 0.00 - - 0.00 - 0.00 36.76 939 100.00%
VESTIDURA DE DERRAMES (C:A 1:5; e= 2 cm) m 192.83 13.43 2,589.71 0.00 - - 0.00 - 0.00 192.83 2,590 100.00%
TARRAJEO DE DUCTOS (C:A 1:5; e= 2 cm) m2 14.64 36.13 528.94 0.00 - - 0.00 - 0.00 14.64 529 100.00%
BRUÑAS 5 mm*5 mm m 514.31 8.97 4,613.36 0.00 - - 0.00 - 0.00 514.31 4,613 100.00%
TARRAJEO EN FONDO DE ESCALERAS (C:A 1:5; e= 2 cm) m2 15.80 34.87 550.95 0.00 - - 0.00 - 0.00 15.80 551 100.00%
PREPARACIÓN DE GRADAS DE CONCRETO (C:A 1:4; e= 2 cm) m 17.00 24.70 419.90 0.00 - - 0.00 - 0.00 17.00 420 100.00%
PREPARACIÓN DE DESCANSOS (C:A 1;4; e= 2 cm) m2 3.10 20.60 63.86 0.00 - - 0.00 - 0.00 3.10 64 100.00%
GRADAS - VINILO 1.5 mm m 20.10 45.95 923.60 0.00 - - 0.00 - 0.00 20.10 924 100.00%
ENCHAPE GRESITE NIEBLA AZUL 0.33*0.33 m2 36.76 90.25 3,317.59 0.00 - - 0.00 - 0.00 36.76 3,318 100.00%
ENCHAPE TABLAS MACHIHEMBRADAS m2 8.40 45.32 380.69 0.00 - - 0.00 - 0.00 8.40 381 100.00%
CIELO RASOS
CIELORRASO CON MEZCLA C:A 1:5; e= 1.5 cm m2 187.32 19.21 3,598.42 0.00 - - 0.00 - 0.00 187.32 3,598 100.00%
PISOS Y PAVIMENTOS
CONTRAPISO C:4 1:3 e= 2'' m2 81.10 31.29 2,537.62 0.00 - - 0.00 - 0.00 81.10 2,538 100.00%
PISO DE PORCELANATO NAVIA ACERO 0.30*0.90; ALTO TRÁNSITO e= 12 mm m2 24.98 84.97 2,122.55 0.00 - - 0.00 - 0.00 24.98 2,123 100.00%
PISO DE PORCELANATO TEXAS 0.15*0.90; ALTO TRÁNSITO e= 12 mm m2 11.74 155.42 1,824.63 0.00 - - 0.00 - 0.00 11.74 1,825 100.00%
PISO DE PORCELANATO MADERA 0.23*1.20; MEDIO TRÁNSITO e= 8 mm m2 35.98 93.93 3,379.60 0.00 - - 0.00 - 0.00 35.98 3,380 100.00%
PISO DE TABLAS MACHIHEMBRADAS CHANUL m2 8.40 89.56 752.30 0.00 - - 0.00 - 0.00 8.40 752 100.00%
PISO DE CEMENTO PULIDO e= 2'' S/COLOREAR m2 146.00 24.11 3,520.06 0.00 - - 0.00 - 0.00 146.00 3,520 100.00%
ACABADO ALISADO S/COLOREAR Y S/BRUÑADO m2 146.00 10.06 1,468.76 0.00 - - 0.00 - 0.00 146.00 1,469 100.00%
SARDINEL - LADRILLO PANDERETA (0.09*0.11*0.23); APAREJO DE CANTO (C:A 1:5; J= 2 cm) m 47.90 9.39 449.78 0.00 - - 0.00 - 0.00 47.90 450 100.00%
ZÓCALOS Y CONTRAZÓCALOS
ZOCALO CERAMICO AVELLANO 45 X 45 m2 26.51 48.37 1,282.29 0.00 - - 0.00 - 0.00 26.51 1,282 100.00%
CONTRAZOCALO CERÁMICO MARMOLIZADO h=0.095 m m 101.10 15.43 1,559.97 0.00 - - 0.00 - 0.00 101.10 1,560 100.00%
CARPINTERIA DE MADERA
PUERTA PARA GARAJE EN MADERA CEDRO und 1.00 6,599.25 6,599.25 0.00 - - 0.00 - 0.00 1.00 6,599 100.00%
PUERTA PRINCIPAL 1 ENCHAPADA und 1.00 574.40 574.40 0.00 - - 0.00 - 0.00 1.00 574 100.00%
PUERTA INTERIOR 2 ENCHAPADA und 1.00 393.90 393.90 0.00 - - 0.00 - 0.00 1.00 394 100.00%
PUERTA INTERIOR 3 Y 8 ENCHAPADA und 2.00 381.19 762.38 0.00 - - 0.00 - 0.00 2.00 762 100.00%
PUERTA INTERIOR 5 Y 6 ENCHAPADA und 8.00 368.48 2,947.84 0.00 - - 0.00 - 0.00 8.00 2,948 100.00%
PUERTA INTERIOR 7 ENCHAPADA und 2.00 393.90 787.80 0.00 - - 0.00 - 0.00 2.00 788 100.00%
VENTANA 1 und 1.00 184.87 184.87 0.00 - - 0.00 - 0.00 1.00 185 100.00%
VENTANA 2, 3 Y 5 und 3.00 167.92 503.76 0.00 - - 0.00 - 0.00 3.00 504 100.00%
VENTANA 4 Y 7 und 2.00 150.97 301.94 0.00 - - 0.00 - 0.00 2.00 302 100.00%
MAMPARA 1 und 1.00 716.96 716.96 0.00 - - 0.00 - 0.00 1.00 717 100.00%
MAMPARA 2 und 1.00 214.60 214.60 0.00 - - 0.00 - 0.00 1.00 215 100.00%
MAMPARA 3 und 1.00 214.60 214.60 0.00 - - 0.00 - 0.00 1.00 215 100.00%
MAMPARA 4 und 2.00 600.50 1,201.00 0.00 - - 0.00 - 0.00 2.00 1,201 100.00%
MAMPARA 5 und 1.00 197.65 197.65 0.00 - - 0.00 - 0.00 1.00 198 100.00%
MAMPARA 6 und 1.00 231.55 231.55 0.00 - - 0.00 - 0.00 1.00 232 100.00%
CARPINTERIA METALICA
BARANDA DE FIERRO EN ESCALERA m 11.15 482.58 5,380.77 0.00 - - 0.00 - 0.00 11.15 5,381 100.00%
ESCALERA DE GATO und 1.00 868.36 868.36 0.00 - - 0.00 - 0.00 1.00 868 100.00%
VIDRIOS, CRISTALES Y SIMILARES
VENTANA - SISTEMA DIRECTO CON VIDRIO CRUDO e= 8 mm m2 5.84 125.00 730.00 0.00 - - 0.00 - 0.00 5.84 730 100.00%
MAMPARA EN CRISTAL TEMPLADO DE 10 mm m2 64.67 200.73 12,981.21 0.00 - - 0.00 - 0.00 64.67 12,981 100.00%
PINTURAS
PINTURA LATEX EN CIELO RASO, VIGA Y VOLADOS m2 338.52 8.33 2,819.87 0.00 - - 0.00 - 0.00 338.52 2,820 100.00%
PINTURA LATEX EN MUROS, COLUMNAS Y DERRAMES m2 59.59 7.04 419.51 0.00 - - 0.00 - 0.00 59.59 420 100.00%
PINTURA ESMALTE EN MUROS, COLUMNAS Y DERRAMES m2 134.43 7.68 1,032.42 0.00 - - 0.00 - 0.00 134.43 1,032 100.00%
PINTURA OLEOMATE EN MUROS, COLUMNAS Y DERRAMES m2 18.74 8.03 150.48 0.00 - - 0.00 - 0.00 18.74 150 100.00%
EMPASTADO MICROCEMENTO EN MUROS, COLUMNAS Y DERRAMES m2 72.72 29.26 2,127.79 0.00 - - 0.00 - 0.00 72.72 2,128 100.00%
PINTURA DE CONTRAZÓCALOS Y BARANDAS DE ACERO LIVIANO m 379.10 7.94 3,010.05 0.00 - - 0.00 - 0.00 379.10 3,010 100.00%
VARIOS, LIMPIEZA Y JARDINERÍA
LIMPIEZA DURANTE LA EJECUCION DE LA OBRA glb 1.00 130.69 130.69 0.25 33 0.25 33 0.50 65 0.50 0.50 65 50.00%
LIMPIEZA FINAL glb 1.00 130.69 130.69 0.00 - - 0.00 - 0.00 1.00 131 100.00%
LIMPIEZA DE VIDRIOS m2 70.51 1.64 115.64 0.00 - - 0.00 - 0.00 70.51 116 100.00%
ENCERADO DE PISOS m2 146.00 5.18 756.28 0.00 - - 0.00 - 0.00 146.00 756 100.00%
SEMBRADO DE GRASS m2 10.92 16.99 185.53 0.00 - - 0.00 - 0.00 10.92 186 100.00%
TRABAJOS DE JARDINERÍA pza 48.00 69.64 3,342.72 0.00 - - 0.00 - 0.00 48.00 3,343 100.00%
COSTO DIRECTO (CD) 310,062.40 53,593.04 93,479.22 147,072.28 162,990.13
Gastos Generales (10%) 31,006.24 5,359.30 9,347.92 14,707.23 16,299.01
UTILIDAD (8% ) 31,006.24 5,359.30 9,347.92 14,707.23 16,299.01
SUB TOTAL (VM=VALORIZACION DEL MES) 372,074.88 64,311.64 112,175.06 176,486.74 195,588.15
IGV 18% 66,973.48 11,576.10 20,191.51 31,767.61 35,205.87
TOTAL VALORIZADO S/. 439,048.36 75,887.74 132,366.57 208,254.35 230,794.02

COSTO DIRECTO (CD) 93,446.55


Gastos Generales (10%) 9,344.66
UTILIDAD (8% ) 9,344.66
SUB TOTAL (VM=VALORIZACION DEL MES) 112,135.87
IGV 18% 20,184.46
TOTAL VALORIZADO S/. 132,320.33

COSTO DIRECTO (CD) 32.67


Gastos Generales (10%) 3.27
UTILIDAD (8% ) 3.27
SUB TOTAL (VM=VALORIZACION DEL MES) 39.21
IGV 18% 7.06
TOTAL VALORIZADO S/. 46.27
VALORIZACION DE OBRA N° 03
del 01 Agosto al 31 Agosto de 2019

OBRA: Vivienda multifamiliar de 3 niveles


PROPIETARIO: Soberon Monja, Brayan Brandon PLAZO DE EJECUCION: 120 días calendario
CONTRATISTA: USAT VALOR REFERENCIAL Con IGV
RESIDENTE: Soberon Monja, Brayan Brandon PRESUPUESTO CONTRATADO: Con IGV
SUPERVISOR Ing. Cachay Lazo, César Eduardo
UBICACIÓN: Chiclayo
FECHA: Saturday, June 01, 2019

AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Valorizado Metrado Valorizado Valorizado Valorizado
Und. Metrado P. Unit. Presup. Metrado Metrado % Metrado %
S/. S/. S/. S/.
1 ESTRUCTURAS
1.1 OBRAS PROVISIONALES
1.1.1 CASETA Y ALMACÉN DE GUARDIANÍA m2 18.00 44.37 798.66 18.00 799 - 18.00 799 1.00 0.00 - 0.00%
1.1.2 CERCO C/ PANELES DE TRIPLAY m2 60.90 29.53 1,798.38 60.90 1,798 - 60.90 1,798 1.00 0.00 - 0.00%
1.2 OBRAS PRELIMINARES
1.2.1 LIMPIEZA DEL TERRENO MANUAL m2 104.65 3.79 396.62 104.65 397 - 104.65 397 1.00 0.00 - 0.00%
1.2.2 TRAZO, NIVELES Y REPLANTEO m2 104.65 3.75 392.44 104.65 392 - 104.65 392 1.00 0.00 - 0.00%
1.3 MOVIMIENTO DE TIERRAS
1.3.1 EXCAVACIÓN SIMPLE EN TERRENO NATURAL m3 104.21 59.50 6,200.50 104.21 6,201 - 104.21 6,201 1.00 0.00 - 0.00%
1.3.2 EXCAVACIÓN SIMPLE EN MATERIAL DE PRÉSTAMO m3 3.67 37.19 136.49 3.67 136 - 3.67 136 1.00 0.00 - 0.00%
1.3.3 CORTE DE TERRENO NATURAL h = 0.50 m m3 6.00 18.60 111.60 6.00 112 - 6.00 112 1.00 0.00 - 0.00%
1.3.4 RELLENO CON MATERIAL DE PRÉSTAMO m3 57.44 47.51 2,728.97 57.44 2,729 - 57.44 2,729 1.00 0.00 - 0.00%
1.3.5 NIVELACION INTERIOR Y APISONADO m2 79.90 3.43 274.06 79.90 274 - 79.90 274 1.00 0.00 - 0.00%
1.3.6 ELIMINACION DE MATERIAL EXCEDENTE m3 135.47 27.28 3,695.62 135.47 3,696 - 135.47 3,696 1.00 0.00 - 0.00%
1.4 CONCRETO SIMPLE
1.4.1 CONCRETO SOLADO (C:H 1:12; e=0.05 m) m2 64.20 27.54 1,768.07 64.20 1,768 - 64.20 1,768 1.00 0.00 - 0.00%
1.4.2 CONCRETO CICLOPEO CIMIENTO CORRIDO MEZCLA 1:12 + 30% P.G. m3 5.92 186.32 1,103.01 5.92 1,103 - 5.92 1,103 1.00 0.00 - 0.00%
1.4.3 CONCRETO FALSOPISO (f'c= 140 kg/cm2; e=0.10 m) m2 73.27 26.06 1,909.42 73.27 1,909 - 73.27 1,909 1.00 0.00 - 0.00%
1.4.4 CONCRETO GRADAS f'c=140 kg/cm2 m3 0.36 298.22 107.36 0.36 107 - 0.36 107 1.00 0.00 - 0.00%
1.4.5 ENCOFRADO GRADAS m 1.43 25.04 35.81 1.43 36 - 1.43 36 1.00 0.00 - 0.00%
1.5 CONCRETO ARMADO
1.5.1 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 26.57 314.68 8,361.05 26.57 8,361 - 26.57 8,361 1.00 0.00 - 0.00%
1.5.2 ACERO ZAPATAS fy= 4200 kg/cm2 kg 1,340.65 4.39 5,885.45 1340.65 5,885 - 1,340.65 5,885 1.00 0.00 - 0.00%
1.5.3 CONCRETO VIGAS DE CIMENTACION f'c=210 kg/cm2 m3 8.39 335.81 2,817.45 8.39 2,817 - 8.39 2,817 1.00 0.00 - 0.00%
1.5.4 ENCOFRADO EN VIGA DE CIMENTACION m2 47.05 82.65 3,888.68 47.05 3,889 - 47.05 3,889 1.00 0.00 - 0.00%
1.5.5 ACERO VIGAS CIMENTACIÓN fy= 4200 kg/cm2 kg 834.03 4.35 3,628.03 834.03 3,628 - 834.03 3,628 1.00 0.00 - 0.00%
1.5.6 CONCRETO SOBRECIMIENTO f'c=210 kg/cm2 m3 8.01 305.02 2,443.21 8.01 2,443 - 8.01 2,443 1.00 0.00 - 0.00%
1.5.7 ACERO SOBRECIMIENTO FY= 4200 kg/cm2 kg 297.58 4.35 1,294.47 297.58 1,294 - 297.58 1,294 1.00 0.00 - 0.00%
1.5.8 ENCOFRADO DE SOBRECIMIENTO h=0.60 m m2 78.99 51.43 4,062.46 78.99 4,062 - 78.99 4,062 1.00 0.00 - 0.00%
1.5.9 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 16.39 348.10 5,705.36 16.39 5,705 - 16.39 5,705 1.00 0.00 - 0.00%
1.5.10 LADRILLO LOSA ALIGERADA (0.30*0.30*0.15) mll 1.56 1,916.24 2,989.33 1.56 2,989 - 1.56 2,989 1.00 0.00 - 0.00%
1.5.11 ENCOFRADO LOSA ALIGERADA m2 187.32 56.88 10,654.76 187.32 10,655 - 187.32 10,655 1.00 0.00 - 0.00%
1.5.12 ACERO LOSA ALIGERADA fy= 4200 kg/cm2 kg 1,152.39 4.35 5,012.90 1152.39 5,013 - 1,152.39 5,013 1.00 0.00 - 0.00%
1.5.13 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 16.23 455.44 7,391.79 16.23 7,392 - 16.23 7,392 1.00 0.00 - 0.00%
1.5.14 ACERO COLUMNAS fy= 4200 kg/cm2 kg 2,773.30 4.32 11,980.66 2773.30 11,981 - 2,773.30 11,981 1.00 0.00 - 0.00%
1.5.15 ENCOFRADO CARAVISTA COLUMNAS m2 186.81 79.70 14,888.76 186.81 14,889 - 186.81 14,889 1.00 0.00 - 0.00%
1.5.16 CONCRETO COLUMNETAS f'c=210 kg/cm2 m3 9.24 444.93 4,111.15 0.00 - 6.93 3,083 6.93 3,083 0.75 2.31 1,028 25.00%
1.5.17 ENCOFRADO COLUMNETAS m2 126.28 60.56 7,647.52 0.00 - 94.71 5,736 94.71 5,736 0.75 31.57 1,912 25.00%
1.5.18 ACERO COLUMNETAS fy= 4200 kg/cm2 kg 1,151.54 4.51 5,193.45 230.31 1,039 921.23 4,155 1,151.54 5,193 1.00 0.00 - 0.00%
1.5.19 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.91 373.32 6,312.84 16.91 6,313 - 16.91 6,313 1.00 0.00 - 0.00%
1.5.20 ENCOFRADO DE VIGAS m2 100.50 70.68 7,103.34 100.50 7,103 - 100.50 7,103 1.00 0.00 - 0.00%
1.5.21 ACERO VIGAS fy= 4200 kg/cm2 kg 2,256.76 4.35 9,816.91 2256.76 9,817 - 2,256.76 9,817 1.00 0.00 - 0.00%
1.5.22 CONCRETO VIGAS DE BORDE f'c=210 kg/cm2 m3 2.32 330.08 765.79 2.32 766 - 2.32 766 1.00 0.00 - 0.00%
1.5.23 ENCOFRADO DE VIGA DE BORDE Y FRISO h= 0.20 m2 45.09 40.13 1,809.46 45.09 1,809 - 45.09 1,809 1.00 0.00 - 0.00%
1.5.24 ACERO VIGAS DE BORDE fy= 4200 kg/cm2 kg 336.19 4.32 1,452.34 336.19 1,452 - 336.19 1,452 1.00 0.00 - 0.00%
1.5.25 CONCRETO VIGAS COLLARÍN f'c=210 kg/cm2 m3 3.98 356.42 1,418.55 0.00 - 2.99 1,064 2.99 1,064 0.75 1.00 355 25.00%
1.5.26 ENCOFRADO DE VIGA COLLARÍN m2 44.66 40.29 1,799.35 0.00 - 33.50 1,350 33.50 1,350 0.75 11.17 450 25.00%
1.5.27 ACERO VIGA COLLARÍN fy= 4200 kg/cm2 kg 557.50 4.32 2,408.40 0.00 - 446.00 1,927 446.00 1,927 0.80 111.50 482 20.00%
1.5.28 CONCRETO ESCALERAS f´c=210 kg/cm2 m3 4.03 442.60 1,783.68 0.00 - 4.03 1,784 4.03 1,784 1.00 0.00 - 0.00%
1.5.29 ENCOFRADO NORMAL EN ESCALERA m2 29.59 89.88 2,659.55 0.00 - 29.59 2,660 29.59 2,660 1.00 0.00 - 0.00%
1.5.30 ACERO ESCALERA fy= 4200 kg/cm2 kg 381.22 4.32 1,646.87 114.37 494 266.85 1,153 381.22 1,647 1.00 0.00 - 0.00%
1.5.31 JUNTA DE DILATACION e=1/4" m 331.15 35.30 11,689.60 0.00 - 165.58 5,845 165.58 5,845 0.50 165.58 5,845 50.00%
1.5.32 CONCRETO PREMEZCLADO CISTERNA f'c=280 kg/cm2 (aditivo plastificante) m3 1.34 277.20 371.45 1.34 371 - 1.34 371 1.00 0.00 - 0.00%
1.5.33 ENCOFRADO METALICO CISTERNA m2 8.70 36.12 314.24 8.70 314 - 8.70 314 1.00 0.00 - 0.00%
1.5.34 ACERO CISTERNA fy= 4200 kg/cm2 kg 93.51 4.32 403.96 93.51 404 - 93.51 404 1.00 0.00 - 0.00%
1.5.35 CONCRETO PREMEZCLADO PISCINA f'c=280 kg/cm2 (aditivo plastificante) m3 6.30 277.20 1,746.36 6.30 1,746 - 6.30 1,746 1.00 0.00 - 0.00%
1.5.36 ENCOFRADO METALICO PISCINA m2 45.24 29.96 1,355.39 45.24 1,355 - 45.24 1,355 1.00 0.00 - 0.00%
1.5.37 ACERO PISCINA fy= 4200 kg/cm2 kg 361.28 4.32 1,560.73 361.28 1,561 - 361.28 1,561 1.00 0.00 - 0.00%
2 ARQUITECTURA
MUROS Y TABIQUES DE ALBAÑILERÍA
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO SOGA; C:A 1:4 (J= 1.5 cm) m2 309.30 55.60 17,197.08 0.00 - 309.30 17,197 309.30 17,197 1.00 0.00 - 0.00%
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO CABEZA; C:A 1:4 (J= 1.5 cm) m2 25.84 91.36 2,360.74 - 25.84 2,361 25.84 2,361 1.00 0.00 - 0.00%
REVOQUES Y REVESTIMIENTOS 0.00
TARRAJEO RAYADO PRIMARIO (C:A 1:4; e= 2 cm) m2 26.51 21.20 562.01 0.00 - - 0.00 - 0.00 26.51 562 100.00%
TARRAJEO EN INTERIORES (C:A 1:5; e= 2cm) m2 293.28 22.53 6,607.60 0.00 - - 0.00 - 0.00 293.28 6,608 100.00%
TARRAJEO EN COLUMNAS (C:A 1:5; e= 2 cm) m2 178.20 32.14 5,727.35 0.00 - 89.10 2,864 89.10 2,864 0.50 89.10 2,864 50.00%
TARRAJEO EN VIGAS (C:A 1:5; e= 2 cm) m2 136.57 36.15 4,937.01 0.00 - 68.29 2,469 68.29 2,469 0.50 68.29 2,469 50.00%
TARRAJEO CON INPERMEABILIZANTE (C:A 1:3; e= 2 cm) m2 36.76 25.55 939.22 0.00 - 36.76 939 36.76 939 1.00 0.00 - 0.00%
VESTIDURA DE DERRAMES (C:A 1:5; e= 2 cm) m 192.83 13.43 2,589.71 0.00 - - 0.00 - 0.00 192.83 2,590 100.00%
TARRAJEO DE DUCTOS (C:A 1:5; e= 2 cm) m2 14.64 36.13 528.94 0.00 - 7.32 264 7.32 264 0.50 7.32 264 50.00%
BRUÑAS 5 mm*5 mm m 514.31 8.97 4,613.36 0.00 - - 0.00 - 0.00 514.31 4,613 100.00%
TARRAJEO EN FONDO DE ESCALERAS (C:A 1:5; e= 2 cm) m2 15.80 34.87 550.95 0.00 - 3.95 138 3.95 138 0.25 11.85 413 75.00%
PREPARACIÓN DE GRADAS DE CONCRETO (C:A 1:4; e= 2 cm) m 17.00 24.70 419.90 0.00 - 4.25 105 4.25 105 0.25 12.75 315 75.00%
PREPARACIÓN DE DESCANSOS (C:A 1;4; e= 2 cm) m2 3.10 20.60 63.86 0.00 - 1.55 32 1.55 32 0.50 1.55 32 50.00%
GRADAS - VINILO 1.5 mm m 20.10 45.95 923.60 0.00 - 10.05 462 10.05 462 0.50 10.05 462 50.00%
ENCHAPE GRESITE NIEBLA AZUL 0.33*0.33 m2 36.76 90.25 3,317.59 0.00 - - 0.00 - 0.00 36.76 3,318 100.00%
ENCHAPE TABLAS MACHIHEMBRADAS m2 8.40 45.32 380.69 0.00 - - 0.00 - 0.00 8.40 381 100.00%
CIELO RASOS
CIELORRASO CON MEZCLA C:A 1:5; e= 1.5 cm m2 187.32 19.21 3,598.42 0.00 - 140.49 2,699 140.49 2,699 0.75 46.83 900 25.00%
PISOS Y PAVIMENTOS
CONTRAPISO C:4 1:3 e= 2'' m2 81.10 31.29 2,537.62 0.00 - 81.10 2,538 81.10 2,538 1.00 0.00 - 0.00%
PISO DE PORCELANATO NAVIA ACERO 0.30*0.90; ALTO TRÁNSITO e= 12 mm m2 24.98 84.97 2,122.55 0.00 - - 0.00 - 0.00 24.98 2,123 100.00%
PISO DE PORCELANATO TEXAS 0.15*0.90; ALTO TRÁNSITO e= 12 mm m2 11.74 155.42 1,824.63 0.00 - - 0.00 - 0.00 11.74 1,825 100.00%
PISO DE PORCELANATO MADERA 0.23*1.20; MEDIO TRÁNSITO e= 8 mm m2 35.98 93.93 3,379.60 0.00 - - 0.00 - 0.00 35.98 3,380 100.00%
PISO DE TABLAS MACHIHEMBRADAS CHANUL m2 8.40 89.56 752.30 0.00 - - 0.00 - 0.00 8.40 752 100.00%
PISO DE CEMENTO PULIDO e= 2'' S/COLOREAR m2 146.00 24.11 3,520.06 0.00 - 109.50 2,640 109.50 2,640 0.75 36.50 880 25.00%
ACABADO ALISADO S/COLOREAR Y S/BRUÑADO m2 146.00 10.06 1,468.76 0.00 - 109.50 1,102 109.50 1,102 0.75 36.50 367 25.00%
SARDINEL - LADRILLO PANDERETA (0.09*0.11*0.23); APAREJO DE CANTO (C:A 1:5; J= 2 cm) m 47.90 9.39 449.78 0.00 - 47.90 450 47.90 450 1.00 0.00 - 0.00%
ZÓCALOS Y CONTRAZÓCALOS
ZOCALO CERAMICO AVELLANO 45 X 45 m2 26.51 48.37 1,282.29 0.00 - - 0.00 - 0.00 26.51 1,282 100.00%
CONTRAZOCALO CERÁMICO MARMOLIZADO h=0.095 m m 101.10 15.43 1,559.97 0.00 - - 0.00 - 0.00 101.10 1,560 100.00%
CARPINTERIA DE MADERA
PUERTA PARA GARAJE EN MADERA CEDRO und 1.00 6,599.25 6,599.25 0.00 - - 0.00 - 0.00 1.00 6,599 100.00%
PUERTA PRINCIPAL 1 ENCHAPADA und 1.00 574.40 574.40 0.00 - - 0.00 - 0.00 1.00 574 100.00%
PUERTA INTERIOR 2 ENCHAPADA und 1.00 393.90 393.90 0.00 - - 0.00 - 0.00 1.00 394 100.00%
PUERTA INTERIOR 3 Y 8 ENCHAPADA und 2.00 381.19 762.38 0.00 - - 0.00 - 0.00 2.00 762 100.00%
PUERTA INTERIOR 5 Y 6 ENCHAPADA und 8.00 368.48 2,947.84 0.00 - - 0.00 - 0.00 8.00 2,948 100.00%
PUERTA INTERIOR 7 ENCHAPADA und 2.00 393.90 787.80 0.00 - - 0.00 - 0.00 2.00 788 100.00%
VENTANA 1 und 1.00 184.87 184.87 0.00 - - 0.00 - 0.00 1.00 185 100.00%
VENTANA 2, 3 Y 5 und 3.00 167.92 503.76 0.00 - - 0.00 - 0.00 3.00 504 100.00%
VENTANA 4 Y 7 und 2.00 150.97 301.94 0.00 - - 0.00 - 0.00 2.00 302 100.00%
MAMPARA 1 und 1.00 716.96 716.96 0.00 - - 0.00 - 0.00 1.00 717 100.00%
MAMPARA 2 und 1.00 214.60 214.60 0.00 - - 0.00 - 0.00 1.00 215 100.00%
MAMPARA 3 und 1.00 214.60 214.60 0.00 - - 0.00 - 0.00 1.00 215 100.00%
MAMPARA 4 und 2.00 600.50 1,201.00 0.00 - - 0.00 - 0.00 2.00 1,201 100.00%
MAMPARA 5 und 1.00 197.65 197.65 0.00 - - 0.00 - 0.00 1.00 198 100.00%
MAMPARA 6 und 1.00 231.55 231.55 0.00 - - 0.00 - 0.00 1.00 232 100.00%
CARPINTERIA METALICA
BARANDA DE FIERRO EN ESCALERA m 11.15 482.58 5,380.77 0.00 - - 0.00 - 0.00 11.15 5,381 100.00%
ESCALERA DE GATO und 1.00 868.36 868.36 0.00 - - 0.00 - 0.00 1.00 868 100.00%
VIDRIOS, CRISTALES Y SIMILARES
VENTANA - SISTEMA DIRECTO CON VIDRIO CRUDO e= 8 mm m2 5.84 125.00 730.00 0.00 - - 0.00 - 0.00 5.84 730 100.00%
MAMPARA EN CRISTAL TEMPLADO DE 10 mm m2 64.67 200.73 12,981.21 0.00 - - 0.00 - 0.00 64.67 12,981 100.00%
PINTURAS
PINTURA LATEX EN CIELO RASO, VIGA Y VOLADOS m2 338.52 8.33 2,819.87 0.00 - - 0.00 - 0.00 338.52 2,820 100.00%
PINTURA LATEX EN MUROS, COLUMNAS Y DERRAMES m2 59.59 7.04 419.51 0.00 - - 0.00 - 0.00 59.59 420 100.00%
PINTURA ESMALTE EN MUROS, COLUMNAS Y DERRAMES m2 134.43 7.68 1,032.42 0.00 - - 0.00 - 0.00 134.43 1,032 100.00%
PINTURA OLEOMATE EN MUROS, COLUMNAS Y DERRAMES m2 18.74 8.03 150.48 0.00 - - 0.00 - 0.00 18.74 150 100.00%
EMPASTADO MICROCEMENTO EN MUROS, COLUMNAS Y DERRAMES m2 72.72 29.26 2,127.79 0.00 - - 0.00 - 0.00 72.72 2,128 100.00%
PINTURA DE CONTRAZÓCALOS Y BARANDAS DE ACERO LIVIANO m 379.10 7.94 3,010.05 0.00 - - 0.00 - 0.00 379.10 3,010 100.00%
VARIOS, LIMPIEZA Y JARDINERÍA
LIMPIEZA DURANTE LA EJECUCION DE LA OBRA glb 1.00 130.69 130.69 0.50 65 0.25 33 0.75 98 0.75 0.25 33 25.00%
LIMPIEZA FINAL glb 1.00 130.69 130.69 0.00 - - 0.00 - 0.00 1.00 131 100.00%
LIMPIEZA DE VIDRIOS m2 70.51 1.64 115.64 0.00 - - 0.00 - 0.00 70.51 116 100.00%
ENCERADO DE PISOS m2 146.00 5.18 756.28 0.00 - - 0.00 - 0.00 146.00 756 100.00%
SEMBRADO DE GRASS m2 10.92 16.99 185.53 0.00 - - 0.00 - 0.00 10.92 186 100.00%
TRABAJOS DE JARDINERÍA pza 48.00 69.64 3,342.72 0.00 - - 0.00 - 0.00 48.00 3,343 100.00%
COSTO DIRECTO (CD) 310,062.40 147,072.28 65,045.37 212,117.65 97,944.74
Gastos Generales (10%) 31,006.24 14,707.23 6,504.54 16,969.41 9,794.47
UTILIDAD (8% ) 31,006.24 14,707.23 6,504.54 21,211.77 9,794.47
SUB TOTAL (VM=VALORIZACION DEL MES) 372,074.88 176,486.74 78,054.45 250,298.83 117,533.68
IGV 18% 66,973.48 31,767.61 14,049.80 45,053.79 21,156.06
TOTAL VALORIZADO S/. 439,048.36 208,254.35 92,104.25 295,352.62 138,689.74

COSTO DIRECTO (CD) 28,754.74


Gastos Generales (10%) 2,875.47
UTILIDAD (8% ) 2,875.47
SUB TOTAL (VM=VALORIZACION DEL MES) 34,505.68
IGV 18% 6,211.02
TOTAL VALORIZADO S/. 40,716.70

COSTO DIRECTO (CD) 36,290.63


Gastos Generales (10%) 3,629.06
UTILIDAD (8% ) 3,629.06
SUB TOTAL (VM=VALORIZACION DEL MES) 43,548.75
IGV 18% 7,838.78
TOTAL VALORIZADO S/. 51,387.53
VALORIZACION DE OBRA N° 03
del 01 Setiembre al 30 Setiembre de 2019

OBRA: Vivienda multifamiliar de 3 niveles


PROPIETARIO: Soberon Monja, Brayan Brandon PLAZO DE EJECUCION: 120 días calendario
CONTRATISTA: USAT VALOR REFERENCIAL Con IGV
RESIDENTE: Soberon Monja, Brayan Brandon PRESUPUESTO CONTRATADO: Con IGV
SUPERVISOR Ing. Cachay Lazo, César Eduardo
UBICACIÓN: Chiclayo
FECHA: Saturday, June 01, 2019

AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Valorizado Metrado Valorizado Valorizado Valorizado
Und. Metrado P. Unit. Presup. Metrado Metrado % Metrado %
S/. S/. S/. S/.
1 ESTRUCTURAS
1.1 OBRAS PROVISIONALES
1.1.1 CASETA Y ALMACÉN DE GUARDIANÍA m2 18.00 44.37 798.66 18.00 799 - 18.00 799 1.00 0.00 - 0.00%
1.1.2 CERCO C/ PANELES DE TRIPLAY m2 60.90 29.53 1,798.38 60.90 1,798 - 60.90 1,798 1.00 0.00 - 0.00%
1.2 OBRAS PRELIMINARES
1.2.1 LIMPIEZA DEL TERRENO MANUAL m2 104.65 3.79 396.62 104.65 397 - 104.65 397 1.00 0.00 - 0.00%
1.2.2 TRAZO, NIVELES Y REPLANTEO m2 104.65 3.75 392.44 104.65 392 - 104.65 392 1.00 0.00 - 0.00%
1.3 MOVIMIENTO DE TIERRAS
1.3.1 EXCAVACIÓN SIMPLE EN TERRENO NATURAL m3 104.21 59.50 6,200.50 104.21 6,201 - 104.21 6,201 1.00 0.00 - 0.00%
1.3.2 EXCAVACIÓN SIMPLE EN MATERIAL DE PRÉSTAMO m3 3.67 37.19 136.49 3.67 136 - 3.67 136 1.00 0.00 - 0.00%
1.3.3 CORTE DE TERRENO NATURAL h = 0.50 m m3 6.00 18.60 111.60 6.00 112 - 6.00 112 1.00 0.00 - 0.00%
1.3.4 RELLENO CON MATERIAL DE PRÉSTAMO m3 57.44 47.51 2,728.97 57.44 2,729 - 57.44 2,729 1.00 0.00 - 0.00%
1.3.5 NIVELACION INTERIOR Y APISONADO m2 79.90 3.43 274.06 79.90 274 - 79.90 274 1.00 0.00 - 0.00%
1.3.6 ELIMINACION DE MATERIAL EXCEDENTE m3 135.47 27.28 3,695.62 135.47 3,696 - 135.47 3,696 1.00 0.00 - 0.00%
1.4 CONCRETO SIMPLE
1.4.1 CONCRETO SOLADO (C:H 1:12; e=0.05 m) m2 64.20 27.54 1,768.07 64.20 1,768 - 64.20 1,768 1.00 0.00 - 0.00%
1.4.2 CONCRETO CICLOPEO CIMIENTO CORRIDO MEZCLA 1:12 + 30% P.G. m3 5.92 186.32 1,103.01 5.92 1,103 - 5.92 1,103 1.00 0.00 - 0.00%
1.4.3 CONCRETO FALSOPISO (f'c= 140 kg/cm2; e=0.10 m) m2 73.27 26.06 1,909.42 73.27 1,909 - 73.27 1,909 1.00 0.00 - 0.00%
1.4.4 CONCRETO GRADAS f'c=140 kg/cm2 m3 0.36 298.22 107.36 0.36 107 - 0.36 107 1.00 0.00 - 0.00%
1.4.5 ENCOFRADO GRADAS m 1.43 25.04 35.81 1.43 36 - 1.43 36 1.00 0.00 - 0.00%
1.5 CONCRETO ARMADO
1.5.1 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 26.57 314.68 8,361.05 26.57 8,361 - 26.57 8,361 1.00 0.00 - 0.00%
1.5.2 ACERO ZAPATAS fy= 4200 kg/cm2 kg 1,340.65 4.39 5,885.45 1340.65 5,885 - 1,340.65 5,885 1.00 0.00 - 0.00%
1.5.3 CONCRETO VIGAS DE CIMENTACION f'c=210 kg/cm2 m3 8.39 335.81 2,817.45 8.39 2,817 - 8.39 2,817 1.00 0.00 - 0.00%
1.5.4 ENCOFRADO EN VIGA DE CIMENTACION m2 47.05 82.65 3,888.68 47.05 3,889 - 47.05 3,889 1.00 0.00 - 0.00%
1.5.5 ACERO VIGAS CIMENTACIÓN fy= 4200 kg/cm2 kg 834.03 4.35 3,628.03 834.03 3,628 - 834.03 3,628 1.00 0.00 - 0.00%
1.5.6 CONCRETO SOBRECIMIENTO f'c=210 kg/cm2 m3 8.01 305.02 2,443.21 8.01 2,443 - 8.01 2,443 1.00 0.00 - 0.00%
1.5.7 ACERO SOBRECIMIENTO FY= 4200 kg/cm2 kg 297.58 4.35 1,294.47 297.58 1,294 - 297.58 1,294 1.00 0.00 - 0.00%
1.5.8 ENCOFRADO DE SOBRECIMIENTO h=0.60 m m2 78.99 51.43 4,062.46 78.99 4,062 - 78.99 4,062 1.00 0.00 - 0.00%
1.5.9 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 16.39 348.10 5,705.36 16.39 5,705 - 16.39 5,705 1.00 0.00 - 0.00%
1.5.10 LADRILLO LOSA ALIGERADA (0.30*0.30*0.15) mll 1.56 1,916.24 2,989.33 1.56 2,989 - 1.56 2,989 1.00 0.00 - 0.00%
1.5.11 ENCOFRADO LOSA ALIGERADA m2 187.32 56.88 10,654.76 187.32 10,655 - 187.32 10,655 1.00 0.00 - 0.00%
1.5.12 ACERO LOSA ALIGERADA fy= 4200 kg/cm2 kg 1,152.39 4.35 5,012.90 1152.39 5,013 - 1,152.39 5,013 1.00 0.00 - 0.00%
1.5.13 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 16.23 455.44 7,391.79 16.23 7,392 - 16.23 7,392 1.00 0.00 - 0.00%
1.5.14 ACERO COLUMNAS fy= 4200 kg/cm2 kg 2,773.30 4.32 11,980.66 2773.30 11,981 - 2,773.30 11,981 1.00 0.00 - 0.00%
1.5.15 ENCOFRADO CARAVISTA COLUMNAS m2 186.81 79.70 14,888.76 186.81 14,889 - 186.81 14,889 1.00 0.00 - 0.00%
1.5.16 CONCRETO COLUMNETAS f'c=210 kg/cm2 m3 9.24 444.93 4,111.15 6.93 3,083 2.31 1,028 9.24 4,111 1.00 0.00 - 0.00%
1.5.17 ENCOFRADO COLUMNETAS m2 126.28 60.56 7,647.52 94.71 5,736 31.57 1,912 126.28 7,648 1.00 0.00 - 0.00%
1.5.18 ACERO COLUMNETAS fy= 4200 kg/cm2 kg 1,151.54 4.51 5,193.45 1151.54 5,193 - 1,151.54 5,193 1.00 0.00 - 0.00%
1.5.19 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.91 373.32 6,312.84 16.91 6,313 - 16.91 6,313 1.00 0.00 - 0.00%
1.5.20 ENCOFRADO DE VIGAS m2 100.50 70.68 7,103.34 100.50 7,103 - 100.50 7,103 1.00 0.00 - 0.00%
1.5.21 ACERO VIGAS fy= 4200 kg/cm2 kg 2,256.76 4.35 9,816.91 2256.76 9,817 - 2,256.76 9,817 1.00 0.00 - 0.00%
1.5.22 CONCRETO VIGAS DE BORDE f'c=210 kg/cm2 m3 2.32 330.08 765.79 2.32 766 - 2.32 766 1.00 0.00 - 0.00%
1.5.23 ENCOFRADO DE VIGA DE BORDE Y FRISO h= 0.20 m2 45.09 40.13 1,809.46 45.09 1,809 - 45.09 1,809 1.00 0.00 - 0.00%
1.5.24 ACERO VIGAS DE BORDE fy= 4200 kg/cm2 kg 336.19 4.32 1,452.34 336.19 1,452 - 336.19 1,452 1.00 0.00 - 0.00%
1.5.25 CONCRETO VIGAS COLLARÍN f'c=210 kg/cm2 m3 3.98 356.42 1,418.55 2.99 1,064 1.00 355 3.98 1,419 1.00 0.00 - 0.00%
1.5.26 ENCOFRADO DE VIGA COLLARÍN m2 44.66 40.29 1,799.35 33.50 1,350 11.17 450 44.66 1,799 1.00 0.00 - 0.00%
1.5.27 ACERO VIGA COLLARÍN fy= 4200 kg/cm2 kg 557.50 4.32 2,408.40 446.00 1,927 111.50 482 557.50 2,408 1.00 0.00 - 0.00%
1.5.28 CONCRETO ESCALERAS f´c=210 kg/cm2 m3 4.03 442.60 1,783.68 4.03 1,784 - 4.03 1,784 1.00 0.00 - 0.00%
1.5.29 ENCOFRADO NORMAL EN ESCALERA m2 29.59 89.88 2,659.55 29.59 2,660 - 29.59 2,660 1.00 0.00 - 0.00%
1.5.30 ACERO ESCALERA fy= 4200 kg/cm2 kg 381.22 4.32 1,646.87 381.22 1,647 - 381.22 1,647 1.00 0.00 - 0.00%
1.5.31 JUNTA DE DILATACION e=1/4" m 331.15 35.30 11,689.60 165.58 5,845 165.58 5,845 331.15 11,690 1.00 0.00 - 0.00%
1.5.32 CONCRETO PREMEZCLADO CISTERNA f'c=280 kg/cm2 (aditivo plastificante) m3 1.34 277.20 371.45 1.34 371 - 1.34 371 1.00 0.00 - 0.00%
1.5.33 ENCOFRADO METALICO CISTERNA m2 8.70 36.12 314.24 8.70 314 - 8.70 314 1.00 0.00 - 0.00%
1.5.34 ACERO CISTERNA fy= 4200 kg/cm2 kg 93.51 4.32 403.96 93.51 404 - 93.51 404 1.00 0.00 - 0.00%
1.5.35 CONCRETO PREMEZCLADO PISCINA f'c=280 kg/cm2 (aditivo plastificante) m3 6.30 277.20 1,746.36 6.30 1,746 - 6.30 1,746 1.00 0.00 - 0.00%
1.5.36 ENCOFRADO METALICO PISCINA m2 45.24 29.96 1,355.39 45.24 1,355 - 45.24 1,355 1.00 0.00 - 0.00%
1.5.37 ACERO PISCINA fy= 4200 kg/cm2 kg 361.28 4.32 1,560.73 361.28 1,561 - 361.28 1,561 1.00 0.00 - 0.00%
2 ARQUITECTURA
MUROS Y TABIQUES DE ALBAÑILERÍA
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO SOGA; C:A 1:4 (J= 1.5 cm) m2 309.30 55.60 17,197.08 309.30 17,197 - 309.30 17,197 1.00 0.00 - 0.00%
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO CABEZA; C:A 1:4 (J= 1.5 cm) m2 25.84 91.36 2,360.74 25.84 2,361 - 25.84 2,361 1.00 0.00 - 0.00%
REVOQUES Y REVESTIMIENTOS
TARRAJEO RAYADO PRIMARIO (C:A 1:4; e= 2 cm) m2 26.51 21.20 562.01 0.00 - 26.51 562 26.51 562 1.00 0.00 - 0.00%
TARRAJEO EN INTERIORES (C:A 1:5; e= 2cm) m2 293.28 22.53 6,607.60 0.00 - 293.28 6,608 293.28 6,608 1.00 0.00 - 0.00%
TARRAJEO EN COLUMNAS (C:A 1:5; e= 2 cm) m2 178.20 32.14 5,727.35 89.10 2,864 89.10 2,864 178.20 5,727 1.00 0.00 - 0.00%
TARRAJEO EN VIGAS (C:A 1:5; e= 2 cm) m2 136.57 36.15 4,937.01 68.29 2,469 68.29 2,469 136.57 4,937 1.00 0.00 - 0.00%
TARRAJEO CON INPERMEABILIZANTE (C:A 1:3; e= 2 cm) m2 36.76 25.55 939.22 36.76 939 - 36.76 939 1.00 0.00 - 0.00%
VESTIDURA DE DERRAMES (C:A 1:5; e= 2 cm) m 192.83 13.43 2,589.71 0.00 - 192.83 2,590 192.83 2,590 1.00 0.00 - 0.00%
TARRAJEO DE DUCTOS (C:A 1:5; e= 2 cm) m2 14.64 36.13 528.94 7.32 264 7.32 264 14.64 529 1.00 0.00 - 0.00%
BRUÑAS 5 mm*5 mm m 514.31 8.97 4,613.36 0.00 - 514.31 4,613 514.31 4,613 1.00 0.00 - 0.00%
TARRAJEO EN FONDO DE ESCALERAS (C:A 1:5; e= 2 cm) m2 15.80 34.87 550.95 3.95 138 11.85 413 15.80 551 1.00 0.00 - 0.00%
PREPARACIÓN DE GRADAS DE CONCRETO (C:A 1:4; e= 2 cm) m 17.00 24.70 419.90 4.25 105 12.75 315 17.00 420 1.00 0.00 - 0.00%
PREPARACIÓN DE DESCANSOS (C:A 1;4; e= 2 cm) m2 3.10 20.60 63.86 1.55 32 1.55 32 3.10 64 1.00 0.00 - 0.00%
GRADAS - VINILO 1.5 mm m 20.10 45.95 923.60 10.05 462 10.05 462 20.10 924 1.00 0.00 - 0.00%
ENCHAPE GRESITE NIEBLA AZUL 0.33*0.33 m2 36.76 90.25 3,317.59 0.00 - 36.76 3,318 36.76 3,318 1.00 0.00 - 0.00%
ENCHAPE TABLAS MACHIHEMBRADAS m2 8.40 45.32 380.69 0.00 - 8.40 381 8.40 381 1.00 0.00 - 0.00%
CIELO RASOS
CIELORRASO CON MEZCLA C:A 1:5; e= 1.5 cm m2 187.32 19.21 3,598.42 140.49 2,699 46.83 900 187.32 3,598 1.00 0.00 - 0.00%
PISOS Y PAVIMENTOS
CONTRAPISO C:4 1:3 e= 2'' m2 81.10 31.29 2,537.62 81.10 2,538 - 81.10 2,538 1.00 0.00 - 0.00%
PISO DE PORCELANATO NAVIA ACERO 0.30*0.90; ALTO TRÁNSITO e= 12 mm m2 24.98 84.97 2,122.55 0.00 - 24.98 2,123 24.98 2,123 1.00 0.00 - 0.00%
PISO DE PORCELANATO TEXAS 0.15*0.90; ALTO TRÁNSITO e= 12 mm m2 11.74 155.42 1,824.63 0.00 - 11.74 1,825 11.74 1,825 1.00 0.00 - 0.00%
PISO DE PORCELANATO MADERA 0.23*1.20; MEDIO TRÁNSITO e= 8 mm m2 35.98 93.93 3,379.60 0.00 - 35.98 3,380 35.98 3,380 1.00 0.00 - 0.00%
PISO DE TABLAS MACHIHEMBRADAS CHANUL m2 8.40 89.56 752.30 0.00 - 8.40 752 8.40 752 1.00 0.00 - 0.00%
PISO DE CEMENTO PULIDO e= 2'' S/COLOREAR m2 146.00 24.11 3,520.06 109.50 2,640 36.50 880 146.00 3,520 1.00 0.00 - 0.00%
ACABADO ALISADO S/COLOREAR Y S/BRUÑADO m2 146.00 10.06 1,468.76 109.50 1,102 36.50 367 146.00 1,469 1.00 0.00 - 0.00%
SARDINEL - LADRILLO PANDERETA (0.09*0.11*0.23); APAREJO DE CANTO (C:A 1:5; J= 2 cm) m 47.90 9.39 449.78 47.90 450 - 47.90 450 1.00 0.00 - 0.00%
ZÓCALOS Y CONTRAZÓCALOS
ZOCALO CERAMICO AVELLANO 45 X 45 m2 26.51 48.37 1,282.29 0.00 - 26.51 1,282 26.51 1,282 1.00 0.00 - 0.00%
CONTRAZOCALO CERÁMICO MARMOLIZADO h=0.095 m m 101.10 15.43 1,559.97 0.00 - 101.10 1,560 101.10 1,560 1.00 0.00 - 0.00%
CARPINTERIA DE MADERA
PUERTA PARA GARAJE EN MADERA CEDRO und 1.00 6,599.25 6,599.25 0.00 - 1.00 6,599 1.00 6,599 1.00 0.00 - 0.00%
PUERTA PRINCIPAL 1 ENCHAPADA und 1.00 574.40 574.40 0.00 - 1.00 574 1.00 574 1.00 0.00 - 0.00%
PUERTA INTERIOR 2 ENCHAPADA und 1.00 393.90 393.90 0.00 - 1.00 394 1.00 394 1.00 0.00 - 0.00%
PUERTA INTERIOR 3 Y 8 ENCHAPADA und 2.00 381.19 762.38 0.00 - 2.00 762 2.00 762 1.00 0.00 - 0.00%
PUERTA INTERIOR 5 Y 6 ENCHAPADA und 8.00 368.48 2,947.84 0.00 - 8.00 2,948 8.00 2,948 1.00 0.00 - 0.00%
PUERTA INTERIOR 7 ENCHAPADA und 2.00 393.90 787.80 0.00 - 2.00 788 2.00 788 1.00 0.00 - 0.00%
VENTANA 1 und 1.00 184.87 184.87 0.00 - 1.00 185 1.00 185 1.00 0.00 - 0.00%
VENTANA 2, 3 Y 5 und 3.00 167.92 503.76 0.00 - 3.00 504 3.00 504 1.00 0.00 - 0.00%
VENTANA 4 Y 7 und 2.00 150.97 301.94 0.00 - 2.00 302 2.00 302 1.00 0.00 - 0.00%
MAMPARA 1 und 1.00 716.96 716.96 0.00 - 1.00 717 1.00 717 1.00 0.00 - 0.00%
MAMPARA 2 und 1.00 214.60 214.60 0.00 - 1.00 215 1.00 215 1.00 0.00 - 0.00%
MAMPARA 3 und 1.00 214.60 214.60 0.00 - 1.00 215 1.00 215 1.00 0.00 - 0.00%
MAMPARA 4 und 2.00 600.50 1,201.00 0.00 - 2.00 1,201 2.00 1,201 1.00 0.00 - 0.00%
MAMPARA 5 und 1.00 197.65 197.65 0.00 - 1.00 198 1.00 198 1.00 0.00 - 0.00%
MAMPARA 6 und 1.00 231.55 231.55 0.00 - 1.00 232 1.00 232 1.00 0.00 - 0.00%
CARPINTERIA METALICA
BARANDA DE FIERRO EN ESCALERA m 11.15 482.58 5,380.77 0.00 - 11.15 5,381 11.15 5,381 1.00 0.00 - 0.00%
ESCALERA DE GATO und 1.00 868.36 868.36 0.00 - 1.00 868 1.00 868 1.00 0.00 - 0.00%
VIDRIOS, CRISTALES Y SIMILARES
VENTANA - SISTEMA DIRECTO CON VIDRIO CRUDO e= 8 mm m2 5.84 125.00 730.00 0.00 - - 0.00 - 0.00 5.84 730 100.00%
MAMPARA EN CRISTAL TEMPLADO DE 10 mm m2 64.67 200.73 12,981.21 0.00 - 32.34 6,491 32.34 6,491 0.50 32.34 6,491 50.00%
PINTURAS
PINTURA LATEX EN CIELO RASO, VIGA Y VOLADOS m2 338.52 8.33 2,819.87 0.00 - 338.52 2,820 338.52 2,820 1.00 0.00 - 0.00%
PINTURA LATEX EN MUROS, COLUMNAS Y DERRAMES m2 59.59 7.04 419.51 0.00 - 59.59 420 59.59 420 1.00 0.00 - 0.00%
PINTURA ESMALTE EN MUROS, COLUMNAS Y DERRAMES m2 134.43 7.68 1,032.42 0.00 - 134.43 1,032 134.43 1,032 1.00 0.00 - 0.00%
PINTURA OLEOMATE EN MUROS, COLUMNAS Y DERRAMES m2 18.74 8.03 150.48 0.00 - 18.74 150 18.74 150 1.00 0.00 - 0.00%
EMPASTADO MICROCEMENTO EN MUROS, COLUMNAS Y DERRAMES m2 72.72 29.26 2,127.79 0.00 - 72.72 2,128 72.72 2,128 1.00 0.00 - 0.00%
PINTURA DE CONTRAZÓCALOS Y BARANDAS DE ACERO LIVIANO m 379.10 7.94 3,010.05 0.00 - 189.55 1,505 189.55 1,505 0.50 189.55 1,505 50.00%
VARIOS, LIMPIEZA Y JARDINERÍA
LIMPIEZA DURANTE LA EJECUCION DE LA OBRA glb 1.00 130.69 130.69 0.75 98 0.25 33 1.00 131 1.00 0.00 - 0.00%
LIMPIEZA FINAL glb 1.00 130.69 130.69 0.00 - - 0.00 - 0.00 1.00 131 100.00%
LIMPIEZA DE VIDRIOS m2 70.51 1.64 115.64 0.00 - - 0.00 - 0.00 70.51 116 100.00%
ENCERADO DE PISOS m2 146.00 5.18 756.28 0.00 - 73.00 378 73.00 378 0.50 73.00 378 50.00%
SEMBRADO DE GRASS m2 10.92 16.99 185.53 0.00 - - 0.00 - 0.00 10.92 186 100.00%
TRABAJOS DE JARDINERÍA pza 48.00 69.64 3,342.72 0.00 - - 0.00 - 0.00 48.00 3,343 100.00%
COSTO DIRECTO (CD) 310,062.40 212,117.65 85,066.39 297,184.05 12,878.35
Gastos Generales (10%) 31,006.24 21,211.77 8,506.64 29,718.41 1,287.84
UTILIDAD (8% ) 31,006.24 21,211.77 8,506.64 29,718.41 1,287.84
SUB TOTAL (VM=VALORIZACION DEL MES) 372,074.88 254,541.19 102,079.67 356,620.87 15,454.03
IGV 18% 66,973.48 45,817.41 18,374.34 64,191.76 2,781.73
TOTAL VALORIZADO S/. 439,048.36 300,358.60 120,454.01 420,812.63 18,235.76

COSTO DIRECTO (CD) 10,070.63


Gastos Generales (10%) 1,007.06
UTILIDAD (8% ) 1,007.06
SUB TOTAL (VM=VALORIZACION DEL MES) 12,084.75
IGV 18% 2,175.26
TOTAL VALORIZADO S/. 14,260.01

COSTO DIRECTO (CD) 74,995.76


Gastos Generales (10%) 7,499.58
UTILIDAD (8% ) 7,499.58
SUB TOTAL (VM=VALORIZACION DEL MES) 89,994.92
IGV 18% 16,199.09
TOTAL VALORIZADO S/. 106,194.01
VALORIZACION DE OBRA N° 03
del 01 Setiembre al 30 Setiembre de 2019

OBRA: Vivienda multifamiliar de 3 niveles


PROPIETARIO: Soberon Monja, Brayan Brandon PLAZO DE EJECUCION: 120 días calendario
CONTRATISTA: USAT VALOR REFERENCIAL Con IGV
RESIDENTE: Soberon Monja, Brayan Brandon PRESUPUESTO CONTRATADO: Con IGV
SUPERVISOR Ing. Cachay Lazo, César Eduardo
UBICACIÓN: Chiclayo
FECHA: Saturday, June 01, 2019

AVANCE
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
PARTIDA DESCRIPCION
Valorizado Metrado Valorizado Valorizado Valorizado
Und. Metrado P. Unit. Presup. Metrado Metrado % Metrado %
S/. S/. S/. S/.
1 ESTRUCTURAS
1.1 OBRAS PROVISIONALES
1.1.1 CASETA Y ALMACÉN DE GUARDIANÍA m2 18.00 44.37 798.66 18.00 799 - 18.00 799 1.00 0.00 - 0.00%
1.1.2 CERCO C/ PANELES DE TRIPLAY m2 60.90 29.53 1,798.38 60.90 1,798 - 60.90 1,798 1.00 0.00 - 0.00%
1.2 OBRAS PRELIMINARES
1.2.1 LIMPIEZA DEL TERRENO MANUAL m2 104.65 3.79 396.62 104.65 397 - 104.65 397 1.00 0.00 - 0.00%
1.2.2 TRAZO, NIVELES Y REPLANTEO m2 104.65 3.75 392.44 104.65 392 - 104.65 392 1.00 0.00 - 0.00%
1.3 MOVIMIENTO DE TIERRAS
1.3.1 EXCAVACIÓN SIMPLE EN TERRENO NATURAL m3 104.21 59.50 6,200.50 104.21 6,201 - 104.21 6,201 1.00 0.00 - 0.00%
1.3.2 EXCAVACIÓN SIMPLE EN MATERIAL DE PRÉSTAMO m3 3.67 37.19 136.49 3.67 136 - 3.67 136 1.00 0.00 - 0.00%
1.3.3 CORTE DE TERRENO NATURAL h = 0.50 m m3 6.00 18.60 111.60 6.00 112 - 6.00 112 1.00 0.00 - 0.00%
1.3.4 RELLENO CON MATERIAL DE PRÉSTAMO m3 57.44 47.51 2,728.97 57.44 2,729 - 57.44 2,729 1.00 0.00 - 0.00%
1.3.5 NIVELACION INTERIOR Y APISONADO m2 79.90 3.43 274.06 79.90 274 - 79.90 274 1.00 0.00 - 0.00%
1.3.6 ELIMINACION DE MATERIAL EXCEDENTE m3 135.47 27.28 3,695.62 135.47 3,696 - 135.47 3,696 1.00 0.00 - 0.00%
1.4 CONCRETO SIMPLE
1.4.1 CONCRETO SOLADO (C:H 1:12; e=0.05 m) m2 64.20 27.54 1,768.07 64.20 1,768 - 64.20 1,768 1.00 0.00 - 0.00%
1.4.2 CONCRETO CICLOPEO CIMIENTO CORRIDO MEZCLA 1:12 + 30% P.G. m3 5.92 186.32 1,103.01 5.92 1,103 - 5.92 1,103 1.00 0.00 - 0.00%
1.4.3 CONCRETO FALSOPISO (f'c= 140 kg/cm2; e=0.10 m) m2 73.27 26.06 1,909.42 73.27 1,909 - 73.27 1,909 1.00 0.00 - 0.00%
1.4.4 CONCRETO GRADAS f'c=140 kg/cm2 m3 0.36 298.22 107.36 0.36 107 - 0.36 107 1.00 0.00 - 0.00%
1.4.5 ENCOFRADO GRADAS m 1.43 25.04 35.81 1.43 36 - 1.43 36 1.00 0.00 - 0.00%
1.5 CONCRETO ARMADO
1.5.1 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 26.57 314.68 8,361.05 26.57 8,361 - 26.57 8,361 1.00 0.00 - 0.00%
1.5.2 ACERO ZAPATAS fy= 4200 kg/cm2 kg 1,340.65 4.39 5,885.45 1340.65 5,885 - 1,340.65 5,885 1.00 0.00 - 0.00%
1.5.3 CONCRETO VIGAS DE CIMENTACION f'c=210 kg/cm2 m3 8.39 335.81 2,817.45 8.39 2,817 - 8.39 2,817 1.00 0.00 - 0.00%
1.5.4 ENCOFRADO EN VIGA DE CIMENTACION m2 47.05 82.65 3,888.68 47.05 3,889 - 47.05 3,889 1.00 0.00 - 0.00%
1.5.5 ACERO VIGAS CIMENTACIÓN fy= 4200 kg/cm2 kg 834.03 4.35 3,628.03 834.03 3,628 - 834.03 3,628 1.00 0.00 - 0.00%
1.5.6 CONCRETO SOBRECIMIENTO f'c=210 kg/cm2 m3 8.01 305.02 2,443.21 8.01 2,443 - 8.01 2,443 1.00 0.00 - 0.00%
1.5.7 ACERO SOBRECIMIENTO FY= 4200 kg/cm2 kg 297.58 4.35 1,294.47 297.58 1,294 - 297.58 1,294 1.00 0.00 - 0.00%
1.5.8 ENCOFRADO DE SOBRECIMIENTO h=0.60 m m2 78.99 51.43 4,062.46 78.99 4,062 - 78.99 4,062 1.00 0.00 - 0.00%
1.5.9 CONCRETO LOSA ALIGERADA f'c= 210 kg/cm2 m3 16.39 348.10 5,705.36 16.39 5,705 - 16.39 5,705 1.00 0.00 - 0.00%
1.5.10 LADRILLO LOSA ALIGERADA (0.30*0.30*0.15) mll 1.56 1,916.24 2,989.33 1.56 2,989 - 1.56 2,989 1.00 0.00 - 0.00%
1.5.11 ENCOFRADO LOSA ALIGERADA m2 187.32 56.88 10,654.76 187.32 10,655 - 187.32 10,655 1.00 0.00 - 0.00%
1.5.12 ACERO LOSA ALIGERADA fy= 4200 kg/cm2 kg 1,152.39 4.35 5,012.90 1152.39 5,013 - 1,152.39 5,013 1.00 0.00 - 0.00%
1.5.13 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 16.23 455.44 7,391.79 16.23 7,392 - 16.23 7,392 1.00 0.00 - 0.00%
1.5.14 ACERO COLUMNAS fy= 4200 kg/cm2 kg 2,773.30 4.32 11,980.66 2773.30 11,981 - 2,773.30 11,981 1.00 0.00 - 0.00%
1.5.15 ENCOFRADO CARAVISTA COLUMNAS m2 186.81 79.70 14,888.76 186.81 14,889 - 186.81 14,889 1.00 0.00 - 0.00%
1.5.16 CONCRETO COLUMNETAS f'c=210 kg/cm2 m3 9.24 444.93 4,111.15 9.24 4,111 - 9.24 4,111 1.00 0.00 - 0.00%
1.5.17 ENCOFRADO COLUMNETAS m2 126.28 60.56 7,647.52 126.28 7,648 - 126.28 7,648 1.00 0.00 - 0.00%
1.5.18 ACERO COLUMNETAS fy= 4200 kg/cm2 kg 1,151.54 4.51 5,193.45 1151.54 5,193 - 1,151.54 5,193 1.00 0.00 - 0.00%
1.5.19 CONCRETO VIGAS f'c=210 kg/cm2 m3 16.91 373.32 6,312.84 16.91 6,313 - 16.91 6,313 1.00 0.00 - 0.00%
1.5.20 ENCOFRADO DE VIGAS m2 100.50 70.68 7,103.34 100.50 7,103 - 100.50 7,103 1.00 0.00 - 0.00%
1.5.21 ACERO VIGAS fy= 4200 kg/cm2 kg 2,256.76 4.35 9,816.91 2256.76 9,817 - 2,256.76 9,817 1.00 0.00 - 0.00%
1.5.22 CONCRETO VIGAS DE BORDE f'c=210 kg/cm2 m3 2.32 330.08 765.79 2.32 766 - 2.32 766 1.00 0.00 - 0.00%
1.5.23 ENCOFRADO DE VIGA DE BORDE Y FRISO h= 0.20 m2 45.09 40.13 1,809.46 45.09 1,809 - 45.09 1,809 1.00 0.00 - 0.00%
1.5.24 ACERO VIGAS DE BORDE fy= 4200 kg/cm2 kg 336.19 4.32 1,452.34 336.19 1,452 - 336.19 1,452 1.00 0.00 - 0.00%
1.5.25 CONCRETO VIGAS COLLARÍN f'c=210 kg/cm2 m3 3.98 356.42 1,418.55 3.98 1,419 - 3.98 1,419 1.00 0.00 - 0.00%
1.5.26 ENCOFRADO DE VIGA COLLARÍN m2 44.66 40.29 1,799.35 44.66 1,799 - 44.66 1,799 1.00 0.00 - 0.00%
1.5.27 ACERO VIGA COLLARÍN fy= 4200 kg/cm2 kg 557.50 4.32 2,408.40 557.50 2,408 - 557.50 2,408 1.00 0.00 - 0.00%
1.5.28 CONCRETO ESCALERAS f´c=210 kg/cm2 m3 4.03 442.60 1,783.68 4.03 1,784 - 4.03 1,784 1.00 0.00 - 0.00%
1.5.29 ENCOFRADO NORMAL EN ESCALERA m2 29.59 89.88 2,659.55 29.59 2,660 - 29.59 2,660 1.00 0.00 - 0.00%
1.5.30 ACERO ESCALERA fy= 4200 kg/cm2 kg 381.22 4.32 1,646.87 381.22 1,647 - 381.22 1,647 1.00 0.00 - 0.00%
1.5.31 JUNTA DE DILATACION e=1/4" m 331.15 35.30 11,689.60 331.15 11,690 - 331.15 11,690 1.00 0.00 - 0.00%
1.5.32 CONCRETO PREMEZCLADO CISTERNA f'c=280 kg/cm2 (aditivo plastificante) m3 1.34 277.20 371.45 1.34 371 - 1.34 371 1.00 0.00 - 0.00%
1.5.33 ENCOFRADO METALICO CISTERNA m2 8.70 36.12 314.24 8.70 314 - 8.70 314 1.00 0.00 - 0.00%
1.5.34 ACERO CISTERNA fy= 4200 kg/cm2 kg 93.51 4.32 403.96 93.51 404 - 93.51 404 1.00 0.00 - 0.00%
1.5.35 CONCRETO PREMEZCLADO PISCINA f'c=280 kg/cm2 (aditivo plastificante) m3 6.30 277.20 1,746.36 6.30 1,746 - 6.30 1,746 1.00 0.00 - 0.00%
1.5.36 ENCOFRADO METALICO PISCINA m2 45.24 29.96 1,355.39 45.24 1,355 - 45.24 1,355 1.00 0.00 - 0.00%
1.5.37 ACERO PISCINA fy= 4200 kg/cm2 kg 361.28 4.32 1,560.73 361.28 1,561 - 361.28 1,561 1.00 0.00 - 0.00%
2 ARQUITECTURA
MUROS Y TABIQUES DE ALBAÑILERÍA
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO SOGA; C:A 1:4 (J= 1.5 cm) m2 309.30 55.60 17,197.08 309.30 17,197 - 309.30 17,197 1.00 0.00 - 0.00%
MURO DE LADRILLO KK 18H (0.09*0.13*0.24); APAREJO CABEZA; C:A 1:4 (J= 1.5 cm) m2 25.84 91.36 2,360.74 25.84 2,361 - 25.84 2,361 1.00 0.00 - 0.00%
REVOQUES Y REVESTIMIENTOS
TARRAJEO RAYADO PRIMARIO (C:A 1:4; e= 2 cm) m2 26.51 21.20 562.01 26.51 562 - 26.51 562 1.00 0.00 - 0.00%
TARRAJEO EN INTERIORES (C:A 1:5; e= 2cm) m2 293.28 22.53 6,607.60 293.28 6,608 - 293.28 6,608 1.00 0.00 - 0.00%
TARRAJEO EN COLUMNAS (C:A 1:5; e= 2 cm) m2 178.20 32.14 5,727.35 178.20 5,727 - 178.20 5,727 1.00 0.00 - 0.00%
TARRAJEO EN VIGAS (C:A 1:5; e= 2 cm) m2 136.57 36.15 4,937.01 136.57 4,937 - 136.57 4,937 1.00 0.00 - 0.00%
TARRAJEO CON INPERMEABILIZANTE (C:A 1:3; e= 2 cm) m2 36.76 25.55 939.22 36.76 939 - 36.76 939 1.00 0.00 - 0.00%
VESTIDURA DE DERRAMES (C:A 1:5; e= 2 cm) m 192.83 13.43 2,589.71 192.83 2,590 - 192.83 2,590 1.00 0.00 - 0.00%
TARRAJEO DE DUCTOS (C:A 1:5; e= 2 cm) m2 14.64 36.13 528.94 14.64 529 - 14.64 529 1.00 0.00 - 0.00%
BRUÑAS 5 mm*5 mm m 514.31 8.97 4,613.36 514.31 4,613 - 514.31 4,613 1.00 0.00 - 0.00%
TARRAJEO EN FONDO DE ESCALERAS (C:A 1:5; e= 2 cm) m2 15.80 34.87 550.95 15.80 551 - 15.80 551 1.00 0.00 - 0.00%
PREPARACIÓN DE GRADAS DE CONCRETO (C:A 1:4; e= 2 cm) m 17.00 24.70 419.90 17.00 420 - 17.00 420 1.00 0.00 - 0.00%
PREPARACIÓN DE DESCANSOS (C:A 1;4; e= 2 cm) m2 3.10 20.60 63.86 3.10 64 - 3.10 64 1.00 0.00 - 0.00%
GRADAS - VINILO 1.5 mm m 20.10 45.95 923.60 20.10 924 - 20.10 924 1.00 0.00 - 0.00%
ENCHAPE GRESITE NIEBLA AZUL 0.33*0.33 m2 36.76 90.25 3,317.59 36.76 3,318 - 36.76 3,318 1.00 0.00 - 0.00%
ENCHAPE TABLAS MACHIHEMBRADAS m2 8.40 45.32 380.69 8.40 381 - 8.40 381 1.00 0.00 - 0.00%
CIELO RASOS
CIELORRASO CON MEZCLA C:A 1:5; e= 1.5 cm m2 187.32 19.21 3,598.42 187.32 3,598 - 187.32 3,598 1.00 0.00 - 0.00%
PISOS Y PAVIMENTOS
CONTRAPISO C:4 1:3 e= 2'' m2 81.10 31.29 2,537.62 81.10 2,538 - 81.10 2,538 1.00 0.00 - 0.00%
PISO DE PORCELANATO NAVIA ACERO 0.30*0.90; ALTO TRÁNSITO e= 12 mm m2 24.98 84.97 2,122.55 24.98 2,123 - 24.98 2,123 1.00 0.00 - 0.00%
PISO DE PORCELANATO TEXAS 0.15*0.90; ALTO TRÁNSITO e= 12 mm m2 11.74 155.42 1,824.63 11.74 1,825 - 11.74 1,825 1.00 0.00 - 0.00%
PISO DE PORCELANATO MADERA 0.23*1.20; MEDIO TRÁNSITO e= 8 mm m2 35.98 93.93 3,379.60 35.98 3,380 - 35.98 3,380 1.00 0.00 - 0.00%
PISO DE TABLAS MACHIHEMBRADAS CHANUL m2 8.40 89.56 752.30 8.40 752 - 8.40 752 1.00 0.00 - 0.00%
PISO DE CEMENTO PULIDO e= 2'' S/COLOREAR m2 146.00 24.11 3,520.06 146.00 3,520 - 146.00 3,520 1.00 0.00 - 0.00%
ACABADO ALISADO S/COLOREAR Y S/BRUÑADO m2 146.00 10.06 1,468.76 146.00 1,469 - 146.00 1,469 1.00 0.00 - 0.00%
SARDINEL - LADRILLO PANDERETA (0.09*0.11*0.23); APAREJO DE CANTO (C:A 1:5; J= 2 cm) m 47.90 9.39 449.78 47.90 450 - 47.90 450 1.00 0.00 - 0.00%
ZÓCALOS Y CONTRAZÓCALOS
ZOCALO CERAMICO AVELLANO 45 X 45 m2 26.51 48.37 1,282.29 26.51 1,282 - 26.51 1,282 1.00 0.00 - 0.00%
CONTRAZOCALO CERÁMICO MARMOLIZADO h=0.095 m m 101.10 15.43 1,559.97 101.10 1,560 - 101.10 1,560 1.00 0.00 - 0.00%
CARPINTERIA DE MADERA
PUERTA PARA GARAJE EN MADERA CEDRO und 1.00 6,599.25 6,599.25 1.00 6,599 - 1.00 6,599 1.00 0.00 - 0.00%
PUERTA PRINCIPAL 1 ENCHAPADA und 1.00 574.40 574.40 1.00 574 - 1.00 574 1.00 0.00 - 0.00%
PUERTA INTERIOR 2 ENCHAPADA und 1.00 393.90 393.90 1.00 394 - 1.00 394 1.00 0.00 - 0.00%
PUERTA INTERIOR 3 Y 8 ENCHAPADA und 2.00 381.19 762.38 2.00 762 - 2.00 762 1.00 0.00 - 0.00%
PUERTA INTERIOR 5 Y 6 ENCHAPADA und 8.00 368.48 2,947.84 8.00 2,948 - 8.00 2,948 1.00 0.00 - 0.00%
PUERTA INTERIOR 7 ENCHAPADA und 2.00 393.90 787.80 2.00 788 - 2.00 788 1.00 0.00 - 0.00%
VENTANA 1 und 1.00 184.87 184.87 1.00 185 - 1.00 185 1.00 0.00 - 0.00%
VENTANA 2, 3 Y 5 und 3.00 167.92 503.76 3.00 504 - 3.00 504 1.00 0.00 - 0.00%
VENTANA 4 Y 7 und 2.00 150.97 301.94 2.00 302 - 2.00 302 1.00 0.00 - 0.00%
MAMPARA 1 und 1.00 716.96 716.96 1.00 717 - 1.00 717 1.00 0.00 - 0.00%
MAMPARA 2 und 1.00 214.60 214.60 1.00 215 - 1.00 215 1.00 0.00 - 0.00%
MAMPARA 3 und 1.00 214.60 214.60 1.00 215 - 1.00 215 1.00 0.00 - 0.00%
MAMPARA 4 und 2.00 600.50 1,201.00 2.00 1,201 - 2.00 1,201 1.00 0.00 - 0.00%
MAMPARA 5 und 1.00 197.65 197.65 1.00 198 - 1.00 198 1.00 0.00 - 0.00%
MAMPARA 6 und 1.00 231.55 231.55 1.00 232 - 1.00 232 1.00 0.00 - 0.00%
CARPINTERIA METALICA
BARANDA DE FIERRO EN ESCALERA m 11.15 482.58 5,380.77 11.15 5,381 - 11.15 5,381 1.00 0.00 - 0.00%
ESCALERA DE GATO und 1.00 868.36 868.36 1.00 868 - 1.00 868 1.00 0.00 - 0.00%
VIDRIOS, CRISTALES Y SIMILARES
VENTANA - SISTEMA DIRECTO CON VIDRIO CRUDO e= 8 mm m2 5.84 125.00 730.00 0.00 - 5.84 730 5.84 730 1.00 0.00 - 0.00%
MAMPARA EN CRISTAL TEMPLADO DE 10 mm m2 64.67 200.73 12,981.21 32.34 6,491 32.34 6,491 64.67 12,981 1.00 0.00 - 0.00%
PINTURAS
PINTURA LATEX EN CIELO RASO, VIGA Y VOLADOS m2 338.52 8.33 2,819.87 338.52 2,820 - 338.52 2,820 1.00 0.00 - 0.00%
PINTURA LATEX EN MUROS, COLUMNAS Y DERRAMES m2 59.59 7.04 419.51 59.59 420 - 59.59 420 1.00 0.00 - 0.00%
PINTURA ESMALTE EN MUROS, COLUMNAS Y DERRAMES m2 134.43 7.68 1,032.42 134.43 1,032 - 134.43 1,032 1.00 0.00 - 0.00%
PINTURA OLEOMATE EN MUROS, COLUMNAS Y DERRAMES m2 18.74 8.03 150.48 18.74 150 - 18.74 150 1.00 0.00 - 0.00%
EMPASTADO MICROCEMENTO EN MUROS, COLUMNAS Y DERRAMES m2 72.72 29.26 2,127.79 72.72 2,128 - 72.72 2,128 1.00 0.00 - 0.00%
PINTURA DE CONTRAZÓCALOS Y BARANDAS DE ACERO LIVIANO m 379.10 7.94 3,010.05 189.55 1,505 189.55 1,505 379.10 3,010 1.00 0.00 - 0.00%
VARIOS, LIMPIEZA Y JARDINERÍA 0.00
LIMPIEZA DURANTE LA EJECUCION DE LA OBRA glb 1.00 130.69 130.69 1.00 131 - 1.00 131 1.00 0.00 - 0.00%
LIMPIEZA FINAL glb 1.00 130.69 130.69 0.00 - 1.00 131 1.00 131 1.00 0.00 - 0.00%
LIMPIEZA DE VIDRIOS m2 70.51 1.64 115.64 0.00 - 70.51 116 70.51 116 1.00 0.00 - 0.00%
ENCERADO DE PISOS m2 146.00 5.18 756.28 73.00 378 73.00 378 146.00 756 1.00 0.00 - 0.00%
SEMBRADO DE GRASS m2 10.92 16.99 185.53 0.00 - 10.92 186 10.92 186 1.00 0.00 - 0.00%
TRABAJOS DE JARDINERÍA pza 48.00 69.64 3,342.72 0.00 - 48.00 3,343 48.00 3,343 1.00 0.00 - 0.00%
COSTO DIRECTO (CD) 310,062.40 297,184.05 12,878.35 310,062.40 0.00
Gastos Generales (10%) 31,006.24 29,718.41 1,287.84 31,006.24 0.00
UTILIDAD (8% ) 31,006.24 29,718.41 1,287.84 31,006.24 0.00
SUB TOTAL (VM=VALORIZACION DEL MES) 372,074.88 356,620.87 15,454.03 372,074.88 0.00
IGV 18% 66,973.48 64,191.76 2,781.73 66,973.48 0.00
TOTAL VALORIZADO S/. 439,048.36 420,812.63 18,235.76 439,048.36 0.00

COSTO DIRECTO (CD) 0.00


Gastos Generales (10%) 0.00
UTILIDAD (8% ) 0.00
SUB TOTAL (VM=VALORIZACION DEL MES) 0.00
IGV 18% 0.00
TOTAL VALORIZADO S/. 0.00

COSTO DIRECTO (CD) 12,878.35


Gastos Generales (10%) 1,287.84
UTILIDAD (8% ) 1,287.84
SUB TOTAL (VM=VALORIZACION DEL MES) 15,454.03
IGV 18% 2,781.73
TOTAL VALORIZADO S/. 18,235.76
FORMULA POLINOMICA - CONTRATO PRINCIPAL
Zona Geográfica = 1
ARQUITECTURA

K= 0.118 Jr/Jo + 0.119 DCr/DCo + 0.070 Cr/Co + 0.169 MQNr/MQNo + 0.234 GUr/GUo
Jan-18
Simbolo IU Concepto Coeficiente Incidencia
Indice Io

J 47 Mano de Obra, inc. Leyes sociales 0.415 100.00% 582.52 582.52


487.20
C 21 Cemento Portalnd tipo I 0.07 83.47% 475.73 397.09
4 Agregado fino 16.53% 545.09 90.10
438.96
LAD 17 Bloque y ladrillo 0.111 50.79% 627.06 318.48
24 Cerámica esmaltada y sin esmaltar 49.21% 244.83 120.48
412.91
DOL 30 Maquinaria y Equipo Nacional 0.152 64.76% 462.02 299.20
51 Perfil de acero liviano 35.24% 322.67 113.71

P 54 Pintura látex 0.014 100.00% 406.6 406.60


652.09
M 43 Madera nacional encofrado y carp. 0.085 83.23% 722.03 600.95
37 Herramienta manual 16.77% 304.98 51.15

GU 39 Indice general de preciso al consumidor 0.153 100.00% 442.87 442.87


Coeficiente de reajuste (K) 1.000

FORMULA POLINOMICA - CONTRATO PRINCIPAL


Zona Geográfica = 1
ESTRUCTURAS

K= 0.118 Jr/Jo + 0.119 DCr/DCo + 0.070 Cr/Co + 0.169 MQNr/MQNo + 0.234 GUr/GUo
Jan-18
Simbolo IU Concepto Coeficiente Incidencia
Indice Io

J 47 Mano de Obra, inc. Leyes sociales 0.359 100.00% 582.52 582.52


482.06
C 21 Cemento Portalnd tipo I 0.177 68.37% 475.73 325.24
17 Bloque y ladrillo 8.16% 627.06 51.19
5 Agregado grueso 23.47% 450.09 105.63

A 3 Acero de construcción corrugado 0.188 100.00% 475.87 475.87


209.22
MI 49 Maquinaria y equipo importado 0.046 48.08% 299.65 144.07
31 Dólar más inflación 17.31% 376.35 65.15
51 Perfil de acero liviano 34.61% 322.67 111.68
825.65
M 43 Madera nacional encofrado y carp. 0.138 85.99% 722.03 620.87
13 Asfalto 14.01% 1461.65 204.78

GU 39 Indice general de preciso al consumidor 0.092 100.00% 442.87 442.87


Coeficiente de reajuste (K) 1.000
Jan-18 Mar-18 Jun-18 Jul-18
Ir Incidencia Indice Ir Incidencia Indice Ir Incidencia Indice Ir

582.520 0.415 582.52 582.52 0.415 582.52 582.52 0.415 582.52 582.52
487.20 0.070 487.96 0.070 487.72 0.070 487.80
397.092 476.04 397.35 476.04 397.35 476.04 397.35
90.103 548.18 90.61 546.69 90.37 547.19 90.45
438.96 0.111 438.22 0.111 436.47 0.110 436.13
318.484 626.79 318.35 622.17 316.00 622.77 316.30
120.481 243.6 119.88 244.80 120.47 243.5 119.83
412.91 0.152 424.37 0.156 433.58 0.160 434.71
299.204 471.87 305.58 479.58 310.58 481.37 311.74
113.709 337.08 118.79 349.06 123.01 348.95 122.97

406.600 0.014 406.6 406.60 0.014 406.6 406.60 0.014 406.6 406.60
652.09 0.085 655.74 0.085 650.28 0.085 654.95
600.946 726.59 604.74 720.1 599.34 725.34 603.70
51.145 304.11 51.00 303.74 50.94 305.61 51.25

442.870 0.153 446.24 446.24 0.154 445.61 445.61 0.154 447.1 448.81
1.000 1.005 1.008

Jan-18 Mar-18 Jun-18 Jul-18


Ir Incidencia Indice Ir Incidencia Indice Ir Incidencia Indice Ir

582.520 0.359 582.52 582.52 0.359 582.52 582.52 0.359 582.52 582.52
482.06 0.177 482.12 0.177 482.58 0.177 482.75
325.242 476.04 325.45 476.04 325.45 476.04 325.45
51.187 626.79 51.16 622.17 50.79 622.77 50.84
105.632 449.53 105.50 453.1 106.34 453.63 106.46

475.870 0.188 506.47 506.47 0.200 508.81 508.81 0.201 512.37 512.37
209.22 0.046 207.29 0.046 209.10 0.046 209.55
144.072 295.18 141.92 298.83 143.68 299.69 144.09
65.146 377.6 65.36 377.94 65.42 378.15 65.46
111.676 337.08 116.66 349.06 120.81 348.95 120.77
825.65 0.138 830.41 0.139 823.99 0.138 828.50
620.874 726.59 624.79 720.1 619.21 725.34 623.72
204.777 1467.65 205.62 1461.65 204.78 1461.65 204.78

442.870 0.092 446.14 446.14 0.093 445.61 445.61 0.093 448.81 448.81
1.000 1.014 1.014
Jul-18 Aug-18 Sep-18
Incidencia Indice Ir Incidencia Indice Ir Incidencia

0.415 602.11 602.11 0.429 602.11 602.11 0.429


0.07 488.07 0.07 488.33 0.07
476.04 397.35 476.04 397.35
548.83 90.72 550.37 90.98
0.11 435.43 0.11 435.10 0.11
621.6 315.711 620.58 315.1926
243.29 119.72 243.66 119.91
0.16 436.34 0.161 439.74 0.162
483.02 312.804 486.67 315.1675
350.57 123.54 353.51 124.58

0.014 408.58 408.58 0.014 408.51 408.51 0.014


0.085 661.02 0.086 670.92 0.087
732.59 609.73 744.41 619.57
305.79 51.28 306.17 51.34

0.155 449.4 449.4 0.155 450.26 450.26 0.156


1.009 1.025 1.028

Jul-18 Aug-18 Sep-18


Incidencia Indice Ir Incidencia Indice Ir Incidencia

0.359 602.11 602.11 0.371 602.11 602.11 0.371


0.177 482.86 0.177 481.04 0.177
476.04 325.45 476.04 325.45
624.6 50.99 620.58 50.66
453.45 106.42 447.09 104.93

0.202 525.48 525.48 0.208 527.89 527.89 0.209


0.046 210.81 0.046 212.14 0.047
302.2 145.298 304.74 146.519
378.47 65.5132 379.12 65.62567
350.57 121.33 353.51 122.35
0.138 853.65 0.143 872.68 0.146
732.59 629.95 744.41 640.12
1596.69 223.70 1660 232.57

0.093 449.4 449.4 0.093 450.26 450.26 0.094


1.015 1.038 1.044
FECHA PRESUPUESTO Thursday, January 10, 2019
CONTRATO Wednesday, March 20, 2019
INICIO DE OBRA Saturday, June 01, 2019
I.G.V. 18%
% DE ADELANTO 10%
ADELANTO (10%) S/.37,207.49
MONTO DEL CONTRATO S/.372,074.88

FECHA MONTO
VALORIZACIÓN ESPECIALIDAD
INICIO FIN PARCIAL TOTAL
Estructuras S/.64,272.45
1 6/1/2019 6/30/2019 S/.64,311.66
Arquitectura S/.39.21

FECHA MONTO
VALORIZACIÓN ESPECIALIDAD
INICIO FIN PARCIAL TOTAL
Estructuras S/.112,135.87
2 7/1/2019 7/31/2019 S/.112,175.08
Arquitectura S/.39.21

FECHA MONTO
VALORIZACIÓN ESPECIALIDAD
INICIO FIN PARCIAL TOTAL
Estructuras S/.34,505.68
3 8/1/2019 8/31/2019 S/.78,054.43
Arquitectura S/.43,548.75

FECHA MONTO
VALORIZACIÓN ESPECIALIDAD
INICIO FIN PARCIAL TOTAL
Estructuras S/.12,084.75
4 9/1/2019 31/09/2019 S/.102,079.67
Arquitectura S/.89,994.92

FECHA MONTO
VALORIZACIÓN ESPECIALIDAD
INICIO FIN PARCIAL TOTAL
Estructuras S/.0.00
5 10/1/2019 10/10/2019 S/.15,454.03
Arquitectura S/.15,454.03
REAJUSTE DEDUCCIÓN
VALORIZACIÓN BRUTA (VB)
K R = V*(K - 1) Ka K-Ka (AD*V)/(MC*Ka) D
1.014 S/.899.81 1.014 0.000 S/.6,338.51 S/.0.0000 S/.65,172.26
1.008 S/.0.31 1.008 0 S/.3.89 S/.0.0000 S/.39.52

REAJUSTE DEDUCCIÓN
VALORIZACIÓN BRUTA (VB)
K R = V*(K - 1) Ka K-Ka (AD*V)/(MC*Ka) D
1.015 S/.1,682.04 1.014 0.001 S/.11,058.76 S/.11.0588 S/.113,806.85
1.009 S/.0.35 1.008 0.001 S/.3.89 S/.0.0039 S/.39.56

REAJUSTE DEDUCCIÓN
VALORIZACIÓN BRUTA (VB)
K R = V*(K - 1) Ka K-Ka (AD*V)/(MC*Ka) D
1.038 S/.1,311.22 1.014 0.024 S/.3,402.93 S/.81.6702 S/.35,735.23
1.025 S/.1,088.72 1.008 0.017 S/.4,320.31 S/.73.4453 S/.44,564.02

REAJUSTE DEDUCCIÓN
VALORIZACIÓN BRUTA (VB)
K R = V*(K - 1) Ka K-Ka (AD*V)/(MC*Ka) D
1.044 S/.531.73 1.014 0.030 S/.1,191.79 S/.35.7537 S/.12,580.73
1.028 S/.2,519.86 1.008 0.02 S/.8,928.07 S/.178.5613 S/.92,336.22

REAJUSTE DEDUCCIÓN
VALORIZACIÓN BRUTA (VB)
K R = V*(K - 1) Ka K-Ka (AD*V)/(MC*Ka) D
1.044 S/.0.00 1.014 0.030 S/.0.00 S/.0.0000 S/.0.00
1.028 S/.432.71 1.008 0.02 S/.1,533.14 S/.30.6628 S/.15,856.08
VALORIZACIÓN TOTAL A
ALORIZACIÓN BRUTA (VB) AMORTIZACIÓN IGV
NETA (VN) COBRAR

S/.65,211.79 -S/.6,431.17 S/.58,780.62 S/.10,580.51 S/.69,361.13

VALORIZACIÓN TOTAL A
ALORIZACIÓN BRUTA (VB) AMORTIZACIÓN IGV
NETA (VN) COBRAR
S/.113,846.41 -S/.11,217.51 S/.102,628.90 S/.18,473.20 S/.121,102.10

VALORIZACIÓN TOTAL A
ALORIZACIÓN BRUTA (VB) AMORTIZACIÓN IGV
NETA (VN) COBRAR
S/.80,299.25 -S/.7,805.44 S/.72,493.81 S/.13,048.89 S/.85,542.69

VALORIZACIÓN TOTAL A
ALORIZACIÓN BRUTA (VB) AMORTIZACIÓN IGV
NETA (VN) COBRAR
S/.104,916.94 -S/.10,207.97 S/.94,708.97 S/.17,047.62 S/.111,756.59

VALORIZACIÓN TOTAL A
ALORIZACIÓN BRUTA (VB) AMORTIZACIÓN IGV
NETA (VN) COBRAR
S/.15,856.08 -S/.1,545.40 S/.14,310.68 S/.2,575.92 S/.16,886.60