Construction Procedure of
Surface Road Side Drainage-
PART 1 (with picture)
Surface water ( i.e., rain water)
that falls on the ground surface
such as; open field, paved areas or road
Culvert is an open/close drain structure that allows water to flow below a road. It’s surface, roof tops etc are cha...
like a tunnel carrying a stream of water flow.
Concrete Grading and Mix Ratio for your
building or structures.
A Ring/Pipe Culvert
The materials used in reinforced/unreinforced
concrete are commonly weighed and mixed in
large concrete mixers or small batches that are
Procedure for construction of a common Ring/Pipe Culvert (road junction culvert) mix...
includes;
Ring / Pipe Culverts Construction
I. Marking Of Alignment: procedure
Culvert is an open/close drain
structure that allows water to flow
below a road. It’s like a tunnel
carrying a stream of water f...
Construction Procedure of
Surface Road Side Drainage-
PART 2 (with picture)
V. Next step is laying of
concrete base on the blinded
surface and the positioned reinforcement. A
concrete base of 150 mm...
http://constructionhints.blogspot.com/2015/04/ring-pipe-culverts-construction-part-1.html 1/9
1/7/2019 Construction Hints: Ring / Pipe Culverts Construction procedure
II. Digging/Excavation:
Labels
Featured Post
For a 1m pipe culvert, the mathematical process of obtaining the required dept is
to sum together the total width of the pipe + base + blinding.
For dept:
For width:
Construction Hints on Facebook
A minimum of (2.5 x width) m is advisable.
For a 1m pipe drainage,
Since the drainage internal width is 1m, using
http://constructionhints.blogspot.com/2015/04/ring-pipe-culverts-construction-part-1.html 2/9
1/7/2019 Construction Hints: Ring / Pipe Culverts Construction procedure
1.5 x width =
2.5 x 1m = 2.5m
2.5m width excavation minimum is acceptable to create space for construction
work area.
III. The next step after excavation of drainage is the CONCRETE BLINDING
and foundation base preparation.
Blog Archive
▼ 2015 (39)
► January (6)
► February (25)
► March (5)
▼ April (1)
Ring / Pipe Culverts Construction
procedure
► July (2)
► 2016 (16)
► 2017 (2)
Blinding (though optional) is done on the surface area in order to correct any
irregularities in level of the bed of the excavated surface, and to provide a
smooth, level and regular surface to receive the concrete base. It’s usually ±50
mm depending on the rate of regularity of the surface area. Concrete grading
C15 is acceptable.
(See concrete grading and mix ratio). A concrete base of ±150 mm is to be laid
or cast on the blinded floor, concrete grade C15 of ratio 1:2:4 is allowed (See
concrete grading and mix ratio).
A guiding panel is placed into position to guild in the laying of the concrete base
in order to achieve a uniformly alignment base edge, thickness and width, also
to manage concrete material while pouring. The base is cast with the U shape
reinforcement bottom in between the concrete base achieving concrete cover
below and above.
IV. After setting, curing and drying of the concrete base, next is to arrange
the pre-cast pipe Culvert/Rings into the align position.
http://constructionhints.blogspot.com/2015/04/ring-pipe-culverts-construction-part-1.html 3/9
1/7/2019 Construction Hints: Ring / Pipe Culverts Construction procedure
V. After arranging the pre-cast pipe Culvert/Rings into the align position,
arranging the form work panel and then casting of concrete.
Taking the pipe/ring dimension to be 1000 mm (1.0m), the thickness of the top
slab concrete from the top of the pre-cast ring/pipe is between 200mm -
300mm more or less depending on the design.
Assuming the thickness of the top slab concrete from the top of the pre-cast
ring/pipe is between 300mm,
Also, the reinforcement for the head wall is placed into position.
http://constructionhints.blogspot.com/2015/04/ring-pipe-culverts-construction-part-1.html 4/9
1/7/2019 Construction Hints: Ring / Pipe Culverts Construction procedure
Concrete cast.
After casting, and setting, the panel is removed and concrete cured.
http://constructionhints.blogspot.com/2015/04/ring-pipe-culverts-construction-part-1.html 5/9
1/7/2019 Construction Hints: Ring / Pipe Culverts Construction procedure
http://constructionhints.blogspot.com/2015/04/ring-pipe-culverts-construction-part-1.html 6/9
1/7/2019 Construction Hints: Ring / Pipe Culverts Construction procedure
11 comments
Top comments
+1 1 · Reply
Rahul Zarkhaipi
2 years ago
http://constructionhints.blogspot.com/2015/04/ring-pipe-culverts-construction-part-1.html 7/9
1/7/2019 Construction Hints: Ring / Pipe Culverts Construction procedure
yea s ago
good
+1 1 · Reply
Geosynthetic Systems
11 months ago (edited) - Shared publicly
superb! this post is awesome, interesting, & informative . I
appreciate your effort.
+1 1 · Reply
1 · Reply
1 · Reply
1 · Reply
1 · Reply
1 · Reply
1 · Reply
1 · Reply
About Me
Josef toye
http://constructionhints.blogspot.com/2015/04/ring-pipe-culverts-construction-part-1.html 9/9