Вы находитесь на странице: 1из 56

LABOUR SCHEDULE AL-1

LABOUR CHARGES OF 33 kV LINE ON 280 Kg. 9.1 Mtr. LONG PCC POLES, 365 Kg 11 Mtr. LONG PCC POLES AND 152x152 mm., 37.1 Kg./ Mtr., 13
Mtr. LONG H-BEAM POLE WITH RACCOON CONDUCTOR

For 280 Kg. 9.1 Mtr. Long PCC For 365 Kg. 11 Mtr. Long For 152x152 mm 37.1 Kg/Mtr
poles PCC poles 13.0 Mtr Long H-Beam poles
S.
Particulars Unit Qty.
No.
Year 2019-20

Rate Amount Rate Amount Rate Amount


1 Survey Km. 1
2 Tree cutting Km. 1 4558.19 4558.19 4558.19 4558.19 4558.18 4558.18
3 Approach Clearance Km. 1
4 Pit digging No. 10 364.66 3646.55 400.85 4008.48 364.66 3646.55
5 Stay Pit digging No. 3 303.88 911.64 322.77 968.32 303.88 911.64
Transportation of pole from road side to pole pit for a No.
6 10 455.82 4558.19 546.06 5460.61 455.82 4558.19
lead of 1.0 Km.
7 Shifting of materials (other No than pole) to pole pits No. 10 118.51 1185.13 125.88 1258.81 118.51 1185.13
8 Cross arm fixing complete with top clamp No. 10 121.55 1215.52 129.11 1291.09 121.55 1215.52
9 Pole erection complete No. 10 1215.52 12155.18 1488.43 14884.33 1215.52 12155.18
Concreting of stay and base pad for poles 0.00 0.00 0.00 0.00 0.00 0.00
10 (i) For PCC poles Cft 51 24.30 1239.43 25.81 1316.50 0.00 0.00
(ii) For Rail poles Cft 270 0.00 0.00 0.00 0.00 24.31 6563.68
11 Stay erection complete No. 3 212.72 638.15 225.94 677.82 212.72 638.15
12 Insulator fixing at each location No. 30 30.39 911.64 32.28 968.32 30.39 911.64
13 Anti climbing devices and danger board fixing. No. 10 75.97 759.70 80.69 806.93 75.97 759.70
14 Painting and numbering etc including steel support No. 10 91.16 911.64 96.83 968.32 364.65 3646.49
15 Stringing of line for all three Raccoon conductors Km. 1 11851.30 11851.30 12588.11 12588.11 11851.30 11851.30
16 Carpet guarding. Span 1 2582.98 2582.98 2743.56 2743.56 2582.98 2582.98
17 Twisting of jointing sleeves No. 3 91.16 273.49 96.83 290.49 91.16 273.49
TOTAL 47398.72 52789.87 55457.81

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as compared
to the rates applicable for normal soil.
LABOUR SCHEDULE AL-2
SCHEDULE OF LABOUR CHARGES PER 33 kV D.P. STRUCTURE (PCC POLE / 13 MTR. LONG RAIL POLE)
For 280 Kg. 9.1 Mtr. Long For 365 Kg. 11 Mtr. Long For 152x152 mm 37.1 Kg/Mtr
PCC poles PCC poles 13.0 Mtr Long H-Beam poles
S.No. Particulars Unit Qty. Year 2019-20
Rate Amount Rate Amount Rate Amount

1 Pit digging No. 2 364.66 729.31 400.85 801.70 364.66 729.31

2 Stay Pit digging No. 6 303.88 1823.28 303.88 1823.28 303.88 1823.28

3 Shifting of materials to pole pit Set 1 264.38 264.38 264.38 264.38 264.38 264.38

Transportation of pole from road side to pole pit for


4 No. 2 455.82 911.64 546.06 1092.12 455.82 911.64
a lead of 1.0 Km.

5 Cross arm fixing complete including insulator etc. No. 1 835.67 835.67 835.67 835.67 835.67 835.67

6 Pole erection complete (including earthing) No. 2 1215.52 2431.04 1488.43 2976.87 1215.52 2431.04

7 Concreting of stay and poles Cft. 103 24.31 2503.97 24.31 2503.97 24.31 2503.97

8 Stay erection complete with binding of stay wire. No. 6 212.72 1276.29 212.72 1276.29 212.72 1276.29

9 Anticlimbing devices and danger board fixing No. 2 75.97 151.94 75.97 151.94 75.97 151.94

10 Painting of cross arm and numbering of poles etc. No. 2 91.16 182.33 91.16 182.33 364.65 729.30

TOTAL 11109.83 11908.53 11656.81

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE AL-2(A)

SCHEDULE OF LABOUR CHARGES PER 33 kV FOUR POLE STRUCTURE (PCC POLE / 9 MTR. LONG RAIL POLE)

For 280 Kg. 9.1 Mtr. Long PCC For 60 Kg./ Mtr 9.0 Mtr. Long Rail
poles poles
S.No. Particulars Unit Qty.
Year 2019-20
Rate Amount Rate Amount

1 Pit digging No. 4 405.23 1620.93 364.66 1458.62

2 Stay Pit digging No. 8 337.69 2701.56 303.88 2431.04

3 Shifting of materials to pole pit Set 6 293.79 1762.77 264.38 1586.25

Transportation of pole from road side to pole pit for a lead of


4 No. 4 506.54 2026.17 455.82 1823.28
1.0 Km.

5 Cross arm fixing complete including insulator etc. No. 6 928.66 5571.96 835.67 5014.01

6 Pole erection complete (including earthing) No. 4 1350.78 5403.11 1215.52 4862.07

7 Concreting of stay and poles Cft. 134 27.02 3620.09 24.31 3257.59

8 Stay erection complete with binding of stay wire. No. 8 236.39 1891.09 212.72 1701.73

9 Anticlimbing devices and danger board fixing No. 4 84.42 337.69 75.97 303.88

10 Painting of cross arm and numbering of poles etc. No. 6 101.31 607.85 364.65 2187.89

TOTAL 25543.22 24626.36

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE AL-3

LABOUR CHARGES OF 33 kV LINE ON 280 Kg. 9.1 MTR. LONG PCC POLES, 365 Kg 11 MTR. LONG PCC POLES AND 152x152 mm, 37.1 Kg./
Mtr., 13 Mtr. LONG H-BEAM POLE WITH DOG CONDUCTOR

Particulars Unit Qty. For 280 Kg. 9.1 Mtr. Long For 365 Kg. 11 Mtr. Long For 152x152 mm 37.1 Kg/Mtr 13.0
PCC poles PCC poles Mtr Long H-Beam poles
S.
No. Year 2019-20
Rate Amount Rate Amount Rate Amount
1 Survey Km. 1
2 Tree cutting Km. 1 4558.19 4558.19 4558.19 4558.19 4558.19 4558.19
3 Approach Clearance Km. 1
4 Pit digging No. 10 364.66 3646.55 400.85 4008.48 364.66 3646.55
5 Stay Pit digging No. 3 303.88 911.64 303.87 911.62 303.88 911.64
6 Transportation of pole from road side to
No. 10 455.82 4558.19 546.06 5460.61 455.82 4558.19
pole pit for a lead of 1.0 Km.
Shifting of materials (other No than pole) to
7 No. 10 118.51 1185.13 118.51 1185.15 118.51 1185.13
pole pits

8 Cross arm fixing complete with top clamp No. 10 121.55 1215.52 121.56 1215.55 121.55 1215.52

9 Pole erection complete No. 10 1215.52 12155.18 1488.43 14884.33 1215.52 12155.18
10
Concreting of stay and base pad for poles 0.00 0.00 0.00 0.00 0.00 0.00

(i) For PCC poles Cft 51 24.31 1239.83 24.31 1239.83 0.00 0.00
(ii) For Rail poles Cft 270 0.00 0.00 0.00 0.00 24.31 6563.80
11 Stay erection complete No. 3 212.72 638.15 212.72 638.17 212.72 638.15
12 Insulator fixing with G.I. Pin No. 30 30.39 911.64 30.39 911.67 30.39 911.64
13 Anti climbing devices and danger board. No. 10 75.97 759.70 75.96 759.65 75.97 759.70
14 Painting and numbering etc. No. 10 91.16 911.64 91.17 911.67 364.65 3646.49
15 Stringing of line for Dog conductor Km. 1 13674.58 13674.58 13674.58 13674.58 13674.58 13674.58
16 Carpet guarding Span 1 2582.98 2582.98 2582.98 2582.98 2582.98 2582.98
17 Twisting of jointing sleeves No. 3 91.16 273.49 91.17 273.50 91.16 273.49
TOTAL 49222.40 53215.96 57281.22
Particulars Unit Qty. For 280 Kg. 9.1 Mtr. Long For 365 Kg. 11 Mtr. Long For 152x152 mm 37.1 Kg/Mtr 13.0
PCC poles PCC poles Mtr Long H-Beam poles
S.
No. Year 2019-20
Rate Amount Rate Amount Rate Amount
The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE AL-3 (B)

LABOUR CHARGES FOR ADDITIONAL MID-SPAN RAIL POLE FOR 33 kV LINE

Particulars Unit Qty. For 60 Kg. / Mtr. 13.0 Mtr. Rail poles

S. Year 2019-20
No.
Rate Amount

1 Pit digging No. 1 364.66 364.66

2 Transportation of pole from road side to pole pit for a lead of 1.0 Km. No. 1 455.82 455.82

3 Shifting of materials (other No than pole) to pole pits No. 1 118.51 118.51

4 Cross arm fixing complete with top clamp No. 1 121.55 121.55

5 Pole erection complete No. 1 1215.52 1215.52


Concreting of rail @ 0.6 cmt. Per pole and @ 0.05 cmt per pole for
0.00 0.00
6 base padding of rail pole
(i) For Rail poles Cft 24 22.38 537.14

7 Insulator fixing with G.I. Pin No. 3 30.39 91.16

8 Anti climbing devices and danger board. No. 1 75.97 75.97

9 Painting and numbering etc. No. 1 364.65 364.65

10 TOTAL 3344.98

Note :- The rates are proposed for normal soil conditions . In case of soft rock & hard rock, the rates of pit digging will be taken as two
times and ten times respectively as compared to the rates applicable for normal soil.
LABOUR SCHEDULE AL-4

LABOUR CHARGES OF 33 kV LINE ON 60 Kg. / 52 Kg./ MTR. LONG RAIL POLE 13 METER LONG MAX. 50 METER SPAN ON PANTHER
CONDUCTOR

For 60 Kg./ Mtr 13 Mtr. Long Rail poles

S. Year 2019-20
Particulars Unit Qty.
No.

Rate Amount
1 Survey Km. 1
2 Tree cutting Km. 1 4558.19 4558.19
3 Approach Clearance Km. 1
4 Pit digging 7 feet depth No. 20 425.43 8508.63
5 Stay Pit digging No. 12 303.88 3646.55
6 Transportation of pole from road side to pole pit for a lead of 1.0 Km. No. 20 607.76 12155.18
7 Shifting of materials (other No than pole) to pole pits No. 20 118.51 2370.26
8 DC Cross arm fixing No. 30 182.33 5469.83
9 Pole erection complete No. 20 1519.40 30387.95
10 Concreting of stay and base pad for poles 0.00 0.00
(i) For PCC poles Cft 0 0.00 0.00
(ii) For Rail poles Cft 512 24.31 12446.90
11 Stay erection complete No. 12 212.72 2552.59
12 Insulator fixing with hardware No. 180 30.39 5469.83
13 Anti climbing devices and danger board. No. 20 75.97 1519.40
14 Painting and numbering etc. No. 20 364.66 7293.11
15 Stringing of line for Panther conductor Km. 1 45581.92 45581.92
16 Carpet guarding Span 5 3038.79 15193.97
17 Twisting of jointing sleeves No. 6 182.33 1093.97
TOTAL 158248.27

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively
as compared to the rates applicable for normal soil.
LABOUR SCHEDULE AL-5 (REVISED)

SCHEDULE OF LABOUR CHARGES FOR 33 kV / 11 kV UNDERGROUND CABLE CROSSING UNDER EXISTING RAIWAY TRACK 2.5 Mtr. DEEP FROM GROUND
LEVEL. (60 Mtr. LONG CORRIDOR / ROUTE LENGTH OF HDPE PIPE DOUBLE CIRCUIT )

Year 2019-20

Using HDD Technique Using Pipe Pushing


S.
Particulars Unit Qty. 3x240 sq.mm 3x400 sq.mm 3x240 3x400 sq.mm
No.
AB XLPE AB XLPE sq.mm AB AB XLPE
Rate Cable Cable Rate XLPE Cable Cable

Amount Amount Amount Amount


1 2 3 3 7 8 12 13
Labour charges for laying of HDPE Pipe of maximum 240 mm
1 dia, in normal soil under 2.5 mtr. Deep from ground level
using
a Pipe Pushing method * Mtr. 120 19511.81 2341417.26 2341417.26
b Using HDD Technique (Horizontal Directional Drilling) ** Mtr. 120 1830.29 219634.59 219634.59 0.00 0.00 0.00

2 Laying of 240 sqmm 3 core XLPE cable through HDPE pipe. Mtr. 180 487.80 87803.15 0.00 487.80 87803.15 0.00

3 Laying of 400 sqmm 3 core XLPE cable through HDPE pipe. Mtr. 190 487.80 0.00 92681.10 487.80 92681.10
4 Earthing pit digging and laying of earth pipe complete. Set. 10 1063.58 10635.78 10635.78 1063.58 10635.78 10635.78
5 Joining kit labour charges. Set. 4 7804.72 31218.90 31218.90 7804.72 31218.90 31218.90
6 Covering of cable with tiles Mtr. 60 3.88 233.02 233.02 3.88 233.02 233.02
7 Spreading sand and forming with sand round the cable Mtr. 60 14.11 846.73 846.73 14.11 846.73 846.73
8 Laying of GI Pipe Mtr 24 69.89 1677.44 1677.44 69.89 1677.44 1677.44
9 Fixing of 33 kV LA including earthing. Set. 2 303.88 607.76 607.76 303.88 607.76 607.76

10 Jumpering of Lightning Arrestor and fixing of Aluminium lugs. Set. 2 306.54 613.08 613.08 306.54 613.08 613.08

11 Fixing of Riser pipe with clamps Mtr. 12 390.24 4682.83 4682.83 390.24 4682.83 4682.83
12 TOTAL 357953.27 362831.22 2479735.94 2484613.89
13 TOTAL (Rounded Off) 357953.00 362831.00 2479736.00 2484614.00

Note Since our requirement of HDPE Pipe is maximum 240 mm hence HDD technique is suitable in place of pipe pushing.
LABOUR SCHEDULE AL-6 [ for Sch- A-10 ]

SCHEDULE OF LABOUR CHARGES FOR 33 kV / 11 kV UNDERGROUND CABLE CROSSING UNDER PROPOSED RAILWAY TRACK 2.5 Mtr. DEEP FROM
GROUND LEVEL. (60 Mtr. LONG CORRIDOR / ROUTE LENGTH OF HDPE PIPE DOUBLE CIRCUIT ) USING OPEN TRENCH METHOD

Year 2019-20

S. 3x240 sq.mm AB 3x400 sq.mm AB


Particulars Unit Qty. XLPE Cable XLPE Cable
No. Rate

Amount Amount
1 2 3 4 8 9 10
1 Cable trench excavation 1000x0.6x1=600 ordinary soil. Cube / Mtr. 120 251.76 30211.40 30211.40
Labour charges for laying of HDPE Pipe of maximum 240 mm dia, in
2 normal soil under 2.5 mtr. Deep from ground level using Open Trench Mtr. 120 54.36 6522.92 6522.92
Method
3 Laying of 240 sqmm 3 core XLPE cable through HDPE pipe. Mtr. 180 487.80 87803.15
4 Laying of 400 sqmm 3 core XLPE cable through HDPE pipe. Mtr. 190 487.80 92681.10
5 Earthing pit digging and laying of earth pipe complete. Set. 10 1063.58 10635.78 10635.78
6 Joining kit labour charges. Set. 4 7804.72 31218.90 31218.90
7 Covering of cable with tiles Mtr. 60 3.88 233.02 233.02
8 Spreading sand and forming with sand round the cable Mtr. 60 14.11 846.73 846.73
9 Laying of GI Pipe Mtr 24 69.89 1677.44 1677.44
10 Fixing of 33 kV LA including earthing. Set. 2 303.88 607.76 607.76
11 Jumpering of Lightning Arrestor and fixing of Aluminium lugs. Set. 2 306.54 613.08 613.08
12 Fixing of Riser pipe with clamps Mtr. 12 390.24 4682.83 4682.83
TOTAL 175052.99 179930.95
TOTAL (Rounded Off) 175053 179931
LABOUR SCHEDULE BL-1
SCHEDULE OF LABOUR CHARGES OF 33/11 kV SUB-STATION EXCLUDING TRANSFORMER 1.6 MVA & ABOVE
Year 2019-20
S.No. Particulars Unit 1.6 MVA 3.15 MVA 5.0 MVA
Rate (Rs)
Qty. Amt. (Rs) Qty. Amt. (Rs) Qty. Amt. (Rs)
1 Pole pit digging No. 364.66 28 10210.35 28 10210.35 32 11668.97
Shifting of materials (Other than pole) to pole pits in case of: 0.00 0 0.00 0 0.00 0 0.00
2 (a) S/s materials excluding yard lighting Set 151.94 22 3342.67 22 3342.67 22 3342.67
(b) Yard lighting Set 45.58 6 273.49 6 273.49 6 273.49
3 Transportation of support from road side to pole pits for a lead for 1.0 Km. 0.00 0.00 0 0.00 0 0.00
(a) Bus bar gantry structure & PCC pole for yard lighting No. 455.82 22 10028.02 22 10028.02 26 11851.30
4 Cross arm fixing complete including insulator etc. No. 455.82 33 15042.03 33 15042.03 41 18688.59
Pole erection complete 0.00 0.00 0 0.00 0 0.00
(i)H-Beam for mounting DO fuse units & DP. No. 759.70 12 9116.38 12 9116.38 14 10635.78
5
(ii) Bus bar structure. No. 1215.52 10 12155.18 10 12155.18 12 14586.21
(iii) Tabular pole for yard lighting No. 759.70 6 4558.19 6 4558.19 6 4558.19
6 Concreting of supports Cft. 24.31 36.60 889.76 36.60 889.76 45.00 1093.97
7 Fixing of 33 kV DO fuse units. Set. 379.85 1 379.85 0 0.00 0 0.00
8 Fixing of 11 kV DO fuse units. Set. 303.88 1 303.88 1 303.88 1 303.88
9 Fixing of 33 kV LA including earthing. Set. 303.88 1 303.88 1 303.88 1 303.88
10 Fixing of 11 kV LA including earthing. Set. 227.91 12 2734.92 12 2734.92 15 3418.64
11 Fixing of 33 kV AB switch complete with handle. Set. 1063.58 1 1063.58 1 1063.58 1 1063.58
12 Fixing of 11 kV AB switch complete with handle isolator Set. 911.64 3 2734.92 3 2734.92 4 3646.55
Stringing of DOG ACSR conductor with fixing of terminal clamps. 0.00 0.00 0 0.00 0 0.00
(a) 33 kV incoming gantry structure LS 1519.38 1 1519.38 1 1519.38 1 1519.38
13
(b) 11 kV incoming gantry structure LS 3037.99 1 3037.99 1 3037.99 1 3037.99
(c) for transformer protection LS 759.79 1 759.79 1 759.79 1 759.79
0.00 0.00 0 0.00 0 0.00
(d) Bus bar structure (per bus) No. 507.31 3 1521.92 3 1521.92 4 2029.23
14 Digging and concreting of foundation of X-mer LS 15193.85 1 15193.85 1 15193.85 1 15193.85
15 Digging and concreting of foundation of VCB. No. 3038.79 3 9116.38 3 9116.38 4 12155.18
16 Digging of trenches, pits & laying out earthing mat, interconnection etc. LS 21271.78 1 21271.78 1 21271.78 1 21271.78
17 Handling & installation of 33 kV X-mer control and feeder VCB on foundation. No. 2926.77 0 0.00 1 2926.77 1 2926.77
18 Handling & installation of 11 kV X-mer control and feeder VCB on foundation. No. 2127.16 3 6381.47 3 6381.47 4 8508.63
19 Preparation of cable trench from 11 kV VCB to control room LS 3902.36 1 3902.36 1 3902.36 1 3902.36
20 Fixing of T-clamps for jumpers & bimetallic clamps No. 25.37 106 2688.73 106 2688.73 111 2815.55
21 Painting of channels and supports LS 4557.96 1 4557.96 1 4557.96 1 4557.96
22 Handling & installation of station X-mer. LS 1215.59 1 1215.59 1 1215.59 1 1215.59
23 Fixing of LT switch box complete & crimping. LS 911.59 1 911.59 1 911.59 1 911.59
24 Fixing of 3 Ph. 4 wire LT meters. LS 911.59 1 911.59 1 911.59 1 911.59
25 Handling & installation of battery charger & distn. Board. LS 911.59 1 911.59 1 911.59 1 911.59
26 Handling & Installation of batteries. LS 1560.94 1 1560.94 1 1560.94 1 1560.94
27 DC cabling from distn. Board to yard connection. LS 911.59 1 911.59 1 911.59 1 911.59
28 Laying of under-ground cable complete including fixing of terminal block. LS 911.59 1 911.59 1 911.59 1 911.59
29 Fixing arrangement of search light of support & handling and fixing of search light. LS 682.91 1 682.91 1 682.91 1 682.91
30 Jumpering of DO fuse, AB switch & transformer and fixing of terminal clamps. LS 911.59 1 911.59 1 911.59 1 911.59
31 Installation, testing and commissioning of 33 kV ME No. 2926.77 1 2926.77 1 2926.77 1 2926.77
32 Installation, testing and commissioning of 11 kV ME No. 1951.18 2 3902.36 2 3902.36 3 5853.54
33 Installation, testing and commissioning of HT meter complete with box No. 975.59 3 2926.77 3 2926.77 4 3902.36
34 Total labour charges. 161773.61 164320.54 185725.85
35 Total Labour Charges. (Rounded off) 161774.00 164321.00 185726.00
Year 2019-20
S.No. Particulars Unit 1.6 MVA 3.15 MVA 5.0 MVA
Rate (Rs)
Qty. Amt. (Rs) Qty. Amt. (Rs) Qty. Amt. (Rs)
Note- The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as compared to the rates
applicable for normal soil.
LABOUR SCHEDULE BL-2

SCHEDULE OF LABOUR CHARGES FOR POWER TRANSFORMER IN PARALLEL EXCLUDING BAY

Year 2019-20
S.No. Particulars Unit Qty.
Rate Amt.

1 Pit digging No. 4 364.66 1458.62

2 Shifting of materials (Other than pole) to pole pits No. 3 136.73 410.18

3 Transportation of support from road side to pole pits for a lead for 1.0 Km. No. 4 273.45 1093.80

4 Cross arm fixing complete including insulator etc. No. 2 410.18 820.35

5 Pole erection complete (Joist) No. 4 683.63 2734.50

6 Concreting of supports Cft. 42.00 21.88 918.79

7 Fixing of 33 kV DO fuse units. Set. 1 341.81 341.81

8 Fixing of 11 kV DO fuse units. Set. 1 273.45 273.45

9 Fixing of 33 kV LA including earthing. Set. 1 273.45 273.45

10 Fixing of 11 kV LA including earthing. Set. 1 205.09 205.09

11 Stringing of Dog ACSR conductor with fixing of terminal clamps. LS LS LS 1519.40

12 Digging and concreting of foundation of X-mer LS LS LS 15193.97

13 Digging and concreting of foundation of VCB. No. 1 2734.50 2734.50

14 Handling & installation of 11 kV X-mer control and feeder VCB on foundation. LS LS LS 2127.16

15 Preparation of cable trench from 11 kV VCB to control room LS LS LS 911.64

16 Painting of channels and supports LS LS LS 911.64


Total Labour Charges. (Rounded off) 31928.36

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times
respectively as compared to the rates applicable for normal soil.
LABOUR SCHEDULE BL-3

SCHEDULE OF LABOUR CHARGES FOR 33/11 kV POWER TRANSFORMER

Year 2019-20

S.No. Particulars Unit Qty.

1.6 MVA 3.15 MVA 5.0 MVA

1 Shifting of Xmer on foundation (Incl. lifting from A/S ) No. 1 39024.52 48779.75 58534.98

2 Assembling, No. 1 7804.54 9755.23 11707.71

3 Testing including testing of 11 kV VCB and commissioning LS LS 15219.31 15219.31 15609.09

Total Labour Charges. (Rounded off) 62048.37 73754.29 85851.79

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE BL-4
LABOUR CHARGES FOR 11 kV OUTDOOR YARD EXTENSION OF ADDITIONAL BAY
S.No. Particulars Unit Qty. Year 2019-20

Rate Amount
1 Pit digging No. 2 365.60 731.21
2 Shifting of materials to pole pits No. 6 152.33 914.01
3 Transportation of pole from road side to pole pit No. 2 419.62 839.23
4 Cross arm fixing with insulator HW with insulator etc. No. 6 419.62 2517.70
5 Pole erection complete No. 2 1118.98 2237.96
6 Concreting of poles Cft. 35 22.38 783.28

7 Fixing of 11 kV AB switch / Isolator complete with operating handle. No. 3 839.23 2517.70

8 Stringing of DOG conductor including jumpering . L.S. L.S. L.S. 2098.08


9 Fixing of T-clamps for jumpering No. 11 15.26 167.85

10 Digging and concreting of foundation of 11 kV VCB. No. 1 3046.70 3046.70

11 Handling & installation of VCB on foundation No. 1 2132.69 2132.69

12 Preparation of cable trench from 11 kV VCB to control room. L.S. L.S. L.S. 914.01

13 Painting of structure. L.S. L.S. L.S. 1523.35

14 Digging of pits & laying out earthing mat, interconnection etc. L.S. L.S. L.S. 3046.70

15 Levelling & Metalling L.S. L.S. L.S. 6093.40


TOTAL 29563.86

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten
times respectively as compared to the rates applicable for normal soil.
LABOUR SCHEDULE BL-5

LABOUR CHARGES FOR 33 kV OUT DOOR YARD


Year 2019-20
S.No. Particulars Unit Qty.

Rate Amount
1 Pit digging No. 2 365.60 731.21
2 Shifting of materials to pole pit No. 6 152.33 914.01
3 Transportation of pole from road side to pole pit Set 2 457.00 914.01

4 Cross arm fixing with insulator HW including channel for AB switch No. 6 457.00 2742.03

5 Pole erection complete No. 2 1218.68 2437.36


6 Concreting of stay and poles Cft. 35 24.37 853.08

7 Fixing of isolator complete with operating handle. Set 1 1066.34 1066.34

Stringing of double conductor including jumpering and fixing of terminal clamps


8 L.S. LS L.S. 2285.02
etc.
9 Fixing of T-clamps for jumpering No. 18 18.28 329.04
10 Painting of Structure L.S. LS L.S. 1523.35

11 Digging of trenches, pits & laying out earthing mat, interconnection etc. L.S. L.S. L.S. 3046.70

12 Levelling & Metalling L.S. L.S. L.S. 6093.40


TOTAL 22935.54

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times
respectively as compared to the rates applicable for normal soil.
LABOUR SCHEDULE BL-6

SCHEDULE OF LABOUR CHARGES FOR INSTALLATION OF 33 kV VCB

S. 2015-16 Year 2019-20


Particulars Unit
No.
R
a
Rate Qty. Amt. (Rs)
t
e
1 Digging and concreting of foundation of VCB. No. ### 3038.79 1 3038.79

2 Handling & installation of 33 kV X-mer control and feeder VCB on foundation. No. ### 2926.77 1 2926.77

3 Fixing of T-clamps for jumpers & bimetallic clamps No. ### 25.37 35 887.79

4 DC cabling from distn. Board to yard connection. LS ### 911.59 1 911.59

5 Laying of under-ground cable complete including fixing of terminal block. LS ### 911.59 1 911.59

Total labour charges 8676.54

Total Labour Charges. (Rounded off) 8677.00

Note - The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times
respectively as compared to the rates applicable for normal soil.

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE BL-7

SCHEDULE OF LABOUR CHARGES FOR INSTALLATION OF 11 kV SINGLE PHASE AB SWITCH ON EXISTING OUTGOING FEEDER DP
FROM 33/11 kV S/S

Year 2019-20
S.No. Particulars Unit

Rate Qty. Amt. (Rs)

1 Fixing of 11 kV AB switch complete with handle isolator Set. 911.64 1 911.64

Stringing of DOG ACSR conductor with fixing of terminal clamps. 0.00 0.00
2
(a) 11 kV incoming gantry structure LS 1519.38 1 1519.38

3 Fixing of T-clamps for jumpers & bimetallic clamps No. 25.37 35 887.79

4 Jumpering of DO fuse, AB switch & transformer and fixing of terminal clamps. LS 911.59 1 911.59

Total labour charges. 4230.40

Total Labour Charges. (Rounded off) 4230.00

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times
respectively as compared to the rates applicable for normal soil.

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE BL-8
SCHEDULE OF LABOUR CHARGES FOR AUGMENTATION OF 33/11 kV S/s CAPACITY REPLACEMENT OF POWER
TRANSFORMER

2015-16
R Year 2019-20
S.No. Particulars Unit a
Rate Qty. Amt. (Rs)
t
e
1 Shifting of Xmer on foundation (including lifting from A/Store) No. ### 48779.52 1 48779.52

2 Assembling No. ### 9755.90 1 9755.90

3 Testing and Commissioning of Xmer and VCB No. ### 15219.20 1 15219.20

4 Digging and concreting of foundation of VCB. No. ### 3038.79 1 3038.79

5 Handling & installation of 33 kV X-mer control and feeder VCB on foundation. No. ### 2926.77 1 2926.77

6 Fixing of T-clamps for jumpers & bimetallic clamps No. ### 25.37 35 887.79

7 DC cabling from distn. Board to yard connection. LS ### 911.59 1 911.59

8 Laying of under-ground cable complete including fixing of terminal block. LS ### 911.59 1 911.59

Total labour charges 82431.15

Total Labour Charges. (Rounded off) 82431.00

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two
times and ten times respectively as compared to the rates applicable for normal soil.

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE BL-9
SCHEDULE OF LABOUR CHARGES FOR INSTALLATION OF 1.6 MVA POWER TRANSFORMER ON LINE

Year 2019-20
S.No. Particulars Unit Qty.
Rate Amt.
1 Pit digging No. 10 364.66 3646.55

2 Shifting of materials (Other than pole) to pole pits No. 5 151.94 759.70

3 Transportation of support from road side to pole pits for a lead for 1.0 Km. No. 10 303.88 3038.79

4 Cross arm fixing complete including insulator etc. No. 5 455.82 2279.10

5 Pole erection complete (Joist) No. 10 759.70 7596.99

6 Concreting of supports Cft. 185 24.31 4497.42

7 Fixing of 33 kV DO fuse units. Set. 1 379.85 379.85

8 Fixing of 11 kV DO fuse units. Set. 1 303.88 303.88

9 Fixing of 33 kV LA including earthing. Set. 1 303.88 303.88

10 Fixing of 11 kV LA including earthing. Set. 1 227.91 227.91

11 Stringing of Dog ACSR conductor with fixing of terminal clamps. LS LS LS 1519.40

12 Digging and concreting of foundation of X-mer LS LS LS 15193.97

13 Painting of channels and supports LS LS LS 911.64

14 Shifting of Xmer (including lifting from A/Store) No. 1 36519.65 36519.65

15 Assembling No. 1 7303.93 7303.93

16 Testing and commissioning of power Xmer No. 1 14242.66 14242.66

17 Digging of pits and laying out earthing mate connecteion etc LS LS LS 3038.78
Total Labour Charges 101764.09
203528.18

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively
as compared to the rates applicable for normal soil.

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE CL-1

LABOUR CHARGES OF 11 kV LINE ON PCC POLES.

Year 2019-20
S. No. Particulars Unit Qty.

Rate Amount
1 Survey Km. 1
2 Tree cutting Km. 1 4570.05 4570.05
3 Approach Clearence Km. 1
4 Pit digging No. 12 304.67 3656.04
5 Stay Pit digging No. 4 274.20 1096.81
6 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 12 304.67 3656.04
7 Shifting of materials to pole pits No. 12 60.93 731.21
8 Cross arm fixing complete with top clamp No. 12 91.40 1096.81
9 Pole erection complete (including earthing) No. 12 761.67 9140.09
10 Concreting of stay and poles Cft. 51 24.37 1243.05
11 Stay erection complete No. 4 198.04 792.14
12 Insulator fixing with GI Pin No. 36 21.33 767.77
13 Anti climbing devices and danger board fixing No. 12 76.17 914.01
14 Painting of cross arm & numbering of poles No. 12 76.17 914.01
15 Stringing of line (Rabbit) all three conductor Km. 1 10968.11 10968.11
16 Carpet guarding Span 1 1523.35 1523.35
17 Twisting of jointing sleves No. 3 67.03 201.08
TOTAL 41270.56
Stringing of line (Weasel) all three conductor Km. 1 10054.10 36726.55

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times
respectively as compared to the rates applicable for normal soil.
LABOUR SCHEDULE CL-2

LABOUR CHARGES PER KM. OF 11 kV D.P. STRUCTURE ON PCC POLE


S. No.

Year 2019-20
Particulars Unit Qty.

Rate Amount
1 Pit digging No. 2 304.67 609.34

2 Stay Pit digging No. 6 274.20 1645.22

3 Shifting of materials to pole pit Set 1 213.27 213.27

4 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 2 304.67 609.34

5 Cross arm fixing complete including insulator etc. No. 1 457.00 457.00

6 Pole erection complete (including earthing) No. 2 761.67 1523.35

7 Concreting of stay and poles Cft. 76 24.37 1852.39

8 Stay erection complete No. 6 198.04 1188.21

9 Anticlimbing devices and danger board fixing No. 2 76.17 152.33

10 Painting of cross arm and numbering of poles etc. No. 2 91.40 182.80

TOTAL 8433.26

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively
as compared to the rates applicable for normal soil.
LABOUR SCHEDULE CL-3
LABOUR CHARGES FOR 25 / 63 / 100 / 200 kVA 11/0.4 kV OUT DOOR TRANSFORMER SUB-STATION
25 kVA X-Mer 63/100 kVA X-Mer 200 kVA X-Mer
S. Year 2019-20
Particulars Unit Qty.
No.
Rate Amount Rate Amount Rate Amount
1 Pit digging Each 2 303.88 607.76 303.88 607.76 365.60 731.21
2 Stay Pit digging Each 4 273.49 1093.97 273.49 1093.97 274.20 1096.81
3 Shifting of materials to pole pits Set 1 303.88 303.88 303.88 303.88 304.67 304.67
4 Transportation of pole from road side to pole pit Each 2 303.88 607.76 303.88 607.76 304.67 609.34
5 DC Cross arm fixing complete including insulator Each 2 455.82 911.64 455.82 911.64 457.00 914.01
6 Pole erection complete including earthing Each 2 759.70 1519.40 759.70 1519.40 0.00 0.00
7 Concreting of stay and base pad for poles Cft. 70 24.31 1701.73 24.31 1701.73 24.31 1701.73
8 Stay erection complete Each 4 197.52 790.09 197.52 790.09 197.52 790.09
9 Fixing of LA Set Set 1 227.91 227.91 227.91 227.91 227.91 227.91
10 Anti climbing devices and danger board fixing Each 2 75.97 151.94 75.97 151.94 75.97 151.94

11 Painting of cross arm & numbering of poles. Each 2 121.55 243.10 121.55 243.10 364.66 729.31

12 Fixing of LT switch box & transformer wiring etc. Job 1 607.76 607.76 911.64 911.64 911.64 911.64

13 Handling and installation of transformer on structure Job 1 911.64 911.64 1215.52 1215.52 1823.28 1823.28

14 Fixing of D.O fuse complete with base channel Set 1 303.88 303.88 303.88 303.88 303.88 303.88

Earthing of S/s including pit digging, laying and connecting wires to


15 Set 1 1063.58 1063.58 1063.58 1063.58 1063.58 1063.58
supports X-mer etc.

16 Fixing of 11 kV AB switch Set 1 0.00 0.00 0.00 0.00 911.64 911.64


17 Installation & commissioning of DT Meter Job 1 1002.80 1002.80 1002.80 1002.80 1002.80 1002.80

18 Rail / H Beam Pole erection complete incl. earthing No. 2 0.00 0.00 0.00 0.00 1215.52 2431.04

TOTAL 12048.82 12656.58 15704.86


The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE CL-3 (B)
LABOUR CHARGES FOR PER KM. OF 11 kV LINE ON H-BEAM (11 MTR. ) & 200 kG PCC POLE 9 MTR. WITH AB CABLE
With 200 kG 9 Mtr long PCC
With H-Beam
Pole
S. No. Particulars Unit Qty.
Year 2019-20

Rate Amount Rate Amount


1 Survey Km. 1
2 Tree cutting Km. 1 4558.19 4558.19 4558.19 4558.19
3 Approach Clearance Km. 1
4 Pit digging No. 29 364.66 10575.01 364.65 10574.88
5 Stay Pit digging No. 12 303.88 3646.55 303.88 3646.55
6 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 29 455.82 13218.76 379.85 11015.73
7 Shifting of materials to pole pits No. 29 60.78 1762.50 60.78 1762.50
8 Cross arm fixing complete with top clamp No. 37 91.16 3373.06 91.16 3373.06
9 Pole erection complete (including earthing) No. 29 1215.52 35250.02 1021.97 29637.03
10 Concreting of stay and poles Cft. 625 24.31 15193.97 24.31 15193.97
11 Stay erection complete No. 12 212.72 2552.59 212.72 2552.59
12 Anti climbing devices and danger board fixing No. 29 75.97 2203.13 75.97 2203.13
13 Painting of Hardware and numbering of poles including steel pole. No. 29 364.66 10575.01 22.69 658.00
14 Stringing of AB Cable 3x35+35 three conductor Km. 1.06 10028.02 10629.70 10028.02 10629.70
15 Formation of Cable termination Kit Set. 9 3883.59 34952.33 3883.59 34952.33
16 Formation of Cable straight through joint Set. 6 4591.62 27549.74 4591.62 27549.74
TOTAL 176040.55 158307.39

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as compared
to the rates applicable for normal soil.
LABOUR SCHEDULE CL-4
LABOUR CHARGES FOR PER KM. OF 11 kV LINE ON 11 MTR. LONG H-BEAM / 365 Kg PCC POLE

Using H-Beam Using 365 Kg 11 Mtr long PCC Pole


S.
Particulars Unit Qty.
No. Year 2019-20

Rate Amount Rate Amount


1 Survey Km. 1
2 Tree cutting Km. 1 4558.19 4558.19 4558.19 4558.19
3 Approach Clearance Km. 1
4 Pit digging No. 12 364.66 4375.86 400.85 4810.18
5 Stay Pit digging No. 4 303.88 1215.52 303.87 1215.49
6 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 12 455.82 5469.83 546.06 6552.73
7 Shifting of materials to pole pits No. 12 60.78 729.31 60.78 729.33
8 Cross arm fixing complete with top clamp No. 12 91.16 1093.97 91.17 1094.00
9 Pole erection complete (including earthing) No. 12 1215.52 14586.21 1488.43 17861.19
10 Concreting of stay and poles Cft. 270 24.31 6563.80 24.31 6563.17
11 Stay erection complete No. 4 212.72 850.86 212.72 850.89
12 Insulator fixing with GI Pin No. 36 21.27 765.78 21.27 765.64
13 Anti climbing devices and danger board fixing No. 12 75.97 911.64 75.96 911.57
14 Painting of Hardware and numbering of poles including steel pole. No. 12 364.66 4375.86 91.17 1094.00
15 Stringing of line (Weasel) all three conductor Km. 1 10028.02 10028.02 10028.02 10028.02
16 Carpet guarding Span 1 1519.40 1519.40 1519.40 1519.40
17 Twisting of jointing sleeves No. 3 66.85 200.56 91.17 273.50
TOTAL 57244.82 58827.31

Stringing of line (Rabbit) all three conductor Km. 1 10939.66 58156.45 10939.66 59738.95
Stringing of line (Raccoon) all three conductor Km. 1 11851.30 59068.09 11851.30 60650.58
Stringing of line (Dog) all three conductor Km. 1 13674.58 60891.38 13674.58 62473.87

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as compared to
the rates applicable for normal soil.
LABOUR SCHEDULE CL-5

LABOUR CHARGES PER KM. OF 11 kV D.P. STRUCTURE ON 11 MTR LONG H-BEAM / 365 KG PCC POLE

Using H-Beam Using 365 Kg 11 Mtr long PCC Pole

S.No. Particulars Unit Qty.


Year 2019-20

Rate Amount Rate Amount


1 Pit digging No. 2 364.66 729.31 400.85 801.70

2 Stay Pit digging No. 6 303.88 1823.28 303.87 1823.24

3 Shifting of materials to pole pit Set 1 212.72 212.72 212.72 212.72

Transportation of pole from road side to pole pit


4 No. 2 455.82 911.64 546.06 1092.12
for a lead of 1 Km.

DC Cross arm fixing complete including insulator


5 No. 1 455.82 455.82 455.82 455.82
etc.

6 Pole erection complete (including earthing) No. 2 1215.52 2431.04 1488.43 2976.87

7 Concreting of stay and poles Cft. 76 24.31 1847.59 24.31 1847.41

8 Stay erection complete No. 6 212.72 1276.29 212.72 1276.33

9 Anticlimbing devices and danger board fixing Set 2 75.97 151.94 75.96 151.93

Painting of cross arm, pole and numbering of


10 No. 2 364.66 729.31 91.17 182.33
poles etc.
TOTAL 10568.93 10820.47

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE CL-6
LABOUR CHARGES FOR PER KM. OF 11 kV LINE ON R.S. JOIST (11 MTR.)
2
0
1
5 Year 2019-20
S.No. Particulars Unit Qty. -
2
0
1
6
R Rate Amount
a
1 Survey Km. 1
t
2 Tree cutting Km. e
1 ### 4558.19 4558.19
3 Approach Clearance Km. 1
4 Pit digging No. 12 ### 364.66 4375.86
5 Stay Pit digging No. 4 ### 303.88 1215.52
6 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 12 ### 455.82 5469.83
7 Shifting of materials to pole pits No. 12 ### 60.78 729.31
8 Cross arm fixing complete with top clamp No. 12 ### 91.16 1093.97
9 Pole erection complete with earthing No. 12 ### 1215.52 14586.21
10 Concreting of stay and poles Cft. 270 ### 24.31 6563.80
11 Stay erection complete. No. 4 ### 212.72 850.86
12 Insulator fixing with GI Pin. No. 36 ### 21.27 765.78
13 Anti climbing devices and danger board fixing No. 12 ### 75.97 911.64
14 Painting of Hardware and numbering of poles including steel pole. No. 12 ### 364.66 4375.86
15 Stringing of line (Weasel) all three conductor. Km. 1 ### 10028.02 10028.02
16 Carpet guarding. Span 1 ### 1519.40 1519.40
17 Twisting of jointing sleeves. No. 3 ### 66.85 200.56
TOTAL 57244.82
Stringing of line (Rabbit) all three conductor. Km. 1 ### 10939.65 58156.45
The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compare to the rates applicable for normal soil.
LABOUR SCHEDULE CL-7

LABOUR CHARGES PER KM. OF 11 kV D.P. STRUCTURE WITH R.S.JOIST

Year 2019-20
S. No. Particulars Unit Qty.
Rate Amount

1 Pit digging No. 2 364.66 729.31

2 Stay Pit digging No. 6 303.88 1823.28

3 Shifting of materials to pole pit Set 1 212.72 212.72

4 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 2 455.82 911.64

5 DC Cross arm fixing complete including insulator etc. No. 1 455.82 455.82

6 Pole erection complete (including earthing) No. 2 1215.52 2431.04

7 Concreting of stay and poles Cft. 76 24.31 1847.59

8 Stay erection complete No. 6 212.72 1276.29

9 Anticlimbing devices and danger board fixing Set 2 75.97 151.94

10 Painting of cross arm, pole and numbering of poles etc. No. 2 364.66 729.31

TOTAL 10568.93

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compare to the rates applicable for normal soil.
LABOUR SCHEDULE CL-7 (B-1) B

LABOUR SCHEDULE - FOR RENOVATION OF EXISTING DISTRIBUTION TRANSFORMER SUB-STATION.


S. Particulars Unit Rate Year 2019-20
No. Year 2019-20 63 kVA X-mer 100 kVA X-mer 200 kVA X-mer
Qty. Amount Qty. Amount Qty. Amount

1 Shifting of material to pole pits Set 295.70 1 295.70 1 295.70 1 295.70


Fixing of LT distribution Box with Cable 0.00 0.00 0.00 0.00
2 63/100 kVA Each 1697.05 1 1697.05 1 1697.05 0 0.00
3 200 kVA Each 3162.68 0.00 0.00 1 3162.68
4 Handling/ Inst. Of Transformer Each LS 1 2081.57 1 3798.49 1 3798.49
5 Earthing of S/s LS LS 1 1823.28 1 1823.28 1 1823.28
TOTAL 5897.60 7614.51 9080.15

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE CL-8 (G-1)
SINGLE POLE MOUNTED LOW CAPACITY SINGLE PHASE / THREE PHASE 11/0.4 kV DISTRIBUTION
TRANSFORMER SUB-STATION
2
0 Year 2019-20
S. No. Particulars Unit Qty.
1
A
7 Rate Amount
m
-
1 Pit digging Each 1 ### 303.88 303.88
o
2
2 Stay Pit digging Each 4 u
0
### 273.49 1093.97
n
1
3 Shifting of materials to pole pits Set 1 t8
### 303.88 303.88
4 Transportation of pole from road side to pole pit Each 1 ### 379.85 379.85
5 DC/ V Cross arm fixing complete including insulator Each 1 ### 455.82 455.82
6 Pole erection complete including earthing Each 1 ### 759.70 759.70
7 Concreting of stay and base pad for poles Cft. 47 ### 24.31 1142.59
8 Stay erection complete Each 4 ### 197.52 790.09
9 Fixing of LA Set (2 Nos.) Set 1 ### 151.94 151.94
10 Anti climbing devices and danger board fixing Each 1 ### 75.97 75.97
11 Painting of cross arm & numbering of poles. Each 1 ### 121.55 121.55
12 Fixing of LT switch box & transformer wiring etc. Job 1 ### 227.91 227.91
13 Handling and installation of transformer on structure Job 1 ### 303.88 303.88
14 Fixing of D.O fuse complete with base channel Set 1 ### 151.94 151.94

15 Earthing of S/s including pit digging laying and conecting wires to supports X-mer etc. Set 1 ### 1063.58 1063.58

16 Installation & commissioning of TPN switch & DT Meter Job 1 ### 1002.80 1002.80
TOTAL ### 8329.34

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE CL-9
LABOUR SCHEDULE - PLINTH MOUNTED DISTRIBUTION TRANSFORMER S/s.
S. No. Particulars Unit Rate Year 2019-20
Year 2019-20
63 kVA X-mer 100 kVA X-mer 200 kVA X-mer
Qty. Amount Qty. Amount Qty. Amount
Pole Pit digging
1 (i) RSJ No. 385.69 2 771.39 2 771.39 0 0.00
(ii) H.Beam No. 439.69 0 0.00 0 0.00 2 879.38
2 Stay pit digging Each 295.70 4 1182.79 4 1182.79 4 1182.79
3 Shifting of material to pole pits Set 295.70 1 295.70 1 295.70 1 295.70
4 Transportation of pole from Road side to pole pit Each 295.70 2 591.40 2 591.40 2 591.40
5 Cross arm fixing complete. Each 1195.65 2 2391.30 2 2391.30 2 2391.30

6 (a) Pole erection complete including earthing (RSJ) Each 1118.51 2 2237.02 2 2237.02 0 0.00

(b) Pole erection complete including earthing H-Beam Each 1542.77 0.00 0.00 2 3085.55
7 Concreting Cmt. 907.92 11.47 10413.72 11.47 10413.72 11.89 10799.41
8 Stay erection complete Each 334.27 4 1337.07 4 1337.07 4 1337.07
9 Fixing of LA set. Set 449.98 1 449.98 1 449.98 1 449.98
10 Anticlimbing device and danger board fixing Each 90.00 2 179.99 2 179.99 2 179.99
11 Painting of HW/No. of pole Each 64.28 2 128.56 2 128.56 2 128.56
12 Fixing of LT distribution of Box 0.00 0.00 0.00 0.00
63/100 kVA Each 1697.05 1 1697.05 1 1697.05 0 0.00
200 kVA Each 3162.68 0.00 0.00 1 3162.68
13 Handling/ Inst. Of Transformer Each LS 1 2081.57 1 3798.49 1 3798.49
14 Earthing of S/s LS LS 1 1823.28 1 1823.28 1 1823.28
15 Fixing of DO fuse unit Set 497.67 1 497.67 1 497.67 1 497.67
16 Fixing of AB Switch Set 995.33 0 0.00 1 995.33 1 995.33
TOTAL 26078.47 28790.73 31598.57
S. No. Particulars Unit Rate Year 2019-20
Year 2019-20
63 kVA X-mer 100 kVA X-mer 200 kVA X-mer
Qty. Amount Qty. Amount Qty. Amount
The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE CL-10

LABOUR SCHEDULE FOR LAYING 1 KM. LENGTH OF 11 kV 3 CORE 95 SQMM. UNDER GROUND CABLE / 3
CORE 240 SQMM. UNDER GROUND CABLE / 3 CORE 400 SQMM. UNDER GROUND CABLE.

Year 2019-20
S. No. Particulars Unit
Qty. Amount

1 Cable trench excavation 1000x0.6x1=600 ordinary soil. Cube / Mtr. 600 160448.36

2 Laying of cable in trench, refilling & cosolidction Km. 1 69603.59

3 Making of straight through No. 3 13774.86

4 Making of cable terminactions No. 2 7767.16

5 Covering of cable with tiles Km. 1 3883.58

6 Spreading sand and forming with sand round the cable Km. 1 14112.16

7 Laying of RCC hume pipes Mtr 100 5773.71

8 Laying of GI Pipe Mtr 8 559.14

9 Laying of route & joint indicating stares No. 30 3190.73

10 Rate for reinstatement of roads (as per Nagar Nigam / Nagar Palika) LS 0.00

TOTAL 279113.30

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times
respectively as compared to the rates applicable for normal soil.

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE CL-10 (B)

LABOUR SCHEDULE - FOR AUGMENTATION OF 11/0.4 kV S/s CAPACITY ( ASSUMING 25 YEARS OF LIFE & 10
YEARS IN SERVICE )
Year 2019-20
S. Rate
Particulars Unit 63 kVA X-mer 100 kVA X-mer 200 kVA X-mer
No. Year 2019-20
Qty. Amount Qty. Amount Qty. Amount

Pole Pit digging


1 (i) RSJ No. 385.69 4 1542.77 4 1542.77 0 0.00
(ii) H.Beam No. 439.69 0 0.00 0 0.00 4 1758.76
2 Stay pit digging Each 295.70 4 1182.79 4 1182.79 4 1182.79
3 Shifting of material to pole pits Set 295.70 1 295.70 1 295.70 1 295.70

4 Transportation of pole from Road side to pole pit Each 295.70 4 1182.79 4 1182.79 4 1182.79

5 Cross arm fixing complete. Each 1195.65 2 2391.30 2 2391.30 2 2391.30


6
Pole erection complete including earthing (RSJ) Each 1118.51 2 2237.02 2 2237.02 0 0.00
(a)
(b) Pole erection complete including earthing H-Beam Each 1542.77 0.00 0.00 2 3085.55
7 Concreting Cft. 25.71 104 2674.14 104 2674.14 104 2674.14
8 Stay erection complete Each 334.27 4 1337.07 4 1337.07 4 1337.07
9 Fixing of LA set. Set 449.98 1 449.98 1 449.98 1 449.98
10 Anticlimbing device and danger board fixing Each 90.00 2 179.99 2 179.99 2 179.99
11 Painting of HW/No. of pole Each 64.28 2 128.56 2 128.56 2 128.56
12 Fixing of LT distribution of Box 0.00 0.00 0.00 0.00
63/100 kVA Each 1697.05 1 1697.05 1 1697.05 0 0.00
200 kVA Each 3162.68 0.00 0.00 1 3162.68
13 Handling/ Inst. Of Transformer Each LS 1 2081.58 1 3798.49 1 3798.49
14 Earthing of S/s LS LS 1 1823.28 1 1823.28 1 1823.28
15 Fixing of DO fuse unit Set 531.79 1 531.79 1 531.79 1 531.79
16 Fixing of AB Switch Set 1063.58 0 0.00 1 1063.58 1 1063.58
TOTAL 19735.81 22516.30 25046.45
The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE CL-11

LABOUR SCHEDULE FOR INSTALLATION OF COMPACT R.M.U. 11 kV CLASS SF6 / VCB TYPE (1
INCOMING + 2 BREAKER + 1 OUTGOING)
S. Particulars Unit Qty. Year 2019-20
No.
Rate Amount

1 Digging and concreting of foundation of R.M.U. No. 1 3038.80 3038.80

2 Handling & installation of R.M.U. on foundation. No. 1 2926.78 2926.78

3 Fixing of incoming & outgoing cables on terminals of R.M.U. L.S. 1 911.59 911.59

4 Earthing of RMU including pit digging, laying and connecting wires to RMU etc. Set 1 1063.57 1063.57

5 Lettering the R.M.U. with enamel paint and also writing single line diagram of each Per 1 751.92 751.92
panel, caution Board, Danger Board etc. including cost of paint, Brush etc. Panel

6 Total Labour Charges 8692.66

7 Total Labour Charges (Rounded Off) 8693.00


LABOUR SCHEDULE DL-1
LABOUR SCHEDULE OF LT LINE ON PCC SUPPORTS PER KM.
R Year 2019-20
S.No. Particulars Unit Qty. a
R Rate 3P5W 3P4W 1P3W
ta
1 Survey Km. 1 e
t
2 Tree cutting Km. 1 ###e 4558.19 4558.19 4558.19 4558.19
f
3 Approach Clearance Km. 1 o
4 Pit digging No. 17 ###r 303.88 5165.95 5165.95 5165.95
5 Shifting of materials to pole pits No. 17 ### 60.78 1033.19 1033.19 1033.19
2
6 Stay Pit digging No. 9 0
### 273.49 2461.42 2461.42 2461.42
1
7 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 17 5
### 303.88 5165.95 5165.95 5165.95
-
2
8 Fixing of LT clamps complete per location including insulator fixing No. 22 ###
0 75.97 1671.34 1671.34 1671.34
1
9 Pole erection complete with earthing No. 17 ###
6 759.70 12914.88 12914.88 12914.88

10 Concreting of stay and base pad for poles Cft. 100 ### 24.31 2431.04 2431.04 2431.04
11 Stay erection complete No. 9 ### 212.72 1914.44 1914.44 1914.44
12 Painting of cross arm and numbering of poles. No. 22 ### 60.78 1337.07 1337.07 1337.07
13 Carpet guarding Span 1 ### 911.64 911.64 911.64 911.64
14 Diamond Guarding Pair 17 ### 60.78 1033.19 1033.19 1033.19
TOTAL 40598.30 40598.30 40598.30
15 Stringing of line
(i) 3P 5W (4 Weasel + 1 Squirrel) Each 5 16685.91 0.00 0.00
(ii) 3P 4W (3 Weasel + 1 Squirrel) Each 4 0.00 13286.93 0.00
(ii) 1P 3W (2 Weasel + 1 Squirrel) Each 3 0.00 0.00 9337.06
57284.21 53885.23 49935.36

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compare to the rates applicable for normal soil.
LABOUR SCHEDULE DL-2
LABOUR CHARGES PER KM. OF LT LINE ON R.S. JOIST
3P 5W LT line on RSJ 125x70 mm Max 3P 5W LT line on RSJ 175x85 mm Max
span 45 Mtr. span 65 Mtr.
S.
Particulars Unit Qty. Year 2019-20 Qty. Year 2019-20
No.

Rate Amount Rate Amount


1 Survey Km. 1 1
2 Tree cutting Km. 1 4558.19 4558.19 1 4558.19 4558.19
3 Approach Clearance Km. 1 1
4 Pit digging No. 22 303.88 6685.35 15 303.88 4558.19
5 Shifting of materials to pole pits No. 22 60.78 1337.07 15 60.78 911.64
6 Stay pit digging No. 12 273.49 3281.90 9 273.49 2461.42
Transportation of pole from road side to pole pit for
7 No. 22 243.10 5348.28 15 303.88 4558.19
a lead of 1 Km.
8 Fixing of 5 Pin cross arm No. 27 75.97 2051.19 20 75.97 1519.40
9 Pole erection complete with earthing No. 22 607.76 13370.70 15 759.70 11395.48
10 Concreting of supports Cft. 508 24.31 12349.66 352 24.31 8557.25
11 Stay erection complete No. 12 303.88 3646.55 9 212.72 1914.44
Painting of cross arm, pole and numbering of
12 No. 22 303.88 6685.35 15 303.88 4558.19
poles
13 Carpet guarding Span 1 911.64 911.64 1 911.64 911.64
14 Diamond guarding Pair 22 60.78 1337.07 15 60.78 911.64
TOTAL 61562.94 46815.67
15 Stringing of line 3 Ph. 5 Wire Each 5 12622.69 5 16409.49
74185.63 63225.16

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compared to the rates applicable for normal soil.
LABOUR SCHEDULE DL-3 (E-1)
LABOUR SCHEDULE FOR CONVERSION OF LT LINE INTO 11 kV LINE
Year 2019-20
S. No. Particular Unit Qty.
Rate Amount

1 Survey Km. 1
2 Tree cutting Km. 1 2279.10 2279.10
3 Approach Clearance Km. 1
4 Pit digging for 140 Kg PCC pole No. 1 303.88 303.88
5 Transportation of PCC pole from road side to pole pit. No. 1 303.88 303.88
6 Pole erection complete earthing No. 1 759.70 759.70
7 Dismantalling of L.T. cross arm No. 17 69.89 1188.17
8 Dismantalling of L.T. conductor 3 Phase 4 wire Km. 4 1671.34 6685.35
9 Shifting of material to pole pits No. 17 60.78 1033.19
10 V cross arm and top clamp fixing complete No. 17 91.16 1549.79
11 Earthing of metallic parts (V-cross and top clamp) No. 17 212.72 3616.17
12 Pin insulator fixing with GI pin No. 51 21.27 1084.85
13 Anti climbing devices and danger board. No. 17 75.97 1291.49
14 Painting of cross arm, pole and numbering of poles No. 17 75.97 1291.49
15 Stringing of line weasel / Rabbit all three conductor with binding on insulators Km. 1 10028.02 10028.02
16 Carpet guarding. No. 1 1519.40 1519.40
17 Twisting of jointing sleeves No. 3 66.85 200.56
18 Re-aligning of leaning PCC pole No. 5 395.04 1975.22
TOTAL 35110.23

Note:- In 3 Phase 4 Wire LT system, 4th conductor i.e. neutral conductor will be returned to area stores and depreciated value of neutral conductor will be
reduced at the time of estimate framing. L.T. R, Y and B Phase conductor will be reutilised and where ever new conductor for 11 KV line required, the same
may be incorporated in the estimate.

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE DL-4

LABOUR SCHEDULE PER KM. OF LT LINE CONVERSION MAX. SPAN OF 45 MTR.


S. Particulars Unit Year
No. 2019-20 1 Ph. 2 Wire to 1 Ph. 3 1 Ph. 2 Wire to 3 Ph. 4 1 Ph. 3 Wire to 3 Ph. 4 Wire 1 Ph. 3 Wire to 3 Ph. 5 Wire
Wire Conversion Wire Conversion Conversion Conversion

Year 2019-20

Qty. Amount Qty. Amount Qty. Amount Qty. Amount

Shifting of materials to
1 No. 75.97 22 1671.34 22 1671.34 22 1671.34 22 1671.34
pole-pit

Fixing of LT cross arm &


2 shackle insulator per No. 136.75 24 3281.90 24 3281.90 24 3281.90 24 3281.90
location

3 Painting of LT cross arm No. 30.39 24 729.31 24 729.31 24 729.31 24 729.31

Each
4 Stringing of conductor 6442.24 1 6442.24 2 12884.49 1 6442.24 2 12884.49
wire

5 Diamond guarding No. 48.62 44 2139.31 44 2139.31 44 2139.31 44 2139.31

TOTAL 14264.10 20706.35 14264.10 20706.35

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE DL-5 (E-2)
LABOUR SCHEDULE FOR CONVERSION OF 1 KM. 1 PHASE 3 WIRE LT LINE INTO 11 kV LINE
Year 2019-20
S.No. Particulars Unit Qty.
Rate Amount

1 Survey Km. 1
2 Tree cutting Km. 1 2279.10 2279.10
3 Approach Clearance Km. 1
4 Pit digging for 140 Kg PCC pole No. 1 303.88 303.88
5 Transportation of PCC pole from road side to pole pit. No. 1 303.88 303.88
6 Pole erection complete with earthing No. 1 759.70 759.70
7 Dismantling of L.T. Cross arm. No. 22 69.89 1537.63
8 Dismantling of LT conductor 3 phase 4 wire Km. 3 1671.34 5014.01
9 Shifting of materials to pole pits. No. 22 60.78 1337.07
10 V - Cross arm and top clamp fixing complete. No. 22 91.16 2005.60
11 Earthing of metallic parts. (V - cross and top clamp) No. 22 212.72 4679.74
12 Pin Insulator fixing with GI pins. No. 66 21.27 1403.92
13 Anti Climbing devices and danger board fixing No. 22 75.97 1671.34
14 Painting of cross arm, pole and numbering of poles No. 22 75.97 1671.34
15 Stringing of line Weasel / Rabbit all three conductor with binding on insulators. Km. 1 10028.02 10028.02
16 Stringing of line squirrel conductor. Km. 1.03 3342.67 3442.95
17 Carpet guarding with stay. No. 1 1519.40 1519.40
18 Carpet guarding without stay. No. 21 182.33 3828.88
19 Twisting for jointing sleeves No. 3 66.85 200.56
20 Re-aligning of leaning PCC pole No. 5 395.04 1975.22
21 Laying of PVC insulated cable 16 sqmm 2 core unarmoured with 4 mm G.I. wire. Mtr. 10.5 714.12 7498.23

TOTAL 51460.47

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE DL-6 (E-3)
LABOUR SCHEDULE FOR CONVERSION OF 1 KM. 3 PHASE 5 WIRE LT LINE INTO 11 kV LINE
Year 2019-20

S.No. Particulars Unit Qty.


Rate Amount

1 Survey Km. 1
2 Tree cutting Km. 1 2279.10 2279.10
3 Approach Clearance Km. 1
4 Pit digging for 140 Kg PCC pole No. 1 303.88 303.88
5 Transportation of PCC pole from road side to pole pit. No. 1 303.88 303.88
6 Pole erection complete with earthing No. 1 759.70 759.70
7 Dismantling of L.T. cross arm. No. 22 69.89 1537.63
8 Dismantling of LT conductor 3 phase 4 wire Km. 5 1671.34 8356.69
9 Shifting of materials to pole pits. No. 22 60.78 1337.07
10 V - Cross arm and top clamp fixing complete. No. 22 91.16 2005.60
11 Earthing of metallic parts (V - cross and top clamp) No. 17 212.72 3616.17
12 Pin Insulator fixing with GI pins. No. 66 21.27 1403.92
13 Anti Climbing devices and danger board fixing No. 22 75.97 1671.34
14 Painting of cross arm, pole and numbering of poles No. 22 75.97 1671.34
15 Stringing of line Weasel / Rabbit all three conductor with binding on insulators. Km. 1 10028.02 10028.02
16 Stringing of line squirrel Conductor. Km. 1.03 3342.67 3442.95
17 Carpet guarding with stay No. 1 1519.40 1519.40
18 Carpet guarding without stay. No. 21 182.33 3828.88
19 Twisting for jointing sleeves No. 3 66.85 200.56
20 Re-aligning of leaning PCC pole No. 5 395.04 1975.22
21 Laying of PVC insulated cable 16 Sqmm 2 Core unarmoured with 4 mm G.I. wire Mtr. 1050 7.14 7497.11
TOTAL 53738.45

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE DL-6 (A)

LABOUR SCHEDULE FOR REPLACEMENT OF EXISTING 1 KM. 3 PHASE 5 WIRE L.T. LINE ON BARE
CONDUCTOR WITH A.B. CABLE FOR URBAN AREA
Year 2019-20

S.No. Particulars Unit Qty. Using 1100 V grade AB Cable


3x50+1x25+1x35 sqmm.

Rate Amount
1 Survey Km. 1
2 Tree cutting Km. 1 4585.63 4585.63
3 Approach Clearance Km. 1
4 Shifting of materials to pole pits. No. 20 60.78 1215.52

Fixing of LT clamps complete per location including service ring, Distrbution box ,
5 No. 30 75.96 2278.86
piercing connector

6 Straight through Jointing No. 20 91.16 1823.16

7 Stringing of 3 Phase 5 Wire (Cable ) Each 1 16409.43 16409.43

Dismentling of Bare Conductor (50% of Transport & Labour Charges other than
8 0 0.00 17380.74
Dismentling )
TOTAL 43693.33
9 Transportation Charges 1 7627.23 7627.23
Grand Total 51320.56
Grand Total (ROUND OFF) 51321.00

file:///conversion/tmp/scratch/433924070.xls
LABOUR SCHEDULE DL-6 (B)
LABOUR SCHEDULE FOR ADDITIONAL L.T. MID SPAN JOIST SUPPORT WITH A.B. CABLE
Year 2019-20
S.No. Particulars Unit Qty.
Rate Amount
1 Pit digging No. 1 303.88 303.88
2 Shifting of materials to pole pits No. 1 60.78 60.78
3 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 1 303.88 303.88

Fixing of LT clamps complete per location including Service ring, Distribution box, piercing
4 No. 1 75.97 75.97
connector,etc.

5 Pole erection complete with earthing No. 1 759.70 759.70

6 Concreting of base pad and pole Cft. 18 24.31 437.59


7 Painting of cross arm and numbering of poles. No. 1 60.78 60.78
TOTAL 2002.57

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as
compare to the rates applicable for normal soil.
COST SCHEDULE -- DL - 7
1 kM OF 3 PHASE 5 WIRE LINE ON 140 KG. PCC POLE 8 MTR. LONG USING AB XLPE CABLE FOR RURAL AREAS WITH MAXIMUM SPAN 50 MTRS. AND R.S. JOIST / H-BEAM POLE SUPPORT USING AB
XLPE CABLE WITH MAXIMUM SPAN 50 METER URBAN AREA

Year 2019-20

RS Joist (175X85) mm 9.3 Mtr Long i.e. 19.495 kg/mtr x H-BEAM 152x152 mm 37.1 Kg/Mtr 9.0 Mtr long i.e. 333.9
140 Kg, 8.0 Mtr. long PCC support
9.3 mtr = 181.30 kg x 20 No = 3626.07 Kgs Kg/pole x 20 Nos = 6678 Kgs

S.
PARTICULARS Unit Qty.
No. Using 1100 V grade AB Using 1100 V grade AB Using 1100 V grade AB
Using 1100 V grade AB Cable Using 1100 V grade AB Cable Using 1100 V grade AB Cable
Cable 3x50 + 1x25 + 1x35 Cable 3x35 + 1x16 + 1x35 Cable 3x35 + 1x16 + 1x35
3x50 + 1x25 + 1x35 sqmm. 3x50 + 1x25 + 1x35 sqmm. 3x35 + 1x16 + 1x35 sqmm.
sqmm. sqmm. sqmm.

Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount Rate Amount
1 Survey Km. 1
2 Tree cutting Km. 1 4558.19 4558.19 4558.19 4558.19 4558.19 4558.19 4558.19 4558.19 4558.19 4558.19 4558.19 4558.19
3 Approach Clearance Km. 1
4 Pit digging No. 20 303.88 6077.59 303.88 6077.59 303.88 6077.59 303.88 6077.59 303.88 6077.59 303.88 6077.59
Shifting of materials to pole
5
pits
No. 20 60.78 1215.52 60.78 1215.52 60.78 1215.52 60.78 1215.52 60.78 1215.52 60.78 1215.52
6 Stay Pit digging No. 12 273.49 3281.90 273.49 3281.90 273.49 3281.90 273.49 3281.90 273.49 3281.90 273.49 3281.90
Transportation of pole from
7 road side to pole pit for a lead No. 20 303.88 6077.59 303.88 6077.59 303.88 6077.59 303.88 6077.59 303.88 6077.59 303.88 6077.59
of 1 Km.

Fixing of LT clamps complete


per location including Service
8
ring, distribution box, piercing
No. 20 75.97 1519.40 75.97 1519.40 75.97 1519.40 75.97 1519.40 75.97 1519.40 75.97 1519.40
connector

Pole erection complete with


9
earthing
No. 20 759.70 15193.97 759.70 15193.97 759.70 15193.97 759.70 15193.97 759.70 15193.97 759.70 15193.97
Concreting of stay and base
10
pad for poles
Cft. 119 24.31 2892.93 24.31 2892.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 Concreting of stay and pole Cft. 299 0.00 0.00 0.00 0.00 24.31 7268.80 24.31 7268.80 0.00 0.00 0.00 0.00
12 Concreting of stay and pole Cft. 440 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.31 10696.56 24.31 10696.56
13 Stay erection complete No. 12 212.72 2552.59 212.72 2552.59 212.72 2552.59 212.72 2552.59 212.72 2552.59 212.72 2552.59
Painting of cross arm and
14
numbering of poles.
No. 20 60.78 1215.52 60.78 1215.52 303.88 6077.59 303.88 6077.59 303.88 6077.59 303.88 6077.59
15 TOTAL 44585.20 44585.20 53823.13 53823.13 57250.89 57250.89
16 Stringing of line
17 (i) 3P 5W ( Cable ) Each 1 16409.49 16409.49 16409.49 16409.49 16409.49 16409.49 16409.49 16409.49 16409.49 16409.49 16409.49 16409.49
18 (ii) 3P 4W ( Cable ) Each 0 13066.83 0.00 13066.83 0.00 13066.83 0.00 13066.83 0.00 13066.83 0.00 13066.83 0.00
19 (ii) 1P 3W ( Cable ) Each 0 9724.14 0.00 9724.14 0.00 9724.14 0.00 9724.14 0.00 9724.14 0.00 9724.14 0.00
TOTAL 60994.69 60994.69 70232.62 70232.62 73660.38 73660.38
r
8
a
.
COST SCHEDULE -- DL - 8 d0
for D-6 (3)
e
1 kM OF 1 PHASE 3 WIRE LINE ON 140 KG. PCC POLE 8 MTR. LONG USING AB XLPE CABLE
FOR RURAL AREAS WITH MAXIMUM SPAN 50 MTRS. M
A
tB
r
.C
2015-16 Year 2019-20
a 140 Kg, 8.0 Mtr. long PCC support
S. b
PARTICULARS Unit Qty. ll
No. Using 1100 V grade AB Cable 1x25 + 1x16 + 1x25 sqmm.
o
e
R
n
a
g
1 Rate Amount
t
1 2 3 4 ### x
e 5 6
P
2
1 Survey Km. 1 C
5
2 Tree cutting Km. 1 C 4558.19 4558.19
3 Approach Clearance Km. 1 +
s
4 Pit digging No. 20 ### u
1 303.88 6077.59
p
x
5 Shifting of materials to pole pits No. 20 ### p 60.78 1215.52
1
6 Stay Pit digging No. 12 ### o
6 273.49 3281.90
r
Transportation of pole from road side to pole pit for a lead of 1 t
7 No. 20 ### + 303.88 6077.59
Km.
Fixing of LT clamps complete per location including Service 1
8 No. 20 ###
x 75.97 1519.40
ring, distribution box, piercing connector etc.
2
9 Pole erection complete with earthing No. 5
20 ### 759.70 15193.97

10 Concreting of stay and base pad for poles Cft. 119 ###
s 24.31 2892.93
q
11 Stay erection complete No. 12 ###m 212.72 2552.59
12 Painting of cross arm and numbering of poles. No. 20 ###m 60.78 1215.52
.
13 TOTAL 44585.19
14 Stringing of line
15 (ii) 1P 3W ( Cable ) Set. 1 ### 9724.14 9724.14
Grand TOTAL ### 54309.33
GRAND TOTAL (ROUND OFF) 54309.00
COST SCHEDULE -- DL - 9 for D-6 (4)
1 kM OF 3 PHASE 4 WIRE LINE ON 140 KG. PCC POLE 8 MTR. LONG USING AB XLPE CABLE FOR
PUMP CONNECTION UPTO 5 HP & 5 CONNECTION PER KM. WITH MAXIMUM SPAN 50 MTRS.

Year 2019-20

S. 140 Kg, 8.0 Mtr. long PCC support


PARTICULARS Unit Qty.
No. Using 1100 V grade AB Cable 3x16 + 1x25 sqmm.
Rate
1 2 3 4 5
1 Survey Km. 1
2 Tree cutting Km. 1 4558.19
3 Approach Clearance Km. 1
4 Pit digging No. 20 303.88
5 Shifting of materials to pole pits No. 20 60.78
6 Stay Pit digging No. 12 273.49

7 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 20 303.88

Fixing of LT clamps complete per Set including Service ring, Spring


8 Set. 5 312.19
loaded distribution Box, piercing connector, etc.

Fixing of Piller Box (including Transportation) with concreting of


9 No. 1 4292.60
columns and bottom area of Piller box
10 Pole erection complete with earthing No. 20 759.70
11 Concreting of stay and base pad for poles Cft. 119 24.31
12 Stay erection complete No. 12 212.72
13 Painting of cross arm and numbering of poles. No. 20 60.78
14 TOTAL
15 Stringing of line
16 (ii) 3P 4W ( Cable ) Set. 1 13066.82
GRAND TOTAL
GRAND TOTAL (ROUND OFF)
Year 2019-20
, 8.0 Mtr. long PCC support
grade AB Cable 3x16 + 1x25 sqmm.
Amount
6

4558.19

6077.59
1215.52
3281.90

6077.59

1560.94

4292.60

15193.97
2892.93
2552.59
1215.52
48919.34

13066.82
61986.16
61986.00
LABOUR SCHEDULE DL-10 , HVDS 200 KVA

HVDS SYSTEM OF 200 kVA PARENT DISTRIBUTION TRANSFORMER TAKING 4 KM. LT TO BE CONVERTED
Year 2019-20
S. No. Particulars Unit Qty.
Rate Amount
1 Pit digging Each 10 303.88 3038.79
2 Stay Pit digging Each 40 273.49 10939.66
3 Shifting of materials to pole pits Set 10 303.88 3038.79
4 Transportation of pole from road side to pole pit Each 10 379.85 3798.49
5 DC Cross arm fixing complete including insulator Each 10 455.82 4558.19
6 Pole erection complete including earthing Each 10 759.70 7596.99
7 Concreting of stay and base pad for poles Cft. 315 24.31 7657.76
8 Stay erection complete Each 40 197.52 7900.87
9 Fixing of LA Set (2 Nos.) Set 10 151.94 1519.40
10 Anti climbing devices and danger board fixing Each 10 75.97 759.70
11 Painting of cross arm & numbering of poles. Each 10 121.55 1215.52
12 Painting of V cross arm, Top clamps & numbering of poles. Each 65 75.96 4937.52
13 Fixing of LT switch box & transformer wiring etc. Job 10 227.91 2279.10
14 Handling and installation of transformer on structure Job 10 303.88 3038.79
15 Fixing of D.O fuse complete with base channel Set 10 151.94 1519.40
16 Earthing of S/s including pit digging laying and conecting wires to supports X-mer etc. Set 10 1063.58 10635.78
17 Installation & commissioning of TPN switch & DT Meter Job 10 1002.80 10028.02
18 Fixing of V cross arm with top clamp Set 65 91.16 5925.26
19 Insulator fixing with GI pin Set 195 21.27 4147.10
20 Shifting of material to pole side other than xmer location Set 55 60.77 3342.12
21 Earthing of Metals parts of pole No 55 212.02 11661.37
22 Stringing of 11 kv line km 4 10027.99 40111.95
23 Dismentaling of LT line (conductor and Bracket) km 4 16665.24 66660.98
TOTAL 216311.55

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively
as compared to the rates applicable for normal soil.
LABOUR SCHEDULE DL-11 , HVDS 100 kVA

HVDS SYSTEM OF 100 kVA PARENT DISTRIBUTION TRANSFORMER TAKING 3 KM. LT TO BE CONVERTED
S. Year 2019-20
Particulars Unit Qty.
No. Rate Amount
1 Pit digging Each 8 303.88 2431.04
2 Stay Pit digging Each 30 273.49 8204.75
3 Shifting of materials to pole pits Set 8 303.88 2431.04
4 Transportation of pole from road side to pole pit Each 8 379.85 3038.79
5 DC Cross arm fixing complete including insulator Each 8 455.82 3646.55
6 Pole erection complete including earthing Each 8 759.70 6077.59
7 Concreting of stay and base pad for poles Cft. 237 24.31 5761.55
8 Stay erection complete Each 30 197.52 5925.65
9 Fixing of LA Set (2 Nos.) Set 8 151.94 1215.52
10 Anti climbing devices and danger board fixing Each 8 75.97 607.76
11 Painting of cross arm & numbering of poles. Each 8 121.55 972.41
12 Painting of V cross arm, Top clamps & numbering of poles. Each 45 75.96 3418.28
13 Fixing of LT switch box & transformer wiring etc. Job 8 227.91 1823.28
14 Handling and installation of transformer on structure Job 8 303.88 2431.04
15 Fixing of D.O fuse complete with base channel Set 8 151.94 1215.52
16 Earthing of S/s including pit digging laying and conecting wires to supports X-mer etc. Set 6 1063.58 6381.47
17 Installation & commissioning of TPN switch & DT Meter Job 6 1002.80 6016.81
18 Fixing of V cross arm with top clamp Set 45 91.16 4102.10
19 Insulator fixing with GI pin Set 135 21.27 2871.07
20 Shifting of material to pole side other than xmer location Set 37 60.77 2248.34
21 Earthing of Metals parts of pole No 37 212.02 7844.92
22 Stringing of 11 kv line km 3 10027.99 30083.96
23 Dismentaling of LT line (conductor and Bracket) km 3 16665.24 49995.73
TOTAL 158745.17
The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten
times respectively as compared to the rates applicable for normal soil.
LABOUR SCHEDULE DL-12 , HVDS 63 KVA
HVDS SYSTEM OF 63 kVA PARENT DISTRIBUTION TRANSFORMER TAKING 2 KM. LT TO BE CONVERTED

Year 2019-20
S.No. Particulars Unit Qty.
Rate Amount
1 Pit digging Each 6 303.88 1823.28
2 Stay Pit digging Each 25 273.49 6837.29
3 Shifting of materials to pole pits Set 6 303.88 1823.28
4 Transportation of pole from road side to pole pit Each 6 379.85 2279.10
5 DC Cross arm fixing complete including insulator Each 6 455.82 2734.92
6 Pole erection complete including earthing Each 6 759.70 4558.19
7 Concreting of stay and base pad for poles Cft. 196 24.31 4764.83
8 Stay erection complete Each 25 197.52 4938.04
9 Fixing of LA Set (2 Nos.) Set 6 151.94 911.64
10 Anti climbing devices and danger board fixing Each 6 75.97 455.82
11 Painting of cross arm & numbering of poles. Each 6 121.55 729.31
12 Painting of V- cross arm, Top clamps & numbering of poles. Each 45 75.96 3418.28
13 Fixing of LT switch box & transformer wiring etc. Job 6 227.91 1367.46
14 Handling and installation of transformer on structure Job 6 303.88 1823.28
15 Fixing of D.O fuse complete with base channel Set 6 151.94 911.64
16 Earthing of S/s including pit digging laying and conecting wires to supports X-mer etc. Set 4 1063.58 4254.31
17 Installation & commissioning of TPN switch & DT Meter Job 4 1002.80 4011.21
18 Fixing of V cross arm with top clamp Set 45 91.16 4102.10
19 Insulator fixing with GI pin Set 195 21.27 4147.10
20 Shifting of material to pole side other than xmer location Set 39 60.77 2369.87
21 Earthing of Metals parts of pole No 39 212.02 8268.97
22 Stringing of 11 kv line km 2 10027.99 20055.97
23 Dismentling of LT line (conductor and Bracket) km 2 16665.24 33330.49

TOTAL 119916.36

The rates are proposed for normal soil conditions. In case of soft rock & hard rock, the rates of pit digging will be taken as two times and ten times respectively as compared to the rates
applicable for normal soil.

Вам также может понравиться