Академический Документы
Профессиональный Документы
Культура Документы
ENGINEERING
1
Chapter One
Introduction and Concepts
of Hydropower
2
Introduction
• Hydropower is the energy extracted from the
natural potential of usable water resources.
It is the capture of the energy of moving
water for some useful purpose.
• When the energy of flowing water is used to
run turbines, then the electricity generated is
called Hydroelectric power.
• The head causing flow, runs the turbine
blades, and thus producing electricity from
the generator coupled to the turbine.
3
4
5
6
Hydrologic cycle….
• Evaporation from
water bodies
• Water vapour
moves upwards
• Cloud formation
• Condensation
• Precipitate
• Interception
• Transpiration
• Infiltration
• Runoff–streamflow
• Deep percolation
• Ground water flow
Catchment area….
• A watershed is a geographical unit in
which the hydrological cycle and its
components can be analysed.
Watershed/
catchment
Watershed/
catchment
Introduction…
• Any water resource program of which a
hydropower scheme may has environmental
and social impacts, which must be taken into
consideration at the initial planning stage.
• Also, legal and political implications must be
carefully considered.
• The latest technological advancements in
hydroelectric power generation permit the
selection of proper designs incorporating
environmental and social requirements.
10
Terms and parameters pertinent
to hydropower schemes
11
• Dead storage. The storage in the reservoir
resulting from the accumulation of sediment
• Live storage. The volume of water that is stored in
a reservoir that can be used for power generation
and etc.
• Spillway. The structure over or through which
reservoir flood flows are discharged.
• Forebay. The impoundment of water above a dam
or hydroelectric plant.
• Baseload. The minimum constant amount of load
connected to the power system over a given period
of time
12
• Peakload. The greatest amount of power
given out or taken by a machine or power
distribution system in a given time
• Generator. A machine that converts
mechanical energy in to electrical energy
• Head. The difference in elevation between
the head water surface and the tail water
surface
• Turbine. A machine which converts the
kinetic energy of fluids to mechanical energy
13
Appurtenant features: Any physical feature other than the
dam, such as the
spillway, outlet, powerhouse, penstock, tunnels, etc.
Excess Inflow
Normal Pool Level, NPL
Intake
Structure
Spillway
Bottom Outlet
Dead Storage
Advantages of hydropower
Hydropower plants do not require fuel
well suited for peaking power condition
Hydropower plants are highly
reliable, robust, and have higher life
expectancy
Thermal & nuclear 25-30 years
Hydropower 50-100 years
Hydropower is clean and free of
environmental pollutions.
Hydropower has by far the highest energy
conversion efficiency, at 80-90% (Thermal &15
nuclear 30-60 %)
Sources of Energy
• Energy can be described as potential for
work, which may be withdrawn if needed.
16
Sources of energy...
Two major sources of energy (Status)
20
21
22
Nuclear power plant
23
• Simply, fission is the action of splitting the
nucleus, or specifically
24
Wind turbine plant
25
Ocean tides
• There is a tremendous energy in ocean tides and
waves but it is very difficult to harness this power.
27
History of hydropower development
• The first hydroelectric power plant was
installed in England in 1870.
• Industrial use of hydropower started in 1880
• The largest projects, Itaipu in Brazil with
14,000 MW and Three Gorges in China with
22,400 MW,
• Hydropower projects are always site-specific
and thus designed according to the river
system they inhabit.
28
Hydropower status in the world
• The installed capacity of hydropower by the end of
2008 contributed 16% of worldwide electricity
supply
• The total worldwide technical potential for
hydropower generation is 14,576 TWh/yr
• Worldwide total installed hydropower capacity in
2009 was 926 GW, producing annual generation of
3,551 TWh/y
• Undeveloped capacity ranges from about 47% in
Europe and North America to 92% in Africa
29
Hydropower generation (TWh) by region
30
Regional hydropower technical potential
31
8000
Power (Twh/yr)
7000
6000
5000
4000
3000
2000
1000
0
Potential Exploited
32
Utilized percentage worldwide
60
50
40
%age utilized
30
20
10
33
Hydropower Potential and Its Development in Ethiopia
• The water power (electricity generation), came to
existence in Ethiopia at the beginning of 1930's
• The first hydropower scheme was Abasamuel (Awash
basin) commissioned in 1932
• This station was capable of generating 6 MW and
operational up to 1970
• In Ethiopia, by 1990,
– about 94 % of the energy requirement satisfied through the
traditional energy sources (wood, charcoal…)
– the remaining 6% through modern sources such as fuel oil, gas
and electricity
• Ethiopia has got substantial hydropower potential from
which very small amount has been utilized yet
34
• Ethiopia is naturally endowed with quite a
substantial amount of water resource potential.
35
• The hydropower potential of Ethiopia is very
considerable more than 45,000 MW
36
37
Potential Gross hydro-
Runoff irrigable land electric potential Estimated ground
River basin Area (km2) (Bm3) (ha) GWH/yr water potential (Bm3)
Tekeze 8235*** 8.2 83,368 5,980 0.2
Abbay 199,812 54.8 815,581 78,820 1.8
Baro-Akobo 75,912 23.6 1,019,523 13,765 0.28
Omo-Gibe 79,000 16.6 36,560 0.42
Rift Valley 52,739 5.6 139,300 * 800 0.1
Mereb 5,900 *** 0.65 67,560 0.05
Afar /Denakil 74,002 **** 0.86 158,776
Awash 112,696 4.9 134,121 4,470 0.14
Aysha 2,223 **** - - - -
Ogaden 77,121 **** - - - -
Wabi-
Shebelle* 202,697 ** 3.16 237,905 5,440 0.07
39
Under construction or Proposed
Hydroelectric
station Type Capacity Year completed River
Gilgel Gibe III Reservoir 1870 2015 Omo River
Fincha Amerti
Neshe Reservoir 100
Gilgel Gibe IV Reservoir 1472 Omo River
Gilgel Gibe V Reservoir 660 Omo River
Grand Ethiopian
Renaissance Reservoir 6000 2017 Blue Nile River
Halele
Worabesa Reservoir 440 2015 Omo River
Chemoga Yeda Reservoir 278 2015
40
Chapter two
41
Classification and Types of
Hydropower Plants
• Hydropower plants could be classified on
the basis of
– The hydraulic features of the plant
– Operating features
– Location & topographical features
– Presence or absence of storage
– The range of operating heads
– The hydraulic features of the plant
42
Classification based on hydraulic
features
The basic hydraulic principle governs the type
44
Run-off-river plants
Navigation lock
47
ROR Hydropower plant in Germany
2. Diversion Canal
the flow from the impounded water in
the river upstream of the barrage is
diverted in to a power canal and rejoins
the river further downstream after
passing through the power station
49
Diversion canal plant
3. Valley dam plants (medium to high head
plant)
51
Valley dam plants
52
Valley dam Hydropower plant
54
4. Storage Plants / high head plants
– are essentially having an upstream
storage / reservoir of sufficient size.
– the dam structure is separated from the
power station by a considerable distance
over which the water is conveyed by a
tunnel or a canal.
55
Storage/high head plant
Storage
56
Pumped Storage Plants
generates power during peak hours, but
during the off-peak hours, water is
pumped back from the tail water pool to
the head water pool for future use.
57
Pumped Storage Plant
Pumped Storage
Upper Reservoir
Lower Reservoir
59
60
Oskar VonMiller
power plant in
Germany
61
62
63
Potential site in our country, Abaya-Chamo lakes
GOD Bridge
64
BASIC CONCEPTS
• Pumped/storage hydropower developments
are energy-storing systems.
– Water is pumped from a lower reservoir to a
higher one,
– utilizing low-cost "dump" power produced during
periods of low demand by power plants
– which can be operated economically at a
constant load.
• The water in the higher reservoir is then
released through turbines to produce power
needed during periods of peak demand.
65
• In this system more energy is expended in
pumping than can be produced by the
turbines,
66
Figure Graphic accounting of energy storage cycle for pumped/storage
hydropower development.
67
APPLICATION SITUATIONS
• Three basic situations should be considered
for planning purposes:
– Short-term peaking,
– Weekly peaking, and
– Seasonal peaking.
68
Short-term peaking
• This involve turbines operating for a few
hours each day
69
Weekly peaking
• This requires operating turbines in generating
mode to meet several peak loads during the
workweek,
• Refilling the upper reservoir to a degree each
day but gradually drawing down the upper
reservoir during the week
• Major recovery pumping during the weekend
when loads are low.
• This requires relatively large reservoirs.
70
Figure Weekly electric load variation and
pumped/storage operation.
71
Seasonal peaking
• Seasonal peaking would require very large
upper reservoir storage
72
ARRANGEMENT OF UNITS
1. Complete pump and motor units and
separate but complete turbine and
generator units, involving four machines
2. Multistage pump and impulse turbine with a
common motor/generator, involving three
machines
3. A single-stage pump/turbine and a common
motor/generator involving two machines in
which units have reversible directions for
operation
73
74
PLANNING AND SELECTION
• Two Important parameters in planning for
pumped/storage hydropower development are
– Head and
– Discharge to be utilized in sizing the plant.
76
• Example
Tidal power Plants
77
Classification on the basis of operation
Based on actual operation in meeting the
demand
Nuclear
Thermal
Time (months)
Place of hydropower in a power system.
Classification based Classification based
on plant capacity on head
81
• To provide these functions, the following
components are used
– Dam or weir
– Reservoir
– Intake
– Headrace (canal or tunnel)
– Forebay or surge tank
– Penstock or pressure shaft
– Control equipments (gates and valves)
– Power house (turbines and generators)
– Draft tube
– Tailrace
– Switch yard 82
• The components of Hydro electric power
scheme can be seen in two different
layout
84
Surface hydropower layout
Dam
Main river
Reservoir
Power canal
Reservoir
forebay
penstocks
power house
85
Surface hydropower plant
penstocks
Power house
86
Chapter three
Hydropower Planning and
Hydrological Analysis for
Hydropower
87
Hydropower studies
• Three types of studies are commonly made:
9
Total loss = h L = ∑ h i
i =1
Hydropower system design
Entry arrangements: Trash rack losses
43
t v2
ht = K t sin φ
b 2g
Values for Kt
Hydropower system design
Entry arrangements: trash racks
Hydropower system design
Entry arrangements: Entry losses into the
penstock
Hydropower system design
Entry arrangements: Entry losses into
the penstock
v2
he = K e
2g
Type Ke
Hooded 1.0
Projecting 0.8
v2
hb = K b
2g
r/D Kb
r
1 0.6
2 0.5
3 0.4
4 0.3
Hydropower system design
Penstocks: Other Losses
• Contractions
D1/d2 Kc
1.5 0.25
2 0.35
2.5 0.40
5 0.50
• Valves
Type Kv
Spherical 0
Gate 0.1
Butterfly 0.3
Estimating Power Potential of a river
Water power potential is the amount of power
generated when Q m3/sec of water is allowed
to fall through a head difference of H meter
which is given by:
P theoretical = γw ȠQ H (KW)
30
(12, 28.75)
(10, 23.96)
25
Cummulative flow (Mm)
Mass curve
3
Demand line
20
(10, 17.5)
15
(3, 11.25)
10
(3, 7.19)
5
0 0, 0
0 1 2 3 4 5 6 7 8 9 10 11 12 13
months 103
Flow duration curve
• A flow duration curve is a plot of flow versus
the percent of time a particular flow can be
expected to be exceeded.
• A flow duration curve merely reorders the
flows in order of magnitude instead of the
true time ordering of flows in a flow versus
time plot.
• The flow duration curve also allows the
characterizing of the flow over long periods
of time to be presented in one compact
curve 104
Determination of flow for power estimation of a rivers
40
Q (m /s)
3
30
20
Qmean
Q50
10 Q95
Q100
0
0 10 20 30 40 50 60 70 80 90 100
% tage of time 105
Power System Terminologies
40
Q (m /s)
3
30
20
10
Q100 for firm power
0
0 10 20 30 40 50 60 70 80 90 100 110
% tage of time 106
Conventional Potential Powers
• Minimum Potential Power – P100 Q100
computed from the minimum flow that is
available for 100% of the time (365 days or
8760 hrs.)
107
Conventional Potential Powers
• Median Potential Power – P50 Q50
computed from the flow available for 50% of
time
• Mean Potential Power – Pm Qm gross
power potential
To compute the technical available power from the
theoretical potential, introduce a reduction factor (0.75
– 0.80) to account for conveyance and plant losses.
109
• The peak load usually determines the size of the plant
200
Peak load Average load
Load, MW
150
Average load
100
50
Base load
0
0 2 4 6 8 10 12 14
110
Time
Load Duration Curve
Firm Power
Secondary power
111
Average load
Load Factor =
peak load
Load factor - gives an idea of degree of utilization capacity. Thus an
annual load factor of say 0.4 indicates that the machines are
producing only 40% of their yearly maximum production capacity.
Average output of plant for a given period
Capacity Factor =
Full plant capacity
Energy actually produced
=
Energy that a plant is capable of producing at full capacity
113
• Hydropower potential is commonly divided
into three categories:
Theoretical: is the sum of the potential of all
natural flows from the largest rivers to the
smallest, regardless of the inevitable losses
and unfeasible sites.
Technical: From technical point of view,
extremely low heads (less than around 0.5m)
are considered as infeasible.
Economic: Economic potential is only that
part of the potential of more favorable sites
114
Extrapolation of flow data to
ungauged sites
• Most of the time the stream flow data might
not be available at the location for which a
hydropower site analysis is to be made.
115
• This type of analysis is particularly useful
116
• A separate curve is developed for each
exceedance interval used.
117
118
FDC for gauging stations in a homogeneous drainage basin
Parametric flow duration curves 119
Chapter four
Water Conveyance
Structures
120
Cont’d
Conveyance system
is required to carry the water from the reservoir or
pond to the power house. It includes:
Intake
Tunnels or canals
Pipes ( penstocks / pressure shafts )
Penstock/Pressure shafts – are high pressurized conduits
which carry water from the fore bay or surge tank to the
turbine
Fore bay
an enlarged body of water just upstream of the penstocks. A
fore bay is required only when the conveyance system has
channel flow 121
Cont’d
Surge tank
If the conveyance system is tunnel under a very high
pressure, surge tank is usually required at the beginning of
pressure shaft to reduce the effect of water hammer
Power house
is a building for housing the equipments required for
generation of power, such as
turbines, generators, transformers etc….
Tail race
is the channel in which the water after passing through the
turbines is discharged in to the natural stream
122
• Intakes
–An intake is provided at the mouth of
a water conveyance system for a
hydropower project.
• Necessary conditions for intake,
– minimum head loss as water enters from the
reservoir
– there should not be any formation of vortices
– floating material should not enter the water
conducting system.
123
124
• Tunnels
• Tunnels are
underground
conveyance
structures
constructed by
special tunneling
methods
• Important in high
head plant
125
• Tunnels of hydropower projects fall into
two categories:
– water carrying tunnels
• Subjected for high pressure
– Head race tunnel, Tail race tunnel and diversion tunnel
– service tunnels
• Cable tunnels: to carry cables from underground
power house to the switch yard
• Ventilation tunnels: fitted with fans at the open end
to supply fresh air to the underground
• Access or approach tunnels: this is a passage
tunnel from surface to underground power house.
126
127
Classification of Tunnels
• Classification based on shape, alignment
and design aspects.
– Shape: Tunnels are either circular or non-
circular in shape.
129
130
Diversion Tunnel Concrete Lining
132
133
• Lining of tunnels is required:
– For structural reasons to resist external forces
when the strata is of very low strength.
– When the internal pressure is high, above 100m
– For prevention or reduction of seepage losses
– For protection of rock against aggressive water
138
Optimum X-section
• The optimum x-section of a tunnel or a shaft
is one for which the sum of tunnel
construction cost and the economic loss due
to head loss is minimum.
For concrete-lined tunnels:
D = 0.62 Q 0.48
Total cost
Cost
For steel-lined tunnels
Q 0.45
Economic loss
Construction cost D = 1.12 0.12
H
X-section
139
Tunneling Methods
• Two commonly used types of tunneling
techniques:
– Conventional “Drill and Blast”
– Use of tunnel boring machines (TBM)
• Conventional “Drill and Blast” Method:
– The main equipment used is the so-called drilling
jumbo or drilling rig
141
• The wheel is forced against the tunnel face by
hydraulic jacks and is made to rotate.
• As excavation proceeds, the rock-cuttings are
picked up in buckets attached around the rim
of the wheel and are discharged on to a
conveyor belt
142
• Advantages of TBM over conventional
drilling and blasting method
143
Tunnel Supports
• The following support methods are the most
commonly used in hydropower tunneling
– Rock bolting
– Shotcreting
– Steel support
– Grouting
– Concrete lining
144
• Rock bolting
– A rock bolt is a steel bar, which is inserted into a hole drilled
in a rock to improve the rock competency.
On average, the length of rock bolts in water tunnels is 1.5 to 4 m and the
145
diameter is 16 to 25 mm.
• Shotcreting
– A shotcrete is a quick-setting concrete plaster shot
at rock surfaces pneumatically.
– In practice the shotcrete is placed in 5 cm layers
until a desired thickness is attained.
– The use of steel fibers in the concrete mix has an
effect of increasing the strength of the shotcrete
147
• Steel support
148
Water Hammer
149
• The time required for pressure wave to travel
the entire length L of the conduit is
151
• In order to present clear analysis of maximum
pressure along the penstock the following case
should be considered
152
Surge Tanks
• A surge tank is a device introduced within a
hydropower water conveyance system to
absorb the excess pressure rise in case of a
sudden valve closure.
• It also acts as a small storage from which
water may be supplied in case of a sudden
valve opening of the turbine.
153
Fig Typical Arrangements of Surge Tanks
154
• Types of Surge Tanks
• Surge tanks may be classified according to :
– Material of construction
• Concrete
• or steel
– Location relative to terrain
• underground surge tank
• over ground surge tank
– Location in the hydraulic system
• Upstream surge tank
• Downstream surge tank on the tailrace tunnel
– Hydraulic functioning & cross-sectional shape
155
• Classification based on hydraulic functioning &
cross-sectional shape
157
• Restricted Orifice
Surge Tank: A
simple surge tank
in which the inlet is
throttled to
improve damping
of oscillations
158
• Differential Surge
tank is a throttled
surge tank with an
addition of a riser
pipe may be inside
the main shaft,
connected to main
shaft by orifice or
ports.
159
Design Consideration of Surge Tank
• The hydraulic design of surge tank considers
two main aspects.
– Its height
– Its cross-sectional area.
• For up-surge, the worst conditions are:
– Instantaneous total closure
– Reservoir level at its maximum
• For down-surge, the worst conditions are
– Instantaneous total opening
– Reservoir level at its minimum
160
Z1up
HRWL
Hlive
LRWL
Z0
Z1 down
Pressure tunnel
h
161
Chapter Five
Power Houses
and Facilities
162
Hydraulic Turbines
164
Reaction turbines or pressure turbines
165
Examples of Reaction turbines
166
Constitutive elements of reaction
turbines
• wicket gates (or guide vanes)
vanes that guide water onto the
runner, with appropriate velocity
and direction
167
Francis Turbine
• Flow enters through a
scroll casing which is
designed to distribute
the flow around the
periphery of the inlet
guide vane.
• The inlet guide vanes
increases the angular
momentum of the water
168
169
170
Runner
171
172
Scroll case – Gilgel Gibe II
173
Turbine installation – Gilgel Gibe II
174
Kaplan Turbine
• Kaplan turbines are
axial flow reaction
turbine, generally
used for low heads.
177
Impulse turbines...
• Prior to hitting the turbine blades, the water's
pressure (potential energy) is converted to
kinetic energy by a nozzle and focused on
the turbine.
• No pressure change occurs at the turbine
blades, and the turbine doesn't require a
housing for operation.
• Pelton wheel consists of one or more nozzles
which produces high velocity jet of water
which impact a series of buckets
178
179
180
• Turbines may also be classified according to
the main direction of flow of water in the
runner as
181
• Reference values of working parameters
and outputs for the main types of hydraulic
turbines:
182
Characteristics of Turbines
• The speed at which the turbine runs for a
particular discharge (Q) and unit head to
produce unit power is NS (specific speed)
183
Specific speed empirical correlation
for various types of turbines
184
Speed
• If the turbine is directly connected to the
generator, the turbine speed, n, must be a
synchronous speed.
• For turbine speed, n, to be synchronous, the
following equation must be fulfilled:
186
• speed factor or peripheral coefficient , φ is the
ratio of peripheral speed v to water speed
v ωr 2πN πDN
φ= = φ= =
DN
2 gH 2 gH ω= 60 2 gH 84.6 H
60
D and H in m; N in rpm
187
Procedure in preliminary selection of Turbines
• From design Q and H, calculate approximate
P that can be generated , P = η γ Q H
f
n = 120
• From calculate n ( or assume ) &
Np
DN
• Calculate D from: φ =
84.6 H
• D =a
n
D in m; Q in m3/s; n in rpm
• a = 4.4 for Francis and a = 4.57 for Kaplan.
• Nominal diameter, D , of pelton wheel
H
D = 38 dj is diameter of the jet for
N
Q
dj = 0.542
H
192
Francis turbine with steel spiral case
Straight
conical draft
tube
195
Cavitation and turbine setting
• Cavitation is defined as the formation of voids
within a body of moving liquid when the local
pressure is lower than vapor pressure and the
particles of liquid fail to adhere to the
boundaries of the passage way
199
• The above criteria can be fullfilled by
calculating Thoma cavitation coefficient 𝝈:
σ = Thoma number
patm = atmospheric pressure
pv = vapour pressure
Ys = elevation above tailwater
H = total net head
ρ = density
g = gravity
In order to avoid cavitation, Thoma coefficient must
be higher than a critical threshold value 𝜎c
2
Ns for Francis
σ c = 0.0432
100
3
N
σ c = 0.28 + 0.0024 s for propeller
100 200
With an increase by 10% for Kaplan turbines.
THE END
201