METHOD STATEMENT FOR INSTALLATION

OF ELECTRIC PVC CONDUITS AND


ACCESSORIES

1. INTRODUCTION AND SCOPE


This method statement explains the detailed requirements and procedures for
the installation of PVC Conduits and accessories in the concrete slabs,
columns, block works and concrete walls.

2. APPLICABLE PROJECT
SPECIFICATION
 Document No.:

 Section: Conduit

 Division:

 Sub-division:

3. LOCATION OF ACTIVITY
Inside and out side the building.

4. OPERATION
Material: Material used will be as approved by the engineer. The sizes and
routes routing will be as per the approved shop drawing.

Storage and Protection: Deliver components parts to site, completely


identified in accordance with shop and certified CAD drawings prepared for
this work. Store in accordance with the manufacturer’s instructions, above
ground, properly protected from the weather and construction activities.

5. INSTALLATION
1. During the course of the installation of the conduit system, procedures
for working and dressing the installation as recommended shall be
employed.

2. All bends and sets shall be in accordance with IEE regulation 522-08
formed with the aid of a helical spring fitted internally, with if necessary,
the conduit warmed sufficiently for it to move without avoidable wall
thinning of the out side of the bend.

3. Conduit system shall be installed so as to ensure compliance with the


requirements of Specified Standard and Regulation.

4. Joints between PVC conduit + fittings shall be made with suitable


adhesive, but expansion couplings shall be installed where any length
of conduit , inclusive of draw in boxes etc, exceeds five meters in
length.

5. The minimum and maximum sizes of conduit to be employed shall be


20mm and 32mmdiameter respectively, unless otherwise stated in
subsequent sections of the specification.

6. Conduits in floors shall be routed and installed so as to avoid the


fixings of floor standing equipment to be installed on the floor.

6. FIXING OF CONDUITS
When conduits are run on shuttering, prior to the laying of concrete insitu,
additional security must be provided near to every box and at intervals of not
more than 1.2 meters by binding short lengths of steel wire, of not less than
2mm diameter twisted around the conduit and reinforcing steel. The conduits
shall be adequately fixed to prevent excessive movement and damage during
the pouring and setting of concrete and shall be protected from mechanical
damage. Check there is no damage before screed / concrete is poured.
Unless otherwise indicated to cast in conduits shall not be less than
30mm.cores to plastered over conduits shall not be less than 5mm.

Where conduits are left "open ended" prior to wiring they shall be protected by
caps or plugs to prevent the ingress of building material.

All conduits runs must be designed to permit wiring to be readily installed after
the complete erection of the conduits through the available draw-in, accessory
and luminary suspension boxes.

Where surface mounted equipment (other than luminaries) is specified, all


concealed conduits shall be terminated and an adaptable box installed
recessed into the wall at every surface mounted equipment position.
Where conduits pass through an external wall/roof the conduit box shall be
fitted on the side and after wiring filled with an inert, permanently plastic
compound having a high insulation value.

Make provision in conduit and trunking, installation where building expansion


joints are crossed or settlement is likely

Ensure conduits are not concealed until works has been inspected and
approved. Ensure that conduit and fittings buried in concrete or behind plaster
are protected against corrosion or electrolytic action prior to rendering.

7. RESPONSIBILITY
 Project Manager:

o To ensure that all the preparation and application works are


carried out according to the Contract Specification and with the
approved drawings.

o To ensure that the progressing of work is carried out according


to the planned program and as per the approved method of
statement.

o To ensure that all the equipment and materials required to


execute the work are available according to the planned
construction program.

o To co –ordinate with the Main contractor, MEP Coordinator and


Safety Officer, for a safe and proper execution of the works.

 Site Engineer:

o To ensure that the works are carried out according to the


Contract Specifications, approved method statement and the
shop drawings.

o To provide all necessary information and distribute


responsibilities to his construction team.

o To monitor the progress of work in relation with the work


program and to report to the Project Manager.

o To co-ordinate with the safety officer and to ensure that the


works are carried out in safe practicing methods.
 Foreman:

o The foreman will carryout his duties by maintaining continuous


coordination with the site engineer on daily basis, and ensure
proper distribution of the workforce in the required and planned
locations.

o To ensure that his assistant foreman/ charge hand are aware of


the job requirements and they have enough information to
carryout their duties properly.

o To ensure in consultation with the site engineer that the


manpower involved in the works are moving as agreed and
planned for the work.

o To ensure that the daily work is progressing as planned and


advise the site engineer of any requirement for additional
resources.

o To control disposal of waste materials according to the


instructions received from the site engineer.

o To ensure full coordination with the safety officer to maintain


safe working and proper house keeping of the site, following the
approved safety measures and further ensure that all his
working team are aware of the same to prevent accident and
losses.

o To inform the site engineer and of the areas ready for


inspection.

o Distribution and the control of material shall be monitored by


foreman and store keeper.

8. EQUIPMENT REQUIREMENTS
The requirements that will be engaged for PVC Conduiting works will be as
follows:

1. Hack saw

2. Measuring tape

3. Cutting plier
4. Knipex (End cutter)

5. Bending spring

6. Drilling Machine

9. HEALTH AND SAFETY


Strictly followed as per the manufacturer’s Health and Safety
recommendations for handling and use of the materials. Ensure all involved
personnel shall be aware of the same.

10. INSPECTION AND TEST PLAN


FORMAT FOR INSTALLATION OF PVC
CONDUITS AND ACCESSORIES IN THE
CONCRETE SLABS, COLUMNS, BLOCK
WORKS AND CONCRETE WALLS