Вы находитесь на странице: 1из 6

STEEL Accessories Limited

W.I 7.5-02 QSP 7.5-1


Revision : 00 Issue Date :15-05-2012
Effluent Treatment Plant Work Instruction & Standard Operating Procedure

DESIGN BASIS
Our treatment scheme is designed based on the inlet characteristics furnished below: Inlet Effluent
Characteristics:-

CHARACTERISTICS
Flow (Average) m3/hr 75.0
PH 9 -11
TSS mg/L 300 -400
BOD5 mg/L 300-450
COD mg/L 600-1000
Color Co.Pt 1245
TDS - 2000-3500
Outlet Effluent Characteristics:-

CHARACTERISTICS
PH 6.0 – 9.0
TSS mg/L < 150
BOD5 mg/L < 50
COD mg/L < 150
Dissolve Oxygen mg/L 4.5-8
Color Co.Pt <150
TDS - Not treated
Analysis sheet waste water (Before & after treatment) doing by Department of Environment,
peoples Republic of Bangladesh.
Sample Location Date PH TS TDS SS DO BOD COD Oil &
mg/lit mg/lit mg/lit mg/lit mg/lit mg/lit Grease
mg/lit
Waste water 02/02/11 6.0 1665 1053 612 4.1 42 471 12.5
(B.T) of SAL
Waste water 02/02/11 8.4 2072 2004 68 4.6 38 182 4.0
(A.T) of SAL
Standard as per ECR 1971 in 6.5-8.5 Below Below Below 4.5-8.5 Below Below Below
Bangladesh 2100 2100 100 50 200 10

Our treatment scheme is based on the inlet parameters. It consists of the following steps:-

1. Screening

2. Oil Screamer
3. Equalization

4. High Rate Soiled Contract Clarifier(HRSCC)

5. DAF- Dissolved Air floatation System.

6. PH correction Tank.

7. Clarified water tank.

8. Sludge Drying Bed.

9. Sludge pit.

10. MGF- Multi grade filter(out let)

1. Screening:

The raw effluent from the plant complex would be first screened through the bar screen, where all the
big particles are screened and clear effluent is taken into the Grit chamber and equalization tank.

2. Oil Screamer:

Oil screamer removes floating oil from collection zone of Equalization Tank.

3. Equalization:

The raw waste from the screen Chamber is collected in the equalization tank. Six hour retention is given
in the beginning for the effluent before taking it service. Air blower is also started with its respective
flow rate when retention period is complete and if level of effluent in tank is sufficient, pump can be
started. Keep the PH value of the raw effluent 9.5 to 11.0.It can be adjustable by dosing NaOH or HCl.

Operation:

Start unit after sufficient level i.e; P1 (Effluent transfer pump)

Start operation with aeration grid with blower B1 (Air blower pump). Open valve V-01, this liquid is taken
to clarifier.

4. Flocculation Clarification:

The equalization waste is then pumped into the flash mixer compartment of the HRCC, where coagulant
PAC and polymer is dosed in the flocculation compartment to aid in the process of settling. The overflow
from the flocculation compartments taken into the clarification zone of the clarifier for removal of TSS
and BOD/COD. The overflow from the clarifier is taken for further treatment while the under flow is
taken for sludge treatment.
5. High Rate solid Contract Clarifier:

Effluent from equalization tank is taken to HRSCC and the bio mass is settled by gravity in it. When
sufficient sludge level is there in SCL, sludge is taken to sludge pit. Output water is taken into BMT after
checking parameters. We dose two coagulant caustic and electrolyte polymer at HRSCC. At HRSCC P H
value should be 9.5 to 11.0.

Operation:

Start DP-1(PAC dosing pump), DP-2(Polymer dosing pump)

Start impeller and scraper of HRSCC

For sludge remove open V-1

6. Dissolved Air Flotation-DAF:

Air is dissolved under pressure in the liquid, which is then released to atmospheric pressure in the
floatation cell. As the microscopic air bubbles come out of solution, they attach to the suspended solids
in the liquid, causing them to float to the surface forming a thick sludge. A special skimmer removes the
sludge with the help of patented “KROFTA” SPIRAL SCOOP and pours it into the stationary centre section
from where it is discharged by gravity for either recycling or disposal.

7. PH correction Tank:

The clarified effluent form HRCC will have alkaline P H. Acid dosing (HCl) will be required to reach a
neutral PH(6.5-7.5) level for the on ward biological treatment.

8. Sludge Drying Bed:

The under flow from the HRSCC clarifier having a sludge consistency of around 2- 3% is called in the
sludge pit & through to the thickener tank from where it is pumped in to a sludge drying Bed for
dewatering is taken back to the equalization tank.

9. Sludge Pit(SP):

The sludge mainly comes from the HRSCC and only partly comes from LC. When level in sludge pit is ok,
sludge transfer pump can be started for further disposal.

Operation:

Start sludge transfer pump P3-A/B

This sludge is taken to centrifuge for disposal.

10. MGF- Multi grade filter (out let)

Finally treated water goes through the MGF for drain out let. Out let water PH should be 6.5-8.5
11. Record & Data

 Daily PH value measuring log book

 Daily chemical dosing & consumption log book

12. Operating range of different tanks PH & others parameters

 Equalization tank PH 9.5 to 11.o. Adjustable by dosing NaOH or HCl

 HRSCC tank PH 9.5 to 11.0, TS <2100 ppm, TDS <2100 ppm, SS <100ppm, DO: 4.5-8.5ppm, BOD
<50ppm, COD <200ppm, Oil & Grease <10 ppm. Above mention all the parameters can be
adjustable by dosing PAC, Electrolyte polymer and NaOH in a standard ratio.

 DAF system helps the treated water comes from HRSCC to maintain the acceptable range of BOD,
COD and DO.

 PH correction tank PH range should be 6.5 to 7.5. It can be adjustable by dosing HCl.

 Finally treated water goes through the MGF, before drain out through MGF there need 10 to 15 min back wash. Out
let water PH range will be 6.5 to 8.5.

ETP Plant starting time need to do:

 Operation starting time first increase the PH of raw Effluent (9.5 to 11.0) then dosing all chemicals.

 Please switch off the Effluent transfer pump before the starting time of PAC, Poly & NaOH dosing pump.

 Start Air blower.

 Start HRSCC (High rate soiled contract clarifier), RD (Roller drive) & SD (Scrapper drive)

 Start filter feed pump.

Chemical Dosing

 Please maintain jar test after every two to three hours of inlet Effluent.

 Make PAC & polymer solution after jar test.

 Please neutralize the Effluent before equalization tank.

 Poly Aluminum Chloride Dosing: 200 ppm = 200 mg/lit = 200 gm/m3

o 200 × 15 = 3000 gm/Hr = 3 kg per Hour.

 Poly Electrolyte Dosing: (0.5 to 1) ppm, 1 ppm = 1 mg/lit = 1 gm/m3

o 1 × 15 = 15 gm/Hr.
MAINTENANCE & TROUBLE SHOOTING
The following conditions, causes and actions are listed to assist the operator in trouble shooting the installation.
CONDITION POSSIBLE CAUSE REMEDIAL CAUSE

1 Haze in effluent or flock 1. Mal-adjustment of 1. Check chemical feeds


carryover chemical feeds
2. Clean plates
2. Fouling of plates
3. Increase blowdown
3. High sludge inventory
4. Adjust feeds
4. High flow rate

2 High dissolved constituent As above As above

3 High oil and / or grease in 1. High oil in influent 1. Monitor feed stream and correct
effluent
2. Oil not removed from 2. Use oil removal device
separation section
3. Observe and adjust
3. Incorrect chemical
treatment

4 Flow surges 1. Mal-adjustment of 1. Adjust


influent valving
2. Monitor feed stream and correct
2. Feed stream rate

5 Unequal distribution 1. Mal-adjustment of 1. Check and study


dislocation of plates
2. Monitor and adjust
2. High or low influent
flow to lamella

6 High colour in effluent 1. Mal-adjustment of 1. Check and adjust


chemical feeds
2. Monitor and adjust
2. Contamination of feed
stream 3. Clean plates

3. Fouling of plates 4. Increase blowdown frequency

4. High sludge inventory

7 Plate touching or binding Plate flexing Check plate mounting and repair
according to IEI advice

8 High sludge inventory 1. Mal-adjustment of 1. Check and adjust


chemical feeds
2. Increase blowdown frequency
2. Incorrect blowdown
3. Clean the pipes
3. Plugged sludge pipes
BY NAME DESIGNATION SIGNATURE DATE

WRITTEN BY Mr. AMZAD HOSSAIN In charge

REVIEWED Mr. B. RAVICHANDRAN Production Manager


BY:
APPROVED Mr. M NURUL ISLAM Plant Head
BY:
ISSUED BY Mr. M Nurul Islam MR

Вам также может понравиться