Академический Документы
Профессиональный Документы
Культура Документы
Content
1 Executive Summary 1
1.2 Background 1
2 Project Objectives 2
3.1 Scope 3
3.2 Exclusions 5
4 Constraints 6
5 Assumptions 6
6 Deliverables 6
6.1 Managerial 6
6.2 Technical 6
6.3 Quality 7
7 Training 7
8 Business Benefits 7
9 Risk Assessment 9
11 Project Controls 10
12.1 Staffing 11
14 Communications Strategy 12
14.5 Suppliers 13
16 Acceptance Criteria 14
19 Authorisation 18
1 Executive Summary
1.2 Background
In January 2014, a project team with representation from the HR and BCPM
services was formed to review the existing HR systems and their associated
contractual agreements. This led to a full review of the key systems being
operated within HR, which included the HR and payroll system, online
recruitment, training and workforce development and employee and manager self
service.
In addition to the review of systems, a full review of the HR and BCPM services
commenced in February 2014 with an overarching objective to simplify and
streamline business processes, leading to the realisation of both financial and
non-financial savings.
Page 1
Calderdale MBC
iTrent HR and Payroll System Project
In order to achieve value for money and ensure continuity of service beyond
June 2015, and in line with the objectives of the HR and BCPM review, it was
recommended that the Council undertakes a complete OJEU tender process to
procure a new, modern HR and Payroll system. Advice was also taken from the
Council’s procurement team to ensure the relevant procedures were followed.
Prior to the actual procurement exercise, soft market testing was undertaken to
establish the current market, evaluate options and gain a more accurate
understanding of the potential costs. This exercise concluded that systems were
available in the market that would meet the Council’s current and future
requirements and enable us to achieve value for money through undertaking the
procurement exercise.
2 Project Objectives
The overall vision for the project is to achieve the following objectives:
Provide a simple and efficient migration of data and processes to the new
HR & Payroll operating environment (where necessary)
Provide systems, tools and processes to deliver the HR and Payroll
strategic objective of becoming efficient in service delivery
Page 2
Calderdale MBC
iTrent HR and Payroll System Project
The iTrent System will support the core activities of the Human Resources and
Payroll functions and their interaction with the wider customer base (internal and
external customers). This will ensure that all transactional activities undertaken
within these services are efficiently managed. It will bring together professionals
from all Directorates, enhance communication within the team and create a
support network for all stakeholders.
3.1 Scope
HR administration
Payroll
Online Recruitment
Page 3
Calderdale MBC
iTrent HR and Payroll System Project
All the above modules will be fully integrated. Additional integration with existing
systems such as the Oracle based in-house developed Finance system will also
be required. In addition, the system will have the capacity to accommodate an
increasing number of employees and employee related records.
The system needs to be flexible, with the ability to meet the changing needs of
HR. In addition, the system needs to support the Council’s internal and external
customers and partners, including schools and academies.
The project will support and facilitate the delivery of the HR and Payroll
strategies for the Council
The system will be run centrally and the data maintained locally e.g.
Service users will use functions to maintain master data in order to
simplify processes and transactions
Page 4
Calderdale MBC
iTrent HR and Payroll System Project
Users and ICT staff at all levels will be involved at the relevant stages of
the project to ensure that there is a smooth cultural exchange
The solution will be delivered on a phased basis, with the initial phase
focusing on providing (as a minim) the same functionality that users have
with the existing system
3.2 Exclusions
Further developments (outside of the final scope) are excluded from this
project. Additional funding will have to be sought for further developments.
All further developments will be considered on the strength of the business
case produced at the appropriate time
The phased delivery of the system will mean that a number of interfaces
and data migrations will be required to move from the existing HR and
Payroll systems. The same will apply to other systems that will need to
interface with the HR and Payroll systems e.g. Corporate Financials
This project will have interfaces with other systems at different phases in
the project. It is the responsibility of the Project Lead to ensure that
interaction with other projects/systems is open, collaborative and
transparent
The Project Board will keep the Project Lead and Project Team up to date
with developments on the HR and BCPM service review. The project must
be flexible to incorporate recommendations from the Project Board
The Project Lead will keep up to date with other projects that may impact
the HR and Payroll System
Page 5
Calderdale MBC
iTrent HR and Payroll System Project
4 Constraints
5 Assumptions
It should be accepted that the initial priority for this project is to, as a
minimum provide the same level of functionality as exists in the current
system as part of phase 1 and a reduction in timescale would impact on
the quality of this exercise
The Project Team during the implementation phase will become experts
on the HR and Payroll processes, the configuration of the system
implemented and the interfaces with other systems across the Council. It
is essential this expertise is not lost at the end of the project; skills transfer
will be planned into the project
6 Deliverables
The Project Lead will maintain documentation for the project. The following
sections discuss the deliverables at the appropriate levels:
6.1 Managerial
Establishment and initiation of Project Board (PB), Project Team (PT) and
Working Groups (WG)
Production of Project Initiation Document (PID) and associated planning
and project control documents
Regular progress reports to Project Board
Contact with Implementation partners
Recommendations for business process review and design
End user testing plan, scripts and report of outcomes
User acceptance reports
Project closure report
6.2 Technical
Page 6
Calderdale MBC
iTrent HR and Payroll System Project
7 Training
8 Business Benefits
The key benefits of the project will be the implementation of the most appropriate
system for the Council, which will meet its current and future business needs.
This will deliver the following initial business benefits:
Promoting corporate culture. The new systems and processes will provide
excellent customer service, promoting the corporate image and
professionalism of the new HR, ICT and Transformation Service.
Page 7
Calderdale MBC
iTrent HR and Payroll System Project
Reduce staff data input time. Providing user-friendly and easy access to
HR/payroll transactions, sensible sequencing and combination of input
screens (HR/payroll actions) and appropriate use of automated data input
tools would speed up data input time
Increased productivity. Process times and time lags within processes will
be reduced, increasing the productivity of staff involved
Page 8
Calderdale MBC
iTrent HR and Payroll System Project
Provide a robust and supported system. The system and processes will
satisfy current and future requirements and be able to incorporate future
statutory changes
9 Risk Assessment
The following risks and countermeasures will be recorded in the risk register and
further analysis of impacts and contingencies will be made. The risk register can
be found in Appendix B. An issue log will also be kept to record any issues
arising during the course of the project.
Page 9
Calderdale MBC
iTrent HR and Payroll System Project
Each of the working groups illustrated above will deal with specific functionality. It
is understood that some functionality will be common to more than one area and
as such resources will work across those areas.
11 Project Controls
The Project Lead will provide regular written progress reports to the Board for
their information, and will respond promptly to any queries arising. The Board
must, if necessary, make decisions on any issues brought to them by the Project
Lead.
The Board will meet every 6 weeks, and these meetings will be related to
significant events during the life of the project such as end-stage points. The
Board will function to commit resources and authorise progress at these critical
points.
Page 10
Calderdale MBC
iTrent HR and Payroll System Project
12.1 Staffing
Staffing resources for the core project team for phase 1 have been agreed.
Existing staff from the HR and Payroll functions will contribute a percentage of
their time to this project. Business Change and Performance Management
(BCPM) have also agreed resources to work on the project. The Project Board
may need to review resource requirements from time to time and upon request
from the Project Lead to ensure that the project is appropriately resourced.
The project costs have been approved for the HR and Payroll System and details
of this are set out in Appendix D. The budget will be monitored on an ongoing
basis throughout the project lifecycle in accordance with existing capital and
revenue budget monitoring procedures.
The implementation of iTrent will do more than automate key processes and
streamline tasks. By implementing new systems, changes to the structure and
the role of HR and Payroll within the Council will be necessary. Most of this will
be managed through the current review of the HR and BCPM services.
A clear insight into the strategy behind the changed working practices
Training and support they need to help them adapt to their expanding role
successfully
Likewise, all staff will need to be consulted, informed and encouraged
throughout the period of change if they are to engage with the project and
use the new systems and processes
Given that employees and managers are already using aspects of
employee/manager self service, the focus will be on how the iTrent system
functionality will better support them
Page 11
Calderdale MBC
iTrent HR and Payroll System Project
Seek out the benefits required, plan and communicate their delivery to
manage expectations
Assess impacts on individuals with their ability to cope in terms of time
and resource with new responsibilities given to them, and provide support
14 Communications Strategy
Objectives:
Objectives: to ensure that the Project Team communicates with management and
other stakeholders, to ensure that all requirements are met in delivering the new
HR and Payroll System.
1. The Project Board is the main supervisory body, which will need to be kept
informed of the project progress by the Project Lead
2. Distribute regular highlight reports to PB members by e-mail
3. Escalate unresolved risks and issues to the PB using the most appropriate
method
4. Distribute reports of key achievements to the PB by e-mail for information
5. Project Lead to feedback issues escalating from the Working Groups and
update the Project Team
Objective: to ensure that the PT is kept up to date with project progress and
issues.
Page 12
Calderdale MBC
iTrent HR and Payroll System Project
Objective: to ensure that the Working Group is kept up to date with progress and
issues.
Objective: to create awareness amongst all staff affected by the HR and Payroll
System Project.
1. To ensure that staff understand and are committed to the aims and
objectives of the Project, and what this means for them
2. To provide channels for staff views to shape the development of the
Project, especially around business processes
3. To improve awareness of activities of the HR and Payroll System Project
4. To facilitate the flow of information and knowledge of the Project
throughout the Council
14.5 Suppliers
1. Suppliers will provide the relevant resources at each stage of the project
2. Advise on best practice, limitations and implications of the agreed
implementation strategies
3. Provide project management support to ensure internal and external
resources are utilized efficiently throughout the implementation phase
Page 13
Calderdale MBC
iTrent HR and Payroll System Project
Project staff training and development needs have already been identified and
initial training has been provided where necessary. The Project Lead will work
closely with MidlandHR and the Training and Development Staff to plan and
deliver additional training where this is required.
16 Acceptance Criteria
All products of the project must meet the approval and be signed off by the
Project Board. Deliverables will be defined in further detail as part of the
blueprinting exercise, which will define the functional specification.
This phase of the project includes the Kick Off Meeting and sets out the
governance for the project, including contingency plans, benefits and confirms
the members of the Project Board and Project Team, including MidlandHR
resources.
The purpose of the Blueprint phase is to develop a full business blueprint based
upon the Council’s ‘To Be’ processes. This business blueprint will provide a road
map and basis for building, testing and implementing the system.
Page 14
Calderdale MBC
iTrent HR and Payroll System Project
The Realisation phase focuses on building and testing the iTrent system. This
solution will be based upon the processes to support the business area/s that will
have been identified in the Blueprint phase.
The purpose of this phase is to implement the live integrated iTrent solution for
the agreed business area/s, covering the core business process areas as defined
during the Blueprint Phase.
A post go live review meeting will be held after each go live to assess problems
and issues. These issues will be recorded and resolved using a rolling business
action list.
The following activities are planned for the implementation of the iTrent HR and
Payroll system. This is not a complete project plan but is intended to show major
activities and indicate possible dates. A more detailed project plan for the
implementation phase has also been produced and will be made available to all
stakeholders.
Page 15
Calderdale MBC
iTrent HR and Payroll System Project
Page 16
Calderdale MBC
iTrent HR and Payroll System Project
Supplier
In-house interface development Project Team, May 15 June 15
Supplier
User Acceptance Testing Project Team, June 15 July 15
Supplier
Additional training – core HR/payroll Project Team, July 15 July 15
team Supplier
Recruitment Module
Configuration and setup Project Team, Aug 15 Aug 15
Supplier
Build processes and workflows Project Team, Aug 15 Aug 15
Supplier
User training Project Team, Aug 15 Aug 15
Supplier
Learning and Development Module
Configuration and setup Project Team, Aug 15 Sep 15
Supplier
Build processes and workflows Project Team, Aug 15 Sep 15
Supplier
Data migration Project Team, Aug 15 Sep 15
Supplier
User training Project Team, Aug 15 Sep 15
Supplier
Parallel Running
Parallel run 1 Project Team, Aug 15 Aug 15
HR/Payroll Team
Parallel run 2 Project Team, Sep 15 Sep 15
HR/Payroll Team
Parallel run 3 (reverse parallel) Project Team, Oct 15 Oct 15
HR/Payroll Team
PHASE 1 LIVE – October 2015
Phase 2 planning (Performance Project Team, Oct 15 Oct 15
Management, Talent Management, Supplier
Employee Relations, FWP)
Page 17
Calderdale MBC
iTrent HR and Payroll System Project
19 Authorisation
Project Sponsor
Finance
IT
HR
HR
Project Lead
MidlandHR Project
Manager
Page 18
Calderdale MBC
iTrent HR and Payroll System Project
Organisational Accountabilities
Project Sponsor
Accountabilities
The following summarises the main duties of the Project Board, which should be
undertaken in consultation with the Project Lead:
Page 19
Calderdale MBC
iTrent HR and Payroll System Project
Post Title
Director of Communities and Service Support
Head of Finance
Corporate Lead for HR
Corporate Lead for Workforce
HR Service Manager (Business and Pay)
Corporate Lead for ICT
HR Business Manager
Page 20
Calderdale MBC
iTrent HR and Payroll System Project
Post Title
Service Manager, Business and Pay
HR Business Manager
Payroll Manager
HR Administration Manager
HR Projects Co-ordinator
HR Projects Co-ordinator
Page 21
Appendix B: Risk Register
Page 22
Appendix C: Project Plan – Initial Phase
Page 23