Академический Документы
Профессиональный Документы
Культура Документы
DIM XX GS
SUMMARY DATA SHEET
4.0 REVIEWERS:
(Name / Dept) V. K Raja/ DPD-GuE
Chee Weng Kong / DPD-CSD
Choong Chee Keong / DPD-SFD III
INTERNATIONAL STANDARDS
ENVIRONMENTAL
EMEP EXCEPTION
SAFETY/HEALTH
OPERABILITY
CORROSION
EXCEPTION
SCHEDULE
APPLICATION
(USD K) (YES/NO)
No Revised company name and format Company name change and new formatting standards.
P No 4.3 TRANSPORTER shall furnish grillage and tiedown Transporter not fabricator to furnish tie down material.
materials (other than those specified in 7.3.5) to secure the Reduce cost and facilitate disposal.
components and appurtenances on barge deck per drawings
supplied by TRANSPORTER and approved by EMEPMI.
Welding shall be approved by EMEPMI and EMEPMI Marine
Surveyor. All tiedown materials provided by TRANSPORTOR
shall remain the property of TRANSPORTER.
No 5.1.4-7 Added requirement that Erector witness Insure erector confirms that testing is adequate
No 6.2 Tiedown drawings (IFC) shall be provided 45 days prior Clarified when deliverable required.
to loadout
INTERNATIONAL STANDARDS
ENVIRONMENTAL
EMEP EXCEPTION
SAFETY/HEALTH
OPERABILITY
CORROSION
EXCEPTION
SCHEDULE
APPLICATION
(USD K) (YES/NO)
P P No Added following requirements to FABRICATOR's loadout Recommended per lesson learned 543 SFD Gate 5 #1
procedure requirement
6.3.14 Method to control personnel access to cargo bare
(e.g. personnel tag system)
INTERNATIONAL STANDARDS
ENVIRONMENTAL
EMEP EXCEPTION
SAFETY/HEALTH
OPERABILITY
CORROSION
EXCEPTION
SCHEDULE
APPLICATION
(USD K) (YES/NO)
P P No 6.4 All lifting slings used shall be permanently tagged with its Made sling and shackle testing same as offshore
permissible safe working load. All slings and shackles shall specification.
be certified within the previous 6 months by a recognized
certifying authority such as ABS, Lloyds or DNV. Slings
shall be certified by load testing to two times the safe working
load (SWL) or the maximum anticipated load. For slings with
SWL of 250 metric tons or more the sling test load may be
reduced to 1.25 times the SWL if CONTRACTOR can
demonstrate a limitation in regionally available sling testing
facilities. Shackle bodies and pins shall be inspected by
magnetic particle. Slings and shackles for heavy lifts
(>800MT) shall be inspected prior to each use. Sling
certificates and shackle inspection records shall be submitted
to EMEPMI for review.
INTERNATIONAL STANDARDS
ENVIRONMENTAL
EMEP EXCEPTION
SAFETY/HEALTH
OPERABILITY
CORROSION
EXCEPTION
SCHEDULE
APPLICATION
(USD K) (YES/NO)
P P D, $3K/ No 6.6 Updated Loadout durations per Safety Committee Updated Loadout durations per Safety Committee
recommendations. recommendations to reduce the rush at loadout.
barge
For combinations of components on the same cargo barge not
addressed above, the duration for the loadout shall be
determined by adding the individual component durations
together minus 48 hours times one less the number of
individual components durations used.
No 7.3.3 MSF/BSF/deck legs, tiedown braces between the legs Added requirement for doubler plate.
and barge shall be connected to doubler plates welded to the
legs.
The GS 0-5-21 refers to API RP 2A latest addition. Other GS's are referred that refer to several
international standards. There are no known conflicts and these GSs require that the latest revision
of the standards and practices be used. These GSs also requires any conflicts to be resolved by
EMEPMI.
2. Is this new/revised standard really necessary? Yes Meet the 5 year revision cycle
requirement
3. Conform to applicable International standards Yes International Standards incorporated
by reference
4. Conform to applicable National standards NA
5. Conform to EMEP NA
8. Reflect latest developments and lessons learned Yes LL 543 SFD Gate 5 #3 incorporated
New Loadout durations
recommended by Safety Committee
incorporated.
9. Consider facilities abandonment requirements (Refer NA
to PETRONAS Guidelines for Platform
Decommissioning)
11. Consider effects of new/updated industry standards Yes Refer to section 6 above.
Notes* - Include PCN No., Safety Bulletin Ref. No., Lesson Learned Ref. No. and GS/DIM Bulletin Ref. No.