Академический Документы
Профессиональный Документы
Культура Документы
I. EXCAVATION WORKS
I.A. COLUMN FOOTING QTY: 13.00 cu.m
LABOR
1 - Const. Foreman 3 day(s) @ P 550.00 / day(s) - P 1,650.00
4 - Laborers for 3 day(s) @ P 365.00 / day(s) - P 4,380.00
Labor Cost 6,030.00
DIRECT COST 6,030.00
OCM 603.00
Contractor's Profit 603.00
ITEM COST 7,236.00
Unit Cost 556.62 / cu.m
II. BACKFILLING
II.A. COLUMN FOOTING QTY: 11.00 cu.m
LABOR
1 - Const. Foreman 3 day(s) @ P 550.00 / day(s) - P 1,650.00
4 - Laborers for 3 day(s) @ P 365.00 / day(s) - P 4,380.00
Labor Cost 6,030.00
DIRECT COST 6,030.00
OCM 603.00
Contractor's Profit 603.00
ITEM COST 7,236.00
Unit Cost 657.82 / cu.m
I. CONCRETING WORKS
III.A. FOOTINGS QTY: 2.56 cu.m
1 MATERIALS
24 bag(s) - Portland Cement @ P 260.00 / bag(s) - P 6,240.00
1.28 cu.m - Washed Sand @ P 800.00 / cu.m - P 1,024.00
2.56 cu.m - Screened Gravel @ P 800.00 / cu.m - P 2,048.00
36 pc(s) - 16mm dia. Deformed RSB x 6m L @ P 368.00 / pc(s) - P 13,248.00
4 kg(s) - #16 G.I Wire @ P 80.00 / kg(s) - P 320.00
Material Cost P 22,880.00
2 LABOR
1 - Foreman 3 day(s) @ P 550.00 / day(s) - P 1,650.00
4 - Laborers 3 day(s) @ P 365.00 / day(s) - P 4,380.00
2 - Steelman 3 day(s) @ P 450.00 / day(s) - P 2,700.00
2 - Mason 3 day(s) @ P 450.00 / day(s) - P 2,700.00
Labor Cost 11,430.00
3 EQUIPMENT RENTAL
1 - Concrete Mixer 1 day(s) @ P 1,700.00 / day(s) - P 1,700.00
Equipment Cost 1,700.00
DIRECT COST 36,010.00
OCM 3,601.00
Contractor's Profit 3,601.00
ITEM COST 43,212.00
Unit Cost 16,879.69 / cu.m
III.A. FOOTING TIE BEAM QTY: 1.78 cu.m
1 MATERIALS
16 bag(s) - Portland Cement @ P 260.00 / bag(s) - P 4,160.00
1.00 cu.m - Washed Sand @ P 800.00 / cu.m - P 800.00
2.00 cu.m - Screened Gravel @ P 800.00 / cu.m - P 1,600.00
41 pc(s) - 10mm dia. Deformed RSB x 6m L @ P 168.00 / pc(s) - P 6,888.00
5 kg(s) - #16 G.I Wire @ P 80.00 / kg(s) - P 400.00
Material Cost P 13,848.00
2 LABOR
1 - Foreman 2 day(s) @ P 550.00 / day(s) - P 1,100.00
4 - Laborers 2 day(s) @ P 365.00 / day(s) - P 2,920.00
1 - Steelman 2 day(s) @ P 450.00 / day(s) - P 900.00
1 - Mason 2 day(s) @ P 450.00 / day(s) - P 900.00
Labor Cost 5,820.00
3 EQUIPMENT RENTAL
1 - Concrete Mixer 1 day(s) @ P 1,700.00 / day(s) - P 1,700.00
Equipment Cost 1,700.00
DIRECT COST 21,368.00
OCM 2,136.80
Contractor's Profit 2,136.80
ITEM COST 25,641.60
Unit Cost 14,437.84 / cu.m
2 LABOR
1 - Foreman 18 day(s) @ P 550.00 / day(s) - P 9,900.00
2 - Welders 18 day(s) @ P 500.00 / day(s) - P 18,000.00
2 - Painters 6 day(s) @ P 450.00 / day(s) - P 5,400.00
2 - Tinsmith 18 day(s) @ P 450.00 / day(s) - P 16,200.00
4 - Laborers 18 day(s) @ P 365.00 / day(s) - P 26,280.00
Labor Cost 75,780.00
3 EQUIPMENT
1 - Welding Machine 18 day(s) @ P 750.00 / day(s) - P 13,500.00
Equipment Cost 13,500.00
DIRECT COST 280,613.00
OCM 28,061.30
Contractor's Profit 28,061.30
ITEM COST 336,735.60
Unit Cost 3,030.92 / sq.m
Prepared by:
Approved by: